HomeMy WebLinkAbout20240905PAC to Staff 139-2 - Attachment 002 4.3_Copco_II_Substation_Expansion_Construction_Schedule.pdfID Task Mode Task Name Duration Start Finish Predecessors 1 Copco II Yard Expansion 130 days?Mon 6/5/23 Fri 12/1/23 2 Mobilization 5 days Mon 6/5/23 Fri 6/9/23 3 BMP Installation 10 days Mon 6/12/23 Fri 6/23/23 2 4 Reroute existing Copco  II‐Westside 69KV Line  10 days Mon  6/26/23 Fri 7/7/23 3 5 Clearing & Grubbing 15 days Mon 7/10/23 Fri 7/28/23 4 6 Cut & Fill 25 days Mon 7/31/23 Fri 9/1/23 5 7 Fence Installation 15 days Mon 9/4/23 Fri 9/22/23 6 8 Concrete Foundaitons 15 days Mon 9/4/23 Fri 9/22/23 6 9 Conduit Installation 5 days Mon 9/25/23 Fri 9/29/23 8 10 Grounding Installation 15 days Mon 10/2/23 Fri 10/20/23 9 11 Install steel 2 days Mon 10/23/2 Tue 10/24/2310 12 Install electrical equipment 15 days Wed 10/25/2 Tue 11/14/2311 13 Install above ground conduit  & grounding  10 days Wed  10/25/23 Tue 11/7/23 11 14 Install and terminate control  and pwr cable 5 days Wed  11/8/23 Tue  11/14/23 13 15 Test and Commisioning 5 days Wed 11/15/2 Tue 11/21/2314 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 June 2023 July 2023 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: 4.3 Copco II Substation Date: Fri 5/19/23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 August 2023 September 2023 October 2023 November 2023 December Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: 4.3 Copco II Substation Date: Fri 5/19/23