HomeMy WebLinkAbout20240823PAC to Bayer 55 Attachment - c.v.1 GWW D1 Tline BL App.pdf GWW DA Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J I F M A M J J A S O N D J F M A M J J A S O GWW D.1 Project Baseline_Approved 696d 696d 20-Jul-22 31-Oct-24 Od • • •• ��� • 15iSep-2?, Exhibit I:Owner I ilestopes ALL-MS-0100 Effective Date of Release No. 1 Od Od 20-Jul-22* Od j Effective Date of Rel :as No. 1, ALL-MS-0110 Full Notice to Proceed Od Od 15-Sep-22* 7d ♦'Full Nbtice td Pdocded' ALL-MS-0120 Owner Provided Approval for Project Si' Od Od 01 Sep-22* Od * Owner Provided Approval_for Project Site&Equipment Mobilization', Y, g_ ,- --r , ALL-MS-0130 ROW Access Provided for Surve Stah Od Od 15Au 22 10d ROW;Acaess Provided for Survey,Staked&Planning ALL-MS-0140 ROW Access Provided for Constructior Od Od 15Sep-22 7d ♦ ROW Acdes8 Provided for Construction:Element)1 -I Wihdstar10 Shirley:Basin(Se ALL-MS-0150 ROW Access Provided for Constructior Od Od 15Sep-22 293d ♦ ROW j cges§Pkvioed,for Cgnstructio6:Elemeni 2 Dave;Joh?nsgn Arrrassa(Se ALL-MS-0160 ROW Access Provided for Constructior Od Od 15Sep-22 79d I♦ ROW Access Provided for Cdnstructiorl:Elerdentl 2:Amas�a-'Shirley Bdsinl(Sl§ctidi ALL-MS-0170 ROW Access Provided for Constructior Od Od 15Sep-22 283d ♦ RqW�ccess Provided,for,Construction:Element)3:Aeolus Freezeout(Section 5). ----------------- I Critical Milestones 696d 696d 20-Jul-22 31-Oct-24 Od L Overall Project 696d 696d 20-Jul- - L S-0220 Site Mobilization(Access) Od Od 15Sep-22 7d ♦ SitgN objlizakio6(gccess)S-0240 Final Project Completion Date Od Od 31-Oct-24* Od ntractEx cu S-0200 Contract Execution Od Od 20,Jul-22 12d j Cq e ItiorlS-0210 Baseline Schedule Approved Od Od 03Sep-22 17d Baseline Schedule Approved - c Od Od Element 1 -1 Wa Od Od Element 3-Aeolus to Freezeout Od Od Interim Milestones 36d l 36d 29-Jul-22 09Sep-Sep 12d / 09$ep-2�,IrjterjmlVlilosta,neg Overall Project 36d 36d 29 Jul-22 09 Sep 2 09$ep-2�,Overall Oroject, ALL-MS-0300 Limited Notice to Proceed Od Od 12 Aug-22 2d :+ ',Limited Notice to Proceed) ALL-MS-0310 Letter of Credit ;Od Od 29,Jul-22 14d Letter of Credit ALL-MS-0320 Baseline Schedule for Initial Submissio Od 20Aug-Aug 17d ♦I Basellne;Schedlule for Initial Submiss_ibn fbrApprovbl ---------------- ALL-MS-0330 Issue QA/QC Plan Od 09Se 22 12d P- -- MssOe(�AIIQC,PI�n ALL-MS-0340 Issue Safety Plan Od 12Aug-Aug 36d ;♦ IlssUe Safety'Plah ALL-MS-0350 Issue Environmental Assurance Plan Od 09Sep-Sep 12d * Issue itnviron,mentalAssurance Plan 1Wc Od 1 Wa Od Od IV Aeolus-Freezeout Od Od Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline ML= Critical Remaining Work Page 1 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J I F M A M J J A S O N I D J I F M A M J J A S O ALL-SUM-1050 Evironmental/SWPPP Controls/BMF 602d 602d 15Aug-22 07-Aug-24 Od ALLSUM-1000 Project Management/Overhead 602d 602d 15Aug-22 07-Aug-24 Od Element Summary-1Wc 654d 654d 20-Jul-22 11Sep-24 42d 11 EL2SUM-1100 Engineering and Design Procurement 27d 27d 20-Jul-22 19-Aug-22 81d o , EL2SUM-9000 Element 2-Mobilization Payment(809 28d 28d 15Aug-22 15Sep-22 646d EL2SUM-9010 Element 2-Mobilization(20%)(to start 347d 347d 15Aug-22 04-Oct-23 327d (1)1 Wo-148 g-22 29 Apr-23 29-Apr-23,I(1);1 Wo-148 to 11Wd-209 Milestones 185d 185d 15Sep-22 29Apr-23 196d 2'9-Apr-23,'Milest6nes WC1-MS-1000 1 Wo-149 to 1Wo-208 Start Od Od 15Se 22 79d ♦ to+ c� 08+Start WC1-MS-1010 1 Wo-149 to 1 Wo-208 Foundation Con Od Od 28-0ct-22 313d + 1 i W6-149 tb 1 Wo:208 Fbundationi Completion WC1-MS-1030 1 Wo-149 to 1Wo-208 Mechanical Con Od Od 25-Mar-23* 196d + 1 IWc-149 to 1Wo-20a Mechanical Completion(Req.Nov,10, WC1-MS-1040 1 Wo-149 to 1Wo-208 Substantial Corr Od Od 29-Apr-23* 196d f 1'WG149 to Substantial Completion(�eq.Dec: Summary 212d 212d 15Aug-22 29Apr-23 196d mm,mmr 29-Apr-23,(Summary: WC1SUM-1125 Direct Embed Foundations Summary( 22d 22d 01-Oct-22 26-Oct-22 130d I ^ I I I I I I WC1SUM-1130 Structure Framing Summary(5 person 19d 19d 01-Oct-22 22-Oct-22 306d j WC1SUM-1140 Structure Setting Crew(6 person crew) 25d 25d 11-Oct-22 08-Nov-22 92d min WC1SUM-1180 Structure Salvage(16 person crew) 7d 7d 18-Mar--23 25-Mar-23 196d WC1SUM-1150 Structure Setting Crew(6 person crew) 1d 1d 13-Mar--23 13-Mar-23 196d --- - --+-- - --;-- ----- --------- -- -------- ---- -- -- ---- WC1SUM-SUM Stringing Crew(29 person crew) 24d 24d 01-Nov-22 01-Deo-22 79d -- WC1SUM-1170 Stringing Crew for Cut In(29 person cr 5d 5d 13-Mar--23 17-Mar-23 196d WC1SUM-1120 Access Summary(1x29-person crew) 21d 21d 15Sep-22 08-Oct-22 144d WC1SUM-1126 Drilled Pier Foundations Summary(15 21d 21d 05-Oct-22 28-Oct-22 137d WC1SUM-1110 Project Management/OH Summary 212d 212d 15Aug-22 29Apr-23 196d WC1SUM-1105 Engineering and Design Project Suppc 212d 212d 15Aug-22 29Apr-23 196d (6)1 We-1 (Dave Johnson)to 1 We-49B(Amassa) 418d 20-Jut-22 30-11 wmmmmwmm.mV 3,0-Nov 23j(6)1 Wo-a (Dave John Milestones 186d 186d I 28-Apr-23 30-Nov-23 278d 30-Nov+23;Milestones WC6-MS-6000 1We:Dave Johnson to Amassa SS Cc Od Od 28-Apr-23 110d + 1Wc;Dave'Johnsbn to Amassa SS Construbtioh Start WC6-MS-6010 1We:Dave Johnson to Amassa SS Fol Od Od 20Sep-23 183d + 1Wc:;Dae Johnson toAmaSsa;SS Found r - -- -- WC6-MS-6030 1Wc:Dave Johnson to Amassa SS Me Od Od 26-Oct-23* 152d * 1W&Dave:Johnson to Amassa S$M' WC6-MS-6040 1Wc:Dave Johnson to Amassa SS Su Od Od 30-Nov-23* 278d 1IWe: Dave Johngon;toAmassa S Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline OIL= Critical Remaining Work Page 2 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J F M A M J J A S O N D J F M A M J J A S O Summary 418d 418d 20,Jul-22 30-Nov-23 278d —TNOV-23 burnmary WC6SUM-6130 Access Summary(1x8-person crews) 8d 8d 28-Apr-23 06-May-23 278d •0 WC6SUM-6140 Direct Embed Foundations Summary( 17d 17d 01Sep-23 20-Sep-23 22d P j --.- ------ WC6SUM-6160 Structure Framing Summary(5 person 15d 15d 02Aug-23 18-Aug-23 50d d WC6SUM-6170 Structure Setting Crew(6 person crew) 18d 18d 14Sep-23 04-W-23 16d 4 WC6SUM-6190 Structure Salvage(16 person crew) 7d 7d 11-May-23 18-May-23 110d WC6SUM-6180 Stringing Crew(29 person crew) 19d 19d 05-Oct-23 26-Od-23 Od WC6SUM-6150 Drilled Pier Foundations Summary(15 14d 14d 19-Jul-23 03-Aug-23 68d WC6SUM-6100 Engineering and Design Procurement 27d 27d 20-Jul-22 19-Aug-22 81d WC6SUM-6120 Project Management/OH Summary 396d 396d 15Aug-22 30-Nov-23 278d WC6SUM�110 Engineering and Design Project Suppc 396d 396d 15Aug-Aug 3 1 0-Nov-23 278d c�9B(Amassa)to 1 We-148 586d 586d 15 Aug 22 9-Jul-24 19,Ju1-24, Milestones 368d 368d 08-May-23 19-Jul-24 88d ;19;,Jul-24„ WC7-MS-7000 Amassa—1 We 148 Construction Star Od Od 08-May-23 278d + Amassa—I 1 VVc 14&C0 ns ruGtioq Start WC7-MS-7020 Amassa—1 We 148 Foundation Coml Od Od 16-Nov-23 172d ♦ Amassa}1,W¢148 Kouridation Co WC7-MS-7030 Amassa—1 We 148 Mechanical ComF Od Od 14 Jun-24* Od ♦ Amassa+1 WC7-MS-7040 Amassa—1 We 148 Substantial Comr Od Od 19-Jul-24* 88d ♦:Amassa Summary 586d 586d 15Aug-22 19-Jul-24 88d 19,Jul-24, WC7SUM-7130 Access Summary(1x8-person crews) 27d 27d 08-May-23 07-Jun-23 284d e WC7SUM-7140 Direct Embed Foundations Summary(: 37d 37d 05-Oct-23 16-Nov-23 152d 4 WC7SUM-7160 Structure Framing Summary(5 person 29d 29d 05-Oct-23 07-Nov-23 168d WC7SUM-7170 Structure Setting Crew(6 person crew) 36d 36d 13-Oct-23 23-Nov-23 161d + 4 i WC7SUM-7190 Structure Salvage(16 person crew) 18d 18d 19-May-23 08-Jun-23 305d •� WC7SUM-7180 Stringing Crew(29 person crew) 38d 38d 02-May-24 14-Jun-24 Od WC7SUM-7150 Drilled Pier Foundations Summary(15 17d 17d 05-Oct-23 24-W-23 173d e WC7SUM-7120 Project Management/OH Summary 586d 586d 15Aug-22 19,Jul-24 88d WC7SUM-7110 Engineering and Design Project Suppc 586d 586d 15 Aug-22 19-Jul-24 88d (8)1 Wo-209 tot We-267(He 605d 15 Aug-22 r 10-Au' 10-'Aug - ------------------------------------------------- Milestones - - - -360d 360d 08-Jun-23 10-Aug-24 69d 10Aug WC8-MS-8030 We-209 to Heward Mechanical Comple Od Od 06-Jul-24* Od * VVo:209 to WC8-MS-8040 We-209 to Heward Substantial Comple Od Od 10-Aug-24* 69d ♦ WG20 WC8-MS-8000 1Wc-209-Heward Construction Start Od Od 08-Jun-23 284d * 1 We-209 Heward Construction Start Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort Remaining Work Primary Baseline Critical Remaining Work Page 3 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J F M A M J J A S O N D J F M A M J J A S O WC8-MS-8010 1 We-209-Heward Foundation Comple Od Od 13-Dec-23 168d 1 We-209�Hewerd Foundation C Summary 605d 605d 15Aug-22 10-Aug-24 69d :10 Aug WC8SUM-8130 Access Summary(1x8-person crews) 26d 26d 08,Jun-23 07,Jul-23 284d 4 WC8SUM-8140 Direct Embed Foundations Summary( 23d 23d 17-Nov-23 13-Dec-23 152d WC8SUM-8160 Structure Framing Summary(5 person 19d 19d 08-Nov-23 29-Nov-23 168d WC8SUM-8170 Structure Setting Crew(6 person crew) 22d 22d 25-Nov-23 20-Dec-23 156d WC8SUM-8190 Structure Salvage(16 person crew) 6d 6d 08-Jul-23 14-Jul-23 292d go WC8SUM 8180 Stringing Crew(29 person crew) 19d 19d 15 Jun-24 06-Jul-24 Od 4 WC8SUM-8150 Drilled Pier Foundations Summary(15 6d 6d 25-Oct-23 31-Oct-23 197d S WC8SUM-8120 Project Management/OH Summary 605d 605d 15Aug-22 10-Aug-24 69d WC8SUM-8110 Engineering and Design Project Suppc 605d 605d 15Aug-22 10-Aug-24 69d (9)1 We-268(Heward)-1 We-7/2(Shirley Basin) 654d 654d 20-Jul-22 11-Sep- 11 Milestones 285d 285d 05-Oct-23 11-Sep-24 42d 11 WC9-MS-9000 Heward SS to Shirley Basin SS Constr Od Od 05-Oct-23 327d Weward SS tq Shirhy Basin SS Constru� WC9-MS-9010 Heward SS to Shirley Basin SS Found; Od Od 24-Jan-24 240d * Hjeward'SS to 81h&y Basin WC9-MS-9030 Heward SS to Shirley Basin SS Mecha Od Od 07 Aug-24* Od HeWard P- d WC9-MS-9040 Heward SS to Shirley Basin SS Substa Od Od 11Se 24* 42d ♦ He Summary 654d 654d 20-Jul-22 11Sep-24 42d 11 WC9SUM-9130 Access Summary(1x8-person crews) 21d 21d 05-Oct-23 28-Od-23 232d e WC9SUM-9140 Direct Embed Foundations Summary(: 27d 27d 14-Dec-23 24-Jan-24 152d WC9SUM-9160 Structure Framing Summary(5 person 22d 22d 30-Nov-23 04-Jan-24 169d Q di-- -- --- -- WC9SUM-9170 Structure Setting Crew(6 person crew) 24d 24d 03-Jan-24 30-Jan-24 152d WC9SUM-9190 Structure Salvage(16 person crew) 12d 12d 10-Oct-23 23-Od-23 311d e WC9SUM-9180 Stringing Crew(29 person crew) 27d 27d 08-Jul-24 07-Aug-24 Od e WC9SUM-9150 Drilled Pier Foundations Summary(15 7d 7d 01-Nov-23 08-Nov-23 209d WC9SUM-9100 Engineering and Design Procurement 27d 27d 20,Jul-22 19-Aug-22 81d e l ----------,--;--'--+--;--' --+--+--;----- ----- --------------------- -- -- -- -- WC9SUM-9120 Project Management/OH Summary 632d 632d 15Aug-22 11Sep-24 42d WC9SUM-9110 Engineering and Design Project Suppc 632d 632d 15Aug-22 11Sep-24 42d Element 1 Summary-1 Wa 399d 399d 20,Jul-22 08-Nov-23 297d U8-Nov-23, Element 1 Summary's 1 EL1SUM-9020 Element 1 -Mobilization(80%) Od Od 15Sep-22 647d ♦'Element I -Mobilization($00%) EL1SUM-9030 Element 1 -Mobilization(20%)(to start 161d 161d 15Sep-22 01Apr-23 107d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 4 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I F M A M J J A S O N D J F M A M J J A S O EL1-SUM-9070 Engineering and Design Procurement 27d 27d 20-Jul-22 19-Aug-22 73d o , (2)W&(Whdstar)to 1Wa-54 279d 279d 15Aug-22 17-Jul-2 129dmmmmmm.mV:17,Jul-23,(2)Wa4(Whdstat)to 1 Wa-54 Milestones 252d 252d 15Sep-22 17,Jul-23 129d ;17,Jul-23,Milestones WA2-MS-2000 WindstarSSto 1 Wa54 StartConstrur Od Od 15Sep-22 7d ♦IWihdstarlSSIo 1 Wa54 Star'tCbnstrudimi WA2-MS-2010 WindstarSSto 1 Wa54 Foundation C, Od Od 23-Nov-22 291d ♦ V_VindstarS_S to 1 VVaj54:Fwndatign 4ompletion -- - - a5 WA2-MS�030 V�ndstar SS to 1 Wa-54 Medtarical C Od Od 12tilun-23* 129d ♦ Wndstar SS to 1 Wa-54 Mechanical Completion'(R WA2-MS-2040 WndstarSSto 1 Wa-54 Su bstantial C, Od Od 17,Jul-23* 129d ♦;VVindgtar;SSto 1 Wa-54 SubstahtialCbmpletion; Summary 279d 279d 15 Aug-22 17,Jul-23 129d j 1y,Jul-23;,S{mrnary WA2-SUM-2130 Access Summary(1x8-person crews) 21 d 21 d 15Sep-22 08-Oot-22 7d WA2-SUM-2140 Direct Embed Foundations Summary( 17d 17d 27-Oct-22 15-Nov-22 130d e -- -- --- --------------- WA2-SUM-2160 Structure Framing Summary(5 person 16d 16d 01-Oct-22 19-W-22 163d P WA2-SUM-2170 Structure Setting Crew(6 person crew) 26d 26d 034Nov-22 06-Dec22 140d WA2-SUM-2180 Stringing Crew(29 person crew) 29d 29d 01-May-23 02-Jun-23 Od WA2-SUM-2150 Drilled Pier Foundations Summary(15 22d 22d 29-Oct-22 23-Nov-22 143d WA2-SUM-2120 Project Management/OH Summary 279d 279d 15Aug-22 17-Jul-23 129d -- -- --- -------- WA2-SUM-2110 Engineering and Design Project Suppc 279d 279d 15Aug-22 17-Jul-23 129d (3)1Wa-344(Shirley Basin) to 1 Wa-227 319d 319d 15-Aug-22 01-Sep-23 89d 01-$ep-23,(3)lWa* (Shid�y$as;n) to I Milestones 271d 271d 10-Oct-22 01Sep-23 89d v 01-8ep 23j Milestones WA3-MS3000 1Wa-344 -1Wa-227 Construction Starl Od Od 104Oct-22 7d ♦ `IWa-344 r 1Wa;227 Cbnstrudtioh Start; WA3-MS3010 1Wa-344 -1Wa-227 Foundation Comr Od Od 03,Jun-23 137d * Wa-344 !Wa-�27 Found atign Oornplgtiorr --, ---- WA3-MS3030 1 Wa344-1 Wa-227 Mechanical Corr Od Od 28-Jul-23* 89d cal CoMplet 11V1/e344-�1 VVa-227 Ms;chani ion(f WA3-MS3040 1 Wa344-1 Wa-227 Substantial Com Od Od 01Sep-23* 89d * VVh344= 1 VVa 227 SlubstarXtial;Completio Summary 319d 319d 15Aug-22 01Sep-23 89d 01-8ep.23 Siumriiary WA3-SUM-3103 Access Summary 1 (1x8-person crews) 58d 58d 10-Oct-22 19-Dec22 7d WA3-SUM-3104 Direct Embed Foundations 1 Summaq 29d 29d 16-Nov-22 22-Dec-22 130d WA3-SUM-3106 Structure Framing Summary 1 (5 perse 28d 28d 16-Nov-22 21-Dec-22 140d WA3-SUM-3108 Structure Setting Crew 1 (6 person crei 14d 14d 07-Dec-22 22-Dec-22 140d e WA3-SUM-3109 Stringing Crew(29 person crew) 48d 48d 03-Jun-23 28-Jul-23 Od T WA3-SUM-3105 Drilled Pier Foundations 1 Summary(1 21 d 21 d 28-Nov-22 21-Dec-22 151 d WA3-SUM-3102 Project Management/OH Summary 319d 319d 15Aug-22 01Sep-23 89d Mimi -- - WA3-SUM-3101 Engineering and Design Project Suppc 319d 319d 15Aug-22 01Sep-23 89d (4)1 Wa-227 to 1 Wa-5 77d 377d 15 Aug 22 08-Nov-23 31d 0,8-Nov-23,(4)1W, a-22r'to 1 Wa-55 Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 5 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A I S O N D J F M A M J J A S O N D J F M A M J J I A S O -Dec-22 08-Nov-23 ov- Milestones:Milestones 271d 271 d 20 WA4-MS4000 1 Wa-227-1 Wa55 Construction Stara Od Od 20-0eo-22 7d ♦' 1 WVa 1227-I Wa65 Construction$tart WA4-MS4010 1 Wa-227-1 Wa55 Foundation Comr Od Od 19-Aug-23 70d ♦I 1 UVaa27- 1 1IUa55 FAuhdatiort Comoletion - -�-- 1--------------'---1--�----------- WA4-MS4030 1 Wa-227-1 Wa55 Mechanical Com Od Od 04-Oct-23* 31d * 27 a�55 Mgch�nical OoMplg WA4-MS4040 1 Wa-227-1 Wa55 Substantial Comp Od Od 08-Nov-23* 31d ti V1/a 27-1 M55 SObsBantial Co Summary 377d 377d 15Aug-22 08-Nov-23 31d 08-Nov-23,Summary WA4-SUM-4103 Access Summary 2(1x8-person crew) 94d 94d 20-0eo-22 15Apr-23 107d WA4-SUM-4104 Direct Embed Foundations 2 Summan 62d 62d 09,Jun-23 19-Aug-23 7d . ; , , WA4-SUM-4106 Structure Framing Summary2(5 persc 50d 50d 25-May-23 21-Jul-23 32d WA4-SUM-4107 Structure Setting Crew 2(6 person crei 53d 53d 28-Jun-23 28-Aug-23 7d �d WA4-SUM-4108 Stringing Crew(29 person crew) 58d 58d 29-Jul-23 04-W-23 Od WA4-SUM-4105 Drilled Pier Foundations 2 Summary(1 32d 32d 24-May-23 29-Jun-23 51 d now WA4-SUM-4102 Project Management/OH Summary 377d 377d 15Aug-22 08-Nov-23 31d WA4-SUM-4101 Engineering and Design Project Suppc 377d 377d 15Aug-22 08-Nov-23 31d Element 3 Summary-Aeolus to Freezeout 390d 390d 20-Jul-22 28-W-23 306d 2S-Oct-23,Element 3 Summary-Aeol EL3-SUM-9040 Element 3-Mobilization(80%) Od Od 15Sep-22 647d ♦ Elomont 3-Mobilization($0%0) EL3SUM-9050 Element 3-Mobilization(20%)(to start 173d 173d 15Sep-22 15 Apr-23 110d 390d 390d 20-Jut-22 28Oct-2 28-Oct-23,(5)AF-1 to AF51; ---;--; --; - -- --'-- --------------------------- -- -- - ---- Milestones 168d 168d 17Apr-23 28-0ct-23 1d 28-Oat-23,Mil6st6ne AF5-MS5000 Aeolus SS to Freezeout SS Constructi4 Od Od 17 Apr-23 110d ♦ Aeolus SS to Freezeout SS CoHstnktion$tart AF5-MS5020 Aeolus SS to Freezeout SS Foundatioi Od Od 31-Aug-23 38d Aeolus SS to Fre6zebutl SS Foundation Coft AF5-MS5030 Aeolus SS to Freezeout SS; Mechanic Od Od 14-Oct-23* Od ♦:Aeplus S$tq Frge2;eogt S;S; I ephanic� AF5-MS5040 Aeolus SS to Freezeout SS;Substanti; Od Od 28-Oct-23* 1 d Ae olds SS to Fredzebut LSSt Substanti Summary 390d 390d 20,Jul-22 28-W-23 1d 20-W-23,Summary, AF5SUM5103 Access Summary(1x8-person crew) 10d 10d 17 Apr-23 27Apr-23 110d AF5SUM5104 Direct Embed Foundations Summary( 10d 10d 21Aug-23 31-Aug-23 12d AF5SUM5106 Structure Framing Summary(5 person 9d 9d 22,Jul-23 01-Aug-23 38d AF5SUM5107 Structure Setting Crew(6 person crew) 14d 14d 29Aug-23 13Sep-23 7d --r--, --,-- AF5SUM5109 Structure Salvage(16 person crew) 1d 1d 28Apr-Apr 28Apr-Apr 120d7-7 ll AF5SUM5108 Stringing Crew(29 person crew) 13d 13d 30Sep-23 14-W-23 Od AF5SUM5105 Drilled Pier Foundations Summary(15 16d 16d 30,Jun-23 I 18,Jul-23 55d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 6 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S 1 O N D J I F M A M J J A S O N D J F M A M J J A S O AF5SUM-5100 Engineering and Design Procurement 27d 27d 20-Jut-22 19-Aug-22 204d o , AF5SUM-6102 Project Management/OH Summary 368d 368d 15Aug-22 28-Oct-23 1 d AF5SUM-5101 Engineering and Design Project Suppc 368d 368d 15Aug-Aug 28-0ct-23 1d • • • •• 03-Febr23,Material Prdcurement ALL-MAT-1240 Prepare&Submit Material RFQ's 5d 5d 20-Jul-22 25-Jul-22 !73dALL-MAT-1250 Quote Submission Period 10d 10d 26�Jul-22 05-Aug-2273d ALL-MAT-1260 Evaluation of Quotes 5d 5d 06Aug-22 11-Aug-22 73d ALL-MAT-1270 Award Suppliers(Place Orders&Enter 8d 8d 12Aug-22 19-Aug-22 85d 8 EL1-MAT-1290 Element 1 -Insulators+Hardware Mat Od Od 19-Aug-22 73d ♦' Element i1 -'Insulators+Hardware Material Order Progress Payment,(15%clown) EL2-MAT-1280 Element 2-Insulators+Hardware Mat Od Od 19-Aug-22 81d ♦: Element,2-:Insulators+Hardware Material Order Progress Payment(15%down) EL3-MAT-1300 Element 3-Insulators+Hardware Mat Od Od 19-Aug-22 204d ♦I Element j3-',Insulatore+Hardware Ma{eHei Order Progrese Payment(1$%down) Material Receipt 78d 78d 25-Oct-22 03-Feb-23 436d V!E�IF 03-Feb,23'I Material Receipt 3-D i riority -- -- -- -- © P Priority Order 1 25-Oct-2= 03-Dec-22 ed-2Z Order 1 WC1-MAT-1200 Priority Order 1 -Section WC 1:Wo-14f 40d 40d 25-Oct-22 03-Dec-22 106d I A ©3-Febr23,Priority Order 2 Priority Order 2 1,lan- 03-Feb-23 52076 WA2-MAT-1220 Priority Order 2-Section WA2:Wa-1 to 14d 14d 21-Jan-Jan 03-Feb-23 86d WA3-MAT-1230 Priority Order 2-Section WA3:Wa-344 14d 14d 21 plan-23 03-Feb-23 119d WA4-MAT-1240 Priont Order 2 Section WA4:Wa-227 14d 14d 21-Jan-Jan 03-Feb-23 175d r ; --;-- -,- y AF5-MAT-1250 Priority Order 2-Section AF5:AF-1 to E 14d 14d 21-Jan-Jan 03-Feb-23 238d WC6-MAT-1260 Priority Order 2-Section WC6:Wo-1 R 14d 14d 21-Jan-Jan 03-Feb-23 243d B WC7-MAT-1270 Priority Order 2-Section WC7:Wo-491 14d 14d 21-Jan-Jan 03-Feb-23 453d WC8-MAT-1280 Priority Order 2-Section WC8:Wo-20E 14d 14d 21-Jan-Jan 03-Feb-23 497d B WC9-MAT-1290 Priont Order 2-Section WC9:Wo-7/2 14d 14d 21-Jan-Jan 03-Feb-23 520d T ; y Od Od . ® . 07-Aul Pre-Construction Activities 602d 602d 15 Aug-22 07-Aug-24 Od 07Aue Construction Mobilization 72d 72d 15-Aug-22 0 - - �� ©5-Nov-22,Con§truftioh Mobiliza'tiori - --r--, --,-- -- - - ---- -- ALL-PRE-3000 Pre-Construction Mobilization&Site Oi 72d 72d I 15-Aug-22" 05-Nov-22 Od Project Setup 30d 15-Aug-22 17-Sep-22 ►I 17FSe�p-22,Project)Setup) ALL-PRE-3010 Setup Project Infrastructure;offices,lad 30d 30d 15-Aug-22 17-Sep-22 7d B Construction Staking d 162d 18-Aug-22 06-Mar-23 105d V mmW 06-Mar,-23,Construction Staking Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 7 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D J F M A M J I J I A S O N D J F M A M J J A S O ALL-PRE-3020 Staking of Clearing and ROW Bounda 24d 24d 18 Aug-22 14-Sep-22 7d I I -- -- -- ALL-PRE-3030 Initial Construction Layout,Confirmatic 150d 150d 01Sep-22 06-Mar-23 105d Material Management' OM b7-Auk ALL-PRE-3040 Mal Management(In Yard)3 pers< 602d 602d 777 AugDistribution of Materials 570d 570d 07-Aul ALL-PRE-3050 Material Distribution Along ROW 570d 570d (1)1Wc-149to1We-208(September 15,2022 March1,. p -- 25-Mar-23,,1-- ' - - -- (September-' --O22 - 155d 155d 15Se 22 25-Mar-23 196d O I1 Wa1#9 to 1,WG2Q8 15,2 Access Installation(2 Crews) ep-22 08Oct- ITOW 08-Octr22,'ACcegs lhstallation;(2 Crews) WC1-ACS 1200 Access Installation Pull 18c:We-149-\ 4d 4d 15Sep-22 19Sep-22 79d f WC1-ACS-1210 Access Installation Pull 19c:We-165-\ 3d 3d 20Sep-22 22Sep-22 105d WC1-ACS-1220 Access Installation Pull 20c:We-180 V 4d 4d 23Sep-22 27Sep-22 107d �I p- p- ---I --,- - ---------_ WC1-ACS-1230 Access Installation Pull 21c:We-189A- 3d 3d 28Se 22 30Se 22 107d WC1-ACS-1240 Access Installation Pull 22c:We-204-\ 4d 4d 01-Oct-22 05-0ct-22 118d WC1-ACS-1250 Access Installation Pull23c:Cutovertc 3d 3d 06-Oct-22 08-Oct-22 144d irect Embe t- 26Oct- VOW 26-O,ct-22,Direct Embed Foundations WC1-DEF-1300 Direct Embed Foundations Pull 18c:W 6d 6d 01-Oct-22 07-Od-22 86d WC1-DEF-1310 Direct Embed Foundations Pull 19c:W 5d 5d 08-Oct-22 13-Od-22 92d WC1-DEF-1320 Direct Embed Foundations Pull 20c:W 3d 3d 14-Oct-22 17-Od-22 93d WC1-DEF-1330 Direct Embed Foundations Pull 21c:W 6d 6d 18-Oct-22 24-W-22 93d WC1-DEF-1340 Direct Embed Foundations Pull 22c:W 1d 1d 25-Oct-22 25-0ct-22 102d WC1-DEF-1350 Direct Embed Foundations Pull 23c:C, 1d 1d 26-Oct-22 26-0ct-22 130d Dulled Pier Foundation 05-0ct- 28-0Oct-2 28 Qct- 2,;Dri ed Pi�rFpurx io4� WC1-DPF-1400 Drilled Pier Foundations Pull 18c:Wo-1 5d 5d 05-Oct-22 10-Oct-22 137d , , WC1-DPF-1410 Drilled Pier Foundations Pull 19c:Wo-1 5d 5d 11-0ct-22 15-0ct-22 137d WC1-DPF-1420 Drilled Pier Foundations Pull 20c:Wo-1 3d 3d 17-Oct-22 19-Od-22 137d j WC1-DPF-1430 Drilled Pier Foundations Pull 21c:Wo-1 5d 5d 20-Oct-22 25-Od-22 137d WC1-DPF-1440 Drilled Pier Foundations Pull 22c:Wo-2 2d 2d 26-Oct-22 27-W-22 137d WC1-DPF-1450 Drilled Pier Foundations Pull23c:Cuto 1d 1d 28-Oct-22 28-0ct-22 137d Frame Structures 9d 01-Oct 22 22-0ct-2 22-0ct-2 , game Structures WC1-FRM-1500 Frame Structures Pull 18c:Wo-149-W 5d 5d 01-Oct-22 06-Oct-22 79d WC1-FRM-1510 Frame Structures Pull 19c:Wo-165-W I 4d 4d 07-Oct-22 11-Oct-22 94d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 8 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I Fl M A M J I J I A S O N D J I F I M A M J J A S O WC1-FRM-1520 Frame Structures Pull 20c:Wo-180 W 3d 3d 12-Oct-22 14-Oct-22 96d WC1-FRM-1530 Frame Structures Pull 21c:Wc-189A-\ 5d 5d 15-Oct-22 20-Oct-22 96d 8 WC1-FRM-1540 Frame Structures Pull 22c:Wo-204-W 1d 1d 21-Oct-22 21-Oct-22 105d WC1-FRM-1550 Frame Structures Pull 23c:Cutoverto 1 1dt6d 22-Oct-22 22-Oct-22 306d Set Structures(Including 3-Pole Framing) 11-Oct-22 13-Mar-23 L 13�Mq- ,, n� je ( Frpmjnga r2 -Set t Jctu, s, Inpl u ing 3 0l WC1-SET-1600 Set Structures Pull 18c:Wo-149-Wc1I 6d11-Oct-22 17-Oct-22 79dWCISET--1610 Set Structures Pull 19c:Wo-165-Wo-1 6d18-Oct-22 24-Oct-22 89dWCISET--1620 Set Structures Pull 20c:Wo-180 Wo-1I 4d 25-Oct-22 28-Oct-22 89d A WCISET--1630 Set Structures Pull 21c:Wo-189A-Wd 7d 7d 29-Oct-22 05-Nov-22 89d 8 WCISET-1640 Set Structures Pull 22c:Wo-204-Wc21 2d 2d 07-Nov-22 08-Nov-22 92d WCISET-1660 Set Structures Pull 23c:Cutoverto Ling 1d 1d 13-Mar--23 13-Mar-23 196d WCISET-1650 *OUTAGE START` Od Od 13-Mar-23* Od ;♦ *OUTAGE START* WC1SET-1670 *OUTAGE COMPLETE* Od Od 13-Mar-23 196d ;♦I*OUTAGE COMPLETE* Wire Stri 17,Mar--23,Wire Stringing; WC1-STR-1700 Conductor Stringing Pull 18c:Wo-149• 5d 5d 01-Nov-22 05-Nov-22 79d -- I-- --,- - WCISTR-1710 Conductor Stringing Pull 19c:Wo-165 5d 5d 07-Nov-22 11-Nov-22 79d ;A WCISTR-1720 Conductor Stringing Pull 20c:Wo-180 5d 5d 12-Nov-22 17-Nov-22 79d 8 WC1STR-1730 Conductor Stringing Pull 21c:Wo-189A 5d 5d 18-Nov-22 23-Nov-22 79d 8 WC1STR-1740 Conductor Stringing Pull 22c:Wo-204• 4d 4d 28-Nov-22 01-Dec22 79d A WC1STR-1760 Conductor Stringing Pull 23c:Cutover, 4d 4d 14-Mar--23 17-Mar-23 196d -- - *O. ,G --;- WC1STR-1750 *OUTAGE START* Od Od 13-Mar-23* Od i♦ UTA STAFFT* WC1-STR-1770 *OUTAGE COMPLETE* Od Od 17-Mar-23 196d ♦I*OUTAGE COMPLETE* Structure Salvag 25-Mar- I A 2$-M,ar--�3,6trgct6re$alyag,e WC1-SLV-1800 Structure Salvage Pull 22c:Wo-204-V 1d 1d 18-Mar--23 18-Mar-23 196d WC1SLV-1820 Structure Salvage Pull 20c:Wo-180 W 1d 1d 22-Mar--23 22-Mar-23 196d WC1SLV-1830 Structure Salvage Pull 19c:Wo-165 V 1d 1d 23-Mar--23 23-Mar-23 196d WC1SLV-1840 Structure Salvage Pull 18c:Wo-149-V 2d 2d 24aVlar-Mar 25-Mar-23 196d �I WC1SLV-1810 Structure Salvage Pull 21c:Wo-189A- 2d 2d 20-Mar-23 21-Mar-23 196d (2)1Wa-1 (Windstar)to 1 Wa-54(Finish by August 10,202' 222d 222d 15-Sep-22 12-Jun-23 129d ;12Tlun-23,(2)1VVa-,1 (1MrldsFdr)to 1Wa 54(Finish by I Access Installation(2 Crews) 21d 15-Sep-22 08-Oct-22 _ Access Installation;(2 Crews); r7 08-Oct 22j Alice r W42-ACS-2200 Access Installation Pull la:Windstar-\ 3d 3d 15-Sep-22 17-Sep-22 7d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 9 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S I O N D J I F M A M J I J I A S O N D J I F I M A M J J A S O WA2-ACS-2210 Access Installation Pull 2a:Wa-1 -Wa 3d 3d 19-Sep-22 21-Sep-22 7d WA2-ACS-2220 Access Installation Pull 3a:Wa-2-Wa- 3d 3d 22Sep-22 24Sep-22 7d WA2-ACS-2230 Access Installation Pull 4a:Wad-Wa- 2d 2d 26Sep-22 27Sep-22 7d �I WA2-ACS-2240 Access Installation Pull 5a:Wa-18-We 3d 3d 28Sep-22 30Sep-22 7d WA2-ACS-2250 Access Installation Pull 6a:Wa26-We 2d 2d 01-Oct-22 03-Od-22 7d WA2-ACS-2260 Access Installation Pull 7a:Wa42-We 3d 3d 04-Oct-22 06-Od-22 7d WA2-ACS-2270 Access Installation Pull 8a:Wa45-We 2d 2d 07-Oct-22 08-0ct-22 7d Direct Embed Foundations 27-Oct-22 15-Nov-2 130d VV;15-Nov-2;2,Direct Embed:Foundations: WA2-DEF2300 Direct Embed Foundations Pull 3a:Wa 1d 1d 27-Oct-22 27-Oct-22 130d ---------- N- - --+- - -- -- ----- -------- ---- -- -- -- -- WA2-DEF2310 Direct Embed Foundations Pull 4a:Wa 4d 4d 28-Oct-22 01-Nov-22 130d WA2-DEF2320 Direct Embed Foundations Pull 5a:Wa 2d 2d 02-Nov-22 03-Nov-22 130d WA2-DEF2330 Direct Embed Foundations Pull 6a:Wa 6d 6d 04-Nov-22 10-Nov-22 130d WA2-DEF2340 Direct Embed Foundations Pull 7a:Wa 1d 1d 11-Nov-22 11-Nov-22 130d WA2-DEF 2350 Direct Embed Foundations Pull 8a:Wa 3d 3d 12-Nov-22 15-Nov-22 130d A Dulled Pier Foundatio 29 Oct-22 23-Nov-2 VOW 23-Nbv-22,I,Drilledl Pidr Fbundations WA2-DPF2400 Drilled Pier Foundations Pull 1a:WindE 1d 1d 29-Oct-22 29-Oct-22 137d WA2-DPF2410 Drilled Pier Foundations Pull 2a:Wa-1 • 2d 2d 31-Oct-22 01-Nov-22 137d WA2 DPF2420 Drilled Pier Foundations Pull 3a:Wa-2• 2d 2d 02-Nov-22 03-Nov-22 137d WA2 DPF2430 Drilled Pier Foundations Pull 4a:Wa-4• 5d 5d 04-Nov-22 09-Nov-22 137d WA2 DPF2440 Drilled Pier Foundations Pull 5a:Wa-1 f 5d 5d 10-Nov-22 15-Nov-22 139d 0 WA2 DPF2450 Drilled Pier Foundations Pull 6a:Wa-2f 2d 2d 16-Nov-22 17-Nov-22 141d WA2 DPF2460 Drilled Pier Foundations Pull 7a:Wa-4: 2d 2d 18-Nov-22 19-Nov-22 143d j WA2-DPF 2470 Drilled Pier Foundations Pull 8a:Wa-4! 3d 3d 21-Nov-22 23-Nov-22 143d e Structures 01-Oct-22 19-0ct-22 163d TV:19-Odt-22,Frame Structures - --r--, --;- WA2 FRM-2500 Frame Structures Pull 3a:Wa-2-Wa-4 1d 1d 01-Oct-22 01-W-22 163d WA2 FRM-2510 Frame Structures Pull 4a:Wa-4-Wa-1 4d 4d 03-Oct-22 06-W-22 163d f WA2 FRM-2520 Frame Structures Pull 5a:Wa-18-Wa 2d 2d 07-Oct-22 08-W-22 163d WA2 FRM-2530 Frame Structures Pull 6a:Wa-26-Wa- 5d 5d 10-Oct-22 14-W-22 163d WA2 FRM-2540 Frame Structures Pull 7a:Wa-42-Wa- 1d 1d 15-Oct-22 15-W-22 163d -- ; WA2-FRM-2550 Frame Structures Pull 8a:Wa 45-Wa, 3d 3d 17 Oct-22 19-0ct-22 163d ` Set Structures(Including 3-Pole Framing) 03-Nov-22 06-Dec-22 1 V=.I 06-De6-22,Sot Stntctutes'(Intluding;3-Polo Framing) Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 10 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S I O N D J I F1 M A M J I J I A S O N D J I F I M A M J I J I A S O WA2-SET-2600 Set Structures Pull la:Windstar-Wa-1 1d 1d 03-Nov-22 03-Nov-22 140d WA2-SE17-2610 Set Structures Pull 2a:Wa-1 -Wa-2 1d 1d 04-Nov-22 04-Nov-22 140d WA2-SET-2620 Set Structures Pull 3a:Wa-2-Wa-4 1d 1d 05-Nov-22 05-Nov-22 140d WA2-SET-2630 Set Structures Pull 4a:Wa-4-Wa-18 6d 6d 10-Nov-22 16-Nov-22 137d A WA2-SET-2640 Set Structures Pull 5a:Wa-18-Wa-26 4d 4d 17-Nov-22 21-Nov-22 138d Q WA2-SET-2650 Set Structures Pull 6a:Wa-26-Wa-42 4d 4d 22-Nov-22 29-Nov-22 138d 8 WA2-SE17-2660 Set Structures Pull 7a:Wa-42-Wa-45 2d 2d 30-Nov-22 01-Dec-22 140d WA2-SET-2670 Set Structures Pull 8a:Wa-45-Wa-53/ 4d 4d 02-Dec-22 06-Dec-22 140d b l Wire Stringing 01-May 23 02tilun-2 �► ©2-Jun;23,1 WiYe Stringing WA2-STR-2700 Conductor Stringing Pull 1a:Windstar• 2d 2d 01-May-23* 02-May-23 Od WA2-STR-2710 Conductor Stringing Pull2a:Wa-1 -W< 2d 2d 03-May-23 04-May-23 Od WA2-STR-2720 Conductor Stringing Pull3a:Wa-2-W< 2d 2d 05-May-23 06-May-23 Od WA2-STR-2730 Conductor Stringing Pull4a:Wa-4-W< 5d 5d 08-May-23 12-May-23 Od WA2 STR-2740 Conductor Stringing Pull 5a:Wa-18-V 4d 4d 13-May-23 17-May-23 Od WA2 STR-2750 Conductor Stringing Pull 6a:Wa-26-V 5d 5d 18-May-23 23-May-23 Od WA2 STR-2760 Conductor Stringing Pull 7a:Wa-42-V 4d 4d 24-May-23 27-May-23 Od WA2 STR-2770 Conductor Stringing Pull 8a:Wa-45-V 5d 5d 29-May-23 02-Jun-23 Od Build Temporary Line&Cutover(Outage Required) 03-1un-23 12tiJun-23 129d W;12;,Juh-23,BUildTemporaty L'inel&Cutover(Qutdge --'-- -- -- ------------------------ -- -- -- -- -- WA2 TMP-2800 Build Temporary Line Pull 1T Temp 01 2d 2d 03,Jun-23 05,Jun-23 129d WA2 TMP-2810 Build Temporary Line Pull 2T Temp 05 2d 2d 06,Jun-23 07,Jun-23 129d WA2 TMP-2820 String Temporary Line Pull 1T Temp 01 2d 2d 08,Jun-23 09,Jun-23 129d WA2 TMP-2830 String Temporary Line Pull 2T Temp Of 2d 2d 10,Jun-23 12,Jun-23 129d (3)1Wa-344 (SIB)to 1Wa-227(Finish by November 10,20: 241d 241d 1O-Oct-22 28-Jul-23 Od 28,Ju1-20,(0)MOO 0)to1V1�a-227'(Finish: �'19 D�o-�2, cces�In jtall ptign(�Crete)Access Installation 2 Crews 10-Oct-22 _ 19-Dec-22_ WA3-ACS-3290 Access Installation Pull 20a:Wa-227 13d 13d 05-Dec-22 19-Dec-22 7d WA3-ACS-3280 Access Installation Pull 21 a:Wa-249- 13d 13d 16-Nov-22 03-Dec-22 7d WA3-ACS-3270 Access Installation Pull 22a:Wa-265 4d 4d 11-Nov-22 15-Nov-22 7d WA3-ACS-3260 Access Installation Pull 23a:Wa-272- 4d 4d 07-Nov-22 10-Nov-22 7d A ---' --- ----- -------- WA3-ACS-3250 Access Installation Pull 24a:Wa-290 4d 4d 02-Nov-22 05-Nov-22 7d d WA3-ACS-3240 Access Installation Pull 25a:Wa-307- 4d 4d 28-Oct-22 01-Nov-22 7d A WA3-ACS-3230 Access Installation Pull 26a:Wa,321 - 4d 4d 24-Oct-22 I 27-Od-22 7d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 11 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O 1 N I D I J F M A M J J A S O N D J F M A M J J A S O WA3-ACS-3220 Access Installation Pull 27a:Wa-329- 4d 4d 19-Oct-22 22-Oct-22 7d WA3-ACS-3210 Access Installation Pull 28a:Wa-340- 4d 4d 14-Oct-22 18-Od-22 7d 0 WA3-ACS-3200 Access Installation Pull 29a:Wa-344 4d 4d 10-Oct-22 13-Od-22 7d Direct Embed Foundations 08-lunl,23,Direct Erhbod Foundations WA3-DEF3380 Direct Embed Foundations Pull 20a:V1 8d 8d 31-May-23 08,Jun-23 7d WA3-DEF3370 Direct Embed Foundations Pull 21a:V\ 6d 6d 24-May-23* 30-May-23 7d 1' WA3-DEF3360 Direct Embed Foundations Pull 22a:V\ 3d 3d 20-0ec-22 22-Dec-22 130d --- -- -----}--'--'F T T -- -- ------------------------F-------- WA3-DEF3350 Direct Embed Foundations Pull 23a:V\ 7d 7d 12-0ec-22 19-Dec-22 130d WA3-DEF3340 Direct Embed Foundations Pull 24a:V\ 6d 6d 05-0ec-22 10-Dec-22 130d WA3-DEF3330 Direct Embed Foundations Pull 25a:V\ 5d 5d 29-Nov-22 03-Dec-22 130d A WA3-DEF3320 Direct Embed Foundations Pull 26a:V\ 3d 3d 22-Nov-22 28-Nov-22 130d 8 WA3-DEF3310 Direct Embed Foundations Pull 27a:V\ 4d 4d 17-Nov-22 21-Nov-22 130d A -- -- -- -- ------- - - - WA3-DEF3300 Direct Embed Foundations Pull 28a:V\ 1d 1d 16-Nov-22 16-Nov-22 130d j Dulled Per Foundations 28-Nov-22 21-Dec- *►, 21,-0gc- 2,prilMed;Pier FQurjdatjon$ WA3-DPF3470 Drilled Pier Foundations Pull 20a:Wa: 2d 2d 20-Dec-22 21-Dec-22 151d WA3-DPF3460 Drilled Pier Foundations Pull 21a:Wa: 2d 2d 15-0ec-22 16-Dec-22 151d WA3-DPF3450 Drilled Pier Foundations Pull 24a:Wa: 6d 6d 08-0ec-22 14-Dec-22 143d jt WA3-DPF3440 Drilled Pier Foundations Pull 25a:Wal' 2d 2d 06-Dec22 07-Dec22 143d WA3-DPF3430 Drilled Pier Foundations Pull 26a:Wal' 2d 2d 03-Dec-22 05-Dec22 143d WA3-DPF3420 Drilled Pier Foundations Pull 27a:Wal' 2d 2d 01-Dec22 02-Dec22 143d WA3-DPF3410 Drilled Pier Foundations Pull 28a:Wal' 2d 2d 294Nov-22 30-Nov-22 143d WA3-DPF 3400 Drilled Pier Foundations Pull 29a:Wal' 1d 1d 28-Nov-22 28-Nov-22 143d �y Frame Structures ov- 24-May-2 24-M 3,jFi�me Structure WA3-FRM-3580 Frame Structures Pull 20a:Wa-227-Vt 7d 7d 17-May-23 24-May-23 26d WA3-FRM-3570 Frame Structures Pull 21a:VUa-249-V5d 5d 16-Dec22 21-Dec22 140d WA3-FRM-3560 Frame Structures Pull 22a:Wa-265-Vt 2d 2d 14-Dec22 15-Dec22 140d j WA3-FRM-3550 Frame Structures Pull 23a:Wa-272-VA 6d 6d 07-Dec22 13-Dec22 140d - - - WA3-FRM-3540 Frame Structures Pull 24a:Wa-290-Vt 5d 5d 01-Dec22 06-Dec22 140d WA3-FRM-3530 Frame Structures Pull 25a:Wa3W-Vt 4d 4d 234Nov-22 30-Nov-22 140d WA3-FRM-3520 Frame Structures Pull 26a:Wa321 -V 2d 2d 21-Nov-22 22-Nov-22 140d WA3-FRM-3510 Frame Structures Pull 27a:Wa329-V 3d 3d 17-Nov-22 19-Nov-22 140d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 12 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J F I M I A I M J I J I A I S 1 O 1 N I D I J F M A M J J A S O WA3-FRM-3500 Frame Structures Pull 28a:Wa 340-V 1d 1d 16-Nov-22 16-Nov-22 140d L Set Structures(Including 3-Pole Framinq� j& 167d 07-Dec-22 27-Jun-23 mmmmV 27-Jun-23,;SetStructures(Including 3-Pole FraminJ WA3-SET-3690 Set Structures Pull 20a:Wa-227-Wa 6d 6d 21,Jun-23 27,Jun-23 3d WA3-SET-3680 Set Structures Pull 21a:Wa-249-Wa 4d 4d 16,Jun-23 20,Jun-23 3d Q WA3-SET-3670 Set Structures Pull 22a:Wa-265-Wa 2d 2d 14,Jun-23 15,Jun-23 3d WA3-SET-3660 Set Structures Pull 23a:VVa-272-Wa: 4d 4d 09-Jun-23* 13-Jun-23 3d 8 WA3-SEr-3650 Set Structures Pull 24a:VVa-290-Watt 4d 4d 19-0ec-22 22-Dec-22 140d A WA3-SET-3640 Set Structures Pull 25a:Wa307-Watt 4d 4d 14-0ec-22 17-Dec-22 140d A WA3-SET-3630 Set Structures Pull 26a:Wa321 -Watt 2d 2d 12-0ec-22 13-Dec-22 140d WA3-SET-3620 Set Structures Pull 27a:Wa329-Watt 2d 2d 09-0ec-22 10-Dec-22 140d WA3-SET-3610 Set Structures Pull 28a:Wa340-Watt 1d 1d 08-0ec-22 08-Dec-22 140d WA3-SEr-3600 Set Structures Pull 29a:Wa344-Strd, 1d 1d 07-0ec-22 07-Dec-22 140d Wire StringingJun- 28-Jul-23 TOWEV 28-JUI-23,Wire Stringing WA3-STR3790 Conductor Stringing Pull 20a:VVa-227• 6d 6d 22-Jul-23 28-Jul-23 Od WA3-STR3780 Conductor Stringing Pull 21a:VVa-249 5d 5d 17-Jul-23 21-Jul-23 Od WA3-STR3770 Conductor Stringing Pull 22a:VVa-265 4d 4d 12-Jul-23 15-Jul-23 Od - --' - - -- -- --------------- -- -- ---------- - - - WA3-STR3760 Conductor Stringing Pull 23a:VVa-272• 6d 6d 05-Jul-23 11-Jul-23 Od WA3-STR3750 Conductor Stringing Pull 24a:Wa-290• 6d 6d 28,Jun-23 04,Jul-23 Od WA3-STR3740 Conductor Stringing Pull 25a:Wa307• 5d 5d 22,Jun-23 27,Jun-23 Od WA3-STR3730 Conductor Stringing Pull 26a:Wa321 • 5d 5d 16,Jun-23 21,Jun-23 Od WA3-STR3720 Conductor Stringing Pull 27a:Wa329• 5d 5d 10,Jun-23 15,Jun-23 Od f WA3-STR3710 Conductor Stringing Pull 28a:Wa340• 4d 4d 06,Jun-23 09,Jun-23 Od j WA3-STR3700 Conductor Stringing Pull 29a:Wa344• 2d 2d 03,Jun-23 05,Jun-23 Od (4)1 Wa-228 to 1 Wa-55 (Finish by November 10,2023) 299d 299d 10-Oct-22 04-Oct-23 Od 04-Oct-23,I(4).1Wa-22& 11u;1 Wa-55 (Fins Access Installation(2 Crews) 152d 10-Oct-22 15Apr--23 107 15Apr--23,Access installation(2;Cr6m) WA4-ACS-4250 Access Installation Pull 9a:Wa-63A-V 12d 12d 03-Apr-23 15 Apr-23 107d WA4-ACS-4245 Access Installation Pull 10a:Wa-77-V 12d 12d 20-Mar--23 01 Apr-23 107d WA4-ACS-4240 Access Installation Pull 11 a:Wa-100-I 10d 10d 08-Mar--23 18-Mar-23 107d 8 WA4-ACS-4235 Access Installation Pull 12a:Wa-106 12d 12d 22-Feb-23 07-Mar-23 107d WA4-ACS-4230 Access Installation Pull 13a:Wa-119- 10d 10d 10-Feb-23 21-Feb-23 107d 8 WA4-ACS-4225 Access Installation Pull 14a:Wa-132- 12d 12d 27-Jan-23 09-Feb-23 107d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 13 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Fl 2023 2024 oat Comments (CD) (CD) A S O N I D I J I Fl M A M J J A S O N D J I F I M A M J I J I A S O WA4-ACS-4220 Access Installation Pull 15a:Wa-143- 4d 4d 24-Oct-22 27-Oct-22 212d WA4-ACS-4215 Access Installation Pull 16a:Wa-166- 4d 4d 19-Oct-22 22-Od-22 207d 0 WA4-ACS-4210 Access Installation Pull 17a:Wa-189- 4d 4d 14-Oct-22 18-Od-22 206d WA4-ACS-4205 Access Installation Pull 18a:Wa-201 - 4d 4d 10-Oct-22 13-Od-22 206d WA4-ACS-4200 Access Installation Pull 19a:Wa-213- 26d 26d 20-Dec-22 26-Jan-23 7d --'---- , -- -- --- --------- Direct Embed Foundations un- 19-Aug- Vm!=!W 19-AEI g- 23,©ire Embed Foundatibns WA4-DEF4350 Direct Embed Foundations Pull 9a:VVa 8d 8d 11-Aug-23 19-Aug-23 7d 8 1 WA4-DEF-4345 Direct Embed Foundations Pull 10a:V\ 8d 8d 02 Aug-23 10-Aug-23 7d WA4-DEF-4340 Direct Embed Foundations Pull 11a:W 2d 2d 31-Jul-23 01-Aug-23 7d WA4-DEF-4335 Direct Embed Foundations Pull 12a:V\ 4d 4d 26-Jul-23 29-Jul-23 7d A -- -- -- WA4-DEF-4330 Direct Embed Foundations Pull 13a:V\ 5d 5d 20-Jul-23 25-Jul-23 7d 8 WA4-DEF-4325 Direct Embed Foundations Pull 14a:V\ 4d 4d 15-Jul-23 19-Jul-23 7d 0 WA4-DEF-4320 Direct Embed Foundations Pull 15a:V\ 8d 8d 06-Jul-23 14-Jul-23 7d ;8 WA4-DEF4315 Direct Embed Foundations Pull 16a:V1 9d 9d 26,Jun-23 05,Jul-23 7d 8 WA4DEF4310 Direct Embed Foundations Pull 17a:V1 5d 5d 20,Jun-23 24,Jun-23 7d A WA4-DEF-4305 Direct Embed Foundations Pull 18a:V1 4d 4d 15,Jun-23 19,Jun-23 7d 8 WA4-DEF-4300 Direct Embed Foundations Pull 19a:V1 5d 5d 09,Jun-23 14-Jun-23 7d Q Drilled Pier Foundation 32d 24-May-23 29.1 �I 29ti1Un-23,;Drilledl Pier Fbundations WA4-DPF4435 Drilled Pier Foundations Pull 9a:Wa-5; 5d 5d 24,Jun-23 29,Jun-23 51d 1 WA4-DPF-4430 Drilled Pier Foundations Pull 10a:Wa- 6d 6d 17,Jun-23 23,Jun-23 48d 8 -- - r- r T-------------- WA4-DPF-4425 Drilled Pier Foundations Pull 12a:Wa-' 5d 5d 12,Jun-23 16,Jun-23 48d A WA4-DPF-4420 Drilled Pier Foundations Pull 13a:Wa-' 3d 3d 08,Jun-23 101jun-23 48d WA4-DPF-4415 Drilled Pier Foundations Pull 15a:Wa-' 6d 6d 01,Jun-23 07,Jun-23 41d B WA4-DPF-4410 Drilled Pier Foundations Pull 16a:Wa-' 3d 3d 29-May-23 31-May-23 40d WA4-DPF4405 Drilled Pier Foundations Pull 18a:Wa, 2d 2d 26-May-23 27-May-23 37d WA4-DPF-4400 Drilled Pier Foundations Pull 19a:Wa: 2d 2d 24-Ma 23 25-Ma 23 35d �T r--. ; ;- y- y- I I I I I I I I I I r Frame Structures 25-May-23 21-Jul-23 32d J"=N/j 21 JUI-23,Frame Strubtutesl WA4-FRM-4550 Frame Structures Pull 9a:Wa-53A-W. 6d 6d 15-Jul-23 21,Jul-23 32d 8 WA4-FRM-4545 Frame Structures Pull 10a:Wa 77-WE 6d 6d 08,Jul-23 14,Jul-23 30d 0 WA4FIRM-4540 Frame Structures Pull 11a:Wa-100-V1 2d 2d 06-Jul-23 07-Jul-23 30d -- -- -------------------------- --- -------------- WA4-FRM-4535 Frame Structures Pull 12a:Wa-106-Ut 3d 3d 03-Jul-23 05-Jul-23 30d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 14 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I F M A M J I J I A S O N D J I F M A M J J A S O WA4-FRM-4530 Frame Structures Pull 13a:Wa-119-V1 4d 4d 28-Jun-23 01,Jul-23 30d WA4-FRM-4525 Frame Structures Pull 14a:Wa-132-V 3d 3d 24-Jun-23 27-Jun-23 30d Q WA4-FRM-4520 Frame Structures Pull 15a:Wa-143-V 7d 7d 16-Jun-23 23-Jun-23 27d 8 WA4-FRM-4515 Frame Structures Pull 16a:Wa-166-V 7d 7d 08-Jun-23 15-Jun-23 27d 8 -- -- -- -- - - --- WA4-FRM-4510 Frame Structures Pull 17a:Wa-189-V 4d 4d 03-Jun-23 07-Jun-23 27d WA4-FRM-4505 Frame Structures Pull 18a:Wa-201 -V 4d 4d 30-May-23 02-Jun-23 27d 0 WA4-FRM-4500 Frame Structures Pull 19a:Wa-213-V 4d 4d 25-May-23 29-May-23 27d I' Set Structures(Including 3-Pole Framin 28-Jun-23 �28-Aug-2 *"�* 2.8-Ajug.23,'Set Structures(Induding 3-Pole WA4-SEr-4650 Set Structures Pull 9a:Wa-53A-Wa-7( 7d 7d 21-Aug-23 28-Aug-23 7d 81 - --------- -- WA4-SEr-4645 Set Structures Pull 10a:VVa 77-Wa-1( 8d 8d 11-Aug-23 19-Aug-23 7d 8 WA4-SEr-4640 Set Structures Pull 11a:Wa-100-Wa-1 1d 1d 10 Aug-23 10-Aug-23 7d WA4SEf-4635 Set Structures Pull 12a:VVa 106-Wa-' 5d 5d 04Aug-23 09-Aug-23 7d WA4-SEr-4630 Set Structures Pull 13a:VVa 119-VVa-1 5d 5d 29-Jul-23 03-Aug-23 7d WA4-SET-4625 Set Structures Pull 14a:Wa 132-Wa-' 2d 2d 27-Jul-23 28-Jul-23 7d WA4-SEr-4620 Set Structures Pull 15a Wa-143-Wa-1 8d 8d 18,Jul-23 26,Jul-23 7d 8; WA4-SET-4615 Set Structures Pull 16a:Wa 166-Wa-' 7d 7d 10,Jul-23 17,Jul-23 7d B WA4-SET-4610 Set Structures Pull 17a:Wa 189-Wa 3d 3d 06,Jul-23 08,Jul-23 7d WA4-SET-4605 Set Structures Pull 18a:Wa-201 -Wa 3d 3d 03,Jul-23 05,Jul-23 7d WA4-SET-4600 Set Structures Pull 19a:Wa-213-Wa 4d 4d 28,Jun-23 01,Jul-23 7d Wire Stringing 29-Jul-23 04-Oct- r 04-Oct-23,I Wire Stringing WA4-STR4750 Conductor Stringing Pull9a:Wa-53A- 6d 6d 28Sep-23 04-Oct-23 Od b WA4-STR4745 Conductor Stringing Pull 10a:Wa 77- 6d 6d 21Sep-23 27Sep-23 Od WA4-STR4740 Conductor Stringing Pull 11a:Wa-100• 4d 4d 16Sep-23 20Sep-23 Od WA4-STR-4735 Conductor Stringing Pull 12a:VVa 106• 5d 5d 11Sep-23 15Sep-23 Od f WA4-STR-4730 Conductor Stringing Pull 13a:VVa 119• 5d 5d 05Sep-23 09Sep-23 Od 1 WA4-STR4725 Conductor Stringing Pull 14a:VVa4 32• 5d 5d 30Aug-23 04Sep-23 Od WA4-STR4720 Conductor Stringing Pull 15a:VVa443 6d 6d 23Aug-23 29-Aug-23 Od WA4-STR4715 Conductor Stringing Pull 16a:VVa466 6d 6d 16Aug-23 22-Aug-23 Od t WA4-STR-4710 Conductor Stringing Pull 17a:VVa489 5d 5d 10Aug-23 15-Aug-23 Od WA4-STR4705 Conductor Stringing Pull 18a:VVa-201 • 5d 5d 04Aug-23 09-Aug-23 Od WA4-STR4700 Conductor Stringing Pull 19a:VVa-213 5d 5d 29-Jul-23 03-Aug-23 Od Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort m Remaining Work Primary Baseline 01= Critical Remaining Work Page 15 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D J I F M A M J J A S O N I D J I F M A M I J I J I A S O Shirley Basin to TB Flats 8d 8d 25-May-23 03-Jun-23 137d wun, i ey Basin o mats WA3 SBT-9000 Set 1 Structure(TB-2), Modify 1 Stnacti 8d 8d 25-May-23 03-Jun-23 137d (5)Aeolus SS to Freezeout SS(Finish by October 15,2023� 156d 156d 17 Apr-23 14-W-23 Od ;14 0ct-23,(5)Aeolus SS to Fjeezeout Access Installation(2 Cre W 27 Apr-23,Access,Installation(2 Qreuvs) AF5-ACS-5200 AFAccess Installation Pull 1:Aeolus-E 2d 2d 17 Apr-23 18Apr-23 110d AF5-ACS-5210 AFAccess Installation Pull 2:AF1 -AF1 2d 2d 19Apr-23 20Apr-23 110d AF5-ACS-5220 AFAccess Installation Pull 3:AF11 -AF 2d 2d 21Apr-23 22Apr-23 110d AF5-ACS-5230 AFAccess Installation Pull 4:AF16-AF 2d 2d 24Apr-23 25Apr-23 110d AF5-ACS-5240 AFAccess Installation Pull 5:AF30-AF 2d 2d 26-Apr-23 27 Apr-23 110d - -f--r I;-7--;--;- --;- -- - -- -7-7-- Structure Salvage d 28-Apr-23 28 Apr- I w 28-Apr-23,StructUre Salvage AF5-SLV5310 Salvage Structures(2 Total) :Od :Od d 28-Apr-23 28Apr-Apr 120d �I AF5SLV5320 AF Structure Salvage Complete d 28Apr-Apr 120d * AF structure Salvage Complete AF5SLV5300 Begin AF Structure Salvage 28-Apr-23 120d Begin Ar Structure Salvage' Embed Foundation 21 Aug-Aug 31-Aug-23 w 31-Plug-23,1,DifecC Erhbcd Rour�datioris AF5-DEF-5400 AF Direct Embed Foundations Pull 2:P 3d 3d 21 Aug-Aug 23-Aug-23 L AF5-DEF5410 AF Direct Embed Foundations Pull 3:P 2d 2d 24Aug-23 25-Aug-23AF5-DEF-5420 AF Direct Embed Foundations Pull 4: 5d 5d 26Aug-23 31-Aug-23 Drilled Pier Foundation 16d 30,Jun-23 18,Ju1-2 TV:18-Jul-23,DHlled Pier Foundations AF5-DPF5500 Drilled Pier Foundation AF Pull 1:Aeolt 1d 1d 30,Jun-23 30-Jun-23 51d AF5-DPF5510 Drilled Pier Foundation AF Pull 2:AF1 • 5d 5d 01,Jul-23 06,Jul-23 52d AF5-DPF5520 Drilled Pier Foundation AF Pull 3:AF11 3d 3d 07,Jul-23 10,Jul-23 52d 0 AF5-DPF5530 Drilled Pier Foundation AF Pull 4:AF16 5d 5d 11,Jul-23 15,Jul-23 52d j B AF5-DPF-5540 Drilled Pier Foundation AF Pull 5:AF3C 2d 2d 17,Ju1-23 18,Ju1-23 55d - - - - - - - ------- ---- ----------- - - - e Structures tilul- If 01-Aug:23�Fr6m6 Structures AF5-FRM5600 Frame StructuresAF Pull 1:Aeolus-Af 1d 1d 22,1u1-23 22,Jul-23 37d AF5-FRM5610 Frame StructuresAF Pull 2:AF1 -AF11 2d 2d 24,Jul-23 25,Jul-23 37d AF5-FRM5620 Frame StructuresAF Pull 3:AF11 -AF 2d 2d 26�1u1-23 27�1u1-23 38d AF5-FRM-5630 Frame StructuresAF Pull 4:AF16-AF, 4d 4d 28-Jul-23 01-Aug-23 38d ' Set Structures(Including 3-Pole Framing d 29 Aug-23 13-Sep-2-3 7 W;13�ep-23,Set Structures(Including 3-Pole AFSSET-SET Set StructuresAF Pull 1:Aeolus-AF1 1d 1d 29-Aug-23 29-Aug-23 7d AF5SET5710 Set StructuresAF Pull 2:AF1 -AF11 5d 5d 30Aug-23 04Sep-23 7d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 16 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I F M A M J J A S O N I D. J I F I M A M I J I J I A S O AF5SET5720 Set StructuresAF Pull 3:AF11 -AF 16 2d 2d 05-Sep-23 06-Sep-23 7d AF5SET5730 Set Structures AF Pull 4:AF16-AF30 5d 5d 07Sep-23 12Sep-23 7d 1 AF5SET5740 Set StructuresAF Pull 5:AF30-AF31 1d 1d 13Sep-23 13Sep-23 7d Wire Stringing d 30Sep-Sep 14-Oct-2 w;14;Oct-23,Wire;Stringing, AF5STR5800 Conductor Stringing AF Pull 1:Aeolus• 2d 2d 30Sep-23 02-0ct-23 Od AF5STR5810 Conductor Stringing AF Pull 2:AF1 -AI 3d 3d 03-Oct-23 05-Od-23 Od AF5STR5820 Conductor Stringing AF Pull 3:AF11 -A 3d 3d 06-Oct-23 09-Od-23 Od ------ AF5STR5830 Conductor Stringing AF Pull 4:AF16-E 3d 3d 10-Oct-23 12-0ct-23 Od AF5STR5840 Conductor Stringing AF Pull 5:AF30 4 2d 2d 13-Oct-23 14-Oct-23* Od Mc:Dave Johnson toAmassa SS 156d 156d 28-Apr-23 26-W-23 130d 26-Oct-23,9 Wb:Dave Jbhn§od to'Arri Access Installation(2 Crews) 28-Apr-23 06-May-2 A 06-May-23,A"ce s Ihstbllatiori(2,Crdws� WC6-ACS5200 Access Installation Pull 1c:Dave John; 1d 1d 28-Apr-23 28 Apr-23 110d �I WC6-ACS5210 Access Installation Pull 2c:We-1 -Wo, 1d 1d 29- r-23 r-23 120d AP 29 A P WC6-ACS-6220 Access Installation Pull 3c:Wo-2-Wo-' 1d 1d 01-May-23 01-May-23 120d WC6-ACS-6230 Access Installation Pull 4c:Wo-13-We 1d 1d 02-May-23 02-May-23 120d WC6-ACS-6240 Access Installation Pull 5c:Wo-26-We 1d 1d 03-May-23 03-May-23 120d WC6-ACS-6250 Access Installation Pull 6c:Wo-43-We 1d 1d 04-May-23 04-May-23 120d ----------- -- -- -- -- ------------ ------ - WC6-ACS-6260 Access Installation Pull 7c:Wo-49A-W 1d 1d 05-May-23 05-May-23 120d j WC6-ACS-6270 Access Installation Pull 8c:Wo-49B-Ai 1d 1d 06-May-23 06-May-23 278d Structure Salvage d 11-May-23 18-May-23 11 Od'M A'I 18-M6y-23,Structure Salvage WC6-SLV-6300 Salvage Pull 1c:Dave Johnson-Wo-1 1d 1d 11-May-23 11-May-23 110d WC6SLV£310 Salvage Pull2c:Wo-1 -Wo-2 1d 1d 12-May-23 12-May-23 110d WC6SLV£320 Salvage Pull 3c:Wo-2-Wo-13 1d 1d 13-May-23 13-May-23 110d WC6SLV£330 Salvage Pull 4c:Wo-13-Wo-26 1d 1d 15-May-23 15-May-23 110d WC6SLV£340 Salvage Pull 5c:Wo-26-Wo-43 1d 1d 16-May-23 16-May-23 110d WC6SLV-6350 Salvage Pull 6c:Wo-43-Wc-49A 1d 1d 17-May-23 17-May-23 110d WC6SLV-6360 1 Salvage Pull7c:Wo-49A-Wc-4913 1d 1d 18-May-23 18-May-23 110d irect Embed Foundations 01 Sep-23 0-Sep-23 r►; 2QS�p-?3, (irgct�mbe4 Faun—iation� WC6-DEF-6400 Direct Embed Foundations Pull 3c:We 4d 4d 01Sep-23 05-Sep-23 18d WC6-DEF5410 Direct Embed Foundations Pull 4c:We 5d 5d 06Sep-Sep 11Sep-23 18d 1 WC6-DEF5420 Direct Embed Foundations Pull 5c:We 6d 6d 12Sep-Sep 18Sep-Sep 18d j Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 17 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I F M A M J J A S O N I D. J I F I M A M I J I J I A S O WC6 DEF-6430 Direct Embed Foundations Pull 6c We 2d 2d 19 Sep 23 20 Sep 23 22d ri Drilled Pier Foundations 4d 19 Jul-23 03 Aug 23 68d TV 03-Aug;23;D lled Pier Foundations WC6-DPF-6500 Drilled Pier Foundation Pull 1c:Dave J, 2d 2d 19-Jul-23 20-Jul-23 58d j WC6-DPF-6510 Drilled Pier Foundation Pull 2c:Wo-1 - 2d 2d 21-Jul-23 22-Jul-23 58d WC6-DPF-6520 Drilled Pier Foundation Pull 3c:Wo-2- 2d 2d 24-Jul-23 25-Jul-23 58d WC6-DPF-6530 Drilled Pier Foundation Pull 4c:Wc13 2d 2d 26-Jul-23 27-Jul-23 59d WC6-DPF-6540 Drilled Pier Foundation Pull 5c:Wc26 2d 2d 28-Jul-23 29-Jul-23 61d WC6-DPF-6550 Drilled Pier Foundation Pull 6c:Wo43 3d 3d 31-Jul-23 02-Aug-23 64d WC6-DPF-6560 Drilled Pier Foundation Pull 7c:Wo49E 1d 1d 03Aug-23 03-Aug-23 68d Frame Structures 15d 02 Aug-23 18-Aug-23 VI' 18-Adg-23,Frame iStructures WC6-FRM-6600 Frame Structures Pull 3c:Wc2-We-1 i 4d 4d 02Aug-23 05-Aug-23 46d -- -- --- -------- WC6-FRM-6610 Frame Structures Pull 4c:Wc13-Wc, 4d 4d 07Aug-23 10-Aug-23 46d A WC6-FRM-6620 Frame Structures Pull 5c:Wc26-Wo-e 5d 5d 11-Aug-23 16-Aug-23 46d 8 WC6-FRM-6630 Frame Strictures Pull 6c:Wo43-Wo-e 2d 2d 17Aug-23 18-Aug-23 50d ctures(Including 3-Pole Framin e - IV* 64-6ct-23,I Set StnaGture's(Including 2-P WC6-SET-6700 Set Structures Pull 1c:Dave Johnson- 1d 1d 14Sep-Sep 14Sep-Sep 7d WC6SET-SET Set Structures Pull 2c:We-1 -Wc2 1d 1d 15Sep-Sep 15Sep-Sep 13d WC6SET-SET Set Structures Pull 3c:We-2-Wc13 3d 3d 16Sep-Sep 19Sep-Sep 13d WC6SET-SET Set Structures Pull 4c:We-13-Wc26 4d 4d 20Sep-Sep 23Sep-Sep 13d WC6SET-SET Set Structures Pull 5c:We-26-Wc-43 5d 5d 25Sep-Sep 29Sep-Sep 13d d WC6-SET-6750 Set Structures Pull 6c:Wo43-Wc-49P 3d 3d 30Sep-Sep 03-Od-23 14d - -- -- -------------------- WC6-SET-6760 Set Strictures Pull 7c:We-49A-Wo49 1d 1d 04-Oct-23 04-Od-23 16d ;� Wire Stringing t- 26-Oct-23,Wirb Stringino WC6STR-6800 Conductor Stringing Pull 1c: Dave Johi 1d 1d 05-Oct-23 05-Od-23 Od ;� WC6-STR-6810 Conductor Stringing Pull 2c:Wc1 -We 2d 2d 06-Oct-23 07-Od-23 Od j WC6-STR-6820 Conductor Stringing Pull 3c:Wc2-We 2d 2d 09-Oct-23 10-W-23 Od -- -- --- -------- WC6-STR-6830 Conductor Stringing Pull 4c:Wc13-V\ 4d 4d 11-W-23 14-W-23 Od WC6-STR-6840 Conductor Stringing Pull 5c:Wo-26-V\ 4d 4d 16-Oct-23 19-W-23 Od WC6-STR-6850 Conductor Stringing Pull 6c:Wo43-V\ 3d 3d 20-Oct-23 23-W-23 Od WC6-STR-6860 Conductor Stringing Pull 7c:Wo49A-I 2d 2d 24-Oct-23 25-W-23 Od WC6-STR-6870 Conductor Stringing Pull8c:Wo49B- 1d 1d 26-Oct-23 26-W-23 Od Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 18 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D J I F M A M J J A S O N I D J F M A M J J A S O Amassa to 1 Wc148&1 We-209 to Heward (Finish by Octot 357d 357d 08-May-23 06-Jul-24 Od u Amassa to 1 We-148 338 08-May- 14,Jun-24 _ Od i 14:Juh-24,A Access Installation(2 Crews) 27d 27d 08-May-23 07-Jun-23 284d VM,V 67�un,23,A&ess Installation,(2 Crewsl WC7 ACS-7200 Access Installation Pull 9c:Amassa#2 1d 1d 08-May-23 08-May-23 278d WC7 ACS-7210 Access Installation Pull 10c:Wo-49C- 1d 1d 09-May-23 09-May-23 278d WC7 ACS-7220 Access Installation Pull 11c:We-491)-1 1d 1d 10-May-23 10-May-23 278d WC7 ACS-7230 Access Installation Pull 12c:We-66-W 3d 3d 11-May-23 13-May-23 282d WC7 ACS-7240 Access Installation Pull 13c:We-88-W 3d 3d 15-May-23 17-May-23 282d WC7 ACS-7250 Access Installation Pull 14c:Wc-95-W 3d 3d 18-May-23 20-May-23 282d WC7 ACS-7260 Access Installation Pull 15c:We-106-\ 5d 5d 22-May-23 26-May-23 282d WC7 ACS-7270 Access Installation Pull 16c:We-112 5d 5d 27-Ma 23 01-Jun-23 282d 0 WC7 ACS-7280 Access Installation Pull 17c:We-137-\ 5d 5d 02,Jun-23 07-Jun-23 284d B Structure Salvage 18d 18d 19-May-23 08-Jun-23 305d VW 08-jun'23,Structure Salvage WC7SVG7300 Salvage Pull 9c:Amassa#2-Wo-49C 1 d 1 d 19-May-23 19-May-23 312d WC7SVG7310 Salvage Pull 10c:Wc-49C-We-491) 1d 1d 20-May-23 20-May-23 312d WC7SVG7320 Salvage Pull 11c:Wc-49D-Wo66 1d 1d 22aMay-23 22-May-23 312d WC7SVG7330 Salvage Pull 12c:Wo66-Wc-88 2d 2d 23-May-23 24-May-23 312d WC7SVG7340 Salvage Pull 13c:Wo-88-Wo-95 1d 1d 25-May-23 25-May-23 312d WC7SVG7350 Salvage Pull 14c:Wo-95-Wo-1 06 1d 1d 26-May-23 26-May-23 312d �I WC7SVG7360 Salvage Pull 15c:Wo-1 06-Wo-1 12 1d 1d 27-May-23 27-May-23 312d WC7SVG7370 Salvage Pull Pull 16c:Wo-112-Wo-13' 2d 2d 02,Jun-23 03,Jun-23 308d WC7SVG7380 I Salvage Pull 17c:Wo-1 37-Wo-1 49 1d 1d 08,Jun-23 08,Jun-23 305d Direct Embed Foundations 37d 37d 05-Oct-23 16-Nov-23 152d Oirpct Erm$edj Fopnclati WC7-DEF-7400 Direct Embed Foundations Pull 11c:W 7d 7d 05-Oct-23 12-W-23 152d ;A WC7-DEF-7410 Direct Embed Foundations Pull 12c:W 8d 8d 13-Oct-23 21-W-23 152d 8 - - - - - - - ------ WC7-DEF-7420 Direct Embed Foundations Pull 13c:W 2d 2d 23-Oct-23 24-W-23 152d j WC7-DEF-7430 Direct Embed Foundations Pull 14c:W 4d 4d 25-Oct-23 28-W-23 152d WC7-DEF-7440 Direct Embed Foundations Pull 15c:W 2d 2d 30-Oct-23 31-W-23 152d WC7-DEF-7450 Direct Embed Foundations Pull 16c:W 9d 9d 01-Nov-23 10-Nov-23 152d WC7-DEF-7460 Direct Embed Foundations Pull 17c:W 5d 5d 11-Nov-23 16-Nov-23 152d B Drilled Pier Foundations 17d 17d 05-Oct-23 24-W-23 173d T. V. 24-0bt-23, Drilla?d Piet Fdundatibns Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 19 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N I D I J I F M A M J J A S O N I D. J I F I M A M J I J I A S O WC7-DPF-7500 Drilled Pier Foundations Pull 9c:Amas: 1d 1d 05-Oct-23* 05-Oct-23 160d WC7-DPF-7510 Drilled Pier Foundations Pull 10c:Wo-0 2d 2d 06-Oct-23 07-Od-23 160d WC7-DPF-7520 Drilled Pier Foundations Pull 11c:Wo-4 3d 3d 09-Oct-23 11-Oct-23 160d WC7-DPF-7530 Drilled Pier Foundations Pull 12c:Wo-6 3d 3d 12-Oct-23 14-Od-23 164d WC7-DPF-7540 Drilled Pier Foundations Pull 13c:Wo-6 1d 1d 16-Oct-23 16-Od-23 173d WC7-DPF-7550 Drilled Pier Foundations Pull 14c:Wo-9 2d 2d 17-Oct-23 18-Od-23 173d WC7-DPF-7560 Drilled Pier Foundations Pull 15c:Wo-1 2d 2d 19-Oct-23 20-Od-23 173d WC7-DPF-7570 Drilled Pier Foundations Pull 16c:Wo-1 3d 3d 21-Oct-23 24-W-23 173d Frame Structures 29d 29d 05-Oct-23 07-Nov-23 168d ^I 07-Nov-23,Rarrie Structures -- -- --- -------- WC7-FRM-7600 Frame Structures Pull 11c:We-49D-VN 4d 4d 05-Od-23* 09-Od-23 162d 'A WC7-FRM-7610 Frame Structures Pull 12c:We-66-We 7d 7d 10-Oct-23 17-Od-23 162d 8 WC7-FRM-7620 Frame Structures Pull 13c:We-88-We 2d 2d 18-Oct-23 19-Od-23 165d WC7-FRM-7630 Frame Structures Pull 14c:We-95-We 3d 3d 20-Oct-23 23-Od-23 165d A j WC7-FRM-7640 Frame Structures Pull 15c:Wo-106-W 2d 2d 24-Oct-23 25-W-23 165d - - - - - ------ - -- -- --- -------- WC7-FRM-7650 Frame Structures Pull 16c:Wo-112-W 7d 7d 26-Oct-23 02-Nov-23 165d WC7-FRM-7660 Frame Structures Pull 17c:Wo-137-W 4d 4d 03-Nov-23 07-Nov-23 168d Set Structures(Including 3-Pole Framing) 36d 36d 13-Oct-23 23-Nov-23 161d 2 -Nov-23,Set Structures(Indiudiri WC7SET-7700 Set Structures Pull 9c:Amassa#2-We 1d 1d 13-Oct-23 13-W-23 157d WC7SET-7710 Set Structures Pull 10c:Wo-49C-Wo-e 1d 1d 14-Oct-23 14-Od-23 157d WC7SET-7720 Set Structures Pull 11c:Wo-49D-Wc-E 7d 7d 16-Oct-23 23-Od-23 157d WC7SET-7730 Set Structures Pull 12c:Wo-66-Wc-M 7d 7d 24-Oct-23 31-Oct-23 157d d WC7SET-7740 Set Structures Pull 13c:Wo-88-Wo-95 2d 2d 01-Nov-23 02-Nov-23 160d WC7SET-7750 Set Structures Pull 14c:Wo-95-Wo-1C 3d 3d 03-Nov-23 06-Nov-23 160d WC7SET-7760 Set Structures Pull 15c:Wo-106-Wo-1 2d 2d 07-Nov-23 08-Nov-23 160d WC7SET-7770 Set Structures Pull 16c:Wo-112-Wo-1 8d 8d 11-Nov-23 20-Nov-23 158d B WC7SET-7780 Set Structures Pull 17c:Wo-137-Wo-1 3d 3d 21-Nov-23 23-Nov-23 161d Wire Stringing 38d 38d 02-May-24 14-Jun-24 Od VwT►;14;Juh-24, WC7STR-7800 Conductor Stringing Pull 9c:Amassa#, 2d 2d 02-May-24 03-May-24 Od WC7STR-7810 Conductor Stringing Pull 10c:Wo-49C 2d 2d 04-May-24 06-May-24 Od r--;- WC7STR-7820 Conductor Stringing Pull 11c:Wo-49D• 5d 5d 07aV1ay-24 11-May-24 Od WC7STR-7830 Conductor Stringing Pull 12c:Wo-66-1 5d 5d 13-May-24 I 17-May-24 Od f Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 20 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J I F M A I M J I J I A S O N I D I J I F I M A M J I J I A S 1 O WC7STR-7840 Conductor Stringing Pull 13c:We-88-1 4d 4d 18-May-24 22-May-24 Od WC7STR-7850 Conductor Stringing Pull 14c:Wo-95-1 5d 5d 23-May-24 28-May-24 Od I' WC7STR-7860 Conductor Stringing Pull 15c:Wo-106• 4d 4d 29-May-24 01-Jun-24 Od , , , , , , ------------------------------------------------------------------------------------ WC7STR-7870 Conductor Stringing Pull 16c:Wo-112- 6d 6d 03-Jun-24 08-Jun-24 Od WC7STR-7880 Conductor Stringing Pull 17c:Wo-137• 5d 5d 10-Jun-24 14-Jun-24 Od 1Wc-209toHeward d un- 06-Jul-24 ©6�Vu1-24, Access Installation(2 Crews) 26d 26d 08-Jun-23 07-Jul-23 284d �W 07-Ju1-23,Access Installation(2 Crews) WC8 ACS-8200 Access Installation Pull 24c:Wc-208-\ 7d 7d 08-Jun-23 15-Jun-23 284d -- ----- -------- -- -- -- -- ------- WC8-ACS-8210 Access Installation Pull 25c:We-225-\ 6d 6d 16-Jun-23 22-Jun-23 284d WC8-ACS-8220 Access Installation Pull 26c:We-244-\ 7d 7d 23-Jun-23 30-Jun-23 284d 8 WC8-ACS-8230 Access Installation Pull 27c:We-254-I 6d 6d 01-Jul-23 07-Jul-23 284d Structure Salvage 6d 6d 08-Jul-23 14-Jul-23 292d A;14;Jul,23;Sttucture Shcvage WC8SLV-8300 Salvage Pull 24c:Wo-208-Wo-225 1d 1d 08-Jul-23 08-Jul-23 292d WC8SLV-8310 Salvage Pull 25c:Wo-225-Wo-244 2d 2d 10-Jul-23 11-Jul-23 292d WC8SLV-8320 Salvage Pull 26c:Wo-244-Wo-254 2d 2d 12-Jul-23 13-Jul-23 292d WC8SLV-8330 Salvage Pull 27c:Wo-254-Heward#1 1d 1d 14-Jul-23 14-Jul-23 292d Direct Embed Foundations 23d 23d 17-Nov-23 13-Dec-23 152d �!► 13-De 2 irept mtied',Fo nd WC8-DEF-8400 Direct Embed Foundations Pull 24c:W 7d 7d 17-Nov-23 24-Nov-23 152d 8 WC8-DEF-8410 Direct Embed Foundations Pull 25c:W 7d 7d 25-Nov-23 02-Dec-23 152d WC8-DEF-8420 Direct Embed Foundations Pull 26c:W 8d 8d 04-0ec-23 12-Dec-23 152d A WC8-DEF-8430 Direct Embed Foundations Pull 27c:W 1d 1d 13-0ec-23 13-Dec-23 152d Drilled Pier Foundations 6d 6d 25-Oct-23 31-Od-23 197d A 31-Oct-23,iDrilled Pier Fbundations WC8-DPF-8500 Drilled Pier Foundations Pull 25c:Wo-2 2d 2d 25-Oct-23 26-Od-23 190d WC8-DPF-8510 Drilled Pier Foundations Pull 26c:Wo-2 2d 2d 27-Oct-23 28-W-23 194d WC8-DPF-8520 Drilled Pier Foundations Pull 27c:Wo-2 2d 2d 30-Oct-23 31-Od-23 197d Frame Structures 19d 19d 08-Nov-23 29-Nov-23 168d '► 29-Nov,23;Frame Structures WC8-FRM-8600 Frame Structures Pull 24c:We-208-W 6d 6d 08-Nov-23 14-Nov-23 168d 0 WC8-FRM-8610 Frame Structures Pull 25c:We-225-W 6d 6d 15-Nov-23 21-Nov-23 168d 0 ; WC8-FRM-8620 Frame Structures Pull 26c:We-244-W 6d 6d 22-Nov-23 28-Nov-23 168d BI WC8-FRM-8630 Frame Structures Pull 27c:We-254-H, 1d 1d 29-Nov-23 29-Nov-23 168d Set Structures(Including 3-Pole Framing) 22d 22d 25-Nov-23 20-Dec-23 156d V"I 2Q-Dec-23,Setl Structures(IndL( WC8SET-8700 I Set Structures Pull 24c:Wo-208-Wo-2 4d 4d 25-Nov-23 29-Nov-23 161d Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 110= Remaining Work Primary Baseline SEE=] Critical Remaining Work Page 21 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S O N D J F M A M J J A S O N D J F M A M J J A S O WC8SET-8710 Set Structures Pull 25c:We-225-Wo-2 5d 5d 04-Dec-23 08-Dec-23 158d -- -- -- WC8SET-8720 Set Structures Pull 26c:Wo-244-Wo-2 5d 5d 13-0ec-23 18-Dec-23 156d 8 WC8SET-8730 Set Structures Pull 27c:Wo-254-Hew, 2d 2d 19-0ec-23 20-Dec-23 156d Wire Stringing 19d 19d 15-Jun-24 06-Jul-24 Od 06,Uu1-24, WC8STR-8800 Conductor Stringing Pull 24c:Wo-208• 5d 5d 15,Jun-24 20,Jun-24 Od WC8STR-8810 Conductor Stringing Pull25c:Wo-225• 6d 6d 21-Jun-24 27-Jun-24 Od WC8STR-8820 Conductor Stringing Pull 26c:Wo-244• 6d 6d 28-Jun-24 04-Jul-24 Od WC8STR-8830 Conductor Stringing Pull 27c:Wo-254• 2d 2d 05-Jul-24 06-Jul-24 Od Heward Basin to Shirley Basin SS 255d 255d 05-Oct-23 07-Aug-24 72d Q7-Aug Access Installation(2 Crews) 05-Oct-23 28-0ct-2 26-Oct-�3,Ades§In,5tal atign( G e WC9-ACS-9200 Access Installation Pull 28c:We-268-\ 4d 4d 05-W-23* 09-W-23 208d WC9-ACS-9210 Access Installation Pull 29c:Wo-288-\ 3d 3d 10-Oct-23 12-W-23 213d WC9-ACS-9220 Access Installation Pull 30c:We-306-\ 4d 4d 13-Oct-23 17-W-23 216d A WC9-ACS-9230 Access Installation Pull 31 c:Wo-319-\ 3d 3d 18-Oct-23 20-Od-23 218d WC9-ACS-9240 Access Installation Pull 32c:Wo-2/177/ 4d 4d 21-Oct-23 25-W-23 232d f WC9-ACS-9250 Access Installation Pull 33c:Wo-1/3-S 3d 3d 26-Oct-23 28-Od-23 232d Structure Salvage ct-23 23-0ct-23, tnicture alyage WC9SLV-9300 Salvage Pull 28c:Wo-262-Wo-288 2d 2d 10-Oct-23 11-Oct-23 316d WC9SLV-9310 Salvage Pull 29c:Wo-288-Wo-306 2d 2d 13-Oct-23 14-W-23 315d WC9SLV-9320 Salvage Pull 30c:Wo-306-Wo-319 1d 1d 18-Oct-23 18-Od-23 313d WC9-SLV-9330 Salvage Pull 31 c:Wo-319-Wo-2/177A 2d 2d 21 Oct-23 23-0ct-23 311 d ' Direct Embed Fou 14-0ec-23 24--Jan-2 VEMI 24-Jan-24,Direct Embed Fd WC9-DEF-9400 Direct Embed Foundations Pull 28c:W 8d 8d 14-Dec-23 02-Jan-24 152d WC9-DEF-9410 Direct Embed Foundations Pull 29c:W 7d 7d 03,Jan-24 10,Jan-24 152d WC9-DEF-9420 Direct Embed Foundations Pull 30c:W 42d2d 5d 11,Jan-24 16-,Jan-24 152d WC9-DEF-9430 Direct Embed Foundations Pull 31c:W 7d 17,Jan-24 24,Jan-24 152d A 0�', W- �,08- ' 2 Dnll, �d Pier,Fo ndp q ns Drilled Pier Foundatio d 01-Nov 23 08 Nov-23 WC9-DPF-9500 Drilled Pier Foundations Pull 28c:Wo-2 01-Nov-23 02-Nov-23 197d WC9-DPF-9510 Drilled Pier Foundations Pull 29c:Wo-2 2d 2d 03-Nov-23 04-Nov-23 202d WC9-DPF-9520 Drilled Pier Foundations Pull 31c:Wo-3 3d 3d 06-Nov-23 08-Nov-23 209d Frame Structures 30-Nov-23 04-Jan-24 169d M #mV 04-)an-24, Frpmg S}rugturps Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 22 of 23 GWW D.1 Project Baseline_Approved 13-Aug-2411:30 Activity ID Activity Name Orig dur Rem Dur Start Finish Total Float Comments 2023 2024 (CD) (CD) A S 1 O N I D I J I F M A M J J A S O N D J F M A M J J A S O WC9-FRM-9600 Frame Structures Pull 28c:We-268-W 6d 6d 30-Nov-23 06-Dec-23 168d WC9-FRM-9610 Frame Structures Pull 29c:We-288-W 6d 6d 07-0ec-23 13-Dec-23 169d 8 WC9-FRM-9620 Frame Structures Pull 30c:We-306-W 4d 4d 14-0ec-23 18-Dec-23 169d A WC9-FRM-9630 Frame Structures Pull 31c:We-319-W 6d 6d 19-0ec-23 04-Jan-24 169d Q Set Structures(Including 3-Pole Framing) M�MMMJM03-,Ian-24 30-Jan-qMM VmV �0-},an�24,Se; Struqurps(Ij -- -- -- WC9-SET-9700 Set Structures Pull 28c:Wo-268-Wo-2 6d 6d 03,Jan-24 09,Jan-24 154d WC9SET-9710 Set Structures Pull 29c:Wo-288-Wo-3 5d 5d 11,Jan-24 16-Jan-24 154d 8 1 WC9SET-9720 Set Structures Pull 30c:Wo-306-Wo-3 3d 3d 17,Jan-24 19-Jan-24 156d WC9-SET-9730 Set Structures Pull 31c:Wo-319-Wo-2 5d 5d 25,Jan-24 30,Jan-24 152d Wire Stringing 27d 08-Jul-24 07-Aug-24 V- wV 07Au� WC9STR-9800 Conductor Stringing Pull 28c:Wo-268• 6d 6d 08-Jul-24 13-Jul-24 Od WC9STR-9810 Conductor Stringing Pull 29c:Wo-288• 5d 5d 15-Jul-24 19-Jul-24 Od WC9STR-9820 Conductor Stringing Pull 30c:Wo-306• 5d 5d 20-Jul-24 25-Jul-24 Od WC9STR-9830 Conductor Stringing Pull 31c:Wo-319• 5d 5d 26-Jul-24 31-Jul-24 Od WC9STR-9840 Conductor Stringing Pull 32c:Wo-2/17' 4d 4d 01 Aug-24 05-Aug-24 Od - -;--;- - - -- WC9STR-9850 Conductor Stringing Pull 33c:Wo-1/3- 2d 2d 06Aug-Aug 07-Aug-24 Od ;� ALL-FIN-510 Final Construction Demob 24d 24d 25-Jul-24 21-Aug-24 60d ALL-FIN-520 Final Reclamation and Clean UpActivi 24d 24d 25,Jul-24 21-Aug-24 Od ALL-FIN-560 Mechanical Completion Od Od 28-Aug-24 36d + Meci ALL-FIN-530 Punch List Items 18d 18d 08Au 24 28-Au 24 36d ALL-FIN-540 QC Forms Submitted 18d 18d 08Aug-24 28-Aug-24 36d ALL-FIN-550 As-Built Submittals 18d 18d 08Aug-24 28-Aug-24 36d Al L-FIN-580 SybatgpWLCompletion Od Od 30-Od-24 Od ALL-FIN-570 Testing Verification 18d 18d 29Aug-24 18Sep-24 36d ALL-FIN-590 Final Project Completion Date(Requin Od Od 30-Oct-24* Od ALL-FIN-500 Construction Completion Od Od 07-Aug-24 Od Constrq Remaining Level of Effort Actual Work GATEWAY SOUTH Date Revision Checked Approved Actual Level of Effort 0 Remaining Work Primary Baseline K= Critical Remaining Work Page 23 of 23