HomeMy WebLinkAboutIntermountain Gas 16 Nov Meridian Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins Date(s): 16-Nov-20
Company/Owner: Intermountain Gas Unit/OPID: 8160
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days:1 1
Standard:F—] Construction:F71 Training: F__J (T)(D)Integrity Management: Incident:
M/M: = Follow-up: Oct: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company
16 November 2020(1.0) construction)
Observed a Das-co crew installing a new W service lines and stubs at 2605/2624 E Ashlar Dr, Meridian, Idaho.
All procedures were followed. Typed up report.
Areas observed during this project were: Excavating, line locating, pressure testing, EFV install,
bedding/backfilling, riser install and purging
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily iteneraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of job ticket.
Corrective Action Required: Yes No X
Follow-up Required: by(date): Yes No X
Inspector (Lead): Date:
Bruce Perkins 16-Nov-202y?
Reviewer: Date:
Darrin UlmerAw�Ak 1,1V 2PZO
IPUC Form 1