HomeMy WebLinkAbout20240829PAC to Staff 132-2 - 132(c) - c.v.2 GWWD1 BL Slips in Schedule.pdfProject Schedule Analysis Report PC Form Oct 2020 / Rev 0 Schedule Report 1 Gateway West D.1 Project Baseline Schedule Update Current Schedule Data Date: July 31, 2024 Project Schedule Analysis Report PC Form Oct 2020 / Rev 0 Schedule Report 2 MILESTONE SUMMARY Contract Milestones: Phasing Completion Dates: NA COMMENTS (Comment on the status of any Milestone Changes and detail the reason for the Changes) 1. Initial Project delays occurred at the start of the project; September 2021 – October 2021 a. Bureau of Land Management would not release Right of Way pending final decisions within agency. b. This delay a critical phase of mountain work that created a 1 year delay due to environmental restrictions. 2. Severe weather conditions over November 2022 – February 2023 added further delays to the project. 3. Contractor’s failure on many levels of management to react to each of the items referenced in items 1 & 2 above, created additional contractor delays. 4. Material deliveries that were the responsibility of the Owner, did add to some delays based on critical activities. 5. Schedule was re-figured to apply some common understanding and recovery management. Activity ID Milestones Baseline 1 Schedule (Date) Previous Schedule (Date) Current Schedule (Date) ALL-MS-0240 Final Project Completion 10/31/2024 09/09/2025 ALL-FIN-560 Mechanical Completion 08/28/2024 12/05/2024 ALL-FIN-580 Substantial Completion 10/30/2024 12/15/2024 ALL-FIN-500 Construction Completion 08/07/2024 NA Activity ID Milestones Baseline 1 Schedule Previous Schedule Current Schedule ALL-MS-0400 Mechanical Completion (1Wa) 12/05/2024 ALL-MS-0410 Substantial Completion (1Wa) 12/15/2024 ALL-MS-0420 Mechanical Completion (1Wc) 11/20/2024 ALL-MS-0430 Substantial Completion (1Wc) 11/30/2024 ALL-MS-0440 Mechanical Completion (AF) 08/20/2024 ALL-MS-0450 Substantial Completion (AF) 08/30/2024