Budget ID Maintenance(expanded)for #35745 Scope Document Add Budget ID Last Query_ New Query_ Main Menu
Budget ID IT215210001 Title IT215 10-year inspection repairs,Ontario-Weiser 69kV
Solution 7041 I Location T215-LINE#215 69 kV-Ontario-Holly-Weiser(Ind Jacobsor v Submitted 05/06/2020
Co-Deps: Category Transmission By Whom PLS5566 Status Authorized v
Origin IT&D Engineering&Reliability CCI Leader I Heazle,David v
Master Project Transmission 10-yr Inspection Follow-Up Estimated In Srvc 12/15/2024
Master Group Date Completed
2-Compliance v B v Program No v Purchase Cv Asset Replacement No v
EIM Impact No v �v Complexity High v
Repair or replace deteriorated poles,crossarms,and insulators identified during the Pole Inspection and ground line Treatment Program and
the annual routine Line Patrols.
l
Correct issues identified during detailed aerial inspection,ground line inspection and outstanding Priority 2 and 3 defects identified by
patrolmen.
d
(if no action) May result in reduced reliability. Equipment failure could lead to an extensive outage and possible property damage.
d
Related
Info Line 215 was originally built in 1950.The Ten Year Maintenance Plan for this line begins in 2022 with the Pole Inspection and Groundline
Treatment followed by design in 2023 and construction in 2024.
V
Options
Evaluated
d
Status 12/27/2022:(JG)Replaced detailed estimate with project schedule forecast...12/20/2022 MJS:Assigned David Heazle as PL. 9/19/2022
Comments DJP:Updated to No for EIM impact per Whitaker.2021-09-17(update via code)Status set to Authorized per Mark Stute. . ..7/27/2020(LB)
Updated title to new 10 Year Inspection Repair naming convention...5/6/2020:(JG)Created BID for this Ten Year Maintenance project.Once
the Corrective Action Plan is completed,a detailed estimate will need to replace the existing estimate and MSP schedule.
Environmental Raptor zone
d
Right-of-Way Private,road right of way
l
d
clris/Products/Budgets/ProjectUpdate.cfm?ProjNo=35745&CC=577&CFID=106449&CFTOKEN=35df123bf0695dd4-A2D34334-08BB-0084-51 C7CF486262ECFF 1/2
9/5/24, 12:54 PM CLRIS
Permitting Traffic control
d
Outages will need to be coordinated
Legacy Agrmt
Contract
0 ,
Long Lead
Attachments « 102_850dw_20120131103649_9080.JPG
2012 Grdline report.pdf
Refresh 2012 Ln215 work summary.xlsx
L T215 v 2015 Priority 2 defects Line 215.xlsx
*Attachments for Projects should be stored in//Fresno/CUSTOMERLR/CLRIS Attachments.
Budget&Costs Initial Scope Design Port Mmgt Actual
Account Sp CC Type Estimate Estimate Estimate Estimate Benefit To Date
Capital v 577 v 33-Transmission Lines v C 260000 0.000 1243668.16
Detailed Cost Estimates
Aut Car Def Rev Date Rev By Year
O ❑ ❑ S-Scope v 12/27/2022 Gray,Jesse v 2023 0
12 El DC-Design&Construction v 12/18/2023 Sullivan,Melissa v 2024 683,582 0
Add or Delete Year and linked information? All 716,585 0
Replace Detailed Estimate with Project Schedule Forecast
12 Portfolio Managed Project 19 Portfolio Reviewed Change Log
clris/Products/Budgets/ProjectUpdate.cfm?ProjNo=35745&CC=577&CFID=106449&CFTOKEN=35df123bf0695dd4-A2D34334-08BB-0084-51 C7CF486262ECFF 2/2