HomeMy WebLinkAboutIntermountain Gas 19 Oct Nampa Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins I Date(s): 1 Oct-20
Company/Owner: Intermountain Gas Company Unit/OPID: 1 8160
Inspection Type &Time (1 day) Total Inspection Days:1 1
Standard:FI Construction:� Training: F—] (T)(D) Integrity Management: Incident:
M/M: F7 Follow-up: Oct: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
19 Oct 2020: (1.0 Construction)
Observed a Das-co crew installing a new W service line after tapping off a 2" steel main at 426/430 1st Ave N,
Nampa, Idaho. Discovered existing gas leak on old abandoned line.All procedures were followed. Typed up
report.
Areas observed during this project were: Excavating, line locating, steel brazing, EFV installation
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of Job ticket.
Corrective Action Required: Follow-up Required: Yes No X
Yes No 71 by (date):
Inspector (Lead): �,- , Date:
Bruce Perkins " 10/19/2020
Reviewer: Date:
Darrin Ulmer
IPUC Form 1