Re: Case No. IPC-E-24-22
In The Matter of Idaho Power Company's Compliance Filing to Update the
Customer Surcharge to Collect Incremental Costs of Distribution
Undergrounding of the New 138 kV Transmission Line in the Wood River
Valley and Establish Necessary Regulatory Accounting Treatment
Dear Commission Secretary:
Attached for electronic filing is Idaho Power Company's Motion to Suspend
Procedural Schedule in the above-entitled matter. If you have any questions about the
attached filing, please do not hesitate to contact me.
Sincerely,
Donovan Walker
DEW:cd
Enclosures
1221 W. Idaho St(83702)
P.O. Box 70
Boise, ID 83707
DONOVAN E. WALKER (ISB No. 5921)
MEGAN GOICOECHEA ALLEN (ISB No. 7623)
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-2664
Facsimile: (208) 388-6936
dwalkerCcDidahopower.com
mgoicoecheaallenCa�_idahopower.com
Attorneys for Idaho Power Company
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER )
COMPANY'S IN THE MATTER OF IDAHO ) CASE NO. IPC-E-24-22
POWER COMPANY'S COMPLIANCE )
FILING TO UPDATE THE CUSTOMER ) IDAHO POWER COMPANY'S
SURCHARGE TO COLLECT ) MOTION TO SUSPEND
INCREMENTAL COSTS OF DISTRIBUTION ) PROCEDURAL SCHEDULE
UNDERGROUNDING OF THE NEW 138 KV )
TRANSMISSION LINE IN THE WOOD )
RIVER VALLEY AND ESTABLISH )
NECESSARY REGULATORY )
ACCOUNTING TREATMENT )
COMES NOW, Idaho Power Company ("Idaho Power" or "Company"), and,
pursuant to Idaho Public Utilities Commissions ("Commission") Rules of Procedure 56
and 256, hereby respectfully submits the following Motion in this case.
I. INTRODUCTION AND MOTION
On May 31, 2024, Idaho Power made a Compliance Filing seeking to update the
previously approved customer surcharge to collect the incremental costs of distribution
undergrounding as part of the construction of the new 138 kV transmission line in the
IDAHO POWER COMPANY'S MOTION TO SUSPEND PROCEDURAL SCHEDULE - 1
Wood River Valley. After the intervention period expired with no interventions the
Commission issued Order No. 36297, Notice of Modified Procedure, on August 23, 2024,
setting a written Comment deadline of October 25, 2024, and a Company Reply Comment
deadline of November 8, 2024.
The Company's request was premised upon the anticipated completion and
energization of the distribution line in November 2024. However, due to circumstances
outside of the Company's control the distribution line will not be fully completed and
energized by that time.
Therefore, Idaho Power respectfully moves the Commission to suspend the
procedural schedule established for this matter until such time as the distribution line
completion and energization is reasonably anticipated to occur. At such time Idaho Power
will file a Motion with the Commission to reinstitute a procedural schedule and make any
necessary updates to the initial filing, if required.
II. CONCLUSION AND PRAYER FOR RELIEF
Pursuant to the Commission's Rules of Procedure 56 and 256 Idaho Power
respectfully moves that the procedural schedule set forth by Order No. 36297 for this
matter be suspended.
Respectfully submitted this 16th day of October 2024.
-
DONOVAN WALKER
Attorney for Idaho Power Company
IDAHO POWER COMPANY'S MOTION TO SUSPEND PROCEDURAL SCHEDULE - 2
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 16t" day of October 2024, 1 served a true and
correct copy of the within and foregoing IDAHO POWER COMPANY'S MOTION TO
SUSPEND PROCEDURAL SCHEDULE upon the following named parties by the method
indicated below, and addressed to the following:
Michael Duval Hand Delivered
Deputy Attorneys General U.S. Mail
Idaho Public Utilities Commission Overnight Mail
11331 W. Chinden Blvd., Bldg. No. 8, FAX
Suite 201-A (83714) X Email - michael.duval(c)_puc.idaho.gov
PO Box 83720
Boise, ID 83720-0074
MVIV-
Christy Davenport, Legal Assistant
IDAHO POWER COMPANY'S MOTION TO SUSPEND PROCEDURAL SCHEDULE - 3