HomeMy WebLinkAbout20240830PAC to Staff 214 Attachment Houston Lake-Ponderosa Project Schedule.pdfID % Complete Task Name Duration Start Finish 1 48%ILB_Huston Lake 99.58 days Mon 7/8/24 Fri 10/18/24 2 7%CORRAL ‐ OCHOCO #1 230kv 56.16 days Mon 7/29/24Wed 9/25/24 3 33% **POLE WORK**48.34 days Mon 7/29/24Tue 9/17/24 4 0%A - 0001 0.08 days Mon 9/16/24 Mon 9/16/24 5 100%1/1 - 1010 0.08 days Mon 7/29/24 Mon 7/29/24 6 100%2/1 - 1020 0.17 days Mon 7/29/24 Mon 7/29/24 7 100%3/1 - 1030 0.17 days Mon 7/29/24 Mon 7/29/24 8 100%4/1 - 1040 0.17 days Mon 7/29/24 Mon 7/29/24 9 100%5/1 - 1050 0.17 days Mon 7/29/24 Mon 7/29/24 10 100%6/1 - 1060 0.08 days Mon 7/29/24 Mon 7/29/24 11 0%7/1 - 1070 0.17 days Mon 9/16/24 Mon 9/16/24 12 0%8/1 - 1080 0.08 days Mon 9/16/24 Mon 9/16/24 13 0%9/1 - 1090 0.17 days Mon 9/16/24 Mon 9/16/24 14 0%10/1 - 1100 0.08 days Mon 9/16/24 Mon 9/16/24 15 0%11/1 - 1110 0.17 days Mon 9/16/24 Mon 9/16/24 16 0%12/1 - 1120 0.17 days Mon 9/16/24 Mon 9/16/24 17 0%1/2 - 2010 0.08 days Mon 9/16/24 Mon 9/16/24 18 0%2/2 - 2020 0.17 days Mon 9/16/24 Tue 9/17/24 19 0%3/2 - 2030 0.17 days Tue 9/17/24 Tue 9/17/24 20 0%4/2 - 2040 0.33 days Tue 9/17/24 Tue 9/17/24 21 0% **WIRE WORK**6.42 days Wed 9/18/24Wed 9/25/24 22 0%DEAD END/CLIP WIRE/JUMPERS 1/1 - 8/1 2.38 days Thu 9/19/24 Fri 9/20/24 23 0%WIRE PULL : 1/1 - 8/1 1.08 days Wed 9/18/24 Thu 9/19/24 24 0%DEAD END/CLIP WIRE/JUMPERS 8/1 - 10/1 0.79 days Fri 9/20/24 Mon 9/23/24 25 0%WIRE PULL: 8/1 - 10/1 0.63 days Thu 9/19/24 Thu 9/19/24 26 0%DEAD END/CLIP WIRE/JUMPERS 10/1 -1/2 0.92 days Mon 9/23/24 Tue 9/24/24 27 0%WIRE PULL: 10/1 -1/2 0.67 days Thu 9/19/24 Fri 9/20/24 28 0%WIRE PULL: 1/2 - 4/2 0.75 days Fri 9/20/24 Fri 9/20/24 29 0%DEAD END/CLIP WIRE/JUMPERS 1/2 - 4/2 0.75 days Tue 9/24/24 Tue 9/24/24 30 0%WIRE REMOVAL/INSTALL A - 1/1 0.5 days Tue 9/24/24 Wed 9/25/24 31 0%DEAD END/CLIP WIRE/JUMPERS A - 1/1 0.42 days Tue 9/24/24 Wed 9/25/24 32 25%Corral – Ochoco 230kV /  Houston Lake – Ponderosa #2 115k81.7 days Thu 7/25/24 Fri 10/18/24 33 56%**POLE WORK**77.49 days Thu 7/25/24 Tue 10/15/24 34 100%5/2 - 2050 0.08 days Thu 7/25/24 Thu 7/25/24 35 0%6/2 - 2060 0.08 days Thu 7/25/24 Thu 7/25/24 36 0%7/2 - 2070 0.17 days Thu 7/25/24 Thu 7/25/24 37 0%8/2 - 2080 0.17 days Thu 7/25/24 Thu 7/25/24 38 0%9/2 - 2090 0.17 days Thu 7/25/24 Thu 7/25/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 39 100%10/2 - 2100 0.08 days Thu 7/25/24 Thu 7/25/24 40 0%11/2 - 2110 0.17 days Thu 7/25/24 Thu 7/25/24 41 0%12/2 - 2120 0.17 days Thu 7/25/24 Thu 7/25/24 42 100%13/2 - 2130 0.08 days Thu 7/25/24 Fri 7/26/24 43 0%1/3 - 3010 0.17 days Fri 7/26/24 Fri 7/26/24 44 0%2/3 - 3020 0.17 days Fri 7/26/24 Fri 7/26/24 45 0%3/3 - 3030 0.17 days Fri 7/26/24 Fri 7/26/24 46 0%4/3 - 3040 0.17 days Fri 7/26/24 Fri 7/26/24 47 100%5/3 - 3050 0.08 days Fri 7/26/24 Fri 7/26/24 48 100%6/3 - 3060 0.08 days Fri 7/26/24 Fri 7/26/24 49 100%7/3 - 3070 0.17 days Fri 7/26/24 Fri 7/26/24 50 100%8/3 - 3080 0.17 days Fri 7/26/24 Fri 7/26/24 51 100%9/3 - 3090 0.17 days Fri 7/26/24 Mon 7/29/24 52 100%10/3 - 3100 0.17 days Mon 7/29/24 Mon 7/29/24 53 100%11/3 - 3110 0.17 days Mon 7/29/24 Mon 7/29/24 54 100%12/3 - 3120 0.08 days Tue 10/15/24Tue 10/15/24 55 100%12x1/3 - 3121 CATALINA SUB 0.08 days Tue 10/15/24Tue 10/15/24 56 100%12x2/3 - 3122 CATALINA SUB 0.33 days Tue 10/15/24Tue 10/15/24 57 0%12x3/3 - 3123 CATALINA SUB 0.83 days Wed 9/4/24 Wed 9/4/24 58 0%12x4/3 - 3124 CATALINA SUB 0.83 days Wed 9/4/24 Thu 9/5/24 59 0%12x5/3 - 3125 CATALINA SUB 0.83 days Thu 9/5/24 Fri 9/6/24 60 100%13/3 - 3130 0.17 days Tue 10/15/24Tue 10/15/24 61 0%14/3 - 3140 0.17 days Mon 7/29/24 Mon 7/29/24 62 100%1/4 - 4010 0.08 days Fri 10/11/24 Fri 10/11/24 63 100%2/4 - 4020 0.08 days Fri 10/11/24 Fri 10/11/24 64 0%3/4 - 4030 0.13 days Fri 10/11/24 Fri 10/11/24 65 0%4/4 - 4040 0.13 days Fri 10/11/24 Fri 10/11/24 66 100%5/4 - 4050 0.08 days Tue 10/15/24Tue 10/15/24 67 100%6/4 - 4060 0.17 days Mon 7/29/24 Mon 7/29/24 68 100%7/4 - 4070 0.17 days Mon 7/29/24 Mon 7/29/24 69 100%8/4 - 4080 0.17 days Mon 7/29/24 Mon 7/29/24 70 100%9/4 - 4090 0.17 days Mon 7/29/24 Mon 7/29/24 71 100%10/4 - 4100 0.17 days Mon 7/29/24 Tue 7/30/24 72 100%11/4 0.08 days Tue 7/30/24 Tue 7/30/24 73 100%12/4 - 4120 0.17 days Tue 7/30/24 Tue 7/30/24 74 100%1/5 - 5010 0.17 days Tue 7/30/24 Tue 7/30/24 75 100%2/5 - 5020 0.17 days Tue 7/30/24 Tue 7/30/24 76 0%3/5 - 5030 0.17 days Tue 7/30/24 Tue 7/30/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 2 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 77 100%4/5 - 5040 0.17 days Tue 7/30/24 Tue 7/30/24 78 100%5/5 - 5050 0.08 days Tue 7/30/24 Tue 7/30/24 79 100%6/5 - 5060 0.17 days Wed 7/31/24 Thu 8/1/24 80 0%7/5 - 5070 0.17 days Thu 8/1/24 Thu 8/1/24 81 100%8/5 - 5080 0.17 days Thu 8/1/24 Thu 8/1/24 82 0%9/5 - 5090 1.25 days Wed 9/4/24 Thu 9/5/24 83 100%10/5 - 5100 0.17 days Thu 8/1/24 Thu 8/1/24 84 100%11/5 - 5110 0.08 days Thu 8/1/24 Thu 8/1/24 85 100%12/5 - 5120 0.17 days Thu 8/1/24 Thu 8/1/24 86 100%13/5 - 5130 0.17 days Thu 8/1/24 Thu 8/1/24 87 100%1/6 - 6010 0.17 days Thu 8/1/24 Thu 8/1/24 88 0%2/6 - 6020 1.25 days Tue 9/3/24 Wed 9/4/24 89 0%3/6 - 6030 1.25 days Fri 8/30/24 Tue 9/3/24 90 0%4/6 - 6040 1.25 days Thu 8/29/24 Fri 8/30/24 91 0%5/6 - 6050 1.25 days Wed 8/28/24 Thu 8/29/24 92 0%6/6 - 6060 1.25 days Wed 8/28/24 Wed 8/28/24 93 0%7/6 - 6070 1.25 days Tue 8/27/24 Wed 8/28/24 94 0%8/6 - 6080 1.25 days Mon 8/26/24 Tue 8/27/24 95 100%9/6 - 6090 0.17 days Thu 8/1/24 Thu 8/1/24 96 0%10/6 - 6100 1.25 days Fri 8/23/24 Mon 8/26/24 97 100%11/6 - 6110 0.17 days Thu 8/1/24 Fri 8/2/24 98 100%1/7 - 7010 0.17 days Fri 8/2/24 Fri 8/2/24 99 100%2/7 - 7020 0.17 days Fri 8/2/24 Fri 8/2/24 100 100%3/7 - 7030 0.17 days Fri 8/2/24 Fri 8/2/24 101 100%4/7 - 7040 1.25 days Thu 8/22/24 Fri 8/23/24 102 100%5/7 - 7050 0.08 days Thu 8/22/24 Thu 8/22/24 103 100%6/7 - 7060 1.25 days Wed 8/21/24 Thu 8/22/24 104 100%7/7 - 7070 1.25 days Tue 8/20/24 Wed 8/21/24 105 100%8/7 - 7080 1.25 days Mon 8/19/24 Tue 8/20/24 106 0%9/7 - 7090 1.25 days Fri 8/16/24 Mon 8/19/24 107 0%10/7 - 7100 1.25 days Thu 8/15/24 Fri 8/16/24 108 100%11/7 - 7110 0.17 days Fri 8/2/24 Fri 8/2/24 109 100%12/7 - 7120 0.17 days Fri 8/2/24 Fri 8/2/24 110 100%13/7 - 7130 0.17 days Fri 8/2/24 Fri 8/2/24 111 100%1/8 - 8010 0.17 days Fri 8/2/24 Fri 8/2/24 112 100%2/8 - 8020 0.17 days Fri 8/2/24 Mon 8/5/24 113 100%3/8 - 8030 0.17 days Mon 8/5/24 Mon 8/5/24 114 100%4/8 - 8040 0.17 days Mon 8/5/24 Mon 8/5/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 3 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 115 100%5/8 - 8050 0.17 days Mon 8/5/24 Mon 8/5/24 116 100%6/8 - 8060 0.08 days Mon 8/5/24 Mon 8/5/24 117 100%7/8 - 8070 0.17 days Mon 8/5/24 Mon 8/5/24 118 100%8/8 - 8080 0.17 days Mon 8/5/24 Mon 8/5/24 119 100%9/8 - 8090 0.17 days Mon 8/5/24 Mon 8/5/24 120 100%10/8 - 8100 0.17 days Mon 8/5/24 Mon 8/5/24 121 100%11/8 - 8110 1.25 days Wed 8/14/24 Wed 8/14/24 122 100%12/8 - 8120 1.25 days Tue 8/13/24 Tue 8/13/24 123 100%1/9 - 9010 0.08 days Tue 8/13/24 Tue 8/13/24 124 100%2/9 - 9020 0.17 days Mon 8/12/24 Tue 8/13/24 125 100%3/9 - 9030 0.17 days Mon 8/12/24 Mon 8/12/24 126 100%4/9 - 9040 0.08 days Mon 8/12/24 Mon 8/12/24 127 100%5A/9 - 9051 0.83 days Thu 8/8/24 Thu 8/8/24 128 100%6A/9 0.83 days Wed 8/7/24 Thu 8/8/24 129 100%7A/9 1.67 days Mon 8/12/24 Tue 8/13/24 130 100%8A/9 1.67 days Thu 8/8/24 Mon 8/12/24 131 100%9/9 0.08 days Mon 8/5/24 Tue 8/6/24 132 100%10/9 0.17 days Tue 8/6/24 Tue 8/6/24 133 100%11/9 0.17 days Tue 8/6/24 Tue 8/6/24 134 100%12/9 0.17 days Tue 8/6/24 Tue 8/6/24 135 100%13/9 0.17 days Tue 8/6/24 Tue 8/6/24 136 100%14/9 0.17 days Tue 8/6/24 Tue 8/6/24 137 100%1/10 0.17 days Tue 8/6/24 Tue 8/6/24 138 100%2/10 0.17 days Tue 8/6/24 Tue 8/6/24 139 100%3/10 0.17 days Tue 8/6/24 Wed 8/7/24 140 100%4/10 0.17 days Wed 8/7/24 Wed 8/7/24 141 100%5/10 0.42 days Wed 8/7/24 Wed 8/7/24 142 100%6/10 0.17 days Wed 8/7/24 Wed 8/7/24 143 100%7/10 0.17 days Wed 8/7/24 Wed 8/7/24 144 100%8/10 0.25 days Wed 8/14/24 Thu 8/15/24 145 100%9/10 0.08 days Thu 8/15/24 Thu 8/15/24 146 100%10/10 0.08 days Thu 8/15/24 Thu 8/15/24 147 100%1/11 0.83 days Thu 8/15/24 Thu 8/15/24 148 100%2/11 0.83 days Wed 8/7/24 Thu 8/8/24 149 100%3/11 0.83 days Thu 8/8/24 Thu 8/8/24 150 100%4/11 0.83 days Mon 8/12/24 Mon 8/12/24 151 100%5/11 0.83 days Thu 8/8/24 Fri 8/9/24 152 100%6/11 0.83 days Fri 8/9/24 Mon 8/12/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 4 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 153 0%CROSSINGS (GUARD STRUCTURES)4.17 days Thu 9/5/24 Tue 9/10/24 154 0%**WIRE WORK**65.2 days Mon 8/12/24Fri 10/18/24 155 0%WIRE PULL; 4/2 - 10/2 0.94 days Wed 10/9/24 Thu 10/10/24 156 0%DEAD END/CLIP WIRE/JUMPERS 4/2 - 10/2 2.25 days Thu 10/10/24Fri 10/11/24 157 0%WIRE PULL 10/2 - 13/2 1.67 days Mon 10/7/24 Tue 10/8/24 158 0%DEAD END/CLIP WIRE/JUMPERS 10/2 - 13/2 0.92 days Tue 10/8/24 Wed 10/9/24 159 0%WIRE PULL 13/2 - 5/3 0.83 days Fri 10/4/24 Fri 10/4/24 160 0%DEAD END/CLIP WIRE/JUMPERS 13/2 - 5/3 1.17 days Fri 10/4/24 Mon 10/7/24 161 0%WIRE PULL 1 SPAN BETWEEN 5/3-6/3 0.42 days Thu 10/3/24 Thu 10/3/24 162 0%DEAD END/CLIP WIRE/JUMPERS 5/3-6/3 0.63 days Thu 10/3/24 Fri 10/4/24 163 0%WIRE PULL 6/3 - 12/3 1.04 days Tue 10/1/24 Wed 10/2/24 164 0%DEAD END/CLIP WIRE/JUMPERS 6/3 - 12/3 1.29 days Wed 10/2/24 Thu 10/3/24 165 0%WIRE PULL 12/3 - 13/3 (INCLUDING SHIELD WIR 1.67 days Tue 9/24/24 Wed 9/25/24 166 0%DEAD END/CLIP WIRE/JUMPERS 12/3 - 13/3 5.21 days Wed 9/25/24 Tue 10/1/24 167 0%WIRE REMOVAL @ CATALINA SUB 0.42 days Tue 9/24/24 Tue 9/24/24 168 0%WIRE PULL 13/3 - 5/4 0.94 days Mon 9/23/24 Tue 9/24/24 169 0%DEAD END/CLIP WIRE/JUMPERS 13/3 - 5/4 1.29 days Tue 9/24/24 Wed 9/25/24 170 0%WIRE PULL 5/4 - 11/4 0.94 days Thu 9/19/24 Fri 9/20/24 171 0%DEAD END/CLIP WIRE/JUMPERS 5/4 - 11/4 1.29 days Fri 9/20/24 Mon 9/23/24 172 0%WIRE PULL 11/4 - 5/5 0.94 days Wed 9/18/24 Thu 9/19/24 173 0%DEAD END/CLIP WIRE/JUMPERS 11/4 - 5/5 1.29 days Thu 9/19/24 Thu 9/19/24 174 0%WIRE PULL 5/5 - 11/5 0.94 days Mon 9/16/24 Tue 9/17/24 175 0%DEAD END/CLIP WIRE/JUMPERS 5/5 - 11/5 1.29 days Tue 9/17/24 Wed 9/18/24 176 0%WIRE PULL 11/5 - 5/6 (SNUB SITE)2.5 days Wed 9/11/24 Fri 9/13/24 177 0%DEAD END/CLIP WIRE/JUMPERS 11/5 - 5/6 1.38 days Fri 9/13/24 Mon 9/16/24 178 0%WIRE PULL 5/6 (SNUB SITE) - 5/7 3.33 days Fri 9/6/24 Tue 9/10/24 179 0%DEAD END/CLIP WIRE/JUMPERS 5/6 (SNUB SITE1.92 days Tue 9/10/24 Wed 9/11/24 180 0%WIRE PULL 5/7 - 6/8 2.5 days Wed 8/28/24 Fri 8/30/24 181 0%DEAD END/CLIP WIRE/JUMPERS 5/7 - 6/8 2.29 days Fri 8/30/24 Wed 9/4/24 182 0%WIRE PULL 6/8 - 4/9 1.56 days Mon 8/26/24 Tue 8/27/24 183 0%DEAD END/CLIP WIRE/JUMPERS 6/8 - 4/9 2.17 days Tue 8/27/24 Wed 8/28/24 184 0%WIRE PULL 4/9 - 7A/9 0.63 days Thu 8/22/24 Fri 8/23/24 185 0%DEAD END/CLIP WIRE/JUMPERS 4/9 - 7A/9 0.92 days Fri 8/23/24 Fri 8/23/24 186 0%WIRE PULL 7A/9 - 9/9 0.63 days Wed 8/21/24 Wed 8/21/24 187 0%DEAD END/CLIP WIRE/JUMPERS 7A/9 - 9/9 1.33 days Wed 8/21/24 Thu 8/22/24 188 0%WIRE PULL 9/9 - 5/10 1.56 days Fri 8/16/24 Tue 8/20/24 189 0%DEAD END/CLIP WIRE/JUMPERS 9/9 - 5/10 1.79 days Tue 8/20/24 Wed 8/21/24 190 0%WIRE PULL 5/10 - 10/10 1.04 days Thu 8/15/24 Fri 8/16/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 5 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 191 0%DEAD END/CLIP WIRE/JUMPERS 5/10 - 10/10 1.17 days Fri 8/16/24 Fri 8/16/24 192 0%WIRE PULL 10/10 - 4/11 0.83 days Tue 8/13/24 Wed 8/14/24 193 0%DEAD END/CLIP WIRE/JUMPERS 10/10 - 4/11 1.33 days Wed 8/14/24 Thu 8/15/24 194 0%WIRE PULL 4/11 - PONDEROSA SUB 0.83 days Mon 8/12/24 Mon 8/12/24 195 0%DEAD END/CLIP WIRE/JUMPERS 4/11 - PONDER1.29 days Mon 8/12/24 Tue 8/13/24 196 0%HOUSTON LAKE ‐ PONDEROSA #2 115KV 5.37 days Fri 10/11/24 Fri 10/18/24 197 0%1 0.83 days Fri 10/11/24 Tue 10/15/24 198 0%2 0.42 days Tue 10/15/24Tue 10/15/24 199 0%3 0.83 days Tue 10/15/24Wed 10/16/2 200 0%4 0 days Wed 10/16/2 Wed 10/16/2 201 0%WIRE PULLS & SAG 1.04 days Wed 10/16/2 Wed 10/16/2 202 0%DEAD END/CLIP WIRE/JUMPERS 2.25 days Wed 10/16/2 Fri 10/18/24 203 88%Crux Houston Lake ‐ Ponderosa 54.25 days Mon 7/8/24 Fri 8/30/24 204 100%Mobilization 1.25 days Mon 7/8/24 Tue 7/9/24 206 100%STR. 6/11 (5'‐6" x 18‐ft) DP 3.75 days Tue 7/9/24 Thu 7/11/24 210 100%STR. 5/11 (3.0' x 11‐ft) DE 1.56 days Tue 7/9/24 Wed 7/10/24 213 100%STR. 4/11 (6'‐0" x 20‐ft) DP 2.75 days Thu 7/11/24 Mon 7/15/24 217 100%STR. 3/11 (3.0' x 11‐ft) DE 0.56 days Wed 7/10/24Wed 7/10/24 220 100%STR. 2/11 (3.0' x 9.6") DE 0.53 days Wed 7/10/24Thu 7/11/24 223 100%STR. 1/11 (5'‐0" x 18‐ft) DP 2.88 days Mon 7/15/24Wed 7/17/24 227 100%STR. 8A/9 (L) ‐ (4'‐6" x 14‐ft) DP / 3 Pole Str.2.88 days Wed 7/17/24Fri 7/19/24 231 100%STR. 8A/9 (C) ‐ (4'‐6" x 14‐ft) DP 2.75 days Mon 7/22/24Tue 7/23/24 235 100%STR. 8A/9 (R) ‐ (4'‐6" x 14‐ft) DP 2.75 days Wed 7/24/24Thu 7/25/24 239 100%STR. 7A/9 (L) ‐ (4'‐6" x 14‐ft) DP / 3 Pole Str.2.88 days Fri 7/26/24 Tue 7/30/24 243 100%STR. 7A/9 (C) ‐ (4'‐6" x 14‐ft) DP 2.75 days Tue 7/30/24 Thu 8/1/24 247 100%STR. 7A/9 (R) ‐ (4'‐6" x 14‐ft) DP 2.75 days Thu 8/1/24 Mon 8/5/24 251 100%STR. 6A/9 (3.0' x 10'‐6") DE 0.92 days Thu 7/11/24 Thu 7/11/24 254 100%STR. 5A/9 (3.0' x 11‐ft) DE 0.56 days Thu 7/11/24 Fri 7/12/24 257 100%STR. 12/8 (3.5' x 16‐ft) DE 0.88 days Fri 7/12/24 Fri 7/12/24 260 100%STR. 11/8 (3.5' x 16‐ft) DE 0.75 days Fri 7/12/24 Mon 7/15/24 263 0%STR. 10/7 (4.0' x 17‐ft) DE 1.75 days Mon 8/26/24Tue 8/27/24 264 0%Set‐Up 2 hrs Mon 8/26/24 Mon 8/26/24 265 0%Drill 12 hrs Mon 8/26/24 Tue 8/27/24 266 0%STR. 9/7 (4.0' x 18‐ft) DE 0.94 days Tue 8/27/24 Wed 8/28/24 267 0%Set‐Up 2 hrs Tue 8/27/24 Tue 8/27/24 268 0%Drill 5.5 hrs Tue 8/27/24 Wed 8/28/24 269 100%STR. 8/7 (4.0' x 18‐ft) DE 1.31 days Tue 7/16/24 Wed 7/17/24 272 100%STR. 7/7 (4.0' x 17‐ft) DE 0.88 days Wed 7/17/24Thu 7/18/24 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 6 Project: ILB_Houston Project Sc Date: Tue 8/27/24 ID % Complete Task Name Duration Start Finish 275 100%STR. 6/7 (3.5' x16‐ft) DE 0.75 days Thu 7/18/24 Thu 7/18/24 278 100%STR. 4/7 (3.5' x 16‐ft) DE 0.75 days Thu 7/18/24 Fri 7/19/24 281 100%STR. 10/6 (3.5' x 16‐ft) DE 0.75 days Fri 7/19/24 Fri 7/19/24 284 100%STR. 8/6 (4.0' x 16.5‐ft) DE 0.75 days Fri 7/19/24 Mon 7/22/24 287 100%STR. 7/6 (4.0' x 17‐ft) DE 0.88 days Mon 7/22/24Tue 7/23/24 290 100%STR. 6/6 (4.0' x 17.5‐ft) DE 0.88 days Tue 7/23/24 Tue 7/23/24 293 100%STR. 5/6 (4.0' x 18‐ft) DE 0.94 days Tue 7/23/24 Wed 7/24/24 296 100%STR. 4/6 (4.5' x 20‐ft) DE 1 day Wed 7/24/24Thu 7/25/24 299 100%STR. 3/6 (4.5' x 20‐ft) DE 1 day Thu 7/25/24 Thu 7/25/24 302 100%STR. 2/6 (4.0' x 18‐ft) DE 0.94 days Thu 7/25/24 Fri 7/26/24 305 100%STR. 9/5 (3.5' x 16‐ft) DE 0.88 days Fri 7/26/24 Mon 7/29/24 308 100%STR. 12x5/3 (6'‐6" x 18‐ft) DP 31.13 days Tue 7/9/24 Thu 8/8/24 313 100%STR. 12x4/3 (7'‐0" x 20‐ft) DP 33.38 days Wed 7/10/24Tue 8/13/24 318 100%STR. 12x3/3 (3.5' x 13‐ft) DE 17.7 days Wed 7/10/24Mon 7/29/24 322 100%STR. 4/1 (3.5' x 14‐ft) DE 18.63 days Thu 7/11/24 Wed 7/31/24 326 83%STR. 3/1 (7'‐0" x 20‐ft) DP 43.13 days Fri 7/12/24 Mon 8/26/24 327 100%Perf 1.88 days Fri 7/12/24 Mon 7/15/24 328 100%Set‐Up 1.88 days Tue 8/13/24 Thu 8/15/24 329 100%Drill 2.5 days Thu 8/15/24 Fri 8/16/24 330 0%Concrete 1.25 days Mon 8/26/24 Mon 8/26/24 331 59%STR. 2/1 (3.5 x 15‐ft) DE 16.32 days Mon 7/15/24Wed 7/31/24 332 100%Perf 2 hrs Mon 7/15/24 Tue 7/16/24 333 100%Set‐Up 3 hrs Wed 7/31/24 Wed 7/31/24 334 0%Drill 3.5 hrs Wed 7/31/24 Wed 7/31/24 335 8%STR. 1/1 (6'‐6" x 18‐ft) DP 45.13 days Tue 7/16/24 Thu 8/29/24 336 100%Perf 3 hrs Tue 7/16/24 Tue 7/16/24 337 0%Set‐Up 3 hrs Mon 8/26/24 Tue 8/27/24 338 0%Drill 2.5 days Tue 8/27/24 Wed 8/28/24 339 0%Concrete 1.25 days Thu 8/29/24 Thu 8/29/24 340 0%Mob to SubStation for Foundations 1 day Thu 8/29/24 Fri 8/30/24 341 0%Cleanup & Mob 1 day Thu 8/29/24 Fri 8/30/24 Perf Crew 1 Perf Crew 1 Drill Crew Drill Crew Perf Crew 1 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 July 2024 August 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 7 Project: ILB_Houston Project Sc Date: Tue 8/27/24 Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Wire Crew Clipping Crew Wire Crew Clipping Crew 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 8 Project: ILB_Houston Project Sc Date: Tue 8/27/24 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 9 Project: ILB_Houston Project Sc Date: Tue 8/27/24 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 10 Project: ILB_Houston Project Sc Date: Tue 8/27/24 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 11 Project: ILB_Houston Project Sc Date: Tue 8/27/24 Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew Wire Crew 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 12 Project: ILB_Houston Project Sc Date: Tue 8/27/24 Clipping Crew Wire Crew Clipping Crew Wire Crew Clipping Crew 10/16 Drill Crew 2 Drill Crew 2 Drill Crew 2 Drill Crew 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 13 Project: ILB_Houston Project Sc Date: Tue 8/27/24 Drill Crew 1 Drill Crew 1 Concrete Crew 1 w 2 w 2 Drill Crew 1 Drill Crew 1 Concrete Crew 1 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 4 September 2024 October 2024 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 14 Project: ILB_Houston Project Sc Date: Tue 8/27/24