20240829PAC to Staff 132-2 - 132(c) - c.v.3 GWW D1 Schedule DD July 2024.pdf
#Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1 Gateway West ProjecGateway West Project - Current Schedule (Expanded)Gateway West Project - Current Schedule (Expanded)5187.45 576.00 356.00 20-Jul-22 A 09-Sep-25 0.00 20-Jul-22 09-Sep-25 0.00 2 Exhibit I: Owner MileExhibit I: Owner MilestonesExhibit I: Owner Milestones 59.00 59.00 0.00 20-Jul-22 A 27-Sep-22 A 20-Jul-22 27-Sep-22 0.00 3 ALL-MS-0100 Effective Date of Release No. 1 100%0.00 0.00 0.00 20-Jul-22 A 20-Jul-22 0.00 4 ALL-MS-0130 ROW Access Provided for Survey, Staking & Planning 100%0.00 0.00 0.00 15-Aug-22 A 15-Aug-22 0.00 5 ALL-MS-0120 Owner Provided Approval for Project Site & Equipment Mobilization 100%0.00 0.00 0.00 01-Sep-22 A 01-Sep-22 0.00 6 ALL-MS-0140 ROW Access Provided for All Construction 100%0.00 0.00 0.00 27-Sep-22 A 27-Sep-22 0.00 7 Exhibit G.1.1 CriticalExhibit G.1.1 Critical & Interim MilestonesExhibit G.1.1 Critical & Interim Milestones 932.00 516.00 356.00 20-Jul-22 A 09-Sep-25 0.00 20-Jul-22 09-Sep-25 0.00 8 Critical MilestonesCritical MilestonesCritical Milestones 932.00 59.00 315.50 20-Jul-22 A 09-Sep-25 0.00 20-Jul-22 09-Sep-25 0.00 9 Overall ProjectOverall ProjectOverall Project 932.00 59.00 0.00 20-Jul-22 A 09-Sep-25 0.00 20-Jul-22 09-Sep-25 0.00 10 ALL-MS-0200 Contract Execution 100%0.00 0.00 0.00 20-Jul-22 A 20-Jul-22 0.00 11 ALL-MS-0210 Baseline Schedule Approved 100%0.00 0.00 0.00 02-Sep-22 A 02-Sep-22 0.00 12 ALL-MS-0220 Site Mobilization (Access)100%0.00 0.00 0.00 14-Sep-22 A 14-Sep-22 0.00 13 ALL-MS-0110 Full Notice to Proceed 100%0.00 0.00 0.00 27-Sep-22 A 27-Sep-22 0.00 14 ALL-MS-0240 Final Project Completion Date (includes reclamation)0%0.00 0.00 0.00 09-Sep-25 0.00 09-Sep-25 0.00 15 1Wa Line1Wa Line1Wa Line 8.95 0.00 8.95 05-Dec-24 15-Dec-24 0.38 05-Dec-24 15-Dec-24 0.00 16 ALL-MS-0400 Mechanical Completion (Updated to Dec 5, 2024)0%0.00 0.00 0.00 05-Dec-24*0.33 05-Dec-24 0.00 17 ALL-MS-0410 Substantial Completion (Updated to Dec 15, 2024)0%0.00 0.00 0.00 15-Dec-24*0.38 15-Dec-24 0.00 18 1Wc Line1Wc Line1Wc Line 6.35 0.00 6.35 20-Nov-24 30-Nov-24 0.00 20-Nov-24 30-Nov-24 0.00 19 ALL-MS-0420 Mechanical Completion (updated to Nov 20, 2024)0%0.00 0.00 0.00 20-Nov-24*0.35 20-Nov-24 0.00 20 ALL-MS-0430 Substantial Completion (updated o Nov 30, 2024)0%0.00 0.00 0.00 30-Nov-24*0.55 30-Nov-24 0.00 21 Aeolus to FreezeoAeolus to FreezeoutAeolus to Freezeout 9.00 0.00 9.00 20-Aug-24 30-Aug-24 0.50 20-Aug-24 30-Aug-24 0.00 22 ALL-MS-0440 Mechanical Completion ( updated to Aug 20, 2024)0%0.00 0.00 0.00 20-Aug-24*0.50 20-Aug-24 0.00 23 ALL-MS-0450 Substantial Completion (updated to Aug 30, 2024)0%0.00 0.00 0.00 30-Aug-24*0.50 30-Aug-24 0.00 24 Interim MilestonesInterim MilestonesInterim Milestones 36.00 36.00 0.00 29-Jul-22 A 09-Sep-22 A 29-Jul-22 09-Sep-22 0.00 25 Overall ProjectOverall ProjectOverall Project 36.00 36.00 0.00 29-Jul-22 A 09-Sep-22 A 29-Jul-22 09-Sep-22 0.00 26 ALL-MS-0310 Letter of Credit 100%0.00 0.00 0.00 29-Jul-22 A 29-Jul-22 0.00 27 ALL-MS-0300 Limited Notice to Proceed 100%0.00 0.00 0.00 12-Aug-22 A 12-Aug-22 0.00 28 ALL-MS-0340 Issue Safety Plan 100%0.00 0.00 0.00 14-Aug-22 A 14-Aug-22 0.00 29 ALL-MS-0320 Baseline Schedule for Initial Submission for Approval 100%0.00 0.00 0.00 30-Aug-22 A 30-Aug-22 0.00 30 ALL-MS-0330 Issue QA/QC Plan 100%0.00 0.00 0.00 09-Sep-22 A 09-Sep-22 0.00 31 ALL-MS-0350 Issue Environmental Assurance Plan 100%0.00 0.00 0.00 09-Sep-22 A 09-Sep-22 0.00 32 Substation ReadineSubstation Readiness Dates (Feb 21, 2023 email)Substation Readiness Dates (Feb 21, 2023 email)171.00 111.00 0.00 17-Nov-23 A 01-Jul-24 113.00 17-Nov-23 01-Jul-24 0.00 33 ALL-MS-360 Windstar 100%0.00 0.00 0.00 17-Nov-23 A 17-Nov-23 0.00 34 ALL-MS-380 Amasa (Nov 17, 2023 - TBD Dec 4, 2024)100%0.00 0.00 0.00 04-Dec-23 A 04-Dec-23 0.00 35 ALL-MS-340 Shirley Basin (Dec 11, 2023 cancelled moved to Jan 16, jan 23)100%0.00 0.00 22-Jan-24 A 22-Jan-24 0.00 36 ALL-MS-400 SB Sub to TB Flats Bay Readiness - set for Feb 5 100%0.00 0.00 0.00 31-Jan-24 A 31-Jan-24 0.00 37 ALL-MS-370 Freezeout (Request Required by June 1, 2024)100%0.00 0.00 0.00 31-Mar-24 A 01-Jun-24 53.00 38 ALL-MS-350 Dave Johnson (Request Required by March 1, 2024)100%0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 0.00 39 ALL-MS-410 Aeolus 100%0.00 0.00 0.00 20-Apr-24 A 20-Apr-24 0.00 40 ALL-MS-390 Heward (Request Required by July 1, 2024)0%0.00 0.00 0.00 01-Jul-24*9.00 01-Jul-24 0.00 41 Project DelaysProject DelaysProject Delays 484.00 527.00 9.00 15-Sep-22 A 14-Jul-24 116.00 15-Sep-22 20-Apr-24 -69.00 42 Construction DelayConstruction DelaysConstruction Delays 484.00 527.00 9.00 15-Sep-22 A 14-Jul-24 116.00 15-Sep-22 20-Apr-24 -69.00 43 ALL-DEL-0001 Delay to "ALL-MS-0110" FNTP at WC1 due to Landowner Issues 100%12.00 12.00 0.00 15-Sep-22 A 26-Sep-22 A 15-Sep-22 26-Sep-22 0.00 44 ALL-DEL-0004 Material Delays- Poles WA2 Str 1-53a 100%3.00 53.00 0.00 01-Oct-22 A 22-Nov-22 A 01-Oct-22 22-Nov-22 0.00 45 ALL-DEL-0002 Delay Due to Agency requested Access Route Changes on WC1 Str 165-171 100%41.00 85.00 0.00 21-Sep-22 A 14-Dec-22 A 21-Sep-22 14-Dec-22 0.00 46 ALL-DEL-0003 Material Delays- Poles WA3 Poles Str 227-344a 100%3.00 190.75 0.00 20-Oct-22 A 28-Apr-23 A 20-Oct-22 28-Apr-23 0.00 47 ALL-DEL-0007 Carbon County Condtional Use Permit Expiry AF- notice 1 100%3.00 99.33 0.00 28-Mar-23 A 05-Jul-23 A 28-Mar-23 05-Jul-23 0.00 48 ALL-DEL-0006 Anchor Bolt Material Delay (Section Wa54-Wa132)100%3.00 39.92 0.00 08-Jun-23 A 17-Jul-23 A 08-Jun-23 17-Jul-23 0.00 49 ALL-DEL-0008 Carbon County Road use Agreement AF- notice 2 100%3.00 14.92 0.00 05-Jul-23 A 19-Jul-23 A 05-Jul-23 19-Jul-23 0.00 50 ALL-DEL-0009 USFS Goshawk Survey (delays to access and structures WC 172-187)100%27.50 49.92 0.00 01-Jun-23 A 20-Jul-23 A 01-Jun-23 20-Jul-23 0.00 51 ALL-DEL-0005 Golden Eagle Nest at Str Wa49-Wa61 *Cleared July 24th*100%3.00 91.92 0.00 24-Apr-23 A 24-Jul-23 A 24-Apr-23 24-Jul-23 0.00 52 ALL-DEL-0011 Rawlins BLM approval delay on of variance 36 - Shutdown from structure 232 - 323 on both lines TBD 100%3.00 17.00 0.00 09-Aug-23 A 25-Aug-23 A 09-Aug-23 25-Aug-23 0.00 53 ALL-DEL-0010 Aelous to Freezout Right of Way Grant Approval (delayed access start)100%0.00 9.00 0.00 01-Sep-23 A 10-Sep-23 A 01-Sep-23 10-Sep-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 09-Sep-25, Gateway West 09-Sep-25, Exhibit G.1.1 C 09-Sep-25, Critical Mileston 09-Sep-25, Overall Project Final Project Completion Da 15-Dec-24, 1Wa Line Mechanical Completion (Updated to Dec 5, 2024), 05-Dec-24* Substantial Completion (Updated to Dec 15, 2024), 15-Dec-24* 30-Nov-24, 1Wc Line Mechanical Completion (updated to Nov 20, 2024), 20-Nov-24* Substantial Completion (updated o Nov 30, 2024), 30-Nov-24* 30-Aug-24, Aeolus to Freezeout Mechanical Completion ( updated to Aug 20, 2024), 20-Aug-24* Substantial Completion (updated to Aug 30, 2024), 30-Aug-24* 01-Jul-24, Substation Readiness Dates (Feb 21, 2023 email) - TBD Dec 4, 2024), 04-Dec-23 A Dec 11, 2023 cancelled moved to Jan 16, jan 23), 22-Jan-24 A B Flats Bay Readiness - set for Feb 5, 31-Jan-24 A Freezeout (Request Required by June 1, 2024), 31-Mar-24 A ve Johnson (Request Required by March 1, 2024), 01-Apr-24 A Aeolus, 20-Apr-24 A Heward (Request Required by July 1, 2024), 01-Jul-24* 14-Jul-24, Project Delays 14-Jul-24, Construction Delays Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 1 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 54 ALL-DEL-0022 Delay to Access Str Wc-166-169 due to work stoppage on Access non-conformance (plan Submitted Oct 2, 2023) 100%0.00 20.92 0.00 28-Sep-23 A 18-Oct-23 A 28-Sep-23 18-Oct-23 0.00 55 ALL-DEL-0019 Delay to WAPA Outage on Aeoulos to Freezeout Oct 14-20 (Str AF-6-7)100%9.17 10.92 0.00 14-Oct-23 A 24-Oct-23 A 14-Oct-23 24-Oct-23 0.00 56 ALL-DEL-0023 Delay to Str 297 setting due to manufacturing error - TBD TAP response 100%0.00 36.92 0.00 20-Sep-23 A 26-Oct-23 A 20-Sep-23 26-Oct-23 0.00 57 ALL-DEL-0012 Delay on AF Str 19-25 contingent on NSO Watercrossing Variance (all ground disturbance work) 100%3.00 46.92 0.00 11-Sep-23 A 27-Oct-23 A 11-Sep-23 27-Oct-23 0.00 58 ALL-DEL-0025 Delay to Windstor Substation Deadend to do Pull 1a into the Substation TBD Again due to steel issues 100%0.00 155.92 0.00 12-Jun-23 A 14-Nov-23 A 12-Jun-23 14-Nov-23 0.00 59 ALL-DEL-0027 Delay due to Structure Deflection from Str Wa120-122 TBD Nov 15 100%1.00 9.00 0.00 07-Nov-23 A 15-Nov-23 A 07-Nov-23 15-Nov-23 0.00 60 ALL-DEL-0026 NO Access to Str Wa-320 "Muddy Creek Wetland Reclamation Plan" TBD Dec 11 (pushed) 100%0.00 48.92 0.00 29-Sep-23 A 16-Nov-23 A 29-Sep-23 16-Nov-23 0.00 61 ALL-DEL-0017 Delay to Windstar Substation Readiness - moved to Nov 17 TBD 100%0.92 71.92 0.00 07-Sep-23 A 17-Nov-23 A 07-Sep-23 17-Nov-23 0.00 62 ALL-DEL-0021 Delay to Access Wc-Str 170-171 due to Casper BLM Work Stoppage 100%0.00 110.92 0.00 03-Aug-23 A 21-Nov-23 A 03-Aug-23 21-Nov-23 0.00 63 ALL-DEL-0013 Outage Coordination for Wc Line Cutover Delay - completed delay when new sequence did not require outage 100%9.00 28.00 0.00 03-Nov-23 A 30-Nov-23 A 03-Nov-23 30-Nov-23 0.00 64 ALL-DEL-0014 Delay to TEMP Tie-Line 01 Outage Coordination (Updated to Dec 4)100%46.00 70.00 0.00 25-Sep-23 A 03-Dec-23 A 25-Sep-23 03-Dec-23 0.00 65 ALL-DEL-0024 Delay to Amasa Substation Readiness TBD Dec 3 (outage Dec 4)100%0.00 81.92 0.00 13-Sep-23 A 03-Dec-23 A 13-Sep-23 03-Dec-23 0.00 66 ALL-DEL-0030 Delay to Str Wc-208 drilled pier guy anchor locations - RFI -442 submitted Dec 11, Resp Jan 5 100%0.00 6.00 0.00 11-Dec-23 A 18-Dec-23 A 11-Dec-23 18-Dec-23 0.00 67 ALL-DEL-0020 Delay to Structure Setting due to Rock Drilling (Str 190-153 Both Wc + Wa Line) Nov 22 TBD 100%43.00 72.00 0.00 10-Oct-23 A 20-Dec-23 A 10-Oct-23 20-Dec-23 0.00 68 ALL-DEL-0030b Delay to Str Wc-208 drilled pier guy anchor locations - RFI -442 - further info required 100%2.00 2.00 0.00 09-Jan-24 A 11-Jan-24 A 09-Jan-24 11-Jan-24 0.00 69 ALL-DEL-0031 Project Shutdown due to frigid temperatures Jan 12, 13, 15, 16 100%4.00 4.00 0.00 12-Jan-24 A 16-Jan-24 A 12-Jan-24 16-Jan-24 0.00 70 ALL-DEL-0028 Delay to Wa-249 Structure Setting Due to Anchor Bolts + Pole Incompatible. TBD Jan 19 100%0.00 48.33 0.00 01-Dec-23 A 18-Jan-24 A 01-Dec-23 18-Jan-24 0.00 71 ALL-DEL-0033 Delay to OPGW Str Wa-123-132 span due to incorrect fiber reel order. BG Approval required 100%0.00 63.92 0.00 17-Nov-23 A 19-Jan-24 A 17-Nov-23 19-Jan-24 0.00 72 ALL-DEL-0034 Delay to Str Wc-232 Anchor Bolt Delay (ongoing)100%0.00 78.92 0.00 02-Nov-23 A 19-Jan-24 A 02-Nov-23 19-Jan-24 0.00 73 ALL-DEL-0015 Delay to Shirley Basin Substation Readiness - Outage Dec 11, 2023, moved to jan 16 dec 12, jan 23 100%1.00 174.92 0.00 01-Aug-23 A 22-Jan-24 A 01-Aug-23 22-Jan-24 0.00 74 ALL-DEL-0016 Delay to Shirley Basin Substation TB Flats Bay Readiness - TBD Jan 25, feb 5, now feb 1 100%0.92 183.92 0.00 01-Aug-23 A 31-Jan-24 A 01-Aug-23 31-Jan-24 0.00 75 ALL-DEL-0029 Delay to Wc-204 Structure Setting Due to Anchor Bolts + Pole Incompatible. TBD Feb 5 100%0.00 48.92 0.00 15-Dec-23 A 01-Feb-24 A 15-Dec-23 01-Feb-24 0.00 76 ALL-DEL-0037 Delay to structure setting due to receipt of damaged pulls str. #'s Wc-8,14,21,22 100%3.27 3.27 0.00 01-Mar-24 A 05-Mar-24 A 01-Mar-24 05-Mar-24 0.00 77 ALL-DEL-0036 Delay to Structures 254-190 due to BLM Row Shutdown due to "excessive rutting" (delay cutover at 205) 100%3.00 54.00 0.00 21-Jan-24 A 15-Mar-24 A 21-Jan-24 15-Mar-24 0.00 78 ALL-DEL-0032 Delay to all work between Str Wc-149-189, due to snow and winter weather 100%74.00 74.92 0.00 18-Jan-24 A 01-Apr-24 A 18-Jan-24 01-Apr-24 0.00 79 ALL-DEL-0018 Delay to Aeolus Substation Readiness (TBD March 2024)100%3.00 223.00 0.00 11-Sep-23 A 20-Apr-24 A 11-Sep-23 20-Apr-24 0.00 80 ALL-DEL-0047 Delay to Structure Salvage work due to rain/wet weather conditions 100%5.00 5.00 0.00 06-May-24 A 10-May-24 A 81 ALL-DEL-0035 Delay to Str Wc-266A and 267 - require NSO variance, 2 structures were rejected, has been submitted target comp. Jul14 0%21.00 312.00 14.00 24-Aug-23 A 14-Jul-24 45.57 24-Aug-23 10-Apr-24 -95.00 82 Owner Supplied MatOwner Supplied MaterialsOwner Supplied Materials 637.00 527.00 82.32 15-Sep-22 A 09-Oct-24 21.68 15-Sep-22 09-Oct-24 0.00 83 Poles, Arms, and CrPoles, Arms, and Cross Braces *Re-named Feb 2023*Poles, Arms, and Cross Braces *Re-named Feb 2023*787.00 655.00 100.38 15-Sep-22 A 09-Oct-24 0.30 15-Sep-22 09-Oct-24 0.00 84 Client Guaranteed Client Guaranteed Pole Material Delivery MilestonesClient Guaranteed Pole Material Delivery Milestones 335.00 380.00 0.00 13-Jun-23 A 01-Jul-24 85.68 13-Jun-23 16-Apr-24 -75.00 85 ALL-MS-0510 SEGMENT 9b- 1 Wc-268, 1 (15-Apr-23)100%0.00 0.00 0.00 13-Jun-23 A 13-Jun-23 0.00 86 ALL-MS-0500 SEGMENT 3 - 1Wa-227 to 1Wa-344, 119 (15-Apr-23)100%0.00 0.00 0.00 23-Jul-23 A 23-Jul-23 0.00 87 ALL-MS-0520 SEGMENT 4 - 1Wa-206 to 1Wa-226, 21 (27-May-23)100%0.00 0.00 0.00 05-Aug-23 A 05-Aug-23 0.00 88 ALL-MS-0530 SEGMENT 5 - 1Wa-54 to 1Wa-132, 79 (19-Jun-23)100%0.00 0.00 0.00 12-Aug-23 A 12-Aug-23 0.00 89 ALL-MS-0540 SEGMENT 6 - A-F 1 to A-F 30, 30(13-Jul-23)100%0.00 0.00 0.00 18-Oct-23 A 18-Oct-23 0.00 90 ALL-MS-0550 SEGMENT 7 - 1Wa-133 to 1Wa-205, 74 (16-Sep-23)100%0.00 0.00 0.00 10-Nov-23 A 10-Nov-23 0.00 91 ALL-MS-0560 SEGMENT 8 - 1Wc-1 to 1Wc-49B, 51 (03-Oct-23) str 32 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 0.00 92 ALL-MS-0580 SEGMENT 10 - 1Wc-49C to 1Wc-148, 101 (25-Mar-24)100%0.00 0.00 0.00 27-Jun-24 A 01-Apr-24 -87.00 93 ALL-MS-0570 SEGMENT 9 - 1Wc-209 to 1Wc-267, 60 (24-Mar-24) *Updated to 2023 0%0.00 0.00 0.00 01-Jul-24*34.16 01-Apr-24 -91.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Delay to Str Wc-266A and 267 - require NSO variance, 2 structures were rejected, has been submi 09-Oct-24, Owner Supplied Materials 09-Oct-24, Poles, Arms, and Cross Braces *Re-named Feb 2023* 01-Jul-24, Client Guaranteed Pole Material Delivery Milestones -Jun-23 A Apr-23), 23-Jul-23 A 7-May-23), 05-Aug-23 A -Jun-23), 12-Aug-23 A 30(13-Jul-23), 18-Oct-23 A 1Wa-205, 74(16-Sep-23), 10-Nov-23 A NT 8 - 1Wc-1 to 1Wc-49B, 51(03-Oct-23) str 32, 01-Mar-24 A SEGMENT 10 - 1Wc-49C to 1Wc-148, 101 (25-Mar-24), 27-Jun-24 A SEGMENT 9 - 1Wc-209 to 1Wc-267, 60(24-Mar-24) *Updated to 2023, 01-Jul-24* Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 2 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 94 ALL-MS-0590 SEGMENT 11 - 1Wc-269 to 1Wc-2/177A , 69 (16-Apr-24)0%0.00 0.00 0.00 01-Jul-24*68.63 16-Apr-24 -75.00 95 Receiving Pole MaReceiving Pole MaterialsReceiving Pole Materials 594.00 655.00 2.00 15-Sep-22 A 02-Jul-24 83.68 15-Sep-22 30-Apr-24 -63.00 96 ALL-OSM-0005 Receive Poles, Arms, and Cross Braces WC1 (Wc-149-208) (65/65 poles)100%31.00 28.00 0.00 15-Sep-22 A 12-Oct-22 A 15-Sep-22 12-Oct-22 0.00 97 ALL-OSM-0003 Receive Poles, Arms, and Cross Braces WA2 (Wa-1-53A) (55/55)100%30.00 18.00 0.00 17-Oct-22 A 03-Nov-22 A 17-Oct-22 03-Nov-22 0.00 98 ALL-OSM-0004 Receive Poles, Arms, and Cross Braces WA3 (Wa-227-344) (119/119)100%42.00 230.08 0.00 05-Dec-22 A 23-Jul-23 A 05-Dec-22 23-Jul-23 0.00 99 ALL-OSM-0006a Receive Poles, Arms, and Cross Braces WA4 (Wa-227-207) (21/21)100%21.00 63.00 0.00 03-Jun-23 A 05-Aug-23 A 03-Jun-23 05-Aug-23 0.00 100 ALL-OSM-0006b Receive Poles, Arms, and Cross Braces WA4 (Wa-132-53A) (80/80)100%21.00 96.92 0.00 08-May-23 A 12-Aug-23 A 08-May-23 12-Aug-23 0.00 101 ALL-OSM-0007 Receive Poles, Arms, and Cross Braces AF5 (AF-1-31) (30/30)100%11.00 121.92 0.00 12-Jun-23 A 11-Oct-23 A 12-Jun-23 11-Oct-23 0.00 102 ALL-OSM-0006c Receive Poles, Arms, and Cross Braces WA4 (Wa-133-206) (73/74) str 167 100%21.00 125.92 0.00 08-Jul-23 A 10-Nov-23 A 08-Jul-23 10-Nov-23 0.00 103 ALL-OSM-0008 Receive Poles, Arms, and Cross Braces WC6 (Wc-1-49b) (51/51)100%25.00 115.00 0.00 16-Aug-23 A 08-Dec-23 A 16-Aug-23 08-Dec-23 0.00 104 ALL-OSM-0009 Receive Poles, Arms, and Cross Braces WC7 (Wc-49b-148) (101/101pole segments missing misc hardware) 100%30.00 287.00 0.00 15-Sep-23 A 27-Jun-24 A 15-Sep-23 20-Apr-24 -68.00 105 ALL-OSM-0011 Receive Poles, Arms, and Cross Braces WC9 (Wc-268- 7/2 SB) (83/83 pole segments missing misc hardware)) 80%30.00 91.00 2.00 01-Apr-24 A 02-Jul-24 66.63 01-Apr-24 30-Apr-24 -63.00 106 ALL-OSM-0010 Receive Poles, Arms, and Cross Braces WC8 (Wc-209-267) (60/60 pole segments missing misc hardware) 80%30.00 126.00 2.00 26-Feb-24 A 02-Jul-24 32.16 26-Feb-24 21-Apr-24 -72.00 107 Hauling Poles to SHauling Poles to SiteHauling Poles to Site 536.92 578.00 100.38 01-Dec-22 A 09-Oct-24 0.30 01-Dec-22 09-Oct-24 0.00 108 WA2-MAT-1300 Material Hauling (Section WA2: Wa-1-53A) (55/55)100%14.00 182.00 0.00 01-Dec-22 A 31-May-23 A 01-Dec-22 31-May-23 0.00 109 WA4-MAT-1285 Material Hauling (Section WA4: Wa-227-207 (21/21)100%14.00 26.00 0.00 17-Jul-23 A 12-Aug-23 A 17-Jul-23 12-Aug-23 0.00 110 WA4-MAT-1330 Material Hauling (Section WA4: Wa-53A-132 (79/79)100%14.00 153.92 0.00 20-May-23 A 20-Oct-23 A 20-May-23 20-Oct-23 0.00 111 WA3-MAT-1290 Material Hauling (Section WA3: Wa-344 (SB) to Wa-227) (118/118)100%10.00 93.92 0.00 31-Jul-23 A 01-Nov-23 A 31-Jul-23 01-Nov-23 0.00 112 AF5-MAT-1310 Material Hauling (Section AF5: AF-1 to AF-31) (30/30)100%2.00 46.67 0.00 18-Sep-23 A 03-Nov-23 A 18-Sep-23 03-Nov-23 0.00 113 Crew 2 Material Hauling (Section WC1: Wc-149-208 (SB) to Wa-227) (65/65)100%14.00 155.87 0.00 13-Jul-23 A 15-Dec-23 A 13-Jul-23 04-Aug-24 233.00 114 WC6-MAT-1320 Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa) (ongoing) (51/51)100%14.00 150.35 0.00 24-Jan-24 A 22-Jun-24 A 24-Jan-24 07-Jun-24 -15.70 115 WC7-MAT-1330 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) (44/101)44%14.00 59.78 6.00 02-May-24 A 06-Jul-24 30.34 15-May-24 29-May-24 -38.92 116 WC9-MAT-1350 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward)0%14.00 0.00 14.00 26-Jul-24 09-Aug-24 42.85 26-Jul-24 09-Aug-24 0.00 117 WC8-MAT-1340 Material Hauling Section WC8: Wc-208 to Wc-267 (Heward)0%14.00 0.00 14.00 01-Aug-24 15-Aug-24 0.39 01-Aug-24 15-Aug-24 0.00 118 WA4-MAT-1340 Material Hauling (Section WA4: Wa-133-206 (23/74)60%14.00 328.92 15.00 07-Aug-23 A 09-Oct-24 0.30 07-Aug-23 09-Oct-24 0.00 119 Anchor BoltsAnchor BoltsAnchor Bolts 637.00 521.00 41.00 22-Sep-22 A 20-Aug-24 63.00 22-Sep-22 20-Aug-24 0.00 120 Client Guaranteed Client Guaranteed ABC Material Delivery MilestonesClient Guaranteed ABC Material Delivery Milestones 71.00 119.00 0.00 13-Jun-23 A 10-Oct-23 A 13-Jun-23 10-Oct-23 0.00 121 ALL-MS-600 SEGMENT 9b- 1 Wc-268, 1 (17-Apr-23)100%0.00 0.00 0.00 13-Jun-23 A 13-Jun-23 0.00 122 ALL-MS-630 SEGMENT 6 - A-F 1 to A-F 30, 30(27-Jun-23)100%0.00 0.00 0.00 27-Jun-23 A 27-Jun-23 0.00 123 ALL-MS-590 SEGMENT 3 - 1Wa-227 to 1Wa-344, 119 (17-Apr-23)100%0.00 0.00 0.00 30-Jun-23 A 30-Jun-23 0.00 124 ALL-MS-620 SEGMENT 5 - 1Wa-54 to 1Wa-132, 79 (24-May-23)100%0.00 0.00 0.00 17-Jul-23 A 17-Jul-23 0.00 125 ALL-MS-650 SEGMENT 8 - 1Wc-1 to 1Wc-49B, 51 (01-Oct-23)100%0.00 0.00 0.00 01-Sep-23 A 01-Sep-23 0.00 126 ALL-MS-610 SEGMENT 4 - 1Wa-206 to 1Wa-226, 21 (15-May-23)100%0.00 0.00 0.00 11-Sep-23 A 11-Sep-23 0.00 127 ALL-MS-640 SEGMENT 7 - 1Wa-133 to 1Wa-205, 74 (16-Sep-23)100%0.00 0.00 0.00 12-Sep-23 A 12-Sep-23 0.00 128 ALL-MS-670 SEGMENT 10 - 1Wc-49C to 1Wc-148, 101 (01-Oct-23)100%0.00 0.00 0.00 26-Sep-23 A 26-Sep-23 0.00 129 ALL-MS-660 SEGMENT 9 - 1Wc-209 to 1Wc-267, 60 (01-Oct-23) str 189b 100%0.00 0.00 0.00 10-Oct-23 A 10-Oct-23 0.00 130 ALL-MS-680 SEGMENT 11 - 1Wc-269 to 1Wc-2/177A , 69 (01-Oct-23)100%0.00 0.00 0.00 10-Oct-23 A 10-Oct-23 0.00 131 Receiving ABC MaReceiving ABC MaterialsReceiving ABC Materials 414.08 384.00 0.00 22-Sep-22 A 10-Oct-23 A 22-Sep-22 10-Oct-23 0.00 132 ALL-OSM-0014 Receive Anchor Bolts WC1 (Wc-149-208) (12/12)100%31.00 4.08 0.00 22-Sep-22 A 26-Sep-22 A 22-Sep-22 26-Sep-22 0.00 133 ALL-OSM-0012 Receive Anchor Bolts WA2 (Wa-1-53A)100%30.00 3.00 0.00 17-Oct-22 A 19-Oct-22 A 17-Oct-22 19-Oct-22 0.00 134 ALL-OSM-0016 Receive Anchor Bolts AF5 (AF-1-31) (16 received)100%16.00 0.92 0.00 27-Jun-23 A 27-Jun-23 A 27-Jun-23 27-Jun-23 0.00 135 ALL-OSM-0013 Receive Anchor Bolts WA3 (Wa-228-344) (117/117)100%15.00 162.00 0.00 19-Jan-23 A 30-Jun-23 A 19-Jan-23 30-Jun-23 0.00 136 ALL-OSM-0015b Receive Anchor Bolts WA4 (Wa-132-54) (17/17) TBD June 8 100%14.00 9.00 0.00 08-Jul-23 A 17-Jul-23 A 08-Jul-23 17-Jul-23 0.00 137 ALL-OSM-0015a Receive Anchor Bolts WA4 (Wa-227-207) (1/1) str 227 100%10.00 0.00 0.00 25-Aug-23 A 25-Aug-23 A 25-Aug-23 25-Aug-23 0.00 138 ALL-OSM-0017 Receive Anchor Bolts WC6 (Wc-1-49b) (7/8) str 46 100%6.00 2.00 0.00 31-Aug-23 A 01-Sep-23 A 31-Aug-23 01-Sep-23 0.00 139 ALL-OSM-0015c Receive Anchor Bolts WA4 (Wa-133-206) (6/6)100%6.00 2.00 0.00 11-Sep-23 A 12-Sep-23 A 11-Sep-23 12-Sep-23 0.00 140 ALL-OSM-0018 Receive Anchor Bolts WC7 (Wc-49b-148)100%6.00 27.00 0.00 31-Aug-23 A 26-Sep-23 A 31-Aug-23 26-Sep-23 0.00 141 ALL-OSM-0020 Receive Anchor Bolts WC9 (Wc-268- 7/2 SB)100%6.00 78.00 0.00 25-Jul-23 A 10-Oct-23 A 25-Jul-23 10-Oct-23 0.00 142 ALL-OSM-0019 Receive Anchor Bolts WC8 (Wc-209-267)100%6.00 15.00 0.00 26-Sep-23 A 10-Oct-23 A 26-Sep-23 10-Oct-23 0.00 143 Hauling ABC to SHauling ABC to SiteHauling ABC to Site 365.00 446.00 41.00 02-Jan-23 A 20-Aug-24 63.00 02-Jan-23 20-Aug-24 0.00 144 WA4-MAT-1310 Material Hauling (Section WA2: Wa-1-53A)100%14.00 30.00 0.00 02-Jan-23 A 31-Jan-23 A 02-Jan-23 31-Jan-23 0.00 145 WA4-MAT-1350 Material Hauling (Section WA4: Wa-132 to Wa-53A)100%7.00 11.00 0.00 01-Aug-23 A 12-Aug-23 A 01-Aug-23 12-Aug-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 SEGMENT 11 - 1Wc-269 to 1Wc-2/177A , 69 (16-Apr-24), 01-Jul-24* 02-Jul-24, Receiving Pole Materials Receive Poles, Arms, and Cross Braces WC9 (Wc-268- 7/2 SB) (83/83 pole segments missing misc h Receive Poles, Arms, and Cross Braces WC8 (Wc-209-267) (60/60 pole segments missing misc hard 09-Oct-24, Hauling Poles to Site Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) (44/101), 06-Jul-24 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward), 09-Aug-24 Material Hauling Section WC8: Wc-208 to Wc-267 (Heward), 15-Aug-24 Material Hauling (Section WA4: Wa-133-206 (23/74), 09-Oct-24 20-Aug-24, Anchor Bolts ABC Material Delivery Milestones -Jun-23 A -Jun-23 A 23), 30-Jun-23 A y-23), 17-Jul-23 A 01-Oct-23), 01-Sep-23 A 21 (15-May-23), 11-Sep-23 A 74(16-Sep-23), 12-Sep-23 A 48, 101 (01-Oct-23), 26-Sep-23 A 267, 60(01-Oct-23) str 189b, 10-Oct-23 A c-2/177A , 69 (01-Oct-23), 10-Oct-23 A erials 20-Aug-24, Hauling ABC to Site Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 3 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 146 WA3-MAT-1300 Material Hauling (Section WA3: Wa-344 (SB) to Wa-227)100%7.00 8.00 0.00 02-Oct-23 A 10-Oct-23 A 02-Oct-23 10-Oct-23 0.00 147 AF5-MAT-1320 Material Hauling (Section AF5: AF-1 to AF-31)100%7.00 24.92 0.00 18-Sep-23 A 12-Oct-23 A 18-Sep-23 12-Oct-23 0.00 148 WA4-MAT-1320 Material Hauling (Section WA4: Wa-227 to Wa-207)100%3.00 1.00 0.00 06-Nov-23 A 07-Nov-23 A 06-Nov-23 07-Nov-23 0.00 149 WA4-MAT-1360 Material Hauling (Section WA4: Wa-133 to Wa-206)100%3.00 66.00 0.00 25-Sep-23 A 30-Nov-23 A 25-Sep-23 30-Nov-23 0.00 150 WC1-MAT-1310 Material Hauling (Section WC1: Wc-149-208 (SB) to Wa-227)100%7.00 52.92 0.00 09-Oct-23 A 30-Nov-23 A 09-Oct-23 30-Nov-23 0.00 151 WC6-MAT-1330 Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa)100%7.00 105.92 0.00 01-Dec-23 A 15-Mar-24 A 01-Dec-23 15-Mar-24 0.00 152 WC7-MAT-1340 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) (7/11)65%7.00 133.00 7.00 19-Feb-24 A 07-Jul-24 23.80 19-Feb-24 08-May-24 -60.92 153 WC8-MAT-1350 Material Hauling Section WC8: Wc-208 to Wc-267 (Heward) (4/5)80%7.00 200.92 2.00 13-Dec-23 A 29-Jul-24 33.49 13-Dec-23 29-Jul-24 0.00 154 WC9-MAT-1360 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward) (2/5)40%7.00 52.00 7.00 06-Dec-23 A 20-Aug-24 42.30 06-Dec-23 20-Aug-24 0.00 155 Material ProcuremenMaterial ProcurementMaterial Procurement 636.45 576.00 85.18 20-Jul-22 A 12-Oct-24 0.82 20-Jul-22 12-Oct-24 0.00 156 ALL-MAT-1240 Prepare & Submit Material RFQ's 100%5.00 5.00 0.00 20-Jul-22 A 25-Jul-22 A 20-Jul-22 25-Jul-22 0.00 157 ALL-MAT-1250 Quote Submission Period 100%10.00 10.00 0.00 26-Jul-22 A 05-Aug-22 A 26-Jul-22 05-Aug-22 0.00 158 ALL-MAT-1260 Evaluation of Quotes 100%5.00 5.00 0.00 06-Aug-22 A 11-Aug-22 A 06-Aug-22 11-Aug-22 0.00 159 ALL-MAT-1270 Award Suppliers (Place Orders & Enter Into Agreements) *Upon Signing of LNTP*100%8.00 8.00 0.00 12-Aug-22 A 19-Aug-22 A 12-Aug-22 19-Aug-22 0.00 160 EL1-MAT-1290 Element 1 - Insulators + Hardware Material Order Release (15% down)100%0.00 0.00 0.00 19-Aug-22 A 19-Aug-22 0.00 161 EL2-MAT-1280 Element 2 - Insulators + Hardware Material Order Release (15% down)100%0.00 0.00 0.00 19-Aug-22 A 19-Aug-22 0.00 162 EL3-MAT-1300 Element 3 - Insulators + Hardware Material Order Release(15% down)100%0.00 0.00 0.00 19-Aug-22 A 19-Aug-22 0.00 163 Insulators and HW Insulators and HW - Fabrication and DeliveryInsulators and HW - Fabrication and Delivery 755.50 681.00 103.25 20-Aug-22 A 12-Oct-24 1.83 20-Aug-22 12-Oct-24 0.00 164 Priority Order 1Priority Order 1Priority Order 1 714.27 346.00 7.00 20-Aug-22 A 03-Aug-24 4.53 20-Aug-22 03-Aug-24 0.00 165 FabricationFabricationFabrication 322.08 322.08 0.00 20-Aug-22 A 08-Jul-23 A 20-Aug-22 08-Jul-23 0.00 166 WA2-MAT-1212 Insulators Fabrication (Section WA2: Wa-1 to Wa-54)100%81.00 149.00 0.00 02-Nov-22 A 30-Mar-23 A 02-Nov-22 30-Mar-23 0.00 167 WA2-MAT-1222 Misc. Hardware Fabrication (Section WA2: Wa-1 to Wa-54)100%81.00 300.00 0.00 20-Aug-22 A 15-Jun-23 A 20-Aug-22 15-Jun-23 0.00 168 WC1-MAT-1202 Misc. Hardware Fabrication (Section WC1: Wc-149 to Wc-208)100%81.00 322.00 0.00 20-Aug-22 A 07-Jul-23 A 20-Aug-22 07-Jul-23 0.00 169 WC1-MAT-1200 Insulators Fabrication (Section WC1: Wc-149 to Wc-208)100%30.00 30.00 0.00 08-Jun-23 A 08-Jul-23 A 08-Jun-23 08-Jul-23 0.00 170 Delivery and AcceDelivery and AcceptanceDelivery and Acceptance 489.27 121.00 7.00 02-Apr-23 A 03-Aug-24 4.53 02-Apr-23 03-Aug-24 0.00 171 WA2-MAT-1220 Insulator Material Delivery and Acceptance (Section WA2: Wa-1 to Wa-54) required by Apr 15 100%9.00 9.00 0.00 02-Apr-23 A 10-Apr-23 A 02-Apr-23 10-Apr-23 0.00 172 WC1-MAT-1205 Insulator Material Delivery + Accepteance (Section WC1: Wc-149 to Wc-208)100%14.00 10.00 0.00 01-Jul-23 A 11-Jul-23 A 01-Jul-23 11-Jul-23 0.00 173 WC1-MAT-1215 Misc HW Material Delivery + Accepteance (Section WC1: Wc-149 to Wc-208)100%14.00 10.00 0.00 01-Jul-23 A 11-Jul-23 A 01-Jul-23 11-Jul-23 0.00 174 WA2-MAT-1230 Misc. Hardware Material Delivery and Acceptance (Section WA2: Wa-1 to Wa-54)100%2.00 101.00 0.00 02-Apr-23 A 11-Jul-23 A 02-Apr-23 11-Jul-23 0.00 175 Material Hauling toMaterial Hauling to SiteMaterial Hauling to Site 429.27 43.00 7.00 19-Jun-23 A 03-Aug-24 4.53 19-Jun-23 03-Aug-24 0.00 176 WA2-MAT-1240 Material Hauling - Insulators (Section WA2: Wa-1 to Wa-54) required by Apr 15 100%5.00 12.00 0.00 19-Jun-23 A 30-Jun-23 A 19-Jun-23 30-Jun-23 0.00 177 Crew 2 Material Hauling - HW (Section WA2: Wa-1 to Wa-54)100%5.00 43.00 0.00 19-Jun-23 A 31-Jul-23 A 19-Jun-23 31-Jul-23 0.00 178 WC1-MAT-1225 Material Hauling (Section WC1: Wc-149 to Wc-208)0%7.00 0.00 7.00 27-Jul-24 03-Aug-24 4.53 27-Jul-24 03-Aug-24 0.00 179 WC1-MAT-1235 Material Hauling (Section WC1: Wc-149 to Wc-208)0%7.00 0.00 7.00 27-Jul-24 03-Aug-24 4.53 27-Jul-24 03-Aug-24 0.00 180 Priority Order 2Priority Order 2Priority Order 2 755.50 681.00 103.25 20-Aug-22 A 12-Oct-24 1.83 20-Aug-22 12-Oct-24 0.00 181 Misc. HardwareMisc. HardwareMisc. Hardware 755.50 681.00 103.25 20-Aug-22 A 12-Oct-24 1.83 20-Aug-22 12-Oct-24 0.00 182 FabricationFabricationFabrication 140.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 183 ALL-MAT-1235 Misc. Hardware Fabrication to second delivery 100%140.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 184 Delivery & AcceptaDelivery & AcceptanceDelivery & Acceptance 389.41 331.92 103.25 04-Aug-23 A 12-Oct-24 1.83 04-Aug-23 12-Oct-24 0.00 185 WA4-MAT-1240 Material Delivery and Acceptance (Section WA4: Wa-227 to Wa-55)100%14.00 8.00 0.00 04-Aug-23 A 12-Aug-23 A 04-Aug-23 12-Aug-23 0.00 186 AF5-MAT-1250 Material Delivery and Acceptance (Section AF5: AF-1 to AF-31)100%14.00 14.00 0.00 14-Sep-23 A 28-Sep-23 A 14-Sep-23 28-Sep-23 0.00 187 WA3-MAT-1230 Material Delivery and Acceptance (Section WA3: Wa-344 (SB) to Wa-227) due July 8 100%14.00 11.00 0.00 01-Oct-23 A 11-Oct-23 A 01-Oct-23 11-Oct-23 0.00 188 WC6-MAT-1260 Material Delivery and Acceptance (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa))100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 189 WC7-MAT-1270 Material Delivery and Acceptance (Section WC7: Wc-49B (Amasa) to Wc-149)100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 190 WC8-MAT-1280 Material Delivery and Acceptance (Section WC8: Wc-208 to Wc-267 (Heward))100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 191 WC9-MAT-1290 Material Delivery and Acceptance (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward))100%21.00 124.92 0.00 20-Oct-23 A 21-Feb-24 A 20-Oct-23 21-Feb-24 0.00 192 Material Hauling tMaterial Hauling to SiteMaterial Hauling to Site 375.41 323.92 103.25 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 193 AF5-MAT-1280 Material Hauling (Section AF5: AF-1 to AF-31)100%7.00 26.00 0.00 09-Oct-23 A 03-Nov-23 A 09-Oct-23 03-Nov-23 0.00 194 WA3-MAT-1260 Material Hauling (Section WA3: Wa-344 (SB) to Wa-227)100%7.00 70.00 0.00 11-Oct-23 A 19-Dec-23 A 11-Oct-23 19-Dec-23 0.00 195 WC6-MAT-1290 Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa) 49/51 95%14.00 121.92 1.00 01-Mar-24 A 01-Jul-24 33.80 01-Mar-24 08-Jun-24 -23.19 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) (7/11), 07-Jul-24 Material Hauling Section WC8: Wc-208 to Wc-267 (Heward) (4/5), 29-Jul-24 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward) (2/5), 20-Aug-24 12-Oct-24, Material Procurement 12-Oct-24, Insulators and HW - Fabrication and Delivery 03-Aug-24, Priority Order 1 03-Aug-24, Delivery and Acceptance 03-Aug-24, Material Hauling to Site Material Hauling (Section WC1: Wc-149 to Wc-208), 03-Aug-24 Material Hauling (Section WC1: Wc-149 to Wc-208), 03-Aug-24 12-Oct-24, Priority Order 2 12-Oct-24, Misc. Hardware 12-Oct-24, Delivery & Acceptance 12-Oct-24, Material Hauling to Site Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa) 49/51, 01-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 4 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 196 WC7-MAT-1300 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) 44/101 40%14.00 41.92 7.00 20-May-24 A 07-Jul-24 33.80 22-May-24 05-Jun-24 -32.19 197 WC8-MAT-1310 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward)0%7.00 0.00 7.00 19-Aug-24 26-Aug-24 2.07 19-Aug-24 26-Aug-24 0.00 198 WC9-MAT-1320 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward)0%14.00 0.00 14.00 30-Aug-24 13-Sep-24 0.32 30-Aug-24 13-Sep-24 0.00 199 WA4-MAT-1270 Material Hauling (Section WA4: Wa-227 to Wa-55)80%14.00 323.92 14.00 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 200 25KIP Insulators25KIP Insulators25KIP Insulators 755.50 681.00 103.25 20-Aug-22 A 12-Oct-24 1.83 20-Aug-22 12-Oct-24 0.00 201 FabricationFabricationFabrication 154.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 202 ALL-MAT-1225 25KIP Insulators Fabrication to second delivery 100%154.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 203 Delivery & AcceptaDelivery & AcceptanceDelivery & Acceptance 396.41 334.92 103.25 01-Aug-23 A 12-Oct-24 1.83 01-Aug-23 12-Oct-24 0.00 204 WA4-MAT-1250 Material Delivery and Acceptance (Section WA4: Wa-227 to Wa-55)100%21.00 11.00 0.00 01-Aug-23 A 12-Aug-23 A 01-Aug-23 12-Aug-23 0.00 205 AF5-MAT-1260 Material Delivery and Acceptance (Section AF5: AF-1 to AF-31)100%14.00 14.00 0.00 15-Sep-23 A 29-Sep-23 A 15-Sep-23 29-Sep-23 0.00 206 WA3-MAT-1240 Material Delivery and Acceptance (Section WA3: Wa-344 (SB) to Wa-227)100%21.00 11.00 0.00 01-Oct-23 A 11-Oct-23 A 01-Oct-23 11-Oct-23 0.00 207 WC6-MAT-1270 Material Delivery and Acceptance (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa))100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 208 WC7-MAT-1280 Material Delivery and Acceptance (Section WC7: Wc-49B (Amasa) to Wc-149)100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 209 WC8-MAT-1290 Material Delivery and Acceptance (Section WC8: Wc-208 to Wc-267 (Heward))100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 210 WC9-MAT-1300 Material Delivery and Acceptance (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward))100%21.00 132.92 0.00 20-Oct-23 A 29-Feb-24 A 20-Oct-23 29-Feb-24 0.00 211 Material Hauling tMaterial Hauling to SiteMaterial Hauling to Site 375.41 323.92 103.25 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 212 AF5-MAT-1290 Material Hauling (Section AF5: AF-1 to AF-31)100%7.00 32.92 0.00 02-Oct-23 A 03-Nov-23 A 02-Oct-23 03-Nov-23 0.00 213 WA3-MAT-1270 Material Hauling (Section WA3: Wa-344 (SB) to Wa-227)100%7.00 71.00 0.00 11-Oct-23 A 20-Dec-23 A 11-Oct-23 20-Dec-23 0.00 214 WC6-MAT-1300 Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa)70%14.00 121.92 2.00 01-Mar-24 A 02-Jul-24 33.80 01-Mar-24 08-Jun-24 -24.19 215 WC7-MAT-1310 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149)40%14.00 41.92 7.00 20-May-24 A 07-Jul-24 33.80 22-May-24 05-Jun-24 -32.19 216 WC8-MAT-1320 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward)0%7.00 0.00 7.00 19-Aug-24 26-Aug-24 2.07 19-Aug-24 26-Aug-24 0.00 217 WC9-MAT-1330 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward)0%14.00 0.00 14.00 30-Aug-24 13-Sep-24 0.32 30-Aug-24 13-Sep-24 0.00 218 Crew 2 Material Hauling (Section WA4: Wa-227 to Wa-55)80%14.00 323.92 7.00 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 219 50KIP Insulators50KIP Insulators50KIP Insulators 755.50 681.00 103.25 20-Aug-22 A 12-Oct-24 1.83 20-Aug-22 12-Oct-24 0.00 220 FabricationFabricationFabrication 200.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 221 ALL-MAT-1280 I50KIP Insulators Fabrication (Balance) Mar 7 100%200.00 346.00 0.00 20-Aug-22 A 31-Jul-23 A 20-Aug-22 31-Jul-23 0.00 222 Delivery & AcceptaDelivery & AcceptanceDelivery & Acceptance 396.41 334.92 103.25 01-Aug-23 A 12-Oct-24 1.83 01-Aug-23 12-Oct-24 0.00 223 WA4-MAT-1260 Material Delivery and Acceptance (Section WA4: Wa-227 to Wa-55)100%21.00 11.00 0.00 01-Aug-23 A 12-Aug-23 A 01-Aug-23 12-Aug-23 0.00 224 AF5-MAT-1270 Material Delivery and Acceptance (Section AF5: AF-1 to AF-31)100%14.00 14.00 0.00 15-Sep-23 A 29-Sep-23 A 15-Sep-23 29-Sep-23 0.00 225 WA3-MAT-1250 Material Delivery and Acceptance (Section WA3: Wa-344 (SB) to Wa-227)100%7.00 7.00 0.00 01-Oct-23 A 07-Oct-23 A 01-Oct-23 07-Oct-23 0.00 226 WC6-MAT-1280 Material Delivery and Acceptance (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa))100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 227 WC7-MAT-1290 Material Delivery and Acceptance (Section WC7: Wc-49B (Amasa) to Wc-149)100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 228 WC8-MAT-1300 Material Delivery and Acceptance (Section WC8: Wc-208 to Wc-267 (Heward)100%21.00 103.00 0.00 19-Aug-23 A 30-Nov-23 A 19-Aug-23 30-Nov-23 0.00 229 WC9-MAT-1310 Material Delivery and Acceptance (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward)100%21.00 132.92 0.00 20-Oct-23 A 29-Feb-24 A 20-Oct-23 29-Feb-24 0.00 230 Material Hauling tMaterial Hauling to SiteMaterial Hauling to Site 375.41 323.92 103.25 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 231 AF5-MAT-1300 Material Hauling (Section AF5: AF-1 to AF-31)100%7.00 32.92 0.00 02-Oct-23 A 03-Nov-23 A 02-Oct-23 03-Nov-23 0.00 232 WA3-MAT-1280 Material Hauling (Section WA3: Wa-344 (SB) to Wa-227)100%7.00 70.00 0.00 11-Oct-23 A 19-Dec-23 A 11-Oct-23 19-Dec-23 0.00 233 WC6-MAT-1310 Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa)70%14.00 121.92 2.00 01-Mar-24 A 02-Jul-24 33.80 01-Mar-24 08-Jun-24 -24.19 234 WC7-MAT-1320 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149)40%14.00 41.92 7.00 20-May-24 A 07-Jul-24 33.80 22-May-24 05-Jun-24 -32.19 235 WC8-MAT-1330 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward)0%7.00 0.00 7.00 19-Aug-24 26-Aug-24 2.07 19-Aug-24 26-Aug-24 0.00 236 WC9-MAT-1340 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward)0%14.00 0.00 14.00 30-Aug-24 13-Sep-24 0.32 30-Aug-24 13-Sep-24 0.00 237 WA4-MAT-1290 Material Hauling (Section WA4: Wa-227 to Wa-55)80%14.00 323.92 7.00 12-Aug-23 A 12-Oct-24 1.83 12-Aug-23 12-Oct-24 0.00 238 Milestones + SummaMilestones + Summary ActivitiesMilestones + Summary Activities 5187.45 576.00 137.62 20-Jul-22 A 15-Dec-24 0.38 20-Jul-22 15-Dec-24 0.00 239 ALL-SUM-1060 Misc Projected Manhours Used from Oct 23 - Dec 31, 2023 (CO-4)100%4806.45 49.00 23-Oct-23 A 31-Dec-23 A 23-Oct-23 31-Dec-23 0.00 240 ALL-SUM-1000 Project Management / Overhead 70%615.00 554.00 99.45 15-Aug-22 A 29-Oct-24 0.35 15-Aug-22 29-Oct-24 0.00 241 ALL-SUM-1050 Evironmental / SWPPP Controls / BMP / Road Mainenance / Watering 70%605.00 554.00 99.45 15-Aug-22 A 29-Oct-24 0.35 15-Aug-22 29-Oct-24 0.00 242 Element 2 SummarElement 2 Summary- 1WcElement 2 Summary- 1Wc 701.00 576.00 125.00 20-Jul-22 A 30-Nov-24 0.00 20-Jul-22 30-Nov-24 0.00 243 EL2-SUM-1100 Engineering and Design Procurement Support Summary 100%27.00 27.00 0.00 20-Jul-22 A 19-Aug-22 A 20-Jul-22 19-Aug-22 0.00 244 EL2-SUM-9000 Element 2 - Mobilization Payment (80%)100%28.00 28.00 0.00 15-Aug-22 A 15-Sep-22 A 15-Aug-22 15-Sep-22 0.00 245 EL2-SUM-9010 Element 2 - Mobilization (20%) (to start of last mobilization WC9)100%307.00 345.00 0.00 15-Aug-22 A 05-Oct-23 A 15-Aug-22 05-Oct-23 0.00 246 (1) 1Wc-148 to 1W(1) 1Wc-148 to 1Wc-209 (66str)(1) 1Wc-148 to 1Wc-209 (66str)597.45 554.00 51.45 15-Aug-22 A 03-Sep-24 8.69 15-Aug-22 23-Aug-24 -8.00 247 SummarySummarySummary 597.45 554.00 51.45 15-Aug-22 A 03-Sep-24 8.69 15-Aug-22 23-Aug-24 -8.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149) 44/101, 07-Jul-24 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward), 26-Aug-24 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward), 13-Sep-24 Material Hauling (Section WA4: Wa-227 to Wa-55), 12-Oct-24 12-Oct-24, 25KIP Insulators 12-Oct-24, Delivery & Acceptance 12-Oct-24, Material Hauling to Site Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa), 02-Jul-24 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149), 07-Jul-24 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward), 26-Aug-24 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward), 13-Sep-24 Material Hauling (Section WA4: Wa-227 to Wa-55), 12-Oct-24 12-Oct-24, 50KIP Insulators 12-Oct-24, Delivery & Acceptance 12-Oct-24, Material Hauling to Site Material Hauling (Section WC6: Wc-1 (DJ) to Wc-49B (Amasa), 02-Jul-24 Material Hauling (Section WC7: Wc-49B (Amasa) to Wc-149), 07-Jul-24 Material Hauling (Section WC8: Wc-208 to Wc-267 (Heward), 26-Aug-24 Material Hauling (Section WC9: Wc-7/2 (SB) to Wc-268 (Heward), 13-Sep-24 Material Hauling (Section WA4: Wa-227 to Wa-55), 12-Oct-24 15-Dec-24, Milestones + Summary Activities Pro ject Management / Overhead, 29-Oct-24 Evironmental / SWPPP Controls / BMP / Road Mainenance / Watering, 29-Oct-2 30-Nov-24, Element 2 Summary- 1Wc 03-Sep-24, (1) 1Wc-148 to 1Wc-209 (66str) 03-Sep-24, Summary Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 5 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 248 WC1-SUM-1170 Stringing Crew for Cut In (29 person crew)100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 A 01-Nov-23 01-Nov-23 0.00 249 WC1-SUM-1150 Structure Setting Crew Outage (6 person crew)100%2.37 0.37 0.00 01-Nov-23 A 01-Nov-23 A 01-Nov-23 01-Nov-23 0.00 250 WC1-SUM-1120 Access Summary (1x29-person crew) (66/66)100%4.00 370.00 0.00 03-Oct-22 A 11-Jan-24 A 03-Oct-22 11-Jan-24 0.00 251 WC1-SUM-1126 Drilled Pier Foundations Summary (10/12)83%21.00 184.00 04-Nov-23 A 15-Jul-24 12.53 04-Nov-23 15-Jul-24 0.00 252 WC1-SUM-1130 Structure Framing Summary (54/66)82%19.00 259.00 38.20 09-Aug-23 A 17-Aug-24 1.63 09-Aug-23 17-Aug-24 0.00 253 WC1-SUM-1140 Structure Setting Crew (37/66)56%22.00 175.00 39.70 14-Nov-23 A 19-Aug-24 0.33 14-Nov-23 19-Aug-24 0.00 254 WC1-SUM-1160 Stringing Crew (0/66)0%35.20 0.00 35.20 13-Jul-24 23-Aug-24 2.33 20-Jul-24 23-Aug-24 0.00 255 WC1-SUM-1110 Project Management / OH Summary 64%363.00 554.00 51.45 15-Aug-22 A 03-Sep-24 8.69 15-Aug-22 12-Aug-24 -18.25 256 WC1-SUM-1105 Engineering and Design Project Support Summary 64%363.00 554.00 51.45 15-Aug-22 A 03-Sep-24 8.69 15-Aug-22 12-Aug-24 -18.25 257 (6) 1Wc-1 (Dave Jo(6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa)(51str)(6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa)(51str)677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 59.00 15-Aug-22 19-Sep-24 0.00 258 MilestonesMilestonesMilestones 0.00 0.00 0.00 19-Sep-24 19-Sep-24 59.00 19-Sep-24 19-Sep-24 0.00 259 WC6-MS-6040 1Wc: Dave Johnson to Amassa SS Substantial Completion (updated to Nov 30, 2024) 0%0.00 0.00 0.00 19-Sep-24 59.00 19-Sep-24 0.00 260 SummarySummarySummary 677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 261 WC6-SUM-6130 Access Summary (1x8-person crews) (52/52)100%8.00 211.00 0.00 15-May-23 A 08-Feb-24 A 15-May-23 08-Feb-24 0.00 262 WC6-SUM-6150 Drilled Pier Foundations Summary (7/7)100%95.00 64.00 0.00 04-Dec-23 A 08-Mar-24 A 04-Dec-23 08-Mar-24 0.00 263 WC6-SUM-6160 Structure Framing Summary (49/51)96%128.88 118.66 61.00 13-Feb-24 A 13-Sep-24 0.33 13-Feb-24 13-Sep-24 0.00 264 WC6-SUM-6190 Structure Salvage (49/51)96%128.67 119.32 61.35 12-Feb-24 A 14-Sep-24 1.58 12-Feb-24 14-Sep-24 0.00 265 WC6-SUM-6180 Stringing Crew (49/51)96%91.61 59.21 61.40 22-Apr-24 A 14-Sep-24 0.33 25-May-24 14-Sep-24 0.00 266 WC6-SUM-6170 Structure Setting Crew (49/51)96%130.68 118.96 62.00 13-Feb-24 A 14-Sep-24 1.33 13-Feb-24 14-Sep-24 0.00 267 WC6-SUM-6120 Project Management / OH Summary 97%677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 268 WC6-SUM-6110 Engineering and Design Project Support Summary 97%677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 269 (7) 1Wc-49B (Amas(7) 1Wc-49B (Amassa) to 1Wc-148(101str)(7) 1Wc-49B (Amassa) to 1Wc-148(101str)677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 59.00 15-Aug-22 19-Sep-24 0.00 270 MilestonesMilestonesMilestones 0.00 0.00 0.00 19-Sep-24 19-Sep-24 59.00 19-Sep-24 19-Sep-24 0.00 271 WC7-MS-7040 Amassa – 1 Wc 148 Substantial Completion (updated to Nov 30, 2024)0%0.00 0.00 0.00 19-Sep-24 59.00 19-Sep-24 0.00 272 SummarySummarySummary 677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 273 WC7-SUM-7130 Access Summary (1x8-person crews) (97/101)96%37.00 506.00 5.00 10-Oct-22 A 09-Jul-24 23.58 10-Oct-22 08-Jul-24 -1.00 274 WC7-SUM-7160 Structure Framing Summary (44/101)44%57.69 40.65 16.74 14-May-24 A 23-Jul-24 36.79 15-May-24 25-Jul-24 2.00 275 WC7-SUM-7150 Drilled Pier Foundations Summary (6/11)55%76.00 112.00 24.00 21-Feb-24 A 31-Jul-24 27.00 01-May-24 31-Jul-24 0.00 276 WC7-SUM-7190 Structure Salvage (44/101)44%103.20 42.00 61.20 12-May-24 A 14-Sep-24 1.53 06-May-24 14-Sep-24 0.00 277 WC7-SUM-7170 Structure Setting Crew(44/101)44%87.05 31.70 61.80 24-May-24 A 14-Sep-24 1.33 18-May-24 14-Sep-24 0.00 278 WC7-SUM-7180 Stringing Crew (39/101)39%89.50 29.50 66.00 27-May-24 A 19-Sep-24 0.33 05-Jun-24 19-Sep-24 0.00 279 WC7-SUM-7120 Project Management / OH Summary 55%677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 280 WC7-SUM-7110 Engineering and Design Project Support Summary 55%677.00 554.00 66.00 15-Aug-22 A 19-Sep-24 0.33 15-Aug-22 19-Sep-24 0.00 281 (8) 1Wc-209 to1Wc(8) 1Wc-209 to1Wc-267 (Heward)(60str)(8) 1Wc-209 to1Wc-267 (Heward)(60str)677.00 554.00 60.45 15-Aug-22 A 13-Sep-24 64.55 15-Aug-22 13-Sep-24 0.00 282 MilestonesMilestonesMilestones 0.00 0.00 0.00 13-Sep-24 13-Sep-24 64.55 13-Sep-24 13-Sep-24 0.00 283 WC8-MS-8040 Wc-209 to Heward Substantial Completion (updated to Nov 30, 2024)0%0.00 0.00 0.00 13-Sep-24 64.55 13-Sep-24 0.00 284 SummarySummarySummary 677.00 554.00 60.45 15-Aug-22 A 13-Sep-24 0.33 15-Aug-22 13-Sep-24 0.00 285 WC8-SUM-8130 Access Summary (1x8-person crews) (60/60)100%24.00 60.00 0.00 23-Jul-23 A 30-Sep-23 A 23-Jul-23 30-Sep-23 0.00 286 WC8-SUM-8150 Drilled Pier Foundations Summary (5/6)80%23.00 139.00 23.00 20-Jan-24 A 30-Jul-24 28.00 20-Jan-24 30-Jul-24 0.00 287 WC8-SUM-8190 Structure Salvage Summary 0%15.00 0.00 15.00 30-Jul-24 16-Aug-24 15.83 30-Jul-24 16-Aug-24 0.00 288 WC8-SUM-8160 Structure Framing Summary (5-7 person crew)0%20.00 0.00 20.00 01-Aug-24 24-Aug-24 8.78 01-Aug-24 24-Aug-24 0.00 289 WC8-SUM-8170 Structure Setting Crew (6 person crew)0%27.50 0.00 27.50 02-Aug-24 05-Sep-24 0.33 02-Aug-24 05-Sep-24 0.00 290 WC8-SUM-8180 Stringing Crew (29 person crew)0%14.75 0.00 14.75 26-Aug-24 13-Sep-24 0.33 26-Aug-24 13-Sep-24 0.00 291 WC8-SUM-8120 Project Management / OH Summary 15%677.00 554.00 60.45 15-Aug-22 A 13-Sep-24 0.33 15-Aug-22 13-Sep-24 0.00 292 WC8-SUM-8110 Engineering and Design Project Support Summary 15%677.00 554.00 60.45 15-Aug-22 A 13-Sep-24 0.33 15-Aug-22 13-Sep-24 0.00 293 (9) 1Wc-268 (Hewa(9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin)(83str)(9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin)(83str)701.00 576.00 125.00 20-Jul-22 A 30-Nov-24 0.00 20-Jul-22 30-Nov-24 0.00 294 MilestonesMilestonesMilestones 0.00 0.00 0.00 30-Nov-24 30-Nov-24 0.55 30-Nov-24 30-Nov-24 0.00 295 WC9-MS-9040 Heward SS to Shirley Basin SS Substantial Completion (updated to Nov 30, 2024)0%0.00 0.00 0.00 30-Nov-24 0.55 30-Nov-24 0.00 296 SummarySummarySummary 699.00 576.00 97.45 20-Jul-22 A 26-Oct-24 0.35 20-Jul-22 26-Oct-24 0.00 297 WC9-SUM-9100 Engineering and Design Procurement Support Summary 100%27.00 27.00 0.00 20-Jul-22 A 19-Aug-22 A 20-Jul-22 19-Aug-22 0.00 298 WC9-SUM-9130 Access Summary (1x8-person crews) (30/83)100%0.00 0.00 0.00 08-Sep-23 A 08-Sep-23 A 08-Sep-23 08-Sep-23 0.00 299 WC9-SUM-9160 Structure Framing Summary (5 person crew)0%37.74 0.00 37.74 01-Jul-24 16-Aug-24 46.36 17-Jun-24 16-Aug-24 0.00 300 WC9-SUM-9190 Structure Salvage 0%37.74 0.00 37.74 01-Jul-24 16-Aug-24 46.36 17-Jun-24 16-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Drilled Pier Foundations Summary (10/12), 15-Jul-24 Structure Framing Summary (54/66), 17-Aug-24 Structure Setting Crew (37/66), 19-Aug-24 13-Jul-24 Stringing Crew (0/66), 23-Aug-24 Project Management / OH Summary, 03-Sep-24 Engineering and Design Project Support Summary, 03-Sep-24 19-Sep-24, (6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa)(51str) 19-Sep-24, Milestones 1Wc: Dave Johnson to Amassa SS Substantial Completion (updated to Nov 30, 2024), 19-Sep-24, Summary Structure Framing Summary (49/51), 13-Sep-24 Structure Salvage (49/51), 14-Sep-24 Stringing Crew (49/51), 14-Sep-24 Structure Setting Crew (49/51), 14-Sep-24 Project Management / OH Summary, 19-Sep-24 Engineering and Design Project Support Summary, 19-Sep-24 19-Sep-24, (7) 1Wc-49B (Amassa) to 1Wc-148(101str) 19-Sep-24, Milestones Amassa – 1 Wc 148 Substantial Completion (updated to Nov 30, 2024), 19-Sep-24 19-Sep-24, Summary Access Summary (1x8-person crews) (97/101), 09-Jul-24 Structure Framing Summary (44/101), 23-Jul-24 Drilled Pier Foundations Summary (6/11), 31-Jul-24 Structure Salvage (44/101), 14-Sep-24 Structure Setting Crew(44/101), 14-Sep-24 A Stringing Crew (39/101), 19-Sep-24 Project Management / OH Summary, 19-Sep-24 Engineering and Design Project Support Summary, 19-Sep-24 13-Sep-24, (8) 1Wc-209 to1Wc-267 (Heward)(60str) 13-Sep-24, Milestones Wc-209 to Heward Substantial Completion (updated to Nov 30, 2024), 13-Sep-24 13-Sep-24, Summary Drilled Pier Foundations Summary (5/6), 30-Jul-24 30-Jul-24 Structure Salvage Summary, 16-Aug-24 01-Aug-24 Structure Framing Summary (5-7 person crew), 24-Aug-24 02-Aug-24 Structure Setting Crew (6 person crew), 05-Sep-24 26-Aug-24 Stringing Crew (29 person crew), 13-Sep-24 Project Management / OH Summary, 13-Sep-24 Engineering and Design Project Support Summary, 13-Sep-24 30-Nov-24, (9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin)(83str) 30-Nov-24, Milestones Heward SS to Shirley Basin SS Substantial Completion (updated to Nov 30 26-Oct-24, Summary -Jul-24 Structure Framing Summary (5 person crew), 16-Aug-24 -Jul-24 Structure Salvage, 16-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 6 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 301 WC9-SUM-9150 Drilled Pier Foundations Summary (2/5)40%14.00 157.00 39.00 08-Dec-23 A 17-Aug-24 41.30 08-Dec-23 17-Aug-24 0.00 302 WC9-SUM-9170 Structure Setting Crew (6 person crew)0%19.00 0.00 19.00 10-Aug-24 31-Aug-24 33.80 10-Aug-24 31-Aug-24 0.00 303 WC9-SUM-9180 Stringing Crew (29 person crew)0%37.00 0.00 37.00 13-Sep-24 26-Oct-24 0.35 13-Sep-24 26-Oct-24 0.00 304 WC9-SUM-9120 Project Management / OH Summary 12%677.00 554.00 97.45 15-Aug-22 A 26-Oct-24 0.35 15-Aug-22 26-Oct-24 0.00 305 WC9-SUM-9110 Engineering and Design Project Support Summary 12%677.00 554.00 97.45 15-Aug-22 A 26-Oct-24 0.35 15-Aug-22 26-Oct-24 0.00 306 Element 1 SummarElement 1 Summary - 1WaElement 1 Summary - 1Wa 713.62 576.00 137.62 20-Jul-22 A 15-Dec-24 0.38 20-Jul-22 15-Dec-24 0.00 307 EL1-SUM-9070 Engineering and Design Procurement Support Summary 100%27.00 27.00 0.00 20-Jul-22 A 19-Aug-22 A 20-Jul-22 19-Aug-22 0.00 308 EL1-SUM-9020 Element 1 - Mobilization (80%)100%0.00 0.00 0.00 27-Sep-22 A 27-Sep-22 0.00 309 EL1-SUM-9030 Element 1 - Mobilization (20%)100%214.00 208.00 0.00 27-Sep-22 A 10-Jun-23 A 27-Sep-22 10-Jun-23 0.00 310 (2) Wa-1 (Windstar(2) Wa-1 (Windstar) to 1Wa-54 (56str)(2) Wa-1 (Windstar) to 1Wa-54 (56str)486.00 389.00 0.00 15-Aug-22 A 28-Nov-23 A 15-Aug-22 28-Nov-23 0.00 311 MilestonesMilestonesMilestones 0.00 0.00 0.00 26-Jun-23 A 26-Jun-23 A 26-Jun-23 26-Jun-23 0.00 312 WA2-MS-2040 Windstar SS to 1 Wa-54 Substantial Completion 100%0.00 0.00 0.00 26-Jun-23 A 26-Jun-23 0.00 313 SummarySummarySummary 486.00 389.00 0.00 15-Aug-22 A 28-Nov-23 A 15-Aug-22 28-Nov-23 0.00 314 WA2-SUM-2130 Access Summary (1x8-person crews) (55/55)100%21.00 49.00 0.00 17-Oct-22 A 15-Dec-22 A 17-Oct-22 15-Dec-22 0.00 315 WA2-SUM-2120 Project Management / OH Summary 100%486.00 252.00 0.00 15-Aug-22 A 20-Jun-23 A 15-Aug-22 20-Jun-23 0.00 316 WA2-SUM-2110 Engineering and Design Project Support Summary 100%486.00 258.00 0.00 15-Aug-22 A 26-Jun-23 A 15-Aug-22 26-Jun-23 0.00 317 WA2-SUM-2160 Structure Framing Summary (5-7 person crew) (55/55) deadends remain to be framed by setting crew 100%16.00 206.00 0.00 15-Nov-22 A 27-Jul-23 A 15-Nov-22 27-Jul-23 0.00 318 WA2-SUM-2140 Direct Embed Foundations Summary (2 person crew) (41/41)100%39.00 195.00 0.00 13-Dec-22 A 08-Aug-23 A 13-Dec-22 08-Aug-23 0.00 319 WA2-SUM-2150 Drilled Pier Foundations Summary (15 person crew) (13/13)100%86.00 174.00 0.00 23-Jan-23 A 12-Aug-23 A 23-Jan-23 12-Aug-23 0.00 320 WA2-SUM-2170 Structure Setting Crew (6 person crew) (49/55)100%102.00 168.00 0.00 07-Feb-23 A 21-Aug-23 A 07-Feb-23 21-Aug-23 0.00 321 WA2-SUM-2180 Stringing Crew (29 person crew) (55/55) Substation Tie In remains 100%73.00 137.00 0.00 20-Jun-23 A 28-Nov-23 A 20-Jun-23 28-Nov-23 0.00 322 (3) 1Wa-1Wa-227 - (3) 1Wa-1Wa-227 - 344 (Shirley Basin) (118str)(3) 1Wa-1Wa-227 - 344 (Shirley Basin) (118str)570.50 554.00 16.50 15-Aug-22 A 23-Jul-24 98.50 15-Aug-22 23-Jul-24 0.00 323 MilestonesMilestonesMilestones 0.00 0.00 0.00 23-Jul-24 23-Jul-24 99.50 23-Jul-24 23-Jul-24 0.00 324 WA3-MS-3040 1 Wa-344 - 1 Wa-227 Substantial Completion (Includes SB-TB Flats)0%0.00 0.00 0.00 23-Jul-24 99.50 23-Jul-24 0.00 325 SummarySummarySummary 517.00 554.00 14.50 15-Aug-22 A 20-Jul-24 9.78 15-Aug-22 20-Jul-24 0.00 326 WA3-SUM-3103 Access Summary 1 (1x8-person crews) (118/118)100%19.00 40.00 0.00 01-Aug-23 A 15-Sep-23 A 01-Aug-23 15-Sep-23 0.00 327 Crew 2 Drilled Pier Foundations 1 Summary (15 person crew) (9/9)100%57.00 112.00 0.00 16-Oct-23 A 18-Mar-24 A 16-Oct-23 18-Mar-24 0.00 328 WA3-SUM-3106 Structure Framing Summary 1 (5 person crew) (117/118)99%23.00 253.00 8.00 16-Aug-23 A 12-Jul-24 16.28 16-Aug-23 12-Jul-24 0.00 329 WA3-SUM-3108 Structure Setting Crew 1 (6 person crew) (117/118)99%27.50 216.73 8.00 27-Sep-23 A 12-Jul-24 16.28 27-Sep-23 12-Jul-24 0.00 330 WA3-SUM-3109 Stringing Crew (29 person crew) (105/118)89%146.00 187.00 14.50 01-Nov-23 A 20-Jul-24 0.33 01-Nov-23 20-Jul-24 0.00 331 WA3-SUM-3102 Project Management / OH Summary 95%486.00 554.00 14.50 15-Aug-22 A 20-Jul-24 0.33 15-Aug-22 20-Jul-24 0.00 332 WA3-SUM-3101 Engineering and Design Project Support Summary 95%486.00 554.00 14.50 15-Aug-22 A 20-Jul-24 0.33 15-Aug-22 20-Jul-24 0.00 333 (4) 1Wa-55 - 226 (1(4) 1Wa-55 - 226 (172str)(4) 1Wa-55 - 226 (172str)691.62 554.00 137.62 15-Aug-22 A 15-Dec-24 0.38 15-Aug-22 15-Dec-24 0.00 334 MilestonesMilestonesMilestones 0.00 0.00 0.00 15-Dec-24 15-Dec-24 0.38 15-Dec-24 15-Dec-24 0.00 335 WA4-MS-4040 1 Wa-227 - 1 Wa-55 Substantial Completion (Req. Dec 15, 2023)0%0.00 0.00 0.00 15-Dec-24 0.38 15-Dec-24 0.00 336 SummarySummarySummary 639.18 554.00 137.62 15-Aug-22 A 15-Dec-24 0.38 15-Aug-22 15-Dec-24 0.00 337 WA4-SUM-4103 Access Summary 2 (1x8-person crew) (150/150)100%218.00 206.00 0.00 29-Sep-22 A 10-Jun-23 A 29-Sep-22 10-Jun-23 0.00 338 WA4-SUM-4105 Drilled Pier Foundations 2 Summary (15 person crew) (20/22)91%90.00 290.00 9.00 04-Jul-23 A 13-Jul-24 24.28 04-Jul-23 13-Jul-24 0.00 339 WA4-SUM-1180 Structure Salvage (0/58)0%19.18 0.00 19.18 20-Sep-24 12-Oct-24 0.82 20-Sep-24 12-Oct-24 0.00 340 WA4-SUM-4106 Structure Framing Summary 2 (5 person crew) (119/172)69%88.00 332.00 88.57 16-May-23 A 16-Oct-24 14.93 16-May-23 16-Oct-24 0.00 341 WA4-SUM-4107 Structure Setting Crew 2 (6 person crew) (119/172)69%107.00 308.00 103.17 13-Jun-23 A 02-Nov-24 0.83 13-Jun-23 02-Nov-24 0.00 342 WA4-SUM-4108 Stringing Crew (29 person crew) (115/172 fully clipped in)67%107.27 246.00 112.67 24-Aug-23 A 13-Nov-24 0.33 24-Aug-23 13-Nov-24 0.00 343 WA4-SUM-4102 Project Management / OH Summary 85%486.00 554.00 137.62 15-Aug-22 A 15-Dec-24 0.38 15-Aug-22 15-Dec-24 0.00 344 WA4-SUM-4101 Engineering and Design Project Support Summary 85%486.00 554.00 137.62 15-Aug-22 A 15-Dec-24 0.38 15-Aug-22 15-Dec-24 0.00 345 Element 3 SummarElement 3 Summary- Aeolus to FreezeoutElement 3 Summary- Aeolus to Freezeout 658.00 576.00 49.50 20-Jul-22 A 30-Aug-24 0.50 20-Jul-22 30-Aug-24 0.00 346 EL3-SUM-9040 Element 3 - Mobilization (80%)100%0.00 0.00 0.00 27-Sep-22 A 27-Sep-22 0.00 347 EL3-SUM-9050 Element 3 - Mobilization (20%) (to start of last mobilization AF5 Apr 17, 2023)100%220.00 286.00 0.00 27-Sep-22 A 11-Sep-23 A 27-Sep-22 11-Sep-23 0.00 348 (5) AF-1 to AF-31 ((5) AF-1 to AF-31 (31str)(5) AF-1 to AF-31 (31str)658.00 576.00 49.50 20-Jul-22 A 30-Aug-24 0.50 20-Jul-22 30-Aug-24 0.00 349 MilestonesMilestonesMilestones 0.00 0.00 0.00 30-Aug-24 30-Aug-24 0.50 30-Aug-24 30-Aug-24 0.00 350 AF5-MS-5040 Aeolus SS to Freezeout SS; Substantial Completion (Req. October 31, 2023)0%0.00 0.00 0.00 30-Aug-24 0.50 30-Aug-24 0.00 351 SummarySummarySummary 658.00 576.00 49.50 20-Jul-22 A 30-Aug-24 0.50 20-Jul-22 30-Aug-24 0.00 352 AF5-SUM-5100 Engineering and Design Procurement Support Summary 100%27.00 27.00 0.00 20-Jul-22 A 19-Aug-22 A 20-Jul-22 19-Aug-22 0.00 353 AF5-SUM-5103 Access Summary (1x8-person crew) (20/31)100%15.00 48.00 0.00 11-Sep-23 A 03-Nov-23 A 11-Sep-23 03-Nov-23 0.00 354 AF5-SUM-5105 Drilled Pier Foundations Summary (15 person crew) (6/6)100%9.00 34.00 0.00 08-Oct-23 A 16-Nov-23 A 08-Oct-23 16-Nov-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Drilled Pier Foundations Summary (2/5), 17-Aug-24 10-Aug-24 Structure Setting Crew (6 person crew), 31-Aug-24 13-Sep-24 Stringing Crew (29 person crew), 26-Oct-24 Project Management / OH Summary, 26-Oct-24 Engineering and Design Project Support Summary, 26-Oct-24 15-Dec-24, Element 1 Summary - 1Wa Windstar) to 1Wa-54 (56str) 26-Jun-23 A 23-Jul-24, (3) 1Wa-1Wa-227 - 344 (Shirley Basin) (118str) 23-Jul-24, Milestones 1 Wa-344 - 1 Wa-227 Substantial Completion (Includes SB-TB Flats), 23-Jul-24 20-Jul-24, Summary Structure Framing Summary 1 (5 person crew) (117 /118 ), 12-Jul-24 Structure Setting Crew 1 (6 person crew) (117/118), 12-Jul-24 Stringing Crew (29 person crew) (105/118), 20-Jul-24 Project Management / OH Summary, 20-Jul-24 Engineering and Design Project Support Summary, 20-Jul-24 15-Dec-24, (4) 1Wa-55 - 226 (172str) 15-Dec-24, Milestones 1 Wa-227 - 1 Wa-55 Substantial Completion (Req. Dec 15, 2023), 15-De 15-Dec-24, Summary Drilled Pier Foundations 2 Summary (15 person crew) (20/22), 13-Jul-24 20-Sep-24 Structure Salvage (0/58), 12-Oct-24 Structure Framing Summary 2 (5 person crew) (119 /172), 16-Oct-24 Structure Setting Crew 2 (6 person crew) (119/172), 02-Nov-24 Stringing Crew (29 person crew) (115/172 fully clipped in), 13-Nov-24 Project Management / OH Summary, 15-Dec-24 Engineering and Design Pro ject Support Summary, 15-Dec-24 30-Aug-24, Element 3 Summary- Aeolus to Freezeout 30-Aug-24, (5) AF-1 to AF-31 (31str) 30-Aug-24, Milestones Aeolus SS to Freezeout SS; Substantial Completion (Req. October 31, 2023), 30-Aug-24 30-Aug-24, Summary Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 7 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 355 AF5-SUM-5109 Structure Modifications(16 person crew)100%0.00 0.00 0.00 11-Mar-24 A 12-Mar-24 A 11-Mar-24 12-Mar-24 0.00 356 AF5-SUM-5106 Structure Framing Summary (5 person crew) (26/31)85%16.00 79.00 14.50 17-Oct-23 A 20-Jul-24 13.50 17-Oct-23 20-Jul-24 0.00 357 AF5-SUM-5107 Structure Setting Crew (6 person crew) (26/31)85%23.00 79.00 17.50 17-Oct-23 A 24-Jul-24 11.50 17-Oct-23 24-Jul-24 0.00 358 AF5-SUM-5108 Stringing Crew (29 person crew) (11/31)20%155.00 74.00 34.50 23-Oct-23 A 13-Aug-24 0.50 23-Oct-23 13-Aug-24 0.00 359 AF5-SUM-5102 Project Management / OH Summary 80%367.00 304.00 49.50 15-Aug-22 A 30-Aug-24 0.50 15-Aug-22 30-Aug-24 0.00 360 AF5-SUM-5101 Engineering and Design Project Support Summary 80%367.00 304.00 49.50 15-Aug-22 A 30-Aug-24 0.50 15-Aug-22 30-Aug-24 0.00 361 Gateway West D1 CoGateway West D1 ConstructionGateway West D1 Construction 910.00 554.00 356.00 15-Aug-22 A 09-Sep-25 0.00 15-Aug-22 09-Sep-25 0.00 362 Pre-Construction APre-Construction ActivitiesPre-Construction Activities 609.00 554.00 97.45 15-Aug-22 A 26-Oct-24 0.35 15-Aug-22 26-Oct-24 0.00 363 Construction MobConstruction MobilizationConstruction Mobilization 72.00 68.00 0.00 15-Aug-22 A 01-Nov-22 A 15-Aug-22 01-Nov-22 0.00 364 ALL-PRE-3000 Pre-Construction Mobilization & Site Orientations 100%72.00 68.00 0.00 15-Aug-22 A 01-Nov-22 A 15-Aug-22 01-Nov-22 0.00 365 Project SetupProject SetupProject Setup 30.00 183.00 0.00 15-Aug-22 A 30-Mar-23 A 15-Aug-22 30-Mar-23 0.00 366 ALL-PRE-3010 Setup Project Infrastructure; offices, laydown yards, temp power, etc.100%30.00 183.00 0.00 15-Aug-22 A 30-Mar-23 A 15-Aug-22 30-Mar-23 0.00 367 Construction StakConstruction StakingConstruction Staking 162.00 447.00 0.00 18-Aug-22 A 29-Feb-24 A 18-Aug-22 29-Feb-24 0.00 368 ALL-PRE-3020 Staking of Clearing and ROW Boundaries 100%24.00 24.00 0.00 18-Aug-22 A 14-Sep-22 A 18-Aug-22 14-Sep-22 0.00 369 ALL-PRE-3030 Initial Construction Layout, Confirmations and Rework (ongoing)100%150.00 435.00 0.00 01-Sep-22 A 29-Feb-24 A 01-Sep-22 29-Feb-24 0.00 370 Material ManagemeMaterial ManagementMaterial Management 609.00 554.00 97.45 15-Aug-22 A 26-Oct-24 0.35 15-Aug-22 26-Oct-24 0.00 371 ALL-PRE-3040 Material Management (In Yard) 3 person crew 0%609.00 554.00 97.45 15-Aug-22 A 26-Oct-24 0.35 15-Aug-22 26-Oct-24 0.00 372 Construction: ClienConstruction: Clients Elements 1, 2, 3, 5 (Sections 1, 2,3,4)Construction: Clients Elements 1, 2, 3, 5 (Sections 1, 2,3,4)652.62 515.00 131.62 29-Sep-22 A 15-Dec-24 218.38 29-Sep-22 15-Dec-24 0.00 373 AccessAccessAccess 289.00 373.00 0.00 29-Sep-22 A 11-Jan-24 A 29-Sep-22 11-Jan-24 0.00 374 WA4-MS-4000 1 Wa-227 - 1 Wa-55 Construction Start 100%0.00 0.00 0.00 29-Sep-22 A 29-Sep-22 0.00 375 WC1-MS-1000 1 Wc-149 to 1Wc-208 Start 100%0.00 0.00 0.00 03-Oct-22 A 03-Oct-22 0.00 376 WA4-ACS-4225 Access Installation Pull 14a: Wa-133 - Wa-143*SUBCONTRACTOR*100%12.00 12.00 0.00 29-Sep-22 A 12-Oct-22 A 29-Sep-22 12-Oct-22 0.00 377 WA2-MS-2000 Windstar SS to 1 Wa 54 Start Construction *Access Mobilization Oct 11*100%0.00 0.00 0.00 17-Oct-22 A 17-Oct-22 0.00 378 WA2-ACS-2200 Access Installation Pull 1a: Windstar - Wa-1 100%3.00 2.00 0.00 17-Oct-22 A 18-Oct-22 A 17-Oct-22 18-Oct-22 0.00 379 WA2-ACS-2210 Access Installation Pull 2a: Wa-1 - Wa-2 (1)100%3.00 5.00 0.00 17-Oct-22 A 21-Oct-22 A 17-Oct-22 21-Oct-22 0.00 380 WA2-ACS-2220 Access Installation Pull 3a: Wa-2 - Wa-4 (3)100%3.00 4.00 0.00 19-Oct-22 A 22-Oct-22 A 19-Oct-22 22-Oct-22 0.00 381 WA4-ACS-4205 Access Installation Pull 18a: Wa-201 - Wa-207 *SUBCONTRACTOR*100%5.00 5.00 0.00 27-Oct-22 A 01-Nov-22 A 27-Oct-22 01-Nov-22 0.00 382 WA2-ACS-2240 Access Installation Pull 5a: Wa-18 - Wa-26 (8/8)100%3.00 16.00 0.00 22-Oct-22 A 09-Nov-22 A 22-Oct-22 09-Nov-22 0.00 383 WA2-ACS-2230 Access Installation Pull 4a: Wa-4 - Wa-18 (154/15)100%2.00 47.00 0.00 20-Oct-22 A 31-Jan-23 A 20-Oct-22 31-Jan-23 0.00 384 WA2-ACS-2260 Access Installation Pull 7a: Wa-42 - Wa-45 (/3)100%3.00 3.00 0.00 04-May-23 A 06-May-23 A 04-May-23 06-May-23 0.00 385 WA2-ACS-2270 Access Installation Pull 8a: Wa-45 - Wa-53A *move to WA4*100%2.00 2.00 0.00 08-May-23 A 09-May-23 A 08-May-23 09-May-23 0.00 386 WA2-ACS-2250 Access Installation Pull 6a: Wa-26 - Wa-42 (/16)100%2.00 31.00 0.00 22-Oct-22 A 10-May-23 A 22-Oct-22 10-May-23 0.00 387 WC1-ACS-1200 Access Installation Pull 18c: Wc-149 - Wc165 (17/17) (Crew 2 - May 1 start, remob at WA3) 100%7.00 63.00 0.00 03-Oct-22 A 03-Jun-23 A 03-Oct-22 03-Jun-23 0.00 388 WA4-ACS-4250 Access Installation Pull 9a: Wa-53A - Wa-76 - note (23/23)100%4.00 24.00 0.00 15-May-23 A 10-Jun-23 A 15-May-23 10-Jun-23 0.00 389 WA4-ACS-4245 Access Installation Pull 10a: Wa-77 - Wa-100 - note (Crew 1 - start after May 1) (23/23) 100%4.00 34.00 0.00 10-May-23 A 17-Jun-23 A 10-May-23 17-Jun-23 0.00 390 WA4-ACS-4240 Access Installation Pull 11a: Wa-100 - Wa-106 (SUBCONTRACTOR- start here after Jul 15) 100%4.00 6.00 0.00 12-Jun-23 A 18-Jun-23 A 12-Jun-23 18-Jun-23 0.00 391 WA4-ACS-4210 Access Installation Pull 17a: Wa-189 - Wa-201 (SUBCONTRACTOR - move to WC7 14c) (6/12) 100%4.00 66.00 0.00 04-Oct-22 A 28-Jun-23 A 04-Oct-22 28-Jun-23 0.00 392 WC1-ACS-1240 Access Installation Pull 22c: Wc-204 - Wc208 *SUBCONTRACTOR* (4/4)100%4.00 5.00 0.00 26-Jun-23 A 30-Jun-23 A 26-Jun-23 30-Jun-23 0.00 393 WC1-ACS-1230 Access Installation Pull 21c: Wc-189A - Wc204 *SUBCONTRACTOR*(21/21)100%4.00 22.00 0.00 20-Jun-23 A 14-Jul-23 A 20-Jun-23 14-Jul-23 0.00 394 WC1-ACS-1250 Access Installation Pull 23c: Cutover to Line 1Wa *SUBCONTRACTOR- move to WA4* 100%1.00 1.00 0.00 19-Jul-23 A 19-Jul-23 A 19-Jul-23 19-Jul-23 0.00 395 WA4-ACS-4235 Access Installation Pull 12a: Wa-106 - Wa-116 (SUBCONTRACTOR)100%4.00 30.00 0.00 15-Jun-23 A 19-Jul-23 A 15-Jun-23 19-Jul-23 0.00 396 WA4-ACS-4200 Access Installation Pull 19a: Wa-207 - Wa-226 (Crew 2 - end) (20/20)100%5.00 7.00 0.00 20-Jul-23 A 28-Jul-23 A 20-Jul-23 28-Jul-23 0.00 397 WA3-MS-3000 1Wa-344 - 1Wa-227 Construction Start (after july 15)100%0.00 0.00 0.00 01-Aug-23 A 01-Aug-23 0.00 398 Access Installation Pull 29a: Wa-344 - Shirley Basin BG *start here after July 15*100%3.00 3.00 0.00 01-Aug-23 A 03-Aug-23 A 01-Aug-23 03-Aug-23 0.00 399 WA3-ACS-3210 Access Installation Pull 28a: Wa-340 - Wa-344 BG 100%3.00 5.00 0.00 04-Aug-23 A 09-Aug-23 A 04-Aug-23 09-Aug-23 0.00 400 WA3-ACS-3220 Access Installation Pull 27a: Wa-329 - Wa-340 BG 100%3.00 5.00 0.00 09-Aug-23 A 14-Aug-23 A 09-Aug-23 14-Aug-23 0.00 401 WA3-ACS-3230 Access Installation Pull 26a: Wa-323 - Wa-329 100%3.00 2.00 0.00 14-Aug-23 A 15-Aug-23 A 14-Aug-23 15-Aug-23 0.00 402 WA4-ACS-4230 Access Installation Pull 13a: Wa-117 - Wa-132 (SUBCONTRACTOR) (18/18)100%5.00 100.00 0.00 24-Oct-22 A 18-Aug-23 A 24-Oct-22 18-Aug-23 0.00 403 WA3-ACS-3240 Access Installation Pull 25a: Wa-304 - Wa-322 (19/19)100%3.00 5.00 0.00 28-Aug-23 A 01-Sep-23 A 28-Aug-23 01-Sep-23 0.00 404 WA4-ACS-4215 Access Installation Pull 16a: Wa-166 - Wa-189 (SUBCONTRACTOR) (/24)100%4.00 114.00 0.00 04-Oct-22 A 06-Sep-23 A 04-Oct-22 06-Sep-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Structure Framing Summary (5 person crew) (26/31), 20-Jul-24 Structure Setting Crew (6 person crew) (26/31), 24-Jul-24 Stringing Crew (29 person crew) (11 /31), 13-Aug-24 Project Management / OH Summary, 30-Aug-24 Engineering and Design Project Support Summary, 30-Aug-24 09-Sep-25, Gateway West 26-Oct-24, Pre-Construction Activities 24 A, Construction Staking 26-Oct-24, Material Management Material Management (In Yard) 3 person crew, 26-Oct-24 15-Dec-24, Construction: Clients Elements 1, 2, 3, 5 (Sections 1, 2,3,4) cess r july 15), Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 8 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 405 WA3-ACS-3250 Access Installation Pull 24a: Wa-290 - Wa-303 (15/15)100%3.00 11.00 0.00 28-Aug-23 A 08-Sep-23 A 28-Aug-23 08-Sep-23 0.00 406 WA3-ACS-3260 Access Installation Pull 23a: Wa-272 - Wa-290 - (18/18)100%2.00 3.00 0.00 07-Sep-23 A 09-Sep-23 A 07-Sep-23 09-Sep-23 0.00 407 WA3-ACS-3270 Access Installation Pull 22a: Wa-266 - Wa-272 (7)100%3.00 2.00 0.00 10-Sep-23 A 12-Sep-23 A 10-Sep-23 12-Sep-23 0.00 408 Crew 2 Access Installation Pull 21a: Wa-249 - Wa-265 (sage grouse Jul 15) (crew 1- move to WC6) (17/17) 100%3.00 6.00 0.00 16-Aug-23 A 15-Sep-23 A 16-Aug-23 15-Sep-23 0.00 409 WC1-ACS-1220 Access Installation Pull 20c: Wc-180 Wc-189A *SUBCONTRACTOR* *after July 1, str 172-188* (6/10) 100%14.00 6.00 0.00 24-Jul-23 A 16-Sep-23 A 24-Jul-23 16-Sep-23 0.00 410 WA3-ACS-3290 Access Installation Pull 20a: Wa-227 - Wa-249 (sage grouse Jul 15) (crew 2 - move to WC6) 100%3.00 48.00 0.00 24-Jul-23 A 16-Sep-23 A 24-Jul-23 16-Sep-23 0.00 411 WA4-ACS-4220 Access Installation Pull 15a: Wa-143 - Wa-166 (SUBCONTRACTOR) (23/23)100%4.00 150.00 0.00 30-Sep-22 A 07-Oct-23 A 30-Sep-22 07-Oct-23 0.00 412 WC1-ACS-1210 Access Installation Pull 19c: Wc-166 - Wc-180 TBD DELAYS 0021 and 0022 100%7.00 14.00 0.00 02-Nov-22 A 11-Jan-24 A 02-Nov-22 11-Jan-24 0.00 413 Drilled Pier FoundDrilled Pier FoundationsDrilled Pier Foundations 364.00 374.00 0.00 05-Dec-22 A 21-Mar-24 A 05-Dec-22 21-Mar-24 0.00 414 Crew 1Crew 1Crew 1 321.00 331.00 0.00 05-Dec-22 A 30-Jan-24 A 05-Dec-22 30-Jan-24 0.00 415 WA2-DPF-2460 Drilled Pier Foundations Pull 7a: Wa-43 - Wa-45 (1/1- str 45) *BG*100%2.00 2.00 0.00 16-Jan-23 A 18-Jan-23 A 16-Jan-23 18-Jan-23 0.00 416 WA2-DPF-2400 Drilled Pier Foundations Pull 1a: Windstar - Wa-1 (1/1)*Moved to Start in January*100%1.00 1.00 0.00 23-Jan-23 A 23-Jan-23 A 23-Jan-23 23-Jan-23 0.00 417 WA2-DPF-2420 Drilled Pier Foundations Pull 3a: Wa-2 - Wa-4 (1/1)100%2.00 2.00 0.00 07-Feb-23 A 08-Feb-23 A 07-Feb-23 08-Feb-23 0.00 418 WA2-DPF-2410 Drilled Pier Foundations Pull 2a: Wa-1 - Wa-2 (1/1)100%2.00 1.00 0.00 08-Feb-23 A 09-Feb-23 A 08-Feb-23 09-Feb-23 0.00 419 WA2-DPF-2430 Drilled Pier Foundations Pull 4a: Wa-5 - Wa-18 (3/3)100%5.00 62.00 0.00 24-Jan-23 A 05-Apr-23 A 24-Jan-23 05-Apr-23 0.00 420 WA2-DPF-2450 Drilled Pier Foundations Pull 6a: Wa-27 - Wa-42 (1/1- str 42) (crew 1 - move to WA4) 100%5.00 40.00 0.00 23-Mar-23 A 20-May-23 A 23-Mar-23 20-May-23 0.00 421 WA2-DPF-2440 Drilled Pier Foundations Pull 5a: Wa-19 - Wa-26 (3/3 - str 20-c, 22-c, 25-c ) (crew 1 - start may 12) 100%5.00 14.00 0.00 17-Feb-23 A 24-May-23 A 17-Feb-23 24-May-23 0.00 422 WA2-DPF-2470 Drilled Pier Foundations Pull 8a: Wa-46 - Wa-53A (crew 1-move to WA4 9a)100%3.00 128.00 0.00 05-Dec-22 A 12-Aug-23 A 05-Dec-22 12-Aug-23 0.00 423 WA4-DPF-4430 Drilled Pier Foundations Pull 10a: Wa-77 - Wa-100 - note (4/4) (crew 1)100%6.00 51.00 0.00 12-Jul-23 A 08-Sep-23 A 12-Jul-23 08-Sep-23 0.00 424 WA4-DPF-4435 Drilled Pier Foundations Pull 9a: Wa-53A - Wa-76 - note (3/3) (crew 1 - start after june 1, move to 10a) 100%12.00 26.00 0.00 14-Aug-23 A 13-Sep-23 A 14-Aug-23 13-Sep-23 0.00 425 WA4-DPF-4425 Drilled Pier Foundations Pull 12a: Wa-106 - Wa-119 - note (4/4)100%8.00 67.00 0.00 04-Jul-23 A 19-Sep-23 A 04-Jul-23 19-Sep-23 0.00 426 WA4-DPF-4420 Drilled Pier Foundations Pull 13a: Wa-119 - Wa-149 (6/6) (Crew 1 move to WA3 28a) 100%12.00 43.00 0.00 10-Aug-23 A 28-Sep-23 A 10-Aug-23 28-Sep-23 0.00 427 WA3-DPF-3410 Drilled Pier Foundations Pull 28a: Wa-340 - Wa-343 (1/1) 340 100%4.00 4.00 0.00 16-Oct-23 A 19-Oct-23 A 16-Oct-23 19-Oct-23 0.00 428 WA3-DPF-3440 Drilled Pier Foundations Pull 25a: Wa-304 - Wa-321 (1/1) 312 100%4.00 3.00 0.00 20-Oct-23 A 23-Oct-23 A 20-Oct-23 23-Oct-23 0.00 429 WA3-DPF-3430 Drilled Pier Foundations Pull 26a: Wa-321 - Wa-329 (1/1) 329 100%4.00 4.00 0.00 20-Oct-23 A 24-Oct-23 A 20-Oct-23 24-Oct-23 0.00 430 WA3-DPF-3450 Drilled Pier Foundations Pull 24a: Wa-290 - Wa-303 (1/1) 299 100%4.00 3.00 0.00 24-Oct-23 A 26-Oct-23 A 24-Oct-23 26-Oct-23 0.00 431 WC1-DPF-1400c Drilled Pier Foundations Pull 18c: Wc-149 - Wc165 (011) Str 153 100%4.00 3.00 0.00 01-Nov-23 A 03-Nov-23 A 01-Nov-23 03-Nov-23 0.00 432 WC1-DPF-1400d Drilled Pier Foundations Pull 18c: Wc-149 - Wc165 (1/1) Str 158 100%4.00 10.00 0.00 04-Nov-23 A 14-Nov-23 A 04-Nov-23 14-Nov-23 0.00 433 WC1-DPF-1400 Drilled Pier Foundations Pull 18c: Wc-149 - Wc165 (1/1) Str 149 100%4.00 4.00 0.00 14-Nov-23 A 17-Nov-23 A 14-Nov-23 17-Nov-23 0.00 434 WA4-DPF-4415 Drilled Pier Foundations Pull 15a: Wa-148 - Wa-166 (Salvage Section) (3/3) Str 148c,152c,154c 100%12.00 11.00 0.00 17-Nov-23 A 02-Dec-23 A 17-Nov-23 02-Dec-23 0.00 435 WC1-DPF-1440 Drilled Pier Foundations Pull 22c: Str Wc208 - issues 100%4.00 5.00 0.00 11-Nov-23 A 22-Jan-24 A 11-Nov-23 22-Jan-24 0.00 436 WC1-DPF-1450c Drilled Pier Foundations Pull 20c: Str Wc189b - issues 100%6.00 14.00 0.00 10-Jan-24 A 30-Jan-24 A 10-Jan-24 30-Jan-24 0.00 437 Crew 2Crew 2Crew 2 88.00 102.00 0.00 27-Oct-23 A 18-Mar-24 A 27-Oct-23 18-Mar-24 0.00 438 WA3-DPF-3470 Drilled Pier Foundations Pull 20a: Str Wa249 (water/clsm)100%8.00 5.00 0.00 27-Oct-23 A 01-Nov-23 A 27-Oct-23 01-Nov-23 0.00 439 WA3-DPF-3460 Drilled Pier Foundations Pull 21a: Str Wa265 100%4.00 3.00 0.00 02-Nov-23 A 04-Nov-23 A 02-Nov-23 04-Nov-23 0.00 440 WC1-DPF-1430b Drilled Pier Foundations Pull 21c: Str Wc204 100%4.00 3.00 0.00 08-Nov-23 A 10-Nov-23 A 08-Nov-23 10-Nov-23 0.00 441 Crew 2 Drilled Pier Foundations Pull 21c: Str Wc190 100%4.00 5.00 0.00 27-Nov-23 A 01-Dec-23 A 27-Nov-23 01-Dec-23 0.00 442 WA3-DPF-3470b Drilled Pier Foundations Pull 20a: Str Wa227 (water/clsm)100%4.00 5.00 0.00 02-Dec-23 A 07-Dec-23 A 02-Dec-23 07-Dec-23 0.00 443 WA3-DPF-3400 Drilled Pier Foundations Pull 29a: Str Wa343 (current variance granted Jan 8-22)100%4.00 3.00 0.00 18-Jan-24 A 20-Jan-24 A 18-Jan-24 20-Jan-24 0.00 444 WA3-DPF-3400b Drilled Pier Foundations Pull 29a: Str Wa344 - dependant on TB flats outage delay due to rawlins blm 100%4.00 4.00 0.00 14-Mar-24 A 18-Mar-24 A 14-Mar-24 18-Mar-24 0.00 445 Crew 3Crew 3Crew 3 16.64 17.00 0.00 27-Nov-23 A 15-Dec-23 A 27-Nov-23 15-Dec-23 0.00 446 WC1-DPF-1410d Drilled Pier Foundations Pull 19c: Str Wc180 100%4.00 7.00 0.00 27-Nov-23 A 04-Dec-23 A 27-Nov-23 04-Dec-23 0.00 447 WC1-DPF-1420 Drilled Pier Foundations Pull 20c: Str Wc182 100%3.67 3.67 0.00 04-Dec-23 A 07-Dec-23 A 04-Dec-23 07-Dec-23 0.00 448 WC1-DPF-1450b Drilled Pier Foundations Pull 20c: Str Wc186 100%4.00 6.36 0.00 08-Dec-23 A 15-Dec-23 A 08-Dec-23 15-Dec-23 0.00 449 Crew 4Crew 4Crew 4 4.00 5.00 0.00 08-Dec-23 A 14-Dec-23 A 08-Dec-23 14-Dec-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 ar-24 A, Drilled Pier Foundations Crew 1 ar-24 A, Crew 2 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 9 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 450 WA4-DPF-4400 Drilled Pier Foundations Pull 17a: Str Wa206 (Salv.Sect)100%4.00 5.00 0.00 08-Dec-23 A 14-Dec-23 A 08-Dec-23 14-Dec-23 0.00 451 Concrete CuringConcrete CuringConcrete Curing 341.00 429.00 0.00 17-Jan-23 A 21-Mar-24 A 17-Jan-23 21-Mar-24 0.00 452 WA2-CON-2505 Concrete Curing Pull 7a: STR 45 100%14.00 14.95 0.00 17-Jan-23 A 31-Jan-23 A 17-Jan-23 31-Jan-23 0.00 453 WA2-CON-2406 Concrete Curing Pull 1a: STR 1 100%14.00 13.95 0.00 24-Jan-23 A 06-Feb-23 A 24-Jan-23 06-Feb-23 0.00 454 WA2-CON-2435 Concrete Curing Pull 4a: STR 10 100%14.00 14.95 0.00 25-Jan-23 A 08-Feb-23 A 25-Jan-23 08-Feb-23 0.00 455 WA2-CON-2425 Concrete Curing Pull 3a: STR 4 100%14.00 13.95 0.00 09-Feb-23 A 22-Feb-23 A 09-Feb-23 22-Feb-23 0.00 456 WA2-CON-2415 Concrete Curing Pull 2a: STR 2 100%14.00 13.95 0.00 10-Feb-23 A 23-Feb-23 A 10-Feb-23 23-Feb-23 0.00 457 WA2-CON-2475 Concrete Curing Pull 5a: STR 22 100%14.00 12.95 0.00 19-Feb-23 A 04-Mar-23 A 19-Feb-23 04-Mar-23 0.00 458 WA2-CON-2465 Concrete Curing Pull 5a: STR 20 100%14.00 13.95 0.00 14-Mar-23 A 27-Mar-23 A 14-Mar-23 27-Mar-23 0.00 459 Crew 2 Concrete Curing Pull 4a: STR 17 100%14.00 13.95 0.00 17-Mar-23 A 30-Mar-23 A 17-Mar-23 30-Mar-23 0.00 460 WA2-CON-2445 Concrete Curing Pull 4a: STR 13 100%14.00 15.00 0.00 27-Mar-23 A 10-Apr-23 A 27-Mar-23 10-Apr-23 0.00 461 WA2-CON-2495 Concrete Curing Pull 6a: STR 42 100%14.00 14.00 0.00 21-May-23 A 03-Jun-23 A 21-May-23 03-Jun-23 0.00 462 WA2-CON-2485 Concrete Curing Pull 5a: STR 25 100%14.00 14.00 0.00 25-May-23 A 07-Jun-23 A 25-May-23 07-Jun-23 0.00 463 WA4-CON-4445 Concrete Curing Pull 12a: STR 110 100%14.00 14.00 0.00 07-Jul-23 A 20-Jul-23 A 07-Jul-23 20-Jul-23 0.00 464 WA4-CON-4426 Concrete Curing Pull 10a: STR 97 100%14.00 14.00 0.00 17-Jul-23 A 30-Jul-23 A 17-Jul-23 30-Jul-23 0.00 465 WA4-CON-4435 Concrete Curing Pull 10a: STR 100 100%7.00 14.00 0.00 31-Jul-23 A 13-Aug-23 A 31-Jul-23 13-Aug-23 0.00 466 WA2-CON-2515 Concrete Curing Pull 8a: STR 52 100%7.00 8.00 0.00 09-Aug-23 A 16-Aug-23 A 09-Aug-23 16-Aug-23 0.00 467 WA2-CON-2525 Concrete Curing Pull 8a: STR 53A 100%7.00 8.00 0.00 12-Aug-23 A 19-Aug-23 A 12-Aug-23 19-Aug-23 0.00 468 WA4-CON-4415 Concrete Curing Pull 9a: STR 75 100%7.00 9.95 0.00 20-Aug-23 A 30-Aug-23 A 20-Aug-23 30-Aug-23 0.00 469 WA4-CON-4407 Concrete Curing Pull 9a: STR 68 100%7.00 14.00 0.00 17-Aug-23 A 30-Aug-23 A 17-Aug-23 30-Aug-23 0.00 470 WA4-CON-4456 Concrete Curing Pull 13a: STR 125 100%7.00 7.27 0.00 26-Aug-23 A 02-Sep-23 A 26-Aug-23 02-Sep-23 0.00 471 WA4-CON-4448 Concrete Curing Pull 12a: STR 119 100%7.00 7.00 0.00 01-Sep-23 A 07-Sep-23 A 01-Sep-23 07-Sep-23 0.00 472 WA4-CON-4416 Concrete Curing Pull 10a: STR 83 100%7.00 15.00 0.00 25-Aug-23 A 08-Sep-23 A 25-Aug-23 08-Sep-23 0.00 473 WA4-CON-4455 Concrete Curing Pull 13a: STR 123 100%7.00 7.00 0.00 08-Sep-23 A 14-Sep-23 A 08-Sep-23 14-Sep-23 0.00 474 WA4-CON-4425 Concrete Curing Pull 10a: STR 92 100%7.00 7.00 0.00 09-Sep-23 A 15-Sep-23 A 09-Sep-23 15-Sep-23 0.00 475 WA4-CON-4405 Concrete Curing Pull 9a: STR 63 100%7.00 7.00 0.00 13-Sep-23 A 19-Sep-23 A 13-Sep-23 19-Sep-23 0.00 476 WA4-CON-4446 Concrete Curing Pull 12a: STR 113 100%7.00 7.00 0.00 15-Sep-23 A 21-Sep-23 A 15-Sep-23 21-Sep-23 0.00 477 WA4-CON-4447 Concrete Curing Pull 12a: STR 114 100%7.00 7.00 0.00 15-Sep-23 A 21-Sep-23 A 15-Sep-23 21-Sep-23 0.00 478 WA4-CON-4465 Concrete Curing Pull 13a: STR 128 100%7.00 6.00 0.00 22-Sep-23 A 28-Sep-23 A 22-Sep-23 28-Sep-23 0.00 479 WA4-CON-4475 Concrete Curing Pull 13a: STR 132 100%7.00 8.00 0.00 29-Sep-23 A 06-Oct-23 A 29-Sep-23 06-Oct-23 0.00 480 WA4-CON-4474 Concrete Curing Pull 13a: STR 130 100%7.00 7.00 0.00 05-Oct-23 A 11-Oct-23 A 05-Oct-23 11-Oct-23 0.00 481 WA3-CON-3485 Concrete Curing Pull 28a: STR 340 100%3.00 7.00 0.00 19-Oct-23 A 25-Oct-23 A 19-Oct-23 25-Oct-23 0.00 482 WA3-CON-3465 Concrete Curing Pull 25a: STR 312 100%3.00 7.00 0.00 24-Oct-23 A 30-Oct-23 A 24-Oct-23 30-Oct-23 0.00 483 WA3-CON-3475 Concrete Curing Pull 26a: STR 329 100%3.00 7.00 0.00 25-Oct-23 A 31-Oct-23 A 25-Oct-23 31-Oct-23 0.00 484 Crew 2 Concrete Curing Pull 24a: STR 299 100%3.00 7.00 0.00 27-Oct-23 A 02-Nov-23 A 27-Oct-23 02-Nov-23 0.00 485 WA3-CON-3525 Concrete Curing Pull 20a: STR 249 100%3.00 4.00 0.00 02-Nov-23 A 05-Nov-23 A 02-Nov-23 05-Nov-23 0.00 486 WC1-CON-1415 Concrete Curing Pull 18c: STR 153 100%3.00 3.00 0.00 04-Nov-23 A 06-Nov-23 A 04-Nov-23 06-Nov-23 0.00 487 WA3-CON-3535 Concrete Curing Pull 21a: STR 265 100%3.00 3.00 0.00 05-Nov-23 A 08-Nov-23 A 05-Nov-23 08-Nov-23 0.00 488 WC1-CON-1505 Concrete Curing Pull 21c: STR 204 100%3.00 3.00 0.00 11-Nov-23 A 13-Nov-23 A 11-Nov-23 13-Nov-23 0.00 489 WC1-CON-1425 Concrete Curing Pull 18c: STR 158 100%3.00 2.95 0.00 15-Nov-23 A 17-Nov-23 A 15-Nov-23 17-Nov-23 0.00 490 WC1-CON-1405 Concrete Curing Pull 18c: STR 149 100%3.00 3.00 0.00 18-Nov-23 A 20-Nov-23 A 18-Nov-23 20-Nov-23 0.00 491 WA4-CON-4555 Concrete Curing Pull 15a: STR 148 100%3.00 3.00 0.00 19-Nov-23 A 22-Nov-23 A 19-Nov-23 22-Nov-23 0.00 492 WA4-CON-4565 Concrete Curing Pull 15a: STR 152 100%3.00 3.00 0.00 28-Nov-23 A 30-Nov-23 A 28-Nov-23 30-Nov-23 0.00 493 WC1-CON-1495 Concrete Curing Pull 21c: STR 190 100%3.00 3.00 0.00 02-Dec-23 A 04-Dec-23 A 02-Dec-23 04-Dec-23 0.00 494 WA4-CON-4566 Concrete Curing Pull 15a: STR 154 100%3.00 2.95 0.00 03-Dec-23 A 05-Dec-23 A 03-Dec-23 05-Dec-23 0.00 495 WC1-CON-1455 Concrete Curing Pull 19c: STR 180 100%3.00 4.00 0.00 04-Dec-23 A 07-Dec-23 A 04-Dec-23 07-Dec-23 0.00 496 WA3-CON-3515 Concrete Curing Pull 20a: STR 227 100%3.00 3.00 0.00 08-Dec-23 A 10-Dec-23 A 08-Dec-23 10-Dec-23 0.00 497 WC1-CON-1465 Concrete Curing Pull 20c: STR 182 100%3.00 3.00 0.00 08-Dec-23 A 11-Dec-23 A 08-Dec-23 11-Dec-23 0.00 498 WA4-CON-4595 Concrete Curing Pull 17a: STR 206 100%3.00 3.00 0.00 14-Dec-23 A 16-Dec-23 A 14-Dec-23 16-Dec-23 0.00 499 WC1-CON-1475 Concrete Curing Pull 20c: STR 186 100%3.00 3.00 0.00 16-Dec-23 A 18-Dec-23 A 16-Dec-23 18-Dec-23 0.00 500 WA3-CON-3495 Concrete Curing Pull 28a: STR 343 100%3.00 3.00 0.00 19-Jan-24 A 21-Jan-24 A 19-Jan-24 21-Jan-24 0.00 501 WC1-CON-1515 Concrete Curing Pull 22c: STR 208 100%3.00 3.00 0.00 23-Jan-24 A 25-Jan-24 A 23-Jan-24 25-Jan-24 0.00 502 WC1-CON-1485 Concrete Curing Pull 21c: STR 189b 100%3.00 3.00 0.00 31-Jan-24 A 02-Feb-24 A 31-Jan-24 02-Feb-24 0.00 503 WA3-CON-3505 Concrete Curing Pull 29a: STR 344 delay 100%3.00 2.00 0.00 19-Mar-24 A 21-Mar-24 A 19-Mar-24 21-Mar-24 0.00 504 FramingFramingFraming 284.00 475.00 2.00 15-Nov-22 A 12-Jul-24 29.78 15-Nov-22 12-Jul-24 0.00 505 Crew 1Crew 1Crew 1 284.00 475.00 2.00 15-Nov-22 A 12-Jul-24 29.78 15-Nov-22 12-Jul-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 ar-24 A, Concrete Curing 12-Jul-24, Framing 12-Jul-24, Crew 1 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 10 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 506 WA2-FRM-2500 Frame Structures Pull 3a: Wa-2 - Wa-4 * (4/4)100%1.00 50.00 0.00 03-Dec-22 A 02-Mar-23 A 03-Dec-22 02-Mar-23 0.00 507 WA2-FRM-2520 Frame Structures Pull 5a: Wa-18 - Wa-22 (4/4)100%2.00 89.00 0.00 03-Dec-22 A 28-Mar-23 A 03-Dec-22 28-Mar-23 0.00 508 WA2-FRM-2510 Frame Structures Pull 4a: Wa-5 - Wa-18 (15/15)100%4.00 112.00 0.00 01-Dec-22 A 21-Apr-23 A 01-Dec-22 21-Apr-23 0.00 509 WA2-FRM-2540 Frame Structures Pull 7a: Wa-42 - Wa-45 (3/3)100%1.00 29.00 0.00 30-Mar-23 A 02-May-23 A 30-Mar-23 02-May-23 0.00 510 WA2-FRM-2530 Frame Structures Pull 6a: Wa-23 - Wa-42 (20/20)100%5.00 46.00 0.00 15-Nov-22 A 06-Jun-23 A 15-Nov-22 06-Jun-23 0.00 511 WA4-FRM-4545 Frame Structures Pull 10a: Wa-77 - Wa-100 - note (Crew 1 - move to WC1 18c) (18/23) 100%6.00 46.00 0.00 23-May-23 A 14-Jul-23 A 23-May-23 14-Jul-23 0.00 512 WA4-FRM-4530 Frame Structures Pull 13a: Wa-119 - Wa-129(8/8) (deadends for set crew)100%4.00 11.00 0.00 13-Jul-23 A 25-Jul-23 A 13-Jul-23 25-Jul-23 0.00 513 WA2-FRM-2550 Frame Structures Pull 8a: Wa-45 - Wa-53A (Crew 1 - move to WA4 9a) (5/5)100%3.00 184.00 0.00 14-Dec-22 A 27-Jul-23 A 14-Dec-22 27-Jul-23 0.00 514 WA4-FRM-4540 Frame Structures Pull 11a: Wa-100 - Wa-106 (Crew 1- start after July 15, move to 12a) (5/5) 100%2.00 30.00 0.00 24-Jun-23 A 28-Jul-23 A 24-Jun-23 28-Jul-23 0.00 515 WA4-FRM-4550 Frame Structures Pull 9a: Wa-53A - Wa-76 - (Crew 1- start after June 1, move to 10a) (19/23) str 70 damaged 100%6.00 66.00 0.00 16-May-23 A 31-Jul-23 A 16-May-23 31-Jul-23 0.00 516 WC1-FRM-1540 Frame Structures Pull 22c: Wc-191 - Wc207 (crew 1+2 move to WA3 pull 28a) (15/15) 100%5.00 6.00 0.00 09-Aug-23 A 15-Aug-23 A 09-Aug-23 15-Aug-23 0.00 517 WA3-FRM-3500 Frame Structures Pull 28a: Wa-340 - Wa-344 (Crew 1+2- move to 27a) (1/2)100%1.00 2.00 0.00 28-Aug-23 A 29-Aug-23 A 28-Aug-23 29-Aug-23 0.00 518 WA4-FRM-4500 Frame Structures Pull 19a: Wa-213 - Wa-227 (Crew 1) (14/14)100%5.00 14.00 0.00 16-Aug-23 A 31-Aug-23 A 16-Aug-23 31-Aug-23 0.00 519 WA3-FRM-3550 Frame Structures Pull 23a: Wa-272 - Wa-290 - note (Crew 1+2) (18/18)100%4.00 6.00 0.00 20-Sep-23 A 26-Sep-23 A 20-Sep-23 26-Sep-23 0.00 520 WA3-FRM-3560 Frame Structures Pull 22a: Wa-266 - Wa-272 (Crew 1+2) (6/6)100%2.00 2.00 0.00 27-Sep-23 A 28-Sep-23 A 27-Sep-23 28-Sep-23 0.00 521 WA3-FRM-3540 Frame Structures Pull 24a: Wa-290 - Wa-307 (Crew 1+2) (16/16)100%3.00 15.00 0.00 18-Sep-23 A 04-Oct-23 A 18-Sep-23 04-Oct-23 0.00 522 WA3-FRM-3530 Frame Structures Pull 25a: Wa-307 - Wa-315 (8/8)100%2.00 17.00 0.00 15-Sep-23 A 04-Oct-23 A 15-Sep-23 04-Oct-23 0.00 523 WA3-FRM-3510 Frame Structures Pull 27a: Wa-329 - Wa-340 (Crew 1+2) (10/10)100%3.00 35.00 0.00 26-Aug-23 A 06-Oct-23 A 26-Aug-23 06-Oct-23 0.00 524 WC1-FRM-1530 Frame Structures Pull 21c: Wc-189A - Wc190 (3/3)100%1.00 2.00 0.00 10-Oct-23 A 11-Oct-23 A 10-Oct-23 11-Oct-23 0.00 525 Crew 2 Frame Structures Pull 20a: Wa-227 - Wa-249 (SG Jul 15) (Crew 1+2(Crew 1+2 move to WA4 18a) (21/21) 100%3.00 56.00 0.00 16-Aug-23 A 19-Oct-23 A 16-Aug-23 19-Oct-23 0.00 526 WA4-FRM-4525 Frame Structures Pull 14a: Wa-129A - Wa-151 (20/20) (148 delay frame done by setting crew) 100%6.00 5.00 0.00 07-Sep-23 A 21-Oct-23 A 07-Sep-23 21-Oct-23 0.00 527 WA4-FRM-4505 Frame Structures Pull 18a: Wa-208 - Wa-213 (5/5)100%1.00 2.00 0.00 23-Aug-23 A 21-Oct-23 A 23-Aug-23 21-Oct-23 0.00 528 WC1-FRM-1500 Frame Structures Pull 18c: Wc-149 - Wc16 (Crew 1 + 2-start) (13/13)100%5.00 13.00 0.00 17-Jul-23 A 24-Oct-23 A 17-Jul-23 24-Oct-23 0.00 529 WA4-FRM-4535 Frame Structures Pull 12a: Wa-106 - Wa-119 (13/13)100%3.00 101.00 0.00 29-Jun-23 A 24-Oct-23 A 29-Jun-23 24-Oct-23 0.00 530 WA3-FRM-3570 Frame Structures Pull 21a: Wa-249 - Wa-265 (SG Jul 15) (Crew 1+2 ) (15/15)100%3.00 29.00 0.00 28-Sep-23 A 30-Oct-23 A 28-Sep-23 30-Oct-23 0.00 531 WC1-FRM-1510 Frame Structures Pull 19c: Wc-165 - Wc-180 (11/15)Access Delay, 165-169, 174-179 complete, 171 and 173 are deadends 100%4.00 5.00 0.00 25-Oct-23 A 29-Nov-23 A 25-Oct-23 29-Nov-23 0.00 532 WC1-FRM-1520 Frame Structures Pull 20c: Wc-180 Wc-189A (6/10) 181,183,184,185,187,188, rest are deadends captured below 100%3.00 41.00 0.00 11-Oct-23 A 29-Nov-23 A 11-Oct-23 29-Nov-23 0.00 533 WA3-FRM-3520 Frame Structures Pull 26a: Wa-315 - Wa-329 (14/15) str 320 (last tangent structure other then salvage sect) 95%0.25 13.00 2.00 22-Aug-23 A 12-Jul-24 16.28 22-Aug-23 12-Jul-24 0.00 534 Casings / Pre-DrilliCasings / Pre-DrillingCasings / Pre-Drilling 37.00 70.00 0.00 10-Oct-23 A 23-Jan-24 A 10-Oct-23 23-Jan-24 0.00 535 WA3-SET-3655 Install Casings Str Wa-341-331 on tangent structures due to wet conditions 100%10.00 10.00 0.00 16-Oct-23 A 26-Oct-23 A 16-Oct-23 26-Oct-23 0.00 536 WC1-SET-1599 Pre-Rock Drilling Str Wa and Wc-190-153 (78/88) - Wc line complete 100%37.00 70.00 0.00 10-Oct-23 A 23-Jan-24 A 10-Oct-23 23-Jan-24 0.00 537 Direct EmbedmentDirect Embedment +SettingDirect Embedment +Setting 443.98 454.00 1.00 13-Dec-22 A 12-Jul-24 348.00 13-Dec-22 12-Jul-24 0.00 538 Crew 1Crew 1Crew 1 375.00 293.00 0.00 13-Dec-22 A 03-Dec-23 A 13-Dec-22 03-Dec-23 0.00 539 WA2-DEF-2300 Direct Embed Foundations Pull 3a: Wa-2 - Wa-4 (1/1)100%1.00 1.00 0.00 13-Dec-22 A 13-Dec-22 A 13-Dec-22 13-Dec-22 0.00 540 WA2-SET-2610 Set Structures Pull 2a: Wa-1 - Wa-2 (1/1)100%1.00 1.00 0.00 01-Mar-23 A 01-Mar-23 A 01-Mar-23 01-Mar-23 0.00 541 WA2-SET-2620 Set Structures Pull 3a: Wa-2 - Wa-4 ( 1/3)100%1.00 20.00 0.00 07-Feb-23 A 01-Mar-23 A 07-Feb-23 01-Mar-23 0.00 542 WA2-SET-2600 Set Structures Pull 1a: Windstar - Wa-1 (1/1)100%1.00 1.00 0.00 02-Mar-23 A 02-Mar-23 A 02-Mar-23 02-Mar-23 0.00 543 WA2-DEF-2340 Direct Embed Foundations Pull 7a: Wa-42 - Wa-45 (Crew 1- move to WA4 9a/10a) (3/3) 100%1.00 26.00 0.00 01-May-23 A 30-May-23 A 01-May-23 30-May-23 0.00 544 WA2-SET-2660 Set Structures Pull 7a: Wa-42 - Wa-45 (1/3) (Crew 1- move to WA4 9a) (3/3)100%2.00 13.00 0.00 16-May-23 A 30-May-23 A 16-May-23 30-May-23 0.00 545 WA2-DEF-2320 Direct Embed Foundations Pull 5a: Wa-18 - Wa-26 (5/5)100%2.00 66.00 0.00 20-Mar-23 A 03-Jun-23 A 20-Mar-23 03-Jun-23 0.00 546 WA2-DEF-2330 Direct Embed Foundations Pull 6a: Wa-26 - Wa-42 (17/17)100%6.00 31.00 0.00 01-May-23 A 05-Jun-23 A 01-May-23 05-Jun-23 0.00 547 WA2-SET-2640 Set Structures Pull 5a: Wa-18 - Wa-26 (8/8)100%4.00 69.00 0.00 18-Mar-23 A 06-Jun-23 A 18-Mar-23 06-Jun-23 0.00 548 WA2-SET-2650 Set Structures Pull 6a: Wa-26 - Wa-42 (17/17)100%4.00 29.00 0.00 05-May-23 A 07-Jun-23 A 05-May-23 07-Jun-23 0.00 549 WA2-DEF-2310 Direct Embed Foundations Pull 4a: Wa-4 - Wa-18 (12/12) (Crew 1 - start after May 1) str 14,15,16 - nest cleared 100%4.00 158.00 0.00 13-Dec-22 A 17-Jul-23 A 13-Dec-22 17-Jul-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structures Pull 26a: Wa-315 - Wa-329 (14/15) str 320 (last tangent structure other then salv Casings / Pre-Drilling 12-Jul-24, Direct Embedment +Setting Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 11 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 550 WA2-SET-2630 Set Structures Pull 4a: Wa-5 - Wa-18 *new demob* (15/15) (Crew 1- start after May 1) horned owl delay 100%6.00 135.00 0.00 08-Feb-23 A 20-Jul-23 A 08-Feb-23 20-Jul-23 0.00 551 WA2-DEF-2350 Direct Embed Foundations Pull 8a: Wa-45 - Wa-53A (6/7) (Crew 1 start after July 15, move to WA4 11a) 100%3.00 50.00 0.00 13-Mar-23 A 08-Aug-23 A 13-Mar-23 08-Aug-23 0.00 552 WA2-SET-2670 Set Structures Pull 8a: Wa-45 - Wa-53A (8/9) (Crew 1-start after july 15, move to WA4 11a) 100%4.00 141.00 0.00 10-Mar-23 A 21-Aug-23 A 10-Mar-23 21-Aug-23 0.00 553 WA4-SET-4640 Direct Embed + Set Str.'s Pull 11a: Wa-100 - Wa-106 (Crew 1)(5/5)100%1.00 46.00 0.00 03-Jul-23 A 24-Aug-23 A 03-Jul-23 24-Aug-23 0.00 554 WA2-TMP-2800 Build Temporary Line Pull 1T: Temp 01 - Temp 05 - note 100%5.00 5.00 0.00 01-Sep-23 A 06-Sep-23 A 01-Sep-23 06-Sep-23 0.00 555 WA2-TMP-2810 Build Temporary Line Pull 2T: Temp 05 - Temp 11 - note 100%4.00 8.00 0.00 07-Sep-23 A 15-Sep-23 A 07-Sep-23 15-Sep-23 0.00 556 WA4-SET-4650 Direct Embed + Set Str.'s Pull 9a: Wa-53A - Wa-76 - note (Crew 1- start after June 1, move to 10a) (19/23) 100%7.00 88.00 0.00 13-Jun-23 A 22-Sep-23 A 13-Jun-23 22-Sep-23 0.00 557 WA4-SET-4645 Direct Embed + Set Str.'s Pull 10a: Wa-77 - Wa-100 - note (Crew 1) (20/23)100%8.00 81.00 0.00 21-Jun-23 A 22-Sep-23 A 21-Jun-23 22-Sep-23 0.00 558 WA4-SET-4630 Direct Embed + Set Str.'s Pull 13a: Wa-119 - Wa-132 100%7.00 21.00 0.00 06-Sep-23 A 30-Sep-23 A 06-Sep-23 30-Sep-23 0.00 559 WA3-SET-3660 Direct Embed + Str. Setting Pull 23a: Wa-272 - Wa-290 (Crew 1+2) (18/18)100%4.00 3.00 0.00 27-Sep-23 A 30-Sep-23 A 27-Sep-23 30-Sep-23 0.00 560 WA3-SET-3600 Direct Embed + Str. Setting Pull 29a: Wa-344 - Shirley Basin #3 - DELETE DE setting captured in new activity below 100%7.37 0.00 0.00 11-Oct-23 A 11-Oct-23 A 11-Oct-23 11-Oct-23 0.00 561 WA4-SET-4635 Direct Embed + Set Str.'s Pull 12a: Wa-106 - Wa-119 (13/13)100%5.00 96.00 0.00 06-Jul-23 A 25-Oct-23 A 06-Jul-23 25-Oct-23 0.00 562 WA3-SET-3610 Direct Embed + Str. Setting Pull 28a: Wa-340 - Wa-344 (2/4) str343,344 captured in deadend setting below 100%0.50 1.00 0.00 28-Oct-23 A 30-Oct-23 A 28-Oct-23 30-Oct-23 0.00 563 WA3-SET-3640 Direct Embed + Str. Setting Pull 25a: Wa-307 - Wa-315 (9/9) str 312 100%4.00 36.73 0.00 20-Sep-23 A 31-Oct-23 A 20-Sep-23 31-Oct-23 0.00 564 WA3-SET-3620 Direct Embed + Str. Setting Pull 27a: Wa-329 - Wa-340 (11/11)100%2.00 9.00 0.00 27-Oct-23 A 04-Nov-23 A 27-Oct-23 04-Nov-23 0.00 565 WA3-SET-3650 Direct Embed + Str. Setting Pull 24a: Wa-290 - Wa-307 (18/18)100%2.00 32.00 0.00 29-Sep-23 A 06-Nov-23 A 29-Sep-23 06-Nov-23 0.00 566 WA3-SET-3670 Direct Embed + Str. Setting Pull 22a: Wa-266 - Wa-272 (6/6) RFI 271 oct 4 100%2.00 34.73 0.00 28-Sep-23 A 07-Nov-23 A 28-Sep-23 07-Nov-23 0.00 567 WA4-SET-4625 Direct Embed + Str. Setting Pull 14a: Wa-132 - Wa-150 (18/18) includes framing on drilledpiers 100%5.00 17.00 0.00 07-Nov-23 A 03-Dec-23 A 07-Nov-23 03-Dec-23 0.00 568 Crew 2Crew 2Crew 2 214.22 222.73 1.00 20-Sep-23 A 12-Jul-24 52.14 20-Sep-23 12-Jul-24 0.00 569 WC1-SET-1630c Direct Embed + Set Structures Pull 21c: Str Wc194 100%0.75 0.75 0.00 10-Oct-23 A 11-Oct-23 A 10-Oct-23 11-Oct-23 0.00 570 Crew 2 Direct Embed + Str. Setting Pull 18a: Wa-207 - Wa-213 (5/5)100%3.00 2.00 0.00 20-Oct-23 A 23-Oct-23 A 20-Oct-23 23-Oct-23 0.00 571 WC1-SET-1660 Direct Embed + Set Structures Pull 23c: Cutover to Line 1Wa (Outage Dependent) *done by stringing crew 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 A 01-Nov-23 01-Nov-23 0.00 572 WC1-SET-1650 *OUTAGE START* not required with new sequence 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 0.00 573 WC1-SET-1670 *OUTAGE COMPLETE* not required with new sequence 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 0.00 574 WA4-SET-4600 Direct Embed + Str. Setting Pull 19a: Wa-213 - Wa-227 (14/14)100%4.00 12.00 0.00 23-Oct-23 A 04-Nov-23 A 23-Oct-23 04-Nov-23 0.00 575 WA3-SET-3680 Direct Embed + Str. Setting Pull 21a: Wa-249 - Wa-265 (17/17)100%4.00 11.00 0.00 15-Nov-23 A 30-Nov-23 A 15-Nov-23 30-Nov-23 0.00 576 WC1-SET-1600 Direct Embed + Set Structures Pull 18c: Wc-149 - Wc165 (9/17) Str 150-152, 154-157,162,163 complete 100%9.00 4.00 0.00 14-Nov-23 A 04-Dec-23 A 14-Nov-23 04-Dec-23 0.00 577 WC1-SET-1640 Direct Embed + Set Structures Pull 22c: Wc-206 - Wc207 (2/2)100%2.00 4.00 0.00 21-Oct-23 A 04-Dec-23 A 21-Oct-23 04-Dec-23 0.00 578 WC1-SET-1600d Direct Embed + Set Structures Pull 19c: Str Wc161 100%1.00 1.00 0.00 05-Dec-23 A 05-Dec-23 A 05-Dec-23 05-Dec-23 0.00 579 WC1-SET-1610d Direct Embed + Set Structures Pull 19c: Str Wc169 100%0.67 0.67 0.00 08-Dec-23 A 08-Dec-23 A 08-Dec-23 08-Dec-23 0.00 580 WC1-SET-1630 Direct Embed + Set Structures Pull 21c: Str 189D-193, 196-203 100%6.00 14.00 0.00 11-Oct-23 A 09-Dec-23 A 11-Oct-23 09-Dec-23 0.00 581 WC1-SET-1610b Direct Embed + Set Structures Pull 19c: Str Wc167 100%0.67 0.67 0.00 08-Dec-23 A 09-Dec-23 A 08-Dec-23 09-Dec-23 0.00 582 WC1-SET-1600e Direct Embed + Set Structures Pull 19c: Str Wc164 100%1.00 1.00 0.00 13-Dec-23 A 13-Dec-23 A 13-Dec-23 13-Dec-23 0.00 583 WC1-SET-1610i Direct Embed + Set Structures Pull 20c: Str Wc176 100%0.67 0.67 0.00 14-Dec-23 A 15-Dec-23 A 14-Dec-23 15-Dec-23 0.00 584 WC1-SET-1610h Direct Embed + Set Structures Pull 20c: Str Wc175 100%0.67 0.67 0.00 15-Dec-23 A 16-Dec-23 A 15-Dec-23 16-Dec-23 0.00 585 WC1-SET-1600c Direct Embed + Set Structures Pull 19c: Str Wc160 100%1.00 1.00 0.00 16-Dec-23 A 16-Dec-23 A 16-Dec-23 16-Dec-23 0.00 586 WA3-SET-3690.1 Direct Embed + Str. Setting Pull 20a: Wa-227 - Wa-249 (20/22) str 249 deadend setting below 100%1.00 10.00 0.00 04-Nov-23 A 20-Jan-24 A 04-Nov-23 20-Jan-24 0.00 587 WA3-SET-3690.2 Direct Embed + Str. Setting Pull 20a: Wa-227 - Wa-249 (20/22) str 232 *done jan 20 100%1.00 11.00 0.00 04-Nov-23 A 20-Jan-24 A 04-Nov-23 20-Jan-24 0.00 588 WC1-SET-1630d Direct Embed + Set Structures Pull 21c: Str Wc195 100%0.50 0.50 0.00 23-Jan-24 A 23-Jan-24 A 23-Jan-24 23-Jan-24 0.00 589 WA3-SET-3630 Direct Embed + Str. Setting Pull 26a: Wa-315 - Wa-329 (14/15) str Wa320 big game delay 95%3.00 35.73 1.00 20-Sep-23 A 12-Jul-24 16.28 20-Sep-23 12-Jul-24 0.00 590 DeadendsDeadendsDeadends 208.98 136.50 0.00 31-Oct-23 A 01-May-24 A 31-Oct-23 03-May-24 2.00 591 WA3-SET-4020 Deadend Setting Pull 25a: STR 312 100%0.50 0.50 0.00 31-Oct-23 A 31-Oct-23 A 31-Oct-23 31-Oct-23 0.00 592 WA3-SET-4010 Deadend Setting Pull 26a: STR 329 100%0.50 0.50 0.00 01-Nov-23 A 01-Nov-23 A 01-Nov-23 01-Nov-23 0.00 593 WA3-SET-4030 Deadend Setting Pull 24a: STR 299 100%0.50 0.50 0.00 03-Nov-23 A 03-Nov-23 A 03-Nov-23 03-Nov-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 12-Jul-24, Crew 2 ed with new sequence, required with new sequence, 01-Nov-23 A Direct Embed + Str. Setting Pull 26a: Wa-315 - Wa-329 (14/15) str Wa320 big game delay, 12-Jul-2 01-May-24 A, Deadends Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 12 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 594 WA3-SET-4000 Deadend Setting Pull 27a: STR 340 100%0.50 0.50 0.00 03-Nov-23 A 03-Nov-23 A 03-Nov-23 03-Nov-23 0.00 595 WA3-SET-4040 Deadend Setting Pull 21a: STR 265 100%0.50 0.50 0.00 30-Nov-23 A 30-Nov-23 A 30-Nov-23 30-Nov-23 0.00 596 WC1-SET-1610c Drilling and Setting: Wc-168 100%0.67 1.67 0.00 13-Dec-23 A 14-Dec-23 A 13-Dec-23 14-Dec-23 0.00 597 WC1-SET-1720 Deadend Setting: Wc-158 100%0.50 1.50 0.00 13-Dec-23 A 14-Dec-23 A 13-Dec-23 14-Dec-23 0.00 598 WA3-SET-4050 Deadend Setting Pull 20a: STR 227 100%0.50 0.50 0.00 16-Dec-23 A 16-Dec-23 A 16-Dec-23 16-Dec-23 0.00 599 WC1-SET-1790 Deadend Setting Pull 21c: STR 190 100%0.50 0.50 0.00 19-Jan-24 A 19-Jan-24 A 19-Jan-24 19-Jan-24 0.00 600 WA3-SET-4060 Deadend Setting Pull 20a: STR 249 100%0.50 0.50 0.00 20-Jan-24 A 20-Jan-24 A 20-Jan-24 20-Jan-24 0.00 601 WA3-SET-4070 Deadend Framing + Setting Pull 29a: STR 344 100%3.00 1.00 0.00 01-May-24 A 01-May-24 A 01-May-24 03-May-24 2.00 602 WA3-SET-4080 Deadend Framing + Setting Pull 28a: STR 343 100%3.00 1.00 0.00 01-May-24 A 01-May-24 A 01-May-24 03-May-24 2.00 603 StringingStringingStringing 213.00 197.00 0.00 20-Jun-23 A 28-Feb-24 A 20-Jun-23 28-Feb-24 0.00 604 Crew 1Crew 1Crew 1 206.00 173.00 0.00 20-Jun-23 A 31-Jan-24 A 20-Jun-23 31-Jan-24 0.00 605 WA2-STR-2710 Conductor Stringing Pull 2a: Wa-1 - *Wa-2 100%4.00 6.00 0.00 20-Jun-23 A 26-Jun-23 A 20-Jun-23 26-Jun-23 0.00 606 WA2-STR-2720 Conductor Stringing Pull 3a: Wa-2 - Wa-4 100%4.00 6.00 0.00 20-Jun-23 A 26-Jun-23 A 20-Jun-23 26-Jun-23 0.00 607 WA2-STR-2750 Conductor Stringing Pull 6a: Wa-35 - Wa-42 - note (Req. daily outage on 115kvWA05a, 115KvWA05b, and distro1WA04a) 100%6.00 5.00 0.00 07-Jul-23 A 12-Jul-23 A 07-Jul-23 12-Jul-23 0.00 608 WA2-STR-2760 Conductor Stringing Pull 7a: Wa-42 - Wa-45 100%6.00 5.00 0.00 07-Jul-23 A 12-Jul-23 A 07-Jul-23 12-Jul-23 0.00 609 WA2-STR-2730 Conductor Stringing Pull 4a: Wa-4 - Wa-18 - note (Req. daily outages on 230kv1WA01a & DistroWa01b) *Set to ALAP* 100%7.00 8.00 0.00 25-Jul-23 A 02-Aug-23 A 25-Jul-23 02-Aug-23 0.00 610 WA2-STR-2770 Conductor Stringing Pull 8a: Wa-45 - Wa-53A - note (Req. daily outages on Distro1WA07 & Distro1WA05b) (Crew 1- move temp 100%7.00 4.00 0.00 21-Aug-23 A 24-Aug-23 A 21-Aug-23 24-Aug-23 0.00 611 WA2-STR-2740 Conductor Stringing Pull 5a: Wa-18 - Wa-34 (Req. daily outages on 230kvWA03a & 69kvWa03b) - on heels 100%6.00 20.00 0.00 05-Aug-23 A 28-Aug-23 A 05-Aug-23 28-Aug-23 0.00 612 WA4-STR-4740 Conductor Stringing Pull 11a: Wa-100 - Wa-106 100%6.00 7.00 0.00 24-Aug-23 A 31-Aug-23 A 24-Aug-23 31-Aug-23 0.00 613 WA4-STR-4750 Conductor Stringing Pull 9a: Wa-53A - Wa-76 - note (Req. daily outage on distroWA11a)(Crew 1 start, move 10a) 100%7.00 21.00 0.00 25-Sep-23 A 18-Oct-23 A 25-Sep-23 18-Oct-23 0.00 614 WA4-STR-4745 Conductor Stringing Pull 10a: Wa-77 - Wa-100 - note (Req. daily outages on DistroWA14a & distroWa15a) 100%7.00 16.00 0.00 05-Oct-23 A 23-Oct-23 A 05-Oct-23 23-Oct-23 0.00 615 WC1-STR-1760 Conductor Stringing Pull 23c: Cutover to Line 1Wa - not required with new seqeunce 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 A 01-Nov-23 01-Nov-23 0.00 616 WC1-STR-1750 *OUTAGE START* - not required with new seqeunce 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 0.00 617 WC1-STR-1770 *OUTAGE COMPLETE* - not required with new seqeunce 100%0.00 0.00 0.00 01-Nov-23 A 01-Nov-23 0.00 618 WA4-STR-4740b Conductor Stringing Pull 11a: Wa-100 - Wa-106 REDO Descrepancy 100%3.00 6.00 0.00 08-Nov-23 A 13-Nov-23 A 08-Nov-23 13-Nov-23 0.00 619 WA4-STR-4735 Conductor Stringing Pull 12a: Wa-106 - Wa-123 - BG Leaning Structures Corrected 100%7.00 24.00 0.00 24-Oct-23 A 19-Nov-23 A 24-Oct-23 19-Nov-23 0.00 620 WA4-STR-4725 Conductor Stringing Pull 14a: Wa-132 - Wa-148 100%7.00 8.00 0.00 30-Nov-23 A 08-Dec-23 A 30-Nov-23 08-Dec-23 0.00 621 WA4-STR-4700 Conductor Stringing Pull 19a: Wa-213 - Wa-227 - Delete combined with pull 18a 100%0.00 0.00 0.00 12-Dec-23 A 12-Dec-23 A 12-Dec-23 12-Dec-23 0.00 622 WA4-STR-4705 Conductor Stringing Pull 18a +19a: Wa-207 - Wa-227 100%9.00 12.00 0.00 15-Dec-23 A 23-Jan-24 A 15-Dec-23 23-Jan-24 0.00 623 WA4-STR-4730 Conductor Stringing Pull 13a: Wa-124 - Wa-132 - needs OPGW 100%7.00 37.00 0.00 17-Nov-23 A 26-Jan-24 A 17-Nov-23 26-Jan-24 0.00 624 WA3-STR-3790 Conductor Stringing Pull 20a: Wa-227 - Wa-249 (FEHA+GOEA) - take outage 100%8.00 10.00 0.00 18-Jan-24 A 28-Jan-24 A 18-Jan-24 28-Jan-24 0.00 625 WA3-STR-3780 Conductor Stringing Pull 21a: Wa-249 - Wa-265 (FEHA+GOEAFeb1) - take outage 100%7.00 23.00 0.00 15-Dec-23 A 31-Jan-24 A 15-Dec-23 31-Jan-24 0.00 626 Crew 2Crew 2Crew 2 58.00 81.00 0.00 01-Nov-23 A 27-Feb-24 A 01-Nov-23 27-Feb-24 0.00 627 WA3-STR-3750 Conductor Stringing Pull 24a: Wa-299 - Wa-307 100%5.00 10.00 0.00 01-Nov-23 A 10-Nov-23 A 01-Nov-23 10-Nov-23 0.00 628 WA3-STR-3740 Conductor Stringing Pull 25a: Wa-307 - Wa-315 100%5.00 10.00 0.00 01-Nov-23 A 10-Nov-23 A 01-Nov-23 10-Nov-23 0.00 629 WA3-STR-3720 Conductor Stringing Pull 27a: Wa-329 - Wa-340 100%5.00 10.00 0.00 10-Nov-23 A 20-Nov-23 A 10-Nov-23 20-Nov-23 0.00 630 WA3-STR-3760 Conductor Stringing Pull 23a: Wa299-284 Wa-284-272 (FEHA Mar1)100%12.00 11.00 0.00 27-Nov-23 A 08-Dec-23 A 27-Nov-23 08-Dec-23 0.00 631 WA3-STR-3770 Conductor Stringing Pull 22a: Wa-265 - Wa-272 (Req. daily outages on distro1WA46a)(FEHA Mar1) 100%6.00 7.00 0.00 09-Dec-23 A 16-Dec-23 A 09-Dec-23 16-Dec-23 0.00 632 WA4-STR-4725b Conductor Stringing Pull 14a: Wa-148 - Wa-152 - possible design change issue 100%4.00 4.00 0.00 23-Feb-24 A 27-Feb-24 A 23-Feb-24 27-Feb-24 0.00 633 OutagesOutagesOutages 83.00 75.00 0.00 09-Nov-23 A 28-Feb-24 A 09-Nov-23 28-Feb-24 0.00 634 Temp Line 1Temp Line 1Temp Line 1 33.00 27.00 0.00 09-Nov-23 A 12-Dec-23 A 09-Nov-23 12-Dec-23 0.00 635 WA2-TMP-2820 String Temp Line 01 (Str Temp 01 - Temp 04) start Nov8th, move 1a pull 100%3.00 6.00 0.00 09-Nov-23 A 14-Nov-23 A 09-Nov-23 14-Nov-23 0.00 636 WA2-STR-2700 Conductor Stringing Pull 1a: Windstar - Wa-1 (orig Nov 13) A-frame to be completed, take outage after 100%4.00 9.00 0.00 15-Nov-23 A 28-Nov-23 A 15-Nov-23 28-Nov-23 0.00 637 WA2-TMP-2870 OUTAGE START - Temp Line 1 100%0.00 0.00 0.00 04-Dec-23 A 04-Dec-23 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 24 A, Stringing Crew 1 uired with new seqeunce, t required with new seqeunce, 01-Nov-23 A 24 A, Crew 2 24 A, Outages ne 1 p Line 1, Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 13 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 638 WC6-DPF-6550 Drilled Pier Foundation Pull 6c: Wc-43 - Wc-49B (0/2) Str 49A+49B (Temp line 1 outage) 100%4.00 4.00 0.00 04-Dec-23 A 07-Dec-23 A 04-Dec-23 07-Dec-23 0.00 639 WA2-TMP-2850 String Temp Line 01 (Str Temp 04 - Temp 05 and Tie-in) (Outage Required Dec 4)100%5.00 5.00 0.00 04-Dec-23 A 08-Dec-23 A 04-Dec-23 08-Dec-23 0.00 640 WA2-TMP-2880 OUTGAE COMPLETE - Temp 1 100%0.00 0.00 0.00 08-Dec-23 A 08-Dec-23 0.00 641 WC6-CON-5625 Concrete Curing Pull 6: STR 49A 100%7.00 4.00 0.00 09-Dec-23 A 12-Dec-23 A 09-Dec-23 12-Dec-23 0.00 642 WC6-CON-5635 Concrete Curing Pull 7: STR 49B 100%7.00 4.00 0.00 09-Dec-23 A 12-Dec-23 A 09-Dec-23 12-Dec-23 0.00 643 Temp Line 2Temp Line 2Temp Line 2 53.00 51.00 0.00 09-Dec-23 A 28-Feb-24 A 09-Dec-23 28-Feb-24 0.00 644 WA2-TMP-2830 String Temporary Line 02 (str Temp 05 - Temp 10)100%3.00 12.00 0.00 09-Dec-23 A 09-Jan-24 A 09-Dec-23 09-Jan-24 0.00 645 WA2-TMP-2860 OUTAGE TBD - Temp Line 2 Cutover @ Temp 11 100%3.00 3.00 0.00 26-Feb-24 A 28-Feb-24 A 26-Feb-24 28-Feb-24 0.00 646 Temp Line 3Temp Line 3Temp Line 3 7.00 49.00 0.00 12-Dec-23 A 28-Feb-24 A 12-Dec-23 28-Feb-24 0.00 647 WA2-TMP-2840 Fully Construct Temp Line 03 - Feb 12-15 (ready for outage)100%7.00 49.00 0.00 12-Dec-23 A 28-Feb-24 A 12-Dec-23 28-Feb-24 0.00 648 Shirley Basin Line Shirley Basin Line TransferShirley Basin Line Transfer 2.00 2.00 0.00 23-Jan-24 A 24-Jan-24 A 23-Jan-24 24-Jan-24 0.00 649 WA3-SBT-9000 Shirley Basin Line Transfer - BG Varaince Required - TBD, moved again, Jan 16 as of dec 12 100%2.00 2.00 0.00 23-Jan-24 A 24-Jan-24 A 23-Jan-24 24-Jan-24 0.00 650 Cutover at Str Wa-Cutover at Str Wa-152, energize through Wa-1-152Cutover at Str Wa-152, energize through Wa-1-152 4.00 7.00 0.00 21-Feb-24 A 28-Feb-24 A 21-Feb-24 28-Feb-24 0.00 651 WA3-STR-3800 OUTAGE CUTOVER - Energize through new Wa Line Str 1-152 100%4.00 7.00 0.00 21-Feb-24 A 28-Feb-24 A 21-Feb-24 28-Feb-24 0.00 652 TB Flats Re-routeTB Flats Re-routeTB Flats Re-route 4.00 3.00 0.00 01-Feb-24 A 03-Feb-24 A 01-Feb-24 03-Feb-24 0.00 653 WA3-SBT-9020 OUTAGE START - TB Flats 100%0.00 0.00 0.00 01-Feb-24 A 01-Feb-24 0.00 654 WA3-SBT-9010 TB Flatts reroute 100%4.00 3.00 0.00 01-Feb-24 A 03-Feb-24 A 01-Feb-24 03-Feb-24 0.00 655 (1) 1Wc-149 to 1W(1) 1Wc-149 to 1Wc-208(1) 1Wc-149 to 1Wc-208 46.67 0.00 46.67 20-Sep-24 13-Nov-24 0.33 20-Sep-24 13-Nov-24 0.00 656 Wa Salvage & Re bWa Salvage & Rebuild Str Wa151-206Wa Salvage & Rebuild Str Wa151-206 46.67 0.00 46.67 20-Sep-24 13-Nov-24 0.33 20-Sep-24 13-Nov-24 0.00 657 SalvageSalvageSalvage 19.18 0.00 19.18 20-Sep-24 12-Oct-24 0.82 20-Sep-24 12-Oct-24 0.00 658 WA4-SLV-1900 Structure Salvage: Wa-149 0%0.32 0.00 0.32 20-Sep-24 20-Sep-24 0.33 20-Sep-24 20-Sep-24 0.00 659 WA4-SLV-1910 Structure Salvage: Wa-150 0%0.32 0.00 0.32 20-Sep-24 20-Sep-24 0.82 20-Sep-24 20-Sep-24 0.00 660 WA4-SLV-1920 Structure Salvage: Wa-151 0%0.32 0.00 0.32 20-Sep-24 20-Sep-24 0.82 20-Sep-24 20-Sep-24 0.00 661 WA4-SLV-1930 Structure Salvage: Wa-152 0%0.32 0.00 0.32 20-Sep-24 21-Sep-24 0.82 20-Sep-24 21-Sep-24 0.00 662 WA4-SLV-1940 Structure Salvage: Wa-153 0%0.32 0.00 0.32 21-Sep-24 21-Sep-24 0.82 21-Sep-24 21-Sep-24 0.00 663 WA4-SLV-1950 Structure Salvage: Wa-154 0%0.32 0.00 0.32 21-Sep-24 21-Sep-24 0.82 21-Sep-24 21-Sep-24 0.00 664 WA4-SLV-1960 Structure Salvage: Wa-155 0%0.32 0.00 0.32 21-Sep-24 23-Sep-24 0.82 21-Sep-24 23-Sep-24 0.00 665 WA4-SLV-1970 Structure Salvage: Wa-156 0%0.32 0.00 0.32 23-Sep-24 23-Sep-24 0.82 23-Sep-24 23-Sep-24 0.00 666 WA4-SLV-1980 Structure Salvage: Wa-157 0%0.32 0.00 0.32 23-Sep-24 23-Sep-24 0.82 23-Sep-24 23-Sep-24 0.00 667 WA4-SLV-1990 Structure Salvage: Wa-158 0%0.32 0.00 0.32 23-Sep-24 24-Sep-24 0.82 23-Sep-24 24-Sep-24 0.00 668 WA4-SLV-2000 Structure Salvage: Wa-159 0%0.32 0.00 0.32 24-Sep-24 24-Sep-24 0.82 24-Sep-24 24-Sep-24 0.00 669 WA4-SLV-2010 Structure Salvage: Wa-160 0%0.32 0.00 0.32 24-Sep-24 24-Sep-24 0.82 24-Sep-24 24-Sep-24 0.00 670 WA4-SLV-2020 Structure Salvage: Wa-161 0%0.32 0.00 0.32 24-Sep-24 25-Sep-24 0.82 24-Sep-24 25-Sep-24 0.00 671 WA4-SLV-2030 Structure Salvage: Wa-162 0%0.32 0.00 0.32 25-Sep-24 25-Sep-24 0.82 25-Sep-24 25-Sep-24 0.00 672 WA4-SLV-2040 Structure Salvage: Wa-163 0%0.32 0.00 0.32 25-Sep-24 25-Sep-24 0.82 25-Sep-24 25-Sep-24 0.00 673 WA4-SLV-2050 Structure Salvage: Wa-164 0%0.32 0.00 0.32 25-Sep-24 26-Sep-24 0.82 25-Sep-24 26-Sep-24 0.00 674 WA4-SLV-2060 Structure Salvage: Wa-165 0%0.32 0.00 0.32 26-Sep-24 26-Sep-24 0.82 26-Sep-24 26-Sep-24 0.00 675 WA4-SLV-2070 Structure Salvage: Wa-166 0%0.32 0.00 0.32 26-Sep-24 26-Sep-24 0.82 26-Sep-24 26-Sep-24 0.00 676 WA4-SLV-2080 Structure Salvage: Wa-167 0%0.32 0.00 0.32 26-Sep-24 27-Sep-24 0.82 26-Sep-24 27-Sep-24 0.00 677 WA4-SLV-2090 Structure Salvage: Wa-168 0%0.32 0.00 0.32 27-Sep-24 27-Sep-24 0.82 27-Sep-24 27-Sep-24 0.00 678 WA4-SLV-2100 Structure Salvage: Wa-169 0%0.32 0.00 0.32 27-Sep-24 27-Sep-24 0.82 27-Sep-24 27-Sep-24 0.00 679 WA4-SLV-2110 Structure Salvage: Wa-170 0%0.32 0.00 0.32 27-Sep-24 28-Sep-24 0.82 27-Sep-24 28-Sep-24 0.00 680 WA4-SLV-2120 Structure Salvage: Wa-171 0%0.32 0.00 0.32 28-Sep-24 28-Sep-24 0.82 28-Sep-24 28-Sep-24 0.00 681 WA4-SLV-2130 Structure Salvage: Wa-172 0%0.32 0.00 0.32 28-Sep-24 28-Sep-24 0.82 28-Sep-24 28-Sep-24 0.00 682 WA4-SLV-2140 Structure Salvage: Wa-173 0%0.32 0.00 0.32 28-Sep-24 28-Sep-24 0.82 28-Sep-24 28-Sep-24 0.00 683 WA4-SLV-2150 Structure Salvage: Wa-174 0%0.32 0.00 0.32 28-Sep-24 30-Sep-24 0.82 28-Sep-24 30-Sep-24 0.00 684 WA4-SLV-2160 Structure Salvage: Wa-175 0%0.32 0.00 0.32 30-Sep-24 30-Sep-24 0.82 30-Sep-24 30-Sep-24 0.00 685 WA4-SLV-2170 Structure Salvage: Wa-176 0%0.32 0.00 0.32 30-Sep-24 30-Sep-24 0.82 30-Sep-24 30-Sep-24 0.00 686 WA4-SLV-2180 Structure Salvage: Wa-177 0%0.32 0.00 0.32 30-Sep-24 01-Oct-24 0.82 30-Sep-24 01-Oct-24 0.00 687 WA4-SLV-2190 Structure Salvage: Wa-178 0%0.32 0.00 0.32 01-Oct-24 01-Oct-24 0.82 01-Oct-24 01-Oct-24 0.00 688 WA4-SLV-2200 Structure Salvage: Wa-179 0%0.32 0.00 0.32 01-Oct-24 01-Oct-24 0.82 01-Oct-24 01-Oct-24 0.00 689 WA4-SLV-2210 Structure Salvage: Wa-180 0%0.32 0.00 0.32 01-Oct-24 02-Oct-24 0.82 01-Oct-24 02-Oct-24 0.00 690 WA4-SLV-2220 Structure Salvage: Wa-181 0%0.32 0.00 0.32 02-Oct-24 02-Oct-24 0.82 02-Oct-24 02-Oct-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 - Temp 1, 08-Dec-23 A 24 A, Temp Line 2 24 A, Temp Line 3 Shirley Basin Line Transfer 24 A, Cutover at Str Wa-152, energize through Wa-1-152 TB Flats Re-route ART - TB Flats, 13-Nov-24, (1) 1Wc-149 to 1Wc-208 13-Nov-24, Wa Salvage & Rebuild Str Wa151-206 12-Oct-24, Salvage Structure Salvage: Wa-149, 20-Sep-24 Structure Salvage: Wa-150, 20-Sep-24 Structure Salvage: Wa-151, 20-Sep-24 Structure Salvage: Wa-152, 21-Sep-24 Structure Salvage: Wa-153, 21-Sep-24 Structure Salvage: Wa-154, 21-Sep-24 Structure Salvage: Wa-155, 23-Sep-24 Structure Salvage: Wa-156, 23-Sep-24 Structure Salvage: Wa-157, 23-Sep-24 Structure Salvage: Wa-158, 24-Sep-24 Structure Salvage: Wa-159, 24-Sep-24 Structure Salvage: Wa-160, 24-Sep-24 Structure Salvage: Wa-161, 25-Sep-24 Structure Salvage: Wa-162, 25-Sep-24 Structure Salvage: Wa-163, 25-Sep-24 Structure Salvage: Wa-164, 26-Sep-24 Structure Salvage: Wa-165, 26-Sep-24 Structure Salvage: Wa-166, 26-Sep-24 Structure Salvage: Wa-167, 27-Sep-24 Structure Salvage: Wa-168, 27-Sep-24 Structure Salvage: Wa-169, 27-Sep-24 Structure Salvage: Wa-170, 28-Sep-24 Structure Salvage: Wa-171, 28-Sep-24 Structure Salvage: Wa-172, 28-Sep-24 Structure Salvage: Wa-173, 28-Sep-24 Structure Salvage: Wa-174, 30-Sep-24 Structure Salvage: Wa-175, 30-Sep-24 Structure Salvage: Wa-176, 30-Sep-24 Structure Salvage: Wa-177, 01-Oct-24 Structure Salvage: Wa-178, 01-Oct-24 Structure Salvage: Wa-179, 01-Oct-24 Structure Salvage: Wa-180, 02-Oct-24 Structure Salvage: Wa-181, 02-Oct-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 14 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 691 WA4-SLV-2230 Structure Salvage: Wa-182 0%0.32 0.00 0.32 02-Oct-24 02-Oct-24 0.82 02-Oct-24 02-Oct-24 0.00 692 WA4-SLV-2240 Structure Salvage: Wa-183 0%0.32 0.00 0.32 02-Oct-24 03-Oct-24 0.82 02-Oct-24 03-Oct-24 0.00 693 WA4-SLV-2250 Structure Salvage: Wa-184 0%0.32 0.00 0.32 03-Oct-24 03-Oct-24 0.82 03-Oct-24 03-Oct-24 0.00 694 WA4-SLV-2260 Structure Salvage: Wa-185 0%0.32 0.00 0.32 03-Oct-24 03-Oct-24 0.82 03-Oct-24 03-Oct-24 0.00 695 WA4-SLV-2270 Structure Salvage: Wa-186 0%0.32 0.00 0.32 03-Oct-24 04-Oct-24 0.82 03-Oct-24 04-Oct-24 0.00 696 WA4-SLV-2280 Structure Salvage: Wa-187 0%0.32 0.00 0.32 04-Oct-24 04-Oct-24 0.82 04-Oct-24 04-Oct-24 0.00 697 WA4-SLV-2290 Structure Salvage: Wa-188 0%0.32 0.00 0.32 04-Oct-24 04-Oct-24 0.82 04-Oct-24 04-Oct-24 0.00 698 WA4-SLV-2300 Structure Salvage: Wa-189A 0%0.32 0.00 0.32 04-Oct-24 05-Oct-24 0.82 04-Oct-24 05-Oct-24 0.00 699 WA4-SLV-2310 Structure Salvage: Wa-190 0%0.32 0.00 0.32 05-Oct-24 05-Oct-24 0.82 05-Oct-24 05-Oct-24 0.00 700 WA4-SLV-2320 Structure Salvage: Wa-191 0%0.32 0.00 0.32 05-Oct-24 05-Oct-24 0.82 05-Oct-24 05-Oct-24 0.00 701 WA4-SLV-2330 Structure Salvage: Wa-192 0%0.32 0.00 0.32 05-Oct-24 07-Oct-24 0.82 05-Oct-24 07-Oct-24 0.00 702 WA4-SLV-2340 Structure Salvage: Wa-193 0%0.32 0.00 0.32 07-Oct-24 07-Oct-24 0.82 07-Oct-24 07-Oct-24 0.00 703 WA4-SLV-2350 Structure Salvage: Wa-194 0%0.32 0.00 0.32 07-Oct-24 07-Oct-24 0.82 07-Oct-24 07-Oct-24 0.00 704 WA4-SLV-2360 Structure Salvage: Wa-195 0%0.32 0.00 0.32 07-Oct-24 08-Oct-24 0.82 07-Oct-24 08-Oct-24 0.00 705 WA4-SLV-2370 Structure Salvage: Wa-196 0%0.32 0.00 0.32 08-Oct-24 08-Oct-24 0.82 08-Oct-24 08-Oct-24 0.00 706 WA4-SLV-2380 Structure Salvage: Wa-197 0%0.32 0.00 0.32 08-Oct-24 08-Oct-24 0.82 08-Oct-24 08-Oct-24 0.00 707 WA4-SLV-2390 Structure Salvage: Wa-198 0%0.32 0.00 0.32 08-Oct-24 08-Oct-24 0.82 08-Oct-24 08-Oct-24 0.00 708 WA4-SLV-2400 Structure Salvage: Wa-199 0%0.32 0.00 0.32 08-Oct-24 09-Oct-24 0.82 08-Oct-24 09-Oct-24 0.00 709 WA4-SLV-2410 Structure Salvage: Wa-200 0%0.32 0.00 0.32 09-Oct-24 09-Oct-24 0.82 09-Oct-24 09-Oct-24 0.00 710 WA4-SLV-2420 Structure Salvage: Wa-201 0%0.32 0.00 0.32 09-Oct-24 09-Oct-24 0.82 09-Oct-24 09-Oct-24 0.00 711 WA4-SLV-2430 Structure Salvage: Wa-202 0%0.32 0.00 0.32 09-Oct-24 10-Oct-24 0.82 09-Oct-24 10-Oct-24 0.00 712 WA4-SLV-2440 Structure Salvage: Wa-203 0%0.32 0.00 0.32 10-Oct-24 10-Oct-24 0.82 10-Oct-24 10-Oct-24 0.00 713 WA4-SLV-2450 Structure Salvage: Wa-204 0%0.32 0.00 0.32 10-Oct-24 10-Oct-24 0.82 10-Oct-24 10-Oct-24 0.00 714 WA4-SLV-2460 Structure Salvage: Wa-205 0%0.32 0.00 0.32 10-Oct-24 11-Oct-24 0.82 10-Oct-24 11-Oct-24 0.00 715 WA4-SLV-2470 Structure Salvage: Wa-206 0%0.32 0.00 0.32 11-Oct-24 11-Oct-24 0.82 11-Oct-24 11-Oct-24 0.00 716 WA4-SLV-2480 Structure Salvage: Wa-207 0%0.32 0.00 0.32 11-Oct-24 11-Oct-24 0.82 11-Oct-24 11-Oct-24 0.00 717 WA4-SLV-2490 Structure Salvage: Wa-208 0%0.32 0.00 0.32 11-Oct-24 12-Oct-24 0.82 11-Oct-24 12-Oct-24 0.00 718 FrameFrameFrame 19.25 0.00 19.25 24-Sep-24 16-Oct-24 14.93 24-Sep-24 16-Oct-24 0.00 719 WA4-FRM-4600 Frame Structure: Wa-152 (salvage area)0%0.35 0.00 0.35 24-Sep-24 24-Sep-24 0.33 24-Sep-24 24-Sep-24 0.00 720 WA4-FRM-4610 Frame Structure: Wa-153 (salvage area)0%0.35 0.00 0.35 24-Sep-24 25-Sep-24 6.98 24-Sep-24 25-Sep-24 0.00 721 WA4-FRM-4620 Frame Structure: Wa-154 (salvage area)0%0.35 0.00 0.35 25-Sep-24 25-Sep-24 7.13 25-Sep-24 25-Sep-24 0.00 722 WA4-FRM-4630 Frame Structure: Wa-155 (salvage area)0%0.35 0.00 0.35 25-Sep-24 25-Sep-24 7.28 25-Sep-24 25-Sep-24 0.00 723 WA4-FRM-4640 Frame Structure: Wa-156 (salvage area)0%0.35 0.00 0.35 25-Sep-24 26-Sep-24 7.43 25-Sep-24 26-Sep-24 0.00 724 WA4-FRM-4650 Frame Structure: Wa-157 (salvage area)0%0.35 0.00 0.35 26-Sep-24 26-Sep-24 7.58 26-Sep-24 26-Sep-24 0.00 725 WA4-FRM-4660 Frame Structure: Wa-158 (salvage area)0%0.35 0.00 0.35 26-Sep-24 26-Sep-24 7.73 26-Sep-24 26-Sep-24 0.00 726 WA4-FRM-4670 Frame Structure: Wa-159 (salvage area)0%0.35 0.00 0.35 26-Sep-24 27-Sep-24 7.88 26-Sep-24 27-Sep-24 0.00 727 WA4-FRM-4680 Frame Structure: Wa-160 (salvage area)0%0.35 0.00 0.35 27-Sep-24 27-Sep-24 8.03 27-Sep-24 27-Sep-24 0.00 728 WA4-FRM-4690 Frame Structure: Wa-161 (salvage area)0%0.35 0.00 0.35 27-Sep-24 27-Sep-24 8.18 27-Sep-24 27-Sep-24 0.00 729 WA4-FRM-4700 Frame Structure: Wa-162 (salvage area)0%0.35 0.00 0.35 27-Sep-24 28-Sep-24 8.33 27-Sep-24 28-Sep-24 0.00 730 WA4-FRM-4710 Frame Structure: Wa-163 (salvage area)0%0.35 0.00 0.35 28-Sep-24 28-Sep-24 8.43 28-Sep-24 28-Sep-24 0.00 731 WA4-FRM-4720 Frame Structure: Wa-164 (salvage area)0%0.35 0.00 0.35 28-Sep-24 28-Sep-24 8.43 28-Sep-24 28-Sep-24 0.00 732 WA4-FRM-4730 Frame Structure: Wa-165 (salvage area)0%0.35 0.00 0.35 28-Sep-24 30-Sep-24 8.43 28-Sep-24 30-Sep-24 0.00 733 WA4-FRM-4740 Frame Structure: Wa-166 (salvage area)0%0.35 0.00 0.35 30-Sep-24 30-Sep-24 8.43 30-Sep-24 30-Sep-24 0.00 734 WA4-FRM-4750 Frame Structure: Wa-167 (salvage area)0%0.35 0.00 0.35 30-Sep-24 30-Sep-24 8.58 30-Sep-24 30-Sep-24 0.00 735 WA4-FRM-4760 Frame Structure: Wa-168 (salvage area)0%0.35 0.00 0.35 30-Sep-24 01-Oct-24 8.73 30-Sep-24 01-Oct-24 0.00 736 WA4-FRM-4770 Frame Structure: Wa-169 (salvage area)0%0.35 0.00 0.35 01-Oct-24 01-Oct-24 8.88 01-Oct-24 01-Oct-24 0.00 737 WA4-FRM-4780 Frame Structure: Wa-170 (salvage area)0%0.35 0.00 0.35 01-Oct-24 01-Oct-24 9.03 01-Oct-24 01-Oct-24 0.00 738 WA4-FRM-4790 Frame Structure: Wa-171 (salvage area)0%0.35 0.00 0.35 01-Oct-24 02-Oct-24 9.18 01-Oct-24 02-Oct-24 0.00 739 WA4-FRM-4800 Frame Structure: Wa-172 (salvage area)0%0.35 0.00 0.35 02-Oct-24 02-Oct-24 9.33 02-Oct-24 02-Oct-24 0.00 740 WA4-FRM-4810 Frame Structure: Wa-173 (salvage area)0%0.35 0.00 0.35 02-Oct-24 03-Oct-24 9.48 02-Oct-24 03-Oct-24 0.00 741 WA4-FRM-4820 Frame Structure: Wa-174 (salvage area)0%0.35 0.00 0.35 03-Oct-24 03-Oct-24 9.63 03-Oct-24 03-Oct-24 0.00 742 WA4-FRM-4830 Frame Structure: Wa-175 (salvage area)0%0.35 0.00 0.35 03-Oct-24 03-Oct-24 9.78 03-Oct-24 03-Oct-24 0.00 743 WA4-FRM-4840 Frame Structure: Wa-176 (salvage area)0%0.35 0.00 0.35 03-Oct-24 04-Oct-24 9.93 03-Oct-24 04-Oct-24 0.00 744 WA4-FRM-4850 Frame Structure: Wa-177 (salvage area)0%0.35 0.00 0.35 04-Oct-24 04-Oct-24 10.08 04-Oct-24 04-Oct-24 0.00 745 WA4-FRM-4860 Frame Structure: Wa-178 (salvage area)0%0.35 0.00 0.35 04-Oct-24 04-Oct-24 10.23 04-Oct-24 04-Oct-24 0.00 746 WA4-FRM-4870 Frame Structure: Wa-179 (salvage area)0%0.35 0.00 0.35 04-Oct-24 05-Oct-24 10.38 04-Oct-24 05-Oct-24 0.00 747 WA4-FRM-4880 Frame Structure: Wa-180 (salvage area)0%0.35 0.00 0.35 05-Oct-24 05-Oct-24 10.53 05-Oct-24 05-Oct-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Structure Salvage: Wa-182, 02-Oct-24 Structure Salvage: Wa-183, 03-Oct-24 Structure Salvage: Wa-184, 03-Oct-24 Structure Salvage: Wa-185, 03-Oct-24 Structure Salvage: Wa-186, 04-Oct-24 Structure Salvage: Wa-187, 04-Oct-24 Structure Salvage: Wa-188, 04-Oct-24 Structure Salvage: Wa-189A, 05-Oct-24 Structure Salvage: Wa-190, 05-Oct-24 Structure Salvage: Wa-191, 05-Oct-24 Structure Salvage: Wa-192, 07-Oct-24 Structure Salvage: Wa-193, 07-Oct-24 Structure Salvage: Wa-194, 07-Oct-24 Structure Salvage: Wa-195, 08-Oct-24 Structure Salvage: Wa-196, 08-Oct-24 Structure Salvage: Wa-197, 08-Oct-24 Structure Salvage: Wa-198, 08-Oct-24 Structure Salvage: Wa-199, 09-Oct-24 Structure Salvage: Wa-200, 09-Oct-24 Structure Salvage: Wa-201, 09-Oct-24 Structure Salvage: Wa-202, 10-Oct-24 Structure Salvage: Wa-203, 10-Oct-24 Structure Salvage: Wa-204, 10-Oct-24 Structure Salvage: Wa-205, 11-Oct-24 Structure Salvage: Wa-206, 11-Oct-24 Structure Salvage: Wa-207, 11-Oct-24 Structure Salvage: Wa-208, 12-Oct-24 16-Oct-24, Frame Frame Structure: Wa-152 (salvage area), 24-Sep-24 Frame Structure: Wa-153 (salvage area), 25-Sep-24 Frame Structure: Wa-154 (salvage area), 25-Sep-24 Frame Structure: Wa-155 (salvage area), 25-Sep-24 Frame Structure: Wa-156 (salvage area), 26-Sep-24 Frame Structure: Wa-157 (salvage area), 26-Sep-24 Frame Structure: Wa-158 (salvage area), 26-Sep-24 Frame Structure: Wa-159 (salvage area), 27-Sep-24 Frame Structure: Wa-160 (salvage area), 27-Sep-24 Frame Structure: Wa-161 (salvage area), 27-Sep-24 Frame Structure: Wa-162 (salvage area), 28-Sep-24 Frame Structure: Wa-163 (salvage area), 28-Sep-24 Frame Structure: Wa-164 (salvage area), 28-Sep-24 Frame Structure: Wa-165 (salvage area), 30-Sep-24 Frame Structure: Wa-166 (salvage area), 30-Sep-24 Frame Structure: Wa-167 (salvage area), 30-Sep-24 Frame Structure: Wa-168 (salvage area), 01-Oct-24 Frame Structure: Wa-169 (salvage area), 01-Oct-24 Frame Structure: Wa-170 (salvage area), 01-Oct-24 Frame Structure: Wa-171 (salvage area), 02-Oct-24 Frame Structure: Wa-172 (salvage area), 02-Oct-24 Frame Structure: Wa-173 (salvage area), 03-Oct-24 Frame Structure: Wa-174 (salvage area), 03-Oct-24 Frame Structure: Wa-175 (salvage area), 03-Oct-24 Frame Structure: Wa-176 (salvage area), 04-Oct-24 Frame Structure: Wa-177 (salvage area), 04-Oct-24 Frame Structure: Wa-178 (salvage area), 04-Oct-24 Frame Structure: Wa-179 (salvage area), 05-Oct-24 Frame Structure: Wa-180 (salvage area), 05-Oct-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 15 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 748 WA4-FRM-4890 Frame Structure: Wa-181 (salvage area)0%0.35 0.00 0.35 05-Oct-24 05-Oct-24 10.68 05-Oct-24 05-Oct-24 0.00 749 WA4-FRM-4900 Frame Structure: Wa-182 (salvage area)0%0.35 0.00 0.35 05-Oct-24 07-Oct-24 10.83 05-Oct-24 07-Oct-24 0.00 750 WA4-FRM-4910 Frame Structure: Wa-183 (salvage area)0%0.35 0.00 0.35 07-Oct-24 07-Oct-24 10.98 07-Oct-24 07-Oct-24 0.00 751 WA4-FRM-4920 Frame Structure: Wa-184 (salvage area)0%0.35 0.00 0.35 07-Oct-24 07-Oct-24 11.13 07-Oct-24 07-Oct-24 0.00 752 WA4-FRM-4930 Frame Structure: Wa-185 (salvage area)0%0.35 0.00 0.35 07-Oct-24 08-Oct-24 11.28 07-Oct-24 08-Oct-24 0.00 753 WA4-FRM-4940 Frame Structure: Wa-186 (salvage area)0%0.35 0.00 0.35 08-Oct-24 08-Oct-24 11.43 08-Oct-24 08-Oct-24 0.00 754 WA4-FRM-4950 Frame Structure: Wa-187 (salvage area)0%0.35 0.00 0.35 08-Oct-24 08-Oct-24 11.58 08-Oct-24 08-Oct-24 0.00 755 WA4-FRM-4960 Frame Structure: Wa-188 (salvage area)0%0.35 0.00 0.35 08-Oct-24 09-Oct-24 11.73 08-Oct-24 09-Oct-24 0.00 756 WA4-FRM-4970 Frame Structure: Wa-189 (salvage area)0%0.35 0.00 0.35 09-Oct-24 09-Oct-24 11.88 09-Oct-24 09-Oct-24 0.00 757 WA4-FRM-4980 Frame Structure: Wa-190 (salvage area)0%0.35 0.00 0.35 09-Oct-24 09-Oct-24 12.53 09-Oct-24 09-Oct-24 0.00 758 WA4-FRM-4990 Frame Structure: Wa-191 (salvage area)0%0.35 0.00 0.35 09-Oct-24 10-Oct-24 12.68 09-Oct-24 10-Oct-24 0.00 759 WA4-FRM-5000 Frame Structure: Wa-192 (salvage area)0%0.35 0.00 0.35 10-Oct-24 10-Oct-24 12.83 10-Oct-24 10-Oct-24 0.00 760 WA4-FRM-5010 Frame Structure: Wa-193 (salvage area)0%0.35 0.00 0.35 10-Oct-24 11-Oct-24 12.98 10-Oct-24 11-Oct-24 0.00 761 WA4-FRM-5020 Frame Structure: Wa-194 (salvage area)0%0.35 0.00 0.35 11-Oct-24 11-Oct-24 13.13 11-Oct-24 11-Oct-24 0.00 762 WA4-FRM-5030 Frame Structure: Wa-195 (salvage area)0%0.35 0.00 0.35 11-Oct-24 11-Oct-24 13.28 11-Oct-24 11-Oct-24 0.00 763 WA4-FRM-5040 Frame Structure: Wa-196 (salvage area)0%0.35 0.00 0.35 11-Oct-24 12-Oct-24 13.43 11-Oct-24 12-Oct-24 0.00 764 WA4-FRM-5050 Frame Structure: Wa-197 (salvage area)0%0.35 0.00 0.35 12-Oct-24 12-Oct-24 13.58 12-Oct-24 12-Oct-24 0.00 765 WA4-FRM-5060 Frame Structure: Wa-198 (salvage area)0%0.35 0.00 0.35 12-Oct-24 12-Oct-24 13.73 12-Oct-24 12-Oct-24 0.00 766 WA4-FRM-5070 Frame Structure: Wa-199 (salvage area)0%0.35 0.00 0.35 12-Oct-24 14-Oct-24 13.88 12-Oct-24 14-Oct-24 0.00 767 WA4-FRM-5080 Frame Structure: Wa-200 (salvage area)0%0.35 0.00 0.35 14-Oct-24 14-Oct-24 14.03 14-Oct-24 14-Oct-24 0.00 768 WA4-FRM-5090 Frame Structure: Wa-201 (salvage area)0%0.35 0.00 0.35 14-Oct-24 14-Oct-24 14.18 14-Oct-24 14-Oct-24 0.00 769 WA4-FRM-5100 Frame Structure: Wa-202 (salvage area)0%0.35 0.00 0.35 14-Oct-24 15-Oct-24 14.33 14-Oct-24 15-Oct-24 0.00 770 WA4-FRM-5110 Frame Structure: Wa-203 (salvage area)0%0.35 0.00 0.35 15-Oct-24 15-Oct-24 14.48 15-Oct-24 15-Oct-24 0.00 771 WA4-FRM-5120 Frame Structure: Wa-204 (salvage area)0%0.35 0.00 0.35 15-Oct-24 15-Oct-24 14.63 15-Oct-24 15-Oct-24 0.00 772 WA4-FRM-5130 Frame Structure: Wa-205 (salvage area)0%0.35 0.00 0.35 15-Oct-24 16-Oct-24 14.78 15-Oct-24 16-Oct-24 0.00 773 WA4-FRM-5140 Frame Structure: Wa-206 (salvage area)0%0.35 0.00 0.35 16-Oct-24 16-Oct-24 14.93 16-Oct-24 16-Oct-24 0.00 774 SetSetSet 27.50 0.00 27.50 01-Oct-24 02-Nov-24 0.83 01-Oct-24 02-Nov-24 0.00 775 Crew 2 Set Structure: Wa-152 0%0.50 0.00 0.50 01-Oct-24 02-Oct-24 0.33 01-Oct-24 02-Oct-24 0.00 776 WA4-SET-4710 Set Structure: Wa-153 0%0.50 0.00 0.50 02-Oct-24 02-Oct-24 0.33 02-Oct-24 02-Oct-24 0.00 777 WA4-SET-4720 Set Structure: Wa-154 0%0.50 0.00 0.50 02-Oct-24 03-Oct-24 0.33 02-Oct-24 03-Oct-24 0.00 778 WA4-SET-4730 Set Structure: Wa-155 0%0.50 0.00 0.50 03-Oct-24 03-Oct-24 0.33 03-Oct-24 03-Oct-24 0.00 779 WA4-SET-4740 Set Structure: Wa-156 0%0.50 0.00 0.50 03-Oct-24 04-Oct-24 0.33 03-Oct-24 04-Oct-24 0.00 780 WA4-SET-4750 Set Structure: Wa-157 0%0.50 0.00 0.50 04-Oct-24 04-Oct-24 0.33 04-Oct-24 04-Oct-24 0.00 781 WA4-SET-4760 Set Structure: Wa-158 0%0.50 0.00 0.50 04-Oct-24 05-Oct-24 0.33 04-Oct-24 05-Oct-24 0.00 782 WA4-SET-4770 Set Structure: Wa-159 0%0.50 0.00 0.50 05-Oct-24 05-Oct-24 0.33 05-Oct-24 05-Oct-24 0.00 783 WA4-SET-4780 Set Structure: Wa-160 0%0.50 0.00 0.50 05-Oct-24 07-Oct-24 0.33 05-Oct-24 07-Oct-24 0.00 784 WA4-SET-4790 Set Structure: Wa-161 0%0.50 0.00 0.50 07-Oct-24 07-Oct-24 0.33 07-Oct-24 07-Oct-24 0.00 785 WA4-SET-4800 Set Structure: Wa-162 0%0.50 0.00 0.50 07-Oct-24 08-Oct-24 0.33 07-Oct-24 08-Oct-24 0.00 786 WA4-SET-4810 Set Structure: Wa-163 0%0.50 0.00 0.50 08-Oct-24 08-Oct-24 0.33 08-Oct-24 08-Oct-24 0.00 787 WA4-SET-4820 Set Structure: Wa-164 0%0.50 0.00 0.50 08-Oct-24 09-Oct-24 0.33 08-Oct-24 09-Oct-24 0.00 788 WA4-SET-4830 Set Structure: Wa-165 0%0.50 0.00 0.50 09-Oct-24 09-Oct-24 0.33 09-Oct-24 09-Oct-24 0.00 789 WA4-SET-4840 Set Structure: Wa-166 0%0.50 0.00 0.50 09-Oct-24 10-Oct-24 0.33 09-Oct-24 10-Oct-24 0.00 790 WA4-SET-4850 Set Structure: Wa-167 0%0.50 0.00 0.50 10-Oct-24 10-Oct-24 0.33 10-Oct-24 10-Oct-24 0.00 791 WA4-SET-4860 Set Structure: Wa-168 0%0.50 0.00 0.50 10-Oct-24 11-Oct-24 0.33 10-Oct-24 11-Oct-24 0.00 792 WA4-SET-4870 Set Structure: Wa-169 0%0.50 0.00 0.50 11-Oct-24 11-Oct-24 0.33 11-Oct-24 11-Oct-24 0.00 793 WA4-SET-4880 Set Structure: Wa-170 0%0.50 0.00 0.50 11-Oct-24 12-Oct-24 0.33 11-Oct-24 12-Oct-24 0.00 794 WA4-SET-4890 Set Structure: Wa-171 0%0.50 0.00 0.50 12-Oct-24 12-Oct-24 0.33 12-Oct-24 12-Oct-24 0.00 795 WA4-SET-4900 Set Structure: Wa-172 0%0.50 0.00 0.50 12-Oct-24 14-Oct-24 0.33 12-Oct-24 14-Oct-24 0.00 796 WA4-SET-4910 Set Structure: Wa-173 0%0.50 0.00 0.50 14-Oct-24 14-Oct-24 0.33 14-Oct-24 14-Oct-24 0.00 797 WA4-SET-4920 Set Structure: Wa-174 0%0.50 0.00 0.50 14-Oct-24 15-Oct-24 0.33 14-Oct-24 15-Oct-24 0.00 798 WA4-SET-4930 Set Structure: Wa-175 0%0.50 0.00 0.50 15-Oct-24 15-Oct-24 0.33 15-Oct-24 15-Oct-24 0.00 799 WA4-SET-4940 Set Structure: Wa-176 0%0.50 0.00 0.50 15-Oct-24 16-Oct-24 0.33 15-Oct-24 16-Oct-24 0.00 800 WA4-SET-4950 Set Structure: Wa-177 0%0.50 0.00 0.50 16-Oct-24 16-Oct-24 0.33 16-Oct-24 16-Oct-24 0.00 801 WA4-SET-4960 Set Structure: Wa-178 0%0.50 0.00 0.50 16-Oct-24 17-Oct-24 0.33 16-Oct-24 17-Oct-24 0.00 802 WA4-SET-4970 Set Structure: Wa-179 0%0.50 0.00 0.50 17-Oct-24 17-Oct-24 0.33 17-Oct-24 17-Oct-24 0.00 803 WA4-SET-4980 Set Structure: Wa-180 0%0.50 0.00 0.50 17-Oct-24 18-Oct-24 0.33 17-Oct-24 18-Oct-24 0.00 804 WA4-SET-4990 Set Structure: Wa-181 0%0.50 0.00 0.50 18-Oct-24 18-Oct-24 0.33 18-Oct-24 18-Oct-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structure: Wa-181 (salvage area), 05-Oct-24 Frame Structure: Wa-182 (salvage area), 07-Oct-24 Frame Structure: Wa-183 (salvage area), 07-Oct-24 Frame Structure: Wa-184 (salvage area), 07-Oct-24 Frame Structure: Wa-185 (salvage area), 08-Oct-24 Frame Structure: Wa-186 (salvage area), 08-Oct-24 Frame Structure: Wa-187 (salvage area), 08-Oct-24 Frame Structure: Wa-188 (salvage area), 09-Oct-24 Frame Structure: Wa-189 (salvage area), 09-Oct-24 Frame Structure: Wa-190 (salvage area), 09-Oct-24 Frame Structure: Wa-191 (salvage area), 10-Oct-24 Frame Structure: Wa-192 (salvage area), 10-Oct-24 Frame Structure: Wa-193 (salvage area), 11-Oct-24 Frame Structure: Wa-194 (salvage area), 11-Oct-24 Frame Structure: Wa-195 (salvage area), 11-Oct-24 Frame Structure: Wa-196 (salvage area), 12-Oct-24 Frame Structure: Wa-197 (salvage area), 12-Oct-24 Frame Structure: Wa-198 (salvage area), 12-Oct-24 Frame Structure: Wa-199 (salvage area), 14-Oct-24 Frame Structure: Wa-200 (salvage area), 14-Oct-24 Frame Structure: Wa-201 (salvage area), 14-Oct-24 Frame Structure: Wa-202 (salvage area), 15-Oct-24 Frame Structure: Wa-203 (salvage area), 15-Oct-24 Frame Structure: Wa-204 (salvage area), 15-Oct-24 Frame Structure: Wa-205 (salvage area), 16-Oct-24 Frame Structure: Wa-206 (salvage area), 16-Oct-24 02-Nov-24, Set Set Structure: Wa-152, 02-Oct-24 Set Structure: Wa-153, 02-Oct-24 Set Structure: Wa-154, 03-Oct-24 Set Structure: Wa-155, 03-Oct-24 Set Structure: Wa-156, 04-Oct-24 Set Structure: Wa-157, 04-Oct-24 Set Structure: Wa-158, 05-Oct-24 Set Structure: Wa-159, 05-Oct-24 Set Structure: Wa-160, 07-Oct-24 Set Structure: Wa-161, 07-Oct-24 Set Structure: Wa-162, 08-Oct-24 Set Structure: Wa-163, 08-Oct-24 Set Structure: Wa-164, 09-Oct-24 Set Structure: Wa-165, 09-Oct-24 Set Structure: Wa-166, 10-Oct-24 Set Structure: Wa-167, 10-Oct-24 Set Structure: Wa-168, 11-Oct-24 Set Structure: Wa-169, 11-Oct-24 Set Structure: Wa-170, 12-Oct-24 Set Structure: Wa-171, 12-Oct-24 Set Structure: Wa-172, 14-Oct-24 Set Structure: Wa-173, 14-Oct-24 Set Structure: Wa-174, 15-Oct-24 Set Structure: Wa-175, 15-Oct-24 Set Structure: Wa-176, 16-Oct-24 Set Structure: Wa-177, 16-Oct-24 Set Structure: Wa-178, 17-Oct-24 Set Structure: Wa-179, 17-Oct-24 Set Structure: Wa-180, 18-Oct-24 Set Structure: Wa-181, 18-Oct-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 16 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 805 WA4-SET-5000 Set Structure: Wa-182 0%0.50 0.00 0.50 18-Oct-24 19-Oct-24 0.33 18-Oct-24 19-Oct-24 0.00 806 WA4-SET-5010 Set Structure: Wa-183 0%0.50 0.00 0.50 19-Oct-24 19-Oct-24 0.33 19-Oct-24 19-Oct-24 0.00 807 WA4-SET-5020 Set Structure: Wa-184 0%0.50 0.00 0.50 19-Oct-24 21-Oct-24 0.33 19-Oct-24 21-Oct-24 0.00 808 WA4-SET-5030 Set Structure: Wa-185 0%0.50 0.00 0.50 21-Oct-24 21-Oct-24 0.33 21-Oct-24 21-Oct-24 0.00 809 WA4-SET-5040 Set Structure: Wa-186 0%0.50 0.00 0.50 21-Oct-24 22-Oct-24 0.33 21-Oct-24 22-Oct-24 0.00 810 WA4-SET-5050 Set Structure: Wa-187 0%0.50 0.00 0.50 22-Oct-24 22-Oct-24 0.33 22-Oct-24 22-Oct-24 0.00 811 WA4-SET-5060 Set Structure: Wa-188 0%0.50 0.00 0.50 22-Oct-24 23-Oct-24 0.33 22-Oct-24 23-Oct-24 0.00 812 WA4-SET-5070 Set Structure: Wa-189 0%0.50 0.00 0.50 23-Oct-24 23-Oct-24 0.33 23-Oct-24 23-Oct-24 0.00 813 WA4-SET-5080 Set Structure: Wa-190 0%0.50 0.00 0.50 23-Oct-24 24-Oct-24 0.83 23-Oct-24 24-Oct-24 0.00 814 WA4-SET-5090 Set Structure: Wa-191 0%0.50 0.00 0.50 24-Oct-24 24-Oct-24 0.83 24-Oct-24 24-Oct-24 815 WA4-SET-5100 Set Structure: Wa-192 0%0.50 0.00 0.50 24-Oct-24 25-Oct-24 0.83 24-Oct-24 25-Oct-24 0.00 816 WA4-SET-5110 Set Structure: Wa-193 0%0.50 0.00 0.50 25-Oct-24 25-Oct-24 0.83 25-Oct-24 25-Oct-24 0.00 817 WA4-SET-5120 Set Structure: Wa-194 0%0.50 0.00 0.50 25-Oct-24 26-Oct-24 0.83 25-Oct-24 26-Oct-24 0.00 818 WA4-SET-5130 Set Structure: Wa-195 0%0.50 0.00 0.50 26-Oct-24 26-Oct-24 0.83 26-Oct-24 26-Oct-24 0.00 819 WA4-SET-5140 Set Structure: Wa-196 0%0.50 0.00 0.50 26-Oct-24 28-Oct-24 0.83 26-Oct-24 28-Oct-24 0.00 820 WA4-SET-5150 Set Structure: Wa-197 0%0.50 0.00 0.50 28-Oct-24 28-Oct-24 0.83 28-Oct-24 28-Oct-24 0.00 821 WA4-SET-5160 Set Structure: Wa-198 0%0.50 0.00 0.50 28-Oct-24 29-Oct-24 0.83 28-Oct-24 29-Oct-24 0.00 822 WA4-SET-5170 Set Structure: Wa-199 0%0.50 0.00 0.50 29-Oct-24 29-Oct-24 0.83 29-Oct-24 29-Oct-24 0.00 823 WA4-SET-5180 Set Structure: Wa-200 0%0.50 0.00 0.50 29-Oct-24 30-Oct-24 0.83 29-Oct-24 30-Oct-24 0.00 824 WA4-SET-5190 Set Structure: Wa-201 0%0.50 0.00 0.50 30-Oct-24 30-Oct-24 0.83 30-Oct-24 30-Oct-24 0.00 825 WA4-SET-5200 Set Structure: Wa-202 0%0.50 0.00 0.50 30-Oct-24 31-Oct-24 0.83 30-Oct-24 31-Oct-24 0.00 826 WA4-SET-5210 Set Structure: Wa-203 0%0.50 0.00 0.50 31-Oct-24 31-Oct-24 0.83 31-Oct-24 31-Oct-24 0.00 827 WA4-SET-5220 Set Structure: Wa-204 0%0.50 0.00 0.50 31-Oct-24 01-Nov-24 0.83 31-Oct-24 01-Nov-24 0.00 828 WA4-SET-5230 Set Structure: Wa-205 0%0.50 0.00 0.50 01-Nov-24 01-Nov-24 0.83 01-Nov-24 01-Nov-24 0.00 829 WA4-SET-5240 Set Structure: Wa-206 0%0.50 0.00 0.50 01-Nov-24 02-Nov-24 0.83 01-Nov-24 02-Nov-24 0.00 830 StringStringString 27.49 0.00 27.49 12-Oct-24 13-Nov-24 0.33 12-Oct-24 13-Nov-24 0.00 831 Crew 1Crew 1Crew 1 27.49 0.00 27.49 12-Oct-24 13-Nov-24 0.33 12-Oct-24 13-Nov-24 0.00 832 WA4-STR-4720 Stringing: Wa-152 - Wa-166 0%9.00 0.00 9.00 12-Oct-24 23-Oct-24 0.82 12-Oct-24 23-Oct-24 0.00 833 WA4-STR-4715 Stringing: Wa-166 - Wa-189 0%9.00 0.00 9.00 23-Oct-24 02-Nov-24 0.33 23-Oct-24 02-Nov-24 0.00 834 WA4-STR-4710 Stringing: Wa-189 - Wa-206 0%9.00 0.00 9.00 02-Nov-24 13-Nov-24 0.33 02-Nov-24 13-Nov-24 0.00 835 Crew 2Crew 2Crew 2 7.00 0.00 7.00 29-Oct-24 06-Nov-24 6.55 29-Oct-24 06-Nov-24 0.00 836 WA4-STR-4760 RE-String: Wa-106 - Wa-113 (due to bird caging of conductor)0%7.00 0.00 7.00 29-Oct-24 06-Nov-24 6.55 29-Oct-24 06-Nov-24 0.00 837 Construction ComConstruction Completion: Clients Elements 2, 3, 5 (Sections 2,3,4)Construction Completion: Clients Elements 2, 3, 5 (Sections 2,3,4)36.95 0.00 36.95 30-Oct-24 15-Dec-24 0.33 30-Oct-24 15-Dec-24 0.00 838 WAA-FIN-0600 FBT Schedule Contigency **Reduced to 0 days with new sequence**0%0.00 0.00 0.00 13-Nov-24 13-Nov-24 0.33 13-Nov-24 13-Nov-24 0.00 839 WAA-FIN-0610 Construction Completion 0%0.00 0.00 0.00 13-Nov-24 0.33 13-Nov-24 0.00 840 WAA-FIN-0620 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW)0%19.00 0.00 19.00 30-Oct-24 21-Nov-24 9.33 30-Oct-24 21-Nov-24 0.00 841 WAA-FIN-0630 Contractor Testing Complete 0%0.00 0.00 0.00 21-Nov-24 9.33 21-Nov-24 0.00 842 WAA-FIN-0650 Mechanical Completion 0%0.00 0.00 0.00 05-Dec-24 0.33 05-Dec-24 0.00 843 WAA-FIN-0640 Punch List Items 0%22.00 0.00 22.00 13-Nov-24 05-Dec-24 0.33 13-Nov-24 05-Dec-24 0.00 844 WAA-FIN-0670 As Built Submittal *reduced from 30d*0%10.00 0.00 10.00 05-Dec-24 15-Dec-24 0.33 05-Dec-24 15-Dec-24 0.00 845 WAA-FIN-0680 Substantial Completion - ISD (Clients Elements: 2,3,4 - Section 2,3,4) (Required: Dec 15, 2023 - updated to Mar 28,2024) 0%0.00 0.00 0.00 15-Dec-24 0.33 15-Dec-24 0.00 846 WAA-FIN-0660 Close Out Deliverables (Permits, Manuals Training aids, etc)*reduced from 30d*0%10.00 0.00 10.00 05-Dec-24 15-Dec-24 0.33 05-Dec-24 15-Dec-24 0.00 847 (5) Aeolus SS to Fre(5) Aeolus SS to Freezeout SS (Finish by October 15, 2023)(5) Aeolus SS to Freezeout SS (Finish by October 15, 2023)280.50 231.00 40.50 11-Sep-23 A 30-Aug-24 306.50 11-Sep-23 30-Aug-24 0.00 848 Access InstallationAccess Installation (2 Crews)Access Installation (2 Crews)15.00 47.00 0.00 11-Sep-23 A 03-Nov-23 A 11-Sep-23 03-Nov-23 0.00 849 AF5-MS-5000 Aeolus to Freezeout Construction Start (Based on Carbon County Permit)100%0.00 0.00 0.00 11-Sep-23 A 11-Sep-23 0.00 850 AF5-ACS-5200 AF Access Installation Pull 1: Aeolus - AF1 (start after July 15)100%3.00 2.00 0.00 11-Sep-23 A 12-Sep-23 A 11-Sep-23 12-Sep-23 0.00 851 AF5-ACS-5210 AF Access Installation Pull 2: AF1 - AF10 100%3.00 2.00 0.00 11-Sep-23 A 12-Sep-23 A 11-Sep-23 12-Sep-23 0.00 852 AF5-ACS-5240 AF Access Installation Pull 5: AF30 - AF31 *crew 1- move to WA8* (2/2)100%3.00 1.00 0.00 16-Sep-23 A 16-Sep-23 A 16-Sep-23 16-Sep-23 0.00 853 AF5-ACS-5220 AF Access Installation Pull 3: AF11 - AF 16 - str 18 issue 100%3.00 2.00 0.00 13-Sep-23 A 28-Sep-23 A 13-Sep-23 28-Sep-23 0.00 854 AF5-ACS-5230 AF Access Installation Pull 4: AF16 - AF30 - note (14/14) *contingent on NSO Watercrossing Variance str 19-25 100%3.00 4.00 0.00 16-Sep-23 A 03-Nov-23 A 16-Sep-23 03-Nov-23 0.00 855 Structure SalvageStructure SalvageStructure Salvage 2.00 2.00 0.00 11-Mar-24 A 12-Mar-24 A 11-Mar-24 12-Mar-24 0.00 856 AF5-SLV-5300 OUTAGE START : Begin AF Structure Modifications March 11 and 12 - constraint required to hold outage start 100%0.00 0.00 0.00 11-Mar-24 A 11-Mar-24 0.00 857 AF5-SLV-5310 Modify Structures (2 Total) needs to done to complete str 31-32 100%2.00 2.00 0.00 11-Mar-24 A 12-Mar-24 A 11-Mar-24 12-Mar-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Set Structure: Wa-182, 19-Oct-24 Set Structure: Wa-183, 19-Oct-24 Set Structure: Wa-184, 21-Oct-24 Set Structure: Wa-185, 21-Oct-24 Set Structure: Wa-186, 22-Oct-24 Set Structure: Wa-187, 22-Oct-24 Set Structure: Wa-188, 23-Oct-24 Set Structure: Wa-189, 23-Oct-24 Set Structure: Wa-190, 24-Oct-24 Set Structure: Wa-191, 24-Oct-24 Set Structure: Wa-192, 25-Oct-24 Set Structure: Wa-193, 25-Oct-24 Set Structure: Wa-194, 26-Oct-24 Set Structure: Wa-195, 26-Oct-24 Set Structure: Wa-196, 28-Oct-24 Set Structure: Wa-197, 28-Oct-24 Set Structure: Wa-198, 29-Oct-24 Set Structure: Wa-199, 29-Oct-24 Set Structure: Wa-200, 30-Oct-24 Set Structure: Wa-201, 30-Oct-24 Set Structure: Wa-202, 31-Oct-24 Set Structure: Wa-203, 31-Oct-24 Set Structure: Wa-204, 01-Nov-24 Set Structure: Wa-205, 01-Nov-24 Set Structure: Wa-206, 02-Nov-24 13-Nov-24, String 13-Nov-24, Crew 1 Stringing: Wa-152 - Wa-166, 23-Oct-24 Stringing: Wa-166 - Wa-189, 02-Nov-24 Stringing: Wa-189 - Wa-206, 13-Nov-24 06-Nov-24, Crew 2 RE-String: Wa-106 - Wa-113 (due to bird caging of conductor), 06-Nov-24 15-Dec-24, Construction Completion: Clients Elements 2, 3, 5 (Sections FBT Schedule Contigency **Reduced to 0 days with new sequence**, 13-N Construction Completion, 13-Nov-24 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW), 21-Nov-24 Contractor Testing Complete, 21-Nov-24 Mechanical Completion, 05-Dec-24 Punch List Items, 05-Dec-24 As Built Submittal *reduced from 30d*, 15-Dec-24 Substantial Completion - ISD (Clients Elements: 2,3,4 - Section 2,3,4) (R Close Out Deliverables (Permits, Manuals Training aids, etc)*reduced from 30-Aug-24, (5) Aeolus SS to Freezeout SS (Finish by October 15, 2023) tion (2 Crews) rt (Based on Carbon County Permit), r-24 A, Structure Salvage GE START : Begin AF Structure Modifications March 11 and 12 - constraint required to hold outage start, Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 17 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 858 AF5-SLV-5320 OUTAGE COMPLETE: AF Structure Mods Complete 100%0.00 0.00 0.00 12-Mar-24 A 12-Mar-24 0.00 859 Drilled Pier FoundDrilled Pier FoundationsDrilled Pier Foundations 176.00 55.00 0.00 18-Sep-23 A 19-Nov-23 A 18-Sep-23 19-Nov-23 0.00 860 AF5-DPF-5495 Mobilize Drilled Pier Crew 2 100%3.27 6.00 0.00 18-Sep-23 A 24-Sep-23 A 18-Sep-23 24-Sep-23 0.00 861 AF5-DPF-5510 Drilled Pier Foundation AF Pull 2: AF1 - AF10 (2/2) str 8 wet 100%6.00 11.73 0.00 25-Sep-23 A 07-Oct-23 A 25-Sep-23 07-Oct-23 0.00 862 AF5-DPF-5500 Drilled Pier Foundation AF Pull 1: Aeolus - AF1 (1/1)100%3.00 3.00 0.00 08-Oct-23 A 11-Oct-23 A 08-Oct-23 11-Oct-23 0.00 863 AF5-DPF-5520 Drilled Pier Foundation AF Pull 3: AF11 - AF 16 - note (1/1) STR 16 100%13.00 5.00 0.00 16-Oct-23 A 08-Nov-23 A 16-Oct-23 08-Nov-23 0.00 864 AF5-DPF-5530 Drilled Pier Foundation AF Pull 4: AF16 - AF30 - note (1/1) STR 30 100%3.00 6.00 0.00 28-Oct-23 A 16-Nov-23 A 28-Oct-23 16-Nov-23 0.00 865 Concrete Curing /Concrete Curing / Strength AchievedConcrete Curing / Strength Achieved 214.73 51.73 0.00 29-Sep-23 A 19-Nov-23 A 29-Sep-23 19-Nov-23 0.00 866 AF5-CON-5515 Concrete Curing Pull 2: STR 5 100%7.00 6.73 0.00 29-Sep-23 A 05-Oct-23 A 29-Sep-23 05-Oct-23 0.00 867 AF5-CON-5525 Concrete Curing Pull 2: STR 8 100%7.00 6.95 0.00 08-Oct-23 A 14-Oct-23 A 08-Oct-23 14-Oct-23 0.00 868 AF5-CON-5505 Concrete Curing Pull 1: STR 1 100%7.00 7.00 0.00 12-Oct-23 A 18-Oct-23 A 12-Oct-23 18-Oct-23 0.00 869 AF5-CON-5535 Concrete Curing Pull 3: STR 11 100%7.00 7.00 0.00 19-Oct-23 A 25-Oct-23 A 19-Oct-23 25-Oct-23 0.00 870 AF5-CON-5545 Concrete Curing Pull 3: STR 16 100%3.00 3.00 0.00 09-Nov-23 A 11-Nov-23 A 09-Nov-23 11-Nov-23 0.00 871 AF5-CON-5555 Concrete Curing Pull 4: STR 30 100%3.00 3.00 0.00 17-Nov-23 A 19-Nov-23 A 17-Nov-23 19-Nov-23 0.00 872 Frame StructuresFrame StructuresFrame Structures 229.73 222.73 5.50 20-Sep-23 A 20-Jul-24 13.50 20-Sep-23 20-Jul-24 0.00 873 AF5-FRM-5955 Mobilize Aelous to Freezeout Addtional Crew 100%0.00 0.00 0.00 20-Sep-23 A 20-Sep-23 0.00 874 AF5-FRM-5600 Frame Structure: Aeolus - AF1 (1/1)100%1.00 1.00 0.00 17-Oct-23 A 17-Oct-23 A 17-Oct-23 17-Oct-23 0.00 875 AF5-FRM-5610 Frame Structure: AF1 - AF10 (9/9)100%3.00 14.73 0.00 20-Sep-23 A 25-Oct-23 A 20-Sep-23 25-Oct-23 0.00 876 AF5-FRM-5620 Frame Structure: AF11 - AF 15 - note (5/5)100%2.00 10.73 0.00 28-Sep-23 A 15-Nov-23 A 28-Sep-23 15-Nov-23 0.00 877 AF5-FRM-5625 Re-mobilize AF Crews 0%2.00 0.00 2.00 15-Jul-24 16-Jul-24 0.50 15-Jul-24 16-Jul-24 0.00 878 AF5-FRM-5630.1 Frame Structure: AF16 75%2.00 5.00 0.50 26-Sep-23 A 17-Jul-24 0.50 26-Sep-23 17-Jul-24 0.00 879 AF5-FRM-5630.2 Frame Structure AF24 75%1.00 5.00 1.00 26-Sep-23 A 18-Jul-24 0.50 26-Sep-23 18-Jul-24 0.00 880 AF5-FRM-5630.3 Frame Structure: AF25 75%1.00 5.00 1.00 26-Sep-23 A 19-Jul-24 12.50 26-Sep-23 19-Jul-24 0.00 881 AF5-FRM-5630.4 Frame Structure: AF30 75%1.00 5.00 1.00 26-Sep-23 A 20-Jul-24 13.50 26-Sep-23 20-Jul-24 0.00 882 Set Structures (IncSet Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)224.23 222.73 6.00 20-Sep-23 A 24-Jul-24 11.50 20-Sep-23 24-Jul-24 0.00 883 AF5-SET-5700 Set Structure: Aeolus - AF1 (1/1)100%1.00 1.00 0.00 17-Oct-23 A 17-Oct-23 A 17-Oct-23 17-Oct-23 0.00 884 AF5-SET-5710 Set Structure: AF1 - AF10 (9/9)100%5.00 29.23 0.00 20-Sep-23 A 24-Oct-23 A 20-Sep-23 24-Oct-23 0.00 885 AF5-SET-5720 Set Structure: AF11 - AF 15 - note (5/5)100%3.00 41.73 0.00 28-Sep-23 A 15-Nov-23 A 28-Sep-23 15-Nov-23 0.00 886 AF5-SET-5730.1 Set Structure: AF16 (too windy to complete)75%3.00 123.73 0.50 26-Sep-23 A 17-Jul-24 3.00 26-Sep-23 17-Jul-24 0.00 887 AF5-SET-5730.2 Set Structure: AF24 75%2.00 123.73 2.00 26-Sep-23 A 20-Jul-24 0.50 26-Sep-23 20-Jul-24 0.00 888 AF5-SET-5730.3 Set Structure: AF25 75%2.00 123.73 2.00 26-Sep-23 A 23-Jul-24 11.50 26-Sep-23 23-Jul-24 0.00 889 AF5-SET-5740.1 Set Structure: AF30 0%1.00 0.00 1.00 23-Jul-24 24-Jul-24 11.50 23-Jul-24 24-Jul-24 0.00 890 AF5-SET-5740.2 Set Structure: AF31 0%1.00 0.00 1.00 23-Jul-24 24-Jul-24 11.50 23-Jul-24 24-Jul-24 0.00 891 Wire StringingWire StringingWire Stringing 227.50 11.00 20.00 23-Oct-23 A 13-Aug-24 0.50 23-Oct-23 13-Aug-24 0.00 892 AF5-STR-5755 Mobilize Stringing Crew 2 100%0.00 0.00 0.00 23-Oct-23 A 23-Oct-23 0.00 893 AF5-STR-5810 Stringing: AF1 - AF11 (Req. daily outages) (move to Wa299-315)100%5.00 10.00 0.00 25-Oct-23 A 03-Nov-23 A 25-Oct-23 03-Nov-23 0.00 894 AF5-STR-5820 Stringing: AF11 - AF 16 0%7.00 0.00 7.00 20-Jul-24 29-Jul-24 0.50 20-Jul-24 29-Jul-24 0.00 895 AF5-STR-5830 Stringing: AF16 - AF30 0%7.00 0.00 7.00 29-Jul-24 06-Aug-24 0.50 29-Jul-24 06-Aug-24 0.00 896 AF5-STR-5840 Stringing: AF30 - AF31 0%2.00 0.00 2.00 06-Aug-24 08-Aug-24 0.50 06-Aug-24 08-Aug-24 0.00 897 AF5-STR-5800 Stringing: Aeolus - AF1 (Substation Not Ready see delay)0%4.00 0.00 4.00 08-Aug-24 13-Aug-24 0.50 08-Aug-24 13-Aug-24 0.00 898 Construction ComConstruction Completion: Clients Elements 8 (Sections 5)Construction Completion: Clients Elements 8 (Sections 5)15.00 0.00 15.00 13-Aug-24 30-Aug-24 306.50 13-Aug-24 30-Aug-24 0.00 899 AF5-FIN-0800 Construction Completion 0%0.00 0.00 0.00 13-Aug-24 0.50 13-Aug-24 0.00 900 AF5-FIN-0810 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW)0%5.50 0.00 5.50 13-Aug-24 19-Aug-24 1.00 13-Aug-24 19-Aug-24 0.00 901 AF5-FIN-0820 Contractor Testing Complete 0%0.00 0.00 0.00 19-Aug-24 1.00 19-Aug-24 0.00 902 AF5-FIN-0840 Mechanical Completion (Required: Oct 15, 2023)0%0.00 0.00 0.00 20-Aug-24 0.50 20-Aug-24 0.00 903 AF5-FIN-0830 Punch List Items 0%6.00 0.00 6.00 13-Aug-24 20-Aug-24 0.50 13-Aug-24 20-Aug-24 0.00 904 AF5-FIN-0880 Final ROW Reclamation and Restorations 0%10.00 0.00 10.00 13-Aug-24 24-Aug-24 80.50 13-Aug-24 24-Aug-24 0.00 905 AF5-FIN-0860 As Built Submittal 0%9.00 0.00 9.00 20-Aug-24 30-Aug-24 0.50 20-Aug-24 30-Aug-24 0.00 906 AF5-FIN-0870 Substantial Completion - ISD (Clients Elements: 8 - Section 5) (Required: Oct 31, 2023) 0%0.00 0.00 0.00 30-Aug-24 0.50 30-Aug-24 0.00 907 AF5-FIN-0850 Close Out Deliverables (Permits, Manuals Training aids, etc)0%9.00 0.00 9.00 20-Aug-24 30-Aug-24 0.50 20-Aug-24 30-Aug-24 0.00 908 1Wc-1 (DJ) to 1Wc 1Wc-1 (DJ) to 1Wc - 1Wc-7/2 (SB)1Wc-1 (DJ) to 1Wc - 1Wc-7/2 (SB)685.00 506.00 356.00 10-Oct-22 A 09-Sep-25 0.00 10-Oct-22 09-Sep-25 0.00 909 ROW AccessROW AccessROW Access 685.00 506.00 356.00 10-Oct-22 A 09-Sep-25 0.00 10-Oct-22 09-Sep-25 0.00 910 202320232023 326.00 357.00 0.00 10-Oct-22 A 16-Dec-23 A 10-Oct-22 16-Dec-23 0.00 911 WC7-MS-7000 Amassa – 1 Wc 148 Construction Start 100%0.00 0.00 0.00 10-Oct-22 A 10-Oct-22 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 GE COMPLETE: AF Structure Mods Complete, 12-Mar-24 A Foundations uring / Strength Achieved 20-Jul-24, Frame Structures nal Crew, Re-mobilize AF Crews, 16-Jul-24 Frame Structure: AF16, 17-Jul-24 Frame Structure AF24, 18-Jul-24 Frame Structure: AF25, 19-Jul-24 Frame Structure: AF30, 20-Jul-24 24-Jul-24, Set Structures (Including 3-Pole Framing) Set Structure: AF16 (too windy to complete), 17-Jul-24 Set Structure: AF24, 20-Jul-24 Set Structure: AF25, 23-Jul-24 Set Structure: AF30, 24-Jul-24 Set Structure: AF31, 24-Jul-24 13-Aug-24, Wire Stringing Stringing: AF11 - AF 16, 29-Jul-24 Stringing: AF16 - AF30, 06-Aug-24 Stringing: AF30 - AF31, 08-Aug-24 Stringing: Aeolus - AF1 (Substation Not Ready see delay), 13-Aug-24 30-Aug-24, Construction Completion: Clients Elements 8 (Sections 5) Construction Completion, 13-Aug-24 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW), 19-Aug-24 Contractor Testing Complete, 19-Aug-24 Mechanical Completion (Required: Oct 15, 2023), 20-Aug-24 Punch List Items, 20-Aug-24 Final ROW Reclamation and Restorations, 24-Aug-24 As Built Submittal, 30-Aug-24 Substantial Completion - ISD (Clients Elements: 8 - Section 5) (Required: Oct 31, 2023), 30 Close Out Deliverables (Permits, Manuals Training aids, etc), 30-Aug-24 09-Sep-25, 1Wc-1 (DJ) to 1 09-Sep-25, ROW Access Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 18 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 912 WC7-ACS-7270 Access Installation Pull 16c: Wc-112 - Wc-137 (Crew 1- start)100%10.00 18.00 0.00 10-Oct-22 A 29-Oct-22 A 10-Oct-22 29-Oct-22 0.00 913 WC7-ACS-7220 Access Installation Pull 11c: Wc-49D - Wc-66 100%1.00 1.00 0.00 12-May-23 A 12-May-23 A 12-May-23 12-May-23 0.00 914 WC6-MS-6000 1Wc: Dave Johnson to Amassa SS Construction Start 100%0.00 0.00 0.00 15-May-23 A 15-May-23 0.00 915 WC6-ACS-6200 Access Installation Pull 1c: Dave Johnson - Wc-1 100%1.00 1.00 0.00 15-May-23 A 15-May-23 A 15-May-23 15-May-23 0.00 916 WC8-MS-8000 1Wc-209 - Heward Construction Start 100%0.00 0.00 0.00 23-Jul-23 A 23-Jul-23 0.00 917 WC8-ACS-8200 Access Installation Pull 24c: Wc-208 - Wc-225 (SUB)100%7.00 8.00 0.00 31-Jul-23 A 08-Aug-23 A 31-Jul-23 08-Aug-23 0.00 918 WC9-ACS-9240 Access Installation: Wc-2/177A - Wc-1/3 100%1.00 2.00 0.00 08-Aug-23 A 09-Aug-23 A 08-Aug-23 09-Aug-23 0.00 919 WC9-ACS-9250 Access Installation Pull 33c: Wc-1/3 - Shirley Basin #1 (SUB)100%4.00 2.00 0.00 08-Sep-23 A 09-Sep-23 A 08-Sep-23 09-Sep-23 0.00 920 WC7-ACS-7260 Access Installation Pull 15c: Wc-106 - Wc-124 (Subcontractor)100%5.00 56.00 0.00 19-Jun-23 A 19-Sep-23 A 19-Jun-23 19-Sep-23 0.00 921 WC8-ACS-8210 Access Installation Pull 25c: Wc-225 - Wc-244 (6/20) (SUB)100%6.00 52.00 0.00 23-Jul-23 A 21-Sep-23 A 23-Jul-23 21-Sep-23 0.00 922 WC7-ACS-7280 Access Installation Pull 17c: Wc-137 - Wc-149 (Subcontractor-end)100%5.00 59.00 0.00 26-Jun-23 A 22-Sep-23 A 26-Jun-23 22-Sep-23 0.00 923 WC8-ACS-8230 Access Installation Pull 27c: Wc-254 - Heward #1(SUB)100%6.00 2.00 0.00 29-Sep-23 A 30-Sep-23 A 29-Sep-23 30-Sep-23 0.00 924 WC9-MS-9000 Heward SS to Shirley Basin SS Construction Start 100%0.00 0.00 0.00 05-Oct-23 A 05-Oct-23 0.00 925 WC9-ACS-9230 Access Installation Pull 31c: Wc-319 - Wc-2/177A (SUB) (2/32)100%4.00 10.00 0.00 05-Oct-23 A 16-Oct-23 A 05-Oct-23 16-Oct-23 0.00 926 WC8-ACS-8220 Access Installation Pull 26c: Wc-244 - Wc-254 100%7.00 47.00 0.00 21-Sep-23 A 29-Nov-23 A 21-Sep-23 29-Nov-23 0.00 927 WC6-ACS-6260 Access Installation Pull 7c: Wc-49A - Wc-49B 100%2.00 3.00 0.00 30-Nov-23 A 02-Dec-23 A 30-Nov-23 02-Dec-23 0.00 928 WC9-ACS-9200 Access Installation Pull 28c: Wc-268 - Wc-288 100%4.00 4.00 0.00 13-Dec-23 A 16-Dec-23 A 13-Dec-23 16-Dec-23 0.00 929 202420242024 681.00 332.00 356.00 16-May-23 A 09-Sep-25 0.00 16-May-23 09-Sep-25 0.00 930 WC6-ACS-6205 Access 2024 Mobilization 100%0.00 0.00 0.00 23-Jan-24 A 23-Jan-24 0.00 931 WC6-ACS-6210 Access Installation: Wc-1 - Wc-2 100%1.00 4.00 0.00 23-Jan-24 A 26-Jan-24 A 23-Jan-24 26-Jan-24 0.00 932 WC6-ACS-6230 Access Installation: Wc-13 - Wc-18 100%2.00 3.00 0.00 24-Jan-24 A 26-Jan-24 A 24-Jan-24 26-Jan-24 0.00 933 WC6-ACS-6220 Access Installation: Wc-2 - Wc-13 100%4.00 4.00 0.00 02-Feb-24 A 06-Feb-24 A 02-Feb-24 06-Feb-24 0.00 934 WC6-ACS-6270 Access Installation: Wc-49B - Amassa Sub 100%2.00 3.00 0.00 06-Feb-24 A 08-Feb-24 A 06-Feb-24 08-Feb-24 0.00 935 WC7-ACS-7210 Access Installation: Wc-49C - Wc-49D 100%3.00 3.00 0.00 06-Feb-24 A 08-Feb-24 A 06-Feb-24 08-Feb-24 0.00 936 WC6-ACS-6240 Access Installation : Wc-19 - Wc-32 (25/25) BG Variance received 100%2.00 235.00 0.00 16-May-23 A 08-Mar-24 A 16-May-23 08-Mar-24 0.00 937 WC7-ACS-7240 Access Installation: Wc-93 - Wc-88 (9/12)100%4.00 4.00 0.00 01-May-24 A 04-May-24 A 01-May-24 04-May-24 0.00 938 WC7-ACS-7230 Access Installation: Wc-87 - Wc-67 plus str Wc-40-49 100%8.00 7.00 0.00 06-May-24 A 13-May-24 A 06-May-24 14-May-24 1.00 939 WC6-ACS-6250 Access Installation: Wc--39A - Wc-32 (2/7)100%5.00 3.00 0.00 03-Jun-24 A 05-Jun-24 A 27-Jun-24 02-Jul-24 23.00 940 WC7-ACS-7200 Access Installation: Amassa #2 - Wc-49C 100%2.00 104.00 0.00 06-Feb-24 A 05-Jun-24 A 06-Feb-24 08-Feb-24 -101.00 941 WA4-ACS-7300 Access Installation: STR 33 - Nest Found TBD (New activity broken out due to enviro issue) 100%1.00 1.00 0.00 24-Jun-24 A 24-Jun-24 A 942 WC7-ACS-7250 Access/Disturbance: Wc-149-94 50%6.00 54.00 5.00 13-Sep-23 A 09-Jul-24 23.58 13-Sep-23 08-Jul-24 -1.00 943 WC9-ACS-9210 Access Installation: Wc-271 - Wc-306 (SUB) active raptor variance required 0%10.00 0.00 10.00 01-Jul-24 15-Jul-24 12.00 15-May-24 25-May-24 -40.00 944 WC9-ACS-9220 Access Installation: Wc-307 - Wc-323 (mountinan clover rest. after Jul 10)0%5.00 0.00 5.00 11-Jul-24 16-Jul-24 32.00 11-Jul-24 16-Jul-24 0.00 945 WA4-ACS-7290 Access/Disturbance: Wa-167 - Wc-210 0%6.00 0.00 6.00 17-Jul-24 23-Jul-24 32.00 17-Jul-24 23-Jul-24 0.00 946 ReclamationReclamationReclamation 356.00 0.00 356.00 01-Jul-24 09-Sep-25 0.00 27-May-24 09-Sep-25 0.00 947 Crew 1Crew 1Crew 1 142.00 0.00 142.00 16-Jul-24 26-Aug-25 12.00 27-May-24 02-Aug-25 -20.00 948 Crew 2 ROW Reclamation: Wa-01-92 0%27.00 0.00 27.00 16-Jul-24 15-Aug-24 12.00 27-May-24 26-Jun-24 -43.00 949 WA3-FIN-0710 ROW Reclamation: Wa-210-255 0%22.00 0.00 22.00 16-Aug-24 10-Sep-24 12.00 24-Jul-24 17-Aug-24 -20.00 950 WC6-FIN-0720 ROW Reclamation: Wc-01-95 0%30.00 0.00 30.00 11-Sep-24 15-Oct-24 12.00 19-Aug-24 21-Sep-24 -20.00 951 WC7-FIN-0730 ROW Reclamation: Wc-96-153 0%23.00 0.00 23.00 16-Oct-24 10-Jul-25 12.00 23-Sep-24 18-Oct-24 -20.00 952 WC1-FIN-0740 ROW Reclamation: Wc-154-204 0%22.00 0.00 22.00 11-Jul-25 05-Aug-25 12.00 19-Oct-24 12-Jul-25 -20.00 953 WA4-FIN-0690 1Wa ROW Reclamation: Wa-167-210 0%18.00 0.00 18.00 06-Aug-25 26-Aug-25 12.00 14-Jul-25 02-Aug-25 -20.00 954 Crew 2Crew 2Crew 2 128.00 0.00 128.00 01-Jul-24 09-Sep-25 0.00 01-Jul-24 09-Sep-25 0.00 955 WA4-FIN-0750 ROW Reclamation: Wa-93-153 0%25.00 0.00 25.00 01-Jul-24 29-Jul-24 9.00 01-Jul-24 29-Jul-24 0.00 956 WA3-FIN-0740 ROW Reclamation: Wa-256-344 0%45.00 0.00 45.00 30-Jul-24 19-Sep-24 9.00 30-Jul-24 19-Sep-24 0.00 957 WC8-FIN-0750 ROW Reclamation: Wc-205-267 0%25.00 0.00 25.00 15-Jul-25 12-Aug-25 0.00 15-Jul-25 12-Aug-25 0.00 958 WC9-FIN-0760 ROW Reclamation: Wc-268-2/177a 0%24.00 0.00 24.00 13-Aug-25 09-Sep-25 0.00 13-Aug-25 09-Sep-25 0.00 959 Drilled Pier FoundDrilled Pier FoundationsDrilled Pier Foundations 196.00 137.00 41.00 08-Dec-23 A 20-Aug-24 53.50 08-Dec-23 20-Aug-24 0.00 960 2023-2024 Fall/Wi2023-2024 Fall/Winter2023-2024 Fall/Winter 93.00 44.00 0.00 20-Jan-24 A 11-Mar-24 A 20-Jan-24 11-Mar-24 0.00 961 Crew 1Crew 1Crew 1 36.00 13.00 0.00 20-Jan-24 A 02-Feb-24 A 20-Jan-24 02-Feb-24 0.00 962 WC8-DPF-8500.2 Drilled Pier Foundation: Wc-232 *anchor bolt delay 100%4.00 6.00 0.00 20-Jan-24 A 26-Jan-24 A 20-Jan-24 26-Jan-24 0.00 963 WC8-DPF-8500.3 Drilled Pier Foundation: Wc-250 100%4.00 6.00 0.00 26-Jan-24 A 31-Jan-24 A 26-Jan-24 31-Jan-24 0.00 964 WC8-DPF-8520c Drilled Pier Foundation: Wc-266 *NSO Variance Delay 100%4.00 3.00 0.00 31-Jan-24 A 02-Feb-24 A 31-Jan-24 02-Feb-24 0.00 965 Crew 2Crew 2Crew 2 86.00 36.00 0.00 30-Jan-24 A 11-Mar-24 A 30-Jan-24 11-Mar-24 0.00 966 WC6-DPF-6520.2 Drilled Pier Foundation: Wc-16 100%5.00 2.00 0.00 04-Feb-24 A 06-Feb-24 A 04-Feb-24 06-Feb-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 onstruction Start, 09-Sep-25, 2024 Mobilization, Access/Disturbance: Wc-149-94, 09-Jul-24 Access Installation: Wc-271 - Wc-306 (SUB) active raptor variance required, 15-Jul-24 Access Installation: Wc-307 - Wc-323 (mountinan clover rest. after Jul 10), 16-Jul-24 Access/Disturbance: Wa-167 - Wc-210, 23-Jul-24 09-Sep-25, Reclamation 26-Aug-25, Crew 1 ROW Reclamation: Wa-01-92, 15-Aug-24 ROW Reclamation: Wa-210-255, 10-Sep-24 ROW Reclamation: Wc-01-95, 15-Oct-24 ROW Reclamation: Wc-96-153, 10-Ju ROW Reclamation: Wc-154-204, 1Wa ROW Reclamation: Wa- 09-Sep-25, Crew 2 ROW Reclamation: Wa-93-153, 29-Jul-24 ROW Reclamation: Wa-256-344, 19-Sep-24 ROW Reclamation: Wc-205-267 ROW Reclamation: Wc-268 20-Aug-24, Drilled Pier Foundations r-24 A , 2023-2024 Fall/Winter Crew 1 r-24 A , Crew 2 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 19 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 967 WC6-DPF-6500 Drilled Pier Foundation: Wc-1 100%5.00 11.00 0.00 30-Jan-24 A 10-Feb-24 A 30-Jan-24 10-Feb-24 0.00 968 WC6-DPF-6520.1 Drilled Pier Foundation: Wc-4 100%5.00 7.00 0.00 14-Feb-24 A 21-Feb-24 A 14-Feb-24 21-Feb-24 0.00 969 WC6-DPF-6510.1 Drilled Pier Foundation: Wc-2 100%5.00 22.00 0.00 05-Feb-24 A 29-Feb-24 A 05-Feb-24 29-Feb-24 0.00 970 WC6-DPF-6520.4 Drilled Pier Foundation: Wc-46 100%5.00 3.00 0.00 06-Mar-24 A 08-Mar-24 A 06-Mar-24 08-Mar-24 0.00 971 WC6-DPF-6520.3 Drilled Pier Foundation: Wc-32 100%5.00 3.00 0.00 08-Mar-24 A 11-Mar-24 A 08-Mar-24 11-Mar-24 0.00 972 Crew 3Crew 3Crew 3 4.00 3.00 0.00 21-Feb-24 A 23-Feb-24 A 21-Feb-24 23-Feb-24 0.00 973 WC7-DPF-7510.1 Drilled Pier Foundation: Wc-49C (variance received) done with outage 100%2.00 2.00 0.00 21-Feb-24 A 22-Feb-24 A 21-Feb-24 22-Feb-24 0.00 974 WC7-DPF-7510.2 Drilled Pier Foundation: Wc-49D (variance received) done with outage 100%4.00 2.00 0.00 22-Feb-24 A 23-Feb-24 A 22-Feb-24 23-Feb-24 0.00 975 2024 Spring/Sum2024 Spring/Summer2024 Spring/Summer 194.00 133.00 39.00 08-Dec-23 A 17-Aug-24 53.00 08-Dec-23 17-Aug-24 0.00 976 Crew 1Crew 1Crew 1 91.00 28.00 39.00 01-May-24 A 17-Aug-24 41.30 01-May-24 17-Aug-24 0.00 977 WC6-DPF-6555 Mobilze DPF 100%0.00 0.00 0.00 01-May-24 A 01-May-24 0.00 978 WC7-DPF-6520.8 Drilled Pier Foundation: Wc-88 100%5.00 4.00 0.00 01-May-24 A 04-May-24 A 01-May-24 06-May-24 1.00 979 WC7-DPF-6520.7 Drilled Pier Foundation: Wc-67 100%5.00 7.00 0.00 07-May-24 A 13-May-24 A 07-May-24 11-May-24 -2.00 980 WC7-DPF-6520.5 Drilled Pier Foundation: Wc-62 100%5.00 5.00 0.00 12-May-24 A 16-May-24 A 18-May-24 23-May-24 7.00 981 WC7-DPF-6520.6 Drilled Pier Foundation: Wc-64 - weather issues, water in hole 100%5.00 18.00 0.00 14-May-24 A 01-Jun-24 A 13-May-24 17-May-24 -14.00 982 WC1-DPF-1410c Drilled Pier Foundation: Wc171 0%4.00 0.00 4.00 01-Jul-24 08-Jul-24 17.78 01-Jul-24 08-Jul-24 0.00 983 WA4-DPF-4410 Drilled Pier Foundation: Str Wa167 (Salv. Sect) *July 10th is the earliest start date in USFS with Goshawk survey's 0%5.00 0.00 5.00 09-Jul-24 13-Jul-24 24.28 09-Jul-24 13-Jul-24 0.00 984 Crew 2 Drilled Pier Foundation: Wc-112 0%5.00 0.00 5.00 15-Jul-24 19-Jul-24 24.28 15-Jul-24 19-Jul-24 0.00 985 WC7-DPF-6520.1 Drilled Pier Foundation: Wc-106 0%5.00 0.00 5.00 20-Jul-24 25-Jul-24 26.00 20-Jul-24 25-Jul-24 0.00 986 WC7-DPF-6520.9 Drilled Pier Foundation: Wc-95 0%5.00 0.00 5.00 26-Jul-24 31-Jul-24 27.18 26-Jul-24 31-Jul-24 0.00 987 WC9-DPF-9500.3 Drilled Pier Foundation: Wc-306 (Eagle Nest)0%5.00 0.00 5.00 01-Aug-24 06-Aug-24 38.30 01-Aug-24 06-Aug-24 0.00 988 WC9-DPF-9500.4 Drilled Pier Foundation: Wc-329 0%5.00 0.00 5.00 07-Aug-24 12-Aug-24 42.30 07-Aug-24 12-Aug-24 0.00 989 WC9-DPF-9500.1 Drilled Pier Foundation: Wc-2/177A 0%5.00 0.00 5.00 13-Aug-24 17-Aug-24 42.30 13-Aug-24 17-Aug-24 0.00 990 Crew 2Crew 2Crew 2 183.00 5.00 23.00 08-Dec-23 A 05-Aug-24 64.00 08-Dec-23 05-Aug-24 0.00 991 WC9-DPF-9500.1 Drilled Pier Foundation: Wc-268 100%4.00 3.00 0.00 08-Dec-23 A 11-Dec-23 A 08-Dec-23 11-Dec-23 0.00 992 WC9-DPF-9500.2 Drilled Pier Foundation: Wc-270 100%4.00 3.00 0.00 11-Dec-23 A 13-Dec-23 A 11-Dec-23 13-Dec-23 0.00 993 WC1-DPF-1410 Drilled Pier Foundation: Wc173 0%5.00 0.00 5.00 10-Jul-24*15-Jul-24 12.53 10-Jul-24 15-Jul-24 0.00 994 WC7-DPF-6530 Drilled Pier Foundation: Wc-124 0%5.00 0.00 5.00 16-Jul-24 20-Jul-24 14.13 16-Jul-24 20-Jul-24 0.00 995 WC7-DPF-6520.1 Drilled Pier Foundation: Wc-122 0%5.00 0.00 5.00 22-Jul-24 26-Jul-24 14.13 22-Jul-24 26-Jul-24 0.00 996 WC8-DPF-8520b Drilled Pier Foundation: Wc-267 *Water crossing 0%3.00 0.00 3.00 27-Jul-24 30-Jul-24 28.53 27-Jul-24 30-Jul-24 0.00 997 WA4-DPF-4410b Drilled Pier Foundation: Str Wa189 (Salv. Sect)0%5.00 0.00 5.00 31-Jul-24 05-Aug-24 65.00 31-Jul-24 05-Aug-24 0.00 998 Concrete Curing /Concrete Curing / Strength AchievedConcrete Curing / Strength Achieved 253.00 178.00 43.00 12-Dec-23 A 20-Aug-24 63.50 12-Dec-23 20-Aug-24 0.00 999 WC9-CON-9505 Concrete Curing: Wc-268 100%3.00 3.00 0.00 12-Dec-23 A 14-Dec-23 A 12-Dec-23 14-Dec-23 0.00 1000 WC9-CON-9515 Concrete Curing: Wc-270 100%3.00 3.00 0.00 14-Dec-23 A 16-Dec-23 A 14-Dec-23 16-Dec-23 0.00 1001 WC8-CON-8505 Concrete Curing: Wc-232 100%3.00 3.00 0.00 27-Jan-24 A 29-Jan-24 A 27-Jan-24 29-Jan-24 0.00 1002 WC8-CON-8515 Concrete Curing: Wc-250 100%3.00 2.95 0.00 01-Feb-24 A 03-Feb-24 A 01-Feb-24 03-Feb-24 0.00 1003 WC8-CON-8525 Concrete Curing: Wc-266 100%3.00 4.00 0.00 03-Feb-24 A 06-Feb-24 A 03-Feb-24 06-Feb-24 0.00 1004 WC6-CON-5595 Concrete Curing: Wc-16 100%3.00 3.00 0.00 07-Feb-24 A 09-Feb-24 A 07-Feb-24 09-Feb-24 0.00 1005 WC6-CON-5565 Concrete Curing: Wc-1 100%3.00 3.00 0.00 11-Feb-24 A 14-Feb-24 A 11-Feb-24 14-Feb-24 0.00 1006 WC6-CON-5585 Concrete Curing: Wc-4 100%3.00 3.00 0.00 22-Feb-24 A 24-Feb-24 A 22-Feb-24 24-Feb-24 0.00 1007 WC7-CON-7615 Concrete Curing: Wc-49C 100%3.00 3.00 0.00 23-Feb-24 A 25-Feb-24 A 23-Feb-24 25-Feb-24 0.00 1008 WC7-CON-7515 Concrete Curing: Wc-49D 100%3.00 3.00 0.00 24-Feb-24 A 26-Feb-24 A 24-Feb-24 26-Feb-24 0.00 1009 WC6-CON-5575 Concrete Curing: Wc- 2 100%3.00 3.00 0.00 01-Mar-24 A 03-Mar-24 A 01-Mar-24 03-Mar-24 0.00 1010 Crew 2 Concrete Curing: Wc-46 100%3.00 3.00 0.00 09-Mar-24 A 11-Mar-24 A 09-Mar-24 11-Mar-24 0.00 1011 WC6-CON-5605 Concrete Curing: Wc- 32 100%3.00 3.00 0.00 12-Mar-24 A 14-Mar-24 A 12-Mar-24 14-Mar-24 0.00 1012 WC7-CON-7555 Concrete Curing: Wc-88 100%3.00 3.00 0.00 05-May-24 A 08-May-24 A 07-May-24 09-May-24 1.95 1013 WC7-CON-7545 Concrete Curing: Wc-67 100%3.00 3.00 0.00 14-May-24 A 16-May-24 A 12-May-24 14-May-24 -2.00 1014 WC7-CON-7525 Concrete Curing: Wc-62 100%3.00 3.00 0.00 17-May-24 A 19-May-24 A 24-May-24 26-May-24 7.00 1015 WC7-CON-7535 Concrete Curing: Wc-64 100%3.00 4.95 0.00 02-Jun-24 A 06-Jun-24 A 18-May-24 20-May-24 -17.00 1016 WC1-CON-1435 Concrete Curing: Wc-171 0%3.00 0.00 3.00 09-Jul-24 11-Jul-24 20.78 09-Jul-24 11-Jul-24 0.00 1017 WA4-CON-4575 Concrete Curing: Wc-167 0%3.00 0.00 3.00 14-Jul-24 16-Jul-24 86.00 14-Jul-24 16-Jul-24 0.00 1018 WC1-CON-1445 Concrete Curing: Wc-173 0%3.00 0.00 3.00 16-Jul-24 18-Jul-24 14.53 16-Jul-24 18-Jul-24 0.00 1019 WC7-CON-7585 Concrete Curing: Wc-112 0%3.00 0.00 3.00 20-Jul-24 22-Jul-24 28.28 20-Jul-24 22-Jul-24 0.00 1020 WC7-CON-7605 Concrete Curing: Wc-124 0%3.00 0.00 3.00 21-Jul-24 23-Jul-24 21.78 21-Jul-24 23-Jul-24 0.00 1021 WC7-CON-7575 Concrete Curing: Wc-106 0%3.00 0.00 3.00 26-Jul-24 28-Jul-24 30.28 26-Jul-24 28-Jul-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 4 A, Crew 3 17-Aug-24, 2024 Spring/Summer 17-Aug-24, Crew 1 Mobilze DPF, Drilled Pier Foundation: Wc171, 08-Jul-24 Drilled Pier Foundation: Str Wa167 (Salv. Sect) *July 10th is the earliest start date in USFS with Go Drilled Pier Foundation: Wc-112, 19-Jul-24 Drilled Pier Foundation: Wc-106, 25-Jul-24 Drilled Pier Foundation: Wc-95, 31-Jul-24 Drilled Pier Foundation: Wc-306 (Eagle Nest), 06-Aug-24 Drilled Pier Foundation: Wc-329, 12-Aug-24 Drilled Pier Foundation: Wc-2/177A, 17-Aug-24 05-Aug-24, Crew 2 Drilled Pier Foundation: Wc173, 15-Jul-24 Drilled Pier Foundation: Wc-124, 20-Jul-24 Drilled Pier Foundation: Wc-122, 26-Jul-24 Drilled Pier Foundation: Wc-267 *Water crossing, 30-Jul-24 Drilled Pier Foundation: Str Wa189 (Salv. Sect), 05-Aug-24 20-Aug-24, Concrete Curing / Strength Achieved Concrete Curing: Wc-171, 11-Jul-24 Concrete Curing: Wc-167, 16-Jul-24 Concrete Curing: Wc-173, 18-Jul-24 Concrete Curing: Wc-112, 22-Jul-24 Concrete Curing: Wc-124, 23-Jul-24 Concrete Curing: Wc-106, 28-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 20 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1022 WC7-CON-7595 Concrete Curing: Wc-122 0%3.00 0.00 3.00 27-Jul-24 29-Jul-24 17.13 27-Jul-24 29-Jul-24 0.00 1023 WC8-CON-8535 Concrete Curing: Wc-267 0%3.00 0.00 3.00 31-Jul-24 02-Aug-24 33.53 31-Jul-24 02-Aug-24 0.00 1024 WC7-CON-7565 Concrete Curing: Wc-95 0%3.00 0.00 3.00 01-Aug-24 03-Aug-24 32.18 01-Aug-24 03-Aug-24 0.00 1025 WA4-CON-4585 Concrete Curing: Wc-189 0%3.00 0.00 3.00 06-Aug-24 08-Aug-24 75.50 06-Aug-24 08-Aug-24 0.00 1026 WC9-CON-9525 Concrete Curing: Wc-306 0%3.00 0.00 3.00 07-Aug-24 09-Aug-24 44.30 07-Aug-24 09-Aug-24 0.00 1027 WC9-CON-9535 Concrete Curing: Wc-329 0%3.00 0.00 3.00 13-Aug-24 15-Aug-24 52.80 13-Aug-24 15-Aug-24 0.00 1028 WC9-CON-9545 Concrete Curing: Wc-2/177A 0%3.00 0.00 3.00 18-Aug-24 20-Aug-24 50.30 18-Aug-24 20-Aug-24 0.00 1029 Structure SalvageStructure SalvageStructure Salvage 157.07 107.89 37.74 12-Feb-24 A 16-Aug-24 45.36 12-Feb-24 16-Aug-24 0.26 1030 2024 Spring/Sum2024 Spring/Summer2024 Spring/Summer 157.07 107.89 37.74 12-Feb-24 A 16-Aug-24 45.36 12-Feb-24 16-Aug-24 0.26 1031 Crew 1Crew 1Crew 1 157.07 88.05 37.74 12-Feb-24 A 16-Aug-24 45.36 12-Feb-24 16-Aug-24 0.00 1032 WC6-SLV-6300 Mobilize Salvage 100%0.00 0.00 0.00 12-Feb-24 A 12-Feb-24 0.00 1033 WC6-SLV-6340 Salvage Structure: Wc-8 100%0.24 0.24 0.00 12-Feb-24 A 12-Feb-24 A 12-Feb-24 12-Feb-24 0.00 1034 WC6-SLV-6345 Salvage Structure: Wc-9 100%0.24 0.24 0.00 13-Feb-24 A 14-Feb-24 A 13-Feb-24 14-Feb-24 0.00 1035 WC6-SLV-6390 Salvage Structure: Wc-17 100%0.22 0.22 0.00 19-Feb-24 A 20-Feb-24 A 19-Feb-24 20-Feb-24 0.00 1036 WC6-SLV-6350 Salvage Structure: Wc-10 100%0.22 0.22 0.00 21-Feb-24 A 21-Feb-24 A 21-Feb-24 21-Feb-24 0.00 1037 WC6-SLV-6360 Salvage Structure: Wc-12 100%0.22 0.22 0.00 22-Feb-24 A 22-Feb-24 A 22-Feb-24 22-Feb-24 0.00 1038 WC6-SLV-6410 Salvage Structure: Wc-21 100%0.22 0.22 0.00 24-Feb-24 A 24-Feb-24 A 24-Feb-24 24-Feb-24 0.00 1039 WC6-SLV-6355 Salvage Structure: Wc-11 100%0.22 0.22 0.00 26-Feb-24 A 26-Feb-24 A 26-Feb-24 26-Feb-24 0.00 1040 WC6-SLV-6370 Salvage Structure: Wc-13 100%0.22 0.22 0.00 27-Feb-24 A 27-Feb-24 A 27-Feb-24 27-Feb-24 0.00 1041 WC6-SLV-6415 Salvage Structure: Wc-22 100%0.22 0.22 0.00 27-Feb-24 A 27-Feb-24 A 27-Feb-24 27-Feb-24 0.00 1042 WC6-SLV-6420 Salvage Structure: Wc-23 100%0.22 0.22 0.00 27-Feb-24 A 27-Feb-24 A 27-Feb-24 27-Feb-24 0.00 1043 WC6-SLV-6365 Salvage Structure: Wc-13 100%0.22 0.22 0.00 27-Feb-24 A 28-Feb-24 A 27-Feb-24 28-Feb-24 0.00 1044 WC6-SLV-6395 Salvage Structure: Wc-18 100%0.22 0.22 0.00 28-Feb-24 A 28-Feb-24 A 28-Feb-24 28-Feb-24 0.00 1045 WC6-SLV-6385 Salvage Structure: Wc-16 100%0.22 0.22 0.00 29-Feb-24 A 01-Mar-24 A 29-Feb-24 01-Mar-24 0.00 1046 WC6-SLV-6330 Salvage Structure: Wc-6 100%0.24 0.24 0.00 07-Mar-24 A 07-Mar-24 A 07-Mar-24 07-Mar-24 0.00 1047 WC6-SLV-6325 Salvage Structure: Wc-5 100%0.24 0.24 0.00 08-Mar-24 A 09-Mar-24 A 08-Mar-24 09-Mar-24 0.00 1048 WC6-SLV-6305 Salvage Structure: Wc-1 100%0.24 0.24 0.00 11-Mar-24 A 11-Mar-24 A 11-Mar-24 11-Mar-24 0.00 1049 WC6-SLV-6375 Salvage Structure: Wc-14 100%0.22 0.22 0.00 15-Mar-24 A 15-Mar-24 A 15-Mar-24 15-Mar-24 0.00 1050 Crew 2 Salvage Structure: Wc-7 100%0.24 0.24 0.00 15-Mar-24 A 15-Mar-24 A 27-Feb-24 27-Feb-24 -15.00 1051 WC7-SLV-6610 Salvage Structure: Wc-93 *start here*100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1052 WC7-SLV-6605 Salvage Structure: Wc-92 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1053 WC7-SLV-6600 Salvage Structure: Wc-91 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1054 WC7-SLV-6595 Salvage Structure: Wc-90 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1055 WC7-SLV-6590 Salvage Structure: Wc-89 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1056 WC7-SLV-6585 Salvage Structure: Wc-88 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 06-May-24 -6.00 1057 WC7-SLV-6580 Salvage Structure: Wc-87 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 06-May-24 07-May-24 -5.86 1058 WC7-SLV-6575 Salvage Structure: Wc-86 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 07-May-24 07-May-24 -5.71 1059 WC7-SLV-6570 Salvage Structure: Wc-85 100%0.15 0.15 0.00 12-May-24 A 12-May-24 A 07-May-24 07-May-24 -5.56 1060 WC7-SLV-6565 Salvage Structure: Wc-84 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 07-May-24 07-May-24 -6.65 1061 WC7-SLV-6560 Salvage Structure: Wc-83 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 07-May-24 07-May-24 -6.65 1062 WC7-SLV-6555 Salvage Structure: Wc-82 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 07-May-24 07-May-24 -6.65 1063 WC7-SLV-6550 Salvage Structure: Wc-81 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 07-May-24 07-May-24 -6.65 1064 WC7-SLV-6545 Salvage Structure: Wc-80 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 07-May-24 08-May-24 -6.65 1065 WC7-SLV-6535 Salvage Structure: Wc-78 100%0.15 0.00 0.00 14-May-24 A 14-May-24 A 08-May-24 08-May-24 -6.50 1066 WC7-SLV-6540 Salvage Structure: Wc-79 100%0.15 0.15 0.00 14-May-24 A 14-May-24 A 08-May-24 08-May-24 -6.65 1067 WC7-SLV-6530 Salvage Structure: Wc-77 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 08-May-24 08-May-24 -7.65 1068 WC7-SLV-6495 Salvage Structure: Wc-70 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 09-May-24 09-May-24 -6.65 1069 WC7-SLV-6525 Salvage Structure: Wc-76 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 08-May-24 08-May-24 -7.65 1070 WC7-SLV-6490 Salvage Structure: Wc-69 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 09-May-24 09-May-24 -6.65 1071 WC7-SLV-6520 Salvage Structure: Wc-75 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 08-May-24 08-May-24 -7.65 1072 WC7-SLV-6485 Salvage Structure: Wc-68 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 09-May-24 09-May-24 -6.65 1073 WC7-SLV-6515 Salvage Structure: Wc-74 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 08-May-24 08-May-24 -7.65 1074 WC7-SLV-6510 Salvage Structure: Wc-73 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 09-May-24 09-May-24 -7.65 1075 WC7-SLV-6505 Salvage Structure: Wc-72 100%0.15 0.15 0.00 16-May-24 A 16-May-24 A 09-May-24 09-May-24 -7.65 1076 WC7-SLV-6500 Salvage Structure: Wc-71 100%0.15 0.15 0.00 16-May-24 A 17-May-24 A 09-May-24 09-May-24 -7.65 1077 WC7-SLV-6465 Salvage Structure: Wc-64 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 -7.65 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Concrete Curing: Wc-122, 29-Jul-24 Concrete Curing: Wc-267, 02-Aug-24 Concrete Curing: Wc-95, 03-Aug-24 Concrete Curing: Wc-189, 08-Aug-24 Concrete Curing: Wc-306, 09-Aug-24 Concrete Curing: Wc-329, 15-Aug-24 Concrete Curing: Wc-2/177A, 20-Aug-24 16-Aug-24, Structure Salvage 16-Aug-24, 2024 Spring/Summer 16-Aug-24, Crew 1 alvage, Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 21 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1078 WC7-SLV-6460 Salvage Structure: Wc-63 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 10-May-24 -7.65 1079 WC7-SLV-6455 Salvage Structure: Wc-62 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 10-May-24 -7.65 1080 WC7-SLV-6450 Salvage Structure: Wc-61 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 10-May-24 -7.65 1081 WC7-SLV-6480 Salvage Structure: Wc-67 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 09-May-24 10-May-24 -8.65 1082 WC7-SLV-6475 Salvage Structure: Wc-66 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 10-May-24 -8.65 1083 WC7-SLV-6470 Salvage Structure: Wc-65 100%0.15 0.15 0.00 18-May-24 A 18-May-24 A 10-May-24 10-May-24 -8.65 1084 WC7-SLV-6400 Salvage Structure: Wc-51 100%0.15 0.15 0.00 18-May-24 A 19-May-24 A 13-May-24 13-May-24 -5.65 1085 WC7-SLV-6430 Salvage Structure: Wc-57 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 11-May-24 11-May-24 1086 WC7-SLV-6425 Salvage Structure: Wc-56 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 11-May-24 11-May-24 -7.65 1087 WC7-SLV-6420 Salvage Structure: Wc-55 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 11-May-24 11-May-24 -7.65 1088 WC7-SLV-6415 Salvage Structure: Wc-54 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 11-May-24 11-May-24 -7.65 1089 WC7-SLV-6445 Salvage Structure: Wc-60 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 10-May-24 11-May-24 -8.65 1090 WC7-SLV-6410 Salvage Structure: Wc-53 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 13-May-24 13-May-24 -6.65 1091 WC7-SLV-6440 Salvage Structure: Wc-59 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 11-May-24 11-May-24 -8.65 1092 WC7-SLV-6405 Salvage Structure: Wc-52 100%0.15 0.15 0.00 19-May-24 A 19-May-24 A 13-May-24 13-May-24 -6.65 1093 WC7-SLV-6435 Salvage Structure: Wc-58 100%0.15 0.15 0.00 19-May-24 A 20-May-24 A 11-May-24 11-May-24 -8.65 1094 WC6-SLV-6535 Salvage Structure: Wc-46 100%0.15 0.15 0.00 20-May-24 A 20-May-24 A 13-May-24 13-May-24 -6.55 1095 WC6-SLV-6530 Salvage Structure: Wc-45 100%0.15 0.15 0.00 20-May-24 A 20-May-24 A 13-May-24 13-May-24 -6.55 1096 WC6-SLV-6525 Salvage Structure: Wc-44 100%0.15 0.15 0.00 20-May-24 A 20-May-24 A 13-May-24 13-May-24 -6.55 1097 WC6-SLV-6520 Salvage Structure: Wc-43 100%0.15 0.15 0.00 20-May-24 A 20-May-24 A 13-May-24 14-May-24 -6.55 1098 WC6-SLV-6515 Salvage Structure: Wc-42 100%0.15 0.15 0.00 20-May-24 A 20-May-24 A 14-May-24 14-May-24 -6.55 1099 WC6-SLV-6510 Salvage Structure: Wc-41 100%0.15 0.15 0.00 23-May-24 A 23-May-24 A 14-May-24 14-May-24 -9.55 1100 WC6-SLV-6505 Salvage Structure: Wc-40 (move to Wc-268)100%0.15 0.15 0.00 23-May-24 A 24-May-24 A 14-May-24 14-May-24 -9.05 1101 WC9-SLV-9000 Salvage Structure: Wc-268 - done by stringing crew 0%0.26 0.00 0.26 01-Jul-24 01-Jul-24 55.84 17-Jun-24 17-Jun-24 -12.00 1102 WC9-SLV-9005 Salvage Structure: Wc-269 0%0.26 0.00 0.26 26-Jul-24 26-Jul-24 36.83 26-Jul-24 26-Jul-24 0.00 1103 WC9-SLV-9010 Salvage Structure: Wc-270 0%0.26 0.00 0.26 26-Jul-24 27-Jul-24 36.83 26-Jul-24 27-Jul-24 0.00 1104 WC9-SLV-9015 Salvage Structure: Wc-271 0%0.26 0.00 0.26 27-Jul-24 27-Jul-24 36.90 27-Jul-24 27-Jul-24 0.00 1105 WC9-SLV-9020 Salvage Structure: Wc-272 0%0.26 0.00 0.26 27-Jul-24 27-Jul-24 36.90 27-Jul-24 27-Jul-24 0.00 1106 WC9-SLV-9025 Salvage Structure: Wc-273 0%0.26 0.00 0.26 27-Jul-24 27-Jul-24 36.90 27-Jul-24 27-Jul-24 0.00 1107 WC9-SLV-9030 Salvage Structure: Wc-274 0%0.26 0.00 0.26 27-Jul-24 29-Jul-24 36.90 27-Jul-24 29-Jul-24 0.00 1108 WC9-SLV-9035 Salvage Structure: Wc-275 0%0.26 0.00 0.26 29-Jul-24 29-Jul-24 36.90 29-Jul-24 29-Jul-24 0.00 1109 WC9-SLV-9040 Salvage Structure: Wc-276 0%0.26 0.00 0.26 29-Jul-24 29-Jul-24 36.90 29-Jul-24 29-Jul-24 0.00 1110 WC9-SLV-9045 Salvage Structure: Wc-277 0%0.26 0.00 0.26 29-Jul-24 29-Jul-24 36.90 29-Jul-24 29-Jul-24 0.00 1111 WC9-SLV-9050 Salvage Structure: Wc-278 0%0.26 0.00 0.26 29-Jul-24 30-Jul-24 36.90 29-Jul-24 30-Jul-24 0.00 1112 WC9-SLV-9055 Salvage Structure: Wc-279 0%0.26 0.00 0.26 30-Jul-24 30-Jul-24 36.90 30-Jul-24 30-Jul-24 0.00 1113 WC9-SLV-9060 Salvage Structure: Wc-280 0%0.26 0.00 0.26 30-Jul-24 30-Jul-24 36.90 30-Jul-24 30-Jul-24 0.00 1114 WC9-SLV-9065 Salvage Structure: Wc-281 0%0.26 0.00 0.26 30-Jul-24 30-Jul-24 36.90 30-Jul-24 30-Jul-24 0.00 WC9-SLV-9070 Salvage Structure: Wc-282 0%0.26 0.00 0.26 30-Jul-24 31-Jul-24 36.90 30-Jul-24 31-Jul-24 0.00 1116 WC9-SLV-9075 Salvage Structure: Wc-283 0%0.26 0.00 0.26 31-Jul-24 31-Jul-24 36.90 31-Jul-24 31-Jul-24 0.00 1117 WC9-SLV-9080 Salvage Structure: Wc-284 0%0.26 0.00 0.26 31-Jul-24 31-Jul-24 36.90 31-Jul-24 31-Jul-24 0.00 1118 WC9-SLV-9085 Salvage Structure: Wc-285 0%0.26 0.00 0.26 31-Jul-24 31-Jul-24 36.90 31-Jul-24 31-Jul-24 0.00 1119 WC9-SLV-9090 Salvage Structure: Wc-286 0%0.26 0.00 0.26 31-Jul-24 01-Aug-24 36.90 31-Jul-24 01-Aug-24 0.00 1120 WC9-SLV-9095 Salvage Structure: Wc-287 0%0.26 0.00 0.26 01-Aug-24 01-Aug-24 36.90 01-Aug-24 01-Aug-24 0.00 1121 WC9-SLV-9100 Salvage Structure: Wc-288 0%0.26 0.00 0.26 01-Aug-24 01-Aug-24 37.40 01-Aug-24 01-Aug-24 0.00 1122 WC9-SLV-9105 Salvage Structure: Wc-289 0%0.26 0.00 0.26 01-Aug-24 01-Aug-24 37.40 01-Aug-24 01-Aug-24 0.00 1123 WC9-SLV-9110 Salvage Structure: Wc-290 0%0.26 0.00 0.26 01-Aug-24 02-Aug-24 37.40 01-Aug-24 02-Aug-24 0.00 1124 WC9-SLV-9115 Salvage Structure: Wc-291 0%0.26 0.00 0.26 02-Aug-24 02-Aug-24 37.40 02-Aug-24 02-Aug-24 0.00 1125 WC9-SLV-9120 Salvage Structure: Wc-292 0%0.26 0.00 0.26 02-Aug-24 02-Aug-24 37.40 02-Aug-24 02-Aug-24 0.00 1126 WC9-SLV-9125 Salvage Structure: Wc-293 0%0.26 0.00 0.26 02-Aug-24 03-Aug-24 37.40 02-Aug-24 03-Aug-24 0.00 1127 WC9-SLV-9130 Salvage Structure: Wc-294 0%0.26 0.00 0.26 03-Aug-24 03-Aug-24 37.40 03-Aug-24 03-Aug-24 0.00 1128 WC9-SLV-9135 Salvage Structure: Wc-295 0%0.26 0.00 0.26 03-Aug-24 03-Aug-24 37.40 03-Aug-24 03-Aug-24 0.00 1129 WC9-SLV-9140 Salvage Structure: Wc-296 0%0.26 0.00 0.26 03-Aug-24 03-Aug-24 37.40 03-Aug-24 03-Aug-24 0.00 1130 WC9-SLV-9145 Salvage Structure: Wc-297 0%0.26 0.00 0.26 03-Aug-24 05-Aug-24 37.40 03-Aug-24 05-Aug-24 0.00 1131 WC9-SLV-9150 Salvage Structure: Wc-298 0%0.26 0.00 0.26 05-Aug-24 05-Aug-24 37.40 05-Aug-24 05-Aug-24 0.00 1132 WC9-SLV-9155 Salvage Structure: Wc-299 0%0.26 0.00 0.26 05-Aug-24 05-Aug-24 37.40 05-Aug-24 05-Aug-24 0.00 1133 WC9-SLV-9160 Salvage Structure: Wc-300 0%0.26 0.00 0.26 05-Aug-24 05-Aug-24 37.40 05-Aug-24 05-Aug-24 0.00 1134 WC9-SLV-9165 Salvage Structure: Wc-301 0%0.26 0.00 0.26 05-Aug-24 06-Aug-24 37.40 05-Aug-24 06-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Salvage Structure: Wc-268 - done by stringing crew, 01-Jul-24 Salvage Structure: Wc-269, 26-Jul-24 Salvage Structure: Wc-270, 27-Jul-24 Salvage Structure: Wc-271, 27-Jul-24 Salvage Structure: Wc-272, 27-Jul-24 Salvage Structure: Wc-273, 27-Jul-24 Salvage Structure: Wc-274, 29-Jul-24 Salvage Structure: Wc-275, 29-Jul-24 Salvage Structure: Wc-276, 29-Jul-24 Salvage Structure: Wc-277, 29-Jul-24 Salvage Structure: Wc-278, 30-Jul-24 Salvage Structure: Wc-279, 30-Jul-24 Salvage Structure: Wc-280, 30-Jul-24 Salvage Structure: Wc-281, 30-Jul-24 Salvage Structure: Wc-282, 31-Jul-24 Salvage Structure: Wc-283, 31-Jul-24 Salvage Structure: Wc-284, 31-Jul-24 Salvage Structure: Wc-285, 31-Jul-24 Salvage Structure: Wc-286, 01-Aug-24 Salvage Structure: Wc-287, 01-Aug-24 Salvage Structure: Wc-288, 01-Aug-24 Salvage Structure: Wc-289, 01-Aug-24 Salvage Structure: Wc-290, 02-Aug-24 Salvage Structure: Wc-291, 02-Aug-24 Salvage Structure: Wc-292, 02-Aug-24 Salvage Structure: Wc-293, 03-Aug-24 Salvage Structure: Wc-294, 03-Aug-24 Salvage Structure: Wc-295, 03-Aug-24 Salvage Structure: Wc-296, 03-Aug-24 Salvage Structure: Wc-297, 05-Aug-24 Salvage Structure: Wc-298, 05-Aug-24 Salvage Structure: Wc-299, 05-Aug-24 Salvage Structure: Wc-300, 05-Aug-24 Salvage Structure: Wc-301, 06-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 22 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1135 WC9-SLV-9170 Salvage Structure: Wc-302 0%0.26 0.00 0.26 06-Aug-24 06-Aug-24 37.40 06-Aug-24 06-Aug-24 0.00 1136 WC9-SLV-9175 Salvage Structure: Wc-303 0%0.26 0.00 0.26 06-Aug-24 06-Aug-24 37.40 06-Aug-24 06-Aug-24 0.00 1137 WC9-SLV-9180 Salvage Structure: Wc-304 0%0.26 0.00 0.26 06-Aug-24 06-Aug-24 37.40 06-Aug-24 06-Aug-24 0.00 1138 WC9-SLV-9185 Salvage Structure: Wc-305 0%0.26 0.00 0.26 06-Aug-24 07-Aug-24 37.40 06-Aug-24 07-Aug-24 0.00 1139 WC9-SLV-9190 Salvage Structure: Wc-306 0%0.26 0.00 0.26 07-Aug-24 07-Aug-24 37.40 07-Aug-24 07-Aug-24 0.00 1140 WC9-SLV-9195 Salvage Structure: Wc-307 0%0.26 0.00 0.26 07-Aug-24 07-Aug-24 37.40 07-Aug-24 07-Aug-24 0.00 1141 WC9-SLV-9200 Salvage Structure: Wc-308 0%0.26 0.00 0.26 07-Aug-24 07-Aug-24 37.40 07-Aug-24 07-Aug-24 0.00 1142 WC9-SLV-9205 Salvage Structure: Wc-309 0%0.26 0.00 0.26 07-Aug-24 08-Aug-24 37.40 07-Aug-24 08-Aug-24 0.00 1143 WC9-SLV-9210 Salvage Structure: Wc-310 0%0.26 0.00 0.26 08-Aug-24 08-Aug-24 37.40 08-Aug-24 08-Aug-24 0.00 1144 WC9-SLV-9215 Salvage Structure: Wc-311 0%0.26 0.00 0.26 08-Aug-24 08-Aug-24 37.40 08-Aug-24 08-Aug-24 0.00 1145 WC9-SLV-9220 Salvage Structure: Wc-312 0%0.26 0.00 0.26 08-Aug-24 08-Aug-24 37.40 08-Aug-24 08-Aug-24 0.00 1146 WC9-SLV-9225 Salvage Structure: Wc-313 0%0.26 0.00 0.26 08-Aug-24 09-Aug-24 37.40 08-Aug-24 09-Aug-24 0.00 1147 WC9-SLV-9230 Salvage Structure: Wc-314 0%0.26 0.00 0.26 09-Aug-24 09-Aug-24 37.40 09-Aug-24 09-Aug-24 0.00 1148 WC9-SLV-9235 Salvage Structure: Wc-315 0%0.26 0.00 0.26 09-Aug-24 09-Aug-24 37.40 09-Aug-24 09-Aug-24 0.00 1149 WC9-SLV-9240 Salvage Structure: Wc-316 0%0.26 0.00 0.26 09-Aug-24 10-Aug-24 37.40 09-Aug-24 10-Aug-24 0.00 1150 WC9-SLV-9245 Salvage Structure: Wc-317 0%0.26 0.00 0.26 10-Aug-24 10-Aug-24 37.40 10-Aug-24 10-Aug-24 0.00 1151 WC9-SLV-9250 Salvage Structure: Wc-318 0%0.26 0.26 10-Aug-24 10-Aug-24 37.40 10-Aug-24 10-Aug-24 0.00 1152 WC9-SLV-9255 Salvage Structure: Wc-319 0%0.26 0.00 0.26 10-Aug-24 10-Aug-24 37.40 10-Aug-24 10-Aug-24 0.00 1153 WC9-SLV-9260 Salvage Structure: Wc-320 0%0.26 0.00 0.26 10-Aug-24 12-Aug-24 37.40 10-Aug-24 12-Aug-24 0.00 1154 WC9-SLV-9265 Salvage Structure: Wc-321 0%0.26 0.00 0.26 12-Aug-24 12-Aug-24 42.73 12-Aug-24 12-Aug-24 0.00 1155 WC9-SLV-9270 Salvage Structure: Wc-322 0%0.26 0.00 0.26 12-Aug-24 12-Aug-24 42.73 12-Aug-24 12-Aug-24 0.00 1156 WC9-SLV-9275 Salvage Structure: Wc-323 0%0.26 0.00 0.26 12-Aug-24 12-Aug-24 42.73 12-Aug-24 12-Aug-24 0.00 1157 WC9-SLV-9280 Salvage Structure: Wc-324 0%0.26 0.00 0.26 12-Aug-24 13-Aug-24 42.73 12-Aug-24 13-Aug-24 0.00 1158 WC9-SLV-9285 Salvage Structure: Wc-325 0%0.26 0.00 0.26 13-Aug-24 13-Aug-24 42.73 13-Aug-24 13-Aug-24 0.00 1159 WC9-SLV-9290 Salvage Structure: Wc-326 0%0.26 0.00 0.26 13-Aug-24 13-Aug-24 42.73 13-Aug-24 13-Aug-24 0.00 1160 WC9-SLV-9295 Salvage Structure: Wc-327 0%0.26 0.00 0.26 13-Aug-24 13-Aug-24 46.20 13-Aug-24 13-Aug-24 0.00 1161 WC9-SLV-9300 Salvage Structure: Wc-328 0%0.26 0.00 0.26 13-Aug-24 14-Aug-24 46.20 13-Aug-24 14-Aug-24 0.00 1162 WC9-SLV-9305 Salvage Structure: Wc-329 0%0.26 0.00 0.26 14-Aug-24 14-Aug-24 46.20 14-Aug-24 14-Aug-24 0.00 1163 WC9-SLV-9310 Salvage Structure: Wc-330 0%0.26 0.00 0.26 14-Aug-24 14-Aug-24 46.36 14-Aug-24 14-Aug-24 0.00 1164 WC9-SLV-9315 Salvage Structure: Wc-331 0%0.26 0.00 0.26 14-Aug-24 14-Aug-24 46.36 14-Aug-24 14-Aug-24 0.00 1165 WC9-SLV-9320 Salvage Structure: Wc-332 0%0.26 0.00 0.26 14-Aug-24 15-Aug-24 46.36 14-Aug-24 15-Aug-24 0.00 1166 WC9-SLV-9326 Salvage Structure: Wc-333 0%0.26 0.00 0.26 15-Aug-24 15-Aug-24 46.36 15-Aug-24 15-Aug-24 0.00 1167 WC9-SLV-9330 Salvage Structure: Wc-334 0%0.26 0.00 0.26 15-Aug-24 15-Aug-24 46.36 15-Aug-24 15-Aug-24 0.00 1168 WC9-SLV-9336 Salvage Structure: Wc-335 0%0.26 0.00 0.26 15-Aug-24 15-Aug-24 46.36 15-Aug-24 15-Aug-24 0.00 1169 WC9-SLV-9340 Salvage Structure: Wc-336 0%0.26 0.00 0.26 15-Aug-24 16-Aug-24 46.36 15-Aug-24 16-Aug-24 0.00 1170 WC9-SLV-9346 Salvage Structure: Wc-337 0%0.26 0.00 0.26 16-Aug-24 16-Aug-24 46.36 16-Aug-24 16-Aug-24 0.00 1171 WC9-SLV-9350 Salvage Structure: Wc-2/177 0%0.26 0.00 0.26 16-Aug-24 16-Aug-24 46.36 16-Aug-24 16-Aug-24 0.00 1172 Crew 2Crew 2Crew 2 37.50 0.00 37.50 01-Jul-24 16-Aug-24 15.83 03-Jul-24 16-Aug-24 0.00 1173 WC7-SLV-6885 Salvage Structure: Wc-148 - crew 2 start 0%0.24 0.00 0.24 01-Jul-24 01-Jul-24 23.58 03-Jul-24 03-Jul-24 2.00 1174 WC7-SLV-6880 Salvage Structure: Wc-147 0%0.24 0.00 0.24 01-Jul-24 01-Jul-24 23.58 03-Jul-24 03-Jul-24 2.00 1175 WC7-SLV-6875 Salvage Structure: Wc-146 0%0.24 0.00 0.24 01-Jul-24 01-Jul-24 23.58 03-Jul-24 03-Jul-24 2.00 1176 WC7-SLV-6870 Salvage Structure: Wc-145 0%0.24 0.00 0.24 01-Jul-24 01-Jul-24 23.58 03-Jul-24 03-Jul-24 2.00 1177 WC7-SLV-6865 Salvage Structure: Wc-144 0%0.24 0.00 0.24 01-Jul-24 02-Jul-24 23.58 03-Jul-24 08-Jul-24 2.00 1178 WC7-SLV-6860 Salvage Structure: Wc-143 0%0.24 0.00 0.24 02-Jul-24 02-Jul-24 23.58 08-Jul-24 08-Jul-24 2.00 1179 WC7-SLV-6855 Salvage Structure: Wc-142 0%0.24 0.00 0.24 02-Jul-24 02-Jul-24 23.58 08-Jul-24 08-Jul-24 2.00 1180 WC7-SLV-6850 Salvage Structure: Wc-141 0%0.24 0.00 0.24 02-Jul-24 02-Jul-24 23.58 08-Jul-24 08-Jul-24 2.00 1181 WC7-SLV-6845 Salvage Structure: Wc-140 0%0.24 0.00 0.24 02-Jul-24 03-Jul-24 23.58 08-Jul-24 09-Jul-24 2.00 1182 WC7-SLV-6840 Salvage Structure: Wc-139 0%0.24 0.00 0.24 03-Jul-24 03-Jul-24 23.58 09-Jul-24 09-Jul-24 2.00 1183 WC7-SLV-6835 Salvage Structure: Wc-138 0%0.24 0.00 0.24 03-Jul-24 03-Jul-24 23.58 09-Jul-24 09-Jul-24 2.00 1184 WC7-SLV-6830 Salvage Structure: Wc-137 0%0.24 0.00 0.24 03-Jul-24 03-Jul-24 23.58 09-Jul-24 09-Jul-24 2.00 1185 WC7-SLV-6825 Salvage Structure: Wc-136 0%0.24 0.00 0.24 03-Jul-24 08-Jul-24 23.58 09-Jul-24 10-Jul-24 2.00 1186 WC7-SLV-6820 Salvage Structure: Wc-135 0%0.24 0.00 0.24 08-Jul-24 08-Jul-24 23.58 10-Jul-24 10-Jul-24 2.00 1187 WC7-SLV-6815 Salvage Structure: Wc-134 0%0.24 0.00 0.24 08-Jul-24 08-Jul-24 23.58 10-Jul-24 10-Jul-24 2.00 1188 WC7-SLV-6810 Salvage Structure: Wc-133 0%0.24 0.00 0.24 08-Jul-24 08-Jul-24 23.58 10-Jul-24 10-Jul-24 2.00 1189 WC7-SLV-6805 Salvage Structure: Wc-132 0%0.24 0.00 0.24 08-Jul-24 09-Jul-24 23.58 10-Jul-24 11-Jul-24 2.00 1190 WC7-SLV-6800 Salvage Structure: Wc-131 0%0.24 0.00 0.24 09-Jul-24 09-Jul-24 23.58 11-Jul-24 11-Jul-24 2.00 1191 WC7-SLV-6795 Salvage Structure: Wc-130 0%0.24 0.00 0.24 09-Jul-24 09-Jul-24 23.58 11-Jul-24 11-Jul-24 2.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Salvage Structure: Wc-302, 06-Aug-24 Salvage Structure: Wc-303, 06-Aug-24 Salvage Structure: Wc-304, 06-Aug-24 Salvage Structure: Wc-305, 07-Aug-24 Salvage Structure: Wc-306, 07-Aug-24 Salvage Structure: Wc-307, 07-Aug-24 Salvage Structure: Wc-308, 07-Aug-24 Salvage Structure: Wc-309, 08-Aug-24 Salvage Structure: Wc-310, 08-Aug-24 Salvage Structure: Wc-311, 08-Aug-24 Salvage Structure: Wc-312, 08-Aug-24 Salvage Structure: Wc-313, 09-Aug-24 Salvage Structure: Wc-314, 09-Aug-24 Salvage Structure: Wc-315, 09-Aug-24 Salvage Structure: Wc-316, 10-Aug-24 Salvage Structure: Wc-317, 10-Aug-24 Salvage Structure: Wc-318, 10-Aug-24 Salvage Structure: Wc-319, 10-Aug-24 Salvage Structure: Wc-320, 12-Aug-24 Salvage Structure: Wc-321, 12-Aug-24 Salvage Structure: Wc-322, 12-Aug-24 Salvage Structure: Wc-323, 12-Aug-24 Salvage Structure: Wc-324, 13-Aug-24 Salvage Structure: Wc-325, 13-Aug-24 Salvage Structure: Wc-326, 13-Aug-24 Salvage Structure: Wc-327, 13-Aug-24 Salvage Structure: Wc-328, 14-Aug-24 Salvage Structure: Wc-329, 14-Aug-24 Salvage Structure: Wc-330, 14-Aug-24 Salvage Structure: Wc-331, 14-Aug-24 Salvage Structure: Wc-332, 15-Aug-24 Salvage Structure: Wc-333, 15-Aug-24 Salvage Structure: Wc-334, 15-Aug-24 Salvage Structure: Wc-335, 15-Aug-24 Salvage Structure: Wc-336, 16-Aug-24 Salvage Structure: Wc-337, 16-Aug-24 Salvage Structure: Wc-2/177, 16-Aug-24 16-Aug-24, Crew 2 Salvage Structure: Wc-148 - crew 2 start, 01-Jul-24 Salvage Structure: Wc-147, 01-Jul-24 Salvage Structure: Wc-146, 01-Jul-24 Salvage Structure: Wc-145, 01-Jul-24 Salvage Structure: Wc-144, 02-Jul-24 Salvage Structure: Wc-143, 02-Jul-24 Salvage Structure: Wc-142, 02-Jul-24 Salvage Structure: Wc-141, 02-Jul-24 Salvage Structure: Wc-140, 03-Jul-24 Salvage Structure: Wc-139, 03-Jul-24 Salvage Structure: Wc-138, 03-Jul-24 Salvage Structure: Wc-137, 03-Jul-24 Salvage Structure: Wc-136, 08-Jul-24 Salvage Structure: Wc-135, 08-Jul-24 Salvage Structure: Wc-134, 08-Jul-24 Salvage Structure: Wc-133, 08-Jul-24 Salvage Structure: Wc-132, 09-Jul-24 Salvage Structure: Wc-131, 09-Jul-24 Salvage Structure: Wc-130, 09-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 23 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1192 WC7-SLV-6790 Salvage Structure: Wc-129 0%0.24 0.00 0.24 09-Jul-24 09-Jul-24 23.58 11-Jul-24 11-Jul-24 2.00 1193 WC7-SLV-6785 Salvage Structure: Wc-128 0%0.24 0.00 0.24 09-Jul-24 09-Jul-24 23.58 11-Jul-24 11-Jul-24 2.00 1194 WC7-SLV-6780 Salvage Structure: Wc-127 0%0.24 0.00 0.24 09-Jul-24 10-Jul-24 23.58 11-Jul-24 12-Jul-24 2.00 1195 WC7-SLV-6775 Salvage Structure: Wc-126 0%0.24 0.00 0.24 10-Jul-24 10-Jul-24 23.58 12-Jul-24 12-Jul-24 2.00 1196 WC7-SLV-6770 Salvage Structure: Wc-125 0%0.24 0.00 0.24 10-Jul-24 10-Jul-24 23.58 12-Jul-24 12-Jul-24 2.00 1197 WC7-SLV-6765 Salvage Structure: Wc-124 0%0.24 0.00 0.24 10-Jul-24 10-Jul-24 23.58 12-Jul-24 12-Jul-24 2.00 1198 WC7-SLV-6760 Salvage Structure: Wc-123 0%0.24 0.00 0.24 10-Jul-24 11-Jul-24 23.58 12-Jul-24 13-Jul-24 2.00 1199 WC7-SLV-6755 Salvage Structure: Wc-122 0%0.24 0.00 0.24 11-Jul-24 11-Jul-24 23.58 13-Jul-24 13-Jul-24 2.00 1200 WC7-SLV-6750 Salvage Structure: Wc-121 0%0.24 0.00 0.24 11-Jul-24 11-Jul-24 23.58 13-Jul-24 13-Jul-24 2.00 1201 WC7-SLV-6745 Salvage Structure: Wc-120 0%0.24 0.00 0.24 11-Jul-24 11-Jul-24 23.58 13-Jul-24 13-Jul-24 2.00 1202 WC7-SLV-6740 Salvage Structure: Wc-119 0%0.24 0.00 0.24 11-Jul-24 12-Jul-24 23.58 13-Jul-24 15-Jul-24 2.00 1203 WC7-SLV-6735 Salvage Structure: Wc-118 0%0.24 0.00 0.24 12-Jul-24 12-Jul-24 23.58 15-Jul-24 15-Jul-24 2.00 1204 WC7-SLV-6730 Salvage Structure: Wc-117 0%0.24 0.00 0.24 12-Jul-24 12-Jul-24 23.58 15-Jul-24 15-Jul-24 2.00 1205 WC7-SLV-6725 Salvage Structure: Wc-116 0%0.24 0.00 0.24 12-Jul-24 12-Jul-24 23.58 15-Jul-24 15-Jul-24 2.00 1206 WC7-SLV-6720 Salvage Structure: Wc-115 0%0.24 0.00 0.24 12-Jul-24 13-Jul-24 23.58 15-Jul-24 16-Jul-24 2.00 1207 WC7-SLV-6715 Salvage Structure: Wc-114 0%0.24 0.00 0.24 13-Jul-24 13-Jul-24 23.58 16-Jul-24 16-Jul-24 2.00 1208 WC7-SLV-6710 Salvage Structure: Wc-113 0%0.24 0.00 0.24 13-Jul-24 13-Jul-24 23.58 16-Jul-24 16-Jul-24 2.00 1209 WC7-SLV-6705 Salvage Structure: Wc-112 0%0.24 0.00 0.24 13-Jul-24 13-Jul-24 23.58 16-Jul-24 16-Jul-24 2.00 1210 WC7-SLV-6700 Salvage Structure: Wc-111 0%0.24 0.00 0.24 13-Jul-24 13-Jul-24 23.58 16-Jul-24 16-Jul-24 2.00 1211 WC7-SLV-6695 Salvage Structure: Wc-110 0%0.24 0.00 0.24 13-Jul-24 15-Jul-24 23.58 16-Jul-24 17-Jul-24 2.00 1212 WC7-SLV-6690 Salvage Structure: Wc-109 0%0.24 0.00 0.24 15-Jul-24 15-Jul-24 23.58 17-Jul-24 17-Jul-24 2.00 1213 WC7-SLV-6685 Salvage Structure: Wc-108 0%0.24 0.00 0.24 15-Jul-24 15-Jul-24 23.58 17-Jul-24 17-Jul-24 2.00 1214 WC7-SLV-6680 Salvage Structure: Wc-107 0%0.24 0.00 0.24 15-Jul-24 15-Jul-24 23.58 17-Jul-24 17-Jul-24 2.00 1215 WC7-SLV-6675 Salvage Structure: Wc-106 0%0.24 0.00 0.24 15-Jul-24 16-Jul-24 23.58 17-Jul-24 18-Jul-24 2.00 1216 WC7-SLV-6670 Salvage Structure: Wc-105 0%0.24 0.00 0.24 16-Jul-24 16-Jul-24 23.58 18-Jul-24 18-Jul-24 2.00 1217 WC7-SLV-6665 Salvage Structure: Wc-104 0%0.24 0.00 0.24 16-Jul-24 16-Jul-24 23.58 18-Jul-24 18-Jul-24 2.00 1218 WC7-SLV-6660 Salvage Structure: Wc-103 0%0.24 0.00 0.24 16-Jul-24 16-Jul-24 23.58 18-Jul-24 18-Jul-24 2.00 1219 Crew 2 Salvage Structure: Wc-102 0%0.24 0.00 0.24 16-Jul-24 17-Jul-24 23.58 18-Jul-24 19-Jul-24 2.00 1220 WC7-SLV-6650 Salvage Structure: Wc-101 0%0.24 0.00 0.24 17-Jul-24 17-Jul-24 23.58 19-Jul-24 19-Jul-24 2.00 1221 WC7-SLV-6645 Salvage Structure: Wc-100 0%0.24 0.00 0.24 17-Jul-24 17-Jul-24 23.58 19-Jul-24 19-Jul-24 2.00 1222 WC7-SLV-6640 Salvage Structure: Wc-99 0%0.24 0.00 0.24 17-Jul-24 17-Jul-24 23.58 19-Jul-24 19-Jul-24 2.00 1223 WC7-SLV-6635 Salvage Structure: Wc-98 0%0.24 0.00 0.24 17-Jul-24 18-Jul-24 23.58 19-Jul-24 20-Jul-24 2.00 1224 WC7-SLV-6630 Salvage Structure: Wc-97 0%0.24 0.00 0.24 18-Jul-24 18-Jul-24 23.58 20-Jul-24 20-Jul-24 2.00 1225 WC7-SLV-6625 Salvage Structure: Wc-96 0%0.24 0.00 0.24 18-Jul-24 18-Jul-24 23.58 20-Jul-24 20-Jul-24 2.00 1226 WC7-SLV-6620 Salvage Structure: Wc-95 0%0.24 0.00 0.24 18-Jul-24 18-Jul-24 23.58 20-Jul-24 20-Jul-24 2.00 1227 WC7-SLV-6615 Salvage Structure: Wc-94 *jump to WC8 at str 208*0%0.24 0.00 0.24 18-Jul-24 18-Jul-24 23.58 20-Jul-24 20-Jul-24 2.00 1228 WC8-SLV-8500 Salvage Structure: Wc-208 0%0.25 0.00 0.25 30-Jul-24 30-Jul-24 0.33 30-Jul-24 30-Jul-24 0.00 1229 WC8-SLV-8510 Salvage Structure: Wc-209 0%0.25 0.00 0.25 30-Jul-24 30-Jul-24 13.83 30-Jul-24 30-Jul-24 0.00 1230 WC8-SLV-8520 Salvage Structure: Wc-210 0%0.25 0.00 0.25 31-Jul-24 31-Jul-24 16.83 31-Jul-24 31-Jul-24 0.00 1231 WC8-SLV-8530 Salvage Structure: Wc-211 0%0.25 0.00 0.25 31-Jul-24 31-Jul-24 16.83 31-Jul-24 31-Jul-24 0.00 1232 WC8-SLV-8540 Salvage Structure: Wc-212 0%0.25 0.00 0.25 31-Jul-24 31-Jul-24 16.83 31-Jul-24 31-Jul-24 0.00 1233 WC8-SLV-8550 Salvage Structure: Wc-213 0%0.25 0.00 0.25 31-Jul-24 31-Jul-24 16.83 31-Jul-24 31-Jul-24 0.00 1234 WC8-SLV-8560 Salvage Structure: Wc-214 0%0.25 0.00 0.25 01-Aug-24 01-Aug-24 16.83 01-Aug-24 01-Aug-24 0.00 1235 WC8-SLV-8570 Salvage Structure: Wc-215 0%0.25 0.00 0.25 01-Aug-24 01-Aug-24 16.83 01-Aug-24 01-Aug-24 0.00 1236 WC8-SLV-8580 Salvage Structure: Wc-216 0%0.25 0.00 0.25 01-Aug-24 01-Aug-24 16.83 01-Aug-24 01-Aug-24 0.00 1237 WC8-SLV-8590 Salvage Structure: Wc-217 0%0.25 0.00 0.25 01-Aug-24 01-Aug-24 16.83 01-Aug-24 01-Aug-24 0.00 1238 WC8-SLV-8600 Salvage Structure: Wc-218 0%0.25 0.00 0.25 02-Aug-24 02-Aug-24 16.83 02-Aug-24 02-Aug-24 0.00 1239 WC8-SLV-8610 Salvage Structure: Wc-219 0%0.25 0.00 0.25 02-Aug-24 02-Aug-24 16.83 02-Aug-24 02-Aug-24 0.00 1240 WC8-SLV-8620 Salvage Structure: Wc-220 0%0.25 0.00 0.25 02-Aug-24 02-Aug-24 16.83 02-Aug-24 02-Aug-24 0.00 1241 WC8-SLV-8630 Salvage Structure: Wc-221 0%0.25 0.00 0.25 02-Aug-24 02-Aug-24 16.83 02-Aug-24 02-Aug-24 0.00 1242 WC8-SLV-8640 Salvage Structure: Wc-222 0%0.25 0.00 0.25 03-Aug-24 03-Aug-24 16.83 03-Aug-24 03-Aug-24 0.00 1243 WC8-SLV-8650 Salvage Structure: Wc-223 0%0.25 0.00 0.25 03-Aug-24 03-Aug-24 16.83 03-Aug-24 03-Aug-24 0.00 1244 WC8-SLV-8660 Salvage Structure: Wc-224 0%0.25 0.00 0.25 03-Aug-24 03-Aug-24 16.83 03-Aug-24 03-Aug-24 0.00 1245 Crew 2 Salvage Structure: Wc-225 0%0.25 0.00 0.25 03-Aug-24 03-Aug-24 16.83 03-Aug-24 03-Aug-24 0.00 1246 WC8-SLV-8680 Salvage Structure: Wc-226 0%0.25 0.00 0.25 05-Aug-24 05-Aug-24 16.83 05-Aug-24 05-Aug-24 0.00 1247 WC8-SLV-8690 Salvage Structure: Wc-227 0%0.25 0.00 0.25 05-Aug-24 05-Aug-24 16.83 05-Aug-24 05-Aug-24 0.00 1248 WC8-SLV-8700 Salvage Structure: Wc-228 0%0.25 0.00 0.25 05-Aug-24 05-Aug-24 16.83 05-Aug-24 05-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Salvage Structure: Wc-129, 09-Jul-24 Salvage Structure: Wc-128, 09-Jul-24 Salvage Structure: Wc-127, 10-Jul-24 Salvage Structure: Wc-126, 10-Jul-24 Salvage Structure: Wc-125, 10-Jul-24 Salvage Structure: Wc-124, 10-Jul-24 Salvage Structure: Wc-123, 11-Jul-24 Salvage Structure: Wc-122, 11-Jul-24 Salvage Structure: Wc-121, 11-Jul-24 Salvage Structure: Wc-120, 11-Jul-24 Salvage Structure: Wc-119, 12-Jul-24 Salvage Structure: Wc-118, 12-Jul-24 Salvage Structure: Wc-117, 12-Jul-24 Salvage Structure: Wc-116, 12-Jul-24 Salvage Structure: Wc-115, 13-Jul-24 Salvage Structure: Wc-114, 13-Jul-24 Salvage Structure: Wc-113, 13-Jul-24 Salvage Structure: Wc-112, 13-Jul-24 Salvage Structure: Wc-111, 13-Jul-24 Salvage Structure: Wc-110, 15-Jul-24 Salvage Structure: Wc-109, 15-Jul-24 Salvage Structure: Wc-108, 15-Jul-24 Salvage Structure: Wc-107, 15-Jul-24 Salvage Structure: Wc-106, 16-Jul-24 Salvage Structure: Wc-105, 16-Jul-24 Salvage Structure: Wc-104, 16-Jul-24 Salvage Structure: Wc-103, 16-Jul-24 Salvage Structure: Wc-102, 17-Jul-24 Salvage Structure: Wc-101, 17-Jul-24 Salvage Structure: Wc-100, 17-Jul-24 Salvage Structure: Wc-99, 17-Jul-24 Salvage Structure: Wc-98, 18-Jul-24 Salvage Structure: Wc-97, 18-Jul-24 Salvage Structure: Wc-96, 18-Jul-24 Salvage Structure: Wc-95, 18-Jul-24 Salvage Structure: Wc-94 *jump to WC8 at str 208*, 18-Jul-24 Salvage Structure: Wc-208, 30-Jul-24 Salvage Structure: Wc-209, 30-Jul-24 Salvage Structure: Wc-210, 31-Jul-24 Salvage Structure: Wc-211, 31-Jul-24 Salvage Structure: Wc-212, 31-Jul-24 Salvage Structure: Wc-213, 31-Jul-24 Salvage Structure: Wc-214, 01-Aug-24 Salvage Structure: Wc-215, 01-Aug-24 Salvage Structure: Wc-216, 01-Aug-24 Salvage Structure: Wc-217, 01-Aug-24 Salvage Structure: Wc-218, 02-Aug-24 Salvage Structure: Wc-219, 02-Aug-24 Salvage Structure: Wc-220, 02-Aug-24 Salvage Structure: Wc-221, 02-Aug-24 Salvage Structure: Wc-222, 03-Aug-24 Salvage Structure: Wc-223, 03-Aug-24 Salvage Structure: Wc-224, 03-Aug-24 Salvage Structure: Wc-225, 03-Aug-24 Salvage Structure: Wc-226, 05-Aug-24 Salvage Structure: Wc-227, 05-Aug-24 Salvage Structure: Wc-228, 05-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 24 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1249 WC8-SLV-8710 Salvage Structure: Wc-229 0%0.25 0.00 0.25 05-Aug-24 05-Aug-24 16.83 05-Aug-24 05-Aug-24 0.00 1250 WC8-SLV-8720 Salvage Structure: Wc-230 0%0.25 0.00 0.25 06-Aug-24 06-Aug-24 16.83 06-Aug-24 06-Aug-24 0.00 1251 WC8-SLV-8730 Salvage Structure: Wc-231 0%0.25 0.00 0.25 06-Aug-24 06-Aug-24 16.83 06-Aug-24 06-Aug-24 0.00 1252 WC8-SLV-8740 Salvage Structure: Wc-232 0%0.25 0.00 0.25 06-Aug-24 06-Aug-24 16.83 06-Aug-24 06-Aug-24 0.00 1253 WC8-SLV-8750 Salvage Structure: Wc-233 0%0.25 0.00 0.25 06-Aug-24 06-Aug-24 16.83 06-Aug-24 06-Aug-24 0.00 1254 WC8-SLV-8760 Salvage Structure: Wc-234 0%0.25 0.00 0.25 07-Aug-24 07-Aug-24 16.83 07-Aug-24 07-Aug-24 0.00 1255 WC8-SLV-8770 Salvage Structure: Wc-235 0%0.25 0.00 0.25 07-Aug-24 07-Aug-24 16.83 07-Aug-24 07-Aug-24 0.00 1256 WC8-SLV-8780 Salvage Structure: Wc-236 0%0.25 0.00 0.25 07-Aug-24 07-Aug-24 16.83 07-Aug-24 07-Aug-24 0.00 1257 WC8-SLV-8790 Salvage Structure: Wc-237 0%0.25 0.00 0.25 07-Aug-24 07-Aug-24 16.83 07-Aug-24 07-Aug-24 0.00 1258 WC8-SLV-8800 Salvage Structure: Wc-238 0%0.25 0.00 0.25 08-Aug-24 08-Aug-24 16.83 08-Aug-24 08-Aug-24 0.00 1259 WC8-SLV-8810 Salvage Structure: Wc-239 0%0.25 0.00 0.25 08-Aug-24 08-Aug-24 16.83 08-Aug-24 08-Aug-24 0.00 1260 WC8-SLV-8820 Salvage Structure: Wc-240 0%0.25 0.00 0.25 08-Aug-24 08-Aug-24 16.83 08-Aug-24 08-Aug-24 0.00 1261 WC8-SLV-8830 Salvage Structure: Wc-241 0%0.25 0.00 0.25 08-Aug-24 08-Aug-24 16.83 08-Aug-24 08-Aug-24 0.00 1262 WC8-SLV-8840 Salvage Structure: Wc-242 0%0.25 0.00 0.25 09-Aug-24 09-Aug-24 16.83 09-Aug-24 09-Aug-24 0.00 1263 WC8-SLV-8850 Salvage Structure: Wc-243 0%0.25 0.00 0.25 09-Aug-24 09-Aug-24 16.83 09-Aug-24 09-Aug-24 0.00 1264 WC8-SLV-8860 Salvage Structure: Wc-244 0%0.25 0.00 0.25 09-Aug-24 09-Aug-24 16.83 09-Aug-24 09-Aug-24 0.00 1265 WC8-SLV-6900 Salvage Structure: Wc-245 *raptor restriction start*0%0.25 0.00 0.25 09-Aug-24 09-Aug-24 16.83 09-Aug-24 09-Aug-24 0.00 1266 WC8-SLV-6905 Salvage Structure: Wc-246 0%0.25 0.00 0.25 10-Aug-24 10-Aug-24 16.83 10-Aug-24 10-Aug-24 0.00 1267 WC8-SLV-6910 Salvage Structure: Wc-247 0%0.25 0.00 0.25 10-Aug-24 10-Aug-24 16.83 10-Aug-24 10-Aug-24 0.00 1268 WC8-SLV-6915 Salvage Structure: Wc-248 0%0.25 0.00 0.25 10-Aug-24 10-Aug-24 16.83 10-Aug-24 10-Aug-24 0.00 1269 WC8-SLV-6920 Salvage Structure: Wc-249 0%0.25 0.00 0.25 10-Aug-24 10-Aug-24 16.83 10-Aug-24 10-Aug-24 0.00 1270 WC8-SLV-6925 Salvage Structure: Wc-250 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 16.83 12-Aug-24 12-Aug-24 0.00 1271 WC8-SLV-6930 Salvage Structure: Wc-251 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 16.83 12-Aug-24 12-Aug-24 0.00 1272 WC8-SLV-6935 Salvage Structure: Wc-252 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 16.83 12-Aug-24 12-Aug-24 0.00 1273 WC8-SLV-6940 Salvage Structure: Wc-253 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 16.83 12-Aug-24 12-Aug-24 0.00 1274 WC8-SLV-6945 Salvage Structure: Wc-254 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 16.83 13-Aug-24 13-Aug-24 0.00 1275 WC8-SLV-6950 Salvage Structure: Wc-255 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 16.83 13-Aug-24 13-Aug-24 0.00 1276 WC8-SLV-6955 Salvage Structure: Wc-256 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 16.83 13-Aug-24 13-Aug-24 0.00 1277 WC8-SLV-6960 Salvage Structure: Wc-257 *Raptor restriction end 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 16.83 13-Aug-24 13-Aug-24 0.00 1278 WC8-SLV-8870 Salvage Structure: Wc-258 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 16.83 14-Aug-24 14-Aug-24 0.00 1279 WC8-SLV-8880 Salvage Structure: Wc-259 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 16.83 14-Aug-24 14-Aug-24 0.00 1280 WC8-SLV-8890 Salvage Structure: Wc-260 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 16.83 14-Aug-24 14-Aug-24 0.00 1281 WC8-SLV-8900 Salvage Structure: Wc-261 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 16.83 14-Aug-24 14-Aug-24 0.00 1282 WC8-SLV-8910 Salvage Structure: Wc-262 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 16.83 15-Aug-24 15-Aug-24 0.00 1283 WC8-SLV-8920 Salvage Structure: Wc-263 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 16.83 15-Aug-24 15-Aug-24 0.00 1284 WC8-SLV-8930 Salvage Structure: Wc-264 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 16.83 15-Aug-24 15-Aug-24 0.00 1285 WC8-SLV-8940 Salvage Structure: Wc-265 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 16.83 15-Aug-24 15-Aug-24 0.00 1286 WC8-SLV-8950 Salvage Structure: Wc-266 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 16.83 16-Aug-24 16-Aug-24 0.00 1287 WC8-SLV-8960 Salvage Structure: Wc-267 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 16.83 16-Aug-24 16-Aug-24 0.00 1288 Crew 2Crew 3 (done with framing/setting/stringing)Crew 3 (done with framing/setting/stringing)82.16 82.16 0.00 12-Mar-24 A 15-Jun-24 A 24-May-24 16-Aug-24 50.11 1289 WC6-SLV-6440 Salvage Structure: Wc-27 100%0.22 2.22 0.00 12-Mar-24 A 14-Mar-24 A 01-Jul-24 01-Jul-24 93.00 1290 WC6-SLV-6310 Salvage Structure: Wc-2 100%0.24 0.24 0.00 24-Apr-24 A 24-Apr-24 A 24-May-24 24-May-24 26.00 1291 WC6-SLV-6315 Salvage Structure: Wc-3 100%0.24 0.24 0.00 27-Apr-24 A 27-Apr-24 A 24-May-24 24-May-24 23.00 1292 WC6-SLV-6320 Salvage Structure: Wc-4 100%0.24 0.24 0.00 27-Apr-24 A 27-Apr-24 A 24-May-24 24-May-24 23.00 1293 WC6-SLV-6380 Salvage Structure: Wc-15 100%0.22 0.22 0.00 27-Apr-24 A 27-Apr-24 A 24-May-24 24-May-24 23.00 1294 WC6-SLV-6425 Salvage Structure: Wc-24 100%0.22 0.22 0.00 06-May-24 A 06-May-24 A 25-Jun-24 25-Jun-24 43.00 1295 WC6-SLV-6400 Salvage Structure: Wc-19 100%0.22 0.22 0.00 11-May-24 A 11-May-24 A 24-May-24 25-May-24 11.94 1296 WC6-SLV-6405 Salvage Structure: Wc-20 100%0.22 1.22 0.00 11-May-24 A 13-May-24 A 25-May-24 25-May-24 10.94 1297 WC6-SLV-6970 Salvage Structure: Wc-47 Golden Eagle Nest - Variance Granted 100%0.25 0.25 0.00 23-May-24 A 23-May-24 A 16-Aug-24 16-Aug-24 70.38 1298 WC6-SLV-6975 Salvage Structure: Wc-48 Golden Eagle Nest - Variance Granted 100%0.25 0.25 0.00 23-May-24 A 23-May-24 A 16-Aug-24 16-Aug-24 70.38 1299 WC6-SLV-6475 Salvage Structure: Wc-34 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 05-Jun-24 A 06-Jun-24 A 10-Jul-24 10-Jul-24 26.83 1300 WC6-SLV-6480 Salvage Structure: Wc-35 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 06-Jun-24 A 06-Jun-24 A 11-Jul-24 11-Jul-24 27.34 1301 WC6-SLV-6485 Salvage Structure: Wc-36 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 06-Jun-24 A 06-Jun-24 A 12-Jul-24 12-Jul-24 27.85 1302 WC6-SLV-6490 Salvage Structure: Wc-37 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 06-Jun-24 A 06-Jun-24 A 12-Jul-24 13-Jul-24 28.35 1303 WC6-SLV-6470 Salvage Structure: Wc-33 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 06-Jun-24 A 06-Jun-24 A 09-Jul-24 10-Jul-24 25.32 1304 WC6-SLV-6495 Salvage Structure: Wc-38 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 06-Jun-24 A 06-Jun-24 A 13-Jul-24 13-Jul-24 28.86 1305 WC6-SLV-6435 Salvage Structure: Wc-26 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 07-Jun-24 A 07-Jun-24 A 01-Jul-24 01-Jul-24 19.78 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Salvage Structure: Wc-229, 05-Aug-24 Salvage Structure: Wc-230, 06-Aug-24 Salvage Structure: Wc-231, 06-Aug-24 Salvage Structure: Wc-232, 06-Aug-24 Salvage Structure: Wc-233, 06-Aug-24 Salvage Structure: Wc-234, 07-Aug-24 Salvage Structure: Wc-235, 07-Aug-24 Salvage Structure: Wc-236, 07-Aug-24 Salvage Structure: Wc-237, 07-Aug-24 Salvage Structure: Wc-238, 08-Aug-24 Salvage Structure: Wc-239, 08-Aug-24 Salvage Structure: Wc-240, 08-Aug-24 Salvage Structure: Wc-241, 08-Aug-24 Salvage Structure: Wc-242, 09-Aug-24 Salvage Structure: Wc-243, 09-Aug-24 Salvage Structure: Wc-244, 09-Aug-24 Salvage Structure: Wc-245 *raptor restriction start*, 09-Aug-24 Salvage Structure: Wc-246, 10-Aug-24 Salvage Structure: Wc-247, 10-Aug-24 Salvage Structure: Wc-248, 10-Aug-24 Salvage Structure: Wc-249, 10-Aug-24 Salvage Structure: Wc-250, 12-Aug-24 Salvage Structure: Wc-251, 12-Aug-24 Salvage Structure: Wc-252, 12-Aug-24 Salvage Structure: Wc-253, 12-Aug-24 Salvage Structure: Wc-254, 13-Aug-24 Salvage Structure: Wc-255, 13-Aug-24 Salvage Structure: Wc-256, 13-Aug-24 Salvage Structure: Wc-257 *Raptor restriction end, 13-Aug-24 Salvage Structure: Wc-258, 14-Aug-24 Salvage Structure: Wc-259, 14-Aug-24 Salvage Structure: Wc-260, 14-Aug-24 Salvage Structure: Wc-261, 14-Aug-24 Salvage Structure: Wc-262, 15-Aug-24 Salvage Structure: Wc-263, 15-Aug-24 Salvage Structure: Wc-264, 15-Aug-24 Salvage Structure: Wc-265, 15-Aug-24 Salvage Structure: Wc-266, 16-Aug-24 Salvage Structure: Wc-267, 16-Aug-24 15-Jun-24 A, Crew 3 (done with fram ing/sett ing/stringing) Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 25 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1306 WC6-SLV-6445 Salvage Structure: Wc-28 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 08-Jun-24 A 08-Jun-24 A 02-Jul-24 02-Jul-24 20.24 1307 WC6-SLV-6465 Salvage Structure: Wc-32 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 08-Jun-24 A 08-Jun-24 A 09-Jul-24 09-Jul-24 23.05 1308 WC6-SLV-6430 Salvage Structure: Wc-25 Sage Grouse - Variance Granted 100%1.22 1.22 0.00 10-Jun-24 A 11-Jun-24 A 26-Jun-24 26-Jun-24 13.13 1309 WC6-SLV-6450 Salvage Structure: Wc-29 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 12-Jun-24 A 12-Jun-24 A 03-Jul-24 03-Jul-24 17.75 1310 WC6-SLV-6460 Salvage Structure: Wc-31 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 12-Jun-24 A 13-Jun-24 A 08-Jul-24 08-Jul-24 18.76 1311 WC6-SLV-6500 Salvage Structure: Wc-39 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 13-Jun-24 A 13-Jun-24 A 15-Jul-24 15-Jul-24 24.26 1312 WC6-SLV-6455 Salvage Structure: Wc-30 Sage Grouse - Variance Granted 100%0.22 0.22 0.00 15-Jun-24 A 15-Jun-24 A 03-Jul-24 08-Jul-24 15.25 1313 Frame StructuresFrame StructuresFrame Structures 163.41 113.42 44.75 13-Feb-24 A 24-Aug-24 38.55 13-Feb-24 26-Aug-24 0.40 1314 2024 Spring/Sum2024 Spring/Summer2024 Spring/Summer 163.41 113.42 44.75 13-Feb-24 A 24-Aug-24 38.55 13-Feb-24 26-Aug-24 0.40 1315 Crew 1Crew 1Crew 1 100.26 100.52 0.00 13-Feb-24 A 08-Jun-24 A 13-Feb-24 26-Aug-24 63.55 1316 WC6-FRM-6000 2024 Line Construction Mobilization (Crew 1)100%0.00 0.00 0.00 13-Feb-24 A 13-Feb-24 0.00 1317 WC6-FRM-6040 Frame Structure: Wc-8 100%0.30 0.30 0.00 13-Feb-24 A 13-Feb-24 A 13-Feb-24 13-Feb-24 0.00 1318 WC6-FRM-6045 Frame Structure: Wc-9 100%0.30 0.30 0.00 14-Feb-24 A 14-Feb-24 A 14-Feb-24 14-Feb-24 0.00 1319 WC6-FRM-6085 Frame Structure: Wc-17 100%0.30 0.30 0.00 20-Feb-24 A 20-Feb-24 A 20-Feb-24 20-Feb-24 0.00 1320 WC6-FRM-6050 Frame Structure: Wc-10 100%0.30 0.30 0.00 22-Feb-24 A 23-Feb-24 A 22-Feb-24 23-Feb-24 0.00 1321 WC6-FRM-6105 Frame Structure: Wc-21 100%0.40 0.40 0.00 26-Feb-24 A 26-Feb-24 A 26-Feb-24 26-Feb-24 0.00 1322 WC6-FRM-6110 Frame Structure: Wc-22 100%0.40 0.40 0.00 26-Feb-24 A 27-Feb-24 A 26-Feb-24 27-Feb-24 0.00 1323 WC6-FRM-6055 Frame Structure: Wc-11 100%0.30 0.30 0.00 27-Feb-24 A 27-Feb-24 A 27-Feb-24 27-Feb-24 0.00 1324 WC6-FRM-6115 Frame Structure: Wc-23 100%0.40 0.40 0.00 27-Feb-24 A 28-Feb-24 A 27-Feb-24 28-Feb-24 0.00 1325 WC6-FRM-6065 Frame Structure: Wc-13 100%0.30 0.30 0.00 27-Feb-24 A 28-Feb-24 A 27-Feb-24 28-Feb-24 0.00 1326 WC6-FRM-6035 Frame Structure: Wc-7 100%0.30 0.30 0.00 28-Feb-24 A 28-Feb-24 A 28-Feb-24 28-Feb-24 0.00 1327 WC6-FRM-6060 Frame Structure: Wc-12 100%0.30 0.30 0.00 28-Feb-24 A 28-Feb-24 A 28-Feb-24 28-Feb-24 0.00 1328 WC6-FRM-6090 Frame Structure: Wc-18 100%0.30 0.30 0.00 29-Feb-24 A 29-Feb-24 A 29-Feb-24 29-Feb-24 0.00 1329 WC6-FRM-6080 Frame Structure: Wc-16 100%0.30 0.30 0.00 29-Feb-24 A 01-Mar-24 A 29-Feb-24 01-Mar-24 0.00 1330 WC6-FRM-6005 Frame Structure: Wc-1 100%0.30 0.30 0.00 11-Mar-24 A 11-Mar-24 A 11-Mar-24 11-Mar-24 0.00 1331 WC6-FRM-6030 Frame Structure: Wc-6 100%0.30 0.30 0.00 14-Mar-24 A 15-Mar-24 A 14-Mar-24 15-Mar-24 0.00 1332 WC6-FRM-6070 Frame Structure: Wc-14 100%0.30 0.30 0.00 15-Mar-24 A 15-Mar-24 A 15-Mar-24 15-Mar-24 0.00 1333 WC7-FRM-7205 Frame Structure: Wc-92 100%0.20 0.20 0.00 14-May-24 A 14-May-24 A 15-May-24 15-May-24 0.85 1334 Crew 2 Frame Structure: Wc-91 100%0.20 0.20 0.00 14-May-24 A 14-May-24 A 15-May-24 15-May-24 0.85 1335 WC7-FRM-7190 Frame Structure: Wc-89 100%0.20 0.20 0.00 15-May-24 A 16-May-24 A 15-May-24 15-May-24 -0.15 1336 WC7-FRM-7185 Frame Structure: Wc-88 100%0.20 0.20 0.00 16-May-24 A 16-May-24 A 16-May-24 16-May-24 -0.45 1337 WC7-FRM-7180 Frame Structure: Wc-87 100%0.20 0.20 0.00 17-May-24 A 17-May-24 A 16-May-24 16-May-24 -1.15 1338 WC7-FRM-7175 Frame Structure: Wc-86 100%0.20 0.20 0.00 17-May-24 A 17-May-24 A 16-May-24 16-May-24 -1.15 1339 WC7-FRM-7170 Frame Structure: Wc-85 100%0.20 0.20 0.00 17-May-24 A 17-May-24 A 16-May-24 16-May-24 -1.15 1340 WC7-FRM-7115 Frame Structure: Wc-74 100%0.20 0.20 0.00 17-May-24 A 18-May-24 A 18-May-24 18-May-24 0.85 1341 WC7-FRM-7110 Frame Structure: Wc-73 100%0.20 0.20 0.00 18-May-24 A 18-May-24 A 20-May-24 20-May-24 1.85 1342 WC7-FRM-7105 Frame Structure: Wc-72 100%0.20 0.20 0.00 18-May-24 A 18-May-24 A 20-May-24 20-May-24 1.85 1343 WC7-FRM-7100 Frame Structure: Wc-71 100%0.20 0.20 0.00 18-May-24 A 18-May-24 A 20-May-24 20-May-24 1.85 1344 WC7-FRM-7095 Frame Structure: Wc-70 100%0.20 0.20 0.00 18-May-24 A 18-May-24 A 20-May-24 20-May-24 1.85 1345 WC7-FRM-7130 Frame Structure: Wc-77 100%0.20 0.20 0.00 19-May-24 A 19-May-24 A 18-May-24 18-May-24 -0.85 1346 WC7-FRM-7125 Frame Structure: Wc-76 100%0.20 0.20 0.00 19-May-24 A 19-May-24 A 18-May-24 18-May-24 -0.85 1347 WC7-FRM-7120 Frame Structure: Wc-75 100%0.20 0.20 0.00 19-May-24 A 19-May-24 A 18-May-24 18-May-24 -0.85 1348 WC7-FRM-7135 Frame Structure: Wc-78 100%0.20 0.20 0.00 21-May-24 A 22-May-24 A 18-May-24 18-May-24 -3.85 1349 WC7-FRM-7075 Frame Structure: Wc-66 100%0.20 0.20 0.00 22-May-24 A 22-May-24 A 21-May-24 21-May-24 -0.85 1350 WC7-FRM-7140 Frame Structure: Wc-79 100%0.20 0.20 0.00 22-May-24 A 22-May-24 A 17-May-24 17-May-24 -4.85 1351 WC7-FRM-7090 Frame Structure: Wc-69 100%0.20 0.20 0.00 22-May-24 A 22-May-24 A 20-May-24 20-May-24 -2.00 1352 WC6-FRM-6300 Frame Structure: Wc-47 Golden Eagle Nest - Variance Granted 100%0.20 0.20 0.00 23-May-24 A 23-May-24 A 24-Aug-24 24-Aug-24 77.38 1353 WC6-FRM-6305 Frame Structure: Wc-48 Golden Eagle Nest - Variance Granted 100%0.20 0.20 0.00 23-May-24 A 23-May-24 A 24-Aug-24 26-Aug-24 77.33 1354 WC6-FRM-6225 Frame Structure: Wc-45 100%0.20 0.20 0.00 23-May-24 A 23-May-24 A 24-May-24 24-May-24 1.15 1355 WC7-FRM-7085 Frame Structure: Wc-68 100%0.20 0.20 0.00 23-May-24 A 24-May-24 A 21-May-24 21-May-24 -2.85 1356 WC6-FRM-6220 Frame Structure: Wc-44 100%0.20 0.20 0.00 23-May-24 A 24-May-24 A 25-May-24 25-May-24 1.15 1357 WC7-FRM-7000 Frame Structure: Wc-51 100%0.20 0.20 0.00 24-May-24 A 24-May-24 A 24-May-24 24-May-24 0.15 1358 WC7-FRM-7055 Frame Structure: Wc-62 100%0.20 0.20 0.00 24-May-24 A 24-May-24 A 22-May-24 22-May-24 -2.20 1359 WC7-FRM-7020 Frame Structure: Wc-55 100%0.20 0.20 0.00 24-May-24 A 24-May-24 A 23-May-24 23-May-24 -0.85 1360 WC7-FRM-7015 Frame Structure: Wc-54 100%0.20 0.20 0.00 24-May-24 A 24-May-24 A 23-May-24 23-May-24 -0.85 1361 WC7-FRM-7035 Frame Structure: Wc-58 100%0.20 0.20 0.00 24-May-24 A 25-May-24 A 23-May-24 23-May-24 -1.85 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 4 24-Aug-24, Frame Structures 24-Aug-24, 2024 Spring/Summer 08-Jun-24 A, Crew 1 Construction Mobilization (Crew 1), Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 26 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1362 WC7-FRM-7080 Frame Structure: Wc-67 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 21-May-24 21-May-24 -3.85 1363 WC7-FRM-7030 Frame Structure: Wc-57 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 23-May-24 23-May-24 -1.85 1364 WC7-FRM-7025 Frame Structure: Wc-56 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 23-May-24 23-May-24 -1.85 1365 WC7-FRM-7045 Frame Structure: Wc-60 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 22-May-24 22-May-24 -2.85 1366 WC6-FRM-6230 Frame Structure: Wc-46 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 24-May-24 24-May-24 -0.85 1367 WC7-FRM-7040 Frame Structure: Wc-59 100%0.20 0.20 0.00 25-May-24 A 25-May-24 A 22-May-24 22-May-24 -2.85 1368 WC7-FRM-7050 Frame Structure: Wc-61 100%0.20 0.00 0.00 26-May-24 A 26-May-24 A 22-May-24 22-May-24 -3.40 1369 WC7-FRM-7010 Frame Structure: Wc-53 100%0.20 0.20 0.00 25-May-24 A 27-May-24 A 24-May-24 24-May-24 -1.85 1370 WC7-FRM-7155 Frame Structure: Wc-82 100%0.20 0.20 0.00 27-May-24 A 27-May-24 A 17-May-24 17-May-24 -8.85 1371 WC7-FRM-7005 Frame Structure: Wc-52 100%0.20 0.20 0.00 27-May-24 A 27-May-24 A 24-May-24 24-May-24 -1.85 1372 WC7-FRM-7150 Frame Structure: Wc-81 100%0.20 0.20 0.00 27-May-24 A 27-May-24 A 17-May-24 17-May-24 -8.85 1373 WC7-FRM-7145 Frame Structure: Wc-80 100%0.20 0.20 0.00 27-May-24 A 27-May-24 A 17-May-24 17-May-24 -8.85 1374 WC7-FRM-7070 Frame Structure: Wc-65 100%0.20 0.20 0.00 28-May-24 A 28-May-24 A 21-May-24 21-May-24 -5.40 1375 WC7-FRM-7210 Frame Structure: Wc-93 100%0.20 0.20 0.00 28-May-24 A 28-May-24 A 15-May-24 15-May-24 -12.00 1376 WC7-FRM-7195 Frame Structure: Wc-90 100%0.20 0.20 0.00 28-May-24 A 28-May-24 A 15-May-24 15-May-24 -11.60 1377 Crew 2 Frame Structure: Wc-84 100%0.20 0.20 0.00 28-May-24 A 28-May-24 A 16-May-24 16-May-24 -10.60 1378 WC7-FRM-7160 Frame Structure: Wc-83 100%0.20 0.20 0.00 28-May-24 A 28-May-24 A 17-May-24 17-May-24 -10.60 1379 WC6-FRM-6210 Frame Structure: Wc-42 100%0.20 0.20 0.00 29-May-24 A 29-May-24 A 25-May-24 25-May-24 -2.96 1380 WC6-FRM-6205 Frame Structure: Wc-41 100%0.20 0.20 0.00 29-May-24 A 29-May-24 A 25-May-24 25-May-24 -2.96 1381 WC6-FRM-6215 Frame Structure: Wc-43 100%0.20 0.20 0.00 29-May-24 A 29-May-24 A 25-May-24 25-May-24 -3.60 1382 WC7-FRM-7065 Frame Structure: Wc-64 100%0.20 0.20 0.00 05-Jun-24 A 05-Jun-24 A 21-May-24 21-May-24 -12.20 1383 WC7-FRM-7060 Frame Structure: Wc-63 100%0.20 0.20 0.00 06-Jun-24 A 06-Jun-24 A 22-May-24 22-May-24 -13.20 1384 WC6-FRM-6200 Frame Structure: Wc-40 - end 100%0.20 0.20 0.00 08-Jun-24 A 08-Jun-24 A 25-May-24 25-May-24 -11.60 1385 Crew 2Crew 2Crew 2 139.75 89.50 44.75 12-Mar-24 A 24-Aug-24 8.78 16-Mar-24 24-Aug-24 0.00 1386 WC6-FRM-6135 Frame Structure: Wc-27 100%0.73 0.73 0.00 12-Mar-24 A 12-Mar-24 A 01-Jul-24 02-Jul-24 95.95 1387 WC6-FRM-6120 Frame Structure: Wc-24 100%0.73 0.73 0.00 14-Mar-24 A 15-Mar-24 A 25-Jun-24 26-Jun-24 88.00 1388 WC6-FRM-6025 Frame Structure: Wc-5 100%0.30 0.30 0.00 16-Mar-24 A 16-Mar-24 A 16-Mar-24 16-Mar-24 0.00 1389 WC6-FRM-6075 Frame Structure: Wc-15 100%0.30 0.30 0.00 19-Apr-24 A 20-Apr-24 A 25-May-24 27-May-24 31.00 1390 WC6-FRM-6015 Frame Structure: Wc-3 100%0.75 0.75 0.00 22-Apr-24 A 23-Apr-24 A 24-May-24 25-May-24 28.00 1391 WC6-FRM-6010 Frame Structure: Wc-2 100%0.50 0.50 0.00 29-Apr-24 A 29-Apr-24 A 24-May-24 24-May-24 22.00 1392 WC6-FRM-6020 Frame Structure: Wc-4 100%0.30 0.30 0.00 29-Apr-24 A 29-Apr-24 A 25-May-24 25-May-24 23.00 1393 WC6-FRM-6095 Frame Structure: Wc-19 100%0.73 0.73 0.00 30-Apr-24 A 30-Apr-24 A 24-Jun-24 24-Jun-24 47.00 1394 WC6-FRM-6100 Frame Structure: Wc-20 100%0.73 0.73 0.00 06-May-24 A 06-May-24 A 24-Jun-24 25-Jun-24 42.89 1395 WC6-FRM-6125 Frame Structure: Wc-25 Sage Grouse - Variance granted 25-39 100%0.73 0.73 0.00 03-Jun-24 A 03-Jun-24 A 26-Jun-24 27-Jun-24 20.35 1396 WC6-FRM-6185 Frame Structure: Wc-37 100%0.73 0.73 0.00 03-Jun-24 A 04-Jun-24 A 13-Jul-24 13-Jul-24 31.62 1397 WC6-FRM-6150 Frame Structure: Wc-30 100%0.73 0.73 0.00 03-Jun-24 A 04-Jun-24 A 08-Jul-24 08-Jul-24 26.62 1398 WC6-FRM-6190 Frame Structure: Wc-38 100%0.73 0.73 0.00 04-Jun-24 A 04-Jun-24 A 13-Jul-24 15-Jul-24 31.62 1399 WC6-FRM-6130 Frame Structure: Wc-26 100%0.73 0.73 0.00 06-Jun-24 A 07-Jun-24 A 01-Jul-24 01-Jul-24 20.89 1400 WC6-FRM-6160 Frame Structure: Wc-32 100%0.50 0.50 0.00 06-Jun-24 A 07-Jun-24 A 09-Jul-24 10-Jul-24 24.97 1401 WC6-FRM-6140 Frame Structure: Wc-28 100%0.73 0.73 0.00 07-Jun-24 A 08-Jun-24 A 02-Jul-24 03-Jul-24 21.24 1402 WC6-FRM-6170 Frame Structure: Wc-34 100%0.73 0.73 0.00 10-Jun-24 A 10-Jun-24 A 10-Jul-24 11-Jul-24 23.83 1403 WC6-FRM-6175 Frame Structure: Wc-35 100%0.73 0.73 0.00 10-Jun-24 A 10-Jun-24 A 11-Jul-24 12-Jul-24 24.57 1404 WC6-FRM-6180 Frame Structure: Wc-36 100%0.73 0.88 0.00 10-Jun-24 A 10-Jun-24 A 12-Jul-24 13-Jul-24 25.15 1405 WC6-FRM-6145 Frame Structure: Wc-29 100%0.73 0.73 0.00 12-Jun-24 A 12-Jun-24 A 03-Jul-24 08-Jul-24 18.24 1406 WC6-FRM-6155 Frame Structure: Wc-31 100%0.73 0.73 0.00 12-Jun-24 A 13-Jun-24 A 08-Jul-24 09-Jul-24 18.97 1407 WC6-FRM-6195 Frame Structure: Wc-39 100%0.73 0.73 0.00 19-Jun-24 A 20-Jun-24 A 15-Jul-24 16-Jul-24 18.76 1408 WC6-FRM-6165 Frame Structure: Wc-33 - Bird Nest Issue 100%0.50 0.50 0.00 24-Jun-24 A 24-Jun-24 A 10-Jul-24 10-Jul-24 11.33 1409 WC1-FRM-1510a Frame Structure: Str Wc170 0%0.25 0.00 0.25 01-Jul-24 01-Jul-24 23.98 16-Jul-24 16-Jul-24 10.22 1410 WC1-FRM-1510b Frame Structure: Str Wc172 0%0.30 0.00 0.30 01-Jul-24 01-Jul-24 23.98 16-Jul-24 16-Jul-24 10.22 1411 WC8-FRM-8000 Frame Structure: Wc-208 0%0.20 0.00 0.20 01-Aug-24 01-Aug-24 0.33 01-Aug-24 01-Aug-24 0.00 1412 WC1-FRM-1514 Frame Structure: Wc-149-208 Assist with deadends 0%8.00 0.00 8.00 01-Aug-24 10-Aug-24 6.88 01-Aug-24 10-Aug-24 0.00 1413 WC8-FRM-8005 Frame Structure: Wc-209 0%0.20 0.00 0.20 10-Aug-24 12-Aug-24 6.88 10-Aug-24 12-Aug-24 0.00 1414 WC8-FRM-8010 Frame Structure: Wc-210 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 6.93 12-Aug-24 12-Aug-24 0.00 1415 WC8-FRM-8015 Frame Structure: Wc-211 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 6.98 12-Aug-24 12-Aug-24 0.00 1416 WC8-FRM-8020 Frame Structure: Wc-212 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 7.03 12-Aug-24 12-Aug-24 0.00 1417 WC8-FRM-8025 Frame Structure: Wc-213 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 7.08 12-Aug-24 12-Aug-24 0.00 1418 WC8-FRM-8030 Frame Structure: Wc-214 0%0.20 0.00 0.20 12-Aug-24 13-Aug-24 7.13 12-Aug-24 13-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 24-Aug-24, Crew 2 4 4 4 4 4 4 4 4 4 24 24 -24 24 Frame Structure: Str Wc170, 01-Jul-24 Frame Structure: Str Wc172, 01-Jul-24 Frame Structure: Wc-208, 01-Aug-24 Frame Structure: Wc-149-208 Assist with deadends, 10-Aug-24 Frame Structure: Wc-209, 12-Aug-24 Frame Structure: Wc-210, 12-Aug-24 Frame Structure: Wc-211, 12-Aug-24 Frame Structure: Wc-212, 12-Aug-24 Frame Structure: Wc-213, 12-Aug-24 Frame Structure: Wc-214, 13-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 27 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1419 Crew 2 Frame Structure: Wc-215 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 7.18 13-Aug-24 13-Aug-24 0.00 1420 WC8-FRM-8040 Frame Structure: Wc-216 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 7.23 13-Aug-24 13-Aug-24 0.00 1421 WC8-FRM-8045 Frame Structure: Wc-217 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 7.28 13-Aug-24 13-Aug-24 0.00 1422 WC8-FRM-8050 Frame Structure: Wc-218 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 7.33 13-Aug-24 13-Aug-24 0.00 1423 WC8-FRM-8055 Frame Structure: Wc-219 0%0.20 0.00 0.20 13-Aug-24 14-Aug-24 7.38 13-Aug-24 14-Aug-24 0.00 1424 WC8-FRM-8060 Frame Structure: Wc-220 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 7.43 14-Aug-24 14-Aug-24 0.00 1425 WC8-FRM-8065 Frame Structure: Wc-221 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 7.48 14-Aug-24 14-Aug-24 0.00 1426 WC8-FRM-8070 Frame Structure: Wc-222 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 7.53 14-Aug-24 14-Aug-24 0.00 1427 WC8-FRM-8075 Frame Structure: Wc-223 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 7.58 14-Aug-24 14-Aug-24 0.00 1428 WC8-FRM-8080 Frame Structure: Wc-224 0%0.20 0.00 0.20 14-Aug-24 15-Aug-24 7.63 14-Aug-24 15-Aug-24 0.00 1429 WC8-FRM-8085 Frame Structure: Wc-225 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 7.68 15-Aug-24 15-Aug-24 0.00 1430 WC8-FRM-8090 Frame Structure: Wc-226 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 7.73 15-Aug-24 15-Aug-24 0.00 1431 WC8-FRM-8095 Frame Structure: Wc-227 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 7.78 15-Aug-24 15-Aug-24 0.00 1432 WC8-FRM-8100 Frame Structure: Wc-228 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 7.83 15-Aug-24 15-Aug-24 0.00 1433 WC8-FRM-8105 Frame Structure: Wc-229 0%0.20 0.00 0.20 15-Aug-24 16-Aug-24 7.88 15-Aug-24 16-Aug-24 0.00 1434 WC8-FRM-8110 Frame Structure: Wc-230 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 7.93 16-Aug-24 16-Aug-24 0.00 1435 WC8-FRM-8115 Frame Structure: Wc-231 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 7.98 16-Aug-24 16-Aug-24 0.00 1436 WC8-FRM-8120 Frame Structure: Wc-232 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 8.03 16-Aug-24 16-Aug-24 0.00 1437 WC8-FRM-8125 Frame Structure: Wc-233 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 8.08 16-Aug-24 16-Aug-24 0.00 1438 WC8-FRM-8130 Frame Structure: Wc-234 0%0.20 0.00 0.20 16-Aug-24 17-Aug-24 8.13 16-Aug-24 17-Aug-24 0.00 1439 WC8-FRM-8135 Frame Structure: Wc-235 0%0.20 0.00 0.20 17-Aug-24 17-Aug-24 8.18 17-Aug-24 17-Aug-24 0.00 1440 WC8-FRM-8140 Frame Structure: Wc-236 0%0.20 0.00 0.20 17-Aug-24 17-Aug-24 8.23 17-Aug-24 17-Aug-24 0.00 1441 WC8-FRM-8145 Frame Structure: Wc-237 0%0.20 0.00 0.20 17-Aug-24 17-Aug-24 8.28 17-Aug-24 17-Aug-24 0.00 1442 WC8-FRM-8150 Frame Structure: Wc-238 0%0.20 0.00 0.20 17-Aug-24 17-Aug-24 8.33 17-Aug-24 17-Aug-24 0.00 1443 WC8-FRM-8155 Frame Structure: Wc-239 0%0.20 0.00 0.20 17-Aug-24 19-Aug-24 8.38 17-Aug-24 19-Aug-24 0.00 1444 Crew 2 Frame Structure: Wc-240 0%0.20 0.00 0.20 19-Aug-24 19-Aug-24 8.43 19-Aug-24 19-Aug-24 0.00 1445 WC8-FRM-8165 Frame Structure: Wc-241 0%0.20 0.00 0.20 19-Aug-24 19-Aug-24 8.48 19-Aug-24 19-Aug-24 0.00 1446 WC8-FRM-8170 Frame Structure: Wc-242 0%0.20 0.00 0.20 19-Aug-24 19-Aug-24 8.53 19-Aug-24 19-Aug-24 0.00 1447 WC8-FRM-8175 Frame Structure: Wc-243 0%0.20 0.00 0.20 19-Aug-24 19-Aug-24 8.58 19-Aug-24 19-Aug-24 0.00 1448 WC8-FRM-8180 Frame Structure: Wc-244 0%0.20 0.00 0.20 19-Aug-24 20-Aug-24 8.63 19-Aug-24 20-Aug-24 0.00 1449 WC8-FRM-8300 Frame Structure: Wc-245 *raptor restriction start*0%0.20 0.00 0.20 20-Aug-24 20-Aug-24 8.68 20-Aug-24 20-Aug-24 0.00 1450 WC8-FRM-8305 Frame Structure: Wc-246 0%0.20 0.00 0.20 20-Aug-24 20-Aug-24 8.73 20-Aug-24 20-Aug-24 0.00 1451 WC8-FRM-8310 Frame Structure: Wc-247 0%0.20 0.00 0.20 20-Aug-24 20-Aug-24 8.78 20-Aug-24 20-Aug-24 0.00 1452 WC8-FRM-8315 Frame Structure: Wc-248 0%0.20 0.00 0.20 20-Aug-24 20-Aug-24 8.83 20-Aug-24 20-Aug-24 0.00 1453 WC8-FRM-8320 Frame Structure: Wc-249 0%0.20 0.00 0.20 20-Aug-24 21-Aug-24 8.88 20-Aug-24 21-Aug-24 0.00 1454 WC8-FRM-8325 Frame Structure: Wc-250 0%0.20 0.00 0.20 21-Aug-24 21-Aug-24 8.93 21-Aug-24 21-Aug-24 0.00 1455 WC8-FRM-8330 Frame Structure: Wc-251 0%0.20 0.00 0.20 21-Aug-24 21-Aug-24 8.98 21-Aug-24 21-Aug-24 0.00 1456 WC8-FRM-8335 Frame Structure: Wc-252 0%0.20 0.00 0.20 21-Aug-24 21-Aug-24 9.03 21-Aug-24 21-Aug-24 0.00 1457 WC8-FRM-8340 Frame Structure: Wc-253 0%0.20 0.00 0.20 21-Aug-24 21-Aug-24 9.08 21-Aug-24 21-Aug-24 0.00 1458 WC8-FRM-8345 Frame Structure: Wc-254 0%0.20 0.00 0.20 21-Aug-24 22-Aug-24 9.13 21-Aug-24 22-Aug-24 0.00 1459 WC8-FRM-8350 Frame Structure: Wc-255 0%0.20 0.00 0.20 22-Aug-24 22-Aug-24 9.18 22-Aug-24 22-Aug-24 0.00 1460 WC8-FRM-8355 Frame Structure: Wc-256 0%0.20 0.00 0.20 22-Aug-24 22-Aug-24 9.23 22-Aug-24 22-Aug-24 0.00 1461 WC8-FRM-8360 Frame Structure: Wc-257 *raptor restriction end* *jump to 47*0%0.20 0.00 0.20 22-Aug-24 22-Aug-24 9.28 22-Aug-24 22-Aug-24 0.00 1462 WC8-FRM-8185 Frame Structure: Wc-258 0%0.20 0.00 0.20 22-Aug-24 22-Aug-24 9.33 22-Aug-24 22-Aug-24 0.00 1463 WC8-FRM-8190 Frame Structure: Wc-259 0%0.20 0.00 0.20 22-Aug-24 23-Aug-24 9.38 22-Aug-24 23-Aug-24 0.00 1464 WC8-FRM-8195 Frame Structure: Wc-260 0%0.20 0.00 0.20 23-Aug-24 23-Aug-24 9.43 23-Aug-24 23-Aug-24 0.00 1465 WC8-FRM-8200 Frame Structure: Wc-261 0%0.20 0.00 0.20 23-Aug-24 23-Aug-24 9.48 23-Aug-24 23-Aug-24 0.00 1466 WC8-FRM-8205 Frame Structure: Wc-262 0%0.20 0.00 0.20 23-Aug-24 23-Aug-24 9.53 23-Aug-24 23-Aug-24 0.00 1467 WC8-FRM-8210 Frame Structure: Wc-263 0%0.20 0.00 0.20 23-Aug-24 23-Aug-24 9.58 23-Aug-24 23-Aug-24 0.00 1468 WC8-FRM-8215 Frame Structure: Wc-264 0%0.20 0.00 0.20 23-Aug-24 24-Aug-24 9.63 23-Aug-24 24-Aug-24 0.00 1469 WC8-FRM-8220 Frame Structure: Wc-265 0%0.20 0.00 0.20 24-Aug-24 24-Aug-24 9.68 24-Aug-24 24-Aug-24 0.00 1470 WC8-FRM-8225 Frame Structure: Wc-266 0%0.20 0.00 0.20 24-Aug-24 24-Aug-24 9.73 24-Aug-24 24-Aug-24 0.00 1471 WC8-FRM-8230 Frame Structure: Wc-267 0%0.20 0.00 0.20 24-Aug-24 24-Aug-24 9.78 24-Aug-24 24-Aug-24 0.00 1472 Crew 3Crew 3Crew 3 37.71 0.00 37.71 01-Jul-24 16-Aug-24 45.36 03-Jul-24 16-Aug-24 0.00 1473 WC7-FRM-7485 Frame Structure: Wc-148 - start here 0%0.30 0.00 0.30 01-Jul-24 01-Jul-24 24.84 03-Jul-24 03-Jul-24 2.00 1474 WC7-FRM-7480 Frame Structure: Wc-147 0%0.30 0.00 0.30 01-Jul-24 01-Jul-24 26.89 03-Jul-24 03-Jul-24 2.00 1475 WC7-FRM-7475 Frame Structure: Wc-146 0%0.30 0.00 0.30 01-Jul-24 02-Jul-24 26.94 03-Jul-24 08-Jul-24 2.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structure: Wc-215, 13-Aug-24 Frame Structure: Wc-216, 13-Aug-24 Frame Structure: Wc-217, 13-Aug-24 Frame Structure: Wc-218, 13-Aug-24 Frame Structure: Wc-219, 14-Aug-24 Frame Structure: Wc-220, 14-Aug-24 Frame Structure: Wc-221, 14-Aug-24 Frame Structure: Wc-222, 14-Aug-24 Frame Structure: Wc-223, 14-Aug-24 Frame Structure: Wc-224, 15-Aug-24 Frame Structure: Wc-225, 15-Aug-24 Frame Structure: Wc-226, 15-Aug-24 Frame Structure: Wc-227, 15-Aug-24 Frame Structure: Wc-228, 15-Aug-24 Frame Structure: Wc-229, 16-Aug-24 Frame Structure: Wc-230, 16-Aug-24 Frame Structure: Wc-231, 16-Aug-24 Frame Structure: Wc-232, 16-Aug-24 Frame Structure: Wc-233, 16-Aug-24 Frame Structure: Wc-234, 17-Aug-24 Frame Structure: Wc-235, 17-Aug-24 Frame Structure: Wc-236, 17-Aug-24 Frame Structure: Wc-237, 17-Aug-24 Frame Structure: Wc-238, 17-Aug-24 Frame Structure: Wc-239, 19-Aug-24 Frame Structure: Wc-240, 19-Aug-24 Frame Structure: Wc-241, 19-Aug-24 Frame Structure: Wc-242, 19-Aug-24 Frame Structure: Wc-243, 19-Aug-24 Frame Structure: Wc-244, 20-Aug-24 Frame Structure: Wc-245 *raptor restriction start*, 20-Aug-24 Frame Structure: Wc-246, 20-Aug-24 Frame Structure: Wc-247, 20-Aug-24 Frame Structure: Wc-248, 20-Aug-24 Frame Structure: Wc-249, 21-Aug-24 Frame Structure: Wc-250, 21-Aug-24 Frame Structure: Wc-251, 21-Aug-24 Frame Structure: Wc-252, 21-Aug-24 Frame Structure: Wc-253, 21-Aug-24 Frame Structure: Wc-254, 22-Aug-24 Frame Structure: Wc-255, 22-Aug-24 Frame Structure: Wc-256, 22-Aug-24 Frame Structure: Wc-257 *raptor restriction end* *jump to 47*, 22-Aug-24 Frame Structure: Wc-258, 22-Aug-24 Frame Structure: Wc-259, 23-Aug-24 Frame Structure: Wc-260, 23-Aug-24 Frame Structure: Wc-261, 23-Aug-24 Frame Structure: Wc-262, 23-Aug-24 Frame Structure: Wc-263, 23-Aug-24 Frame Structure: Wc-264, 24-Aug-24 Frame Structure: Wc-265, 24-Aug-24 Frame Structure: Wc-266, 24-Aug-24 Frame Structure: Wc-267, 24-Aug-24 16-Aug-24, Crew 3 Frame Structure: Wc-148 - start here, 01-Jul-24 Frame Structure: Wc-147, 01-Jul-24 Frame Structure: Wc-146, 02-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 28 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1476 WC7-FRM-7470 Frame Structure: Wc-145 0%0.30 0.00 0.30 02-Jul-24 02-Jul-24 26.99 08-Jul-24 08-Jul-24 2.00 1477 WC7-FRM-7465 Frame Structure: Wc-144 0%0.30 0.00 0.30 02-Jul-24 02-Jul-24 27.04 08-Jul-24 08-Jul-24 2.00 1478 WC7-FRM-7460 Frame Structure: Wc-143 0%0.30 0.00 0.30 02-Jul-24 03-Jul-24 27.09 08-Jul-24 09-Jul-24 2.00 1479 WC7-FRM-7455 Frame Structure: Wc-142 0%0.30 0.00 0.30 03-Jul-24 03-Jul-24 27.14 09-Jul-24 09-Jul-24 2.00 1480 WC7-FRM-7450 Frame Structure: Wc-141 0%0.30 0.00 0.30 03-Jul-24 03-Jul-24 27.19 09-Jul-24 09-Jul-24 2.00 1481 WC7-FRM-7445 Frame Structure: Wc-140 0%0.30 0.00 0.30 03-Jul-24 03-Jul-24 27.24 09-Jul-24 09-Jul-24 2.00 1482 WC7-FRM-7440 Frame Structure: Wc-139 0%0.30 0.00 0.30 03-Jul-24 08-Jul-24 27.29 09-Jul-24 10-Jul-24 2.00 1483 WC7-FRM-7435 Frame Structure: Wc-138 0%0.30 0.00 0.30 08-Jul-24 08-Jul-24 27.34 10-Jul-24 10-Jul-24 2.00 1484 WC7-FRM-7430 Frame Structure: Wc-137 0%0.30 0.00 0.30 08-Jul-24 08-Jul-24 27.39 10-Jul-24 10-Jul-24 2.00 1485 WC7-FRM-7425 Frame Structure: Wc-136 0%0.30 0.00 0.30 08-Jul-24 09-Jul-24 27.44 10-Jul-24 11-Jul-24 2.00 1486 WC7-FRM-7420 Frame Structure: Wc-135 0%0.30 0.00 0.30 09-Jul-24 09-Jul-24 27.49 11-Jul-24 11-Jul-24 2.00 1487 WC7-FRM-7415 Frame Structure: Wc-134 0%0.30 0.00 0.30 09-Jul-24 09-Jul-24 27.54 11-Jul-24 11-Jul-24 2.00 1488 WC7-FRM-7410 Frame Structure: Wc-133 0%0.30 0.00 0.30 09-Jul-24 10-Jul-24 27.59 11-Jul-24 12-Jul-24 2.00 1489 WC7-FRM-7405 Frame Structure: Wc-132 0%0.30 0.00 0.30 10-Jul-24 10-Jul-24 27.64 12-Jul-24 12-Jul-24 2.00 1490 WC7-FRM-7400 Frame Structure: Wc-131 0%0.30 0.00 0.30 10-Jul-24 10-Jul-24 27.69 12-Jul-24 12-Jul-24 2.00 1491 WC7-FRM-7395 Frame Structure: Wc-130 0%0.30 0.00 0.30 10-Jul-24 10-Jul-24 27.74 12-Jul-24 12-Jul-24 2.00 1492 WC7-FRM-7390 Frame Structure: Wc-129 0%0.30 0.00 0.30 10-Jul-24 11-Jul-24 27.79 12-Jul-24 13-Jul-24 2.00 1493 WC7-FRM-7385 Frame Structure: Wc-128 0%0.30 0.00 0.30 11-Jul-24 11-Jul-24 27.84 13-Jul-24 13-Jul-24 2.00 1494 WC7-FRM-7380 Frame Structure: Wc-127 0%0.30 0.00 0.30 11-Jul-24 11-Jul-24 27.89 13-Jul-24 13-Jul-24 2.00 1495 WC7-FRM-7375 Frame Structure: Wc-126 0%0.30 0.00 0.30 11-Jul-24 12-Jul-24 27.94 13-Jul-24 15-Jul-24 2.00 1496 WC7-FRM-7370 Frame Structure: Wc-125 0%0.30 0.00 0.30 12-Jul-24 12-Jul-24 27.99 15-Jul-24 15-Jul-24 2.00 1497 WC7-FRM-7365 Frame Structure: Wc-124 0%0.30 0.00 0.30 12-Jul-24 12-Jul-24 28.04 15-Jul-24 15-Jul-24 2.00 1498 WC7-FRM-7360 Frame Structure: Wc-123 0%0.30 0.00 0.30 12-Jul-24 13-Jul-24 28.24 15-Jul-24 16-Jul-24 2.00 1499 WC7-FRM-7355 Frame Structure: Wc-122 0%0.30 0.00 0.30 13-Jul-24 13-Jul-24 28.29 16-Jul-24 16-Jul-24 2.00 1500 WC7-FRM-7350 Frame Structure: Wc-121 0%0.30 0.00 0.30 13-Jul-24 13-Jul-24 28.49 16-Jul-24 16-Jul-24 2.00 1501 WC7-FRM-7345 Frame Structure: Wc-120 0%0.30 0.00 0.30 13-Jul-24 13-Jul-24 28.54 16-Jul-24 16-Jul-24 2.00 1502 WC7-FRM-7340 Frame Structure: Wc-119 0%0.30 0.00 0.30 13-Jul-24 15-Jul-24 28.59 16-Jul-24 17-Jul-24 2.00 1503 WC7-FRM-7335 Frame Structure: Wc-118 0%0.30 0.00 0.30 15-Jul-24 15-Jul-24 28.64 17-Jul-24 17-Jul-24 2.00 1504 WC7-FRM-7330 Frame Structure: Wc-117 0%0.30 0.00 0.30 15-Jul-24 15-Jul-24 28.69 17-Jul-24 17-Jul-24 2.00 1505 WC7-FRM-7325 Frame Structure: Wc-116 0%0.30 0.00 0.30 15-Jul-24 16-Jul-24 28.74 17-Jul-24 18-Jul-24 2.00 1506 WC7-FRM-7320 Frame Structure: Wc-115 0%0.30 0.00 0.30 16-Jul-24 16-Jul-24 28.79 18-Jul-24 18-Jul-24 2.00 1507 WC7-FRM-7315 Frame Structure: Wc-114 0%0.30 0.00 0.30 16-Jul-24 16-Jul-24 28.84 18-Jul-24 18-Jul-24 2.00 1508 WC7-FRM-7310 Frame Structure: Wc-113 0%0.30 0.00 0.30 16-Jul-24 17-Jul-24 28.89 18-Jul-24 19-Jul-24 2.00 1509 WC7-FRM-7305 Frame Structure: Wc-112 0%0.30 0.00 0.30 17-Jul-24 17-Jul-24 28.94 19-Jul-24 19-Jul-24 2.00 1510 WC7-FRM-7300 Frame Structure: Wc-111 0%0.30 0.00 0.30 17-Jul-24 17-Jul-24 33.89 19-Jul-24 19-Jul-24 2.00 1511 WC7-FRM-7295 Frame Structure: Wc-110 0%0.30 0.00 0.30 17-Jul-24 17-Jul-24 33.94 19-Jul-24 19-Jul-24 2.00 1512 WC7-FRM-7290 Frame Structure: Wc-109 0%0.30 0.00 0.30 17-Jul-24 18-Jul-24 33.99 19-Jul-24 20-Jul-24 2.00 1513 WC7-FRM-7285 Frame Structure: Wc-108 0%0.30 0.00 0.30 18-Jul-24 18-Jul-24 34.04 20-Jul-24 20-Jul-24 2.00 1514 WC7-FRM-7280 Frame Structure: Wc-107 0%0.30 0.00 0.30 18-Jul-24 18-Jul-24 34.09 20-Jul-24 20-Jul-24 2.00 1515 WC7-FRM-7275 Frame Structure: Wc-106 0%0.30 0.00 0.30 18-Jul-24 19-Jul-24 34.14 20-Jul-24 22-Jul-24 2.00 1516 WC7-FRM-7270 Frame Structure: Wc-105 0%0.30 0.00 0.30 19-Jul-24 19-Jul-24 37.24 22-Jul-24 22-Jul-24 2.00 1517 WC7-FRM-7265 Frame Structure: Wc-104 0%0.30 0.00 0.30 19-Jul-24 19-Jul-24 37.29 22-Jul-24 22-Jul-24 2.00 1518 WC7-FRM-7260 Frame Structure: Wc-103 0%0.30 0.00 0.30 19-Jul-24 20-Jul-24 37.34 22-Jul-24 23-Jul-24 2.00 1519 WC7-FRM-7255 Frame Structure: Wc-102 0%0.30 0.00 0.30 20-Jul-24 20-Jul-24 37.39 23-Jul-24 23-Jul-24 2.00 1520 WC7-FRM-7250 Frame Structure: Wc-101 0%0.30 0.00 0.30 20-Jul-24 20-Jul-24 37.44 23-Jul-24 23-Jul-24 2.00 1521 WC7-FRM-7245 Frame Structure: Wc-100 0%0.30 0.00 0.30 20-Jul-24 20-Jul-24 37.49 23-Jul-24 23-Jul-24 2.00 1522 WC7-FRM-7240 Frame Structure: Wc-99 0%0.30 0.00 0.30 20-Jul-24 22-Jul-24 37.54 23-Jul-24 24-Jul-24 2.00 1523 WC7-FRM-7235 Frame Structure: Wc-98 0%0.30 0.00 0.30 22-Jul-24 22-Jul-24 37.59 24-Jul-24 24-Jul-24 2.00 1524 WC7-FRM-7230 Frame Structure: Wc-97 0%0.30 0.00 0.30 22-Jul-24 22-Jul-24 37.64 24-Jul-24 24-Jul-24 2.00 1525 WC7-FRM-7225 Frame Structure: Wc-96 0%0.30 0.00 0.30 22-Jul-24 23-Jul-24 37.69 24-Jul-24 25-Jul-24 2.00 1526 WC7-FRM-7220 Frame Structure: Wc-95 0%0.30 0.00 0.30 23-Jul-24 23-Jul-24 37.74 25-Jul-24 25-Jul-24 2.00 1527 WC7-FRM-7215 Frame Structure: Wc-94 jump to str 208 0%0.30 0.00 0.30 23-Jul-24 23-Jul-24 37.79 25-Jul-24 25-Jul-24 2.00 1528 WC9-FRM-9400 Frame Structure: Wc-268 0%0.20 0.00 0.20 23-Jul-24 23-Jul-24 39.36 25-Jul-24 25-Jul-24 2.00 1529 WC9-FRM-9405 Frame Structure: Wc-269 0%0.20 0.00 0.20 26-Jul-24 26-Jul-24 36.84 26-Jul-24 26-Jul-24 0.00 1530 WC9-FRM-9410 Frame Structure: Wc-270 0%0.20 0.00 0.20 27-Jul-24 27-Jul-24 36.83 27-Jul-24 27-Jul-24 0.00 1531 WC9-FRM-9415 Frame Structure: Wc-271 0%0.20 0.00 0.20 27-Jul-24 27-Jul-24 37.07 27-Jul-24 27-Jul-24 0.00 1532 WC9-FRM-9420 Frame Structure: Wc-272 0%0.20 0.00 0.20 27-Jul-24 27-Jul-24 37.06 27-Jul-24 27-Jul-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structure: Wc-145, 02-Jul-24 Frame Structure: Wc-144, 02-Jul-24 Frame Structure: Wc-143, 03-Jul-24 Frame Structure: Wc-142, 03-Jul-24 Frame Structure: Wc-141, 03-Jul-24 Frame Structure: Wc-140, 03-Jul-24 Frame Structure: Wc-139, 08-Jul-24 Frame Structure: Wc-138, 08-Jul-24 Frame Structure: Wc-137, 08-Jul-24 Frame Structure: Wc-136, 09-Jul-24 Frame Structure: Wc-135, 09-Jul-24 Frame Structure: Wc-134, 09-Jul-24 Frame Structure: Wc-133, 10-Jul-24 Frame Structure: Wc-132, 10-Jul-24 Frame Structure: Wc-131, 10-Jul-24 Frame Structure: Wc-130, 10-Jul-24 Frame Structure: Wc-129, 11-Jul-24 Frame Structure: Wc-128, 11-Jul-24 Frame Structure: Wc-127, 11-Jul-24 Frame Structure: Wc-126, 12-Jul-24 Frame Structure: Wc-125, 12-Jul-24 Frame Structure: Wc-124, 12-Jul-24 Frame Structure: Wc-123, 13-Jul-24 Frame Structure: Wc-122, 13-Jul-24 Frame Structure: Wc-121, 13-Jul-24 Frame Structure: Wc-120, 13-Jul-24 Frame Structure: Wc-119, 15-Jul-24 Frame Structure: Wc-118, 15-Jul-24 Frame Structure: Wc-117, 15-Jul-24 Frame Structure: Wc-116, 16-Jul-24 Frame Structure: Wc-115, 16-Jul-24 Frame Structure: Wc-114, 16-Jul-24 Frame Structure: Wc-113, 17-Jul-24 Frame Structure: Wc-112, 17-Jul-24 Frame Structure: Wc-111, 17-Jul-24 Frame Structure: Wc-110, 17-Jul-24 Frame Structure: Wc-109, 18-Jul-24 Frame Structure: Wc-108, 18-Jul-24 Frame Structure: Wc-107, 18-Jul-24 Frame Structure: Wc-106, 19-Jul-24 Frame Structure: Wc-105, 19-Jul-24 Frame Structure: Wc-104, 19-Jul-24 Frame Structure: Wc-103, 20-Jul-24 Frame Structure: Wc-102, 20-Jul-24 Frame Structure: Wc-101, 20-Jul-24 Frame Structure: Wc-100, 20-Jul-24 Frame Structure: Wc-99, 22-Jul-24 Frame Structure: Wc-98, 22-Jul-24 Frame Structure: Wc-97, 22-Jul-24 Frame Structure: Wc-96, 23-Jul-24 Frame Structure: Wc-95, 23-Jul-24 Frame Structure: Wc-94 jump to str 208, 23-Jul-24 Frame Structure: Wc-268, 23-Jul-24 Frame Structure: Wc-269, 26-Jul-24 Frame Structure: Wc-270, 27-Jul-24 Frame Structure: Wc-271, 27-Jul-24 Frame Structure: Wc-272, 27-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 29 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1533 WC9-FRM-9425 Frame Structure: Wc-273 0%0.20 0.00 0.20 27-Jul-24 29-Jul-24 37.05 27-Jul-24 29-Jul-24 0.00 1534 WC9-FRM-9430 Frame Structure: Wc-274 0%0.20 0.00 0.20 29-Jul-24 29-Jul-24 37.04 29-Jul-24 29-Jul-24 0.00 1535 WC9-FRM-9435 Frame Structure: Wc-275 0%0.20 0.00 0.20 29-Jul-24 29-Jul-24 37.03 29-Jul-24 29-Jul-24 0.00 1536 WC9-FRM-9440 Frame Structure: Wc-276 0%0.20 0.00 0.20 29-Jul-24 29-Jul-24 37.02 29-Jul-24 29-Jul-24 0.00 1537 WC9-FRM-9445 Frame Structure: Wc-277 0%0.20 0.00 0.20 29-Jul-24 30-Jul-24 37.00 29-Jul-24 30-Jul-24 0.00 1538 WC9-FRM-9450 Frame Structure: Wc-278 0%0.20 0.00 0.20 30-Jul-24 30-Jul-24 36.99 30-Jul-24 30-Jul-24 0.00 1539 WC9-FRM-9455 Frame Structure: Wc-279 0%0.20 0.00 0.20 30-Jul-24 30-Jul-24 36.98 30-Jul-24 30-Jul-24 0.00 1540 WC9-FRM-9460 Frame Structure: Wc-280 0%0.20 0.00 0.20 30-Jul-24 30-Jul-24 36.97 30-Jul-24 30-Jul-24 0.00 1541 WC9-FRM-9465 Frame Structure: Wc-281 0%0.20 0.00 0.20 30-Jul-24 31-Jul-24 36.96 30-Jul-24 31-Jul-24 0.00 1542 WC9-FRM-9470 Frame Structure: Wc-282 0%0.20 0.00 0.20 31-Jul-24 31-Jul-24 36.95 31-Jul-24 31-Jul-24 0.00 1543 WC9-FRM-9475 Frame Structure: Wc-283 0%0.20 0.00 0.20 31-Jul-24 31-Jul-24 36.94 31-Jul-24 31-Jul-24 0.00 1544 WC9-FRM-9480 Frame Structure: Wc-284 0%0.20 0.00 0.20 31-Jul-24 31-Jul-24 36.93 31-Jul-24 31-Jul-24 0.00 1545 WC9-FRM-9485 Frame Structure: Wc-285 0%0.20 0.00 0.20 31-Jul-24 01-Aug-24 36.92 31-Jul-24 01-Aug-24 0.00 1546 WC9-FRM-9490 Frame Structure: Wc-286 0%0.20 0.00 0.20 01-Aug-24 01-Aug-24 36.91 01-Aug-24 01-Aug-24 0.00 1547 WC9-FRM-9495 Frame Structure: Wc-287 0%0.20 0.00 0.20 01-Aug-24 01-Aug-24 36.90 01-Aug-24 01-Aug-24 0.00 1548 WC9-FRM-9500 Frame Structure: Wc-288 0%0.20 0.00 0.20 01-Aug-24 01-Aug-24 39.34 01-Aug-24 01-Aug-24 0.00 1549 WC9-FRM-9505 Frame Structure: Wc-289 0%0.20 0.00 0.20 01-Aug-24 02-Aug-24 39.28 01-Aug-24 02-Aug-24 0.00 1550 WC9-FRM-9510 Frame Structure: Wc-290 0%0.20 0.00 0.20 02-Aug-24 02-Aug-24 39.22 02-Aug-24 02-Aug-24 0.00 1551 WC9-FRM-9515 Frame Structure: Wc-291 0%0.20 0.00 0.20 02-Aug-24 02-Aug-24 39.16 02-Aug-24 02-Aug-24 0.00 1552 WC9-FRM-9520 Frame Structure: Wc-292 0%0.20 0.00 0.20 02-Aug-24 02-Aug-24 39.10 02-Aug-24 02-Aug-24 0.00 1553 WC9-FRM-9525 Frame Structure: Wc-293 0%0.20 0.00 0.20 03-Aug-24 03-Aug-24 39.03 03-Aug-24 03-Aug-24 0.00 1554 WC9-FRM-9530 Frame Structure: Wc-294 0%0.20 0.00 0.20 03-Aug-24 03-Aug-24 38.97 03-Aug-24 03-Aug-24 0.00 1555 WC9-FRM-9535 Frame Structure: Wc-295 0%0.20 0.00 0.20 03-Aug-24 03-Aug-24 38.91 03-Aug-24 03-Aug-24 0.00 1556 WC9-FRM-9540 Frame Structure: Wc-296 0%0.20 0.00 0.20 03-Aug-24 03-Aug-24 38.85 03-Aug-24 03-Aug-24 0.00 1557 WC9-FRM-9545 Frame Structure: Wc-297 0%0.20 0.00 0.20 05-Aug-24 05-Aug-24 38.79 05-Aug-24 05-Aug-24 0.00 1558 WC9-FRM-9550 Frame Structure: Wc-298 0%0.20 0.00 0.20 05-Aug-24 05-Aug-24 38.73 05-Aug-24 05-Aug-24 0.00 1559 WC9-FRM-9555 Frame Structure: Wc-299 0%0.20 0.00 0.20 05-Aug-24 05-Aug-24 38.67 05-Aug-24 05-Aug-24 0.00 1560 WC9-FRM-9560 Frame Structure: Wc-300 0%0.20 0.00 0.20 05-Aug-24 06-Aug-24 38.61 05-Aug-24 06-Aug-24 0.00 1561 WC9-FRM-9565 Frame Structure: Wc-301 0%0.20 0.00 0.20 06-Aug-24 06-Aug-24 38.55 06-Aug-24 06-Aug-24 0.00 1562 WC9-FRM-9570 Frame Structure: Wc-302 0%0.20 0.00 0.20 06-Aug-24 06-Aug-24 38.49 06-Aug-24 06-Aug-24 0.00 1563 WC9-FRM-9575 Frame Structure: Wc-303 0%0.20 0.00 0.20 06-Aug-24 06-Aug-24 38.43 06-Aug-24 06-Aug-24 0.00 1564 WC9-FRM-9580 Frame Structure: Wc-304 0%0.20 0.00 0.20 06-Aug-24 07-Aug-24 38.37 06-Aug-24 07-Aug-24 0.00 1565 WC9-FRM-9585 Frame Structure: Wc-305 0%0.20 0.00 0.20 07-Aug-24 07-Aug-24 38.31 07-Aug-24 07-Aug-24 0.00 1566 WC9-FRM-9590 Frame Structure: Wc-306 0%0.20 0.00 0.20 07-Aug-24 07-Aug-24 38.25 07-Aug-24 07-Aug-24 0.00 1567 WC9-FRM-9595 Frame Structure: Wc-307 0%0.20 0.00 0.20 07-Aug-24 07-Aug-24 38.19 07-Aug-24 07-Aug-24 0.00 1568 WC9-FRM-9600 Frame Structure: Wc-308 0%0.20 0.00 0.20 07-Aug-24 08-Aug-24 38.13 07-Aug-24 08-Aug-24 0.00 1569 WC9-FRM-9605 Frame Structure: Wc-309 0%0.20 0.00 0.20 08-Aug-24 08-Aug-24 38.07 08-Aug-24 08-Aug-24 0.00 1570 WC9-FRM-9610 Frame Structure: Wc-310 0%0.20 0.00 0.20 08-Aug-24 08-Aug-24 38.00 08-Aug-24 08-Aug-24 0.00 1571 WC9-FRM-9615 Frame Structure: Wc-311 0%0.20 0.00 0.20 08-Aug-24 08-Aug-24 37.94 08-Aug-24 08-Aug-24 0.00 1572 WC9-FRM-9620 Frame Structure: Wc-312 0%0.20 0.00 0.20 08-Aug-24 09-Aug-24 37.88 08-Aug-24 09-Aug-24 0.00 1573 WC9-FRM-9625 Frame Structure: Wc-313 0%0.20 0.00 0.20 09-Aug-24 09-Aug-24 37.82 09-Aug-24 09-Aug-24 0.00 1574 WC9-FRM-9630 Frame Structure: Wc-314 0%0.20 0.00 0.20 09-Aug-24 09-Aug-24 37.76 09-Aug-24 09-Aug-24 0.00 1575 WC9-FRM-9635 Frame Structure: Wc-315 0%0.20 0.00 0.20 09-Aug-24 09-Aug-24 37.70 09-Aug-24 09-Aug-24 0.00 1576 WC9-FRM-9640 Frame Structure: Wc-316 0%0.20 0.00 0.20 10-Aug-24 10-Aug-24 37.64 10-Aug-24 10-Aug-24 0.00 1577 WC9-FRM-9645 Frame Structure: Wc-317 0%0.20 0.00 0.20 10-Aug-24 10-Aug-24 37.58 10-Aug-24 10-Aug-24 0.00 1578 WC9-FRM-9650 Frame Structure: Wc-318 0%0.20 0.00 0.20 10-Aug-24 10-Aug-24 37.52 10-Aug-24 10-Aug-24 0.00 1579 Crew 2 Frame Structure: Wc-319 0%0.20 0.00 0.20 10-Aug-24 10-Aug-24 37.46 10-Aug-24 10-Aug-24 0.00 1580 WC9-FRM-9660 Frame Structure: Wc-320 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 37.40 12-Aug-24 12-Aug-24 0.00 1581 WC9-FRM-9665 Frame Structure: Wc-321 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 42.79 12-Aug-24 12-Aug-24 0.00 1582 WC9-FRM-9670 Frame Structure: Wc-322 0%0.20 0.00 0.20 12-Aug-24 12-Aug-24 42.78 12-Aug-24 12-Aug-24 0.00 1583 WC9-FRM-9675 Frame Structure: Wc-323 0%0.20 0.00 0.20 12-Aug-24 13-Aug-24 42.77 12-Aug-24 13-Aug-24 0.00 1584 WC9-FRM-9680 Frame Structure: Wc-324 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 42.76 13-Aug-24 13-Aug-24 0.00 1585 WC9-FRM-9685 Frame Structure: Wc-325 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 42.75 13-Aug-24 13-Aug-24 0.00 1586 WC9-FRM-9690 Frame Structure: Wc-326 0%0.20 0.00 0.20 13-Aug-24 13-Aug-24 42.73 13-Aug-24 13-Aug-24 0.00 1587 WC9-FRM-9695 Frame Structure: Wc-327 0%0.20 0.00 0.20 13-Aug-24 14-Aug-24 46.22 13-Aug-24 14-Aug-24 0.00 1588 WC9-FRM-9700 Frame Structure: Wc-328 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 46.21 14-Aug-24 14-Aug-24 0.00 1589 WC9-FRM-9705 Frame Structure: Wc-329 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 46.20 14-Aug-24 14-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structure: Wc-273, 29-Jul-24 Frame Structure: Wc-274, 29-Jul-24 Frame Structure: Wc-275, 29-Jul-24 Frame Structure: Wc-276, 29-Jul-24 Frame Structure: Wc-277, 30-Jul-24 Frame Structure: Wc-278, 30-Jul-24 Frame Structure: Wc-279, 30-Jul-24 Frame Structure: Wc-280, 30-Jul-24 Frame Structure: Wc-281, 31-Jul-24 Frame Structure: Wc-282, 31-Jul-24 Frame Structure: Wc-283, 31-Jul-24 Frame Structure: Wc-284, 31-Jul-24 Frame Structure: Wc-285, 01-Aug-24 Frame Structure: Wc-286, 01-Aug-24 Frame Structure: Wc-287, 01-Aug-24 Frame Structure: Wc-288, 01-Aug-24 Frame Structure: Wc-289, 02-Aug-24 Frame Structure: Wc-290, 02-Aug-24 Frame Structure: Wc-291, 02-Aug-24 Frame Structure: Wc-292, 02-Aug-24 Frame Structure: Wc-293, 03-Aug-24 Frame Structure: Wc-294, 03-Aug-24 Frame Structure: Wc-295, 03-Aug-24 Frame Structure: Wc-296, 03-Aug-24 Frame Structure: Wc-297, 05-Aug-24 Frame Structure: Wc-298, 05-Aug-24 Frame Structure: Wc-299, 05-Aug-24 Frame Structure: Wc-300, 06-Aug-24 Frame Structure: Wc-301, 06-Aug-24 Frame Structure: Wc-302, 06-Aug-24 Frame Structure: Wc-303, 06-Aug-24 Frame Structure: Wc-304, 07-Aug-24 Frame Structure: Wc-305, 07-Aug-24 Frame Structure: Wc-306, 07-Aug-24 Frame Structure: Wc-307, 07-Aug-24 Frame Structure: Wc-308, 08-Aug-24 Frame Structure: Wc-309, 08-Aug-24 Frame Structure: Wc-310, 08-Aug-24 Frame Structure: Wc-311, 08-Aug-24 Frame Structure: Wc-312, 09-Aug-24 Frame Structure: Wc-313, 09-Aug-24 Frame Structure: Wc-314, 09-Aug-24 Frame Structure: Wc-315, 09-Aug-24 Frame Structure: Wc-316, 10-Aug-24 Frame Structure: Wc-317, 10-Aug-24 Frame Structure: Wc-318, 10-Aug-24 Frame Structure: Wc-319, 10-Aug-24 Frame Structure: Wc-320, 12-Aug-24 Frame Structure: Wc-321, 12-Aug-24 Frame Structure: Wc-322, 12-Aug-24 Frame Structure: Wc-323, 13-Aug-24 Frame Structure: Wc-324, 13-Aug-24 Frame Structure: Wc-325, 13-Aug-24 Frame Structure: Wc-326, 13-Aug-24 Frame Structure: Wc-327, 14-Aug-24 Frame Structure: Wc-328, 14-Aug-24 Frame Structure: Wc-329, 14-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 30 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1590 WC9-FRM-9710 Frame Structure: Wc-330 0%0.20 0.00 0.20 14-Aug-24 14-Aug-24 46.44 14-Aug-24 14-Aug-24 0.00 1591 WC9-FRM-9715 Frame Structure: Wc-331 0%0.20 0.00 0.20 14-Aug-24 15-Aug-24 46.43 14-Aug-24 15-Aug-24 0.00 1592 WC9-FRM-9720 Frame Structure: Wc-332 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 46.42 15-Aug-24 15-Aug-24 0.00 1593 WC9-FRM-9725 Frame Structure: Wc-333 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 46.41 15-Aug-24 15-Aug-24 0.00 1594 WC9-FRM-9730 Frame Structure: Wc-334 0%0.20 0.00 0.20 15-Aug-24 15-Aug-24 46.40 15-Aug-24 15-Aug-24 0.00 1595 WC9-FRM-9735 Frame Structure: Wc-335 0%0.20 0.00 0.20 15-Aug-24 16-Aug-24 46.39 15-Aug-24 16-Aug-24 0.00 1596 WC9-FRM-9740 Frame Structure: Wc-336 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 46.38 16-Aug-24 16-Aug-24 0.00 1597 WC9-FRM-9745 Frame Structure: Wc-337 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 46.37 16-Aug-24 16-Aug-24 0.00 1598 WC9-FRM-9750 Frame Structure: Wc-2/177A 0%0.20 0.00 0.20 16-Aug-24 16-Aug-24 46.36 16-Aug-24 16-Aug-24 0.00 1599 Drilling + StructureDrilling + Structure SettingDrilling + Structure Setting 172.41 113.96 53.45 13-Feb-24 A 05-Sep-24 30.35 13-Feb-24 05-Sep-24 0.00 1600 2024 Spring/Sum2024 Spring/Summer2024 Spring/Summer 172.41 113.96 53.45 13-Feb-24 A 05-Sep-24 30.35 13-Feb-24 05-Sep-24 0.00 1601 Crew 1Crew 1Crew 1 119.44 106.96 0.00 13-Feb-24 A 15-Jun-24 A 13-Feb-24 01-Jun-24 -12.50 1602 WC6-SET-6735 Set Structure: Wc-8 100%0.50 0.50 0.00 13-Feb-24 A 13-Feb-24 A 13-Feb-24 13-Feb-24 0.00 1603 WC6-SET-6740 Set Structure: Wc-9 100%0.50 0.50 0.00 14-Feb-24 A 15-Feb-24 A 14-Feb-24 15-Feb-24 0.00 1604 WC6-SET-6780 Set Structure: Wc-17 100%0.50 0.50 0.00 20-Feb-24 A 21-Feb-24 A 20-Feb-24 21-Feb-24 0.00 1605 WC6-SET-6745 Set Structure: Wc-10 100%0.50 0.50 0.00 22-Feb-24 A 22-Feb-24 A 22-Feb-24 22-Feb-24 0.00 1606 WC6-SET-6755 Set Structure: Wc-12 100%0.50 0.50 0.00 23-Feb-24 A 23-Feb-24 A 23-Feb-24 23-Feb-24 0.00 1607 WC6-SET-6750 Set Structure: Wc-11 100%0.50 0.50 0.00 24-Feb-24 A 24-Feb-24 A 24-Feb-24 24-Feb-24 0.00 1608 WC6-SET-6760 Set Structure: Wc-13 100%0.50 0.50 0.00 24-Feb-24 A 24-Feb-24 A 24-Feb-24 24-Feb-24 0.00 1609 WC1-SET-1600b Set Structure: Wc-159 100%1.00 1.00 0.00 28-Feb-24 A 29-Feb-24 A 28-Feb-24 29-Feb-24 0.00 WC6-SET-6730 Set Structure: Wc-7 100%0.50 0.50 0.00 29-Feb-24 A 29-Feb-24 A 29-Feb-24 29-Feb-24 0.00 1611 WC6-SET-6785 Set Structure: Wc-18 100%0.50 0.50 0.00 29-Feb-24 A 29-Feb-24 A 29-Feb-24 29-Feb-24 0.00 1612 WC6-SET-6775 Set Structure: Wc-16 100%0.50 0.50 0.00 02-Mar-24 A 04-Mar-24 A 02-Mar-24 04-Mar-24 0.00 1613 WC6-SET-6725 Set Structure: Wc-6 100%0.50 0.50 0.00 08-Mar-24 A 08-Mar-24 A 08-Mar-24 08-Mar-24 0.00 1614 WC6-SET-6720 Set Structure: Wc-5 100%0.50 0.50 0.00 08-Mar-24 A 09-Mar-24 A 08-Mar-24 09-Mar-24 0.00 1615 WC6-SET-6700 Set Structure: Wc-1 100%0.50 0.50 0.00 11-Mar-24 A 12-Mar-24 A 11-Mar-24 12-Mar-24 0.00 1616 WC6-SET-6705 Set Structure: Wc-2 100%0.50 0.50 0.00 13-Mar-24 A 13-Mar-24 A 13-Mar-24 13-Mar-24 0.00 1617 WC6-SET-6765 Set Structure: Wc-14 100%0.50 0.50 0.00 15-Mar-24 A 16-Mar-24 A 15-Mar-24 16-Mar-24 0.00 1618 WC7-SET-7770 Set Structure: Wc-85 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 21-May-24 21-May-24 -3.05 1619 WC7-SET-7785 Set Structure: Wc-88 DP 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 20-May-24 20-May-24 -4.05 1620 WC7-SET-7805 Set Structure: Wc-92 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 18-May-24 18-May-24 -6.05 1621 WC7-SET-7780 Set Structure: Wc-87 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 20-May-24 20-May-24 -4.05 1622 WC7-SET-7655 Set Structure: Wc-62 DP 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 27-May-24 27-May-24 2.13 1623 WC7-SET-7775 Set Structure: Wc-86 100%0.25 0.25 0.00 24-May-24 A 24-May-24 A 20-May-24 20-May-24 -3.96 1624 WC7-SET-7730 Set Structure: Wc-77 100%0.25 0.25 0.00 25-May-24 A 25-May-24 A 23-May-24 23-May-24 -2.05 1625 WC7-SET-7680 Set Structure: Wc-67 DP 100%0.25 0.25 0.00 25-May-24 A 25-May-24 A 25-May-24 25-May-24 -0.05 1626 WC7-SET-7740 Set Structure: Wc-79 100%0.25 0.25 0.00 25-May-24 A 25-May-24 A 22-May-24 22-May-24 -3.05 1627 WC7-SET-7735 Set Structure: Wc-78 100%0.25 0.25 0.00 25-May-24 A 25-May-24 A 22-May-24 22-May-24 -2.87 1628 WC6-SET-6925 Set Structure: Wc-46 DP 100%0.25 0.25 0.00 25-May-24 A 25-May-24 A 30-May-24 30-May-24 4.13 1629 WC7-SET-7710 Set Structure: Wc-73 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 24-May-24 24-May-24 -2.05 1630 WC7-SET-7705 Set Structure: Wc-72 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 24-May-24 24-May-24 -2.05 1631 WC7-SET-7725 Set Structure: Wc-76 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 23-May-24 23-May-24 -3.05 1632 WC7-SET-7701 Set Structure: Wc-71 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 24-May-24 24-May-24 -2.05 1633 WC7-SET-7720 Set Structure: Wc-75 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 23-May-24 23-May-24 -3.05 1634 WC7-SET-7695 Set Structure: Wc-70 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 24-May-24 24-May-24 -1.87 1635 WC7-SET-7715 Set Structure: Wc-74 100%0.25 0.25 0.00 27-May-24 A 27-May-24 A 23-May-24 23-May-24 -2.87 1636 WC7-SET-7670 Set Structure: Wc-65 100%0.25 0.25 0.00 28-May-24 A 28-May-24 A 27-May-24 27-May-24 -1.00 1637 WC7-SET-7745 Set Structure: Wc-80 100%0.25 0.25 0.00 28-May-24 A 28-May-24 A 22-May-24 22-May-24 -4.75 1638 Crew 2 Set Structure: Wc-82 100%0.25 0.25 0.00 28-May-24 A 28-May-24 A 21-May-24 21-May-24 -5.75 1639 WC7-SET-7750 Set Structure: Wc-81 100%0.25 0.25 0.00 28-May-24 A 28-May-24 A 22-May-24 22-May-24 -5.75 1640 WC7-SET-7765 Set Structure: Wc-84 100%0.25 0.25 0.00 29-May-24 A 29-May-24 A 21-May-24 21-May-24 -6.75 1641 WC7-SET-7760 Set Structure: Wc-83 100%0.25 0.25 0.00 29-May-24 A 29-May-24 A 21-May-24 21-May-24 -6.75 1642 WC7-SET-7600 Set Structure: Wc-51 100%0.25 0.25 0.00 30-May-24 A 30-May-24 A 30-May-24 30-May-24 0.50 1643 WC7-SET-7620 Set Structure: Wc-55 100%0.25 0.25 0.00 30-May-24 A 30-May-24 A 29-May-24 29-May-24 -0.50 1644 WC7-SET-7605 Set Structure: Wc-52 100%0.25 0.25 0.00 30-May-24 A 30-May-24 A 30-May-24 30-May-24 -0.50 1645 WC7-SET-7640 Set Structure: Wc-59 100%0.25 0.25 0.00 31-May-24 A 31-May-24 A 28-May-24 28-May-24 -2.50 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Frame Structure: Wc-330, 14-Aug-24 Frame Structure: Wc-331, 15-Aug-24 Frame Structure: Wc-332, 15-Aug-24 Frame Structure: Wc-333, 15-Aug-24 Frame Structure: Wc-334, 15-Aug-24 Frame Structure: Wc-335, 16-Aug-24 Frame Structure: Wc-336, 16-Aug-24 Frame Structure: Wc-337, 16-Aug-24 Frame Structure: Wc-2/177A, 16-Aug-24 05-Sep-24, Drilling + Structure Setting 05-Sep-24, 2024 Spring/Summer 15-Jun-24 A, Crew 1 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 31 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1646 WC7-SET-7635 Set Structure: Wc-58 100%0.25 0.25 0.00 31-May-24 A 31-May-24 A 28-May-24 28-May-24 -2.50 1647 WC7-SET-7650 Set Structure: Wc-61 100%0.25 0.25 0.00 31-May-24 A 31-May-24 A 28-May-24 28-May-24 -3.50 1648 WC7-SET-7625 Set Structure: Wc-56 100%0.25 0.25 0.00 31-May-24 A 31-May-24 A 29-May-24 29-May-24 -2.50 1649 WC7-SET-7615 Set Structure: Wc-54 100%0.25 0.25 0.00 01-Jun-24 A 01-Jun-24 A 29-May-24 29-May-24 -2.50 1650 WC7-SET-7645 Set Structure: Wc-60 100%0.25 0.25 0.00 01-Jun-24 A 01-Jun-24 A 28-May-24 28-May-24 -4.50 1651 WC7-SET-7690 Set Structure: Wc-69 100%0.25 0.25 0.00 03-Jun-24 A 03-Jun-24 A 25-May-24 25-May-24 -7.00 1652 WC7-SET-7630 Set Structure: Wc-57 100%0.25 0.25 0.00 03-Jun-24 A 03-Jun-24 A 29-May-24 29-May-24 -4.50 1653 WC7-SET-7675 Set Structure: Wc-66 0.25 0.25 0.00 04-Jun-24 A 04-Jun-24 A 25-May-24 25-May-24 -7.75 1654 WC7-SET-7660 Set Structure: Wc-63 100%0.25 0.25 0.00 05-Jun-24 A 05-Jun-24 A 27-May-24 27-May-24 -7.75 1655 WC7-SET-7665 Set Structure: Wc-64 DP 100%0.25 0.25 0.00 06-Jun-24 A 06-Jun-24 A 27-May-24 27-May-24 -8.75 1656 WC7-SET-7685 Set Structure: Wc-68 100%0.25 0.25 0.00 06-Jun-24 A 06-Jun-24 A 25-May-24 25-May-24 -10.00 1657 WC6-SET-6920 Set Structure: Wc-45 100%0.25 0.25 0.00 07-Jun-24 A 07-Jun-24 A 31-May-24 31-May-24 -6.25 1658 WC7-SET-7610 Set Structure: Wc-53 100%0.25 0.25 0.00 07-Jun-24 A 07-Jun-24 A 30-May-24 30-May-24 -7.50 1659 WC6-SET-6915 Set Structure: Wc-44 100%0.25 0.25 0.00 07-Jun-24 A 07-Jun-24 A 31-May-24 31-May-24 -6.25 1660 WC6-SET-6905 Set Structure: Wc-42 100%0.25 0.25 0.00 08-Jun-24 A 08-Jun-24 A 31-May-24 31-May-24 -6.25 1661 WC6-SET-6900 Set Structure: Wc-41 100%0.25 0.25 0.00 08-Jun-24 A 08-Jun-24 A 01-Jun-24 01-Jun-24 -6.25 1662 WC6-SET-6910 Set Structure: Wc-43 100%0.25 0.25 0.00 08-Jun-24 A 08-Jun-24 A 31-May-24 31-May-24 -7.25 1663 WC6-SET-6895 Set Structure: Wc-40 - end 100%0.25 0.25 0.00 10-Jun-24 A 10-Jun-24 A 01-Jun-24 01-Jun-24 -7.25 1664 WC7-SET-7810 Set Structure: Wc-93 100%0.25 0.25 0.00 15-Jun-24 A 15-Jun-24 A 18-May-24 18-May-24 -25.00 1665 WC7-SET-7800 Set Structure: Wc-91 100%0.25 0.25 0.00 15-Jun-24 A 15-Jun-24 A 18-May-24 18-May-24 -24.75 1666 WC7-SET-7795 Set Structure: Wc-90 100%0.25 0.25 0.00 15-Jun-24 A 15-Jun-24 A 18-May-24 18-May-24 -24.75 1667 WC7-SET-7790 Set Structure: Wc-89 100%0.25 0.25 0.00 15-Jun-24 A 15-Jun-24 A 20-May-24 20-May-24 -23.75 1668 Crew 2Crew 2Crew 2 146.77 88.32 53.45 13-Mar-24 A 05-Sep-24 0.33 25-May-24 05-Sep-24 0.00 1669 WC6-SET-6830 Set Structure: Wc-27 100%0.72 0.72 0.00 13-Mar-24 A 14-Mar-24 A 03-Jul-24 08-Jul-24 95.97 1670 WC6-SET-6810 Set Structure: Wc-23 100%0.72 0.72 0.00 15-Mar-24 A 16-Mar-24 A 29-Jun-24 01-Jul-24 90.99 1671 WC6-SET-6771 Set Structure: Wc-15 100%0.50 0.50 0.00 20-Apr-24 A 20-Apr-24 A 27-May-24 27-May-24 31.00 1672 WC6-SET-6711 Set Structure: Wc-3 100%0.50 0.50 0.00 22-Apr-24 A 22-Apr-24 A 25-May-24 25-May-24 29.00 1673 WC6-SET-6790 Set Structure: Wc-19 BG variance granted str 19-32 100%0.72 0.72 0.00 29-Apr-24 A 30-Apr-24 A 26-Jun-24 27-Jun-24 50.00 1674 WC6-SET-6715 Set Structure: Wc-4 100%0.50 5.50 0.00 25-Apr-24 A 01-May-24 A 25-May-24 27-May-24 21.99 1675 WC6-SET-6800 Set Structure: Wc-21 100%0.72 0.72 0.00 09-May-24 A 09-May-24 A 28-Jun-24 29-Jun-24 43.33 1676 WC6-SET-6795 Set Structure: Wc-20 100%0.72 0.72 0.00 13-May-24 A 13-May-24 A 27-Jun-24 28-Jun-24 39.61 1677 WC6-SET-6815 Set Structure: Wc-24 100%0.72 0.72 0.00 15-May-24 A 16-May-24 A 01-Jul-24 02-Jul-24 39.99 1678 WC6-SET-6825 Set Structure: Wc-26 100%0.72 0.72 0.00 06-Jun-24 A 06-Jun-24 A 02-Jul-24 03-Jul-24 22.74 1679 WC6-SET-6855 Set Structure: Wc-32 100%0.50 0.50 0.00 06-Jun-24 A 07-Jun-24 A 11-Jul-24 11-Jul-24 26.46 1680 WC6-SET-6805 Set Structure: Wc-22 100%0.72 0.72 0.00 06-Jun-24 A 07-Jun-24 A 29-Jun-24 29-Jun-24 19.30 1681 WC6-SET-6835 Set Structure: Wc-28 100%0.72 0.72 0.00 07-Jun-24 A 08-Jun-24 A 08-Jul-24 09-Jul-24 22.46 1682 WC6-SET-6930 Set Structure: Wc-47 Golden Eagle Nest - Variance Granted 100%0.25 0.25 0.00 10-Jun-24 A 10-Jun-24 A 02-Sep-24 02-Sep-24 68.66 1683 WC6-SET-6820 Set Structure: Wc-25 Sage Grouse - Variance Grantedstr wc-25-39 100%0.72 0.72 0.00 10-Jun-24 A 10-Jun-24 A 02-Jul-24 02-Jul-24 19.21 1684 WC6-SET-6940 Set Structure: Wc-48 Golden Eagle Nest - Variance Granted 100%0.25 0.25 0.00 10-Jun-24 A 10-Jun-24 A 02-Sep-24 02-Sep-24 68.66 1685 WC6-SET-6885 Set Structure: Wc-38 100%0.72 0.72 0.00 10-Jun-24 A 11-Jun-24 A 16-Jul-24 17-Jul-24 27.68 1686 WC6-SET-6840 Set Structure: Wc-29 100%0.72 0.72 0.00 11-Jun-24 A 12-Jun-24 A 09-Jul-24 09-Jul-24 20.18 1687 WC6-SET-6865 Set Structure: Wc-34 100%0.72 0.72 0.00 12-Jun-24 A 13-Jun-24 A 12-Jul-24 13-Jul-24 22.68 1688 WC6-SET-6875 Set Structure:: Wc-36 100%0.72 0.72 0.00 13-Jun-24 A 13-Jun-24 A 13-Jul-24 15-Jul-24 23.68 1689 WC6-SET-6850 Set Structure: Wc-31 100%0.72 0.72 0.00 13-Jun-24 A 14-Jun-24 A 10-Jul-24 11-Jul-24 20.18 1690 WC6-SET-6870 Set Structure: Wc-35 100%0.72 0.72 0.00 13-Jun-24 A 14-Jun-24 A 13-Jul-24 13-Jul-24 22.74 1691 WC6-SET-6845 Set Structure: Wc-30 100%0.72 0.72 0.00 14-Jun-24 A 15-Jun-24 A 09-Jul-24 10-Jul-24 18.18 1692 WC6-SET-6890 Set Structure: Wc-39 100%0.72 0.72 0.00 20-Jun-24 A 20-Jun-24 A 17-Jul-24 17-Jul-24 20.07 1693 WC6-SET-6880 Set Structure: Wc-37 100%0.72 0.72 0.00 20-Jun-24 A 20-Jun-24 A 15-Jul-24 16-Jul-24 18.46 1694 WC6-SET-6860 Set Structure: Wc-33 - Bird Nest 100%0.50 0.50 0.00 24-Jun-24 A 24-Jun-24 A 11-Jul-24 12-Jul-24 12.47 1695 WC1-SET-1700 Set Structure: Wc-149 DP 0%0.25 0.00 0.25 01-Jul-24 01-Jul-24 23.28 17-Jul-24 18-Jul-24 11.79 1696 WC1-SET-1710 Set Structure: Wc-153 DP 0%0.25 0.00 0.25 01-Jul-24 01-Jul-24 23.28 18-Jul-24 18-Jul-24 11.79 1697 WC1-SET-1600f Set Structure: Wc-165 0%0.25 0.00 0.25 01-Jul-24 01-Jul-24 23.28 18-Jul-24 18-Jul-24 11.79 1698 WC1-SET-1610 Set Structure: Wc-166 0%0.25 0.00 0.25 01-Jul-24 01-Jul-24 23.28 18-Jul-24 18-Jul-24 11.79 1699 WC1-SET-1610e Set Structure: Wc-170 0%0.25 0.00 0.25 13-Jul-24 13-Jul-24 16.28 18-Jul-24 19-Jul-24 4.79 1700 WC1-SET-1610f Set Structure: Wc-172 0%0.25 0.00 0.25 15-Jul-24 15-Jul-24 15.53 19-Jul-24 19-Jul-24 4.04 1701 WC1-SET-1730 Set Structure: Wc-171 DP needs fdn 0%0.75 0.00 0.75 15-Jul-24 15-Jul-24 15.53 19-Jul-24 20-Jul-24 4.04 1702 WC1-SET-1740 Set Structure: Wc-173 DP needs fdn 0%0.75 0.00 0.75 19-Jul-24 19-Jul-24 12.53 20-Jul-24 20-Jul-24 1.04 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 05-Sep-24, Crew 2 4 4 4 4 24 24 24 24 24 24 24 -24 -24 -24 Set Structure: Wc-149 DP, 01-Jul-24 Set Structure: Wc-153 DP, 01-Jul-24 Set Structure: Wc-165, 01-Jul-24 Set Structure: Wc-166, 01-Jul-24 Set Structure: Wc-170, 13-Jul-24 Set Structure: Wc-172, 15-Jul-24 Set Structure: Wc-171 DP needs fdn, 15-Jul-24 Set Structure: Wc-173 DP needs fdn, 19-Jul-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 32 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1703 WC8-SET-8500 Set Structure: Wc-208 0%0.25 0.00 0.25 02-Aug-24 03-Aug-24 0.33 02-Aug-24 03-Aug-24 0.00 1704 WC1-SET-1610g Set Structure: Wc - 174 0%0.75 0.00 0.75 03-Aug-24 03-Aug-24 0.33 03-Aug-24 03-Aug-24 0.00 1705 WC1-SET-1610j Set Structure: Wc-177 0%0.75 0.00 0.75 03-Aug-24 05-Aug-24 0.33 03-Aug-24 05-Aug-24 0.00 1706 WC1-SET-1610k Set Structure: Wc-178 0%0.75 0.00 0.75 05-Aug-24 06-Aug-24 0.33 05-Aug-24 06-Aug-24 0.00 1707 WC1-SET-1610l Set Structure: Wc-179 0%0.75 0.00 0.75 06-Aug-24 07-Aug-24 0.33 06-Aug-24 07-Aug-24 0.00 1708 WC1-SET-1750 Set Structure: Wc-180 0%0.75 0.00 0.75 07-Aug-24 07-Aug-24 0.33 07-Aug-24 07-Aug-24 0.00 1709 WC1-SET-1620 Set Structure: Wc-181 0%0.75 0.00 0.75 07-Aug-24 08-Aug-24 0.33 07-Aug-24 08-Aug-24 0.00 1710 WC1-SET-1620a Set Structure: Wc-183 0%0.75 0.00 0.75 08-Aug-24 09-Aug-24 0.33 08-Aug-24 09-Aug-24 0.00 1711 WC1-SET-1760 Set Structure: Wc-182 0%0.75 0.00 0.75 09-Aug-24 10-Aug-24 0.33 09-Aug-24 10-Aug-24 0.00 1712 WC1-SET-1620b Set Structure: Wc-184 0%0.75 0.00 0.75 10-Aug-24 10-Aug-24 0.33 10-Aug-24 10-Aug-24 0.00 1713 WC1-SET-1620c Set Structure: Wc-185 0%0.75 0.00 0.75 10-Aug-24 12-Aug-24 0.33 10-Aug-24 12-Aug-24 0.00 1714 WC1-SET-1770 Set Structure: Wc-186 0%0.75 0.00 0.75 12-Aug-24 13-Aug-24 0.33 12-Aug-24 13-Aug-24 0.00 1715 WC1-SET-1620d 0%0.75 0.00 0.75 13-Aug-24 14-Aug-24 0.33 13-Aug-24 14-Aug-24 0.00 1716 WC1-SET-1620e Set Structure: Wc-188 0%0.75 0.00 0.75 14-Aug-24 14-Aug-24 0.33 14-Aug-24 14-Aug-24 0.00 1717 WC1-SET-1620f Set Structure: Wc-189 0%0.75 0.00 0.75 14-Aug-24 15-Aug-24 0.33 14-Aug-24 15-Aug-24 0.00 1718 WC1-SET-1780 Set Structure: Wc-189b 0%0.75 0.00 0.75 15-Aug-24 16-Aug-24 0.33 15-Aug-24 16-Aug-24 0.00 1719 WC1-SET-1630b Set Structure: Wc-189C 0%0.75 0.00 0.75 16-Aug-24 17-Aug-24 0.33 16-Aug-24 17-Aug-24 0.00 1720 WC1-SET-1620g Set Structure: Wc-189A 0%0.75 0.00 0.75 17-Aug-24 17-Aug-24 0.33 17-Aug-24 17-Aug-24 0.00 1721 WC1-SET-1800 Set Structure: Wc-204 fabrication issues 0%0.75 0.00 0.75 17-Aug-24 19-Aug-24 0.33 17-Aug-24 19-Aug-24 0.00 1722 WC8-SET-8505 Set Structure: Wc-209 0%0.25 0.00 0.25 19-Aug-24 19-Aug-24 0.33 19-Aug-24 19-Aug-24 0.00 1723 WC8-SET-8510 Set Structure: Wc-210 0%0.25 0.00 0.25 19-Aug-24 20-Aug-24 0.33 19-Aug-24 20-Aug-24 0.00 1724 WC8-SET-8515 Set Structure: Wc-211 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 0.33 20-Aug-24 20-Aug-24 0.00 1725 WC8-SET-8520 Set Structure: Wc-212 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 0.33 20-Aug-24 20-Aug-24 0.00 1726 WC8-SET-8525 Set Structure: Wc-213 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 0.33 20-Aug-24 20-Aug-24 0.00 1727 WC8-SET-8530 Set Structure: Wc-214 0%0.25 0.00 0.25 20-Aug-24 21-Aug-24 0.33 20-Aug-24 21-Aug-24 0.00 1728 WC8-SET-8535 Set Structure: Wc-215 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 0.33 21-Aug-24 21-Aug-24 0.00 1729 WC8-SET-8540 Set Structure: Wc-216 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 0.33 21-Aug-24 21-Aug-24 0.00 1730 WC8-SET-8545 Set Structure: Wc-217 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 0.33 21-Aug-24 21-Aug-24 0.00 1731 WC8-SET-8550 Set Structure: Wc-218 0%0.25 0.00 0.25 21-Aug-24 22-Aug-24 0.33 21-Aug-24 22-Aug-24 0.00 1732 WC8-SET-8555 Set Structure: Wc-219 0%0.25 0.00 0.25 22-Aug-24 22-Aug-24 0.33 22-Aug-24 22-Aug-24 0.00 1733 WC8-SET-8560 Set Structure: Wc-220 0%0.25 0.00 0.25 22-Aug-24 22-Aug-24 0.33 22-Aug-24 22-Aug-24 0.00 1734 WC8-SET-8565 Set Structure: Wc-221 0%0.25 0.00 0.25 22-Aug-24 22-Aug-24 0.33 22-Aug-24 22-Aug-24 0.00 1735 WC8-SET-8570 Set Structure: Wc-222 0%0.25 0.00 0.25 22-Aug-24 23-Aug-24 0.33 22-Aug-24 23-Aug-24 0.00 1736 WC8-SET-8575 Set Structure: Wc-223 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 0.33 23-Aug-24 23-Aug-24 0.00 1737 WC8-SET-8580 Set Structure: Wc-224 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 0.33 23-Aug-24 23-Aug-24 0.00 1738 WC8-SET-8585 Set Structure: Wc-225 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 0.33 23-Aug-24 23-Aug-24 0.00 1739 WC8-SET-8590 Set Structure: Wc-226 0%0.25 0.00 0.25 23-Aug-24 24-Aug-24 0.33 23-Aug-24 24-Aug-24 0.00 1740 WC8-SET-8595 Set Structure: Wc-227 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 0.33 24-Aug-24 24-Aug-24 0.00 1741 WC8-SET-8600 Set Structure: Wc-228 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 0.33 24-Aug-24 24-Aug-24 0.00 1742 WC8-SET-8605 Set Structure: Wc-229 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 0.33 24-Aug-24 24-Aug-24 0.00 1743 WC8-SET-8610 Set Structure: Wc-230 0%0.25 0.00 0.25 24-Aug-24 26-Aug-24 0.33 24-Aug-24 26-Aug-24 0.00 1744 WC8-SET-8615 Set Structure: Wc-231 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 0.33 26-Aug-24 26-Aug-24 0.00 1745 WC8-SET-8620 Set Structure: Wc-232 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 0.33 26-Aug-24 26-Aug-24 0.00 1746 WC8-SET-8625 Set Structure: Wc-233 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 0.33 26-Aug-24 26-Aug-24 0.00 1747 WC8-SET-8630 Set Structure: Wc-234 0%0.25 0.00 0.25 26-Aug-24 27-Aug-24 0.33 26-Aug-24 27-Aug-24 1748 WC8-SET-8635 Set Structure: Wc-235 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 0.33 27-Aug-24 27-Aug-24 0.00 1749 WC8-SET-8640 Set Structure: Wc-236 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 0.33 27-Aug-24 27-Aug-24 0.00 1750 WC8-SET-8645 Set Structure: Wc-237 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 0.33 27-Aug-24 27-Aug-24 0.00 1751 WC8-SET-8650 Set Structure: Wc-238 0%0.25 0.00 0.25 27-Aug-24 28-Aug-24 0.33 27-Aug-24 28-Aug-24 0.00 1752 WC8-SET-8655 Set Structure: Wc-239 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 0.33 28-Aug-24 28-Aug-24 0.00 1753 WC8-SET-8660 Set Structure: c-240 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 0.33 28-Aug-24 28-Aug-24 0.00 1754 WC8-SET-8665 Set Structure: Wc-241 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 0.33 28-Aug-24 28-Aug-24 0.00 1755 WC8-SET-8670 Set Structure: Wc-242 0%0.25 0.00 0.25 28-Aug-24 29-Aug-24 0.33 28-Aug-24 29-Aug-24 0.00 1756 WC8-SET-8675 Set Structure: Wc-243 0%0.25 0.00 0.25 29-Aug-24 29-Aug-24 0.33 29-Aug-24 29-Aug-24 0.00 1757 WC8-SET-8680 Set Structure: Wc-244 0%0.25 0.00 0.25 29-Aug-24 29-Aug-24 0.33 29-Aug-24 29-Aug-24 0.00 1758 WC8-SET-8800 Set Structure: Wc-245 *raptor restrictions start 0%0.25 0.00 0.25 29-Aug-24 29-Aug-24 0.33 29-Aug-24 29-Aug-24 0.00 1759 WC8-SET-8805 Set Structure: Wc-246 0%0.25 0.00 0.25 29-Aug-24 30-Aug-24 0.33 29-Aug-24 30-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Set Structure: Wc-208, 03-Aug-24 Set Structure: Wc - 174, 03-Aug-24 Set Structure: Wc-177, 05-Aug-24 Set Structure: Wc-178, 06-Aug-24 Set Structure: Wc-179, 07-Aug-24 Set Structure: Wc-180, 07-Aug-24 Set Structure: Wc-181, 08-Aug-24 Set Structure: Wc-183, 09-Aug-24 Set Structure: Wc-182, 10-Aug-24 Set Structure: Wc-184, 10-Aug-24 Set Structure: Wc-185, 12-Aug-24 Set Structure: Wc-186, 13-Aug-24 Set Structure: Wc-187, 14-Aug-24 Set Structure: Wc-188, 14-Aug-24 Set Structure: Wc-189, 15-Aug-24 Set Structure: Wc-189b, 16-Aug-24 Set Structure: Wc-189C, 17-Aug-24 Set Structure: Wc-189A, 17-Aug-24 Set Structure: Wc-204 fabrication issues, 19-Aug-24 Set Structure: Wc-209, 19-Aug-24 Set Structure: Wc-210, 20-Aug-24 Set Structure: Wc-211, 20-Aug-24 Set Structure: Wc-212, 20-Aug-24 Set Structure: Wc-213, 20-Aug-24 Set Structure: Wc-214, 21-Aug-24 Set Structure: Wc-215, 21-Aug-24 Set Structure: Wc-216, 21-Aug-24 Set Structure: Wc-217, 21-Aug-24 Set Structure: Wc-218, 22-Aug-24 Set Structure: Wc-219, 22-Aug-24 Set Structure: Wc-220, 22-Aug-24 Set Structure: Wc-221, 22-Aug-24 Set Structure: Wc-222, 23-Aug-24 Set Structure: Wc-223, 23-Aug-24 Set Structure: Wc-224, 23-Aug-24 Set Structure: Wc-225, 23-Aug-24 Set Structure: Wc-226, 24-Aug-24 Set Structure: Wc-227, 24-Aug-24 Set Structure: Wc-228, 24-Aug-24 Set Structure: Wc-229, 24-Aug-24 Set Structure: Wc-230, 26-Aug-24 Set Structure: Wc-231, 26-Aug-24 Set Structure: Wc-232, 26-Aug-24 Set Structure: Wc-233, 26-Aug-24 Set Structure: Wc-234, 27-Aug-24 Set Structure: Wc-235, 27-Aug-24 Set Structure: Wc-236, 27-Aug-24 Set Structure: Wc-237, 27-Aug-24 Set Structure: Wc-238, 28-Aug-24 Set Structure: Wc-239, 28-Aug-24 Set Structure: c-240, 28-Aug-24 Set Structure: Wc-241, 28-Aug-24 Set Structure: Wc-242, 29-Aug-24 Set Structure: Wc-243, 29-Aug-24 Set Structure: Wc-244, 29-Aug-24 Set Structure: Wc-245 *raptor restrictions start, 29-Aug-24 Set Structure: Wc-246, 30-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 33 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1760 WC8-SET-8810 Set Structure: Wc-247 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 0.33 30-Aug-24 30-Aug-24 0.00 1761 WC8-SET-8815 Set Structure: Wc-248 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 0.33 30-Aug-24 30-Aug-24 0.00 1762 WC8-SET-8820 Set Structure: Wc-249 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 0.33 30-Aug-24 30-Aug-24 0.00 1763 WC8-SET-8825 Set Structure: Wc-250 0%0.25 0.00 0.25 30-Aug-24 31-Aug-24 0.33 30-Aug-24 31-Aug-24 0.00 1764 WC8-SET-8830 Set Structure: Wc-251 0%0.25 0.00 0.25 31-Aug-24 31-Aug-24 0.33 31-Aug-24 31-Aug-24 0.00 1765 WC8-SET-8836 Set Structure: Wc-252 0%0.25 0.00 0.25 31-Aug-24 31-Aug-24 0.33 31-Aug-24 31-Aug-24 0.00 1766 WC8-SET-8840 Set Structure: Wc-253 0%0.25 0.00 0.25 31-Aug-24 31-Aug-24 0.33 31-Aug-24 31-Aug-24 0.00 1767 WC8-SET-8845 Set Structure: Wc-254 0%0.25 0.00 0.25 31-Aug-24 02-Sep-24 0.33 31-Aug-24 02-Sep-24 0.00 1768 WC8-SET-8850 Set Structure: Wc-255 0%0.25 0.00 0.25 02-Sep-24 02-Sep-24 0.33 02-Sep-24 02-Sep-24 0.00 1769 WC8-SET-8855 Set Structure: Wc-256 0%0.25 0.00 0.25 02-Sep-24 02-Sep-24 0.33 02-Sep-24 02-Sep-24 0.00 1770 WC8-SET-8860 Set Structure: Wc-257 *raptor restrictions end 0%0.25 0.00 0.25 02-Sep-24 02-Sep-24 0.33 02-Sep-24 02-Sep-24 0.00 1771 WC8-SET-8685 Set Structure: Wc-258 0%0.25 0.00 0.25 02-Sep-24 03-Sep-24 0.33 02-Sep-24 03-Sep-24 0.00 1772 WC8-SET-8690 Set Structure: Wc-259 0%0.25 0.00 0.25 03-Sep-24 03-Sep-24 0.33 03-Sep-24 03-Sep-24 0.00 1773 WC8-SET-8695 Set Structure: Wc-260 0%0.25 0.00 0.25 03-Sep-24 03-Sep-24 0.33 03-Sep-24 03-Sep-24 0.00 1774 WC8-SET-8700 Set Structure: Wc-261 0%0.25 0.00 0.25 03-Sep-24 03-Sep-24 0.33 03-Sep-24 03-Sep-24 0.00 1775 WC8-SET-8705 Set Structure: Wc-262 0%0.25 0.00 0.25 03-Sep-24 04-Sep-24 0.33 03-Sep-24 04-Sep-24 0.00 1776 WC8-SET-8710 Set Structure: Wc-263 0%0.25 0.00 0.25 04-Sep-24 04-Sep-24 0.33 04-Sep-24 04-Sep-24 0.00 1777 WC8-SET-8715 Set Structure: Wc-264 0%0.25 0.00 0.25 04-Sep-24 04-Sep-24 0.33 04-Sep-24 04-Sep-24 0.00 1778 WC8-SET-8720 Set Structure: Wc-265 0%0.25 0.00 0.25 04-Sep-24 04-Sep-24 0.33 04-Sep-24 04-Sep-24 0.00 1779 WC8-SET-8725 Set Structure: Wc-266 0%0.25 0.00 0.25 04-Sep-24 05-Sep-24 0.33 04-Sep-24 05-Sep-24 0.00 1780 WC8-SET-8731 Set Structure: Wc-267 DP 0%0.25 0.00 0.25 05-Sep-24 05-Sep-24 0.33 05-Sep-24 05-Sep-24 0.00 1781 Crew 3Crew 3Crew 3 48.46 0.00 48.46 03-Jul-24 31-Aug-24 32.80 09-Jul-24 31-Aug-24 0.00 1782 WC7-SET-8085 Set Structure: Wc-148 0%0.35 0.00 0.35 03-Jul-24 03-Jul-24 24.84 09-Jul-24 09-Jul-24 2.00 1783 WC7-SET-8080 Set Structure: Wc-147 0%0.35 0.00 0.35 03-Jul-24 08-Jul-24 24.84 09-Jul-24 10-Jul-24 2.00 1784 WC7-SET-8075 Set Structure: Wc-146 0%0.35 0.00 0.35 08-Jul-24 08-Jul-24 24.84 10-Jul-24 10-Jul-24 2.00 1785 WC7-SET-8070 Set Structure: Wc-145 0%0.35 0.00 0.35 08-Jul-24 08-Jul-24 24.84 10-Jul-24 10-Jul-24 2.00 1786 WC7-SET-8065 Set Structure: Wc-144 0%0.35 0.00 0.35 08-Jul-24 09-Jul-24 24.84 10-Jul-24 11-Jul-24 2.00 1787 WC7-SET-8060 Set Structure: Wc-143 0%0.35 0.00 0.35 09-Jul-24 09-Jul-24 24.84 11-Jul-24 11-Jul-24 2.00 1788 WC7-SET-8055 Set Structure: Wc-142 0%0.35 0.00 0.35 09-Jul-24 09-Jul-24 24.84 11-Jul-24 11-Jul-24 2.00 1789 WC7-SET-8050 Set Structure: Wc-141 0%0.35 0.00 0.35 09-Jul-24 10-Jul-24 24.84 11-Jul-24 12-Jul-24 2.00 1790 WC7-SET-8045 Set Structure: Wc-140 0%0.35 0.00 0.35 10-Jul-24 10-Jul-24 24.84 12-Jul-24 12-Jul-24 2.00 1791 WC7-SET-8040 Set Structure: Wc-139 0%0.35 0.00 0.35 10-Jul-24 11-Jul-24 24.84 12-Jul-24 13-Jul-24 2.00 1792 WC7-SET-8035 Set Structure: Wc-138 0%0.35 0.00 0.35 11-Jul-24 11-Jul-24 24.84 13-Jul-24 13-Jul-24 2.00 1793 WC7-SET-8030 Set Structure: Wc-137 0%0.35 0.00 0.35 11-Jul-24 11-Jul-24 24.84 13-Jul-24 13-Jul-24 2.00 1794 WC7-SET-8025 Set Structure: Wc-136 0%0.35 0.00 0.35 11-Jul-24 12-Jul-24 24.84 13-Jul-24 15-Jul-24 2.00 1795 WC7-SET-8020 Set Structure: Wc-135 0%0.35 0.00 0.35 12-Jul-24 12-Jul-24 24.84 15-Jul-24 15-Jul-24 2.00 1796 WC7-SET-8015 Set Structure: Wc-134 0%0.35 0.00 0.35 12-Jul-24 12-Jul-24 24.84 15-Jul-24 15-Jul-24 2.00 1797 WC7-SET-8010 Set Structure: Wc-133 0%0.35 0.00 0.35 12-Jul-24 13-Jul-24 24.84 15-Jul-24 16-Jul-24 2.00 1798 WC7-SET-8005 Set Structure: Wc-132 0%0.35 0.00 0.35 13-Jul-24 13-Jul-24 24.84 16-Jul-24 16-Jul-24 2.00 1799 WC7-SET-8000 Set Structure: Wc-131 0%0.35 0.00 0.35 13-Jul-24 13-Jul-24 24.84 16-Jul-24 16-Jul-24 2.00 1800 WC7-SET-7995 Set Structure: Wc-130 0%0.35 0.00 0.35 13-Jul-24 15-Jul-24 24.84 16-Jul-24 17-Jul-24 2.00 1801 WC7-SET-7990 Set Structure: Wc-129 0%0.35 0.00 0.35 15-Jul-24 15-Jul-24 24.84 17-Jul-24 17-Jul-24 2.00 1802 WC7-SET-7985 Set Structure: Wc-128 0%0.35 0.00 0.35 15-Jul-24 15-Jul-24 24.84 17-Jul-24 17-Jul-24 2.00 1803 WC7-SET-7980 Set Structure: Wc-127 0%0.35 0.00 0.35 15-Jul-24 16-Jul-24 24.84 17-Jul-24 18-Jul-24 2.00 1804 WC7-SET-7975 Set Structure: Wc-126 0%0.35 0.00 0.35 16-Jul-24 16-Jul-24 24.84 18-Jul-24 18-Jul-24 2.00 1805 WC7-SET-7970 Set Structure: Wc-125 0%0.35 0.00 0.35 16-Jul-24 16-Jul-24 24.84 18-Jul-24 18-Jul-24 2.00 1806 WC7-SET-7965 Set Structure: Wc-124 DP 0%0.50 0.00 0.50 24-Jul-24 24-Jul-24 18.78 24-Jul-24 24-Jul-24 0.00 1807 WC7-SET-7960 Set Structure: Wc-123 0%0.35 0.00 0.35 24-Jul-24 24-Jul-24 18.78 24-Jul-24 24-Jul-24 0.00 1808 WC7-SET-7955 Set Structure: Wc-122 DP 0%0.50 0.00 0.50 29-Jul-24 29-Jul-24 15.13 29-Jul-24 29-Jul-24 0.00 1809 WC7-SET-7950 Set Structure: Wc-121 0%0.35 0.00 0.35 30-Jul-24 30-Jul-24 15.13 30-Jul-24 30-Jul-24 0.00 1810 Crew 2 Set Structure: Wc-120 0%0.35 0.00 0.35 30-Jul-24 30-Jul-24 15.13 30-Jul-24 30-Jul-24 0.00 1811 WC7-SET-7940 Set Structure: Wc-119 0%0.35 0.00 0.35 30-Jul-24 31-Jul-24 15.13 30-Jul-24 31-Jul-24 0.00 1812 WC7-SET-7935 Set Structure: Wc-118 0%0.35 0.00 0.35 31-Jul-24 31-Jul-24 15.13 31-Jul-24 31-Jul-24 0.00 1813 WC7-SET-7930 Set Structure: Wc-117 0%0.35 0.00 0.35 31-Jul-24 31-Jul-24 15.13 31-Jul-24 31-Jul-24 0.00 1814 WC7-SET-7925 Set Structure: Wc-116 0%0.35 0.00 0.35 31-Jul-24 01-Aug-24 15.13 31-Jul-24 01-Aug-24 0.00 1815 WC7-SET-7920 Set Structure: Wc-115 0%0.35 0.00 0.35 01-Aug-24 01-Aug-24 15.13 01-Aug-24 01-Aug-24 0.00 1816 WC7-SET-7915 Set Structure: Wc-114 0%0.35 0.00 0.35 01-Aug-24 01-Aug-24 15.13 01-Aug-24 01-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Set Structure: Wc-247, 30-Aug-24 Set Structure: Wc-248, 30-Aug-24 Set Structure: Wc-249, 30-Aug-24 Set Structure: Wc-250, 31-Aug-24 Set Structure: Wc-251, 31-Aug-24 Set Structure: Wc-252, 31-Aug-24 Set Structure: Wc-253, 31-Aug-24 Set Structure: Wc-254, 02-Sep-24 Set Structure: Wc-255, 02-Sep-24 Set Structure: Wc-256, 02-Sep-24 Set Structure: Wc-257 *raptor restrictions end, 02-Sep-24 Set Structure: Wc-258, 03-Sep-24 Set Structure: Wc-259, 03-Sep-24 Set Structure: Wc-260, 03-Sep-24 Set Structure: Wc-261, 03-Sep-24 Set Structure: Wc-262, 04-Sep-24 Set Structure: Wc-263, 04-Sep-24 Set Structure: Wc-264, 04-Sep-24 Set Structure: Wc-265, 04-Sep-24 Set Structure: Wc-266, 05-Sep-24 Set Structure: Wc-267 DP, 05-Sep-24 31-Aug-24, Crew 3 Set Structure: Wc-148, 03-Jul-24 Set Structure: Wc-147, 08-Jul-24 Set Structure: Wc-146, 08-Jul-24 Set Structure: Wc-145, 08-Jul-24 Set Structure: Wc-144, 09-Jul-24 Set Structure: Wc-143, 09-Jul-24 Set Structure: Wc-142, 09-Jul-24 Set Structure: Wc-141, 10-Jul-24 Set Structure: Wc-140, 10-Jul-24 Set Structure: Wc-139, 11-Jul-24 Set Structure: Wc-138, 11-Jul-24 Set Structure: Wc-137, 11-Jul-24 Set Structure: Wc-136, 12-Jul-24 Set Structure: Wc-135, 12-Jul-24 Set Structure: Wc-134, 12-Jul-24 Set Structure: Wc-133, 13-Jul-24 Set Structure: Wc-132, 13-Jul-24 Set Structure: Wc-131, 13-Jul-24 Set Structure: Wc-130, 15-Jul-24 Set Structure: Wc-129, 15-Jul-24 Set Structure: Wc-128, 15-Jul-24 Set Structure: Wc-127, 16-Jul-24 Set Structure: Wc-126, 16-Jul-24 Set Structure: Wc-125, 16-Jul-24 Set Structure: Wc-124 DP, 24-Jul-24 Set Structure: Wc-123, 24-Jul-24 Set Structure: Wc-122 DP, 29-Jul-24 Set Structure: Wc-121, 30-Jul-24 Set Structure: Wc-120, 30-Jul-24 Set Structure: Wc-119, 31-Jul-24 Set Structure: Wc-118, 31-Jul-24 Set Structure: Wc-117, 31-Jul-24 Set Structure: Wc-116, 01-Aug-24 Set Structure: Wc-115, 01-Aug-24 Set Structure: Wc-114, 01-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 34 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1817 WC7-SET-7910 Set Structure: Wc-113 0%0.35 0.00 0.35 01-Aug-24 02-Aug-24 15.13 01-Aug-24 02-Aug-24 0.00 1818 WC7-SET-7905 Set Structure: Wc-112 DP 0%0.50 0.00 0.50 02-Aug-24 02-Aug-24 15.13 02-Aug-24 02-Aug-24 0.00 1819 WC7-SET-7900 Set Structure: Wc-111 0%0.35 0.00 0.35 02-Aug-24 02-Aug-24 19.88 02-Aug-24 02-Aug-24 0.00 1820 WC7-SET-7895 Set Structure: Wc-110 0%0.35 0.00 0.35 03-Aug-24 03-Aug-24 19.88 03-Aug-24 03-Aug-24 0.00 1821 WC7-SET-7890 Set Structure: Wc-109 0%0.35 0.00 0.35 03-Aug-24 03-Aug-24 19.88 03-Aug-24 03-Aug-24 0.00 1822 WC7-SET-7885 Set Structure: Wc-108 0%0.35 0.00 0.35 03-Aug-24 05-Aug-24 19.88 03-Aug-24 05-Aug-24 0.00 1823 WC7-SET-7880 Set Structure: Wc-107 0%0.35 0.00 0.35 05-Aug-24 05-Aug-24 19.88 05-Aug-24 05-Aug-24 0.00 1824 WC7-SET-7875 Set Structure: Wc-106 DP 0%0.50 0.00 0.50 05-Aug-24 05-Aug-24 19.88 05-Aug-24 05-Aug-24 0.00 1825 WC7-SET-7870 Set Structure: Wc-105 0%0.35 0.00 0.35 05-Aug-24 06-Aug-24 22.78 05-Aug-24 06-Aug-24 0.00 1826 WC7-SET-7865 Set Structure: Wc-104 0%0.35 0.00 0.35 06-Aug-24 06-Aug-24 22.78 06-Aug-24 06-Aug-24 0.00 1827 WC7-SET-7860 Set Structure: Wc-103 0%0.35 0.00 0.35 06-Aug-24 06-Aug-24 22.78 06-Aug-24 06-Aug-24 0.00 1828 WC7-SET-7855 Set Structure: Wc-102 0%0.35 0.00 0.35 06-Aug-24 07-Aug-24 22.78 06-Aug-24 07-Aug-24 0.00 1829 WC7-SET-7850 Set Structure: Wc-101 0%0.35 0.00 0.35 07-Aug-24 07-Aug-24 22.78 07-Aug-24 07-Aug-24 0.00 1830 WC7-SET-7845 Set Structure: Wc-100 0%0.35 0.00 0.35 07-Aug-24 07-Aug-24 22.78 07-Aug-24 07-Aug-24 0.00 1831 WC7-SET-7840 Set Structure: Wc-99 0%0.35 0.00 0.35 08-Aug-24 08-Aug-24 22.78 08-Aug-24 08-Aug-24 0.00 1832 WC7-SET-7835 Set Structure: Wc-98 0%0.35 0.00 0.35 08-Aug-24 08-Aug-24 22.78 08-Aug-24 08-Aug-24 0.00 1833 WC7-SET-7830 Set Structure: Wc-97 0%0.35 0.00 0.35 08-Aug-24 09-Aug-24 22.78 08-Aug-24 09-Aug-24 0.00 1834 WC7-SET-7825 Set Structure: Wc-96 0%0.35 0.00 0.35 09-Aug-24 09-Aug-24 22.78 09-Aug-24 09-Aug-24 0.00 1835 WC7-SET-7820 Set Structure: Wc-95 0%0.35 0.00 0.35 09-Aug-24 09-Aug-24 22.78 09-Aug-24 09-Aug-24 0.00 1836 WC7-SET-7815 Set Structure: Wc-94 *move to 268*0%0.25 0.00 0.25 09-Aug-24 09-Aug-24 22.78 09-Aug-24 09-Aug-24 0.00 1837 WC9-SET-9000 Set Structure: Wc-268 DP 0%0.50 0.00 0.50 10-Aug-24 10-Aug-24 24.30 10-Aug-24 10-Aug-24 0.00 1838 WC9-SET-9005 Set Structure: Wc-269 0%0.25 0.00 0.25 10-Aug-24 10-Aug-24 24.30 10-Aug-24 10-Aug-24 0.00 1839 WC9-SET-9010 Set Structure: Wc-270 DP 0%0.50 0.00 0.50 10-Aug-24 12-Aug-24 24.30 10-Aug-24 12-Aug-24 0.00 1840 WC9-SET-9015 Set Structure: Wc-271 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 24.30 12-Aug-24 12-Aug-24 0.00 1841 WC9-SET-9020 Set Structure: Wc-272 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 24.30 12-Aug-24 12-Aug-24 0.00 1842 WC9-SET-9025 Set Structure: Wc-273 0%0.25 0.00 0.25 12-Aug-24 12-Aug-24 24.30 12-Aug-24 12-Aug-24 0.00 1843 WC9-SET-9030 Set Structure: Wc-274 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 24.30 13-Aug-24 13-Aug-24 0.00 1844 WC9-SET-9035 Set Structure: Wc-275 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 24.30 13-Aug-24 13-Aug-24 0.00 1845 WC9-SET-9040 Set Structure: Wc-276 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 24.30 13-Aug-24 13-Aug-24 0.00 1846 WC9-SET-9045 Set Structure: Wc-277 0%0.25 0.00 0.25 13-Aug-24 13-Aug-24 24.30 13-Aug-24 13-Aug-24 0.00 1847 WC9-SET-9050 Set Structure: Wc-278 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 24.30 14-Aug-24 14-Aug-24 0.00 1848 WC9-SET-9055 Set Structure: Wc-279 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 24.30 14-Aug-24 14-Aug-24 0.00 1849 WC9-SET-9060 Set Structure: Wc-280 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 24.30 14-Aug-24 14-Aug-24 0.00 1850 WC9-SET-9065 Set Structure: Wc-281 0%0.25 0.00 0.25 14-Aug-24 14-Aug-24 24.30 14-Aug-24 14-Aug-24 0.00 1851 WC9-SET-9070 Set Structure: Wc-282 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 24.30 15-Aug-24 15-Aug-24 0.00 1852 WC9-SET-9080 Set Structure: Wc-283 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 24.30 15-Aug-24 15-Aug-24 0.00 1853 WC9-SET-9090 Set Structure: Wc-284 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 24.30 15-Aug-24 15-Aug-24 0.00 1854 WC9-SET-9100 Set Structure: Wc-285 0%0.25 0.00 0.25 15-Aug-24 15-Aug-24 24.30 15-Aug-24 15-Aug-24 0.00 1855 WC9-SET-9110 Set Structure: Wc-286 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 24.30 16-Aug-24 16-Aug-24 0.00 1856 WC9-SET-9120 Set Structure: Wc-287 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 24.30 16-Aug-24 16-Aug-24 0.00 1857 WC9-SET-9130 Set Structure: Wc-288 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 27.30 16-Aug-24 16-Aug-24 0.00 1858 WC9-SET-9075 Set Structure: Wc-289 0%0.25 0.00 0.25 16-Aug-24 16-Aug-24 27.30 16-Aug-24 16-Aug-24 0.00 1859 WC9-SET-9085 Set Structure: Wc-290 0%0.25 0.00 0.25 17-Aug-24 17-Aug-24 27.30 17-Aug-24 17-Aug-24 0.00 1860 WC9-SET-9095 Set Structure: Wc-291 0%0.25 0.00 0.25 17-Aug-24 17-Aug-24 27.30 17-Aug-24 17-Aug-24 0.00 1861 WC9-SET-9105 Set Structure: Wc-292 0%0.25 0.00 0.25 17-Aug-24 17-Aug-24 27.30 17-Aug-24 17-Aug-24 0.00 1862 WC9-SET-9115 Set Structure: Wc-293 0%0.25 0.00 0.25 17-Aug-24 17-Aug-24 27.30 17-Aug-24 17-Aug-24 0.00 1863 WC9-SET-9125 Set Structure: Wc-294 0%0.25 0.00 0.25 19-Aug-24 19-Aug-24 27.30 19-Aug-24 19-Aug-24 0.00 1864 WC9-SET-9135 Set Structure: Wc-295 0%0.25 0.00 0.25 19-Aug-24 19-Aug-24 27.30 19-Aug-24 19-Aug-24 0.00 1865 WC9-SET-9140 Set Structure: Wc-296 0%0.25 0.00 0.25 19-Aug-24 19-Aug-24 27.30 19-Aug-24 19-Aug-24 0.00 1866 WC9-SET-9145 Set Structure: Wc-297 0%0.25 0.00 0.25 19-Aug-24 19-Aug-24 27.30 19-Aug-24 19-Aug-24 0.00 1867 WC9-SET-9150 Set Structure: Wc-298 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 27.30 20-Aug-24 20-Aug-24 0.00 1868 WC9-SET-9155 Set Structure: Wc-299 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 27.30 20-Aug-24 20-Aug-24 0.00 1869 WC9-SET-9160 Set Structure: Wc-300 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 27.30 20-Aug-24 20-Aug-24 0.00 1870 WC9-SET-9165 Set Structure: Wc-301 0%0.25 0.00 0.25 20-Aug-24 20-Aug-24 27.30 20-Aug-24 20-Aug-24 0.00 1871 WC9-SET-9170 Set Structure: Wc-302 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 27.30 21-Aug-24 21-Aug-24 0.00 1872 WC9-SET-9175 Set Structure: Wc-303 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 27.30 21-Aug-24 21-Aug-24 0.00 1873 WC9-SET-9180 Set Structure: Wc-304 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 27.30 21-Aug-24 21-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Set Structure: Wc-113, 02-Aug-24 Set Structure: Wc-112 DP, 02-Aug-24 Set Structure: Wc-111, 02-Aug-24 Set Structure: Wc-110, 03-Aug-24 Set Structure: Wc-109, 03-Aug-24 Set Structure: Wc-108, 05-Aug-24 Set Structure: Wc-107, 05-Aug-24 Set Structure: Wc-106 DP, 05-Aug-24 Set Structure: Wc-105, 06-Aug-24 Set Structure: Wc-104, 06-Aug-24 Set Structure: Wc-103, 06-Aug-24 Set Structure: Wc-102, 07-Aug-24 Set Structure: Wc-101, 07-Aug-24 Set Structure: Wc-100, 07-Aug-24 Set Structure: Wc-99, 08-Aug-24 Set Structure: Wc-98, 08-Aug-24 Set Structure: Wc-97, 09-Aug-24 Set Structure: Wc-96, 09-Aug-24 Set Structure: Wc-95, 09-Aug-24 Set Structure: Wc-94 *move to 268*, 09-Aug-24 Set Structure: Wc-268 DP, 10-Aug-24 Set Structure: Wc-269, 10-Aug-24 Set Structure: Wc-270 DP, 12-Aug-24 Set Structure: Wc-271, 12-Aug-24 Set Structure: Wc-272, 12-Aug-24 Set Structure: Wc-273, 12-Aug-24 Set Structure: Wc-274, 13-Aug-24 Set Structure: Wc-275, 13-Aug-24 Set Structure: Wc-276, 13-Aug-24 Set Structure: Wc-277, 13-Aug-24 Set Structure: Wc-278, 14-Aug-24 Set Structure: Wc-279, 14-Aug-24 Set Structure: Wc-280, 14-Aug-24 Set Structure: Wc-281, 14-Aug-24 Set Structure: Wc-282, 15-Aug-24 Set Structure: Wc-283, 15-Aug-24 Set Structure: Wc-284, 15-Aug-24 Set Structure: Wc-285, 15-Aug-24 Set Structure: Wc-286, 16-Aug-24 Set Structure: Wc-287, 16-Aug-24 Set Structure: Wc-288, 16-Aug-24 Set Structure: Wc-289, 16-Aug-24 Set Structure: Wc-290, 17-Aug-24 Set Structure: Wc-291, 17-Aug-24 Set Structure: Wc-292, 17-Aug-24 Set Structure: Wc-293, 17-Aug-24 Set Structure: Wc-294, 19-Aug-24 Set Structure: Wc-295, 19-Aug-24 Set Structure: Wc-296, 19-Aug-24 Set Structure: Wc-297, 19-Aug-24 Set Structure: Wc-298, 20-Aug-24 Set Structure: Wc-299, 20-Aug-24 Set Structure: Wc-300, 20-Aug-24 Set Structure: Wc-301, 20-Aug-24 Set Structure: Wc-302, 21-Aug-24 Set Structure: Wc-303, 21-Aug-24 Set Structure: Wc-304, 21-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 35 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1874 WC9-SET-9185 Set Structure: Wc-305 0%0.25 0.00 0.25 21-Aug-24 21-Aug-24 27.30 21-Aug-24 21-Aug-24 0.00 1875 WC9-SET-9195 Set Structure: Wc-306 DP 0%0.50 0.00 0.50 22-Aug-24 22-Aug-24 27.30 22-Aug-24 22-Aug-24 0.00 1876 WC9-SET-9200 Set Structure: Wc-307 0%0.25 0.00 0.25 22-Aug-24 22-Aug-24 30.30 22-Aug-24 22-Aug-24 0.00 1877 WC9-SET-9205 Set Structure: Wc-308 0%0.25 0.00 0.25 22-Aug-24 22-Aug-24 30.30 22-Aug-24 22-Aug-24 0.00 1878 WC9-SET-9210 Set Structure: Wc-309 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 30.30 23-Aug-24 23-Aug-24 0.00 1879 WC9-SET-9215 Set Structure: Wc-310 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 30.30 23-Aug-24 23-Aug-24 0.00 1880 WC9-SET-9220 Set Structure: Wc-311 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 30.30 23-Aug-24 23-Aug-24 0.00 1881 WC9-SET-9225 Set Structure: Wc-312 0%0.25 0.00 0.25 23-Aug-24 23-Aug-24 30.30 23-Aug-24 23-Aug-24 0.00 1882 WC9-SET-9230 Set Structure: Wc-313 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 30.30 24-Aug-24 24-Aug-24 0.00 1883 WC9-SET-9235 Set Structure: Wc-314 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 30.30 24-Aug-24 24-Aug-24 0.00 1884 WC9-SET-9240 Set Structure: Wc-315 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 30.30 24-Aug-24 24-Aug-24 0.00 1885 WC9-SET-9245 Set Structure: Wc-316 0%0.25 0.00 0.25 24-Aug-24 24-Aug-24 30.30 24-Aug-24 24-Aug-24 0.00 1886 WC9-SET-9250 Set Structure: Wc-317 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 30.30 26-Aug-24 26-Aug-24 0.00 1887 WC9-SET-9255 Set Structure: Wc-318 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 30.30 26-Aug-24 26-Aug-24 0.00 1888 WC9-SET-9260 Set Structure: Wc-319 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 30.30 26-Aug-24 26-Aug-24 0.00 1889 WC9-SET-9265 Set Structure: Wc-320 0%0.25 0.00 0.25 26-Aug-24 26-Aug-24 30.30 26-Aug-24 26-Aug-24 0.00 1890 Crew 2 Set Structure: Wc-321 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 30.30 27-Aug-24 27-Aug-24 0.00 1891 WC9-SET-9275 Set Structure: Wc-322 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 30.30 27-Aug-24 27-Aug-24 0.00 1892 WC9-SET-9280 Set Structure: Wc-323 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 30.30 27-Aug-24 27-Aug-24 0.00 1893 WC9-SET-9285 Set Structure: Wc-324 0%0.25 0.00 0.25 27-Aug-24 27-Aug-24 30.30 27-Aug-24 27-Aug-24 0.00 1894 WC9-SET-9290 Set Structure: Wc-325 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 30.30 28-Aug-24 28-Aug-24 0.00 1895 WC9-SET-9295 Set Structure: Wc-326 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 30.30 28-Aug-24 28-Aug-24 0.00 1896 WC9-SET-9300 Set Structure: Wc-327 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 33.80 28-Aug-24 28-Aug-24 0.00 1897 WC9-SET-9305 Set Structure: Wc-328 0%0.25 0.00 0.25 28-Aug-24 28-Aug-24 33.80 28-Aug-24 28-Aug-24 0.00 1898 WC9-SET-9310 Set Structure: Wc-329 DP 0%0.50 0.00 0.50 29-Aug-24 29-Aug-24 33.80 29-Aug-24 29-Aug-24 0.00 1899 WC9-SET-9315 Set Structure: Wc-330 0%0.25 0.00 0.25 29-Aug-24 29-Aug-24 33.80 29-Aug-24 29-Aug-24 0.00 1900 WC9-SET-9320 Set Structure: Wc-331 0%0.25 0.00 0.25 29-Aug-24 29-Aug-24 33.80 29-Aug-24 29-Aug-24 0.00 1901 WC9-SET-9325 Set Structure: Wc-332 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 33.80 30-Aug-24 30-Aug-24 0.00 1902 WC9-SET-9330 Set Structure: Wc-333 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 33.80 30-Aug-24 30-Aug-24 0.00 1903 WC9-SET-9335 Set Structure: Wc-334 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 33.80 30-Aug-24 30-Aug-24 0.00 1904 WC9-SET-9340 Set Structure: Wc-335 0%0.25 0.00 0.25 30-Aug-24 30-Aug-24 33.80 30-Aug-24 30-Aug-24 0.00 1905 WC9-SET-9345 Set Structure: Wc-336 0%0.25 0.00 0.25 31-Aug-24 31-Aug-24 33.80 31-Aug-24 31-Aug-24 0.00 1906 WC9-SET-9350 Set Structure: Wc-337 0%0.25 0.00 0.25 31-Aug-24 31-Aug-24 33.80 31-Aug-24 31-Aug-24 0.00 1907 WC9-SET-9355 Set Structure: Wc-2/177A DP 0%0.50 0.00 0.50 31-Aug-24 31-Aug-24 33.80 31-Aug-24 31-Aug-24 0.00 1908 Wire StringingWire StringingWire Stringing 203.45 104.00 93.45 01-Mar-24 A 29-Oct-24 256.55 01-Mar-24 29-Oct-24 0.00 1909 2024 Spring/Sum2024 Spring/Summer2024 Spring/Summer 203.45 104.00 93.45 01-Mar-24 A 29-Oct-24 256.55 01-Mar-24 29-Oct-24 0.00 1910 Crew 1Crew 1Crew 1 76.86 59.21 38.40 22-Apr-24 A 27-Aug-24 14.13 25-May-24 10-Sep-24 10.85 1911 WC6-STR-6800 Stringing: Wc-01 - Wc-17/18 100%9.00 8.21 0.00 22-Apr-24 A 06-May-24 A 25-May-24 05-Jun-24 25.79 1912 WC7-STR-7830 Stringing: Wc-88 - Wc-69/70 (Req. daily outages on distro1WC10b & distro1WC13a) 100%7.00 6.75 0.00 27-May-24 A 04-Jun-24 A 05-Jun-24 13-Jun-24 8.54 1913 WC7-STR-7820 Stringing: Wc-69 - Wc-50 (Req. daily outages on distro1WC10a)100%7.00 7.00 0.00 08-Jun-24 A 15-Jun-24 A 01-Jul-24 11-Jul-24 19.00 1914 WC6-STR-6830 Stringing: Wc-17/18 - Wc-32 100%7.00 6.00 0.00 15-Jun-24 A 21-Jun-24 A 12-Jul-24 19-Jul-24 21.00 1915 WC6-STR-6850 Stringing: Wc-48/49 - Wc-32 (outages distroWC01c, 230kv1WC02a, 69kv1WC02b, 115kv1WC03c, 115kv1WC03d) 100%7.00 5.00 0.00 25-Jun-24 A 29-Jun-24 A 02-Sep-24 10-Sep-24 58.50 1916 WC1-STR-1700 Stringing: Wc-171 - Wc149 0%7.00 0.00 7.00 13-Jul-24 22-Jul-24 18.53 20-Jul-24 27-Jul-24 5.75 1917 WC7-STR-7880 Stringing: Wc-149 - Wc-133/134 0%7.00 0.00 7.00 22-Jul-24 30-Jul-24 18.53 29-Jul-24 05-Aug-24 5.75 1918 WC7-STR-7870 Stringing: Wc-134/133 - Wc-112 0%7.00 0.00 7.00 02-Aug-24 10-Aug-24 15.13 06-Aug-24 13-Aug-24 2.35 1919 WC7-STR-7860 Stringing: Wc-112 - Wc-106 0%7.00 0.00 7.00 10-Aug-24 19-Aug-24 15.13 14-Aug-24 21-Aug-24 2.35 1920 WC7-STR-7850 Stringing: Wc-106 - Wc-88 (Req. daily outages on distro1w14a)0%7.00 0.00 7.00 19-Aug-24 27-Aug-24 15.13 22-Aug-24 29-Aug-24 2.35 1921 Crew 2Crew 2Crew 2 129.95 1.95 93.45 11-May-24 A 29-Oct-24 0.35 25-May-24 29-Oct-24 0.00 1922 Crew 2 Stringing: Wa-340 - Wa-344 *Constraint used to hold start date of crew 2 100%7.00 2.95 0.00 11-May-24 A 13-May-24 A 25-May-24 03-Jun-24 18.55 1923 WA3-STR-3730 Stringing: Wa-315 - Wa-329 0%8.50 0.00 8.50 11-Jul-24 20-Jul-24 0.33 11-Jul-24 20-Jul-24 0.00 1924 WA3-STR-3700 Stringing: Wa-265 - Wa344 Deficiencies Allowance 0%2.00 0.00 2.00 20-Jul-24 23-Jul-24 0.33 20-Jul-24 23-Jul-24 0.00 1925 WA3-STR-3370 OUTAGE - Temp 16 Jumper Install (begin Wc269-Wc2/177A, Energize Wa265-Wa344-SB 0%3.00 0.00 3.00 23-Jul-24 26-Jul-24 0.33 23-Jul-24 26-Jul-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Set Structure: Wc-305, 21-Aug-24 Set Structure: Wc-306 DP, 22-Aug-24 Set Structure: Wc-307, 22-Aug-24 Set Structure: Wc-308, 22-Aug-24 Set Structure: Wc-309, 23-Aug-24 Set Structure: Wc-310, 23-Aug-24 Set Structure: Wc-311, 23-Aug-24 Set Structure: Wc-312, 23-Aug-24 Set Structure: Wc-313, 24-Aug-24 Set Structure: Wc-314, 24-Aug-24 Set Structure: Wc-315, 24-Aug-24 Set Structure: Wc-316, 24-Aug-24 Set Structure: Wc-317, 26-Aug-24 Set Structure: Wc-318, 26-Aug-24 Set Structure: Wc-319, 26-Aug-24 Set Structure: Wc-320, 26-Aug-24 Set Structure: Wc-321, 27-Aug-24 Set Structure: Wc-322, 27-Aug-24 Set Structure: Wc-323, 27-Aug-24 Set Structure: Wc-324, 27-Aug-24 Set Structure: Wc-325, 28-Aug-24 Set Structure: Wc-326, 28-Aug-24 Set Structure: Wc-327, 28-Aug-24 Set Structure: Wc-328, 28-Aug-24 Set Structure: Wc-329 DP, 29-Aug-24 Set Structure: Wc-330, 29-Aug-24 Set Structure: Wc-331, 29-Aug-24 Set Structure: Wc-332, 30-Aug-24 Set Structure: Wc-333, 30-Aug-24 Set Structure: Wc-334, 30-Aug-24 Set Structure: Wc-335, 30-Aug-24 Set Structure: Wc-336, 31-Aug-24 Set Structure: Wc-337, 31-Aug-24 Set Structure: Wc-2/177A DP, 31-Aug-24 29-Oct-24, Wire Stringing 29-Oct-24, 2024 Spring/Summer 27-Aug-24, Crew 1 24 Stringing: Wc-171 - Wc149, 22-Jul-24 Stringing: Wc-149 - Wc-133/134, 30-Jul-24 Stringing: Wc-134/133 - Wc-112, 10-Aug-24 Stringing: Wc-112 - Wc-106, 19-Aug-24 Stringing: Wc-106 - Wc-88 (Req. daily outages on distro1w14a), 27-Aug-24 29-Oct-24, Crew 2 Stringing: Wa-315 - Wa-329, 20-Jul-24 Stringing: Wa-265 - Wa344 Deficiencies Allowance, 23-Jul-24 OUTAGE - Temp 16 Jumper Install (begin Wc269-Wc2/177A, Energize Wa265-Wa344-SB, 26-Ju Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 36 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1926 WA3-STR-3800b OUTAGE - Temp 20 Tie-in (Wa205) (begin Wc208-Wc267, Energize Wa205-Wa265) 0%7.00 0.00 7.00 23-Jul-24 30-Jul-24 0.33 23-Jul-24 30-Jul-24 0.00 1927 WC1-STR-1740 Stringing: Wc-195 -Wc-208 0%7.00 0.00 7.00 03-Aug-24 12-Aug-24 3.58 03-Aug-24 12-Aug-24 0.00 1928 WC1-STR-1720 Stringing: Wc-171 - Wc-180 0%9.00 0.00 9.00 13-Aug-24 23-Aug-24 2.33 13-Aug-24 23-Aug-24 0.00 1929 WC1-STR-1730 Stringing: Wc-180 - Wc-195 0%9.00 0.00 9.00 23-Aug-24 03-Sep-24 2.33 23-Aug-24 03-Sep-24 0.00 1930 WC8-STR-8830 Stringing: Wc-254 - Wc-267/ Heward #1 (Req. daily outages on 1WC45a)0%7.00 0.00 7.00 05-Sep-24 13-Sep-24 0.33 05-Sep-24 13-Sep-24 0.00 1931 WC9-STR-9800 Stringing: Wc-268 - Wc-286/287 --0%8.00 0.00 8.00 13-Sep-24 23-Sep-24 0.35 13-Sep-24 23-Sep-24 0.00 1932 WC9-STR-9810 Stringing: Wc-286/287 - Wc-306 0%8.00 0.00 8.00 23-Sep-24 02-Oct-24 0.35 23-Sep-24 02-Oct-24 0.00 1933 WC9-STR-9820 Stringing: Wc-306 - Wc-325/326 0%7.00 0.00 7.00 02-Oct-24 10-Oct-24 0.35 02-Oct-24 10-Oct-24 0.00 1934 WC9-STR-9830 Stringing: Wc-325/326 - Wc-2/177A 0%7.00 0.00 7.00 10-Oct-24 18-Oct-24 0.35 10-Oct-24 18-Oct-24 0.00 1935 WC9-STR-9850 Stringing: Wc-2/177A - Shirley Basin #1 0%7.00 0.00 7.00 18-Oct-24 26-Oct-24 0.35 18-Oct-24 26-Oct-24 0.00 1936 WC9-STR-9840 OUTAGE Stringing: Wc-269 - Wc-268 0%2.00 0.00 2.00 26-Oct-24 29-Oct-24 0.35 26-Oct-24 29-Oct-24 0.00 1937 AF CrewAF CrewAF Crew 14.00 0.00 14.00 26-Aug-24 11-Sep-24 2.08 26-Aug-24 11-Sep-24 0.00 1938 WC8-STR-8800 Stringing: Wc-208 - Wc-232 0%7.00 0.00 7.00 26-Aug-24 03-Sep-24 2.08 26-Aug-24 03-Sep-24 0.00 1939 WC8-STR-8810 Stringing: Wc-232 - Wc-254/255 0%7.00 0.00 7.00 03-Sep-24 11-Sep-24 2.08 03-Sep-24 11-Sep-24 0.00 1940 DELETED PULLS DELETED PULLS DUE TO NEW PULL PLAN MAR 25, 2024DELETED PULLS DUE TO NEW PULL PLAN MAR 25, 2024 0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1941 WC1-STR-1710 Conductor Stringing Pull 19c: Wc-153 - Wc-171 DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1942 WC6-STR-6810 Conductor Stringing Pull 2c: Wc-1 - Wc-2 DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1943 WC6-STR-6820 Stringing: Wc-2 - Wc-13 (Req. daily outages on 230kv: 1Wc00b, distroWC01A, distroWC01b DELETE NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1944 WC6-STR-6840 Stringing: Wc-32 - Wc-43 DELETE NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1945 WC6-STR-6870 Conductor Stringing Pull 8c: Wc-49B - Amassa Sub DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1946 WC7-STR-7800 Conductor Stringing Pull 9c: Amassa #2 - Wc-49C DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1947 WC7-STR-7840 Conductor Stringing Pull 13c: Wc-88 - Wc-93 (Req. daily outages on distro1w14a) DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1948 WC8-STR-8820 Stringing: Wc-244 - Wc-254 DELETE - NEW PULL PLAN 100%0.00 0.00 0.00 01-Mar-24 A 01-Mar-24 A 01-Mar-24 01-Mar-24 0.00 1949 Outage: Amasa SubOutage: Amasa Substaiton Tie-in Amasa - HewardOutage: Amasa Substaiton Tie-in Amasa - Heward 5.55 0.00 5.55 13-Sep-24 19-Sep-24 0.33 13-Sep-24 19-Sep-24 0.00 1950 DJ - Amasa (Wc1-WDJ - Amasa (Wc1-Wc49b)DJ - Amasa (Wc1-Wc49b)5.55 0.00 5.55 13-Sep-24 19-Sep-24 0.33 13-Sep-24 19-Sep-24 0.00 1951 Structure SalvageStructure SalvageStructure Salvage 0.90 0.00 0.90 13-Sep-24 14-Sep-24 1.58 13-Sep-24 14-Sep-24 0.00 1952 WC6-OUT-6355 Outage Start *constraint to hold scheduled start 0%0.00 0.00 0.00 13-Sep-24 0.33 13-Sep-24 0.00 1953 WC6-SLV-6990 Salvage Structure: Wc-49 Golden Eagle Nest 0%0.15 0.00 0.15 13-Sep-24 13-Sep-24 0.33 13-Sep-24 13-Sep-24 0.00 1954 WC6-SLV-6980 Salvage Structure: Wc-49A Golden Eagle Nest 0%0.15 0.00 0.15 13-Sep-24 13-Sep-24 0.38 13-Sep-24 13-Sep-24 0.00 1955 WC6-SLV-7000 Salvage Structure: Wc-49B Golden Eagle Nest 0%0.15 0.00 0.15 13-Sep-24 13-Sep-24 0.43 13-Sep-24 13-Sep-24 0.00 1956 WC7-SLV-7000 Salvage Structure: Wc-49C Golden Eagle Nest 0%0.15 0.00 0.15 13-Sep-24 14-Sep-24 2.48 13-Sep-24 14-Sep-24 0.00 1957 Crew 2 Salvage Structure: Wc-49D Golden Eagle Nest 0%0.15 0.00 0.15 14-Sep-24 14-Sep-24 2.53 14-Sep-24 14-Sep-24 0.00 1958 WC7-SLV-7010 Salvage Structure: Wc-50 Golden Eagle Nest 0%0.15 0.00 0.15 14-Sep-24 14-Sep-24 1.58 14-Sep-24 14-Sep-24 0.00 1959 Structure FramingStructure FramingStructure Framing 1.20 0.00 1.20 13-Sep-24 14-Sep-24 1.33 13-Sep-24 14-Sep-24 0.00 1960 WC6-FRM-7010 Frame Structure: Wc-49 Golden Eagle Nest 0%0.20 0.00 0.20 13-Sep-24 13-Sep-24 0.33 13-Sep-24 13-Sep-24 0.00 1961 WC6-FRM-6310 Frame Structure: Wc-49A Golden Eagle Nest 0%0.20 0.00 0.20 13-Sep-24 13-Sep-24 0.33 13-Sep-24 13-Sep-24 0.00 1962 WC6-FRM-7020 Frame Structure: Wc-49B Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 0.33 14-Sep-24 14-Sep-24 0.00 1963 WC7-FRM-7022 Frame Structure: Wc-49C Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 2.33 14-Sep-24 14-Sep-24 0.00 1964 WC7-FRM-7490 Frame Structure: Wc-49D Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 2.33 14-Sep-24 14-Sep-24 0.00 1965 WC7-FRM-7500 Frame Structure: Wc-50 Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 1.33 14-Sep-24 14-Sep-24 0.00 1966 Structure SettingStructure SettingStructure Setting 1.20 0.00 1.20 13-Sep-24 14-Sep-24 1.33 13-Sep-24 14-Sep-24 0.00 1967 WC6-SET-7030 Set Structure: Wc-49 Golden Eagle Nest 0%0.20 0.00 0.20 13-Sep-24 13-Sep-24 0.33 13-Sep-24 13-Sep-24 0.00 1968 WC6-SET-6950 Set Structure: Wc-49A Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 0.33 14-Sep-24 14-Sep-24 0.00 1969 WC6-SET-7040 Set Structure: Wc-49B Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 0.33 14-Sep-24 14-Sep-24 0.00 1970 WC7-SET-7510 Set Structure: Wc-49C Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 2.33 14-Sep-24 14-Sep-24 0.00 1971 WC7-SET-8110 Set Structure: Wc-49D Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 2.33 14-Sep-24 14-Sep-24 0.00 1972 WC7-SET-8100 Set Structure: Wc-50 Golden Eagle Nest 0%0.20 0.00 0.20 14-Sep-24 14-Sep-24 1.33 14-Sep-24 14-Sep-24 0.00 1973 StringingStringingStringing 5.60 0.00 5.60 14-Sep-24 19-Sep-24 0.33 14-Sep-24 19-Sep-24 0.00 1974 WC6-STR-6860 Stringing Wc-49 - Wc-49B (Req. daily outages on distrowc06a)0%2.60 0.00 2.60 14-Sep-24 16-Sep-24 0.33 14-Sep-24 16-Sep-24 0.00 1975 WC7-STR-7810 Stringing: Wc-49C - Wc-54 0%3.00 0.00 3.00 17-Sep-24 19-Sep-24 0.33 17-Sep-24 19-Sep-24 0.00 1976 WC7-OUT-7815 Outage Finish 0%0.00 0.00 0.00 19-Sep-24 0.33 19-Sep-24 0.00 1977 Construction CompConstruction Completion: Clients Elements 1 (Wc-149 - Wc-208)Construction Completion: Clients Elements 1 (Wc-149 - Wc-208)37.00 0.00 37.00 12-Aug-24 25-Sep-24 67.80 12-Aug-24 25-Sep-24 0.00 1978 WC1-FIN-1900 FBT Schedule Contigency *ALL 100d contingency removed*0%0.00 0.00 0.00 12-Aug-24 12-Aug-24 26.94 12-Aug-24 12-Aug-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 OUTAGE - Temp 20 Tie-in (Wa205) (begin Wc208-Wc267, Energize Wa205-Wa265), 30-Jul-24 Stringing: Wc-195 -Wc-208, 12-Aug-24 Stringing: Wc-171 - Wc-180, 23-Aug-24 Stringing: Wc-180 - Wc-195, 03-Sep-24 Stringing: Wc-254 - Wc-267/ Heward #1 (Req. daily outages on 1WC45a), 13-Sep-24 Stringing: Wc-268 - Wc-286/287 --, 23-Sep-24 Stringing: Wc-286/287 - Wc-306, 02-Oct-24 Stringing: Wc-306 - Wc-325/326, 10-Oct-24 Stringing: Wc-325/326 - Wc-2/177A, 18-Oct-24 Stringing: Wc-2/177A - Shirley Basin #1, 26-Oct-24 OUTAGE Stringing: Wc-269 - Wc-268, 29-Oct-24 11-Sep-24, AF Crew Stringing: Wc-208 - Wc-232, 03-Sep-24 Stringing: Wc-232 - Wc-254/255, 11-Sep-24 24 A, DELETED PULL S DUE TO NEW PULL PLAN MAR 25, 2024 19-Sep-24, Outage: Amasa Substaiton Tie-in Amasa - Heward 19-Sep-24, DJ - Amasa (Wc1-Wc49b) 14-Sep-24, Structure Salvage Outage Start *constraint to hold scheduled start, Salvage Structure: Wc-49 Golden Eagle Nest, 13-Sep-24 Salvage Structure: Wc-49A Golden Eagle Nest, 13-Sep-24 Salvage Structure: Wc-49B Golden Eagle Nest, 13-Sep-24 Salvage Structure: Wc-49C Golden Eagle Nest, 14-Sep-24 Salvage Structure: Wc-49D Golden Eagle Nest, 14-Sep-24 Salvage Structure: Wc-50 Golden Eagle Nest, 14-Sep-24 14-Sep-24, Structure Framing Frame Structure: Wc-49 Golden Eagle Nest, 13-Sep-24 Frame Structure: Wc-49A Golden Eagle Nest, 13-Sep-24 Frame Structure: Wc-49B Golden Eagle Nest, 14-Sep-24 Frame Structure: Wc-49C Golden Eagle Nest, 14-Sep-24 Frame Structure: Wc-49D Golden Eagle Nest, 14-Sep-24 Frame Structure: Wc-50 Golden Eagle Nest, 14-Sep-24 14-Sep-24, Structure Setting Set Structure: Wc-49 Golden Eagle Nest, 13-Sep-24 Set Structure: Wc-49A Golden Eagle Nest, 14-Sep-24 Set Structure: Wc-49B Golden Eagle Nest, 14-Sep-24 Set Structure: Wc-49C Golden Eagle Nest, 14-Sep-24 Set Structure: Wc-49D Golden Eagle Nest, 14-Sep-24 Set Structure: Wc-50 Golden Eagle Nest, 14-Sep-24 19-Sep-24, Stringing Stringing Wc-49 - Wc-49B (Req. daily outages on distrowc06a), 16-Sep-24 Stringing: Wc-49C - Wc-54, 19-Sep-24 Outage Finish, 19-Sep-24 25-Sep-24, Construction Completion: Clients Elements 1 (Wc-149 - Wc-208) FBT Schedule Contigency *ALL 100d contingency removed*, 12-Aug-24 Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 37 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved #Activity ID Activity Name Physical % Complete Original Duration Actual Duration Remaining Duration Start Finish Total Float BL Project Start BL Project Finish Variance - BL Project Finish Date 1979 WC1-FIN-1910 Construction Completion 0%0.00 0.00 0.00 12-Aug-24 26.94 12-Aug-24 0.00 1980 WC1-FIN-1950 Mechanical Completion (Required: Nov 10, 2023)0%0.00 0.00 0.00 20-Aug-24 26.94 20-Aug-24 0.00 1981 WC1-FIN-1920 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW) *Actual date TBD*0%7.00 0.00 7.00 12-Aug-24 20-Aug-24 26.94 12-Aug-24 20-Aug-24 0.00 1982 WC1-FIN-1930 Contractor Testing Complete 0%0.00 0.00 0.00 20-Aug-24 26.94 20-Aug-24 0.00 1983 WC1-FIN-1940 Punch List Items 0%7.00 0.00 7.00 12-Aug-24 20-Aug-24 26.94 12-Aug-24 20-Aug-24 0.00 1984 WC1-FIN-1970 As Built Submittal 0%30.00 0.00 30.00 20-Aug-24 25-Sep-24 67.80 20-Aug-24 25-Sep-24 0.00 1985 WC1-FIN-1980 Substantial Completion - (Clients Elements: 1 - Section 1) (Required: Dec 15, 2023 - updated to March 28, 2024) 0%0.00 0.00 0.00 25-Sep-24 67.80 25-Sep-24 0.00 1986 WC1-FIN-1960 Close Out Deliverables (Permits, Manuals Training aids, etc)0%30.00 0.00 30.00 20-Aug-24 25-Sep-24 67.80 20-Aug-24 25-Sep-24 0.00 1987 Construction ComplConstruction Completion: Clients Element 4, 6, 7 (Wc-1 - Wc2/177/A)Construction Completion: Clients Element 4, 6, 7 (Wc-1 - Wc2/177/A)35.55 0.00 35.55 17-Oct-24 30-Nov-24 0.00 17-Oct-24 30-Nov-24 0.00 1988 WCA-FIN-0500 FBT Schedule Contigency *built in*0%0.00 0.00 0.00 29-Oct-24 29-Oct-24 0.35 29-Oct-24 29-Oct-24 0.00 1989 WCA-FIN-0510 Construction Completion 0%0.00 0.00 0.00 29-Oct-24 0.35 29-Oct-24 0.00 1990 WCA-FIN-0520 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW)0%20.00 0.00 20.00 17-Oct-24 09-Nov-24 9.55 17-Oct-24 09-Nov-24 0.00 1991 WCA-FIN-0530 Contractor Testing Complete 0%0.00 0.00 0.00 09-Nov-24 9.55 09-Nov-24 0.00 1992 WCA-FIN-0550 Mechanical Completion (Required: Oct 7, 2024 - updated to Oct 14, 2024)0%0.00 0.00 0.00 20-Nov-24 0.35 20-Nov-24 0.00 1993 WCA-FIN-0540 Punch List Items 0%19.20 0.00 19.20 29-Oct-24 20-Nov-24 0.35 29-Oct-24 20-Nov-24 0.00 1994 WCA-FIN-0570 As Built Submittal *down from 45d*0%32.00 0.00 32.00 29-Oct-24 30-Nov-24 0.55 29-Oct-24 30-Nov-24 0.00 1995 WCA-FIN-0580 Substantial Completion - ISD 0%0.00 0.00 0.00 30-Nov-24 0.55 30-Nov-24 0.00 1996 WCA-FIN-0560 Close Out Deliverables (Permits, Manuals Training aids, etc)*reduced from 30d*0%32.00 0.00 32.00 29-Oct-24 30-Nov-24 0.55 29-Oct-24 30-Nov-24 0.00 1997 WCA-FIN-0554 Final Site Cleanup and Demob *reduced from 30d*0%32.00 0.00 32.00 29-Oct-24 30-Nov-24 0.55 29-Oct-24 30-Nov-24 0.00 1998 Wc Reclamation WoWc Reclamation WorkWc Reclamation Work 0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 A 01-Apr-24 01-Apr-24 0.00 1999 WCA-FIN-0552 Final Reclamation and Restorations - DELETE - New Sequencing 100%0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 A 01-Apr-24 01-Apr-24 0.00 2000 WCA-FIN-0553 Final Reclamation and Restorations - DELETE - New Sequencing 100%0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 A 01-Apr-24 01-Apr-24 0.00 2001 WCA-FIN-0563 Final Seeding (Activity 1/2) - DELETE - New Sequencing 100%0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 A 01-Apr-24 01-Apr-24 0.00 2002 WCA-FIN-5073 Final Seeding (Activity 2/2) - DELETE - New Sequencing 100%0.00 0.00 0.00 01-Apr-24 A 01-Apr-24 A 01-Apr-24 01-Apr-24 0.00 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2024 2025 2026 Construction Completion, 12-Aug-24 Mechanical Completion (Required: Nov 10, 2023), 20-Aug-24 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW) *Actual date TBD*, 20-Aug-24 Contractor Testing Complete, 20-Aug-24 Punch List Items, 20-Aug-24 As Built Submittal, 25-Sep-24 Substantial Completion - (Clients Elements: 1 - Section 1) (Required: Dec 15, 2023 - u Close Out Deliverables (Permits, Manuals Training aids, etc), 25-Sep-24 30-Nov-24, Construction Completion: Clients Element 4, 6, 7 (Wc-1 - Wc2/1 FBT Schedule Contigency *built in*, 29-Oct-24 Construction Completion, 29-Oct-24 Contractor Testing (X-Ray on IMPLOS, OTDR on OPGW), 09-Nov-24 Contractor Testing Complete, 09-Nov-24 Mechanical Completion (Required: Oct 7, 2024 - updated to Oct 14, 2024), 2 Punch List Items, 20-Nov-24 As Built Submittal *down from 45d*, 30-Nov-24 Substantial Completion - ISD, 30-Nov-24 Close Out Deliverables (Permits, Manuals Training aids, etc)*reduced from 3 Final Site Cleanup and Demob *reduced from 30d*, 30-Nov-24 -Apr-24 A, Wc Reclamation Work Gateway West Project - Current Schedule (Expanded) Data Date: 01-Jul-24 Submission Date: 02-Jul-24 Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Primary Baseline Baseline Milesto... 38 of 38 TASK filter: All Activities UserID: ldirks@forbesbrosltd.ca Date Revision Checked Approved