HomeMy WebLinkAboutIntermountain Gas 1 Jun Nampa Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins I Date(s): 1-Jun-20
Company/Owner: Intermountain Gas Company Unit/OPID: 8160
Inspection Type &Time (1 day) I Total Inspection Days: 1
Standard:71 Construction:FTI Training: F__] (T)(D) Integrity Management: F7 Incident: El
M/M: F-1 Follow-up: F-1 oQ: F-1 Damage Prevention: F-1 D&A:
Inspection Summary
A construction inspection was performed on Track, a contractor for Intermountain Gas Company.
1 June 2020: (.5 Construction, .5 typed report)
Observed a Track crew Installing new W service tees and stubs and fusing 2" main, in New York Landing
Subdivision, Happy Valley Rd/Alma Rd in Nampa, Idaho. All procedures were followed. Typed up report
Attachments:
IPUC Form 4 Construction Inspections
Track Daily Itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Follow-up Required: Yes No X
Yes No X by(date):
Inspector (Lead): Date:
Bruce Perkins 6/1/2020
Reviewer: Date:
Darrin Ulmer -eczb
IPUC Form 1