20240829PAC to Staff 132-2 - 132(c) - c.v.1 GWW D1 Tline BL App.pdf
Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments GWW D.1 Project Baseline_ApprovedGWW D.1 Project Baseline_Approved 696d 696d 20-Jul-22 31-Oct-24 0d Exhibit I: Owner MilestonesExhibit I: Owner Milestones 49d 49d 20-Jul-22 15-Sep-22 293d ALL-MS-0100 Effective Date of Release No. 1 0d 0d 20-Jul-22*0d ALL-MS-0110 Full Notice to Proceed 0d 0d 15-Sep-22*7d ALL-MS-0120 Owner Provided Approval for Project Site & Equipment Mobilization0d0d 01-Sep-22*0d ALL-MS-0130 ROW Access Provided for Survey, Staking & Planning0d 0d 15-Aug-22 10d ALL-MS-0140 ROW Access Provided for Construction: Element 1 - Windstar to Shirley Basin (Section 2,3+4)0d 0d 15-Sep-22 7d ALL-MS-0150 ROW Access Provided for Construction: Element 2 - Dave Johnson - Amassa (Section 6)0d 0d 15-Sep-22 293d ALL-MS-0160 ROW Access Provided for Construction: Element 2: Amassa - Shirley Basin (Section 1,7,8,+9)0d 0d 15-Sep-22 79d ALL-MS-0170 ROW Access Provided for Construction: Element 3: Aeolus Freezeout (Section 5)0d 0d 15-Sep-22 283d Exhibit G.1.1 Critical & Interim MilestonesExhibit G.1.1 Critical & Interim Milestones 696d 696d 20-Jul-22 31-Oct-24 0d Critical MilestonesCritical Milestones 696d 696d 20-Jul-22 31-Oct-24 0d Overall ProjectOverall Project 696d 696d 20-Jul-22 31-Oct-24 0d ALL-MS-0220 Site Mobilization (Access)0d 0d 15-Sep-22 7d ALL-MS-0240 Final Project Completion Date 0d 0d 31-Oct-24*0d ALL-MS-0200 Contract Execution 0d 0d 20-Jul-22 12d ALL-MS-0210 Baseline Schedule Approved 0d 0d 03-Sep-22 17d Element 2 - 1WcElement 2 - 1Wc 0d 0d 0d Element 1 - 1WaElement 1 - 1Wa 0d 0d 0d Element 3 - Aeolus to FreezeoutElement 3 - Aeolus to Freezeout 0d 0d 0d Interim MilestonesInterim Milestones 36d 36d 29-Jul-22 09-Sep-22 12d Overall ProjectOverall Project 36d 36d 29-Jul-22 09-Sep-22 12d ALL-MS-0300 Limited Notice to Proceed 0d 0d 12-Aug-22 2d ALL-MS-0310 Letter of Credit 0d 0d 29-Jul-22 14d ALL-MS-0320 Baseline Schedule for Initial Submission for Approval0d 0d 20-Aug-22 17d ALL-MS-0330 Issue QA/QC Plan 0d 0d 09-Sep-22 12d ALL-MS-0340 Issue Safety Plan 0d 0d 12-Aug-22 36d ALL-MS-0350 Issue Environmental Assurance Plan 0d 0d 09-Sep-22 12d 1Wc1Wc 0d 0d 0d 1Wa1Wa 0d 0d 0d Aeolus - FreezeoutAeolus - Freezeout 0d 0d 0d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 15-Sep-22, Exhibit I: Owner Milestones Effective Date of Release No. 1 Full Notice to Proceed Owner Provided Approval for Project Site & Equipment Mobilization ROW Access Provided for Survey, Staking & Planning ROW Access Provided for Construction: Element 1 - Windstar to Shirley Basin (Section 2,3+4) ROW Access Provided for Construction: Element 2 - Dave Johnson - Amassa (Section 6) ROW Access Provided for Construction: Element 2: Amassa - Shirley Basin (Section 1,7,8,+9) ROW Access Provided for Construction: Element 3: Aeolus Freezeout (Section 5) Site Mobilization (Access) Contract Execution Baseline Schedule Approved 09-Sep-22, Interim Milestones 09-Sep-22, Overall Project Limited Notice to Proceed Letter of Credit Baseline Schedule for Initial Submission for Approval Issue QA/QC Plan Issue Safety Plan Issue Environmental Assurance Plan GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 1 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments Critical Milestones + Summary Activities (Manpower & Resource Loaded)Critical Milestones + Summary Activities (Manpower & Resource Loaded)654d 654d 20-Jul-22 11-Sep-24 42d ALL-SUM-1050 Evironmental / SWPPP Controls / BMP / Road Mainenance / Watering602d602d15-Aug-22 07-Aug-24 0d ALL-SUM-1000 Project Management / Overhead 602d 602d 15-Aug-22 07-Aug-24 0d Element 2 Summary- 1WcElement 2 Summary- 1Wc 654d 654d 20-Jul-22 11-Sep-24 42d EL2-SUM-1100 Engineering and Design Procurement Support Summary27d27d 20-Jul-22 19-Aug-22 81d EL2-SUM-9000 Element 2 - Mobilization Payment (80%)28d 28d 15-Aug-22 15-Sep-22 646d EL2-SUM-9010 Element 2 - Mobilization (20%) (to start of last mobilization WC9 Oct 5, 2023)347d 347d 15-Aug-22 04-Oct-23 327d (1) 1Wc-148 to 1Wc-209(1) 1Wc-148 to 1Wc-209 212d 212d 15-Aug-22 29-Apr-23 196d MilestonesMilestones 185d 185d 15-Sep-22 29-Apr-23 196d WC1-MS-1000 1 Wc-149 to 1Wc-208 Start 0d 0d 15-Sep-22 79d WC1-MS-1010 1 Wc-149 to 1Wc-208 Foundation Completion0d 0d 28-Oct-22 313d WC1-MS-1030 1 Wc-149 to 1Wc-208 Mechanical Completion (Req. Nov 10, 2023)0d 0d 25-Mar-23*196d WC1-MS-1040 1 Wc-149 to 1Wc-208 Substantial Completion (Req. Dec 15, 2023)0d 0d 29-Apr-23*196d SummarySummary 212d 212d 15-Aug-22 29-Apr-23 196d WC1-SUM-1125 Direct Embed Foundations Summary (2 person crew)22d 22d 01-Oct-22 26-Oct-22 130d WC1-SUM-1130 Structure Framing Summary (5 person crew)19d 19d 01-Oct-22 22-Oct-22 306d WC1-SUM-1140 Structure Setting Crew (6 person crew)25d 25d 11-Oct-22 08-Nov-22 92d WC1-SUM-1180 Structure Salvage (16 person crew)7d 7d 18-Mar-23 25-Mar-23 196d WC1-SUM-1150 Structure Setting Crew (6 person crew)1d 1d 13-Mar-23 13-Mar-23 196d WC1-SUM-1160 Stringing Crew (29 person crew)24d 24d 01-Nov-22 01-Dec-22 79d WC1-SUM-1170 Stringing Crew for Cut In (29 person crew)5d 5d 13-Mar-23 17-Mar-23 196d WC1-SUM-1120 Access Summary (1x29-person crew)21d 21d 15-Sep-22 08-Oct-22 144d WC1-SUM-1126 Drilled Pier Foundations Summary (15 person crew)21d 21d 05-Oct-22 28-Oct-22 137d WC1-SUM-1110 Project Management / OH Summary 212d 212d 15-Aug-22 29-Apr-23 196d WC1-SUM-1105 Engineering and Design Project Support Summary212d 212d 15-Aug-22 29-Apr-23 196d (6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa)(6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa)418d 418d 20-Jul-22 30-Nov-23 278d MilestonesMilestones 186d 186d 28-Apr-23 30-Nov-23 278d WC6-MS-6000 1Wc: Dave Johnson to Amassa SS Construction Start0d 0d 28-Apr-23 110d WC6-MS-6010 1Wc: Dave Johnson to Amassa SS Foundation Completion0d0d 20-Sep-23 183d WC6-MS-6030 1Wc: Dave Johnson to Amassa SS Mechanical Completion (Req. October 7, 2024)0d 0d 26-Oct-23*152d WC6-MS-6040 1Wc: Dave Johnson to Amassa SS Substantial Completion (Req. October 31, 2024)0d 0d 30-Nov-23*278d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 11-Sep-24, Critical Milestones + Summary Activities (Manpower & Resource Loaded) 11-Sep-24, Element 2 Summary- 1Wc 29-Apr-23, (1) 1Wc-148 to 1Wc-209 29-Apr-23, Milestones 1 Wc-149 to 1Wc-208 Start 1 Wc-149 to 1Wc-208 Foundation Completion 1 Wc-149 to 1Wc-208 Mechanical Completion (Req. Nov 10, 2023) 1 Wc-149 to 1Wc-208 Substantial Completion (Req. Dec 15, 2023) 29-Apr-23, Summary 30-Nov-23, (6) 1Wc-1 (Dave Johnson) to 1Wc-49B (Amassa) 30-Nov-23, Milestones 1Wc: Dave Johnson to Amassa SS Construction Start 1Wc: Dave Johnson to Amassa SS Foundation Completion 1Wc: Dave Johnson to Amassa SS Mechanical Completion (Req. October 7, 2024) 1Wc: Dave Johnson to Amassa SS Substantial Completion (Req. October 31, 2024) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 2 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments SummarySummary 418d 418d 20-Jul-22 30-Nov-23 278d WC6-SUM-6130 Access Summary (1x8-person crews)8d 8d 28-Apr-23 06-May-23 278d WC6-SUM-6140 Direct Embed Foundations Summary (2 person crew)17d 17d 01-Sep-23 20-Sep-23 22d WC6-SUM-6160 Structure Framing Summary (5 person crew)15d 15d 02-Aug-23 18-Aug-23 50d WC6-SUM-6170 Structure Setting Crew (6 person crew)18d 18d 14-Sep-23 04-Oct-23 16d WC6-SUM-6190 Structure Salvage (16 person crew)7d 7d 11-May-23 18-May-23 110d WC6-SUM-6180 Stringing Crew (29 person crew)19d 19d 05-Oct-23 26-Oct-23 0d WC6-SUM-6150 Drilled Pier Foundations Summary (15 person crew)14d 14d 19-Jul-23 03-Aug-23 68d WC6-SUM-6100 Engineering and Design Procurement Support Summary27d27d 20-Jul-22 19-Aug-22 81d WC6-SUM-6120 Project Management / OH Summary 396d 396d 15-Aug-22 30-Nov-23 278d WC6-SUM-6110 Engineering and Design Project Support Summary396d 396d 15-Aug-22 30-Nov-23 278d (7) 1Wc-49B (Amassa) to 1Wc-148(7) 1Wc-49B (Amassa) to 1Wc-148 586d 586d 15-Aug-22 19-Jul-24 88d MilestonesMilestones 368d 368d 08-May-23 19-Jul-24 88d WC7-MS-7000 Amassa – 1 Wc 148 Construction Start 0d 0d 08-May-23 278d WC7-MS-7020 Amassa – 1 Wc 148 Foundation Completion 0d 0d 16-Nov-23 172d WC7-MS-7030 Amassa – 1 Wc 148 Mechanical Completion (Req. October 7, 2024)0d 0d 14-Jun-24*0d WC7-MS-7040 Amassa – 1 Wc 148 Substantial Completion (Req. October 31, 2024)0d 0d 19-Jul-24*88d SummarySummary 586d 586d 15-Aug-22 19-Jul-24 88d WC7-SUM-7130 Access Summary (1x8-person crews)27d 27d 08-May-23 07-Jun-23 284d WC7-SUM-7140 Direct Embed Foundations Summary (2 person crew)37d 37d 05-Oct-23 16-Nov-23 152d WC7-SUM-7160 Structure Framing Summary (5 person crew)29d 29d 05-Oct-23 07-Nov-23 168d WC7-SUM-7170 Structure Setting Crew (6 person crew)36d 36d 13-Oct-23 23-Nov-23 161d WC7-SUM-7190 Structure Salvage (16 person crew)18d 18d 19-May-23 08-Jun-23 305d WC7-SUM-7180 Stringing Crew (29 person crew)38d 38d 02-May-24 14-Jun-24 0d WC7-SUM-7150 Drilled Pier Foundations Summary (15 person crew)17d 17d 05-Oct-23 24-Oct-23 173d WC7-SUM-7120 Project Management / OH Summary 586d 586d 15-Aug-22 19-Jul-24 88d WC7-SUM-7110 Engineering and Design Project Support Summary586d 586d 15-Aug-22 19-Jul-24 88d (8) 1Wc-209 to1Wc-267 (Heward)(8) 1Wc-209 to1Wc-267 (Heward)605d 605d 15-Aug-22 10-Aug-24 69d MilestonesMilestones 360d 360d 08-Jun-23 10-Aug-24 69d WC8-MS-8030 Wc-209 to Heward Mechanical Completion (Req. October 7, 2024)0d 0d 06-Jul-24*0d WC8-MS-8040 Wc-209 to Heward Substantial Completion (Req. October 31, 2024)0d 0d 10-Aug-24*69d WC8-MS-8000 1Wc-209 - Heward Construction Start 0d 0d 08-Jun-23 284d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 30-Nov-23, Summary 19-Jul-24, (7) 1Wc-49B (Amassa) to 1Wc-148 19-Jul-24, Milestones Amassa – 1 Wc 148 Construction Start Amassa – 1 Wc 148 Foundation Completion Amassa – 1 Wc 148 Mechanical Completion (Req. October 7, 2024) Amassa – 1 Wc 148 Substantial Completion (Req. October 31, 2024) 19-Jul-24, Summary 10-Aug-24, (8) 1Wc-209 to1Wc-267 (Heward) 10-Aug-24, Milestones Wc-209 to Heward Mechanical Completion (Req. October 7, 2024) Wc-209 to Heward Substantial Completion (Req. October 31, 2024) 1Wc-209 - Heward Construction Start GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 3 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC8-MS-8010 1Wc-209 - Heward Foundation Completion 0d 0d 13-Dec-23 168d SummarySummary 605d 605d 15-Aug-22 10-Aug-24 69d WC8-SUM-8130 Access Summary (1x8-person crews)26d 26d 08-Jun-23 07-Jul-23 284d WC8-SUM-8140 Direct Embed Foundations Summary (2 person crew)23d 23d 17-Nov-23 13-Dec-23 152d WC8-SUM-8160 Structure Framing Summary (5 person crew)19d 19d 08-Nov-23 29-Nov-23 168d WC8-SUM-8170 Structure Setting Crew (6 person crew)22d 22d 25-Nov-23 20-Dec-23 156d WC8-SUM-8190 Structure Salvage (16 person crew)6d 6d 08-Jul-23 14-Jul-23 292d WC8-SUM-8180 Stringing Crew (29 person crew)19d 19d 15-Jun-24 06-Jul-24 0d WC8-SUM-8150 Drilled Pier Foundations Summary (15 person crew)6d 6d 25-Oct-23 31-Oct-23 197d WC8-SUM-8120 Project Management / OH Summary 605d 605d 15-Aug-22 10-Aug-24 69d WC8-SUM-8110 Engineering and Design Project Support Summary605d 605d 15-Aug-22 10-Aug-24 69d (9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin)(9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin)654d 654d 20-Jul-22 11-Sep-24 42d MilestonesMilestones 285d 285d 05-Oct-23 11-Sep-24 42d WC9-MS-9000 Heward SS to Shirley Basin SS Construction Start0d 0d 05-Oct-23 327d WC9-MS-9010 Heward SS to Shirley Basin SS Foundation Completion0d 0d 24-Jan-24 240d WC9-MS-9030 Heward SS to Shirley Basin SS Mechanical Completion (Req. October 7, 2024)0d 0d 07-Aug-24*0d WC9-MS-9040 Heward SS to Shirley Basin SS Substantial Completion (Req. October 31, 2024)0d 0d 11-Sep-24*42d SummarySummary 654d 654d 20-Jul-22 11-Sep-24 42d WC9-SUM-9130 Access Summary (1x8-person crews)21d 21d 05-Oct-23 28-Oct-23 232d WC9-SUM-9140 Direct Embed Foundations Summary (2 person crew)27d 27d 14-Dec-23 24-Jan-24 152d WC9-SUM-9160 Structure Framing Summary (5 person crew)22d 22d 30-Nov-23 04-Jan-24 169d WC9-SUM-9170 Structure Setting Crew (6 person crew)24d 24d 03-Jan-24 30-Jan-24 152d WC9-SUM-9190 Structure Salvage (16 person crew)12d 12d 10-Oct-23 23-Oct-23 311d WC9-SUM-9180 Stringing Crew (29 person crew)27d 27d 08-Jul-24 07-Aug-24 0d WC9-SUM-9150 Drilled Pier Foundations Summary (15 person crew)7d 7d 01-Nov-23 08-Nov-23 209d WC9-SUM-9100 Engineering and Design Procurement Support Summary27d27d 20-Jul-22 19-Aug-22 81d WC9-SUM-9120 Project Management / OH Summary 632d 632d 15-Aug-22 11-Sep-24 42d WC9-SUM-9110 Engineering and Design Project Support Summary632d 632d 15-Aug-22 11-Sep-24 42d Element 1 Summary - 1WaElement 1 Summary - 1Wa 399d 399d 20-Jul-22 08-Nov-23 297d EL1-SUM-9020 Element 1 - Mobilization (80%)0d 0d 15-Sep-22 647d EL1-SUM-9030 Element 1 - Mobilization (20%) (to start of last mobilization WA4 Dec 20, 2022)161d 161d 15-Sep-22 01-Apr-23 107d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 1Wc-209 - Heward Foundation Completion 10-Aug-24, Summary 11-Sep-24, (9) 1Wc-268 (Heward) - 1Wc-7/2 (Shirley Basin) 11-Sep-24, Milestones Heward SS to Shirley Basin SS Construction Start Heward SS to Shirley Basin SS Foundation Completion Heward SS to Shirley Basin SS Mechanical Completion (Req. October 7, 2024) Heward SS to Shirley Basin SS Substantial Completion (Req. October 31, 2024) 11-Sep-24, Summary 08-Nov-23, Element 1 Summary - 1Wa Element 1 - Mobilization (80%) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 4 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments EL1-SUM-9070 Engineering and Design Procurement Support Summary27d27d 20-Jul-22 19-Aug-22 73d (2) Wa-1 (Windstar) to 1Wa-54(2) Wa-1 (Windstar) to 1Wa-54 279d 279d 15-Aug-22 17-Jul-23 129d MilestonesMilestones 252d 252d 15-Sep-22 17-Jul-23 129d WA2-MS-2000 Windstar SS to 1 Wa 54 Start Construction 0d 0d 15-Sep-22 7d WA2-MS-2010 Windstar SS to 1 Wa 54 Foundation Completion0d 0d 23-Nov-22 291d WA2-MS-2030 Windstar SS to 1 Wa-54 Mechanical Completion (Req. Nov 10, 2023)0d 0d 12-Jun-23*129d WA2-MS-2040 Windstar SS to 1 Wa-54 Substantial Completion (Req. Dec 15, 2023)0d 0d 17-Jul-23*129d SummarySummary 279d 279d 15-Aug-22 17-Jul-23 129d WA2-SUM-2130 Access Summary (1x8-person crews)21d 21d 15-Sep-22 08-Oct-22 7d WA2-SUM-2140 Direct Embed Foundations Summary (2 person crew)17d 17d 27-Oct-22 15-Nov-22 130d WA2-SUM-2160 Structure Framing Summary (5 person crew)16d 16d 01-Oct-22 19-Oct-22 163d WA2-SUM-2170 Structure Setting Crew (6 person crew)26d 26d 03-Nov-22 06-Dec-22 140d WA2-SUM-2180 Stringing Crew (29 person crew)29d 29d 01-May-23 02-Jun-23 0d WA2-SUM-2150 Drilled Pier Foundations Summary (15 person crew)22d 22d 29-Oct-22 23-Nov-22 143d WA2-SUM-2120 Project Management / OH Summary 279d 279d 15-Aug-22 17-Jul-23 129d WA2-SUM-2110 Engineering and Design Project Support Summary279d 279d 15-Aug-22 17-Jul-23 129d (3) 1Wa-344 (Shirley Basin) to 1Wa-227(3) 1Wa-344 (Shirley Basin) to 1Wa-227 319d 319d 15-Aug-22 01-Sep-23 89d MilestonesMilestones 271d 271d 10-Oct-22 01-Sep-23 89d WA3-MS-3000 1Wa-344 - 1Wa-227 Construction Start 0d 0d 10-Oct-22 7d WA3-MS-3010 1Wa-344 - 1Wa-227 Foundation Completion 0d 0d 03-Jun-23 137d WA3-MS-3030 1 Wa-344 - 1 Wa-227 Mechanical Completion (Includes SB-TB Flats) (Req. Nov 10, 2023)0d 0d 28-Jul-23*89d WA3-MS-3040 1 Wa-344 - 1 Wa-227 Substantial Completion (Includes SB-TB Flats) (Req. Dec 15, 2023)0d 0d 01-Sep-23*89d SummarySummary 319d 319d 15-Aug-22 01-Sep-23 89d WA3-SUM-3103 Access Summary 1 (1x8-person crews)58d 58d 10-Oct-22 19-Dec-22 7d WA3-SUM-3104 Direct Embed Foundations 1 Summary (2 person crew)29d 29d 16-Nov-22 22-Dec-22 130d WA3-SUM-3106 Structure Framing Summary 1 (5 person crew)28d 28d 16-Nov-22 21-Dec-22 140d WA3-SUM-3108 Structure Setting Crew 1 (6 person crew)14d 14d 07-Dec-22 22-Dec-22 140d WA3-SUM-3109 Stringing Crew (29 person crew)48d 48d 03-Jun-23 28-Jul-23 0d WA3-SUM-3105 Drilled Pier Foundations 1 Summary (15 person crew)21d 21d 28-Nov-22 21-Dec-22 151d WA3-SUM-3102 Project Management / OH Summary 319d 319d 15-Aug-22 01-Sep-23 89d WA3-SUM-3101 Engineering and Design Project Support Summary319d 319d 15-Aug-22 01-Sep-23 89d (4) 1Wa-227 to 1Wa-55(4) 1Wa-227 to 1Wa-55 377d 377d 15-Aug-22 08-Nov-23 31d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 17-Jul-23, (2) Wa-1 (Windstar) to 1Wa-54 17-Jul-23, Milestones Windstar SS to 1 Wa 54 Start Construction Windstar SS to 1 Wa 54 Foundation Completion Windstar SS to 1 Wa-54 Mechanical Completion (Req. Nov 10, 2023) Windstar SS to 1 Wa-54 Substantial Completion (Req. Dec 15, 2023) 17-Jul-23, Summary 01-Sep-23, (3) 1Wa-344 (Shirley Basin) to 1Wa-227 01-Sep-23, Milestones 1Wa-344 - 1Wa-227 Construction Start 1Wa-344 - 1Wa-227 Foundation Completion 1 Wa-344 - 1 Wa-227 Mechanical Completion (Includes SB-TB Flats) (Req. Nov 10, 2023) 1 Wa-344 - 1 Wa-227 Substantial Completion (Includes SB-TB Flats) (Req. Dec 15, 2023) 01-Sep-23, Summary 08-Nov-23, (4) 1Wa-227 to 1Wa-55 GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 5 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments MilestonesMilestones 271d 271d 20-Dec-22 08-Nov-23 31d WA4-MS-4000 1 Wa-227 - 1 Wa-55 Construction Start 0d 0d 20-Dec-22 7d WA4-MS-4010 1 Wa-227 - 1 Wa-55 Foundation Completion 0d 0d 19-Aug-23 70d WA4-MS-4030 1 Wa-227 - 1 Wa-55 Mechanical Completion (Req. Nov 10, 2023)0d 0d 04-Oct-23*31d WA4-MS-4040 1 Wa-227 - 1 Wa-55 Substantial Completion (Req. Dec 15, 2023)0d 0d 08-Nov-23*31d SummarySummary 377d 377d 15-Aug-22 08-Nov-23 31d WA4-SUM-4103 Access Summary 2 (1x8-person crew)94d 94d 20-Dec-22 15-Apr-23 107d WA4-SUM-4104 Direct Embed Foundations 2 Summary (2 person crew)62d 62d 09-Jun-23 19-Aug-23 7d WA4-SUM-4106 Structure Framing Summary 2 (5 person crew)50d 50d 25-May-23 21-Jul-23 32d WA4-SUM-4107 Structure Setting Crew 2 (6 person crew)53d 53d 28-Jun-23 28-Aug-23 7d WA4-SUM-4108 Stringing Crew (29 person crew)58d 58d 29-Jul-23 04-Oct-23 0d WA4-SUM-4105 Drilled Pier Foundations 2 Summary (15 person crew)32d 32d 24-May-23 29-Jun-23 51d WA4-SUM-4102 Project Management / OH Summary 377d 377d 15-Aug-22 08-Nov-23 31d WA4-SUM-4101 Engineering and Design Project Support Summary377d 377d 15-Aug-22 08-Nov-23 31d Element 3 Summary- Aeolus to FreezeoutElement 3 Summary- Aeolus to Freezeout 390d 390d 20-Jul-22 28-Oct-23 306d EL3-SUM-9040 Element 3 - Mobilization (80%)0d 0d 15-Sep-22 647d EL3-SUM-9050 Element 3 - Mobilization (20%) (to start of last mobilization AF5 Apr 17, 2023)173d 173d 15-Sep-22 15-Apr-23 110d (5) AF-1 to AF-31(5) AF-1 to AF-31 390d 390d 20-Jul-22 28-Oct-23 1d MilestonesMilestones 168d 168d 17-Apr-23 28-Oct-23 1d AF5-MS-5000 Aeolus SS to Freezeout SS Construction Start0d 0d 17-Apr-23 110d AF5-MS-5020 Aeolus SS to Freezeout SS Foundation Completion0d 0d 31-Aug-23 38d AF5-MS-5030 Aeolus SS to Freezeout SS; Mechanical Completion (Req. October 15, 2023)0d 0d 14-Oct-23*0d AF5-MS-5040 Aeolus SS to Freezeout SS; Substantial Completion (Req. October 31, 2023)0d 0d 28-Oct-23*1d SummarySummary 390d 390d 20-Jul-22 28-Oct-23 1d AF5-SUM-5103 Access Summary (1x8-person crew)10d 10d 17-Apr-23 27-Apr-23 110d AF5-SUM-5104 Direct Embed Foundations Summary (2 person crew)10d 10d 21-Aug-23 31-Aug-23 12d AF5-SUM-5106 Structure Framing Summary (5 person crew)9d 9d 22-Jul-23 01-Aug-23 38d AF5-SUM-5107 Structure Setting Crew (6 person crew)14d 14d 29-Aug-23 13-Sep-23 7d AF5-SUM-5109 Structure Salvage (16 person crew)1d 1d 28-Apr-23 28-Apr-23 120d AF5-SUM-5108 Stringing Crew (29 person crew)13d 13d 30-Sep-23 14-Oct-23 0d AF5-SUM-5105 Drilled Pier Foundations Summary (15 person crew)16d 16d 30-Jun-23 18-Jul-23 55d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 08-Nov-23, Milestones 1 Wa-227 - 1 Wa-55 Construction Start 1 Wa-227 - 1 Wa-55 Foundation Completion 1 Wa-227 - 1 Wa-55 Mechanical Completion (Req. Nov 10, 2023) 1 Wa-227 - 1 Wa-55 Substantial Completion (Req. Dec 15, 2023) 08-Nov-23, Summary 28-Oct-23, Element 3 Summary- Aeolus to Freezeout Element 3 - Mobilization (80%) 28-Oct-23, (5) AF-1 to AF-31 28-Oct-23, Milestones Aeolus SS to Freezeout SS Construction Start Aeolus SS to Freezeout SS Foundation Completion Aeolus SS to Freezeout SS; Mechanical Completion (Req. October 15, 2023) Aeolus SS to Freezeout SS; Substantial Completion (Req. October 31, 2023) 28-Oct-23, Summary GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 6 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments AF5-SUM-5100 Engineering and Design Procurement Support Summary27d27d 20-Jul-22 19-Aug-22 204d AF5-SUM-5102 Project Management / OH Summary 368d 368d 15-Aug-22 28-Oct-23 1d AF5-SUM-5101 Engineering and Design Project Support Summary368d 368d 15-Aug-22 28-Oct-23 1d Material ProcurementMaterial Procurement 161d 161d 20-Jul-22 03-Feb-23 436d ALL-MAT-1240 Prepare & Submit Material RFQ's 5d 5d 20-Jul-22 25-Jul-22 73d ALL-MAT-1250 Quote Submission Period 10d 10d 26-Jul-22 05-Aug-22 73d ALL-MAT-1260 Evaluation of Quotes 5d 5d 06-Aug-22 11-Aug-22 73d ALL-MAT-1270 Award Suppliers (Place Orders & Enter Into Agreements) *Upon Signing of LNTP*8d 8d 12-Aug-22 19-Aug-22 85d EL1-MAT-1290 Element 1 - Insulators + Hardware Material Order Progress Payment (15% down)0d 0d 19-Aug-22 73d EL2-MAT-1280 Element 2 - Insulators + Hardware Material Order Progress Payment (15% down)0d 0d 19-Aug-22 81d EL3-MAT-1300 Element 3 - Insulators + Hardware Material Order Progress Payment (15% down)0d 0d 19-Aug-22 204d Material ReceiptMaterial Receipt 78d 78d 25-Oct-22 03-Feb-23 436d Priority Order 1Priority Order 1 40d 40d 25-Oct-22 03-Dec-22 106d WC1-MAT-1200 Priority Order 1 - Section WC1: Wc-149 to Wc-20840d 40d 25-Oct-22 03-Dec-22 106d Priority Order 2Priority Order 2 14d 14d 21-Jan-23 03-Feb-23 520d WA2-MAT-1220 Priority Order 2 - Section WA2: Wa-1 to Wa-54 **22 weeks14d14d 21-Jan-23 03-Feb-23 86d WA3-MAT-1230 Priority Order 2 - Section WA3: Wa-344 (SB) to Wa-22714d 14d 21-Jan-23 03-Feb-23 119d WA4-MAT-1240 Priority Order 2 - Section WA4: Wa-227 to Wa-5514d 14d 21-Jan-23 03-Feb-23 175d AF5-MAT-1250 Priority Order 2 - Section AF5: AF-1 to AF-31 14d 14d 21-Jan-23 03-Feb-23 238d WC6-MAT-1260 Priority Order 2 - Section WC6: Wc-1 (DJ) to Wc-49B (Amasa)14d 14d 21-Jan-23 03-Feb-23 243d WC7-MAT-1270 Priority Order 2 - Section WC7: Wc-49B (Amasa) to Wc-14914d14d 21-Jan-23 03-Feb-23 453d WC8-MAT-1280 Priority Order 2 - Section WC8: Wc-208 to Wc-267 (Heward)14d 14d 21-Jan-23 03-Feb-23 497d WC9-MAT-1290 Priority Order 2 - Section WC9: Wc-7/2 (SB) to Wc-268 (Heward14d14d 21-Jan-23 03-Feb-23 520d Priority Order 3Priority Order 3 0d 0d 0d Gateway West D1Gateway West D1 602d 602d 15-Aug-22 07-Aug-24 72d Pre-Construction ActivitiesPre-Construction Activities 602d 602d 15-Aug-22 07-Aug-24 0d Construction MobilizationConstruction Mobilization 72d 72d 15-Aug-22 05-Nov-22 0d ALL-PRE-3000 Pre-Construction Mobilization & Site Orientations72d 72d 15-Aug-22*05-Nov-22 0d Project SetupProject Setup 30d 30d 15-Aug-22 17-Sep-22 7d ALL-PRE-3010 Setup Project Infrastructure; offices, laydown yards, temp power, etc.30d 30d 15-Aug-22 17-Sep-22 7d Construction StakingConstruction Staking 162d 162d 18-Aug-22 06-Mar-23 105d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 03-Feb-23, Material Procurement Element 1 - Insulators + Hardware Material Order Progress Payment (15% down) Element 2 - Insulators + Hardware Material Order Progress Payment (15% down) Element 3 - Insulators + Hardware Material Order Progress Payment (15% down) 03-Feb-23, Material Receipt 03-Dec-22, Priority Order 1 03-Feb-23, Priority Order 2 07-Aug-24, Gateway West D1 07-Aug-24, Pre-Construction Activities 05-Nov-22, Construction Mobilization 17-Sep-22, Project Setup 06-Mar-23, Construction Staking GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 7 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments ALL-PRE-3020 Staking of Clearing and ROW Boundaries 24d 24d 18-Aug-22 14-Sep-22 7d ALL-PRE-3030 Initial Construction Layout, Confirmations and Rework150d 150d 01-Sep-22 06-Mar-23 105d Material ManagementMaterial Management 602d 602d 15-Aug-22 07-Aug-24 0d ALL-PRE-3040 Material Management (In Yard) 3 person crew602d 602d 15-Aug-22 07-Aug-24 0d Distribution of MaterialsDistribution of Materials 570d 570d 21-Sep-22 07-Aug-24 0d ALL-PRE-3050 Material Distribution Along ROW 570d 570d 21-Sep-22 07-Aug-24 0d (1) 1Wc-149 to 1Wc-208 (September 15, 2022 - March 1, 2023)(1) 1Wc-149 to 1Wc-208 (September 15, 2022 - March 1, 2023)155d 155d 15-Sep-22 25-Mar-23 196d Access Installation (2 Crews)Access Installation (2 Crews)21d 21d 15-Sep-22 08-Oct-22 144d WC1-ACS-1200 Access Installation Pull 18c: Wc-149 - Wc165 4d 4d 15-Sep-22 19-Sep-22 79d WC1-ACS-1210 Access Installation Pull 19c: Wc-165 - Wc-1803d 3d 20-Sep-22 22-Sep-22 105d WC1-ACS-1220 Access Installation Pull 20c: Wc-180 Wc-189A4d 4d 23-Sep-22 27-Sep-22 107d WC1-ACS-1230 Access Installation Pull 21c: Wc-189A - Wc2043d 3d 28-Sep-22 30-Sep-22 107d WC1-ACS-1240 Access Installation Pull 22c: Wc-204 - Wc208 4d 4d 01-Oct-22 05-Oct-22 118d WC1-ACS-1250 Access Installation Pull 23c: Cutover to Line 1Wa3d 3d 06-Oct-22 08-Oct-22 144d Direct Embed FoundationsDirect Embed Foundations 22d 22d 01-Oct-22 26-Oct-22 130d WC1-DEF-1300 Direct Embed Foundations Pull 18c: Wc-149 - Wc1656d 6d 01-Oct-22 07-Oct-22 86d WC1-DEF-1310 Direct Embed Foundations Pull 19c: Wc-165 - Wc-1805d 5d 08-Oct-22 13-Oct-22 92d WC1-DEF-1320 Direct Embed Foundations Pull 20c: Wc-180 Wc-189A3d 3d 14-Oct-22 17-Oct-22 93d WC1-DEF-1330 Direct Embed Foundations Pull 21c: Wc-189A - Wc2046d 6d 18-Oct-22 24-Oct-22 93d WC1-DEF-1340 Direct Embed Foundations Pull 22c: Wc-204 - Wc2081d 1d 25-Oct-22 25-Oct-22 102d WC1-DEF-1350 Direct Embed Foundations Pull 23c: Cutover to Line 1Wa1d1d 26-Oct-22 26-Oct-22 130d Drilled Pier FoundationsDrilled Pier Foundations 21d 21d 05-Oct-22 28-Oct-22 137d WC1-DPF-1400 Drilled Pier Foundations Pull 18c: Wc-149 - Wc1655d 5d 05-Oct-22 10-Oct-22 137d WC1-DPF-1410 Drilled Pier Foundations Pull 19c: Wc-165 - Wc-1805d 5d 11-Oct-22 15-Oct-22 137d WC1-DPF-1420 Drilled Pier Foundations Pull 20c: Wc-180 Wc-189A3d 3d 17-Oct-22 19-Oct-22 137d WC1-DPF-1430 Drilled Pier Foundations Pull 21c: Wc-189A - Wc2045d 5d 20-Oct-22 25-Oct-22 137d WC1-DPF-1440 Drilled Pier Foundations Pull 22c: Wc-204 - Wc2082d 2d 26-Oct-22 27-Oct-22 137d WC1-DPF-1450 Drilled Pier Foundations Pull 23c: Cutover to Line 1Wa1d 1d 28-Oct-22 28-Oct-22 137d Frame StructuresFrame Structures 19d 19d 01-Oct-22 22-Oct-22 306d WC1-FRM-1500 Frame Structures Pull 18c: Wc-149 - Wc165 5d 5d 01-Oct-22 06-Oct-22 79d WC1-FRM-1510 Frame Structures Pull 19c: Wc-165 - Wc-180 4d 4d 07-Oct-22 11-Oct-22 94d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 07-Aug-24, Material Management 07-Aug-24, Distribution of Materials 25-Mar-23, (1) 1Wc-149 to 1Wc-208 (September 15, 2022 - March 1, 2023) 08-Oct-22, Access Installation (2 Crews) 26-Oct-22, Direct Embed Foundations 28-Oct-22, Drilled Pier Foundations 22-Oct-22, Frame Structures GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 8 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC1-FRM-1520 Frame Structures Pull 20c: Wc-180 Wc-189A 3d 3d 12-Oct-22 14-Oct-22 96d WC1-FRM-1530 Frame Structures Pull 21c: Wc-189A - Wc204 5d 5d 15-Oct-22 20-Oct-22 96d WC1-FRM-1540 Frame Structures Pull 22c: Wc-204 - Wc208 1d 1d 21-Oct-22 21-Oct-22 105d WC1-FRM-1550 Frame Structures Pull 23c: Cutover to Line 1Wa1d 1d 22-Oct-22 22-Oct-22 306d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)122d 122d 11-Oct-22 13-Mar-23 196d WC1-SET-1600 Set Structures Pull 18c: Wc-149 - Wc165 6d 6d 11-Oct-22 17-Oct-22 79d WC1-SET-1610 Set Structures Pull 19c: Wc-165 - Wc-180 6d 6d 18-Oct-22 24-Oct-22 89d WC1-SET-1620 Set Structures Pull 20c: Wc-180 Wc-189A 4d 4d 25-Oct-22 28-Oct-22 89d WC1-SET-1630 Set Structures Pull 21c: Wc-189A - Wc204 7d 7d 29-Oct-22 05-Nov-22 89d WC1-SET-1640 Set Structures Pull 22c: Wc-204 - Wc208 2d 2d 07-Nov-22 08-Nov-22 92d WC1-SET-1660 Set Structures Pull 23c: Cutover to Line 1Wa (Outag e Dependent)1d 1d 13-Mar-23 13-Mar-23 196d WC1-SET-1650 *OUTAGE START*0d 0d 13-Mar-23*0d WC1-SET-1670 *OUTAGE COMPLETE*0d 0d 13-Mar-23 196d Wire StringingWire Stringing 108d 108d 01-Nov-22 17-Mar-23 196d WC1-STR-1700 Conductor Stringing Pull 18c: Wc-149 - Wc1655d 5d 01-Nov-22 05-Nov-22 79d WC1-STR-1710 Conductor Stringing Pull 19c: Wc-165 - Wc-1805d 5d 07-Nov-22 11-Nov-22 79d WC1-STR-1720 Conductor Stringing Pull 20c: Wc-180 Wc-189A5d 5d 12-Nov-22 17-Nov-22 79d WC1-STR-1730 Conductor Stringing Pull 21c: Wc-189A - Wc2045d 5d 18-Nov-22 23-Nov-22 79d WC1-STR-1740 Conductor Stringing Pull 22c: Wc-204 - Wc2084d 4d 28-Nov-22 01-Dec-22 79d WC1-STR-1760 Conductor Stringing Pull 23c: Cutover to Line 1Wa (Outage Dependent)4d 4d 14-Mar-23 17-Mar-23 196d WC1-STR-1750 *OUTAGE START*0d 0d 13-Mar-23*0d WC1-STR-1770 *OUTAGE COMPLETE*0d 0d 17-Mar-23 196d Structure SalvageStructure Salvage 7d 7d 18-Mar-23 25-Mar-23 196d WC1-SLV-1800 Structure Salvage Pull 22c: Wc-204 - Wc208 1d 1d 18-Mar-23 18-Mar-23 196d WC1-SLV-1820 Structure Salvage Pull 20c: Wc-180 Wc-189A1d 1d 22-Mar-23 22-Mar-23 196d WC1-SLV-1830 Structure Salvage Pull 19c: Wc-165 - Wc-180 1d 1d 23-Mar-23 23-Mar-23 196d WC1-SLV-1840 Structure Salvage Pull 18c: Wc-149 - Wc165 2d 2d 24-Mar-23 25-Mar-23 196d WC1-SLV-1810 Structure Salvage Pull 21c: Wc-189A - Wc-2042d 2d 20-Mar-23 21-Mar-23 196d (2) 1Wa-1 (Windstar) to 1Wa-54 (Finish by August 10, 2023)(2) 1Wa-1 (Windstar) to 1Wa-54 (Finish by August 10, 2023)222d 222d 15-Sep-22 12-Jun-23 129d Access Installation (2 Crews)Access Installation (2 Crews)21d 21d 15-Sep-22 08-Oct-22 7d WA2-ACS-2200 Access Installation Pull 1a: Windstar - Wa-1 3d 3d 15-Sep-22 17-Sep-22 7d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 13-Mar-23, Set Structures (Including 3-Pole Framing) *OUTAGE START* *OUTAGE COMPLETE* 17-Mar-23, Wire Stringing *OUTAGE START* *OUTAGE COMPLETE* 25-Mar-23, Structure Salvage 12-Jun-23, (2) 1Wa-1 (Windstar) to 1Wa-54 (Finish by August 10, 2023) 08-Oct-22, Access Installation (2 Crews) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 9 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA2-ACS-2210 Access Installation Pull 2a: Wa-1 - Wa-2 3d 3d 19-Sep-22 21-Sep-22 7d WA2-ACS-2220 Access Installation Pull 3a: Wa-2 - Wa-4 3d 3d 22-Sep-22 24-Sep-22 7d WA2-ACS-2230 Access Installation Pull 4a: Wa-4 - Wa-18 2d 2d 26-Sep-22 27-Sep-22 7d WA2-ACS-2240 Access Installation Pull 5a: Wa-18 - Wa-26 3d 3d 28-Sep-22 30-Sep-22 7d WA2-ACS-2250 Access Installation Pull 6a: Wa-26 - Wa-42 2d 2d 01-Oct-22 03-Oct-22 7d WA2-ACS-2260 Access Installation Pull 7a: Wa-42 - Wa-45 3d 3d 04-Oct-22 06-Oct-22 7d WA2-ACS-2270 Access Installation Pull 8a: Wa-45 - Wa-53A 2d 2d 07-Oct-22 08-Oct-22 7d Direct Embed FoundationsDirect Embed Foundations 17d 17d 27-Oct-22 15-Nov-22 130d WA2-DEF-2300 Direct Embed Foundations Pull 3a: Wa-2 - Wa-41d 1d 27-Oct-22 27-Oct-22 130d WA2-DEF-2310 Direct Embed Foundations Pull 4a: Wa-4 - Wa-184d 4d 28-Oct-22 01-Nov-22 130d WA2-DEF-2320 Direct Embed Foundations Pull 5a: Wa-18 - Wa-262d 2d 02-Nov-22 03-Nov-22 130d WA2-DEF-2330 Direct Embed Foundations Pull 6a: Wa-26 - Wa-426d 6d 04-Nov-22 10-Nov-22 130d WA2-DEF-2340 Direct Embed Foundations Pull 7a: Wa-42 - Wa-451d 1d 11-Nov-22 11-Nov-22 130d WA2-DEF-2350 Direct Embed Foundations Pull 8a: Wa-45 - Wa-53A3d 3d 12-Nov-22 15-Nov-22 130d Drilled Pier FoundationsDrilled Pier Foundations 22d 22d 29-Oct-22 23-Nov-22 143d WA2-DPF-2400 Drilled Pier Foundations Pull 1a: Windstar - Wa-11d 1d 29-Oct-22 29-Oct-22 137d WA2-DPF-2410 Drilled Pier Foundations Pull 2a: Wa-1 - Wa-2 2d 2d 31-Oct-22 01-Nov-22 137d WA2-DPF-2420 Drilled Pier Foundations Pull 3a: Wa-2 - Wa-4 2d 2d 02-Nov-22 03-Nov-22 137d WA2-DPF-2430 Drilled Pier Foundations Pull 4a: Wa-4 - Wa-185d 5d 04-Nov-22 09-Nov-22 137d WA2-DPF-2440 Drilled Pier Foundations Pull 5a: Wa-18 - Wa-265d 5d 10-Nov-22 15-Nov-22 139d WA2-DPF-2450 Drilled Pier Foundations Pull 6a: Wa-26 - Wa-422d 2d 16-Nov-22 17-Nov-22 141d WA2-DPF-2460 Drilled Pier Foundations Pull 7a: Wa-42 - Wa-452d 2d 18-Nov-22 19-Nov-22 143d WA2-DPF-2470 Drilled Pier Foundations Pull 8a: Wa-45 - Wa-53A3d 3d 21-Nov-22 23-Nov-22 143d Frame StructuresFrame Structures 16d 16d 01-Oct-22 19-Oct-22 163d WA2-FRM-2500 Frame Structures Pull 3a: Wa-2 - Wa-4 1d 1d 01-Oct-22 01-Oct-22 163d WA2-FRM-2510 Frame Structures Pull 4a: Wa-4 - Wa-18 4d 4d 03-Oct-22 06-Oct-22 163d WA2-FRM-2520 Frame Structures Pull 5a: Wa-18 - Wa-26 2d 2d 07-Oct-22 08-Oct-22 163d WA2-FRM-2530 Frame Structures Pull 6a: Wa-26 - Wa-42 5d 5d 10-Oct-22 14-Oct-22 163d WA2-FRM-2540 Frame Structures Pull 7a: Wa-42 - Wa-45 1d 1d 15-Oct-22 15-Oct-22 163d WA2-FRM-2550 Frame Structures Pull 8a: Wa-45 - Wa-53A 3d 3d 17-Oct-22 19-Oct-22 163d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)26d 26d 03-Nov-22 06-Dec-22 140d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 15-Nov-22, Direct Embed Foundations 23-Nov-22, Drilled Pier Foundations 19-Oct-22, Frame Structures 06-Dec-22, Set Structures (Including 3-Pole Framing) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 10 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA2-SET-2600 Set Structures Pull 1a: Windstar - Wa-1 1d 1d 03-Nov-22 03-Nov-22 140d WA2-SET-2610 Set Structures Pull 2a: Wa-1 - Wa-2 1d 1d 04-Nov-22 04-Nov-22 140d WA2-SET-2620 Set Structures Pull 3a: Wa-2 - Wa-4 1d 1d 05-Nov-22 05-Nov-22 140d WA2-SET-2630 Set Structures Pull 4a: Wa-4 - Wa-18 6d 6d 10-Nov-22 16-Nov-22 137d WA2-SET-2640 Set Structures Pull 5a: Wa-18 - Wa-26 4d 4d 17-Nov-22 21-Nov-22 138d WA2-SET-2650 Set Structures Pull 6a: Wa-26 - Wa-42 4d 4d 22-Nov-22 29-Nov-22 138d WA2-SET-2660 Set Structures Pull 7a: Wa-42 - Wa-45 2d 2d 30-Nov-22 01-Dec-22 140d WA2-SET-2670 Set Structures Pull 8a: Wa-45 - Wa-53A 4d 4d 02-Dec-22 06-Dec-22 140d Wire StringingWire Stringing 29d 29d 01-May-23 02-Jun-23 0d WA2-STR-2700 Conductor Stringing Pull 1a: Windstar - Wa-1 2d 2d 01-May-23*02-May-23 0d WA2-STR-2710 Conductor Stringing Pull 2a: Wa-1 - Wa-2 2d 2d 03-May-23 04-May-23 0d WA2-STR-2720 Conductor Stringing Pull 3a: Wa-2 - Wa-4 2d 2d 05-May-23 06-May-23 0d WA2-STR-2730 Conductor Stringing Pull 4a: Wa-4 - Wa-18 5d 5d 08-May-23 12-May-23 0d WA2-STR-2740 Conductor Stringing Pull 5a: Wa-18 - Wa-26 4d 4d 13-May-23 17-May-23 0d WA2-STR-2750 Conductor Stringing Pull 6a: Wa-26 - Wa-42 5d 5d 18-May-23 23-May-23 0d WA2-STR-2760 Conductor Stringing Pull 7a: Wa-42 - Wa-45 4d 4d 24-May-23 27-May-23 0d WA2-STR-2770 Conductor Stringing Pull 8a: Wa-45 - Wa-53A 5d 5d 29-May-23 02-Jun-23 0d Build Temporary Line & Cutover (Outage Required)Build Temporary Line & Cutover (Outage Required)8d 8d 03-Jun-23 12-Jun-23 129d WA2-TMP-2800 Build Temporary Line Pull 1T: Temp 01 - Temp 052d 2d 03-Jun-23 05-Jun-23 129d WA2-TMP-2810 Build Temporary Line Pull 2T: Temp 05 - Temp 112d 2d 06-Jun-23 07-Jun-23 129d WA2-TMP-2820 String Temporary Line Pull 1T: Temp 01 - Temp 052d 2d 08-Jun-23 09-Jun-23 129d WA2-TMP-2830 String Temporary Line Pull 2T: Temp 05 - Temp 11 (Including Cutover @ Temp 11)2d 2d 10-Jun-23 12-Jun-23 129d (3) 1Wa-344 (SB) to 1Wa-227 (Finish by November 10, 2023)(3) 1Wa-344 (SB) to 1Wa-227 (Finish by November 10, 2023)241d 241d 10-Oct-22 28-Jul-23 0d Access Installation (2 Crews)Access Installation (2 Crews)58d 58d 10-Oct-22 19-Dec-22 7d WA3-ACS-3290 Access Installation Pull 20a: Wa-227 - Wa-24913d 13d 05-Dec-22 19-Dec-22 7d WA3-ACS-3280 Access Installation Pull 21a: Wa-249 - Wa-26513d 13d 16-Nov-22 03-Dec-22 7d WA3-ACS-3270 Access Installation Pull 22a: Wa-265 - Wa-2724d 4d 11-Nov-22 15-Nov-22 7d WA3-ACS-3260 Access Installation Pull 23a: Wa-272 - Wa-2904d 4d 07-Nov-22 10-Nov-22 7d WA3-ACS-3250 Access Installation Pull 24a: Wa-290 - Wa-3074d 4d 02-Nov-22 05-Nov-22 7d WA3-ACS-3240 Access Installation Pull 25a: Wa-307 - Wa-3214d 4d 28-Oct-22 01-Nov-22 7d WA3-ACS-3230 Access Installation Pull 26a: Wa-321 - Wa-3294d 4d 24-Oct-22 27-Oct-22 7d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 02-Jun-23, Wire Stringing 12-Jun-23, Build Temporary Line & Cutover (Outage Required) 28-Jul-23, (3) 1Wa-344 (SB) to 1Wa-227 (Finish by November 10, 2023) 19-Dec-22, Access Installation (2 Crews) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 11 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA3-ACS-3220 Access Installation Pull 27a: Wa-329 - Wa-3404d 4d 19-Oct-22 22-Oct-22 7d WA3-ACS-3210 Access Installation Pull 28a: Wa-340 - Wa-3444d 4d 14-Oct-22 18-Oct-22 7d WA3-ACS-3200 Access Installation Pull 29a: Wa-344 - Shirley Basin #34d 4d 10-Oct-22 13-Oct-22 7d Direct Embed FoundationsDirect Embed Foundations 166d 166d 16-Nov-22 08-Jun-23 7d WA3-DEF-3380 Direct Embed Foundations Pull 20a: Wa-227 - Wa-2498d 8d 31-May-23 08-Jun-23 7d WA3-DEF-3370 Direct Embed Foundations Pull 21a: Wa-249 - Wa-265 *Remob*6d 6d 24-May-23*30-May-23 7d WA3-DEF-3360 Direct Embed Foundations Pull 22a: Wa-265 - Wa-272 *Demob*3d 3d 20-Dec-22 22-Dec-22 130d WA3-DEF-3350 Direct Embed Foundations Pull 23a: Wa-272 - Wa-2907d 7d 12-Dec-22 19-Dec-22 130d WA3-DEF-3340 Direct Embed Foundations Pull 24a: Wa-290 - Wa-3076d 6d 05-Dec-22 10-Dec-22 130d WA3-DEF-3330 Direct Embed Foundations Pull 25a: Wa-307 - Wa-3215d 5d 29-Nov-22 03-Dec-22 130d WA3-DEF-3320 Direct Embed Foundations Pull 26a: Wa-321 - Wa-3293d 3d 22-Nov-22 28-Nov-22 130d WA3-DEF-3310 Direct Embed Foundations Pull 27a: Wa-329 - Wa-3404d 4d 17-Nov-22 21-Nov-22 130d WA3-DEF-3300 Direct Embed Foundations Pull 28a: Wa-340 - Wa-3441d 1d 16-Nov-22 16-Nov-22 130d Drilled Pier FoundationsDrilled Pier Foundations 21d 21d 28-Nov-22 21-Dec-22 151d WA3-DPF-3470 Drilled Pier Foundations Pull 20a: Wa-227 - Wa-249 **Demob**2d 2d 20-Dec-22 21-Dec-22 151d WA3-DPF-3460 Drilled Pier Foundations Pull 21a: Wa-249 - Wa-2652d 2d 15-Dec-22 16-Dec-22 151d WA3-DPF-3450 Drilled Pier Foundations Pull 24a: Wa-290 - Wa-3076d 6d 08-Dec-22 14-Dec-22 143d WA3-DPF-3440 Drilled Pier Foundations Pull 25a: Wa-307 - Wa-3212d 2d 06-Dec-22 07-Dec-22 143d WA3-DPF-3430 Drilled Pier Foundations Pull 26a: Wa-321 - Wa-3292d 2d 03-Dec-22 05-Dec-22 143d WA3-DPF-3420 Drilled Pier Foundations Pull 27a: Wa-329 - Wa-3402d 2d 01-Dec-22 02-Dec-22 143d WA3-DPF-3410 Drilled Pier Foundations Pull 28a: Wa-340 - Wa-3442d 2d 29-Nov-22 30-Nov-22 143d WA3-DPF-3400 Drilled Pier Foundations Pull 29a: Wa-344 - Shirley Basin #31d1d 28-Nov-22 28-Nov-22 143d Frame StructuresFrame Structures 153d 153d 16-Nov-22 24-May-23 26d WA3-FRM-3580 Frame Structures Pull 20a: Wa-227 - Wa-249 **Remob**7d 7d 17-May-23 24-May-23 26d WA3-FRM-3570 Frame Structures Pull 21a: Wa-249 - Wa-265 **Demob**5d 5d 16-Dec-22 21-Dec-22 140d WA3-FRM-3560 Frame Structures Pull 22a: Wa-265 - Wa-272 2d 2d 14-Dec-22 15-Dec-22 140d WA3-FRM-3550 Frame Structures Pull 23a: Wa-272 - Wa-290 6d 6d 07-Dec-22 13-Dec-22 140d WA3-FRM-3540 Frame Structures Pull 24a: Wa-290 - Wa-307 5d 5d 01-Dec-22 06-Dec-22 140d WA3-FRM-3530 Frame Structures Pull 25a: Wa-307 - Wa-321 4d 4d 23-Nov-22 30-Nov-22 140d WA3-FRM-3520 Frame Structures Pull 26a: Wa-321 - Wa-329 2d 2d 21-Nov-22 22-Nov-22 140d WA3-FRM-3510 Frame Structures Pull 27a: Wa-329 - Wa-340 3d 3d 17-Nov-22 19-Nov-22 140d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 08-Jun-23, Direct Embed Foundations 21-Dec-22, Drilled Pier Foundations 24-May-23, Frame Structures GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 12 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA3-FRM-3500 Frame Structures Pull 28a: Wa-340 - Wa-344 1d 1d 16-Nov-22 16-Nov-22 140d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)167d 167d 07-Dec-22 27-Jun-23 3d WA3-SET-3690 Set Structures Pull 20a: Wa-227 - Wa-249 6d 6d 21-Jun-23 27-Jun-23 3d WA3-SET-3680 Set Structures Pull 21a: Wa-249 - Wa-265 4d 4d 16-Jun-23 20-Jun-23 3d WA3-SET-3670 Set Structures Pull 22a: Wa-265 - Wa-272 2d 2d 14-Jun-23 15-Jun-23 3d WA3-SET-3660 Set Structures Pull 23a: Wa-272 - Wa-290 **Remob**4d 4d 09-Jun-23*13-Jun-23 3d WA3-SET-3650 Set Structures Pull 24a: Wa-290 - Wa-307 **Demob**4d 4d 19-Dec-22 22-Dec-22 140d WA3-SET-3640 Set Structures Pull 25a: Wa-307 - Wa-321 4d 4d 14-Dec-22 17-Dec-22 140d WA3-SET-3630 Set Structures Pull 26a: Wa-321 - Wa-329 2d 2d 12-Dec-22 13-Dec-22 140d WA3-SET-3620 Set Structures Pull 27a: Wa-329 - Wa-340 2d 2d 09-Dec-22 10-Dec-22 140d WA3-SET-3610 Set Structures Pull 28a: Wa-340 - Wa-344 1d 1d 08-Dec-22 08-Dec-22 140d WA3-SET-3600 Set Structures Pull 29a: Wa-344 - Shirley Basin #31d 1d 07-Dec-22 07-Dec-22 140d Wire StringingWire Stringing 48d 48d 03-Jun-23 28-Jul-23 0d WA3-STR-3790 Conductor Stringing Pull 20a: Wa-227 - Wa-2496d 6d 22-Jul-23 28-Jul-23 0d WA3-STR-3780 Conductor Stringing Pull 21a: Wa-249 - Wa-2655d 5d 17-Jul-23 21-Jul-23 0d WA3-STR-3770 Conductor Stringing Pull 22a: Wa-265 - Wa-2724d 4d 12-Jul-23 15-Jul-23 0d WA3-STR-3760 Conductor Stringing Pull 23a: Wa-272 - Wa-2906d 6d 05-Jul-23 11-Jul-23 0d WA3-STR-3750 Conductor Stringing Pull 24a: Wa-290 - Wa-3076d 6d 28-Jun-23 04-Jul-23 0d WA3-STR-3740 Conductor Stringing Pull 25a: Wa-307 - Wa-3215d 5d 22-Jun-23 27-Jun-23 0d WA3-STR-3730 Conductor Stringing Pull 26a: Wa-321 - Wa-3295d 5d 16-Jun-23 21-Jun-23 0d WA3-STR-3720 Conductor Stringing Pull 27a: Wa-329 - Wa-3405d 5d 10-Jun-23 15-Jun-23 0d WA3-STR-3710 Conductor Stringing Pull 28a: Wa-340 - Wa-3444d 4d 06-Jun-23 09-Jun-23 0d WA3-STR-3700 Conductor Stringing Pull 29a: Wa-344 - Shirley Basi n #32d 2d 03-Jun-23 05-Jun-23 0d (4) 1Wa-228 to 1Wa-55 (Finish by November 10, 2023)(4) 1Wa-228 to 1Wa-55 (Finish by November 10, 2023)299d 299d 10-Oct-22 04-Oct-23 0d Access Installation (2 Crews)Access Installation (2 Crews)152d 152d 10-Oct-22 15-Apr-23 107d WA4-ACS-4250 Access Installation Pull 9a: Wa-53A - Wa-76 12d 12d 03-Apr-23 15-Apr-23 107d WA4-ACS-4245 Access Installation Pull 10a: Wa-77 - Wa-10012d 12d 20-Mar-23 01-Apr-23 107d WA4-ACS-4240 Access Installation Pull 11a: Wa-100 - Wa-10610d 10d 08-Mar-23 18-Mar-23 107d WA4-ACS-4235 Access Installation Pull 12a: Wa-106 - Wa-11912d 12d 22-Feb-23 07-Mar-23 107d WA4-ACS-4230 Access Installation Pull 13a: Wa-119 - Wa-13210d 10d 10-Feb-23 21-Feb-23 107d WA4-ACS-4225 Access Installation Pull 14a: Wa-132 - Wa-14312d 12d 27-Jan-23 09-Feb-23 107d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 27-Jun-23, Set Structures (Including 3-Pole Framing) 28-Jul-23, Wire Stringing 04-Oct-23, (4) 1Wa-228 to 1Wa-55 (Finish by November 10, 2023) 15-Apr-23, Access Installation (2 Crews) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 13 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA4-ACS-4220 Access Installation Pull 15a: Wa-143 - Wa-166*SUBCONTRACTOR* demob4d4d24-Oct-22 27-Oct-22 212d WA4-ACS-4215 Access Installation Pull 16a: Wa-166 - Wa-189*SUBCONTRACTOR*4d 4d 19-Oct-22 22-Oct-22 207d WA4-ACS-4210 Access Installation Pull 17a: Wa-189 - Wa-201*SUBCONTRACTOR*4d 4d 14-Oct-22 18-Oct-22 206d WA4-ACS-4205 Access Installation Pull 18a: Wa-201 - Wa-213 *SUBCONTRACTOR*4d 4d 10-Oct-22 13-Oct-22 206d WA4-ACS-4200 Access Installation Pull 19a: Wa-213 - Wa-22726d 26d 20-Dec-22 26-Jan-23 7d Direct Embed FoundationsDirect Embed Foundations 62d 62d 09-Jun-23 19-Aug-23 7d WA4-DEF-4350 Direct Embed Foundations Pull 9a: Wa-53A - Wa-768d 8d 11-Aug-23 19-Aug-23 7d WA4-DEF-4345 Direct Embed Foundations Pull 10a: Wa-77 - Wa-1008d 8d 02-Aug-23 10-Aug-23 7d WA4-DEF-4340 Direct Embed Foundations Pull 11a: Wa-100 - Wa-1062d 2d 31-Jul-23 01-Aug-23 7d WA4-DEF-4335 Direct Embed Foundations Pull 12a: Wa-106 - Wa-1194d 4d 26-Jul-23 29-Jul-23 7d WA4-DEF-4330 Direct Embed Foundations Pull 13a: Wa-119 - Wa-1325d 5d 20-Jul-23 25-Jul-23 7d WA4-DEF-4325 Direct Embed Foundations Pull 14a: Wa-132 - Wa-1434d 4d 15-Jul-23 19-Jul-23 7d WA4-DEF-4320 Direct Embed Foundations Pull 15a: Wa-143 - Wa-1668d 8d 06-Jul-23 14-Jul-23 7d WA4-DEF-4315 Direct Embed Foundations Pull 16a: Wa-166 - Wa-1899d 9d 26-Jun-23 05-Jul-23 7d WA4-DEF-4310 Direct Embed Foundations Pull 17a: Wa-189 - Wa-2015d 5d 20-Jun-23 24-Jun-23 7d WA4-DEF-4305 Direct Embed Foundations Pull 18a: Wa-201 - Wa-2134d 4d 15-Jun-23 19-Jun-23 7d WA4-DEF-4300 Direct Embed Foundations Pull 19a: Wa-213 - Wa-2275d 5d 09-Jun-23 14-Jun-23 7d Drilled Pier FoundationsDrilled Pier Foundations 32d 32d 24-May-23 29-Jun-23 51d WA4-DPF-4435 Drilled Pier Foundations Pull 9a: Wa-53A - Wa-765d 5d 24-Jun-23 29-Jun-23 51d WA4-DPF-4430 Drilled Pier Foundations Pull 10a: Wa-77 - Wa-1006d 6d 17-Jun-23 23-Jun-23 48d WA4-DPF-4425 Drilled Pier Foundations Pull 12a: Wa-106 - Wa-1195d 5d 12-Jun-23 16-Jun-23 48d WA4-DPF-4420 Drilled Pier Foundations Pull 13a: Wa-119 - Wa-1323d 3d 08-Jun-23 10-Jun-23 48d WA4-DPF-4415 Drilled Pier Foundations Pull 15a: Wa-143 - Wa-1666d 6d 01-Jun-23 07-Jun-23 41d WA4-DPF-4410 Drilled Pier Foundations Pull 16a: Wa-166 - Wa-1893d 3d 29-May-23 31-May-23 40d WA4-DPF-4405 Drilled Pier Foundations Pull 18a: Wa-201 - Wa-2132d 2d 26-May-23 27-May-23 37d WA4-DPF-4400 Drilled Pier Foundations Pull 19a: Wa-213 - Wa-227 **Remob*2d 2d 24-May-23 25-May-23 35d Frame StructuresFrame Structures 50d 50d 25-May-23 21-Jul-23 32d WA4-FRM-4550 Frame Structures Pull 9a: Wa-53A - Wa-76 6d 6d 15-Jul-23 21-Jul-23 32d WA4-FRM-4545 Frame Structures Pull 10a: Wa-77 - Wa-100 6d 6d 08-Jul-23 14-Jul-23 30d WA4-FRM-4540 Frame Structures Pull 11a: Wa-100 - Wa-106 2d 2d 06-Jul-23 07-Jul-23 30d WA4-FRM-4535 Frame Structures Pull 12a: Wa-106 - Wa-119 3d 3d 03-Jul-23 05-Jul-23 30d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 19-Aug-23, Direct Embed Foundations 29-Jun-23, Drilled Pier Foundations 21-Jul-23, Frame Structures GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 14 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WA4-FRM-4530 Frame Structures Pull 13a: Wa-119 - Wa-132 4d 4d 28-Jun-23 01-Jul-23 30d WA4-FRM-4525 Frame Structures Pull 14a: Wa-132 - Wa-143 3d 3d 24-Jun-23 27-Jun-23 30d WA4-FRM-4520 Frame Structures Pull 15a: Wa-143 - Wa-166 7d 7d 16-Jun-23 23-Jun-23 27d WA4-FRM-4515 Frame Structures Pull 16a: Wa-166 - Wa-189 7d 7d 08-Jun-23 15-Jun-23 27d WA4-FRM-4510 Frame Structures Pull 17a: Wa-189 - Wa-201 4d 4d 03-Jun-23 07-Jun-23 27d WA4-FRM-4505 Frame Structures Pull 18a: Wa-201 - Wa-213 4d 4d 30-May-23 02-Jun-23 27d WA4-FRM-4500 Frame Structures Pull 19a: Wa-213 - Wa-227 4d 4d 25-May-23 29-May-23 27d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)53d 53d 28-Jun-23 28-Aug-23 7d WA4-SET-4650 Set Structures Pull 9a: Wa-53A - Wa-76 7d 7d 21-Aug-23 28-Aug-23 7d WA4-SET-4645 Set Structures Pull 10a: Wa-77 - Wa-100 8d 8d 11-Aug-23 19-Aug-23 7d WA4-SET-4640 Set Structures Pull 11a: Wa-100 - Wa-106 1d 1d 10-Aug-23 10-Aug-23 7d WA4-SET-4635 Set Structures Pull 12a: Wa-106 - Wa-119 5d 5d 04-Aug-23 09-Aug-23 7d WA4-SET-4630 Set Structures Pull 13a: Wa-119 - Wa-132 5d 5d 29-Jul-23 03-Aug-23 7d WA4-SET-4625 Set Structures Pull 14a: Wa-132 - Wa-143 2d 2d 27-Jul-23 28-Jul-23 7d WA4-SET-4620 Set Structures Pull 15a Wa-143 - Wa-166 8d 8d 18-Jul-23 26-Jul-23 7d WA4-SET-4615 Set Structures Pull 16a: Wa-166 - Wa-189 7d 7d 10-Jul-23 17-Jul-23 7d WA4-SET-4610 Set Structures Pull 17a: Wa-189 - Wa-201 3d 3d 06-Jul-23 08-Jul-23 7d WA4-SET-4605 Set Structures Pull 18a: Wa-201 - Wa-213 3d 3d 03-Jul-23 05-Jul-23 7d WA4-SET-4600 Set Structures Pull 19a: Wa-213 - Wa-227 4d 4d 28-Jun-23 01-Jul-23 7d Wire StringingWire Stringing 58d 58d 29-Jul-23 04-Oct-23 0d WA4-STR-4750 Conductor Stringing Pull 9a: Wa-53A - Wa-76 6d 6d 28-Sep-23 04-Oct-23 0d WA4-STR-4745 Conductor Stringing Pull 10a: Wa-77 - Wa-1006d 6d 21-Sep-23 27-Sep-23 0d WA4-STR-4740 Conductor Stringing Pull 11a: Wa-100 - Wa-1064d 4d 16-Sep-23 20-Sep-23 0d WA4-STR-4735 Conductor Stringing Pull 12a: Wa-106 - Wa-1195d 5d 11-Sep-23 15-Sep-23 0d WA4-STR-4730 Conductor Stringing Pull 13a: Wa-119 - Wa-1325d 5d 05-Sep-23 09-Sep-23 0d WA4-STR-4725 Conductor Stringing Pull 14a: Wa-132 - Wa-1435d 5d 30-Aug-23 04-Sep-23 0d WA4-STR-4720 Conductor Stringing Pull 15a: Wa-143 - Wa-1666d 6d 23-Aug-23 29-Aug-23 0d WA4-STR-4715 Conductor Stringing Pull 16a: Wa-166 - Wa-1896d 6d 16-Aug-23 22-Aug-23 0d WA4-STR-4710 Conductor Stringing Pull 17a: Wa-189 - Wa-2015d 5d 10-Aug-23 15-Aug-23 0d WA4-STR-4705 Conductor Stringing Pull 18a: Wa-201 - Wa-2135d 5d 04-Aug-23 09-Aug-23 0d WA4-STR-4700 Conductor Stringing Pull 19a: Wa-213 - Wa-2275d 5d 29-Jul-23 03-Aug-23 0d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 28-Aug-23, Set Structures (Including 3-Pole Framing) 04-Oct-23, Wire Stringing GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 15 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments Shirley Basin to TB FlatsShirley Basin to TB Flats 8d 8d 25-May-23 03-Jun-23 137d WA3-SBT-9000 Set 1 Structure (TB-2), Modify 1 Structure, Transfer 4 Structures8d8d 25-May-23 03-Jun-23 137d (5) Aeolus SS to Freezeout SS (Finish by October 15, 2023)(5) Aeolus SS to Freezeout SS (Finish by October 15, 2023)156d 156d 17-Apr-23 14-Oct-23 0d Access Installation (2 Crews)Access Installation (2 Crews)10d 10d 17-Apr-23 27-Apr-23 110d AF5-ACS-5200 AF Access Installation Pull 1: Aeolus - AF1 2d 2d 17-Apr-23 18-Apr-23 110d AF5-ACS-5210 AF Access Installation Pull 2: AF1 - AF11 2d 2d 19-Apr-23 20-Apr-23 110d AF5-ACS-5220 AF Access Installation Pull 3: AF11 - AF 16 2d 2d 21-Apr-23 22-Apr-23 110d AF5-ACS-5230 AF Access Installation Pull 4: AF16 - AF30 2d 2d 24-Apr-23 25-Apr-23 110d AF5-ACS-5240 AF Access Installation Pull 5: AF30 - AF31 2d 2d 26-Apr-23 27-Apr-23 110d Structure SalvageStructure Salvage 1d 1d 28-Apr-23 28-Apr-23 120d AF5-SLV-5310 Salvage Structures (2 Total)1d 1d 28-Apr-23 28-Apr-23 120d AF5-SLV-5320 AF Structure Salvage Complete 0d 0d 28-Apr-23 120d AF5-SLV-5300 Begin AF Structure Salvage 0d 0d 28-Apr-23 120d Direct Embed FoundationsDirect Embed Foundations 10d 10d 21-Aug-23 31-Aug-23 12d AF5-DEF-5400 AF Direct Embed Foundations Pull 2: AF1 - AF113d 3d 21-Aug-23 23-Aug-23 12d AF5-DEF-5410 AF Direct Embed Foundations Pull 3: AF11 - AF 162d 2d 24-Aug-23 25-Aug-23 12d AF5-DEF-5420 AF Direct Embed Foundations Pull 4: AF16 - AF305d 5d 26-Aug-23 31-Aug-23 12d Drilled Pier FoundationsDrilled Pier Foundations 16d 16d 30-Jun-23 18-Jul-23 55d AF5-DPF-5500 Drilled Pier Foundation AF Pull 1: Aeolus - AF11d 1d 30-Jun-23 30-Jun-23 51d AF5-DPF-5510 Drilled Pier Foundation AF Pull 2: AF1 - AF11 5d 5d 01-Jul-23 06-Jul-23 52d AF5-DPF-5520 Drilled Pier Foundation AF Pull 3: AF11 - AF 163d 3d 07-Jul-23 10-Jul-23 52d AF5-DPF-5530 Drilled Pier Foundation AF Pull 4: AF16 - AF305d 5d 11-Jul-23 15-Jul-23 52d AF5-DPF-5540 Drilled Pier Foundation AF Pull 5: AF30 - AF312d 2d 17-Jul-23 18-Jul-23 55d Frame StructuresFrame Structures 9d 9d 22-Jul-23 01-Aug-23 38d AF5-FRM-5600 Frame Structures AF Pull 1: Aeolus - AF1 1d 1d 22-Jul-23 22-Jul-23 37d AF5-FRM-5610 Frame Structures AF Pull 2: AF1 - AF11 2d 2d 24-Jul-23 25-Jul-23 37d AF5-FRM-5620 Frame Structures AF Pull 3: AF11 - AF 16 2d 2d 26-Jul-23 27-Jul-23 38d AF5-FRM-5630 Frame Structures AF Pull 4: AF16 - AF30 4d 4d 28-Jul-23 01-Aug-23 38d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)14d 14d 29-Aug-23 13-Sep-23 7d AF5-SET-5700 Set Structures AF Pull 1: Aeolus - AF1 1d 1d 29-Aug-23 29-Aug-23 7d AF5-SET-5710 Set Structures AF Pull 2: AF1 - AF11 5d 5d 30-Aug-23 04-Sep-23 7d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 03-Jun-23, Shirley Basin to TB Flats 14-Oct-23, (5) Aeolus SS to Freezeout SS (Finish by October 15, 2023) 27-Apr-23, Access Installation (2 Crews) 28-Apr-23, Structure Salvage AF Structure Salvage Complete Begin AF Structure Salvage 31-Aug-23, Direct Embed Foundations 18-Jul-23, Drilled Pier Foundations 01-Aug-23, Frame Structures 13-Sep-23, Set Structures (Including 3-Pole Framing) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 16 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments AF5-SET-5720 Set Structures AF Pull 3: AF11 - AF 16 2d 2d 05-Sep-23 06-Sep-23 7d AF5-SET-5730 Set Structures AF Pull 4: AF16 - AF30 5d 5d 07-Sep-23 12-Sep-23 7d AF5-SET-5740 Set Structures AF Pull 5: AF30 - AF31 1d 1d 13-Sep-23 13-Sep-23 7d Wire StringingWire Stringing 13d 13d 30-Sep-23 14-Oct-23 0d AF5-STR-5800 Conductor Stringing AF Pull 1: Aeolus - AF1 2d 2d 30-Sep-23 02-Oct-23 0d AF5-STR-5810 Conductor Stringing AF Pull 2: AF1 - AF11 3d 3d 03-Oct-23 05-Oct-23 0d AF5-STR-5820 Conductor Stringing AF Pull 3: AF11 - AF 16 3d 3d 06-Oct-23 09-Oct-23 0d AF5-STR-5830 Conductor Stringing AF Pull 4: AF16 - AF30 3d 3d 10-Oct-23 12-Oct-23 0d AF5-STR-5840 Conductor Stringing AF Pull 5: AF30 - AF31 2d 2d 13-Oct-23 14-Oct-23*0d 1Wc: Dave Johnson to Amassa SS1Wc: Dave Johnson to Amassa SS 156d 156d 28-Apr-23 26-Oct-23 130d Access Installation (2 Crews)Access Installation (2 Crews)8d 8d 28-Apr-23 06-May-23 278d WC6-ACS-6200 Access Installation Pull 1c: Dave Johnson - Wc-11d 1d 28-Apr-23 28-Apr-23 110d WC6-ACS-6210 Access Installation Pull 2c: Wc-1 - Wc-2 1d 1d 29-Apr-23 29-Apr-23 120d WC6-ACS-6220 Access Installation Pull 3c: Wc-2 - Wc-13 1d 1d 01-May-23 01-May-23 120d WC6-ACS-6230 Access Installation Pull 4c: Wc-13 - Wc-26 1d 1d 02-May-23 02-May-23 120d WC6-ACS-6240 Access Installation Pull 5c: Wc-26 - Wc-43 1d 1d 03-May-23 03-May-23 120d WC6-ACS-6250 Access Installation Pull 6c: Wc-43 - Wc-49A 1d 1d 04-May-23 04-May-23 120d WC6-ACS-6260 Access Installation Pull 7c: Wc-49A - Wc-49B 1d 1d 05-May-23 05-May-23 120d WC6-ACS-6270 Access Installation Pull 8c: Wc-49B - Amassa Sub1d 1d 06-May-23 06-May-23 278d Structure SalvageStructure Salvage 7d 7d 11-May-23 18-May-23 110d WC6-SLV-6300 Salvage Pull 1c: Dave Johnson - Wc-1 1d 1d 11-May-23 11-May-23 110d WC6-SLV-6310 Salvage Pull 2c: Wc-1 - Wc-2 1d 1d 12-May-23 12-May-23 110d WC6-SLV-6320 Salvage Pull 3c: Wc-2 - Wc-13 1d 1d 13-May-23 13-May-23 110d WC6-SLV-6330 Salvage Pull 4c: Wc-13 - Wc-26 1d 1d 15-May-23 15-May-23 110d WC6-SLV-6340 Salvage Pull 5c: Wc-26 - Wc-43 1d 1d 16-May-23 16-May-23 110d WC6-SLV-6350 Salvage Pull 6c: Wc-43 - Wc-49A 1d 1d 17-May-23 17-May-23 110d WC6-SLV-6360 Salvage Pull 7c: Wc-49A - Wc-49B 1d 1d 18-May-23 18-May-23 110d Direct Embed FoundationsDirect Embed Foundations 17d 17d 01-Sep-23 20-Sep-23 22d WC6-DEF-6400 Direct Embed Foundations Pull 3c: Wc-2 - Wc-134d 4d 01-Sep-23 05-Sep-23 18d WC6-DEF-6410 Direct Embed Foundations Pull 4c: Wc-13 - Wc-265d 5d 06-Sep-23 11-Sep-23 18d WC6-DEF-6420 Direct Embed Foundations Pull 5c: Wc-26 - Wc-436d 6d 12-Sep-23 18-Sep-23 18d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 14-Oct-23, Wire Stringing 26-Oct-23, 1Wc: Dave Johnson to Amassa SS 06-May-23, Access Installation (2 Crews) 18-May-23, Structure Salvage 20-Sep-23, Direct Embed Foundations GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 17 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC6-DEF-6430 Direct Embed Foundations Pull 6c: Wc-43 - Wc-49A2d 2d 19-Sep-23 20-Sep-23 22d Drilled Pier FoundationsDrilled Pier Foundations 14d 14d 19-Jul-23 03-Aug-23 68d WC6-DPF-6500 Drilled Pier Foundation Pull 1c: Dave Johnson - Wc-12d 2d 19-Jul-23 20-Jul-23 58d WC6-DPF-6510 Drilled Pier Foundation Pull 2c: Wc-1 - Wc-2 2d 2d 21-Jul-23 22-Jul-23 58d WC6-DPF-6520 Drilled Pier Foundation Pull 3c: Wc-2 - Wc-13 2d 2d 24-Jul-23 25-Jul-23 58d WC6-DPF-6530 Drilled Pier Foundation Pull 4c: Wc-13 - Wc-262d 2d 26-Jul-23 27-Jul-23 59d WC6-DPF-6540 Drilled Pier Foundation Pull 5c: Wc-26 - Wc-432d 2d 28-Jul-23 29-Jul-23 61d WC6-DPF-6550 Drilled Pier Foundation Pull 6c: Wc-43 - Wc-49A3d 3d 31-Jul-23 02-Aug-23 64d WC6-DPF-6560 Drilled Pier Foundation Pull 7c: Wc-49A - Wc-49B1d 1d 03-Aug-23 03-Aug-23 68d Frame StructuresFrame Structures 15d 15d 02-Aug-23 18-Aug-23 50d WC6-FRM-6600 Frame Structures Pull 3c: Wc-2 - Wc-13 4d 4d 02-Aug-23 05-Aug-23 46d WC6-FRM-6610 Frame Structures Pull 4c: Wc-13 - Wc-26 4d 4d 07-Aug-23 10-Aug-23 46d WC6-FRM-6620 Frame Structures Pull 5c: Wc-26 - Wc-43 5d 5d 11-Aug-23 16-Aug-23 46d WC6-FRM-6630 Frame Structures Pull 6c: Wc-43 - Wc-49A 2d 2d 17-Aug-23 18-Aug-23 50d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)18d 18d 14-Sep-23 04-Oct-23 16d WC6-SET-6700 Set Structures Pull 1c: Dave Johnson - Wc-1 1d 1d 14-Sep-23 14-Sep-23 7d WC6-SET-6710 Set Structures Pull 2c: Wc-1 - Wc-2 1d 1d 15-Sep-23 15-Sep-23 13d WC6-SET-6720 Set Structures Pull 3c: Wc-2 - Wc-13 3d 3d 16-Sep-23 19-Sep-23 13d WC6-SET-6730 Set Structures Pull 4c: Wc-13 - Wc-26 4d 4d 20-Sep-23 23-Sep-23 13d WC6-SET-6740 Set Structures Pull 5c: Wc-26 - Wc-43 5d 5d 25-Sep-23 29-Sep-23 13d WC6-SET-6750 Set Structures Pull 6c: Wc-43 - Wc-49A 3d 3d 30-Sep-23 03-Oct-23 14d WC6-SET-6760 Set Structures Pull 7c: Wc-49A - Wc-49B 1d 1d 04-Oct-23 04-Oct-23 16d Wire StringingWire Stringing 19d 19d 05-Oct-23 26-Oct-23 0d WC6-STR-6800 Conductor Stringing Pull 1c: Dave Johnson - Wc-11d 1d 05-Oct-23 05-Oct-23 0d WC6-STR-6810 Conductor Stringing Pull 2c: Wc-1 - Wc-2 2d 2d 06-Oct-23 07-Oct-23 0d WC6-STR-6820 Conductor Stringing Pull 3c: Wc-2 - Wc-13 2d 2d 09-Oct-23 10-Oct-23 0d WC6-STR-6830 Conductor Stringing Pull 4c: Wc-13 - Wc-26 4d 4d 11-Oct-23 14-Oct-23 0d WC6-STR-6840 Conductor Stringing Pull 5c: Wc-26 - Wc-43 4d 4d 16-Oct-23 19-Oct-23 0d WC6-STR-6850 Conductor Stringing Pull 6c: Wc-43 - Wc-49A 3d 3d 20-Oct-23 23-Oct-23 0d WC6-STR-6860 Conductor Stringing Pull 7c: Wc-49A - Wc-49B2d 2d 24-Oct-23 25-Oct-23 0d WC6-STR-6870 Conductor Stringing Pull 8c: Wc-49B - Amassa Sub1d 1d 26-Oct-23 26-Oct-23 0d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 03-Aug-23, Drilled Pier Foundations 18-Aug-23, Frame Structures 04-Oct-23, Set Structures (Including 3-Pole Framing) 26-Oct-23, Wire Stringing GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 18 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments Amassa to 1Wc148 & 1Wc-209 to Heward (Finish by October 7, 2024)Amassa to 1Wc148 & 1Wc-209 to Heward (Finish by October 7, 2024)357d 357d 08-May-23 06-Jul-24 0d Amassa to 1Wc-148Amassa to 1Wc-148 338d 338d 08-May-23 14-Jun-24 0d Access Installation (2 Crews)Access Installation (2 Crews)27d 27d 08-May-23 07-Jun-23 284d WC7-ACS-7200 Access Installation Pull 9c: Amassa #2 - Wc-49C1d 1d 08-May-23 08-May-23 278d WC7-ACS-7210 Access Installation Pull 10c: Wc-49C - Wc-49D1d 1d 09-May-23 09-May-23 278d WC7-ACS-7220 Access Installation Pull 11c: Wc-49D - Wc-66 1d 1d 10-May-23 10-May-23 278d WC7-ACS-7230 Access Installation Pull 12c: Wc-66 - Wc-88 3d 3d 11-May-23 13-May-23 282d WC7-ACS-7240 Access Installation Pull 13c: Wc-88 - Wc-95 3d 3d 15-May-23 17-May-23 282d WC7-ACS-7250 Access Installation Pull 14c: Wc-95 - Wc-106 3d 3d 18-May-23 20-May-23 282d WC7-ACS-7260 Access Installation Pull 15c: Wc-106 - Wc-1125d 5d 22-May-23 26-May-23 282d WC7-ACS-7270 Access Installation Pull 16c: Wc-112 - Wc-1375d 5d 27-May-23 01-Jun-23 282d WC7-ACS-7280 Access Installation Pull 17c: Wc-137 - Wc-1495d 5d 02-Jun-23 07-Jun-23 284d Structure SalvageStructure Salvage 18d 18d 19-May-23 08-Jun-23 305d WC7-SVG-7300 Salvage Pull 9c: Amassa #2 - Wc-49C 1d 1d 19-May-23 19-May-23 312d WC7-SVG-7310 Salvage Pull 10c: Wc-49C - Wc-49D 1d 1d 20-May-23 20-May-23 312d WC7-SVG-7320 Salvage Pull 11c: Wc-49D - Wc-66 1d 1d 22-May-23 22-May-23 312d WC7-SVG-7330 Salvage Pull 12c: Wc-66 - Wc-88 2d 2d 23-May-23 24-May-23 312d WC7-SVG-7340 Salvage Pull 13c: Wc-88 - Wc-95 1d 1d 25-May-23 25-May-23 312d WC7-SVG-7350 Salvage Pull 14c: Wc-95 - Wc-106 1d 1d 26-May-23 26-May-23 312d WC7-SVG-7360 Salvage Pull 15c: Wc-106 - Wc-112 1d 1d 27-May-23 27-May-23 312d WC7-SVG-7370 Salvage Pull Pull 16c: Wc-112 - Wc-137 2d 2d 02-Jun-23 03-Jun-23 308d WC7-SVG-7380 Salvage Pull 17c: Wc-137 - Wc-149 1d 1d 08-Jun-23 08-Jun-23 305d Direct Embed FoundationsDirect Embed Foundations 37d 37d 05-Oct-23 16-Nov-23 152d WC7-DEF-7400 Direct Embed Foundations Pull 11c: Wc-49D - Wc-667d 7d 05-Oct-23 12-Oct-23 152d WC7-DEF-7410 Direct Embed Foundations Pull 12c: Wc-66 - Wc-888d 8d 13-Oct-23 21-Oct-23 152d WC7-DEF-7420 Direct Embed Foundations Pull 13c: Wc-88 - Wc-952d 2d 23-Oct-23 24-Oct-23 152d WC7-DEF-7430 Direct Embed Foundations Pull 14c: Wc-95 - Wc-1064d 4d 25-Oct-23 28-Oct-23 152d WC7-DEF-7440 Direct Embed Foundations Pull 15c: Wc-106 - Wc-1122d 2d 30-Oct-23 31-Oct-23 152d WC7-DEF-7450 Direct Embed Foundations Pull 16c: Wc-112 - Wc-1379d 9d 01-Nov-23 10-Nov-23 152d WC7-DEF-7460 Direct Embed Foundations Pull 17c: Wc-137 - Wc-1495d 5d 11-Nov-23 16-Nov-23 152d Drilled Pier FoundationsDrilled Pier Foundations 17d 17d 05-Oct-23 24-Oct-23 173d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 06-Jul-24, Amassa to 1Wc148 & 1Wc-209 to Heward (Finish by October 7, 2024) 14-Jun-24, Amassa to 1Wc-148 07-Jun-23, Access Installation (2 Crews) 08-Jun-23, Structure Salvage 16-Nov-23, Direct Embed Foundations 24-Oct-23, Drilled Pier Foundations GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 19 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC7-DPF-7500 Drilled Pier Foundations Pull 9c: Amassa #2 - Wc-49C1d 1d 05-Oct-23*05-Oct-23 160d WC7-DPF-7510 Drilled Pier Foundations Pull 10c: Wc-49C - Wc-49D2d 2d 06-Oct-23 07-Oct-23 160d WC7-DPF-7520 Drilled Pier Foundations Pull 11c: Wc-49D - Wc-663d 3d 09-Oct-23 11-Oct-23 160d WC7-DPF-7530 Drilled Pier Foundations Pull 12c: Wc-66 - Wc-883d 3d 12-Oct-23 14-Oct-23 164d WC7-DPF-7540 Drilled Pier Foundations Pull 13c: Wc-88 - Wc-951d 1d 16-Oct-23 16-Oct-23 173d WC7-DPF-7550 Drilled Pier Foundations Pull 14c: Wc-95 - Wc-1062d 2d 17-Oct-23 18-Oct-23 173d WC7-DPF-7560 Drilled Pier Foundations Pull 15c: Wc-106 - Wc-1122d 2d 19-Oct-23 20-Oct-23 173d WC7-DPF-7570 Drilled Pier Foundations Pull 16c: Wc-112 - Wc-1373d 3d 21-Oct-23 24-Oct-23 173d Frame StructuresFrame Structures 29d 29d 05-Oct-23 07-Nov-23 168d WC7-FRM-7600 Frame Structures Pull 11c: Wc-49D - Wc-66 4d 4d 05-Oct-23*09-Oct-23 162d WC7-FRM-7610 Frame Structures Pull 12c: Wc-66 - Wc-88 7d 7d 10-Oct-23 17-Oct-23 162d WC7-FRM-7620 Frame Structures Pull 13c: Wc-88 - Wc-95 2d 2d 18-Oct-23 19-Oct-23 165d WC7-FRM-7630 Frame Structures Pull 14c: Wc-95 - Wc-106 3d 3d 20-Oct-23 23-Oct-23 165d WC7-FRM-7640 Frame Structures Pull 15c: Wc-106 - Wc-112 2d 2d 24-Oct-23 25-Oct-23 165d WC7-FRM-7650 Frame Structures Pull 16c: Wc-112 - Wc-137 7d 7d 26-Oct-23 02-Nov-23 165d WC7-FRM-7660 Frame Structures Pull 17c: Wc-137 - Wc-149 4d 4d 03-Nov-23 07-Nov-23 168d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)36d 36d 13-Oct-23 23-Nov-23 161d WC7-SET-7700 Set Structures Pull 9c: Amassa #2 - Wc-49C 1d 1d 13-Oct-23 13-Oct-23 157d WC7-SET-7710 Set Structures Pull 10c: Wc-49C - Wc-49D 1d 1d 14-Oct-23 14-Oct-23 157d WC7-SET-7720 Set Structures Pull 11c: Wc-49D - Wc-66 7d 7d 16-Oct-23 23-Oct-23 157d WC7-SET-7730 Set Structures Pull 12c: Wc-66 - Wc-88 7d 7d 24-Oct-23 31-Oct-23 157d WC7-SET-7740 Set Structures Pull 13c: Wc-88 - Wc-95 2d 2d 01-Nov-23 02-Nov-23 160d WC7-SET-7750 Set Structures Pull 14c: Wc-95 - Wc-106 3d 3d 03-Nov-23 06-Nov-23 160d WC7-SET-7760 Set Structures Pull 15c: Wc-106 - Wc-112 2d 2d 07-Nov-23 08-Nov-23 160d WC7-SET-7770 Set Structures Pull 16c: Wc-112 - Wc-137 8d 8d 11-Nov-23 20-Nov-23 158d WC7-SET-7780 Set Structures Pull 17c: Wc-137 - Wc-149 3d 3d 21-Nov-23 23-Nov-23 161d Wire StringingWire Stringing 38d 38d 02-May-24 14-Jun-24 0d WC7-STR-7800 Conductor Stringing Pull 9c: Amassa #2 - Wc-49C2d 2d 02-May-24 03-May-24 0d WC7-STR-7810 Conductor Stringing Pull 10c: Wc-49C - Wc-49D2d 2d 04-May-24 06-May-24 0d WC7-STR-7820 Conductor Stringing Pull 11c: Wc-49D - Wc-665d 5d 07-May-24 11-May-24 0d WC7-STR-7830 Conductor Stringing Pull 12c: Wc-66 - Wc-88 5d 5d 13-May-24 17-May-24 0d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 07-Nov-23, Frame Structures 23-Nov-23, Set Structures (Including 3-Pole Framing) 14-Jun-24, Wire Stringing GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 20 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC7-STR-7840 Conductor Stringing Pull 13c: Wc-88 - Wc-95 4d 4d 18-May-24 22-May-24 0d WC7-STR-7850 Conductor Stringing Pull 14c: Wc-95 - Wc-1065d 5d 23-May-24 28-May-24 0d WC7-STR-7860 Conductor Stringing Pull 15c: Wc-106 - Wc-1124d 4d 29-May-24 01-Jun-24 0d WC7-STR-7870 Conductor Stringing Pull 16c: Wc-112 - Wc-1376d 6d 03-Jun-24 08-Jun-24 0d WC7-STR-7880 Conductor Stringing Pull 17c: Wc-137 - Wc-1495d 5d 10-Jun-24 14-Jun-24 0d 1Wc-209 to Heward1Wc-209 to Heward 330d 330d 08-Jun-23 06-Jul-24 0d Access Installation (2 Crews)Access Installation (2 Crews)26d 26d 08-Jun-23 07-Jul-23 284d WC8-ACS-8200 Access Installation Pull 24c: Wc-208 - Wc-2257d 7d 08-Jun-23 15-Jun-23 284d WC8-ACS-8210 Access Installation Pull 25c: Wc-225 - Wc-2446d 6d 16-Jun-23 22-Jun-23 284d WC8-ACS-8220 Access Installation Pull 26c: Wc-244 - Wc-2547d 7d 23-Jun-23 30-Jun-23 284d WC8-ACS-8230 Access Installation Pull 27c: Wc-254 - Heward #16d 6d 01-Jul-23 07-Jul-23 284d Structure SalvageStructure Salvage 6d 6d 08-Jul-23 14-Jul-23 292d WC8-SLV-8300 Salvage Pull 24c: Wc-208 - Wc-225 1d 1d 08-Jul-23 08-Jul-23 292d WC8-SLV-8310 Salvage Pull 25c: Wc-225 - Wc-244 2d 2d 10-Jul-23 11-Jul-23 292d WC8-SLV-8320 Salvage Pull 26c: Wc-244 - Wc-254 2d 2d 12-Jul-23 13-Jul-23 292d WC8-SLV-8330 Salvage Pull 27c: Wc-254 - Heward #1 1d 1d 14-Jul-23 14-Jul-23 292d Direct Embed FoundationsDirect Embed Foundations 23d 23d 17-Nov-23 13-Dec-23 152d WC8-DEF-8400 Direct Embed Foundations Pull 24c: Wc-208 - Wc-2257d 7d 17-Nov-23 24-Nov-23 152d WC8-DEF-8410 Direct Embed Foundations Pull 25c: Wc-225 - Wc-2447d 7d 25-Nov-23 02-Dec-23 152d WC8-DEF-8420 Direct Embed Foundations Pull 26c: Wc-244 - Wc-2548d 8d 04-Dec-23 12-Dec-23 152d WC8-DEF-8430 Direct Embed Foundations Pull 27c: Wc-254 - Heward #11d1d 13-Dec-23 13-Dec-23 152d Drilled Pier FoundationsDrilled Pier Foundations 6d 6d 25-Oct-23 31-Oct-23 197d WC8-DPF-8500 Drilled Pier Foundations Pull 25c: Wc-225 - Wc-2442d 2d 25-Oct-23 26-Oct-23 190d WC8-DPF-8510 Drilled Pier Foundations Pull 26c: Wc-244 - Wc-2542d 2d 27-Oct-23 28-Oct-23 194d WC8-DPF-8520 Drilled Pier Foundations Pull 27c: Wc-254 - Heward #12d 2d 30-Oct-23 31-Oct-23 197d Frame StructuresFrame Structures 19d 19d 08-Nov-23 29-Nov-23 168d WC8-FRM-8600 Frame Structures Pull 24c: Wc-208 - Wc-225 6d 6d 08-Nov-23 14-Nov-23 168d WC8-FRM-8610 Frame Structures Pull 25c: Wc-225 - Wc-244 6d 6d 15-Nov-23 21-Nov-23 168d WC8-FRM-8620 Frame Structures Pull 26c: Wc-244 - Wc-254 6d 6d 22-Nov-23 28-Nov-23 168d WC8-FRM-8630 Frame Structures Pull 27c: Wc-254 - Heward #11d 1d 29-Nov-23 29-Nov-23 168d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)22d 22d 25-Nov-23 20-Dec-23 156d WC8-SET-8700 Set Structures Pull 24c: Wc-208 - Wc-225 4d 4d 25-Nov-23 29-Nov-23 161d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 06-Jul-24, 1Wc-209 to Heward 07-Jul-23, Access Installation (2 Crews) 14-Jul-23, Structure Salvage 13-Dec-23, Direct Embed Foundations 31-Oct-23, Drilled Pier Foundations 29-Nov-23, Frame Structures 20-Dec-23, Set Structures (Including 3-Pole Framing) GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 21 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC8-SET-8710 Set Structures Pull 25c: Wc-225 - Wc-244 5d 5d 04-Dec-23 08-Dec-23 158d WC8-SET-8720 Set Structures Pull 26c: Wc-244 - Wc-254 5d 5d 13-Dec-23 18-Dec-23 156d WC8-SET-8730 Set Structures Pull 27c: Wc-254 - Heward #1 2d 2d 19-Dec-23 20-Dec-23 156d Wire StringingWire Stringing 19d 19d 15-Jun-24 06-Jul-24 0d WC8-STR-8800 Conductor Stringing Pull 24c: Wc-208 - Wc-2255d 5d 15-Jun-24 20-Jun-24 0d WC8-STR-8810 Conductor Stringing Pull 25c: Wc-225 - Wc-2446d 6d 21-Jun-24 27-Jun-24 0d WC8-STR-8820 Conductor Stringing Pull 26c: Wc-244 - Wc-2546d 6d 28-Jun-24 04-Jul-24 0d WC8-STR-8830 Conductor Stringing Pull 27c: Wc-254 - Heward #12d 2d 05-Jul-24 06-Jul-24 0d Heward Basin to Shirley Basin SSHeward Basin to Shirley Basin SS 255d 255d 05-Oct-23 07-Aug-24 72d Access Installation (2 Crews)Access Installation (2 Crews)21d 21d 05-Oct-23 28-Oct-23 232d WC9-ACS-9200 Access Installation Pull 28c: Wc-268 - Wc-2884d 4d 05-Oct-23*09-Oct-23 208d WC9-ACS-9210 Access Installation Pull 29c: Wc-288 - Wc-3063d 3d 10-Oct-23 12-Oct-23 213d WC9-ACS-9220 Access Installation Pull 30c: Wc-306 - Wc-3194d 4d 13-Oct-23 17-Oct-23 216d WC9-ACS-9230 Access Installation Pull 31c: Wc-319 - Wc-2/177A3d 3d 18-Oct-23 20-Oct-23 218d WC9-ACS-9240 Access Installation Pull 32c: Wc-2/177A - Wc-1/34d 4d 21-Oct-23 25-Oct-23 232d WC9-ACS-9250 Access Installation Pull 33c: Wc-1/3 - Shirley Basin #13d 3d 26-Oct-23 28-Oct-23 232d Structure SalvageStructure Salvage 12d 12d 10-Oct-23 23-Oct-23 311d WC9-SLV-9300 Salvage Pull 28c: Wc-262 - Wc-288 2d 2d 10-Oct-23 11-Oct-23 316d WC9-SLV-9310 Salvage Pull 29c: Wc-288 - Wc-306 2d 2d 13-Oct-23 14-Oct-23 315d WC9-SLV-9320 Salvage Pull 30c: Wc-306 - Wc-319 1d 1d 18-Oct-23 18-Oct-23 313d WC9-SLV-9330 Salvage Pull 31c: Wc-319 - Wc-2/177A 2d 2d 21-Oct-23 23-Oct-23 311d Direct Embed FoundationsDirect Embed Foundations 27d 27d 14-Dec-23 24-Jan-24 152d WC9-DEF-9400 Direct Embed Foundations Pull 28c: Wc-268 - Wc-2888d 8d 14-Dec-23 02-Jan-24 152d WC9-DEF-9410 Direct Embed Foundations Pull 29c: Wc-288 - Wc-3067d 7d 03-Jan-24 10-Jan-24 152d WC9-DEF-9420 Direct Embed Foundations Pull 30c: Wc-306 - Wc-3195d 5d 11-Jan-24 16-Jan-24 152d WC9-DEF-9430 Direct Embed Foundations Pull 31c: Wc-319 - Wc-2/177A7d7d 17-Jan-24 24-Jan-24 152d Drilled Pier FoundationsDrilled Pier Foundations 7d 7d 01-Nov-23 08-Nov-23 209d WC9-DPF-9500 Drilled Pier Foundations Pull 28c: Wc-268 - Wc-2882d 2d 01-Nov-23 02-Nov-23 197d WC9-DPF-9510 Drilled Pier Foundations Pull 29c: Wc-288 - Wc-3062d 2d 03-Nov-23 04-Nov-23 202d WC9-DPF-9520 Drilled Pier Foundations Pull 31c: Wc-319 - Wc-2/177A3d 3d 06-Nov-23 08-Nov-23 209d Frame StructuresFrame Structures 22d 22d 30-Nov-23 04-Jan-24 169d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 06-Jul-24, Wire Stringing 07-Aug-24, Heward Basin to Shirley Basin SS 28-Oct-23, Access Installation (2 Crews) 23-Oct-23, Structure Salvage 24-Jan-24, Direct Embed Foundations 08-Nov-23, Drilled Pier Foundations 04-Jan-24, Frame Structures GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 22 of 23 Date Revision Checked Approved Activity ID Activity Name Orig dur (CD) Rem Dur (CD) Start Finish Total Float Comments WC9-FRM-9600 Frame Structures Pull 28c: Wc-268 - Wc-288 6d 6d 30-Nov-23 06-Dec-23 168d WC9-FRM-9610 Frame Structures Pull 29c: Wc-288 - Wc-306 6d 6d 07-Dec-23 13-Dec-23 169d WC9-FRM-9620 Frame Structures Pull 30c: Wc-306 - Wc-319 4d 4d 14-Dec-23 18-Dec-23 169d WC9-FRM-9630 Frame Structures Pull 31c: Wc-319 - Wc-2/177A6d 6d 19-Dec-23 04-Jan-24 169d Set Structures (Including 3-Pole Framing)Set Structures (Including 3-Pole Framing)24d 24d 03-Jan-24 30-Jan-24 152d WC9-SET-9700 Set Structures Pull 28c: Wc-268 - Wc-288 6d 6d 03-Jan-24 09-Jan-24 154d WC9-SET-9710 Set Structures Pull 29c: Wc-288 - Wc-306 5d 5d 11-Jan-24 16-Jan-24 154d WC9-SET-9720 Set Structures Pull 30c: Wc-306 - Wc-319 3d 3d 17-Jan-24 19-Jan-24 156d WC9-SET-9730 Set Structures Pull 31c: Wc-319 - Wc-2/177A 5d 5d 25-Jan-24 30-Jan-24 152d Wire StringingWire Stringing 27d 27d 08-Jul-24 07-Aug-24 0d WC9-STR-9800 Conductor Stringing Pull 28c: Wc-268 - Wc-2886d 6d 08-Jul-24 13-Jul-24 0d WC9-STR-9810 Conductor Stringing Pull 29c: Wc-288 - Wc-3065d 5d 15-Jul-24 19-Jul-24 0d WC9-STR-9820 Conductor Stringing Pull 30c: Wc-306 - Wc-3195d 5d 20-Jul-24 25-Jul-24 0d WC9-STR-9830 Conductor Stringing Pull 31c: Wc-319 - Wc-2/177A5d 5d 26-Jul-24 31-Jul-24 0d WC9-STR-9840 Conductor Stringing Pull 32c: Wc-2/177A - Wc-1/34d 4d 01-Aug-24 05-Aug-24 0d WC9-STR-9850 Conductor Stringing Pull 33c: Wc-1/3 - Shirley Basin #12d 2d 06-Aug-24 07-Aug-24 0d Construction CompletionConstruction Completion 84d 84d 25-Jul-24 30-Oct-24 0d ALL-FIN-510 Final Construction Demob 24d 24d 25-Jul-24 21-Aug-24 60d ALL-FIN-520 Final Reclamation and Clean Up Activities 24d 24d 25-Jul-24 21-Aug-24 0d ALL-FIN-560 Mechanical Completion 0d 0d 28-Aug-24 36d ALL-FIN-530 Punch List Items 18d 18d 08-Aug-24 28-Aug-24 36d ALL-FIN-540 QC Forms Submitted 18d 18d 08-Aug-24 28-Aug-24 36d ALL-FIN-550 As-Built Submittals 18d 18d 08-Aug-24 28-Aug-24 36d ALL-FIN-580 Substantial Completion 0d 0d 30-Oct-24 0d ALL-FIN-570 Testing Verification 18d 18d 29-Aug-24 18-Sep-24 36d ALL-FIN-590 Final Project Completion Date (Required October 31, 2024)0d 0d 30-Oct-24*0d ALL-FIN-500 Construction Completion 0d 0d 07-Aug-24 0d J A S O N D J F M A M J J A S O N D J F M A M J J A S O 2022 2023 2024 30-Jan-24, Set Structures (Including 3-Pole Framing) 07-Aug-24, Wire Stringing Mechanical Completion Construction Completion GWW D.1 Project Baseline_Approved 13-Aug-24 11:30 Remaining Level of Effort Actual Level of Effort Primary Baseline Actual Work Remaining Work Critical Remaining Work GATEWAY SOUTH Page 23 of 23 Date Revision Checked Approved