HomeMy WebLinkAbout20240829PAC to Staff 140-2 - 140 (d) iii - Baseline Schedule 20210918.pdfActivity ID Activity Name Responsible Party Start Finish Primary
Constraint
Orig
Days
Q0754 Steel SolarQ0754 Steel SolarQ0754 Steel Solar 03-17-17 A 03-30-23 2141d
Project PlanningProject PlanningProject Planning 03-17-17 A 06-14-21 A 1538d
0001 System Impact Study 03-17-17 A 0d
0003 Facilities Study (Interconnection Agreement)08-11-17 A 0d
0007 Sign Interconnection Agreement 06-04-18 A 06-28-18 A 60d
0006 Original APR 24014249 ISD = 08-18-2020 09-27-18 A 0d
0008 Customer Placed Project on Suspension 07-16-19 A 10-27-20 A 1d
0005 APR 94010015 ISD = 7-16-2023 10-01-19 A 0d
0009 Parental Guaranty Completed 09-21-20 A 0d
0011 Revised LGIA Executed 05-24-21 A 0d
0010 T&D PMO: PM Reassigned (Howcroft)06-01-21 A 0d
0012 APR 94011668 ISD = 9-16-2022 06-14-21 A 09-16-22 0d
Project MilestonesProject MilestonesProject Milestones 10-13-22 10-13-22 0d
8999.APR Commercial Operations - Approved APR # (94011668)10-13-22*10-13-22 0d
Project InitiationProject InitiationProject Initiation 11-28-18 A 05-06-21 A 30d
0065 PSRAT Approval: Transmission 11-28-18 A 0d
0050 Scoping Request & Development (108F Form)04-01-21 A 05-06-21 A 20d
0080 Project Team Kick-Off Meeting 04-14-21 A 0d
0060 PSRAT Approval: Substation 05-06-21 A 0d
Phase 1Phase 1Phase 1 08-02-17 A 10-13-22 683d
Phase 1 KPI'sPhase 1 KPI'sPhase 1 KPI's 08-30-21 A 09-16-22 260d
3818.01 CAISO Data Package Submittal 08-30-21 A 11-17-21*11-17-21 60d
1799.01 Permits Acquired 09-24-21 0d
3879.01 Full IFC Complete 01-21-22*01-21-22 0d
2215.01 Post to Jagger 01-24-22 01-25-22 2d
2265.01 Contract Award 02-25-22 0d
3890.01 CAISO Data Package Deployment 04-25-22*04-25-22 0d
6922.01 Mechanical Completion 07-22-22 0d
8889.01 Contracted Backfeed Date (Constrain to Contract Backfeed Date)09-16-22*09-16-22 0d
Permitting & LandPermitting & LandPermitting & Land 06-04-18 A 01-25-22 207d
1000.01 Permitting & Land Summary 06-04-18 A 01-25-22 207d
PermittingPermittingPermitting 06-04-18 A 01-25-22 207d
1300.01 Customer Obtains All Permits 06-04-18 A 01-25-22 207d
Property AcquisitionProperty AcquisitionProperty Acquisition 06-04-18 A 01-25-22 207d
1400.01 Customer Acquires Property 06-04-18 A 01-25-22 207d
Right of Way ServiceRight of Way ServicesRight of Way Services 06-04-18 A 01-25-22 207d
1500.01 Customer Acquires ROW 06-04-18 A 01-25-22 207d
EngineeringEngineeringEngineering 08-02-17 A 09-16-22 683d
Cost EngineeringCost EngineeringCost Engineering 08-02-17 A 04-28-21 A 40d
3002.01 Un-Scoped Estimate (+/-50%)08-02-17 A 08-11-17 A 20d
3004.01 Preliminary Scope Estimate (+/-30%)03-28-18 A 04-09-18 A 20d
3003.01 Scoped Estimate (+/- 20%)04-01-21 A 04-28-21 A 1d
Customer EngineerinCustomer Engineering DeliverablesCustomer Engineering Deliverables 05-06-21 A 09-16-22 683d
3013.01 CAS Accounts Estabished 05-06-21 A 09-16-22 683d
3011.01 Customer Contact Information 05-06-21 A 03-22-22 145d
3009.01 Customer General Plan 05-06-21 A 09-24-21 61d
3007.01 Customer One-Line 05-06-21 A 09-24-21 61d
EngineeringEngineeringEngineering 06-10-21 A 12-20-21 66d
3000.01 Engineering Summary 06-10-21 A 12-20-21 66d
Geotech & SurveyGeotech & SurveyGeotech & Survey 08-02-21 A 09-24-21 20d
3018.01 Geotech/Survey: Substation 08-02-21 A 09-24-21 20d
Engineering DesigEngineering Design & Review 1Engineering Design & Review 1 06-10-21 A 08-17-21 A 30d
3115.01 Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 1 06-10-21 A 08-06-21 A 30d
3110.01 Transmission - Design Review 1: PSRAT Scoping 06-21-21 A 07-07-21 A 30d
3170.01 Review 1: Review & Approval 08-06-21 A 08-17-21 A 1d
Engineering DesigEngineering Design & Review 2Engineering Design & Review 2 07-12-21 A 11-22-21 60d
3210.01 Transmission - Design & Review 2: PLS-CADD Model Review 07-12-21 A 09-21-21 40d
3258.01 Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 2 08-17-21 A 09-24-21*09-24-21 30d
3259.01 Review 2: Review & Approval 10-25-21 10-25-21 1d
3280.01 Draft Protection Plan 10-26-21 11-22-21 20d
Engineering DesigEngineering Design & Review 3Engineering Design & Review 3 10-26-21 12-20-21 40d
3315.01 Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 3 10-26-21 11-19-21*11-19-21 19d
3310.01 Transmission - Design & Review 3 10-26-21 11-22-21 20d
3353.01 Finalize & Approve CSP & Protection Plan 11-23-21 12-20-21 20d
3370.01 Review 3: Review & Approval 11-23-21 11-23-21 1d
Issued for ConstructiIssued for Construction PackagesIssued for Construction Packages 11-23-21 02-04-22 53d
3425.01 Transmission - IFC Package 11-23-21 0d
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2017 2018 2019 2020 2021 2022 2023 2024
System Impact Study
Facilities Study (Interconnection Agreement)
Sign Interconnection Agreement
Original APR 24014249 ISD = 08-18-2020
Customer Placed Project on Suspension
APR 94010015 ISD = 7-16-2023
Parental Guaranty Completed
Revised LGIA Executed
T&D PMO: PM Reassigned (Howcroft)
APR 94011668 ISD = 9-16-2022
Commercial Operations - Approved APR # (94011668)
PSRAT Approval: Transmission
Scoping Request & Development (108F Form)
Project Team Kick-Off Meeting
PSRAT Approval: Substation
CAISO Data Package Submittal
Permits Acquired
Full IFC Complete
Post to Jagger
Contract Award
CAISO Data Package Deployment
Mechanical Completion
Contracted Backfeed Date (Constrain to Contract Backfeed Date)
Permitting & Land Summary
Customer Obtains All Permits
Customer Acquires Property
Customer Acquires ROW
Un-Scoped Estimate (+/-50%)
Preliminary Scope Estimate (+/-30%)
Scoped Estimate (+/- 20%)
CAS Accounts Estabished
Customer Contact Information
Customer General Plan
Customer One-Line
Engineering Summary
Geotech/Survey: Substation
Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 1
Transmission - Design Review 1: PSRAT Scoping
Review 1: Review & Approval
Transmission - Design & Review 2: PLS-CADD Model Review
Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 2
Review 2: Review & Approval
Draft Protection Plan
Civil/Sub/P&C/Metering/Comm/SCADA - Design & Review 3
Transmission - Design & Review 3
Finalize & Approve CSP & Protection Plan
Review 3: Review & Approval
Transmission - IFC Package
Q0754 Steel Solar Project Manager
Jeff Howcroft
Print Date 09-23-21 / 20:36
Page 1 of 4
Schedule Prepared by: Jeff Howcroft
Data Date 09-18-21
Activity ID Activity Name Responsible Party Start Finish Primary
Constraint
Orig
Days
3430.01 Civil/Sub/P&C/Metering/Comm/SCADA - IFC Package 11-24-21 01-21-22*01-21-22 43d
3435.01 Full IFC issued to Document Control 01-21-22*01-21-22 0d
3440.01 Document Control Check in & Distribute IFC Package 01-24-22 02-04-22 10d
Post Design EngineerinPost Design EngineeringPost Design Engineering 11-24-21 07-01-22 158d
3900.01 Post Design Engineering Summary 11-24-21 07-01-22 158d
SPCCSPCCSPCC 11-24-21 11-24-21 0d
3975.01 Develop SPCC (Greenfield)11-24-21 11-24-21 0d
P & C EngineeringP & C EngineeringP & C Engineering 05-20-22 07-01-22 31d
3902.01 Relay Settings Development 05-20-22 06-30-22 30d
3904.01 Issue Relay Settings to Area Sub Operations Via P8 07-01-22 07-01-22 1d
MeteringMeteringMetering 01-24-22 02-08-22 12d
3912.01 Meter Output Settings for SCADA and Alternate Control Path to SCADA, Comm o 01-24-22 02-08-22 12d
IT SCADAIT SCADAIT SCADA 02-09-22 02-22-22 10d
3922.01 SCADA Monarch Database DET Entry 02-09-22 02-22-22 10d
Dispatch - T&DDispatch - T&DDispatch - T&D 03-09-22 03-22-22 10d
3932.01 Dispatch Display Build 03-09-22 03-22-22 10d
IT - Transmission SysIT - Transmission SystemsIT - Transmission Systems 02-23-22 03-23-22 21d
3945.01 SCADA Monarch Database Build 02-23-22 03-22-22 20d
3946.01 System Generated Points Created 03-02-22 03-22-22 15d
3948.01 Link Data Points to Dispatch Display 03-23-22 03-23-22 1d
Grid Operations - TF Grid Operations - TF (Transmission)Grid Operations - TF (Transmission)02-23-22 04-05-22 30d
3954.01 System Model Updated 02-23-22 04-05-22 30d
Commissioning NoteCommissioning NotebookCommissioning Notebook 12-27-21 01-21-22 20d
3962.01 Commissioning Engineer to Create & Issue Notebook Prior to Bid Packages 12-27-21 01-21-22 20d
ProcurementProcurementProcurement 05-26-21 A 05-20-22 225d
4000.01 Procurement Summary 05-26-21 A 05-20-22 225d
Procure ConstructionProcure Construction ServicesProcure Construction Services 01-04-22 02-25-22 39d
4008.01 Compile Engineering Bid Package Exhibits 01-04-22 01-10-22 5d
4005.01 Compile Bid Package Documents 01-05-22 01-18-22 10d
4011.01 Bid Package Document Page Turn / Pre-Construction Project Plan Review 01-11-22 01-17-22 5d
4006.01 Review CSP for Durations 01-17-22 01-17-22 1d
4012.01 Bid Package Complete 01-21-22 0d
4025.01 Vendors Prepare Bids 01-26-22 02-15-22 15d
4020.01 Pre-Bid Meeting 02-02-22 02-02-22 1d
4030.01 Bids Due 02-15-22 0d
4032.01 Pricing Review by Estimating 02-16-22 02-17-22 2d
4040.01 Commercial Bid Evaluation (Schedule, EAP, CSP, Drill Plan)02-16-22 02-17-22 2d
4046.01 Final Bid Values Reviewed & Approved by DA (Over 50k)02-16-22 02-17-22 2d
4050.01 Contract Negotiations 02-18-22 02-21-22 2d
4055.01 Requisition Created 02-22-22 02-22-22 1d
4060.01 Release PO / Notice to Proceed 02-23-22 02-25-22 3d
Procure MaterialProcure MaterialProcure Material 05-26-21 A 05-20-22 225d
Major Equipment -Major Equipment - TransmissionMajor Equipment - Transmission 09-22-21 03-01-22 115d
Transmission STransmission Steel StructuresTransmission Steel Structures 09-22-21 03-01-22 115d
4201.01 Trans Steel Structures - Requisition 09-22-21 10-05-21 10d
4206.01 Trans Steel Structures - Release PO 10-06-21 10-12-21 5d
4207.01 Trans Steel Structures - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-13-21 10-26-21 10d
4208.01 Trans Steel Structures - Fabricate & Receive 10-13-21 03-01-22 100d
Major Equipment -Major Equipment - MeteringMajor Equipment - Metering 05-26-21 A 02-18-22 225d
Metering CT/VTMetering CT/VT 138kVMetering CT/VT 138kV 05-26-21 A 01-31-22 225d
4321.01 Metering CT/VT - Spec/Requisition 15049576 05-26-21 A 06-02-21 A 10d
4326.01 Metering CT/VT - Release PO 4501033160 (Koncar)06-02-21 A 06-03-21 A 5d
4328.01 Metering CT/VT - Fabricate & Receive 06-04-21 A 01-31-22*01-31-22 215d
Junction Box foJunction Box for CT's & VT'sJunction Box for CT's & VT's 09-27-21 02-18-22 105d
4311.01 Metering Junction Box for CT's & VT's - Spec/Requisition 09-27-21 10-08-21 10d
4316.01 Metering Junction Box for CT's & VT's - Release PO 10-11-21 10-15-21 5d
4318.01 Metering Junction Box for CT's & VT's - Fabricate & Receive 10-18-21 02-18-22 90d
Major Equipment -Major Equipment - CommunicationsMajor Equipment - Communications 09-06-21 A 03-18-22 105d
SCADA RTUSCADA RTUSCADA RTU 10-25-21 03-18-22 105d
4501.01 SCADA RTU - Spec/Requisition 10-25-21 11-05-21 10d
4506.01 SCADA RTU - Release PO 11-08-21 11-12-21 5d
4508.01 SCADA RTU - Fabricate & Receive 11-15-21 03-18-22 90d
CommunicationCommunication Cable (OPGW/Fiber)Communication Cable (OPGW/Fiber)09-06-21 A 01-21-22 70d
4521.01 Comm Cable (OPGW/Fiber) - Spec/Requisition 15138032 09-06-21 A 09-13-21 A 10d
4526.01 Comm Cable (OPGW/Fiber) - Release PO 4501045809 (AFL)09-13-21 A 09-16-21 A 5d
4528.01 Comm Cable (OPGW/Fiber) - Fabricate & Receive 09-17-21 A 01-21-22*01-21-22 60d
Major Equipment -Major Equipment - CivilMajor Equipment - Civil 09-20-21 03-25-22 135d
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2017 2018 2019 2020 2021 2022 2023 2024
Civil/Sub/P&C/Metering/Comm/SCADA - IFC Package
Full IFC issued to Document Control
Document Control Check in & Distribute IFC Package
Post Design Engineering Summary
Develop SPCC (Greenfield)
Relay Settings Development
Issue Relay Settings to Area Sub Operations Via P8
Meter Output Settings for SCADA and Alternate Control Path to SCADA, Comm or P&C Engr, as required
SCADA Monarch Database DET Entry
Dispatch Display Build
SCADA Monarch Database Build
System Generated Points Created
Link Data Points to Dispatch Display
System Model Updated
Commissioning Engineer to Create & Issue Notebook Prior to Bid Packages
Procurement Summary
Compile Engineering Bid Package Exhibits
Compile Bid Package Documents
Bid Package Document Page Turn / Pre-Construction Project Plan Review
Review CSP for Durations
Bid Package Complete
Vendors Prepare Bids
Pre-Bid Meeting
Bids Due
Pricing Review by Estimating
Commercial Bid Evaluation (Schedule, EAP, CSP, Drill Plan)
Final Bid Values Reviewed & Approved by DA (Over 50k)
Contract Negotiations
Requisition Created
Release PO / Notice to Proceed
Trans Steel Structures - Requisition
Trans Steel Structures - Release PO
Trans Steel Structures - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Trans Steel Structures - Fabricate & Receive
Metering CT/VT - Spec/Requisition 15049576
Metering CT/VT - Release PO 4501033160 (Koncar)
Metering CT/VT - Fabricate & Receive
Metering Junction Box for CT's & VT's - Spec/Requisition
Metering Junction Box for CT's & VT's - Release PO
Metering Junction Box for CT's & VT's - Fabricate & Receive
SCADA RTU - Spec/Requisition
SCADA RTU - Release PO
SCADA RTU - Fabricate & Receive
Comm Cable (OPGW/Fiber) - Spec/Requisition 15138032
Comm Cable (OPGW/Fiber) - Release PO 4501045809 (AFL)
Comm Cable (OPGW/Fiber) - Fabricate & Receive
Q0754 Steel Solar Project Manager
Jeff Howcroft
Print Date 09-23-21 / 20:36
Page 2 of 4
Schedule Prepared by: Jeff Howcroft
Data Date 09-18-21
Activity ID Activity Name Responsible Party Start Finish Primary
Constraint
Orig
Days
Civil Structural Civil Structural SteelCivil Structural Steel 09-20-21 03-25-22 135d
4621.01 Civil Structural Steel - Requisition 09-20-21 10-01-21 10d
4626.01 Civil Structural Steel - Release PO 10-04-21 10-08-21 5d
4627.01 Civil Structural Steel - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-11-21 10-22-21 10d
4628.01 Civil Structural Steel - Vendor Design - Fabricate & Receive 10-11-21 03-25-22 120d
Civil Cable TrenCivil Cable Trench & LidsCivil Cable Trench & Lids 09-20-21 01-07-22 80d
4631.01 Civil Cable Trench & Lids - Requisition 09-20-21 10-01-21 10d
4636.01 Civil Cable Trench & Lids - Release PO 10-04-21 10-08-21 5d
4637.01 Civil Cable Trench & Lids - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-11-21 10-22-21 10d
4638.01 Civil Cable Trench & Lids - Fabricate & Receive 10-11-21 01-07-22 65d
Major Equipment -Major Equipment - SubstationMajor Equipment - Substation 06-03-21 A 05-20-22 175d
Substation CircSubstation Circuit Breaker 138kV 2000A, 40 kASubstation Circuit Breaker 138kV 2000A, 40 kA 09-20-21 05-20-22 175d
4711.01 Sub Circuit Breaker - Requisition 09-20-21 10-01-21 10d
4716.01 Sub Circuit Breaker - Release PO 10-04-21 10-08-21 5d
4718.01 Sub Circuit Breaker - Fabricate & Receive 10-11-21 05-20-22 160d
4717.01 Sub Circuit Breaker - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-11-21 10-22-21 10d
Substation RelaSubstation Relay PanelsSubstation Relay Panels 10-11-21 03-18-22 115d
4731.01 Relay Panels - Requisition 10-11-21 10-22-21 10d
4736.01 Relay Panels - Release PO 10-25-21 10-29-21 5d
4738.01 Relay Panels - Fabricate & Receive 11-01-21 03-18-22 100d
Substation Air BSubstation Air Break Switch 138kV 2000A Vertical BreakSubstation Air Break Switch 138kV 2000A Vertical Break 09-20-21 02-25-22 115d
4721.01 Sub Air Break Switch - Requisition 09-20-21 10-01-21 10d
4726.01 Sub Air Break Switch - Release PO 10-04-21 10-08-21 5d
4727.01 Sub Air Break Switch - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-11-21 10-22-21 10d
4728.01 Sub Air Break Switch - Fabricate & Receive 10-11-21 02-25-22 100d
Substation CCVSubstation CCVT 138kVSubstation CCVT 138kV 06-03-21 A 02-08-22 140d
4741.01 Sub CCVT - Requisition 15050316 06-03-21 A 06-10-21 A 10d
4746.01 Sub CCVT - Release PO 4501034502 (Koncar)06-10-21 A 06-15-21 A 5d
4747.01 Sub CCVT - Ven Eq Dwgs Rcvd/Rvwd/Appvd 06-16-21 A 08-05-21 A 10d
4748.01 Sub CCVT - Fabricate & Receive 06-21-21 A 02-08-22*02-08-22 130d
Substation ConSubstation Control Building 28' x 30'Substation Control Building 28' x 30'09-20-21 04-25-22 156d
4751.01 Sub Control Bldg - Requisition 09-20-21 09-24-21 5d
4756.01 Sub Control Bldg - Release PO 09-27-21 10-01-21 5d
4757.01 Sub Control Bldg - Ven Eq Dwgs Rcvd/Rvwd/Appvd 10-04-21 10-15-21 10d
4758.01 Sub Control Bldg - Fabricate & Receive 10-12-21 04-25-22 140d
Substation BattSubstation Battery BankSubstation Battery Bank 11-22-21 03-01-22 72d
4841.01 Sub Battery Bank - Requisition 11-22-21 12-03-21 10d
4846.01 Sub Battery Bank - Release PO 12-06-21 12-10-21 5d
4848.01 Sub Battery Bank - Fabricate & Receive 12-13-21 03-01-22 57d
Balance of MateriaBalance of MaterialBalance of Material 01-21-22 01-21-22 0d
4930.01 BOM - Metering (Ordered)01-21-22 0d
4970.01 BOM - Substation (Ordered)01-21-22 0d
4960.01 BOM - Civil (Ordered)01-21-22 0d
4950.01 BOM - Communications (Ordered)01-21-22 0d
4920.01 BOM - Transmission (RCMS order released)01-21-22 0d
ConstructionConstructionConstruction 02-28-22 10-13-22 164d
6000.01 Construction Summary 02-28-22 10-13-22 164d
6002.01 Preconstruction Meeting & CSP Review 02-28-22 02-28-22 1d
SubmittalsSubmittalsSubmittals 02-28-22 02-28-22 1d
6080.01 Concrete 02-28-22 02-28-22 1d
6075.01 Finish Rock 02-28-22 02-28-22 1d
6070.01 Base Rock 02-28-22 02-28-22 1d
6051.01 SWPPP 02-28-22 02-28-22 1d
Construction - TransmConstruction - TransmissionConstruction - Transmission 03-15-22 06-06-22 60d
6350.01 Insert Key CSP Activities - Transmission 03-15-22 06-06-22 60d
Construction - MeteriConstruction - MeteringConstruction - Metering 04-26-22 06-06-22 30d
6450.01 Insert Key CSP Activities - Metering 04-26-22 06-06-22 30d
Construction - CommConstruction - CommunicationConstruction - Communication 03-15-22 05-24-22 51d
6525.01 Insert Key CSP Activities - Communications 03-15-22 04-11-22 20d
6510.01 RTU Lab Tested 03-23-22 03-29-22 5d
6515.01 RTU Sent to Field for Installation 03-30-22 04-05-22 5d
6520.01 Install RTU 04-06-22 04-26-22 15d
6535.01 Install & Test Communication Channels 04-27-22 05-24-22 20d
Construction - CivilConstruction - CivilConstruction - Civil 03-01-22 07-22-22 104d
6603.01 Contractor Mobilization 03-01-22 03-14-22 10d
6605.01 Construction - Civil Site Prep 03-15-22 03-28-22 10d
Civil Below GradeCivil Below GradeCivil Below Grade 03-29-22 04-25-22 20d
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2017 2018 2019 2020 2021 2022 2023 2024
Civil Structural Steel - Requisition
Civil Structural Steel - Release PO
Civil Structural Steel - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Civil Structural Steel - Vendor Design - Fabricate & Receive
Civil Cable Trench & Lids - Requisition
Civil Cable Trench & Lids - Release PO
Civil Cable Trench & Lids - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Civil Cable Trench & Lids - Fabricate & Receive
Sub Circuit Breaker - Requisition
Sub Circuit Breaker - Release PO
Sub Circuit Breaker - Fabricate & Receive
Sub Circuit Breaker - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Relay Panels - Requisition
Relay Panels - Release PO
Relay Panels - Fabricate & Receive
Sub Air Break Switch - Requisition
Sub Air Break Switch - Release PO
Sub Air Break Switch - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Sub Air Break Switch - Fabricate & Receive
Sub CCVT - Requisition 15050316
Sub CCVT - Release PO 4501034502 (Koncar)
Sub CCVT - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Sub CCVT - Fabricate & Receive
Sub Control Bldg - Requisition
Sub Control Bldg - Release PO
Sub Control Bldg - Ven Eq Dwgs Rcvd/Rvwd/Appvd
Sub Control Bldg - Fabricate & Receive
Sub Battery Bank - Requisition
Sub Battery Bank - Release PO
Sub Battery Bank - Fabricate & Receive
BOM - Metering (Ordered)
BOM - Substation (Ordered)
BOM - Civil (Ordered)
BOM - Communications (Ordered)
BOM - Transmission (RCMS order released)
Construction Summary
Preconstruction Meeting & CSP Review
Concrete
Finish Rock
Base Rock
SWPPP
Insert Key CSP Activities - Transmission
Insert Key CSP Activities - Metering
Insert Key CSP Activities - Communications
RTU Lab Tested
RTU Sent to Field for Installation
Install RTU
Install & Test Communication Channels
Contractor Mobilization
Construction - Civil Site Prep
Q0754 Steel Solar Project Manager
Jeff Howcroft
Print Date 09-23-21 / 20:36
Page 3 of 4
Schedule Prepared by: Jeff Howcroft
Data Date 09-18-21
Activity ID Activity Name Responsible Party Start Finish Primary
Constraint
Orig
Days
6610.01 Insert Key CSP Activities - Civil Below Grade 03-29-22 04-25-22 20d
Civil Above GradeCivil Above GradeCivil Above Grade 04-12-22 07-22-22 74d
6625.01 Insert Key CSP Activities - Structural 04-12-22 05-23-22 30d
6620.01 Insert Key CSP Activities - Civil Above Grade 06-13-22 07-22-22 30d
Construction - SubstaConstruction - SubstationConstruction - Substation 03-29-22 07-22-22 84d
6707.01 Construction - Ground Grid Testing & Review 03-29-22 03-31-22 3d
6725.01 Insert Key CSP Activities - Substation 05-23-22 07-08-22 35d
6729.01 Install Relays & Panels 07-11-22 07-22-22 10d
COMPASS Requests COMPASS Requests & OutagesCOMPASS Requests & Outages 02-28-22 07-08-22 95d
Pre-EnergizationPre-EnergizationPre-Energization 02-28-22 07-08-22 95d
6813.01 Prepare & Submit Construction COMPASS Request (NOTIFICATION Requiremen 02-28-22 03-02-22 3d
6815.01 ***Insert Construction/Energization Outages Here***(See Notebook)03-03-22 07-08-22 92d
Testing & CommissioTesting & Commissioning / Project Start-UpTesting & Commissioning / Project Start-Up 07-25-22 09-09-22 35d
6903.01 Schedule Techs (See Notebook for Instructions)07-25-22 08-05-22 10d
6941.01 Construction Landscaping 07-25-22 09-02-22 30d
6915.01 Apparatus Testing & Startup 08-08-22 08-19-22 10d
6905.01 Final Point to Point Test & SCADA System Check Out 08-08-22 08-12-22 5d
6917.01 Relay Testing & Commissioning 08-08-22 09-02-22 20d
6910.01 Comm System Test & Startup 08-08-22 08-12-22 5d
6912.01 Metering Test & Startup 08-08-22 08-12-22 5d
6907.01 Finalize Dispatch Display 08-15-22 08-16-22 2d
6925.01 Test & Startup Complete 09-02-22 0d
6930.01 Final Walk Throughs / Inspections 09-05-22 09-05-22 1d
6940.01 Verify Commissioning Notebook Complete - PM Ready to Energize 09-05-22 09-09-22 5d
BackfeedBackfeedBackfeed 07-25-22 09-16-22 40d
6852.01 Notify Dispatch of Target Backfeed Date 07-25-22 07-25-22 1d
6850.01 Arrange Recurring Pre-Backfeed Meetings 07-25-22 07-25-22 1d
6854.01 Customer Requests Backfeed 08-09-22 08-15-22 5d
6856.01 Grid Ops Approves Backfeed 08-16-22 08-29-22 10d
6858.01 Transmission Services Authorizes Backfeed 08-30-22 09-16-22*09-16-22 14d
Initial SyncInitial SyncInitial Sync 09-15-22 09-22-22 6d
7002.01 Customer Requests Initial Sync 09-15-22 0d
7004.01 Grid Ops Approves Initial Sync 09-16-22 09-19-22 2d
7006.01 Transmission Services Authorizes Initial Sync 09-20-22 09-22-22*09-22-22 3d
Commercial OperatioCommercial OperationsCommercial Operations 09-23-22 10-13-22 15d
7102.01 Customer Requests Commercial Operations 09-23-22 09-26-22 2d
7104.01 Grid Ops Approves Commercial Operations 09-27-22 10-03-22 5d
7106.01 Transmission Services Authorizes Commercial Operations 10-04-22 10-13-22*10-13-22 8d
Close-OutClose-OutClose-Out 07-25-22 03-30-23 179d
Post EnergizationPost EnergizationPost Energization 10-14-22 11-10-22 20d
8530 Reclamation 10-14-22 11-10-22 20d
8510 Infrared Testing 10-14-22 10-14-22 1d
Close Out ActivitiesClose Out ActivitiesClose Out Activities 07-25-22 03-30-23 179d
9050 Completed Transmission: Redlines Submitted to Gatekeeper 07-25-22 08-05-22 10d
9030 Completed Substation: Redlines Submitted to Gatekeeper 07-25-22 08-05-22 10d
9060 Completed Communications / SCADA: Redlines Submitted to Gatekeeper 10-14-22 10-27-22 10d
9040 Completed Relay / P&C: Redlines Submitted to Gatekeeper 10-14-22 10-27-22 10d
9020 Completed Metering: Redlines Recv'd from Field 10-14-22 10-27-22 10d
9080 Final Billing to Customer 01-05-23 0d
9990 Project Close Out / Checklist Complete 01-06-23 03-30-23 60d
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
2017 2018 2019 2020 2021 2022 2023 2024
Insert Key CSP Activities - Civil Below Grade
Insert Key CSP Activities - Structural
Insert Key CSP Activities - Civil Above Grade
Construction - Ground Grid Testing & Review
Insert Key CSP Activities - Substation
Install Relays & Panels
Prepare & Submit Construction COMPASS Request (NOTIFICATION Requirements - See Notebook)
***Insert Construction/Energization Outages Here***(See Notebook)
Schedule Techs (See Notebook for Instructions)
Construction Landscaping
Apparatus Testing & Startup
Final Point to Point Test & SCADA System Check Out
Relay Testing & Commissioning
Comm System Test & Startup
Metering Test & Startup
Finalize Dispatch Display
Test & Startup Complete
Final Walk Throughs / Inspections
Verify Commissioning Notebook Complete - PM Ready to Energize
Notify Dispatch of Target Backfeed Date
Arrange Recurring Pre-Backfeed Meetings
Customer Requests Backfeed
Grid Ops Approves Backfeed
Transmission Services Authorizes Backfeed
Customer Requests Initial Sync
Grid Ops Approves Initial Sync
Transmission Services Authorizes Initial Sync
Customer Requests Commercial Operations
Grid Ops Approves Commercial Operations
Transmission Services Authorizes Commercial Operations
Reclamation
Infrared Testing
Completed Transmission: Redlines Submitted to Gatekeeper
Completed Substation: Redlines Submitted to Gatekeeper
Completed Communications / SCADA: Redlines Submitted to Gatekeeper
Completed Relay / P&C: Redlines Submitted to Gatekeeper
Completed Metering: Redlines Recv'd from Field
Final Billing to Customer
Project Close Out / Checklist Complete
Q0754 Steel Solar Project Manager
Jeff Howcroft
Print Date 09-23-21 / 20:36
Page 4 of 4
Schedule Prepared by: Jeff Howcroft
Data Date 09-18-21