HomeMy WebLinkAbout20240830PAC to Staff 207-2 Attachment OTP Q0196 Nephi Schedule - 8.23.24.pdfID Task
Mode
Task Name Start Finish Late Start Late Finish Free Slack Total Slack
1 Nortonville Substation Fri 08/09/24Mon 03/24/25Fri 08/09/24Mon 03/24/25 0 days 0 days
2 Pre Construction Activities Fri 08/09/24 Fri 09/06/24Fri 08/09/24Fri 09/06/24 0 days 0 days
3 Bid Submittal Fri 08/09/24 Fri 08/09/24Fri 08/09/24Fri 08/09/24 0 days 0 days
4 Receive Notice of Award and
PO
Fri 08/16/24 Fri 08/16/24 Fri
08/16/24
Fri
08/16/24
0 days 0 days
5 Procure Contractor
Furninshed Materials
Mon
08/19/24
Fri 08/30/24 Mon
08/19/24
Tue
09/03/24
0 days 1 day
6 Pre Construction Meeting Tue 09/03/24Tue 09/03/24Tue 09/03/24Tue 09/03/24 0 days 0 days
7 Approval of Submittals Wed 09/04/24 Fri 09/06/24Wed 09/04/24Fri 09/06/24 0 days 0 days
8 Construction Activities Tue 09/03/24Mon 03/24/25Wed 09/04/24Mon 03/24/25 0 days 0 days
9 Mobilize Civil Crews Tue 09/03/24Tue 09/03/24Wed 09/04/24Wed 09/04/24 0 days 1 day
10 Clear and Grub Wed 09/04/24Thu 09/05/24Thu 09/05/24Fri 09/06/24 1 day 1 day
11 Complete Subgrade Mon 09/09/24 Fri 09/13/24Mon 09/09/24Fri 09/13/24 0 days 0 days
12 Install Perimeter Fence and
Gates
Mon
09/16/24
Tue
09/24/24
Mon
09/16/24
Tue
09/24/24
0 days 0 days
13 Install Foundations Mon 09/16/24 Fri 10/11/24Mon 09/16/24Fri 10/11/24 0 days 0 days
14 Mobilize Substation Crew Wed 09/25/24Wed 09/25/24Wed 09/25/24Wed 09/25/24 0 days 0 days
15 Install Below Grade Conduit
and Grounding
Thu
09/26/24
Fri 10/11/24 Thu
09/26/24
Fri
10/11/24
0 days 0 days
16 Set Control Building Mon 10/14/24Mon 10/14/24Mon 10/14/24Mon 10/14/24 0 days 0 days
17 Install Substation Steel Mon 10/14/24 Fri 11/01/24Mon 11/11/24Tue 12/03/24 0 days 20 days
18 Transmission Outage Mon 10/14/24Thu 10/31/24Mon 10/14/24Thu 10/31/24 0 days 0 days
19 Install Transmission DE
Structures
Mon
10/14/24
Fri 10/18/24 Mon
10/14/24
Fri
10/18/24
0 days 0 days
20 Remove Static Wire and
String OPGW
Mon
10/21/24
Mon
10/28/24
Mon
10/21/24
Mon
10/28/24
0 days 0 days
21 String OH Conductor into
Sub DE
Tue
10/29/24
Thu
10/31/24
Tue
10/29/24
Thu
10/31/24
0 days 0 days
22 Install Rigid Bus Mon 11/04/24Wed 11/13/24Wed 12/04/24Fri 12/13/24 0 days 20 days
23 Install Electrical Equipment Thu 11/14/24Tue 12/03/24Mon 12/16/24Wed 01/08/25 0 days 20 days
24 Install String Bus Wed 12/04/24Thu 12/12/24Thu 01/09/25Fri 01/17/25 0 days 20 days
25 Install Above Grade Conduit
and Grounding
Fri 12/13/24 Thu
12/19/24
Mon
01/20/25
Fri
01/24/25
0 days 20 days
26 Install Panels and Batteries in
Control House
Fri 12/20/24 Fri 01/03/25 Mon
01/27/25
Fri
01/31/25
0 days 20 days
27 Install and Terminate Power
and Control Cables
Mon
01/06/25
Fri 01/24/25 Mon
02/03/25
Fri
02/21/25
20 days 20 days
28 Install Circuit Breakers Mon 02/24/25Wed 02/26/25Mon 02/24/25Wed 02/26/25 0 days 0 days
29 Substation Testing Thu 02/27/25Wed 03/12/25Thu 02/27/25Wed 03/12/25 0 days 0 days
30 Complete Yard and Finish
Rock
Thu
03/13/25
Fri 03/14/25 Thu
03/13/25
Fri
03/14/25
0 days 0 days
31 Substation Walk Through Mon 03/17/25Mon 03/17/25Mon 03/17/25Mon 03/17/25 0 days 0 days
32 Complete Punch List Items Tue 03/18/25Thu 03/20/25Tue 03/18/25Thu 03/20/25 0 days 0 days
33 Substation Energization Fri 03/21/25 Fri 03/21/25Fri 03/21/25Fri 03/21/25 0 days 0 days
34 De-Mobilization Mon 03/24/25Mon 03/24/25Mon 03/24/25Mon 03/24/25 0 days 0 days
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Aug 11, '24 Aug 18, '24 Aug 25, '24 Sep 01, '24 Sep 08, '24 Sep 15, '24 Sep 22, '24 Sep 29, '24 Oct 06, '24 Oct 13, '24 Oct 20, '24 Oct 27, '24 Nov 03, '24 Nov 10, '24
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: Project Schedule
Date: Fri 08/23/24
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Nov 10, '24 Nov 17, '24 Nov 24, '24 Dec 01, '24 Dec 08, '24 Dec 15, '24 Dec 22, '24 Dec 29, '24 Jan 05, '25 Jan 12, '25 Jan 19, '25 Jan 26, '25 Feb 02, '25 Feb 09, '25 Feb 16, '25 Feb 23, '25 Mar 02, '25 Mar 09, '25 Mar 16, '25 Mar 23, '25
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 2
Project: Project Schedule
Date: Fri 08/23/24