HomeMy WebLinkAbout20240909IPC to Staff 95(e) - Attachment 3 - MLPR200001 Baseline Construction Monthly Summary.pdf Response to no. 95 (e)(v)
AFPR140005 section of project summary monthly reports
2021
August - MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to January of 2022 and construction has moved to the fall of
2023.
September- MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to January of 2022 and construction has moved to the fall of
2023.
October - MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to 2022 with scoping in January of 2022 and construction
has moved to the fall of 2023.
November - MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to 2022 with scoping in January of 2022 and construction
has moved to the fall of 2023.
December- MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to 2022 with scoping in January of 2022 and construction
has moved to the fall of 2023.
2022
January— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
February— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
March — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
April — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
May— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
June — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
July— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
The design for this project has been moved to mid-2022 and construction has moved to the fall of 2023.
August - MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Mark is starting on the design. Construction is being moved to the spring of 2023. We will need
contractors for this work. Maybe the same crew that we use for Lower Salmon?
September - MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Mark is starting on the design. Construction is being moved to the spring of 2023. We will need
contractors for this work. Maybe the same crew that we use for Lower Salmon?Waiting on Basler for
quote and timeline for delivery.
October- MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Mark has started on the design. Schematic review scheduled for the end of the month. Construction is
being moved to the spring of 2023. We will need contractors for this work. Maybe the same crew that
we use for Lower Salmon? Basler quote is in and it is higher than estimated.Also need to send SEL-
751A's to Basler for installation.
November- MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Schematic review is complete, planned P2P at the end of December. Construction is being moved to the
spring of 2023.Working with Akoni Hinojosa to bring on contractors for this work. Maybe the same crew
that we use for Lower Salmon? Basler quote is in and it is higher than estimated. SEL-751A's have been
sent to Basler for installation.
December- MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Schematic review is complete, planned CHQ P2P at the beginning of January. Construction is being
moved to the spring of 2023. Working with Akoni Hinojosa to bring on contractors for this work. Maybe
the same crew that we use for Lower Salmon?
2023
January— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Schematic review and CHQ P2P complete. Mark is working on picking up P2P correction and scheduling
a P2P with operators and techs. Construction is scheduled for the spring of 2023.Working with Akoni
Hinojosa to bring on contractors for this work. Maybe the same crew that we use for Lower Salmon?
February— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Schematic review and CHQ P2P complete. Mark is working on picking up P2P correction and scheduling
a P2P with operators and techs. Construction is scheduled for the spring of 2023.After two RFB
attempts there were no bids. Project site walk completed with Rocky Mountain Electric and Data.
Working on getting their rates and availability.
March — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Construction drawings have been delivered to the plant. Site visit with Rocky Mountain Electric and Data
went well. Working on getting their rates and availability. Outage will have to move to this fall.
April — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Rocky Mountain Electric and Data is interested in this work. Will need to work with Akoni to get a
contract in place. Outage is moving to this fall.
May— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
I am starting to work with Akoni to complete the contract for Rocky Mountain Electric and Data. I plan to
have this complete in the next month. Outage is moving to this fall.
June — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
I am starting to work with Akoni to complete the contract for Rocky Mountain Electric and Data. I plan to
have this complete in the next month. Outage is moving to this fall.
July— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
SOW with RME is in place.All Basler equipment has been delivered.TPC wire is also on site. Outage is
moving to this fall.
August— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
SOW with RME is in place.All Basler equipment has been delivered.TPC wire is also on site. Outage has
started with the techs and maintenance starting the removals. RME to be onsite when a crew is
available.
September— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
RME is onsite. All of the old ABB equipment has been removed and the new Basler equipment has been
placed.There are some drawing issues that are being looked at right now.
October— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
RME is complete. All of the old ABB equipment has been removed and the new Basler equipment has
been installed.There are some drawing issues that are being worked on right now. May only be able to
test out unit#2 in December with 200 cfs of flow.
November— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
RME is complete. May only be able to test out unit#2 in December with 200 cfs of flow. WO for the
project has been split between the units.
December— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
RME is complete. Started unit#2 commissioning but had mechanical issues. Looking to restart on the
11th. Unit#1 will be commissioned in the spring of 2024.
2024
January— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Unit#2 servo was disassembled and there was considerable wear found. Unit#1 will be commissioned
in the spring of 2024.
February— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Unit#2 servo was disassembled and there was considerable wear found. Unit#1 will be commissioned
in the spring of 2024.
March — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Unit#2 servo was disassembled and there was considerable wear found. Unit#1 will be commissioned
in the spring of 2024.
April — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Both units are commissioned and in service.
May— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Both units are commissioned and in service.
June — MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Both units are commissioned and in service.
Drawings have been picked up and in the queue for drafters.
July— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Both units are commissioned and in service.
Drawings have been picked up and in the queue for drafters.
August— MLPR AVR Unit #1 and #2: (MLPR200001)
Stephen Sjostrom
CC642
Both units are commissioned and in service.
Drawings have been picked up and in the queue for drafters.