HomeMy WebLinkAbout20240829PAC to Staff 137-2 - Path C Milestone Schedule 20240808.pdfMilestone Actual Date Baseline Date Site Mobilization 10/3/22 10/3/22 Ben Lomond Shoofly Start 10/10/22 10/10/22 Ben Lomond Foundation Start 10/20/22 10/20/22 Ben Lomond Below Grade Start 11/16/22 11/16/22 Ben Lomond Begin Equipment Installs 11/22/22 11/22/22 Ben Lomond Bus, Jumpers, & Shield Wire Start 4/3/23 4/3/23 Ben Lomond Cable Pulling & Terminating Start 4/17/23 4/17/23 Ben Lomond Testing & Commissioning 5/15/23 5/15/23 Ben Lomond- Populus East #1 345kV Line Reoute 5/31/23 5/31/23 Bridgerland Site Work Start 10/17/22 10/17/22 Bridgerland Foundations Start 11/16/22 11/16/22 Bridgerland Below Grade Start 3/8/23 3/8/23 Bridgerland Cable Trench 5/2/23 5/2/23 Bridgerland Equipment Install Start 4/19/23 4/19/23 Bridgerland Begin to Set Structural Steel 5/17/23 5/17/23 Bridgerland Above Grade Start 6/26/23 6/26/23 Bridgerland Bus, Jumpers, OH Wire & Shield Wire Start 7/12/23 7/12/23 Bridgerland Control Cable Pulling & Terminating Start 2/12/24 8/17/23 Bridgerland Transformer Corrections 1/8/24 Bridgerland Transformer Winding, Core & Pre-Tank Inspection 1/19/24 Bridgerland Transformer Factory Acceptance & Shipment 1/22/24 Bridgerland Transformer Set on Pad 4/4/24 Bridgerland Transformer Dress-Out 4/25/24 Bridgerland Construction Complete 5/17/24 Bridgerland Testing & Commissioning Start 5/28/24 10/24/23 Wheelon Foundation Start 3/4/24 2/22/23 Wheelon Below Grade Start 3/4/24 3/2/23 Wheelon Equipment Removal & Setting Start 3/11/24 3/6/23 Wheelon Steel and Above Grade Start 3/18/24 3/21/23 Wheelon Jumper Install 3/25/24 3/24/23 Wheelon Cable Pulling & Terminations Start 4/1/24 3/28/23 Wheelon Testing & Commissioning Start 4/29/24 4/3/23 Construction Complete 5/24/24 10/23/23 Project Complete 6/24/24 11/23/23 Ben Lomond, Bridgerland & Wheelon Construction Milestone Schedule