Inspector(s): Perkins Date(s): 29-Oct-20
Company/Owner: Intermountain Gas Company Unit/OPID: 8160
Inspection Type&Time (1 day) Total Inspection Days: 1
Standard: ConstructionT_11 Training: (T)(D)Integrity Management: Incident:
M/M: Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
29 Oct 2020: (1.0 Construction)
Observed a Das-co crew tapping a 4" main and installing a new W service line at 12172 W Savage Dr Boise,
Idaho. All procedures were followed.Typed up report.
Areas observed during this project were: Excavating, line locating, saddle/tapping T install, EFV install, riser
install and purging.
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of Job ticket.