HomeMy WebLinkAbout20240829PAC to Staff 137-2 - Path C Milestone Schedule 20220928.pdfMilestone Date Site Mobilization Monday, October 3, 2022 Ben Lomond Shoofly Start Monday, October 10, 2022 Ben Lomond Foundation Start Thursday, October 20, 2022 Ben Lomond Below Grade Start Wednesday, November 16, 2022 Ben Lomond Begin Equipment Installs Tuesday, November 22, 2022 Ben Lomond Bus, Jumpers, & Shield Wire Start Monday, April 3, 2023 Ben Lomond Cable Pulling & Terminating Start Monday, April 17, 2023 Ben Lomond Testing & Commissioning Monday, May 15, 2023 Ben Lomond- Populus East #1 345kV Line Reoute Wednesday, May 31, 2023 Bridgerland Site Work Start Monday, October 17, 2022 Bridgerland Foundations Start Wednesday, November 16, 2022 Bridgerland Below Grade Start Wednesday, March 8, 2023 Bridgerland Cable Trench Tuesday, May 2, 2023 Bridgerland Equipment Install Start Wednesday, April 19, 2023 Bridgerland Begin to Set Structural Steel Wednesday, May 17, 2023 Bridgerland Above Grade Start Monday, June 26, 2023 Bridgerland Bus, Jumpers, OH Wire & Shield Wire Start Wednesday, July 12, 2023 Bridgerland Control Cable Pulling & Terminating Start Thursday, August 17, 2023 Bridgerland Testing & Commissioning Start Tuesday, October 24, 2023 Wheelon Foundation Start Wednesday, February 22, 2023 Wheelon Below Grade Start Thursday, March 2, 2023 Wheelon Equipment Removal & Setting Start Monday, March 6, 2023 Wheelon Steel and Above Grade Start Tuesday, March 21, 2023 Wheelon Jumper Install Friday, March 24, 2023 Wheelon Cable Pulling & Terminations Start Tuesday, March 28, 2023 Wheelon Testing & Commissioning Start Monday, April 3, 2023 Construction Complete Monday, October 23, 2023 Project Complete Thursday, November 23, 2023 Ben Lomond, Bridgerland & Wheelon Construction Milestone Schedule