HomeMy WebLinkAbout20240909IPC to Staff 94(e) - Attachment 5 - HCPR190001 UNIT 2 Commissioning HCPR_2_COMMISSIONING_SIGN_OFF.pdf Hells Canyon Unit 2 Commissioning Plan - MASTER Individual will Initial Each Line when Complete,Each Section will be signed when complete Pre-Start-Up Checks (All Complete Prior To 4/10/2024) Runner E3 Me runner cl`L3�� NSA ion o g Turbine Pi erify all walkways are secured Clean up all tools, parts and liquids Scroll Case L'44® Confirm all scroll case and draft tube drains are clear of equipment and free of debris bW® Make sure piezometer taps are clear and that piping is correctly attached b% V1 Confirm the scroll case and draft tube access doors are closed and secured Stator ® Megger each phase bW E5 Megger the stator Rotor ® Perform post-assembly electrical testing prior to installation 1&%® DC winding resistance Test AOo ® Pole Drop Test i of-5 fVA �B� B Insulation Resistance and Polarization Index—1000 Vdc 99 Perform post-installation electrical testing MR Insulation Resistance and Polarization Index—1000 Vdc&500Vdc(used as baseline for future maintenance testing)w/Field Bus ® Make sure the rotor components(spider, balance weights,covers, blades)are secure and that no foreign objects are present Generator lWD 9 Inspect the entire stator area and upper bracket,including the air gap,for foreign objects DOD ® Take a set of stator air gap readings-Mechanical b3t1 9 Make sure rotor shrouds and fan blade clearances are acceptable/RTD's as well Tl� Inspect brake piping for leaks 21onfperate the brakes i � rm operation of all brake system switches/notifications(gap sensors) �Yd Confirm Brake start cycle setting,currently set to 30%speed,we will confirm this works as we commission unit.Confirm the speed switch setting for the brake actuation is set no higher than 30%synchronous speed. 11Page Revised 0-/0-1/2023 Hells Cc.nyon Rewind and Control System Upgrade CornrnisMoning Plan Internal Use Only Bearings (thrust bearing, turbine guide, generator guide) 19 Verify oil piping has been flushed and new filters installed including new TGB Filter �Lr1 Confirm correct oil levels(visual and indicated) C3�Confirm the bearing oil level alarms and Trips are operational from LL and HH Level Switches. �-/Confirm the bearing temperature measurements are accurate and calibrated r55-L� Verify oil pump(s)are operational and flow rates are acceptable CWd Inspect the oil piping for leaks WD CR-Verify proper operation of high-pressure lift pump system. �L�1 Check bearing pumps for oil flow and no aerating of the oil. ` Make sure that old THB cooler water is off,and we are using the plate exchanger Governor YR d Inspect the cabinet, piping,sumps and servos for oil and air leaks brl�_TO Make sure the accumulator tank oil level is correct, t54;Z�OZHigh/Low alarm check,High/Low Trips. .tN ® ' Mock-Up operation of governor system without operating unit. Operate the wicket gates: 91"'Verify the wicket gate position sensor operates correctly 93""Verify the gates operate smoothly and do not bind fl-Record the gate opening and closing times(nominal 10 sec)w/prop valve S" Record the gate opening and closing times(nominal 10 sec)w/Emergency shut down L►�Verify cushioning and squeeze Er'-High Level-Low pressure gate stroke check and low level-low pressure check ErMake sure servomotor lock engages and disengages -W - Verify Speed Probe gap settings are correct&functioning(bench test) Electrical 15*_'�_H"_Install new generator protective relay settings and verify relay operation Z4Zi ET'_Test all protective relay input and output circuits b�K -Test generator CT circuits-push current and verify polarity 1 ^� Test generator breaker trip and close circuits /�/� C-CTest Governor control and shutdown circuits �C�Test turbine mechanical and electrical over-speed circuits �C�Test Emergency Gate-drop circuits N5—Li_Test 86E Lockout. t5 t Test PLC 86N,94G,5G. Fill out paperwork Visually inspect all undervoltage relay's. Fill out paperwork —�Test unit control circuits t"--Test AVR circuits �Crcomplete and check TMS circuits and shutdowns. Bearings,stator etc. ��Test SCADA control,alarm and indication circuits tt�oY�Verify EMS points and controls 11 Verify PI points are in PI -bon, 6� 0peo4,1IDhJ -,jV4oS ©' Test AC and DC turbine bearing oil pump operation Test oil level,flow,and pressure circuits,Turbine guide and Thrust Bearing 2 Page Revised 05/03/2023 Hells Canyon Rewind and Control System Upgrade Commissioning Dian Internal Use Only B-P'-�Test oil pump control circuits,Turbine Guide and Thrust Bearing t�� 0"-Test oil level trip circuits,Turbine Guide and Thrust Bearing �-3"Test RTD circuits L�3est lift pump operation, permissive operation,and pressure switch -b4rT Test brake circuit equipment,operation and other Systems permissive operation. /V/,4 bo—E Dry run of the wicket gate assembly with a governor shutdown. 100%to-2%gate Check servo timing and cushion EField Ground Relay-Positive,then Negative to ground. IVIA tz -verify all trip test switches are closed. Slow Roll- By Hand -Mechanics V-1C�GT'Check lift and delay on lift, inform techs/controls of delay to be added to startup to accommodate time-to-lift. %w 49 If the unit is unable to move by hand,it may be required to slow roll the unit with water. S/ow 9.11116 by I.Awd o Headgate will be cracked to fill the penstock. Headgate will then be closed. o Gates will be crack open to allow water to flow and slow spin the unit. o Perform as needed. Creep Detect- By Hand -Techs .b-5;ZZ:--2 etVerify Creep Detect operates, manually move SSG to initiate creep 15;:�CVerify loss of speed probes. No speed on start up after xx seconds.Verify brake logic so they will be disabled. 1�e.c.4. 1 i bra. c ne- Perform OOverspeed tests (Bench) (202X OPEN) D � st Mechanical Overspeed trip devices. a� Verify proper trip and shutdown of unit after an overspeed trip. Unit Shut Dpwn (Bench) (202X OPEN) V,vb Lyf Verify the unit can shutdown successfully before proceeding further Pre-Start Up Checks Complete -Signatures Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title 3 Page Devised 05/03/2023 Hells Canyon: Rewind and Control System Upgrade Commissioning Plan Internal Use Only Name,Title Name,Title Unit Start-Up Procedure (242X OPEN) ❑ Prior to Start-Up (202X OPEN) - Record Timeframe ❑ Verify all test instrumentation is turned on and working Variable Sensor Wicket Gate Position PLC Penstock Pressure PLC Scroll Case Pressure PLC Unit Speed PLC Penstock Flow PLC Breaker Open/Closed PLC AC RMS Voltage(Running EE Power Supply and Impedance Test) Transducer AC RMS Current(Running EE Power Supply and Impedance Test) Transducer ❑ Waattering Up - Record Timeframe �0 FF ctional test of Creep detection, move SSG by hand and verify lift pump starts,and brakes release T� Ilr1 eset Creep detect ply the rotor brakes manually B-'­Crack to fill and inspect for areas of leakage: /All access hatches EV urbine shaft seal li et gate stems ead cover flange Vent piping 13'_—Headgate raising Process: uRaise gate to full open, attach indication cable to gate CI/Lower Gate, Full closed,Set PLC Zero Open crack to fill,set in PLC II 1 lnitiate emergency gate-drop via E-Stop button J��Raise gate to full open,verify correct elevation in PLC 4 Page Revised 05/03/2023 Bells Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only 2Open cooling water valves and check piping for leaks L7/ onfirm cooling water flow is present Confirm operation of cooling water flow alarms Confirm water flow to the bearing coolers and stator air coolers Check oil levels to make sure levels are not rising(indication of a water leak into reservoir) C9/�ake sure governor accumulator tank is at full pressure and the oil is at normal level C9' Set up bearing temp trend in the PLC , C9 Record the headwater and tailwater 7�, L elevations= V 0. 13 ❑ Low Speed Checks (202X OPEN) - Record Timeframe 0--'Verify in PLC when Master Start is initiated the gate limit will remain at 0% ,,� Q ,Verify Unit is in Local Control Po�44e G-,-�t l im;� P&H4 + o R— Verify brakes have been disab ed,we will use brakes valving at governor C�//Verify 70OG breaker close output trip jack is open and tagged. I�' Verify 30OG&M3425A manual sync check trip jacks are open and tagged f—�/Using Master Start,start unit [97 Keeping gate limit at 0%,Verify we get a Breakaway fail and 86N lockout. P/Reset lockout and re-start unit. Increase gate limit until the unit spins 2 Use master stop to close wicket gates 6/Manually apply brakes to stop unit ❑ Slow Build to Overspeed trip test (202X OPEN) - Record Timeframe Se- oi, ` I ElSet RwooW oversp ed trip at 10%of rated speed ore el,� 2'�-Verify Unit is in Local Control r Q----Verify Brakes are back in Auto Position q4/G W SSet gate limit to 10% S CG 55 2 Using Master Start,start unit Verify Runaway overspeed trip @ 10%of rated speed GA 15' Verify unit shuts down properlyia -t `o� 2' Listen for unusual noises ' J f�Make sure the brake pads are clear of the runner `�� D"i —0S qq& -1lss u+1 ❑ Record bearing temps. we'" S 6 wpx ❑ Slow Build to Speed No Load (202X OPEN) - Record Timeframe 70-I'Set Runaway overspeed trip to normal 170%of rated speed erify Unit is in Local Control G Verify in PLC when Master Start is initiated,the gate limit will remain at 0% r d bearing temps sing Master Start,start unit Increase gate limit to start unit spinning 5 Page Revised 05/03/2023 Heals Canyon Rewind and ContrOi System Upgrade Commissioning Plan Internal Use Only :�7 Increase geate limit to control unit 1Fify Governor has control of unit at rated speed � Operate the 86N using one of the trip inputs,verify unit shuts down properly. ae o 'PF13per-ly. n Rv tart I I i •ith eiic av6Ve'pre^ d ,ems First offline governor tuning li�r'with Unit at SNL,lower gate limit to reduce Unit speed by 3%,move gate limit to 25%, record prop valve and wi-cket gate movement. Tune governor until satisfied. LN/with Unit at SNL,lower gate limit to reduce Unit speed by 5%, move gate limit to 25%, record prop valve and wicket gate movement. Tune Governor until satisfied. Listen for unusual noises C+3'Make sure the brake pads are clear of the runner -if qrbasystnT-is-recard4ng-the—cJ2aft,� K�- Trend bearing temps in PLC o�---Test-monitadngs4e d P�P"inu owiongckyes-it-take-to-get-to-bFakift speed?, Record time_,Mt_takes-unit-ta-spin-down_to-.bcake_cyclQstar-r speed.---- ❑ Normal Start to Speed No Load (202X OPEN) - Record Timeframe V9 ' erify Unit is in Local Control erify Gate Limit has been set back to normal start up20% re d bearing temps in PLC Sing V Master Start,start unit verify Governor catches and controls unit at rated speed. Verify the Governor tuning is acceptable, if not perform tuning steps again. OPEN) -ReG0rd44nekGR;e-- ❑ ITe ' Unit is in Local Control (Only use the flukes for this test) ❑ Defeat time eeded ❑ Verify Gate Limit is set t ° or start up ❑ Trend bearing temps in PLC ❑ Using Master Start,start unit ❑ Using Gate Limit, increase to 3%or more until ' pins ❑ Under manual control, bring the i p at 2%gate increments to rat eed. Holding a couple minutes at each position for record son. ❑ Gath edance data while unit is rotating.Then bring the unit down in same 2%incre ts,and review data. ❑ Passing test is no instantaneous impedance changes of 3%and no more that 10%throug t the test. ❑ Using Master Stop,stop unit 6 1 P a g e Revised 05/03/2023 Flans Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only AVR on (DECS on) (202X OPEN) - Record Timeframe .-0 I tall Fie ads---- Verify Unit is in Local Control B"Verify AVR start is not disabled rend bearing temps in PLC C3'-Trend the Shunt field and Main field in the PLC � Using Master Start,start unit E "When unit is at Sync speed,start AVR e Perform relay check. Verify relays are metering correct voltage magnitude and phase sequence. Capture oscillography from relay to perform voltage waveform verification. ' sy Is recor rng 2---Check the turbine shaft seal for leakage B-'Review the penstock and scroll case pressure readings Review AVR operation and performance. If performance is unacceptable,tune AVR(approximately 2 hour)(FCR to AVR Mode). n c+artin e,x4tingsetting-5,-p-Lytforrrssteprtesponses_in-ECR-Mode-and verify stability-Upon_step.test-and—., r�rd-review-response,Changes-may-be required Another 1"-"response will-followto-verify-stability-Repeat-y �`���uked,Veri eque aloes-in DEES L�J Transfer to AVR Mode. Perform step test with procedure same as above. � era i 3 Stop unit using Master Stop and record shutdown from the DECS. Verify Unit is in Remote Ek"'Verify 70OG breaker close output trip jack is open and tagged. @"-Verify 30OG& M3425A manual sync check trip jacks are open and tagged 2-'Verify AVR is in AVR mode C1a' Using Master Start,start unit 12 Verify at 95%rated speed the AVR starts automatically.Verify proper field flash.Soft start settings record. Adjust if required.(Stop and restart AVR if needed) ® Voltage matching and sequence of operation.Verify voltage matching control,adjust as needed. S Verify Gov tuning after AVR tuning, might need to make fine adjustments esto"Fmte o-veltag�-A��ex. es. �xOt,i:GElve'ffrlay'-settis�gs-, Protective relay breaker trips V" *open and 201Z closed lose and trip that breaker from all protective relays,trip 1 and trip 2 Close and trip breaker by rolling the 86E lockout )Rr Ready to close the 2MX. Phase Check, Close 202X, and perform phase check across 202Z (202X CLOSED) 7 1 P a g e Revised 05/03/2023 Hells Cmnyor? Rewind and Control System Upgrade Cor-mmissioning Pion Internal Use Only MJ Release clearance on 202X (202X CLOSED) - Record Timeframe 2 Check phhng with 230kV sticks L9 Step�1 L Verif Unit is in Remote i�rift'70OG breaker close trip jack is out and tagged Verify 30OG& M3425A manual sync check trip jacks are open and tagged art Unit Phase-check across 201Z on all three phases to sync scope H' Step�2 H Phase-check the manual sync check of 30OG and Beckwith to sync scope. 0' Step x ; Phase-check auto sync relay to sync scope. Sync Unit Online and Perform Load Testing (202X CLOSED) Generator Breaker Closure (202Z OPEN) - Record Timeframe B- Verify 70OG breaker close output is closed and tagged removed ZrIV-erify 30OG& M3425A manual sync check trip jacks are open and tagged ler Verify Unit is in Remote Control Using Master Start,start unit B"-Transfer Unit back to Local control Manually sync the unit on using Sync Scope,one manual sync relay and Breaker close switch. 6T"'/Open Breaker, leave unit running E Manually sync the unit on using Sync Scope,second manual sync relay and Breaker close switch. II�P ce Unit in Remote Control I�1 Verify 70OG starts and Syncs Unit online Online Protectiontrips (202X CLOSED) - Record Timeframe 2- Unit Online and Breaker closed. M-1s'sue 86N trip using one of the inputs. — LL, Gov pArsole— Verify Unit shuts down properly. M-/Restart Unit 10_1_�Ower Over Speed trip from 105%to 99% i"Vv 94G operation and breaker open. ;:fy 5G timer and 5G trip. Verify Unit shuts down properly. Eft pen breaker on HPLP, using HPLP bypass button start unit to verify Black Start Condition. 8 Page Revised 05/03/2023 dells Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only Online Governor Tuning (202X CLOSED) - Record Timeframe E V rify Unit is in Remote Control sing Master Start, start unit 9--V—erify 70OG syncs unit online VT �sure governor goes to min loading set point ransfer between governor mods and verify it is bump less Er"'O line Gov tuning Perf m a 1%per second gate movement of 20%. Record prop valve and wicket gate movement. ne governor until satisfied. Perform a 3%per second gate movement of 20%. Record prop valve and wicket gate movement. Tune governor until satisfied. Loading to Minimum (Record Value ) and unity power factor for AVR Wing - Record Timeframe Load the unit to 5%of full power. ❑ ery fifteen minutes record the shaft runout readings(Vibrosystm) ❑ Ever fifteen minutes record the generator air gap(Vibrosystm) ❑ Trend b ing temps in PLC ❑ Check the to ine shaft seal for leakage ❑ Review the scrol se and draft tube pressure readings ❑ Trip unit from this op ting point,while recording data with the,DECS-400. ❑ Reload the unit to MW ❑ Collect PD test data for this ope -ng condition(Low Load—Cold Machine,Approx..20min) ❑ Verify voltage across coupler minations. ❑ Review AVR operation and performance. I rformance is unacceptable,tune AVR. (about 2 hours) ❑ Review OEL response stability online. ❑ Review UEL Response.Perform AVR Step Resp es and review, make gain adjustments as required. Record final step respor(se. ❑ Perform verification of electrical quantities in all energized protectiv elays,AVR, DFR, meters,etc. ❑ Verify values into PI and reporting correctly. ❑ Adjust the voltage set point to achieve the maximum MVAR output up to the ov citation limiter in the AVR. Collect MOD-025 data using the DECS-400 and collect generator 3rd harmonic data usin L-300G. ❑ "Balance Vars with sister machine. ❑ just the voltage set point to achieve the minimum MVAR output up to the under-excitation limiter' the AVR. Collect MOD-025 data using the DECS-400 and collect generator 3rd harmonic data using SEL-3)0G. ❑ Balance Vars with sister machine. ❑ Load in .& o Capacity ( MW) (Max before Rough Zone) - Record Timeframe ❑ Load the unit to 12.5%of full power and unity powerfactQ C7 Ever fift n_ninutes record the shaft runout readings(Vibrosyst ❑ Every fifteen minutes record the generator air gap(Vibrosystm) 9 Page Revised 05/03/2023 delis Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only ❑ Trend bearing temps in PLC ❑ eck the turbine shaft seal for leakage ❑ Re iew the scroll case and draft tube pressure readings ❑ Coll t PD test data for this operating condition (Low Load—Cold Machine) ❑ Revie AVR operation and performance. If performance is unacceptable,tune AVR. ❑ erform a step test and review. ❑ Tune PSS( imary&Secondary)—May adjust MW range(12.5%-40%) ❑ De t mine local mode oscillation ❑ Perfo frequency sweep.Collect uncompensated VAR-501 informati Adjust time constants& apply ca ulate compensation. ❑ Determin the PSS lead-lag coefficients ❑ Capture Unc mpensated Bode plot with calculated compensatio for VAR-501 verification. ❑ Adjust PSS Gai s&Output limiters, perform step response to v rify stability. ❑ Verify OEL and L with PSS Active. ❑ Perform verification of ele rical quantities in all energized protectiv relays,AVR,DFR,meters,etc.,A record must be remote started and viewed.We are notable to see real ime in the DFR. ❑ Collect generator 3rd harmonic ata using SEL-30OG ❑ Adjust the voltage set point to a !eve+20 MVAR. Collect MO -026 data using the DECS-400 and collect generator 3`d harmonic data using EL-300G. ❑ Adjust the voltage set point to achie -20 MVAR. Collect OD-026 data using the DECS-400 and collect generator 3`d harmonic data using SEL- OOG. ❑ Return unit to unity power factor. ❑ Proceed to loading the unit in steps to the est-efficie cy power(BEP)and then to full load. The steps can be: 40%( )60%( )75%( M ),90%(_MW),and 100%( MW). These positions can vary,depending on the SN a BEP wicket gate positions. The usual rough zone,typically in the middle range of load,should be avoided. each loading point: ❑ Adjust the voltage set point to achieve+2 M R. Collect MOD-026 data using the DECS-400 and collect generator 3rd harmonic data using SEL- OG. ❑ Adjust the voltage set point to achiev -20 MVAR. Collect MOD-026 data using the DECS-400 and collect generator 3`d harmonic data using S L-300G. ❑ At each loading position per abov , review AVR&PSS peration and performance. If performance is unacceptable,tune AVR. Perfor step test and review r sponse. May require to reduce loading. ❑ During AVR Tuning pe form governor step respo es below. ❑ Get data for steady ate for about 3-5 minutes at ach load ❑ Inject a positive a negative 0.3 Hz frequency at ea loading level ❑ With a 5%droo =>10%change in gate position. ❑ Load to 25%( MW) ❑ Sta ing Gate position= Ending Gate sition= ❑ T' e for Step= Time return= ❑ Load to %(_MW) ❑ Starting Gate position= Ending Gate Positi n= Time for Step= Time to re rn= ❑ L d to 75%( MW) ❑ Starting Gate position= Ending Gate Position= ❑ Time for Step= Time to return= ❑ Load to Pmax( MW) ❑ Starting Gate position= Ending Gate Position= ❑ Time for Step= Time to return= 10 Page Revised 0 /03/2023 Neils Canyon Rewind and c'-'oniro Syster. Upgrade C4m 'sslonl g Plan Internal Use Only -f —Fake-readings while allowing the bearing temperatures to stabilize at each setting(consider runni overnight to heat soak b%� gs-fo ker stabilization) ❑ Return unit to unity power factor. ❑ Collect PD test data ine is at 100%rated output(High Load-Hot Machine i po alize AVR, PSS and VAR-501 commissioning - Record Timeframe ❑ Online V�adjiust t Step Test-While operating at the BEP and after above data points have been collecte e set point to set the stator voltage t proximately 100%of nominal with PSS on. Once stable,perform a 10 secon step in the voltag point using the DECS-400. Multiple step responses will be performed. ❑ While operating at 100%rated output,ad' the ftage set point to achieve the minimum MVAR output up to the under-excitation limiter in th R. Collect MOD- ata using the DECS-400 and collect generator 3rd harmonic data using SEL-30OG ❑ Balance Va ith sister machine. ❑ While operating at 0%rated output,adjust the voltage set point to achieve t aximum MVAR output up to the overe ' ation limiter in the AVR. Hold this operating point for one hour. Colle OD-025 data using the D -400 and collect generator 3 d harmonic data using SEL-300G. ❑ Balance Vars with sister machine. Load Rejections - Record Timeframe 'VCry' erify all sensors are wired out and ready to record load rejections erify Auto Spill PLC input from Unit#ais landed VX erify Unit is in Remote Controlart Unit and open gates to 20% art Recording data Q_�/;rip Unit by rolling 86E lockout _ V�Stop erify Auto Spill matches unit CFS Auto Spill and close Spill gate if opened pi PL mpu r E3"-Verify test data is within limits Dart Unit and open gates to 40% art Recoding data ;Sri Unit by rolling 86E lockout :�--Verify test data is within limits start Unit and open gates to 60% 3--Trip Unit by rolling 86E lockout 2'Verify test data is within limits ®tart Unit and open gates to 80% EP Start Recording data 0 rip Unit by rolling 86E lockout rify test data is within limits art Unit and open gates to 100%or Maximum allowed gate limit rt Recording data Trip Unit by rolling 86E lockout 11 Page Revised 05/03/2023 bells Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only L�1 VV rift'test data is within limits 2G�a>ny of this test data is not within limits,we will stop and re-evaluate. Ira Scroll case pressure not to exceed 125 PSI, Nominal scroll case pressure is 100 PSI 17 Final Controls Check- Record Time Frame I ^ :.•1.-a L_r,.c era Wsed Ye6f, drop ui s. Thi3 bone- ��1+ erify all control panel switches and gauges are working and calibrated. :/Vverify erify all Wonder Ware buttons for Raise/Lower operate correctly EMS controls and alarms ❑ Verify PSS compliance operates correctly to EMS and Plant SCADA. erify Delta Temps compliance �:erify NPDES flows lose Local Service breaker and verify phase rotation at ATS switch,switch local service to this source e all timers have been returned to normal ��erifV ' rify all overspeed trips have been returned to normal PLC has no forced points 1J Verify PI points and values ❑ er a successful start-up test, perform a heat run of the generator ❑ Oper the unit at(approximately 145MW)until the generator stator temper stabilize ❑ Record the ring temperatures as the stator heats up. ❑ Record the stator peratures,identify the hottes perature sensors,these will become the drivers during normal operatio ❑ Verify coolin n is modulating. cord bearing temps ❑ Measure the generator air gap as the stator hea 9-final�oteplate Inspection=Record-Tim-e Frame Apply-L-O O-te4he unWtG411llow for access to the bra i�— ❑__CQmplete fi� nal inspection o the-soleplate-uacking rAdditional Testing and Unit Released for Commercial Ops - Record Time Frame Pe rm additional testing as required(compliance testing,etc). Release for Commercial Operation. [Final Commissioning Complete, Unit Release for Commercial Operation-Signatures 121Page Reylsed 05/03/2023 dells Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only 0 s Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title Name,Title 13 Page Revised 05/03/2023 Hells Canyon Rewind and Control System Upgrade Commissioning Plan Internal Use Only