20240829PAC to Staff 135-2 - O-T TMET-2009-C-001 Schedule 080324.pdf
Activity Name DUR, Days Start Finish Total Float Oquirrh-Terminal TLine 79.00 06-Jun-24 A 13-Sep-24 52.00 Transmission Line 79.00 06-Jun-24 A 13-Sep-24 52.00 Construction Activities 65.00 06-Jun-24 A 13-Sep-24 52.00 Survey 50.00 06-Jun-24 A 24-Aug-24 67.00 ROW Access 65.00 06-Jun-24 A 13-Sep-24 0.00 Foundations 17.00 05-Aug-24 26-Aug-24 14.50 Foundation Str 060 1.50 05-Aug-24 06-Aug-24 14.50 Foundation Str 061 1.50 05-Aug-24 06-Aug-24 14.00 Foundation Str 062 1.50 05-Aug-24 06-Aug-24 11.50 Foundation Str 058 1.50 06-Aug-24 08-Aug-24 14.00 Foundation Str 059 1.50 06-Aug-24 08-Aug-24 11.50 Foundation Str 057 1.50 08-Aug-24 09-Aug-24 14.50 Foundation Str 056 1.50 09-Aug-24 10-Aug-24 11.50 Foundation Str 054 1.50 10-Aug-24 12-Aug-24 14.50 Foundation Str 055 1.50 10-Aug-24 12-Aug-24 14.00 Foundation Str 053 1.50 10-Aug-24 12-Aug-24 11.50 Foundation Str 040 1.50 12-Aug-24 13-Aug-24 14.00 Foundation Str 048 2.00 12-Aug-24 14-Aug-24 14.50 Foundation Str 034 4.00 14-Aug-24 17-Aug-24 14.00 Foundation Str 047 2.00 14-Aug-24 15-Aug-24 11.50 Foundation Str 042 2.50 14-Aug-24 16-Aug-24 14.50 Foundation Str 041 1.50 16-Aug-24 17-Aug-24 11.50 Foundation Str 039 1.50 17-Aug-24 19-Aug-24 14.50 Foundation Str 035 1.50 17-Aug-24 19-Aug-24 11.50 Foundation Str 031 2.00 19-Aug-24 20-Aug-24 14.00 Foundation Str 033 1.50 19-Aug-24 20-Aug-24 14.50 Foundation Str 032 4.00 20-Aug-24 24-Aug-24 11.50 Foundation Str 028 4.00 22-Aug-24 26-Aug-24 14.00 Foundation Str 030 2.00 22-Aug-24 23-Aug-24 14.50 Foundation Str 027 2.00 24-Aug-24 26-Aug-24 14.50 Structure Erection 16.00 05-Aug-24 24-Aug-24 -1.50 Structure 099 0.50 05-Aug-24 05-Aug-24 -1.50 Structure 098 0.50 05-Aug-24 05-Aug-24 -1.50 Structure 097 0.50 06-Aug-24 06-Aug-24 -1.50 Structure 096 0.50 06-Aug-24 06-Aug-24 -1.50 Structure 095 0.50 08-Aug-24 08-Aug-24 -1.50 Structure 094 0.50 08-Aug-24 08-Aug-24 -1.50 Structure 093 0.50 09-Aug-24 09-Aug-24 -1.50 Structure 092 0.50 09-Aug-24 09-Aug-24 -1.50 Structure 091 0.50 10-Aug-24 10-Aug-24 -1.50 Structure 090 0.50 10-Aug-24 10-Aug-24 -1.50 Structure 089 0.50 12-Aug-24 12-Aug-24 -1.50 Structure 088 0.50 12-Aug-24 12-Aug-24 -1.50 Structure 087 0.50 13-Aug-24 13-Aug-24 -1.50 Structure 086 0.50 13-Aug-24 13-Aug-24 -1.50 Structure 085 0.50 14-Aug-24 14-Aug-24 -1.50 Structure 084 0.50 14-Aug-24 14-Aug-24 -1.50 Structure 083 0.50 15-Aug-24 15-Aug-24 -1.50 Aug Sep Oct Nov Dec 2024 Oquirrh-Terminal TLine Transmission Line Construction Activities Survey ROW Access Foundations Foundation Str 060 Foundation Str 061 Foundation Str 062 Foundation Str 058 Foundation Str 059 Foundation Str 057 Foundation Str 056 Foundation Str 054 Foundation Str 055 Foundation Str 053 Foundation Str 040 Foundation Str 048 Foundation Str 034 Foundation Str 047 Foundation Str 042 Foundation Str 041 Foundation Str 039 Foundation Str 035 Foundation Str 031 Foundation Str 033 Foundation Str 032 Foundation Str 028 Foundation Str 030 Foundation Str 027 Structure Erection Structure 099 Structure 098 Structure 097 Structure 096 Structure 095 Structure 094 Structure 093 Structure 092 Structure 091 Structure 090 Structure 089 Structure 088 Structure 087 Structure 086 Structure 085 Structure 084 Structure 083 Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary 3 Week Lookahead - By WBS SORTED BY WBS Page 1 of 2 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Structure 082 0.50 15-Aug-24 15-Aug-24 -1.50 Structure 081 0.50 16-Aug-24 16-Aug-24 -1.50 Structure 080 0.50 16-Aug-24 16-Aug-24 -1.50 Structure 079 0.50 17-Aug-24 17-Aug-24 -1.50 Structure 078 0.50 17-Aug-24 17-Aug-24 -1.50 Structure 077 0.50 19-Aug-24 19-Aug-24 -1.50 Structure 076 0.50 19-Aug-24 19-Aug-24 -1.50 Structure 075 0.50 20-Aug-24 20-Aug-24 -1.50 Structure 074 0.50 20-Aug-24 20-Aug-24 -1.50 Structure 073 0.50 22-Aug-24 22-Aug-24 -1.50 Structure 072 0.50 22-Aug-24 22-Aug-24 -1.50 Structure 071 0.50 23-Aug-24 23-Aug-24 -1.50 Structure 070 0.50 23-Aug-24 23-Aug-24 -1.50 Structure 069 0.50 24-Aug-24 24-Aug-24 -1.50 Structure 068 0.50 24-Aug-24 24-Aug-24 -1.50 Conductor Installation 10.00 17-Aug-24 30-Aug-24 0.00 Wire Pull # 11 (Strs 099 - 097)4.00 17-Aug-24 23-Aug-24 0.00 Wire Pull # 10 (Strs 096 - 091)6.00 23-Aug-24 30-Aug-24 0.00 Aug Sep Oct Nov Dec 2024 Structure 082 Structure 081 Structure 080 Structure 079 Structure 078 Structure 077 Structure 076 Structure 075 Structure 074 Structure 073 Structure 072 Structure 071 Structure 070 Structure 069 Structure 068 Conductor Installation Wire Pull # 11 (Strs 099 - 097) Wire Pull # 10 (Strs 096 - 091) Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary 3 Week Lookahead - By WBS SORTED BY WBS Page 2 of 2 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Oquirrh-Terminal TLine 107.00 06-May-24 A 20-Nov-24 0.00 Milestones 87.00 06-May-24 A 09-Nov-24 -1.50 Project Award 0.00 06-May-24 A Project Start 0.00 06-May-24 A Substation Mechanical Completion 0.00 31-Oct-24 5.50 Substantial Completion 0.00 08-Nov-24*0.00 Transmission Mechanical Completion 0.00 09-Nov-24 -1.50 Transmission Line 107.00 07-May-24 A 20-Nov-24 0.00 Construction Activities 89.00 07-May-24 A 13-Sep-24 52.00 Permitting & Notifications 24.00 07-May-24 A 04-Jun-24 A Mobilization - PM & T-Line Crews 4.00 06-Jun-24 A 10-Jun-24 A Survey 50.00 06-Jun-24 A 24-Aug-24 67.00 ROW Access 65.00 06-Jun-24 A 13-Sep-24 0.00 Foundations 66.00 08-Jul-24 A 30-Sep-24 12.00 Foundation Str 073 1.50 08-Jul-24 A 09-Jul-24 A Foundation Str 074 1.50 09-Jul-24 A 11-Jul-24 A Foundation Str 075 1.50 10-Jul-24 A 12-Jul-24 A Foundation Str 078 1.50 10-Jul-24 A 11-Jul-24 A Foundation Str 096 1.50 12-Jul-24 A 13-Jul-24 A Foundation Str 065 1.50 15-Jul-24 A 16-Jul-24 A Foundation Str 072 1.50 15-Jul-24 A 16-Jul-24 A Foundation Str 098 1.50 15-Jul-24 A 16-Jul-24 A Foundation Str 066 1.50 15-Jul-24 A 16-Jul-24 A Foundation Str 097 2.00 16-Jul-24 A 17-Jul-24 A Foundation Str 067 1.50 16-Jul-24 A 17-Jul-24 A Foundation Str 068 1.50 16-Jul-24 A 17-Jul-24 A Foundation Str 069 1.50 17-Jul-24 A 18-Jul-24 A Foundation Str 093 1.50 17-Jul-24 A 18-Jul-24 A Foundation Str 064 1.50 17-Jul-24 A 19-Jul-24 A Foundation Str 095 1.50 17-Jul-24 A 18-Jul-24 A Foundation Str 070 1.50 18-Jul-24 A 19-Jul-24 A Foundation Str 092 1.50 18-Jul-24 A 20-Jul-24 A Foundation Str 071 1.50 19-Jul-24 A 20-Jul-24 A Foundation Str 094 1.50 19-Jul-24 A 20-Jul-24 A Foundation Str 050 2.00 19-Jul-24 A 20-Jul-24 A Foundation Str 082 1.50 22-Jul-24 A 23-Jul-24 A Foundation Str 099 3.00 22-Jul-24 A 25-Jul-24 A Foundation Str 049 2.00 22-Jul-24 A 23-Jul-24 A Foundation Str 051 2.00 22-Jul-24 A 23-Jul-24 A Foundation Str 088 1.50 23-Jul-24 A 25-Jul-24 A Foundation Str 046 1.50 23-Jul-24 A 24-Jul-24 A Foundation Str 091 1.50 23-Jul-24 A 25-Jul-24 A Foundation Str 052 1.50 24-Jul-24 A 25-Jul-24 A Foundation Str 090 1.50 24-Jul-24 A 25-Jul-24 A Foundation Str 089 1.50 25-Jul-24 A 26-Jul-24 A Foundation Str 063 1.50 25-Jul-24 A 27-Jul-24 A Foundation Str 079 1.50 29-Jul-24 A 30-Jul-24 A Foundation Str 080 1.50 29-Jul-24 A 30-Jul-24 A Aug Sep Oct Nov Dec 2024 Oquirrh-Terminal TLine Milestones Substation Mechanical Completion Substantial Completion Transmission Mechanical Completion Transmission Line Construction Activities Survey ROW Access Foundations Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Update - By WBS SORTED BY WBS Page 1 of 5 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Foundation Str 036 1.50 29-Jul-24 A 30-Jul-24 A Foundation Str 076 1.50 29-Jul-24 A 30-Jul-24 A Foundation Str 084 1.50 30-Jul-24 A 31-Jul-24 A Foundation Str 081 1.50 30-Jul-24 A 31-Jul-24 A Foundation Str 077 1.50 30-Jul-24 A 31-Jul-24 A Foundation Str 085 1.50 30-Jul-24 A 31-Jul-24 A Foundation Str 083 1.50 31-Jul-24 A 01-Aug-24 A Foundation Str 043 3.00 31-Jul-24 A 01-Aug-24 A Foundation Str 037 1.50 31-Jul-24 A 02-Aug-24 A Foundation Str 038 1.50 31-Jul-24 A 02-Aug-24 A Foundation Str 044 1.50 31-Jul-24 A 01-Aug-24 A Foundation Str 086 1.50 31-Jul-24 A 01-Aug-24 A Foundation Str 087 1.50 01-Aug-24 A 03-Aug-24 A Foundation Str 045 2.00 01-Aug-24 A 03-Aug-24 A Foundation Str 060 1.50 05-Aug-24 06-Aug-24 14.50 Foundation Str 061 1.50 05-Aug-24 06-Aug-24 14.00 Foundation Str 062 1.50 05-Aug-24 06-Aug-24 11.50 Foundation Str 058 1.50 06-Aug-24 08-Aug-24 14.00 Foundation Str 059 1.50 06-Aug-24 08-Aug-24 11.50 Foundation Str 057 1.50 08-Aug-24 09-Aug-24 14.50 Foundation Str 056 1.50 09-Aug-24 10-Aug-24 11.50 Foundation Str 054 1.50 10-Aug-24 12-Aug-24 14.50 Foundation Str 055 1.50 10-Aug-24 12-Aug-24 14.00 Foundation Str 053 1.50 10-Aug-24 12-Aug-24 11.50 Foundation Str 040 1.50 12-Aug-24 13-Aug-24 14.00 Foundation Str 048 2.00 12-Aug-24 14-Aug-24 14.50 Foundation Str 034 4.00 14-Aug-24 17-Aug-24 14.00 Foundation Str 047 2.00 14-Aug-24 15-Aug-24 11.50 Foundation Str 042 2.50 14-Aug-24 16-Aug-24 14.50 Foundation Str 041 1.50 16-Aug-24 17-Aug-24 11.50 Foundation Str 039 1.50 17-Aug-24 19-Aug-24 14.50 Foundation Str 035 1.50 17-Aug-24 19-Aug-24 11.50 Foundation Str 031 2.00 19-Aug-24 20-Aug-24 14.00 Foundation Str 033 1.50 19-Aug-24 20-Aug-24 14.50 Foundation Str 032 4.00 20-Aug-24 24-Aug-24 11.50 Foundation Str 028 4.00 22-Aug-24 26-Aug-24 14.00 Foundation Str 030 2.00 22-Aug-24 23-Aug-24 14.50 Foundation Str 027 2.00 24-Aug-24 26-Aug-24 14.50 Foundation Str 029 1.50 26-Aug-24 27-Aug-24 11.50 Foundation Str 024 3.00 27-Aug-24 29-Aug-24 14.50 Foundation Str 025 5.00 27-Aug-24 31-Aug-24 14.00 Foundation Str 026 2.00 27-Aug-24 29-Aug-24 11.50 Foundation Str 023 4.00 29-Aug-24 05-Sep-24 11.50 Foundation Str 021 2.00 30-Aug-24 31-Aug-24 14.50 Foundation Str 018 2.00 03-Sep-24 05-Sep-24 14.50 Foundation Str 022 2.00 03-Sep-24 05-Sep-24 14.00 Foundation Str 020 2.00 05-Sep-24 07-Sep-24 11.50 Foundation Str 015 5.00 06-Sep-24 11-Sep-24 14.50 Foundation Str 019 2.00 06-Sep-24 07-Sep-24 14.00 Aug Sep Oct Nov Dec 2024 Foundation Str 060 Foundation Str 061 Foundation Str 062 Foundation Str 058 Foundation Str 059 Foundation Str 057 Foundation Str 056 Foundation Str 054 Foundation Str 055 Foundation Str 053 Foundation Str 040 Foundation Str 048 Foundation Str 034 Foundation Str 047 Foundation Str 042 Foundation Str 041 Foundation Str 039 Foundation Str 035 Foundation Str 031 Foundation Str 033 Foundation Str 032 Foundation Str 028 Foundation Str 030 Foundation Str 027 Foundation Str 029 Foundation Str 024 Foundation Str 025 Foundation Str 026 Foundation Str 023 Foundation Str 021 Foundation Str 018 Foundation Str 022 Foundation Str 020 Foundation Str 015 Foundation Str 019 Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Update - By WBS SORTED BY WBS Page 2 of 5 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Foundation Str 017 2.50 07-Sep-24 10-Sep-24 11.50 Foundation Str 016 2.00 09-Sep-24 10-Sep-24 14.00 Foundation Str 013 2.00 11-Sep-24 12-Sep-24 14.00 Foundation Str 014 5.00 11-Sep-24 16-Sep-24 11.50 Foundation Str 012 2.00 12-Sep-24 13-Sep-24 14.50 Foundation Str 010 5.00 13-Sep-24 19-Sep-24 14.00 Foundation Str 009 1.50 14-Sep-24 16-Sep-24 14.50 Foundation Str 006 2.00 16-Sep-24 19-Sep-24 14.50 Foundation Str 011 2.00 17-Sep-24 19-Sep-24 11.50 Foundation Str 003 2.00 19-Sep-24 21-Sep-24 14.50 Foundation Str 007 2.00 20-Sep-24 21-Sep-24 15.50 Foundation Str 008 2.00 20-Sep-24 21-Sep-24 11.50 Foundation Str 001 5.00 21-Sep-24 27-Sep-24 14.50 Foundation Str 004 2.00 23-Sep-24 24-Sep-24 15.50 Foundation Str 005 5.00 23-Sep-24 27-Sep-24 11.50 Foundation Str 002 2.00 28-Sep-24 30-Sep-24 11.50 Structure Erection 49.50 05-Aug-24 07-Oct-24 7.00 Structure 099 0.50 05-Aug-24 05-Aug-24 -1.50 Structure 098 0.50 05-Aug-24 05-Aug-24 -1.50 Structure 097 0.50 06-Aug-24 06-Aug-24 -1.50 Structure 096 0.50 06-Aug-24 06-Aug-24 -1.50 Structure 095 0.50 08-Aug-24 08-Aug-24 -1.50 Structure 094 0.50 08-Aug-24 08-Aug-24 -1.50 Structure 093 0.50 09-Aug-24 09-Aug-24 -1.50 Structure 092 0.50 09-Aug-24 09-Aug-24 -1.50 Structure 091 0.50 10-Aug-24 10-Aug-24 -1.50 Structure 090 0.50 10-Aug-24 10-Aug-24 -1.50 Structure 089 0.50 12-Aug-24 12-Aug-24 -1.50 Structure 088 0.50 12-Aug-24 12-Aug-24 -1.50 Structure 087 0.50 13-Aug-24 13-Aug-24 -1.50 Structure 086 0.50 13-Aug-24 13-Aug-24 -1.50 Structure 085 0.50 14-Aug-24 14-Aug-24 -1.50 Structure 084 0.50 14-Aug-24 14-Aug-24 -1.50 Structure 083 0.50 15-Aug-24 15-Aug-24 -1.50 Structure 082 0.50 15-Aug-24 15-Aug-24 -1.50 Structure 081 0.50 16-Aug-24 16-Aug-24 -1.50 Structure 080 0.50 16-Aug-24 16-Aug-24 -1.50 Structure 079 0.50 17-Aug-24 17-Aug-24 -1.50 Structure 078 0.50 17-Aug-24 17-Aug-24 -1.50 Structure 077 0.50 19-Aug-24 19-Aug-24 -1.50 Structure 076 0.50 19-Aug-24 19-Aug-24 -1.50 Structure 075 0.50 20-Aug-24 20-Aug-24 -1.50 Structure 074 0.50 20-Aug-24 20-Aug-24 -1.50 Structure 073 0.50 22-Aug-24 22-Aug-24 -1.50 Structure 072 0.50 22-Aug-24 22-Aug-24 -1.50 Structure 071 0.50 23-Aug-24 23-Aug-24 -1.50 Structure 070 0.50 23-Aug-24 23-Aug-24 -1.50 Structure 069 0.50 24-Aug-24 24-Aug-24 -1.50 Structure 068 0.50 24-Aug-24 24-Aug-24 -1.50 Aug Sep Oct Nov Dec 2024 Foundation Str 017 Foundation Str 016 Foundation Str 013 Foundation Str 014 Foundation Str 012 Foundation Str 010 Foundation Str 009 Foundation Str 006 Foundation Str 011 Foundation Str 003 Foundation Str 007 Foundation Str 008 Foundation Str 001 Foundation Str 004 Foundation Str 005 Foundation Str 002 Structure Erection Structure 099 Structure 098 Structure 097 Structure 096 Structure 095 Structure 094 Structure 093 Structure 092 Structure 091 Structure 090 Structure 089 Structure 088 Structure 087 Structure 086 Structure 085 Structure 084 Structure 083 Structure 082 Structure 081 Structure 080 Structure 079 Structure 078 Structure 077 Structure 076 Structure 075 Structure 074 Structure 073 Structure 072 Structure 071 Structure 070 Structure 069 Structure 068 Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Update - By WBS SORTED BY WBS Page 3 of 5 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Structure 067 0.50 26-Aug-24 26-Aug-24 -1.50 Structure 066 0.50 26-Aug-24 26-Aug-24 -1.50 Structure 065 0.50 27-Aug-24 27-Aug-24 -1.50 Structure 064 0.50 27-Aug-24 27-Aug-24 -1.50 Structure 063 0.50 28-Aug-24 28-Aug-24 -1.50 Structure 062 0.50 28-Aug-24 28-Aug-24 -1.50 Structure 061 0.50 29-Aug-24 29-Aug-24 -1.50 Structure 060 0.50 29-Aug-24 29-Aug-24 -1.50 Structure 059 0.50 30-Aug-24 30-Aug-24 -1.50 Structure 058 0.50 30-Aug-24 30-Aug-24 -1.50 Structure 057 0.50 31-Aug-24 31-Aug-24 -1.50 Structure 056 0.50 31-Aug-24 31-Aug-24 -1.50 Structure 055 0.50 03-Sep-24 03-Sep-24 -1.50 Structure 054 0.50 03-Sep-24 03-Sep-24 -1.50 Structure 053 0.50 05-Sep-24 05-Sep-24 -1.50 Structure 052 0.50 05-Sep-24 05-Sep-24 -1.50 Structure 051 0.50 06-Sep-24 06-Sep-24 -1.50 Structure 050 0.50 06-Sep-24 06-Sep-24 -1.50 Structure 049 0.50 07-Sep-24 07-Sep-24 -1.50 Structure 048 0.50 07-Sep-24 07-Sep-24 -1.50 Structure 047 0.50 09-Sep-24 09-Sep-24 -1.50 Structure 046 0.50 09-Sep-24 09-Sep-24 -1.50 Structure 045 0.50 10-Sep-24 10-Sep-24 2.00 Structure 044 0.50 10-Sep-24 10-Sep-24 2.00 Structure 043 0.50 11-Sep-24 11-Sep-24 2.00 Structure 042 0.50 11-Sep-24 11-Sep-24 2.00 Structure 041 0.50 12-Sep-24 12-Sep-24 2.00 Structure 040 0.50 12-Sep-24 12-Sep-24 2.00 Structure 039 0.50 13-Sep-24 13-Sep-24 2.00 Structure 038 0.50 13-Sep-24 13-Sep-24 2.00 Structure 037 0.50 14-Sep-24 14-Sep-24 2.00 Structure 036 0.50 14-Sep-24 14-Sep-24 2.00 Structure 035 0.50 16-Sep-24 16-Sep-24 2.00 Structure 034 0.50 16-Sep-24 16-Sep-24 2.00 Structure 033 0.50 17-Sep-24 17-Sep-24 2.00 Structure 032 0.50 17-Sep-24 17-Sep-24 2.00 Structure 031 0.50 19-Sep-24 19-Sep-24 2.00 Structure 030 0.50 19-Sep-24 19-Sep-24 2.00 Structure 029 0.50 20-Sep-24 20-Sep-24 2.00 Structure 028 0.50 20-Sep-24 20-Sep-24 2.00 Structure 027 0.50 21-Sep-24 21-Sep-24 2.00 Structure 026 0.50 21-Sep-24 21-Sep-24 4.50 Structure 025 0.50 23-Sep-24 23-Sep-24 4.50 Structure 024 0.50 23-Sep-24 23-Sep-24 4.50 Structure 023 0.50 24-Sep-24 24-Sep-24 4.50 Structure 022 0.50 24-Sep-24 24-Sep-24 4.50 Structure 021 0.50 25-Sep-24 25-Sep-24 4.50 Structure 020 0.50 25-Sep-24 25-Sep-24 4.50 Structure 019 0.50 26-Sep-24 26-Sep-24 4.50 Aug Sep Oct Nov Dec 2024 Structure 067 Structure 066 Structure 065 Structure 064 Structure 063 Structure 062 Structure 061 Structure 060 Structure 059 Structure 058 Structure 057 Structure 056 Structure 055 Structure 054 Structure 053 Structure 052 Structure 051 Structure 050 Structure 049 Structure 048 Structure 047 Structure 046 Structure 045 Structure 044 Structure 043 Structure 042 Structure 041 Structure 040 Structure 039 Structure 038 Structure 037 Structure 036 Structure 035 Structure 034 Structure 033 Structure 032 Structure 031 Structure 030 Structure 029 Structure 028 Structure 027 Structure 026 Structure 025 Structure 024 Structure 023 Structure 022 Structure 021 Structure 020 Structure 019 Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Update - By WBS SORTED BY WBS Page 4 of 5 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24 Activity Name DUR, Days Start Finish Total Float Structure 018 0.50 26-Sep-24 26-Sep-24 4.50 Structure 017 0.50 27-Sep-24 27-Sep-24 4.50 Structure 016 0.50 27-Sep-24 27-Sep-24 4.50 Structure 015 0.50 28-Sep-24 28-Sep-24 4.50 Structure 014 0.50 28-Sep-24 28-Sep-24 4.50 Structure 013 0.50 30-Sep-24 30-Sep-24 4.50 Structure 012 0.50 30-Sep-24 30-Sep-24 4.50 Structure 011 0.50 01-Oct-24 01-Oct-24 4.50 Structure 010 0.50 01-Oct-24 01-Oct-24 4.50 Structure 009 0.50 02-Oct-24 02-Oct-24 7.00 Structure 008 0.50 02-Oct-24 02-Oct-24 7.00 Structure 007 0.50 03-Oct-24 03-Oct-24 7.00 Structure 006 0.50 03-Oct-24 03-Oct-24 7.00 Structure 005 0.50 04-Oct-24 04-Oct-24 7.00 Structure 004 0.50 04-Oct-24 04-Oct-24 7.00 Structure 003 0.50 05-Oct-24 05-Oct-24 7.00 Structure 002 0.50 05-Oct-24 05-Oct-24 7.00 Structure 001 0.50 07-Oct-24 07-Oct-24 7.00 Conductor Installation 65.50 17-Aug-24 09-Nov-24 -1.50 Wire Pull # 11 (Strs 099 - 097)4.00 17-Aug-24 23-Aug-24 0.00 Wire Pull # 10 (Strs 096 - 091)6.00 23-Aug-24 30-Aug-24 0.00 Wire Pull # 09 (Strs 090 - 076)7.00 31-Aug-24 10-Sep-24 -0.50 Wire Pull # 08 (Strs 075 - 065)7.00 11-Sep-24 19-Sep-24 -0.50 Wire Pull # 07 (Strs 064 - 046)9.00 21-Sep-24 01-Oct-24 -1.50 Wire Pull # 06 (Strs 045 - 042)4.00 02-Oct-24 05-Oct-24 -1.50 Wire Pull # 05 (Strs 041 - 027)7.00 07-Oct-24 15-Oct-24 -1.50 Wire Pull # 04 (Strs 026 - 023)4.00 16-Oct-24 19-Oct-24 -1.50 Wire Pull # 03 (Strs 022 - 010)7.00 21-Oct-24 29-Oct-24 -1.50 Wire Pull # 02 (Strs 009 - 001)6.00 30-Oct-24 05-Nov-24 -1.50 Wire Pull # 01 (Sub Deadend)3.00 07-Nov-24 09-Nov-24 -1.50 Restoration and Demobilization54.00 14-Sep-24 20-Nov-24 0.00 Restorations / Clean-up 52.00 14-Sep-24 18-Nov-24 0.00 Demobilization - T-Line Crews 2.00 19-Nov-24 20-Nov-24 0.00 Substation 45.00 09-Sep-24 02-Nov-24 14.00 Mobilization - Sub Crews 2.00 09-Sep-24*10-Sep-24 5.50 Foundations 4.00 11-Sep-24 14-Sep-24 5.50 Demo Static 1.00 16-Sep-24 16-Sep-24 20.50 Erect Deadend 4.00 01-Oct-24 04-Oct-24 5.50 Install Disconnect Switches 5.00 05-Oct-24 11-Oct-24 5.50 Erect Static Mast 1.00 05-Oct-24 05-Oct-24 9.50 Conduit & Grounding 3.00 12-Oct-24 15-Oct-24 13.50 Strain Bus & Static 5.00 12-Oct-24 17-Oct-24 5.50 Above Grade Conduit 3.00 18-Oct-24 21-Oct-24 5.50 Power & Control Cables 3.00 22-Oct-24 25-Oct-24 5.50 Testing & Commissioning 5.00 26-Oct-24 31-Oct-24 5.50 Demobilization - Substation Crews 2.00 01-Nov-24 02-Nov-24 14.00 Aug Sep Oct Nov Dec 2024 Structure 018 Structure 017 Structure 016 Structure 015 Structure 014 Structure 013 Structure 012 Structure 011 Structure 010 Structure 009 Structure 008 Structure 007 Structure 006 Structure 005 Structure 004 Structure 003 Structure 002 Structure 001 Conductor Installation Wire Pull # 11 (Strs 099 - 097) Wire Pull # 10 (Strs 096 - 091) Wire Pull # 09 (Strs 090 - 076) Wire Pull # 08 (Strs 075 - 065) Wire Pull # 07 (Strs 064 - 046) Wire Pull # 06 (Strs 045 - 042) Wire Pull # 05 (Strs 041 - 027) Wire Pull # 04 (Strs 026 - 023) Wire Pull # 03 (Strs 022 - 010) Wire Pull # 02 (Strs 009 - 001) Wire Pull # 01 (Sub Deadend) Restoration and Demobilization Restorations / Clean-up Demobilization - T-Line Crews Substation Mobilization - Sub Crews Foundations Demo Static Erect Deadend Install Disconnect Switches Erect Static Mast Conduit & Grounding Strain Bus & Static Above Grade Conduit Power & Control Cables Testing & Commissioning Demobilization - Substation Crews Oquirrh-Terminal 345KV Transmission Line Project Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Update - By WBS SORTED BY WBS Page 5 of 5 Data Date:05-Aug-24 Run Date:08-Aug-24 Finish Date: 20-Nov-24