HomeMy WebLinkAbout20240828Staff Comments .pdf RECEIVED
Wednesday, August 28, 2024 10:26:22 AM
IDAHO PUBLIC
UTILITIES COMMISSION
ADAM TRIPLETT
DEPUTY ATTORNEY GENERAL
IDAHO PUBLIC UTILITIES COMMISSION
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0318
IDAHO BAR NO. 10221
Street Address for Express Mail:
11331 W CHINDEN BLVD, BLDG 8, SUITE 201-A
BOISE, ID 83714
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER )
COMPANY'S APPLICATION FOR ) CASE NO. IPC-E-24-23
APPROVAL OF AMENDMENTS TO THE )
ENERGY SERVICES AGREEMENTS WITH )
MICRON AND BRISBIE AND REQUEST FOR ) COMMENTS OF THE
UPDATED PRICING ELEMENTS BASED ON ) COMMISSION STAFF
2023 IRP )
COMMISSION STAFF ("STAFF") OF the Idaho Public Utilities Commission, by and
through its Attorney of record, Adam Triplett, Deputy Attorney General, submits the following
comments.
BACKGROUND
On May 30, 2024, Idaho Power Company("Company"), applied for approval of(1)the
Second Amendment to its Special Contract with Brisbie, LLC (`Brisbie"); (2)the Third
Amendment to its Special Contract with Micron Technology, Inc.; (3)updates to pricing
elements in these special contracts and the Clean Energy Your Way("CEYW") Construction
Agreement with the City of Boise that are based on the Company's 2023 Integrated Resource
Plan ("IRP"); (4) associated modifications to Schedule 33—Brisbie, Schedule 26—Micron, and
STAFF COMMENTS 1 AUGUST 28, 2024
Schedule 62CEYW Program("Schedule 62"); and(5) a proposed method for updating prices
contained in CEYW-Construction Program contracts that rely on IRP data.
The Company represents that, through its Schedule 62, large customers served under
Special Contract or Schedule 19—Large Power Service can receive service via tailored
renewable resources (called CEYW-Construction) that cover up to 110 percent of their energy
use.
The Company represents that it has Special Contracts with Brisbie, and Micron
Technology, Inc. ("Micron"), that contain CEYW-Construction pricing elements, such as Excess
Generation Credits and Renewable Capacity Credits.
The Company represents that it has a CEYW Renewable Construction Agreement with
the City of Boise ("Boise").
The Company represents that the Commission has previously approved amendments to
the special contracts with Brisbie and Micron to comply with Commission directives regarding
charges and pricing elements.
The Company represents that, because of Commission guidance and collaborative efforts
with Staff, it formed a Second Amendment to the special contract with Brisbie and a Third
Amendment to the special contract with Micron to ensure the transparent and efficient review of
updates to pricing elements in CEYW-Construction Agreements. These amendments describe
rate components under the Brisbie and Micron Special Contracts and Boise's CEYW-
Construction Agreement, clarify or add definitions for certain pertinent terms, and ensure that
rate charges are considered in separate proceedings.
The Company proposes the Commission direct that future updates to CEYW-
Construction Agreements using IRP inputs for pricing be filed for approval under a single docket
within 30 days of submission of the IRP.
STAFF ANALYSIS
Based on reviewing the Application and Attachments, Staff came to the following
conclusions:
1. Staff recommends the Commission approve of the Second Amendment to Brisbie's
Special Contract and the Third Amendment to Micron's Special Contract.
STAFF COMMENTS 2 AUGUST 28, 2024
2. Staff recommends the pricing updates for the Supplemental Energy Price and the
Mid-Columbia("Mid-C") Forecast used to determine the Excess Generation Price be
based on a 50th percentile ("P50") load forecast instead of the Company's proposed
70th percentile ("P70") load forecast.
3. Staff recommends the City of Boise use the hourly Mid-C price forecast from the
2021 IRP to determine the Excess Generation Price until an hourly Mid-C forecast is
approved in this case.
4. Staff recommends the Commission approve the proposed method for updating future
pricing elements of the CEYW-Construction program.
5. The provided updated tariff schedules include all the necessary updates required to
address the proposed changes in this case, but the Company should submit a
compliance filing to update the date and order number in the proposed tariffs along
with including changes that have occurred to the tariffs as a result of Commission
Orders.
Special Contract Amendments
Staff recommends the Commission approve the Second Amendment to Brisbie's Special
Contract and the Third Amendment to Micron's Special Contract because the amendments
provide consistency between all the CEYW-Construction special contracts and agreements. In
addition, the amendments align with the Company's proposed method for updating future pricing
elements.
The proposed amendments modify the definitions for Excess Generation Price and
Supplemental Energy Price and adds a definition for the Mid-Columbia Forecast. The
definitions for the Excess Generation Price and the Mid-Columbia Forecast are consistent with
the City of Boise CEYW Agreement from Case No. IPC-E-24-18, which Staff recommended
approving. Both the Mid-Columbia Forecast and Supplemental Energy definitions reference the
most recently filed Integrated Resource Plan ("IRP"). This reference aligns with the proposed
timing of future pricing updates, which the Company proposed to occur within 30 days after
filing each IRP with the Commission.
STAFF COMMENTS 3 AUGUST 28, 2024
P50 IRP Forecast for Establishing Energy-Related Rates
Staff recommends the Company use the P50 load forecast for determining the
Supplemental Energy Price and Excess Generation Price instead of the P70 load forecast used in
the IRP. The Company is currently authorized to use the DSM Avoided Cost Averages for the
Supplemental Energy Price and the Mid-C forecast for the Excess Generation Price from the
IRP. However, the Company is currently using a P70 forecast to ensure the Company plans for
sufficient resources to meet reliability requirements,but Staff does not believe it is appropriate
for setting rates and the Company should be using a P50 load forecast, instead.
To be clear, the P50 load, or 50t'percentile load, and the P70 load, or 70t'percentile load,
are from the same forecast. The Company uses the P70 load in the IRP to account for weather
and other factors to ensure it has enough resources in reserve to meet a 1 event in 10-year
reliability target. In other words, the Company plans enough resources to a load forecast where
70 percent of the time, the realized loads are expected to be lower, while only 30 percent of the
time, the loads are expected to be higher. Planning resources to these higher-than-normal loads
provides an extra safety margin so that when peak loads occur, the Company has enough
resources to make outage events rare. However, Staff believes that if the IRP is used for the
purpose of developing rates, the load forecast should be based on loads the Company expects to
serve, which are at the 50th percentile.
Staff recommended the Company calculate marginal avoided costs using a P50 load
forecast in future IRPs in its 2023 IRP comments (Case No. IPC-E-23-23) and maintains this
position for determining the Supplemental Energy Price and the Mid-C forecast used to
determine the Excess Generation Price in this case.
In cost-of-service ratemaking, it is an accepted and necessary practice to develop rates
using expected loads under normal conditions to ensure that rates, on average, reflect costs
incurred in the utility's system. Furthermore, the use of a P70 forecast is inconsistent with IRP-
based avoided cost rates as authorized in Order No. 36037 (Case No. IPC-E-23-25), and
Schedules 20 and 34 marginal cost rates authorized in Order No. 36201 (Case No. IPC-E-24-15),
both of which were based on the P50 load forecast.
STAFF COMMENTS 4 AUGUST 28, 2024
Use of 2021 IRP for Excess Generation Price
In Case No. IPC-E-24-18, the Company did not address which IRP should be used to
determine the Excess Generation Price under its CEYW contract with the City of Boise. Staff
recommended the Commission direct the Company to use the hourly Mid-C forecast from the
2021 IRP to determine the Excess Generation Price under that contract until an hourly Mid-C
forecast is approved in this case. The Commission adopted this recommendation. See Order No.
36302 at 5. The Excess Generation Price authorized by the Commission for Micron is still based
on the Mid-C price forecast from the 2021 IRP and will remain so until the Commission issues
an order to update it in this case.
The Company has proposed to compensate the City of Boise for excess generation based
on the Mid-C price forecast from the 2023 IRP until it can be authorized by the Commission, and
if the rates change as a result of this case, the Company has proposed to true up any credits.
Adopting this recommendation would conflict with the Commission's directive in Order No.
36302 to use the Mid-C price forecast from the 2021 IRP to calculate excess the Excess
Generation Price. Accordingly, consistent with Order No. 36302, Staff recommends the
Commission order the Company to compensate the City for excess generation based on the Mid-
C price forecast from the 2021 IRP until issuance of an order approving Mid-C price forecast
from the 2023 IRP.
Future Pricing Updates
The Company's proposal for updating future pricing elements by filing a single docket
within 30 days of submission of the IRP is reasonable because it provides a defined schedule for
the updates to occur, and ensures the rates authorized by the Commission use information that is
more recent and more accurate by reducing the time from when the information was developed
during the IRP cycle to the time it is authorized by the Commission. Staff recommends the
Commission approve the proposed timing for future pricing updates.
Proposed Tariff Schedules
Staff believes the Company's proposed tariff schedules include all the necessary updates
required to address the proposed changes. Staff recommends updated tariff schedules be
submitted through a compliance filing to update the date and order number from this case along
STAFF COMMENTS 5 AUGUST 28, 2024
with changes that have or will occur as a result of Commission Orders in Case No(s). IPC-E-24-
01 and IPC-E-24-18.
STAFF RECOMMENDATION
Staff recommends the Commission:
1. Approve the Second Amendment to Brisbie's Special Contract and the Third
Amendment to Micron's Special Contract;
2. Approve the Supplemental Energy Price using the Avoided Cost Averages based
on a P50 forecast instead of the Company's proposed P70 forecast;
3. Approve the Mid-C forecast using the hourly Mid-C forecast based on a P50
forecast instead of the Company's proposed P70 forecast;
4. Consistent with Order No. 36302, order the Company to use the hourly Mid-C
price forecast from the 2021 IRP to determine the Excess Generation Price for the
City of Boise until an hourly Mid-C forecast is approved in this case;
5. Approve the proposed method for updating future pricing elements of the CEYW-
Construction program; and
6. Order the Company to submit a compliance filing to update the Tariff Schedules
for Schedules 26, 33, and 62.
Respectfully submitted this 28th day of August 2024.
Adam Triplett
Deputy Attorney General
Technical Staff: Michael Eldred
I:\Utility\UMISC\COMMENTS\IPC-E-24-23 Comments.docx
STAFF COMMENTS 6 AUGUST 28, 2024
CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS -lamg�l DAY OF AUGUST 2024,
SERVED THE FOREGOING COMMENTS OF THE COMMISSION STAFF, IN CASE
NO. IPC-E-24-23, BY &MAILING A COPY THEREOF, TO THE FOLLOWING:
DONOVAN E WALKER ENERGY CONTRACTS
MEGAN GOICOECHEA ALLEN CONNIE ASCHENBRENNER
IDAHO POWER COMPANY GRAND ANDRSON
PO BOX 70 IDAHO POWER COMPANY
BOISE ID 83707-0070 PO BOX 70
E-MAIL: dwalkergidahopower.com BOISE ID 83707-0070
mgoicoecheaallengidahopower.com E-MAIL: energ_ycontractskidahopower.com
docketsgidahopower.com caschenbrennerkidahopower.com
ganderson(kidahopower.com
PATRICIA JORDAN, SIECRETARY
CERTIFICATE OF SERVICE