HomeMy WebLinkAbout20240927Bayer to PAC 44 - 1st Supplemental.pdf RECEIVED
Friday, September 27, 2024
IDAHO PUBLIC
UTILITIES COMMISSION
_ ROCKY MOUNTAIN
POWER
A DIVISION OF FACIFICORP
1407 W North Temple, Suite 330
Salt Lake City, Utah 84116
September 9, 2024
Thomas J. Budge
tj(&racineolson.com(C)
Brian C. Collins bcollins(&consultbai.com
Greg Meyer gmeyerkconsultbai.com
Kevin Higgins khiggins(c�r�,energystrat.com(C)
Neal Townsend ntownsendkenergystrat.com(C)
RE: ID PAC-E-24-04
Bayer Set 2 (21-48)
Please find enclosed Rocky Mountain Power's 1st Supplemental Response to Bayer 2nd Set Data
Request 44.
If you have any questions, please feel free to call me at (801)220-2313.
Sincerely,
/s/
Mark Alder
Manager, Regulation
Enclosures
C.c.: Eric L. Olsen/IIPA elokechohawk.com(C)
Lance Kaufman/IIPA lance(&ae isg insi h�(C)
Matthew Nykiel/ICL matthew.nykiel(&gmail.com
Brad Heusinkveld/ICL bheusinkveld(&idahoconservation.org
Ronald L. Williams/PIIC rwilliamskhawleytroxell.com
Brandon Helgeson/PIIC bhel eg sonLhawleytroxell.com
Bradley Mullins/PIIC brmullins(&mwanalytics.com
Val Steiner/PIIC val.steiner(&itafos.com
Kyle Williams/PIIC williamsk(&byui.edu
Monica Barrios-Sanchez/IPUC monica.barriossanchez(a),puc.idaho.gov
SecretM(a,puc.Idaho.gov
PAC-E-24-04/Rocky Mountain Power
September 27, 2024
Bayer Data Request 44—2nd Supplemental
Bayer Data Request 44
New Wind Generation Plant—Rock River I Repower. For the Rock River I
wind repowering project:
(a) Please separately identify each revenue requirement component (e.g., rate
base, expense, PTCs, REC revenue) associated with Rock River I wind
repowering project in the Jurisdictional Allocation Model and/or the
Regulatory Adjustment Model. In addition, please identify the location within
PacifiCorp's work papers where the amounts for each of these revenue
requirement items are located.
(b) Using each of the identified amounts in a), please provide the revenue
requirement for the Rock River I wind repowering project included in the test
period in Excel format with formulas intact.
(c) Please provide the exact date the repowering project is expected to commence
commercial operation.
(d) If during the pendency of this case, RMP changes the expected commercial
operation date for this project, please provide the revised date for commercial
operation.
2"d Supplemental Response to Bayer Data Request 44
Further to the Company's prior responses to Bayer Data Request 44, the
Company provides the following updated information responsive to subpart(c):
(c) The Rock River I wind repower project achieved commercial operation on
September 23, 2024.
Recordholder: Tim Hemstreet
Sponsor: Tim Hemstreet