HomeMy WebLinkAboutAvista Feb CDA Construction Idaho PUC Pipeline Safety Inspection Summary Inspector(s). Ulmer/Perkins/Russo I Date(s): Feb 5-9, 2018 Company/Owner: Avista Utilities Unit/OPID: 1 31232 Inspection Type &Time (1 day, 0.5 day) Total Inspection Days:1 16 Standard:F7 Construction: 4.5 Training: F3 (T)(D) Integrity Management: Incident: M/M: = Follow-up: oQ: 1.5 Damage Prevention: D&A: Inspection Summary Construction inspections were performed on Avista crews in the Coeur d'Alene area. February 5, 2018: (3 Standard) Traveled to Spokane, WA to conduct inspection. February 6, 2018: (3 Construction) The crew was bedding and backfilling a 6" plastic main that was trenched and joined the day before near the intersection of Chilco Rd and Penobscot Rd near Athol, ID. Areas observed during this project were: locating other utilities, excavation, main installation (tracer wire), bedding and backfilling. February 7, 2018: (3 Operator Training) Met with Avista personnel at their Jack Stewart Training Center and received a tour of the complex. Sat in and observed a Self-Contained Breathing Apparatus (SCBA) refresher class where employees and contractors had to don the gear and pinch off a simulated gas leak on PE and steel pipe. Fire extinguisher training consisted of simulated scenarios of three pipe fires(one stub, one service line and one service line in a trench). Observed an Avista trainer conduct actual Operator Qualifications on: Mechanical Spigot and Sleeve type fitting and PE Pipe Joining on: Mechanical Couplings, Mechanical Service Tees, Electrofusion and Hydraulic Butt Fusion. February 8, 2018: (3 Construction) The crew was installing 2" plastic main and 3/4" plastic service lines leaving stubs for a new housing development in the Cedar Creek Subdivision south of 1500 S Greensferry Rd, CDA, ID. Areas observed during this project were:gas line locating, excavation, plastic main installation (tracer wire), plastic service line installation (tracer wire), plastic pipe joining, hot tapping, electrofusion, mechanical couplings, service tee w/EFV installation, pressure testing, purging, stub locating, bedding and backfilling. An Operator Qualification inspection was performed on C.J. Leonard the Avista Gas Apprentice on a crew in Coeur d'Alene District while performing Pipeline cover, clearance and backfilling. C.J was fully aware of AOC's and performed the task in a satisfactory manner. February 9, 2018: (3 Standard) Traveled back to Boise, ID. IPUC Form 1 Idaho PUC Pipeline Safety Inspection Summary February 12, 2018: (1 Standard) Typed the inspection report, completed IPUC Form 1 and IPUC Form 4s. Attached: PHMSA Form 15, OQ Field Inspection IPUC Form 1, Inspection Summary IPUC Form 4, Construction Inspection Jack Stewart Training Center Schedule Attendance sheet for SCBA Refresher Class Attendance sheet for Gas Fire School Misc. Photos Corrective Action Required: Yes No X Follow-up Required: by(date): Yes No X Close-out Letter Issued: A Yes No X Inspector (Lead): Date: Reviewer: Date: IPUC Form 1