Inspector(s): I Perkins I Date(s): 13-Jul-20
Company/Owner: Intermountain Gas Company Unit/OPID: 1 8160
Inspection Type &Time (1 day) I Total Inspection Days:1 1
Standard:F� Construction: FI Training: (T)(D)Integrity Management: El Incident:
M/M: F-1 Follow-up: F7 OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
13 Jul 2020: (1.0 Construction)
Observed a Das-co crew installing a new W service line at 6194 W Los Flores Dr, Meridian, Idaho.All procedures
were followed.Typed up report
Areas observed during this project were: Excavating, line locating, backfilling, pressure testing and EFV test.
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes No FX_1 by(date):
Inspector (Lead): ;%' / Date:
Bruce Perkins ' / 7/13/2020
Reviewer: Date:
Darrin Ulmer _
IPUC Form 1