HomeMy WebLinkAboutIntermountain Gas 3 Jun Nampa Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins Date(s): 3-Jun-20
Company/Owner: Intermountain Gas Company Unit/OPID: 8160
Inspection Type &Time (1 day) I Total Inspection Days: 1
Standard:FI Construction:� Training: F—] (T)(D)Integrity Management: F-1 Incident:
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co, a contractor for Intermountain Gas Company.
3 June 2020: (.8 Construction, .2 typed report)
Observed a Das-co crew installing a new W service line inside a 2" PE pipe being used as a sleeve because of
rocky ground at 3800 Airport Rd in Nampa, Idaho. All procedures were followed.Typed up report
Areas observed during this project were: Excavating, line locating, boring, bedding, EFV installation, service line
install and pressure testing.
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes NoF X by(date):
Inspector (Lead): Date:
Bruce Perkins 6/3/2020
Reviewer: Date:
Darrin Ulmer q
IPUC Form 1