HomeMy WebLinkAboutIntermountain Gas 7 Jan Meridian Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Russo Date(s): 7-Jan-20
Company/Owner: Intermountain Gas Company Unit/OPID: 8160
Inspection Type &Time (1 day) Total Inspection Days: 1
Standard: Construction: Training: (T)(D)Integrity Management: Incident:
M/M: Follow-up: Oct: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
07 Jan 2020: (1.0 Construction)
Observed a Dasco crew installing a new service from an existing stub. They used proper bedding and
shading procedures as well as squeezing procedures. Pressure tested the service and tied it in. Typed up
report
Areas observed during this project were: Excavating, Line locating, Pressure testing, Backfilling, Squeezing
Attachments:
IPUC Form 4 Construction Inspections
Das-co Daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes No X by(date):
Inspector(Lead): —7) Date:
Kyle Russo — 1/7/2020
Reviewer: Date:
Jqn O
IPUC Form 1