ID Task Name Duration Start Finish % Work Complete Cost (EAC Total Project) 0 WBUT210001 as of 12-16-20231636 days Mon 1/29/18 Wed 7/17/24 0%$2,159,458.17 1 Capital Actuals by DCE 0 days Mon 1/29/18 Mon 1/29/18 0%$380,893.35 2 Labor 0 days Mon 1/29/18 Mon 1/29/18 0%$134,514.68 3 Materials 0 days Mon 1/29/18 Mon 1/29/18 0%$226,079.93 4 Purchased Services 0 days Mon 1/29/18 Mon 1/29/18 0%$19,531.22 5 Accounting Entries 0 days Mon 1/29/18 Mon 1/29/18 0%$0.00 6 Other 0 days Mon 1/29/18 Mon 1/29/18 0%$767.52 7 Payment Received 0 days Mon 1/29/18 Mon 1/29/18 0%$0.00 8 Remaining Costs/ Activities 560 days Mon 5/2/22 Wed 7/17/24 0%$1,778,564.82 9 Scope/ROW 65 days Mon 10/24/22 Thu 1/26/23 100%$0.00 21 Design 167 days Fri 1/27/23 Fri 9/22/23 100%$0.00 30 Long Lead Material/Shops 319 days Mon 1/9/23 Thu 4/11/24 0%$510,948.11 51 Construction 495 days Mon 5/2/22 Mon 4/15/24 0%$1,266,463.91 75 Project Closeout 65 days Tue 4/16/24 Wed 7/17/24 0%$1,152.80 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 2017 2018 2019 2020 2021 2022 2023 2024 2025 Task Critical Task Milestone Summary Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline Page 1 Project: WBUT210001 as of 12-16-202 Date: Fri 9/6/24 Response to Staff Request No. 116 - Attachment 1 I l I l l I I I I I I I I ... I-+ + • -+ + I-+ + I-+ + I- I- I- I- T -..., '-.. , I-..... I-+ + .... -+ + .., ... I-+ + ... - 1111111111111111111111111 -- ♦ • • - T ... -.. .. • • [ --] -◊ - ◊ 'V -v ,(), - ~