HomeMy WebLinkAboutIntermountain Gas 27 May Eagle Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins Date(s): 27-May-20
Company/Owner: Intermountain Gas Company Unit/OPID: T 8-160
Inspection Type &Time (1 day) I Total Inspection Days:1 1
Standard:FI Construction:� Training: (T)(D) Integrity Management: Incident:
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
27 May 2020: (.5 Construction, .5 typed report)
Observed a Dasco crew Installing new W service lines to two different homes at 2593&2647 E Bonita Hills
Eagle, Idaho All procedures were followed.Typed up report
Areas observed during this project were: Excavating, line locating, bedding,backfilling, installing saddle tee,
pressure testing and EFV installation/testing.
Attachments:
IPUC Form 4 Construction Inspections
Das-co Daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes No X by(date):
Inspector(Lead): i' ;' Date:
Bruce Perkins 5/27/2020
Reviewer: Date:
Darrin Ulmer o27
IPUC Form 1