HomeMy WebLinkAboutIntermountain Gas 11-14 May Nampa Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins I Date(s): 11-14 May 202
Company/Owner: Intermountain Gas Company Unit/OPID: 1 8160
Inspection Type &Time (1 day) Total Inspection Days: 4
StandardT-1 Construction:F4 Training: F__] (T)(D) Integrity Management: Incident:
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
11-14 May 2020: (3.5 Construction, .5 typed report)
Observed a Dasco crew abandon service line 6842-371 and HPSS, replace with new service and tie into low
pressure main at 617 Northside Blvd in Nampa. All procedures were followed.Typed up report
Areas observed during this project were: Excavating, line locating, boring, welding, abandonment, bedding and
backfilling, EFV installation, tie-in/hot tapping, service line install and pressure testing.
Attachments:
IPUC Form 4 Construction Inspections
Das-co Daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes No X by(date):
Inspector (Lead): Date:
Bruce Perkins G-�Z,'A,� 5/14/2020
Reviewer: Date:
Darrin Ulmer 7
IPUC Form 1