HomeMy WebLinkAbout20240909IPC to Staff 94(e) - Attachment 2 - HCPR190001 Baseline Construction Variance Notes.pdf Response to no. 94 (e)(iv) Project Variance Notes pulled from current MS Project File 2024 Total Project FAC change: $249k AUG: Project Change$159,288. about$11k for material and purchased services and $148k higher labor costs to finish installation and commissioning of the BOP. JUL: Project Change $89,920. $7,300.92 material costs higher then estimated. $82,619.08 labor higher then estimated to finish up all of the modernization project. JUN: Project Change. $6,666.92 materials higher then estimated. $39,036.08 labor higher then estimated. MAY: Project Change commissioning labor higher then estimated, $50k. Materials higher then estimated $24k. APR: Project Change$15,266. Materials and labor higher then estimated. Next months labor showed up this month. MAR: Project change material costs higher then estimated, $19k. FEB: Project change$11k Materials higher then estimated. JAN: Disregard: Labor increase for unit and BOP $35k and deferred stoplog work from 2023 to 2024 $27k. Labor higher than estimated $19k 2023 Budget Update 4; Total project Change: $1,304,132; Budget Update 1: GWA increases in labor and unit#1, project change of$79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022; Budget Update 2: $296k increases in labor and materials costs to complete the project; Budget Update 3: $722,742 increases in labor and materials costs to complete modernization project and the Outlet Gate indication project; Budget Update 4: Project Change $46,390 labor higher then estimated.; Annual Project Change$1,219,511 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change $159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change$67k, Labor and Materials higher then estimated: U1-$33k, U2-$25k, BOP-$9k. AUG: Project Change$3,519,Third party compliance bill added to project. SEPT: No Cahnge. OCT: Project Change$39k, Stop log labor higher then estimated. NOV: Project Change ($38k), Labor costs lower then estimated, stop logs work moved out. DEC: Project Change ($47k), Labor costs lower then estimated, stop logs work moved out. Annual Project Change$1,266,324 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change $67k, Labor and Materials higher then estimated: U1-$33k, U2-$25k, BOP-$9k. AUG: Project Change$3,519,Third party compliance bill added to project. SEPT: No Cahnge. OCT: Project Change$39k,Stop log labor higher then estimated. NOV: Project Change ($38k), Labor costs lower then estimated, stop logs work moved out. Annual Project Change$1,304,131 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change $67k, Labor and Materials higher then estimated: U1-$33k, U2-$25k, BOP-$9k. AUG: Project Change$3,519,Third party compliance bill added to project. SEPT: No Cahnge. OCT: Project Change$39k,Stop log labor higher then estimated. 2023 Budget Update 3; Total project Change: $1,257,742; Budget Update 1: GWA increases in labor and unit#1, project change of$79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022; Budget Update 2: $296k increases in labor and materials costs to complete the project; Budget Update 3: $722,742 increases in labor and materials costs to complete modernization project and the Outlet Gate indication project; Annual Project Change$1,264,778 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change $67k, Labor and Materials higher then estimated: U1-$33k, U2-$25k, BOP-$9k. AUG: Project Change$3,519,Third party compliance bill added to project. SEPT: No Cahnge. Annual Project Change$1,261,092 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change $159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change $67k, Labor and Materials higher then estimated: U1-$33k, U2-$25k, BOP-$9k. AUG: Project Change$3,519,Third party compliance bill added to project. Annual Project Change$1,257,573 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change $159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. JUN: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. JUL: Project Change$67k, Labor and MAterials higher then estimated: U1-$33k, U2 -$25k, BOP -$9k. 2023 Budget Update 2; Total project Change: $535k; Budget Update 1: GWA increases in labor and unit#1, project change of$79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022; Budget Update 2: $296k increases in labor and materials costs to complete the project; Annual Project Change$1,190,932 JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. June: Project Change $642k, $68k labor higher then estimated, $62k materials higher then estimated, Added $28,947.6 for unit#2 P2P, added $28,626.4 to finish up design, removed $22,791.2 not using e- shop or mech shop, added $60k BOP labor after unit#2, added $210K for Stop Logs, added $250k to BOP labor. Annual Project Change$571k JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. MAY: Project Change$36k, Commisioning labor higher then estimated. Added hours to complete BOP design. Annual Project Change$535k JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change $159k, Labor added to complete construction. APR: Project Change$71k, Labor and materials higher then estimated. 2023 Budget Update 1: Total project Change: $239k; Budget Update 1: GWA increases in labor and unit#1, project change of$79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. Annual Project Change$464k JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change$66K, Labor and material costs higher then estimated. MAR: Project Change$159k, Labor added to complete construction. Annual Project Change $305k JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. FEB: Project Change 66K, Labor and material costs higher then estimated. Annual Project Change$239k JAN: GWA increases in labor and unit#1, $79k. Project change of$106k for added BOP labor and materials. Carryover of$54k for the Outlet Gate project originally in 2022. 2022 Budget Update 4: Total project Change: $489k; Budget Update 1: Carryover $60k, Project change $94k. Supply change delays have move material orders and labor into 2022; Budget Update 2: Project change $129k. Project inservice date moved out. Labor added to new inservice date; Budget Update 3: Project change $(108k). Moved $103,638.53 from capital to O&M operator budget due to outage constraints. Unit#3 complete earlier then scheduled. Unit#1 failure moved labor and materials earlier; Budget Update 4: Accelerated $251 k. added labor to BOP Design, accelerated unit#2 materials to be purchased in 2022. Annual Project Change$373k NOV: ($103k) Decrease in labor and materials DEC: ($12k) Governor manifold cost lower than estimated Annual Project Change$385k NOV: ($103k) Decrease in labor and materials 10/08/22 Current Year: Project change $489k Total FAC Change: $387k Unit#3 labor and materials higher then forcasted to complete unit. Added design hours for BOP. Unit#1 construction moved up because of failure. Ordering unit#2 equipment now due to supply chain issues. Looking innto adding coolers to unit#2, estimated costs are $200k. 2022 Budget Update 3: Total project Change: $238k; Budget Update 1: Carryover $60k, Project change $94k. Supply change delays have move material orders and labor into 2022; Budget Update 2: Project change $129k. Project inservice date moved out. Labor added to new inservice date; Budget Update 3: Project change $(108k). Moved $103,638.53 from capital to O&M operator budget due to outage constraints. Unit#3 complete earlier then scheduled. Unit#1 failure moved labor and materials earlier; 9/12/22 Current Year: Project change $401k Total FAC Change: $276k Unit#3 labor and materials higher then forcasted to complete unit. Added design hours for BOP. Unit#1 construction moved up because of failure. Ordering unit#2 equipment now due to supply chain issues. 8/10/22 Current Year: Project change $324k Total FAC Change: $242k Unit#3 labor and materials higher then forcasted to complete unit. Added design hours for BOP. Unit#1 construction moved up because of failure. Ordering unit#2 equipment now due to supply chain issues. 7/11/22 Current Year: Project change $268k Total FAC Change: ($154.13) Unit#3 labor and materials higher then forcasted to complete unit. Added design hours for BOP. Completion date moved to beginning of May due to Unit#1 failure. Unit#1 construction moved up because of failure. Ordering unit#2 equipment now due to supply chain issues. 2022 Budget Update 2: Total project Change: $284k; Budget Update 1: Carryover $60k, Project change $94k. Supply change delays have move material orders and labor into 2022; Budget Update 2: Project change $129k. Project inservice date moved out. Labor added to new inservice date; 6/9/22 Current Year: Project change $255k Total FAC Change: $26k Unit#3 labor and materials higher then forcasted to complete unit. Added design hours for BOP. Completion date moved to beginning of May due to Unit#1 failure. Unit#1 construction moved up because of failure. 5/12/22 Current Year: Project change $250k Total FAC Change: -$73k Unit#3 labor and materials higher then forcasted.Added design hours for BOP. Completion date moved to beginning of May due to Unit#1 failure. 4/11/22 Current Year: $284k Total FAC Change: $33k Unit#3 labor and materials higher then forcasted.Added design hours for BOP. Completion date moved to end of May due to GE schedule extension. 2022 Budget Update 1: Total project Change: $154k; Budget Update 1: Carryover $60k, Project change $94k. Supply change delays have move material orders and labor into 2022; 3/09/22 Current Year: $326k Total FAC Change: $75k Unit#3 labor and materials higher then forcasted.Added design hours for BOP. Completion date moved to end of May due to GE schedule extension. 2/09/22 Current Year: $260k Total FAC Change: $37k Unit#3 labor and materials higher then forcasted.Added design hours for BOP. Completion date moved to May due to GE schedule extension. 1/11/22 Current Year: $154k Total FAC Change: $1,511,850 Unit#3 labor and materials higher then forcasted.Added design hours for BOP. 2021 Budget Update 4: Total project Change: ($152k); Budget Update 1: Carryover $138k, Servo motor amd governor, labor and equipment were moved to 2021 to align with contracted construction schedule; Budget Update 2: Project Change $62k, Labor increase due to using more labor than anticipated; Budget Update 3: ($212k) Unit#1 construction moved to the fall of 2022 because of unit#3 refurbishment completion date shift to March of 2022; Budget Update 4: ($140k) Unit#1 construction moved to the fall of 2022 because of unit#3 refurbishment completion date shift to March of 2022. Labor and materials costs for the intake gate indication task were higher that projected; 12/13/21 Current Year: Deferred -$26k Total FAC Change: $1,285,084 Unit#3 labor and materials higher then forcasted. Materials and labor for the intake gate incidation project came in higher then forcast. Unit#1 construction moved to fall of 2022. 11/08/21 Current Year: Deferred -$67k Total FAC Change: $1,207,837 Unit#3 labor and materials higher then forcasted. Materials and labor for the intake gate incidation project came in higher then forcast. Unit#1 construction moved to fall of 2022. 10/11/21 Current Year: Deferred -$152k Total FAC Change: $1,101,281 Unit#3 labor and materials higher then forcasted. Materials and labor for the intake gate incidation project came in higher then forcast. Unit#1 construction moved to fall of 2022. 2021 Budget Update 3: Total project Change: ($12k); Budget Update 1: Carryover $138k, Servo motor amd governor, labor and equipment were moved to 2021 to align with contracted construction schedule; Budget Update 2: Project Change $62k, Labor increase due to using more labor than anticipated; Budget Update 3: ($212k) Unit#1 construction moved to the fall of 2022 because of unit#3 refurbishment completion date shift to March of 2022. 9/14/21 Current Year: Deferred -$272k Total FAC Change: $981,634 Unit#1 construction/materials moved next year due to delays in the completion of Unit#3. 8/11/21 Current Year: Deferred -$272k Total FAC Change: $956,529.84 Unit#1 construction/materials moved next year due to delays in the completion of Unit#3. July 2021 Update July 2021 Executive Update: Wiring diagrams for unit#1 are continuing with the P2P planned for the end of August/beginning of September depending on the designers'schedule. Construction is moving forward with unit#3.At the end of the month,the governor oil system will be pressurized and dry tested. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist July 2021 Detailed comments: In-service date (Unit#3 Outage starts 7/1/20) (Unit#1 Outage starts 10/3/22) -Current Unit#3: 2/16/22 Budget Update -Current month Total Project EAC: $5.5 million Brett LaHorgue is continuing with the wiring diagrams for unit#1. Once the unit#1 construction drawings are issued, he will be transitioning to the BOP design.This will put unit#1's design complete one year before construction and give us plenty of time to order parts. Unit#3's construction is going well, and Derek has almost completely taken over for Albert as the CSS for this project. Albert will be retiring at the end of July. Assignments -Designer—Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Construction continues with Unit#3. Design of Unit#1. 2021 Budget Update 2: Total project Change: $200k; Budget Update 1: Carryover $138k, Servo motor amd governor, labor and equipment were moved to 2021 to align with contracted construction schedule; Budget Update 2: Project Change $62k, Labor increase due to using more labor than anticipated; June 2021 Update June 2021 Executive Update: Two projects have been added as part of the modernization.They will not add time to the construction schedule. Wiring diagrams for unit#1 are continuing. Construction is moving forward with unit#3. We are still on schedule to be as far as we can be by the end of July when the wiring crew must move to their next project. Once the wiring crew leaves the technicians, mechanics, and operators will continue with the construction tasks that couldn't be completed while the refurbishment is still going on.This puts us at a good position to complete everything next year when the refurbish project is complete. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist June 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 2/16/22 Budget Update -Current month Total Project EAC: $5.6 million The Intake Gate Indication and Outlet Gate Indication projects have both been moved under this modernization project along with their budgets.This will give the construction team work to accomplish with the extended schedule. Brett LaHorgue is continuing with the wiring diagrams for unit#1. Once the unit#1 construction drawings are issued, he will be transitioning to the BOP design.This will put unit #1's design complete one year before construction and give us plenty of time to order parts. Unit#3's construction is going well, and Derek has almost completely taken over for Albert as the CSS for this project. Albert will be retiring at the end of July. Assignments -Designer—Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Construction continues with Unit#3. Design of Unit#1. May 2021 Update May 2021 Executive Update: The designer has started the wiring diagrams for unit#1. Construction is moving forward with unit#3. We are still on schedule to be as far as we can be by July.This puts us at a good position to complete everything next year when the refurbish project is complete. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist May 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.9 million Brett LaHorgue has started on the wiring diagrams for unit#1. After this he will be transitioning to the BOP design.This will put unit#1's design complete one year before construction and give us plenty of time to order parts. Unit#3's construction is going well, and Derek has almost completely taken over for Albert as the CSS for this project. Albert will be retiring at the end of July and has been shifting more and more of his projects to Derek. Assignments -Designer—Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Construction continues with Unit#3. Design of Unit#1 April 2021 Update April 2021 Executive Update: Schematic review is complete for unit#1. Even with the extension of unit#3's schedule we are keeping to the unit#1 and BOP Design schedule. By doing this we will be prepared for any change in unit#1's schedule. If unit#1 is accelerated the wiring crews schedule will need to be reviewed. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist April 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.9 million Unit#1's schematic review was completed by the new designer Brett, Derek, Albert, Brad and Carson. Brett will continue refining the schematics as action items get answered. Once all the schematic corrections are complete Brett will focus his attention to the wiring diagrams. Unit#3 construction is continuing, and we are not deviating from our current schedule even with the new extension.This will have us performing test outs this summer,those that can be performed without a complete unit.The full test out will occur once the unit is reassembled. Assignments -Designer—Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Construction continues with Unit#3. Design of Unit#1 March 2021 Update March 2021 Executive Update: Construction is moving forward on schedule for unit#3. Design has started for unit#1 and a schematic review is scheduled.To speed the materials purchase for the next unit each construction team is creating a parts list. Once the construction issue is delivered for unit#1 the Balance of Plant (BOP) design will start. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist March 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.9 million Even with material delivery delays the controls project is still on schedule. With the possible extension of the construction window from the generator rewind project a plan is being put in place for design and materials purchase for the next unit and the BOP.The current plan is to have the unit#1 design complete by August and then to start on the BOP design and have it completed by end of the year.This will put either project designed by the time unit#3 is back online with the current proposed schedule. Assignments -Designer—Beau Davidson/Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Construction continues with Unit#3. Design of Unit#1 2021 Budget Update 1; Total project Change: $138k; Budget Update 1: Carryover $138k, Servo motor amd governor, labor and equipment were moved to 2021 to align with contracted construction schedule; February 2021 Update February 2021 Executive Update: Construction is moving forward on schedule.The PLC programming is progressing slow however it will have little effect on test out.This will also not affect the overall project timeline.Scoping of unit#1 is complete and design has started. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist February 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.8 million The programming is a little behind schedule however plans are being made to get assistance from a couple Hagerman techs.The PLCs, engineer workstation, and operator workstation have all been powered up.The available servo drawings had the wrong servo ring information on them.This has caused us to order new rings after the first servo was removed and measured. One servo motor is reinstalled without new rings and the other is disassembled, cleaned, and waiting on new rings.The wiring crew is continuing with construction and has a focus in the control room.The generator RIO cabinet and intake RIO have both been completed. Once end devises have been installed those connections can be tested. Assignments -Designer—Beau Davidson/Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead Unit#3/ Brad Rau Project Tech Lead Unit#1 -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau January 2021 Executive Update: Construction is moving forward on schedule.The PLC programming is a little behind and won't be ready for test out until February.This will not affect the overall project timeline. Planning, scoping, and design of unit#1 will start this month and go into the next. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist January 2021 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.7 million The programming is a little behind schedule. Coordination is being made to have a couple Hagerman techs assist and help trouble shot any program issues.The available servo drawings had the wrong servo ring information on them.This has caused us to order new rings after the first servo was removed and measured. Instead of working on one servo at a time both servos will be removed, cleaned, and inspected while waiting on the new rings.The wiring crew is continuing with construction and has a focus in the control room and generator RIO cabinet. Assignments -Designer—Beau Davidson/Brett LaHorgue -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead -Mechanics/Governor—Laramie Simpson/Matt Paulin -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau 2020 Budget Update 4; Total project Change: $1,073,216; Budget Update 1: Accelerated $200k into 2020 from 2021 for preconstruction materials purchase. $212k was moved from LSPR150003 to HCPR190001. $62k for labor for design support/programming/engineering; Budget Update 2: No Change; Budget Update 3: Accelerated $308,666 for material and labor because of the unit#3 failure and accelerated refurbishment schedule.The scenario continues to change, but these numbers represent our first attempt at accelerating the full controls scope of work for Unit#3 into 2020 and early 2021, while moving the controls work for unit#1 into the slot that was originally planned for unit#3. Budget Update 4: Accelerated $133,865 for the new digital governor's specification, design, fabrication, and labor (both for the dissassembly of the old governor and the installlation of the new) for unit#3 as part of the accelerated schedule caused by the failure of unit#3. December 2020 Update December 2020 Executive Update: The wiring crew has the construction drawings and is continuing with removals and installation.The generator RIO has been placed, stub ups installed, and conductors pulled.The unit control panel is in the control room ready for installation.The PLC program and HMI display is still under development and should be complete by January.The governor manifold is being manufactured and scheduled for delivery by the end of January. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist December 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.8 million The wiring crew has made a lot of progress in a short time.They now have the construction drawings and have already placed the generator RIO along with rebuilt the intake RIO. Cable tray has been installed along with conduit stub ups. Some conductors have been pulled to their respective locations and are ready for termination. Sam is continuing with the programming and Kyle is working on the HMI display. Both will be complete by January. Kyle was able to make a visit to the Hagerman shop to work with Greg on the Wonderware system. In conversations with most of the crews working on this project it sounds like a large portion of them are taking the two weeks around Christmas off. Currently this will not affect the projects schedule. Carson will be on call during this time period and will also be working at the plant. Assignments -Designer—Beau Davidson -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead -Mechanics/Governor—Laramie Simpson -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Start of full construction. November 2020 Update November 2020 Executive Update: The wiring crew arrived on the 9t" of November to start construction. With the arrival of the wiring crew full construction is now starting.The E-Shop is complete with the equipment builds and they have arrived at the plant.The point to point is complete and once all the redlines have been added to the drawings the construction set will be issued. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist November 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 7/28/21 Budget Update -Current month Total Project EAC: $4.8 million At the beginning of the month the P2P was completed and Beau is incorporating all the redlines into the construction set which will be issued once complete. Don Craine and his wiring crew have started work at the Hells Canyon Power Plant.The wiring crew is conducting site prep and disassembly as needed. With the main priority being the Intake RIO.The maintenance crew has sent the SSG to the techs to start test out with the new governor plc. A maintenance crew has been assigned to remove, clean, repair, and reassemble the servo motors. Carson Kindall still has the fiber termination panel to complete at the intake RIO, otherwise the other fiber runs are complete. Kyle Davis is going to contact Greg Peasnall from the Hagerman Tech group to help with the Wonderware/PLC programming,for some time in December. In December this project will be in full construction mode with the construction set drawings,the CSS and wiring crew on site. Assignments -Designer—Beau Davidson -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead -Mechanics/Governor—Laramie Simpson -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Start of full construction October 2020 Update October 2020 Executive Update: The wiring crew has been scheduled to arrive the second week of November to start construction. Preconstruction is ongoing as parts arrive at the plant with full construction to start with the arrival of the wiring crew. Drawings have been sent over to the E-Shop for panel and RIO builds. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist October 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 8/2/21 Budget Update -Current month Total Project EAC: $4.6 million The wiring crew is currently working at the Brownlee power plant and is scheduled to stay there until the second week of November. Once they arrive at Hells Canyon power plant,they will start site prep and disassembly as needed. With the main priority being the Intake RIO.As parts arrive assembly will start.The maintenance crew has already started on the PMG to SSG conversion as well as having the digital governor designed and built with IPC specifications from an outside contractor.The preliminary drawings are now starting to come in for the governor. Kyle Davis and Brad Rau are in contact with Greg Peasnall from the Hagerman Tech group about the PLC programming.They are coordinating to have him visit the site at the end of October or beginning of November, depending on progress and schedules. This has already been affected by multiple projects going on in the canyon complex.A maintenance crew has been assigned to remove, clean, repair, and reassemble the servo motors. Beau Davidson is completing the 2020 Budget Update 4; Total project Change: $1,073,216; Budget Update 1: Accelerated $200k into 2020 from 2021 for preconstruction materials purchase. $212k was moved from LSPR150003 to HCPR190001. $62k for labor for design support/programming/engineering; Budget Update 2: No Change; Budget Update 3: Accelerated $308,666 for material and labor because of the unit#3 failure and accelerated refurbishment schedule.The scenario continues to change, but these numbers represent our first attempt at accelerating the full controls scope of work for Unit#3 into 2020 and early 2021, while moving the controls work for unit#1 into the slot that was originally planned for unit#3. Budget Update 4: Accelerated $133,865 for new digital governor and labor for unit#3 as part of the accelerated schedule caused by the failure of unit#3. September 2020 Update September 2020 Executive Update: We have moved forward with the full control's modernization project.Assignments have been made and priority tasks have been assigned. Preconstruction is ongoing as parts arrive at the plant with full construction to start in November with the arrival of the wiring crew.The wiring crew is scheduled to arrive on November 2"d. With this accelerated schedule the Balance of Plant (BOP) will be moved to in between unit#1 and unit#2. Drawings and equipment are also starting to arrive at the E-Shop for panel and RIO builds. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist September 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 8/2/21 Budget Update -Current month Total Project EAC: $4.65 million We have moved forward with most of the original scope of work for the unit controls upgrade. With the limited amount of design and construction time the BOP is being moved until after Unit#1.This will give the designer time to focus on unit#1 after the drawing package is complete for unit#3.After a conversation with the techs this is preferred as there is not much construction time in between these first units.This will have the BOP starting before unit#2 and finishing with the unit for all final connections.Assignments have been made, as can be seen from the list below.The E-Shop has the drawings for the panels and RIO and as parts arrive,they will be built and set aside for delivery. E-shop equipment builds will be delivered to the plant by mid to late October.This will be right before the wiring crew arrives at the beginning of November.The governor contractor is making a trip to the plant for final measurements before design and fabrication.This is being coordinated through Laramie Simpson. Assignments -Designer—Beau Davidson -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead -Mechanics/Governor—Laramie Simpson -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Possible acceleration of project due to the failure of unit#3. August 2020 Update August 2020 Executive Update: Schematic review is complete. We are moving forward with the full control's modernization project. Assignments have been made and priority tasks have been assigned. Preconstruction is ongoing as parts arrive at the plant with full construction to start in November with the arrival of the wiring crew.The wiring crew is scheduled to arrive on November 2nd. With this accelerated schedule the Balance of Plant (BOP)will be moved to in between unit#1 and unit#2. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Readiness Review Checklist August 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 4/1/21 Budget Update -Current month Total Project EAC: $4.3 million Currently we are moving forward with the full scope of work for the unit controls upgrade. With the limited amount of design and construction time the BOP is being moved until after Unit#1.This will give the designer time to focus on unit#1 after the drawing package is complete for unit#3.After a conversation with the techs this is preferred as there is not much construction time in between these first units.This will have the BOP starting before unit#2 and finishing with the unit for all final connections.Assignments have been made, as can be seen from the list below. By the end of the month parts will be ordered. E-Shop drawings are scheduled to be delivered by the end of September. E-shop equipment builds will be delivered to the plant by mid to late October.This will be right before the wiring crew arrives at the beginning of November. Laramie Simpson and Rob O'Neil are both working on the governor design, specification, and purchase.This is being slowed down from the lack of detailed governor Assignments -Designer—Beau Davidson -Design Engineer—Stephen Sjostrom -Wiring crew—Don Craine -Technicians—Carson Kindall Project Tech Lead -Mechanics/Governor—Laramie Simpson -CSS—Albert Izaguirre/Derek VanderMeer - PLC Programmer—Sam Groner - HMI/Wonderware—Kyle Davis -PLC Configurations—Brad Rau Next month comments: Possible acceleration of project due to the failure of unit#3. July 2020 Update July 2020 Executive Update: Unit#3 had a failure.This failure is causing the refurbishment project to be accelerated. Information is being gathered to determine if this project is also accelerated in full, part, or deferred to another year. Right now we are moving forward with all aspects of this project. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Business Case July 2020 Detailed comments: In-service date (Outage starts 7/1/20) -Current Unit#3: 4/1/21 Budget Update -Current month Total Project EAC: $4.3 million With the failure of the unit we looked at many different scenarios. Currently we are moving forward with the full scope of work for the unit controls upgrade.This has caused the acceleration of 2021 tasks into 2020. Also,the next unit(unit#1) has been moved into Unit#3's outage slot in the fall of 2021 and so on for unit#2 in the fall of 2022. Currently the restrictions for this project are coordinating the wiring crew,they are currently assigned to the local service at Lower Salmon and the protection upgrade at Swan Falls. We are currently looking at having contractors brought in to complete these projects as the Hagerman Technicians don't have the man power to complete them.Also being able to complete a complete design in order to have drawings to the E-Shop for cabinet and rack builds. Another possible obstacle is the controls programming.This PLC programming is new to the Canyon Techs; however they are working off of the program used at Twin Falls and coordination with the Hagerman Techs for sup Resources Scheduled -Designer -Design Engineer -Wiring crew -Technicians -Mechanics -CSS Next month comments: Possible acceleration of project due to the failure of unit#3. June 2020 Update June 2020 Executive Update: Covid-19 has us using WebEx for meetings, sharing, and coordination and has added more time to this phase. Computers are being setup at the Oxbow school house for use during schematic review. Current plans are to conduct this review in July online while the technicians use the computers at the school house. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Business Case June 2020 Detailed comments: In-service date (Outage starts 8/9/21) -Current Unit#3: 2/1/22 Budget Update -Current month Total Project EAC: $4.1 million Do to the current Covid-19 situation we are currently using WebEx for all major meetings.This is a great tool which allows us to share content and discuss it.This has however increased the time needed for these meetings which has increased the budget.The schematic review will be conducted over Webex along with the design review tool. Preconstruction is scheduled to start January 2021. Only items that do not interrupt current operations will be installed Kyle Davis is working on creating HMI displays for all three units to replace the current Realflex HMI this fall.These displays will need to be modified once the new PLCs are installed starting with unit#3. Kidney Loop Filter system -Design will follow Brownlee unit#5 -Laramie Simpson is starting to purchase equipment -Installation will be this summer -Early installation and operation will allow the oil to be clean enough for the new digital governors Resources Scheduled -Designer -Design Engineer -Wiring crew -Technicians -Mechanics -CSS Next month comments: Continuing with design, graphics displays, and PLC logic in preparation for the schematic review in July. Previous month comments: 2020 Budget Update 2; Total project Change: $474,665; Budget Update 1: Accelerated $200k into 2020 from 2021 for preconstruction materials purchase. $212k was moved from LSPR150003 to HCPR190001. $62k for labor for design support/programming/engineering; Budget Update 2: No Change; May 2020 Update May 2020 Executive Update: Schematic/10 review and logic review is complete. Covid-19 has us using WebEx for meetings, sharing, and coordination and has added more time to this phase. Computers are being setup at the Oxbow school house for use during schematic review. Current plans are to conduct this review in July while keeping our social distancing. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Business Case May 2020 Detailed comments: In-service date (Outage starts 8/9/21) -Current Unit#3: 2/1/22 Budget Update -Current month Total Project EAC: $3.9 million Do to the current Covid-19 situation we are currently using WebEx for all major meetings.This is a great tool which allows us to share content and discuss it.This has however increased the time needed for these meetings which has increased the budget. Preconstruction is scheduled to start January 2021. Only items that do not interrupt current operations will be installed Kyle Davis is working on creating HMI displays for all three units to replace the current Realflex HMI this fall.These displays will need to be modified once the new PLCs are installed starting with unit#3. Kidney Loop Filter system -Design will follow Brownlee unit#S -Laramie Simpson is starting to purchase equipment -Installation will be this summer -Early installation and operation will allow the oil to be clean enough for the new digital governors Resources Scheduled -Designer -Design Engineer -Wiring crew -Technicians -Mechanics -CSS Next month comments: Continuing with design, graphics displays, and PLC logic in preparation for the schematic review in July. April 2020 Update April 2020 Executive Update: Standards review is complete. Schematic/10 review will be finished up late this week or early next.This will put us into logic review.This will last another couple weeks. Covid-19 has us using WebEx for meetings, sharing, and coordination and added more time to this phase. Approved Project Framework Phase (Business Case, Planning, Execution, Construction, Close): Business Case April 2020 Detailed comments: In-service date (Outage starts 8/9/21) -Current Unit#3: 2/1/22 Budget Update -Current month Total Project EAC: $3,962K Do to the current Covid-19 situation we are currently using WebEx for all major meetings.This is a great tool which allows us to share content and discuss it.This has however increased the time needed for these meetings. Preconstruction is scheduled to start January 2021. Only items that do not interrupt current operations will be installed Kyle Davis is working on creating HMI displays for all three units to replace the current Realflex HMI this year.These displays will need to be modified once the new PLCs are installed. Kidney Loop Filter system -Design will follow Brownlee unit#5 -Laramie Simpson is starting to purchase equipment -Installation will be this summer -Early installation and operation will allow the oil to be clean enough for the new digital governors Resources Scheduled -Designer -Design Engineer -Wiring crew -Technicians -Mechanics -CSS Next month comments: WebEx meetings impact on budget. Continuing with design,graphics displays, and PLC logic. Previous month comments: 2019 Budget Update 4 Total Project Change: $37.4K Budget Update 4: Accelerated $37.4K for design budgeted in 2020.