HomeMy WebLinkAbout20240829PAC to Staff 137-2 - Path C Milestone Schedule 20220928.pdfMilestone Date
Site Mobilization Monday, October 3, 2022
Ben Lomond Shoofly Start Monday, October 10, 2022
Ben Lomond Foundation Start Thursday, October 20, 2022
Ben Lomond Below Grade Start Wednesday, November 16, 2022
Ben Lomond Begin Equipment Installs Tuesday, November 22, 2022
Ben Lomond Bus, Jumpers, & Shield Wire Start Monday, April 3, 2023
Ben Lomond Cable Pulling & Terminating Start Monday, April 17, 2023
Ben Lomond Testing & Commissioning Monday, May 15, 2023
Ben Lomond- Populus East #1 345kV Line Reoute Wednesday, May 31, 2023
Bridgerland Site Work Start Monday, October 17, 2022
Bridgerland Foundations Start Wednesday, November 16, 2022
Bridgerland Below Grade Start Wednesday, March 8, 2023
Bridgerland Cable Trench Tuesday, May 2, 2023
Bridgerland Equipment Install Start Wednesday, April 19, 2023
Bridgerland Begin to Set Structural Steel Wednesday, May 17, 2023
Bridgerland Above Grade Start Monday, June 26, 2023
Bridgerland Bus, Jumpers, OH Wire & Shield Wire Start Wednesday, July 12, 2023
Bridgerland Control Cable Pulling & Terminating Start Thursday, August 17, 2023
Bridgerland Testing & Commissioning Start Tuesday, October 24, 2023
Wheelon Foundation Start Wednesday, February 22, 2023
Wheelon Below Grade Start Thursday, March 2, 2023
Wheelon Equipment Removal & Setting Start Monday, March 6, 2023
Wheelon Steel and Above Grade Start Tuesday, March 21, 2023
Wheelon Jumper Install Friday, March 24, 2023
Wheelon Cable Pulling & Terminations Start Tuesday, March 28, 2023
Wheelon Testing & Commissioning Start Monday, April 3, 2023
Construction Complete Monday, October 23, 2023
Project Complete Thursday, November 23, 2023
Ben Lomond, Bridgerland & Wheelon Construction Milestone Schedule