HomeMy WebLinkAbout20240823PAC to Bayer 55 Attachment - Rock Creek I and II Schedule.pdf ID Task Task Name Duration Start Finish Predecessors Resource Names Apr 28,'24 Mode _ W T F S S M T W T F 1 Mobilization 2 days Wed 5/15/24Thu 5/16/24 2 Fence removal 2 days Fri 5/17/24 Mon 5/20/24 3 Clearing Grubbing 2 days Mon 5/20/24Tue 5/21/24 4 Excavate common 4 days Wed Mon Earth 5/22/24 5/27/24 5 All Base Course 4 days Mon 4/29/24Thu 5/2/24 6 ;11� Foundations 22 days Fri 5/3/24 Mon 6/3/24 7 Underground Rough 4 days Mon 6/3/24 Thu 6/6/24 in 8 Cable Trench 2 days Mon 6/3/24 Tue 6/4/24 9 UG Grounding 5 days Fri 6/7/24 Thu 6/13/24 10 Site Improvements 10 days Mon 6/3/24 Fri 6/14/24 11 Road Finish 4 days Mon 6/17/24Thu 6/20/24 12 Install Steel 12 days Mon Tue 7/2/24 Structures 6/17/24 13 Install Equipment 14 days Wed 7/3/24 Mon 7/22/24 14 5 and 6 inch buss 7 days Tue 7/23/24 Wed 7/31/24 15 Above ground 4 days Mon Thu 7/25/24 Grounding 7/22/24 16 Above ground 11 days Thu 8/1/24 Thu 8/15/24 Conduit 17 Wire and Cable Pull 20 days Mon 8/12/24 Fri 9/6/24 18 19 Collector Site I Task Inactive Summary External Tasks Split .................. Manual Task I I External Milestone > Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only E Inactive Milestone Finish-only ] Page 1 ID 0 Task Task Name IDuration Start Finish Predecessors Resource Names Apr 28,'24 Mode W T F S S M T W T F 20 *7 CH Foundation 5 days 21 *7 CH Stoop 1 day ■ 22 23 Collector Site II 24 CH Foundation 5 days 25 CH Stoop 1 day ■ Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 2 May 5,'24 May 12,'24 May 19,'24 May 26,'24 Jun 2,'24 Jun 9,'24 S S M T W T F S S M T W T F S S M I T I W I T I F I S S I M I T I W T F S S M I T I W I T I F S S M T W T F S Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary I I Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 3 May 5,'24 May 12,'24 May 19,'24 May 26,'24 Jun 2,'24 Jun 9,'24 S S M T W T F S S M T W T F S S M I T I W I T I F I S S I M I T I W I T I F I S S M I T I W I T I F I S S I M I T I W I T I F I S Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary I I Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 4 Jun 16,'24 Jun 23,'24 Jun 30,'24 Jul 7,'24 Jul 14,'24 Jul 21,'24 Jul 2 S M T W T F S S M T W T F S S M T W T F S S M I T I W I T I F I S S I M I T I W I T I F S S I M I T I W I T I F I S S Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 5 Jun 16,'24 Jun 23,'24 Jun 30,'24 Jul 7,'24 Jul 14,'24 Jul 21,'24 Jul 2 S M T W T F S S M T W T F S S M T W T F S S M I T I W I T I F I S S I M I T I W I T I F S S I M I T I W I T I F I S S Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 6 8,'24 Au $ '24 Au 11,'24 Au 18,'24 Au 25,24 Sep 1,'24 Sep 8,'2 M T W T F S S M T W T F S S M T W T F S S M T I W I T I F I S S M T W I T I F I S S M I T W T F S S M Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary I I Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 7 8,'24 Au $ '24 Au 11,'24 Au 18,'24 Au 25,24 Sep 1,'24 Sep 8,'2 M T W T F S S M T W T F S S M T W T F S S M T I W I T I F I S S I M I T W I T I F I S S I M I T I W I T I F I S S M Task Inactive Summary External Tasks Split .................. Manual Task External Milestone O Milestone ♦ Duration-only Deadline Project: Rock Creek I and II Sch Date: Fri 4/26/24 Summary Manual Summary Rollup Progress Project Summary Manual Summary I I Manual Progress Inactive Task Start-only C Inactive Milestone Finish-only 7 Page 8