20240906PAC to Staff 139-2 - Attachment - Construction Schedule - Line work.pdf
ID Task Name Duration Start Finish 1 NTP 0 days Fri 1/12/24 Fri 1/12/24 2 Mobilize crews 5 days Mon 2/5/24 Fri 2/9/24 3 Remove transmission line, poles and assemblies 40 days Mon 2/12/24 Fri 4/5/24 4 Cleanup and demobe 5 days Mon 4/8/24 Fri 4/12/24 5 Project Complete 0 days Fri 4/12/24 Fri 4/12/24 1/12 4/12 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 3 January 2024 February 2024 March 2024 April 2024 PAC00082 Copco Dam area line modifications and removals, Hornbrook, CA BID DUE: 1/8/24 Key Line Construction Preliminary Schedule Page 1