HomeMy WebLinkAbout20240823PAC to Bayer 55 Attachment - Boswell project schedule.pdf ID Task Task Name Duration Start Finish Qtr 2,2024 Qtr 3,2024 Qtr 4,2024 Qtr 1,2025
Mode Mar Am May Jun Jul Auci Se Oct Nov Dec Jan
1 W Boswell project 170 days Thu 4/18/24 Wed 12/11/e
2 W Contract award 0 days Wed 5/1/24 Wed 5/1/24
3 W IFC available 0 days Wed 5/15/24 Wed 5/15/24 5/15
4 W Freezeout substation 151 days Wed 5/15/2z Wed 12/11/e
5 Material 150 days Wed 5/15/VTue 12/10/2j
6 Transmission structure anchor bolts- Owner furnished 0 days Wed Wed
5/15/24 5/15/24
7 Dead end anchor bolts-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
8 Dead end steel available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24 5/15
9 Control cable available - owner furnished 0 days Wed 5/15/24 Wed 5/15/24
10 Insulators available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
11 Switches available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
12 Breakers available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
13 Metering units available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
14 W4Surge Arresters available-owner furnished 0 days Wed 5/15/24 Wed 5/15/24
15 Transmission material available-owner furnished 0 days Wed Wed
5/15/24 5/15/24
16 Steel order 10 wks Wed 5/15/24Tue 7/23/24
17 Conductor and fittings material order 14 wks Wed 5/15/24Tue 8/20/24
18 Bus and fittings material order 14 wks Wed 5/15/24Tue 8/20/24
19 order rebar for foundations 2 wks Wed 5/15/24Tue 5/28/24 MIT
20 Jumper material for BFO detail 30 wks Wed 5/15/24Tue 12/10/2z
21 Deadend for BXL detail 28 wks Wed 5/15/24Tue 11/26/2z
22 Construction 151 days Wed 5/15/2z Wed 12/11/i
23 W Mobilize 10 days Wed 5/15/24Tue 5/28/24
24 W Take outage to remove Freezeout/Standpipe line 8 days Wed 5/29/2z Fri 6/7/24
25 W Demo substation deadend 2 days Wed 5/29/24Thu 5/30/24
26 W Demo substation deadend foundations 2 days Fri 5/31/24 Mon 6/3/24
27 Drill and pour 3 pole foundation for transmission str 3 days Wed Fri 5/31/24
5/29/24
28 Drill and pour single pole foundation for 2 days Mon 6/3/24 Tue 6/4/24
transmission str.
29 W Pour new substation Deadend foundations 3 days Wed 6/5/24 Fri 6/7/24
30 W Possible installation of Shoo-fly if outage cannot be 2 days Thu 6/6/24 Fri 6/7/24
extended, addition to contract
31 Pour remaining foundations 10 days Mon 6/10/24 Fri 6/21/24
32 Foundation cure time 21 days Mon 6/24/24 Mon 7/22/24
33 Install conduit 10 days Mon 6/24/24 Fri 7/5/24
34 Install Substation dead end steel 3 days Mon 7/8/24 Wed 7/10/24
Task Project Summary 0 0 Manual Task I Start-only C Deadline b
Project: Boswell project schedu Split ................. Inactive Task Duration-only Finish-only 7 Progress
Date: Fri 4/19/24 Milestone ♦ Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
ID Task Task Name Duration Start Finish Qtr 2,2024 Qtr 3,2024 Qtr 4,2024 Qtr 1,2025
Mode Mar Am May Jun Jul AugSep Oct Nov Dec Jan
35 W Install steel structures 10 days Wed 7/24/24Tue 8/6/24
36 Pull Contol and Power cable 10 days Wed 8/7/24 Tue 8/20/24
37 Install Bus 10 days Wed 8/21/24Tue 9/3/24
38 Install Strain bus 2 days Wed 11/27/2Thu 11/28/2z
39 Install switches 15 days Wed 8/7/24 Tue 8/27/24
40 Install breaker 3 days Wed 8/28/24 Fri 8/30/24
41 Install Arresters 1 day Mon 9/2/24 Mon 9/2/24
42 Install Metering units 1 day Tue 9/3/24 Tue 9/3/24
43 Relocate CCVT 1 day Wed 9/4/24 Wed 9/4/24
44 Install most jumpers 10 days Wed 9/4/24 Tue 9/17/24
45 Install jumpers to Breaker with BFO detail 1 day Wed 12/11/2 Wed 12/11/2
46 Install jumpers off strain bus 2 days Wed 11/27/2Thu 11/28/2z
47 Testing and Commissioning 15 days Wed 9/18/24Tue 10/8/24
48 Transmission 75 days Wed 5/29/2zTue 9/10/24
49 Remove Transmission conductor into substation 2 days Wed 5/29/24Thu 5/30/24
50 Relocate Single pole on new foundation 1 day Wed 7/3/24 Wed 7/3/24
PF
51 Relocate Three pole on new foundations 5 days Mon 7/1/24 Fri 7/5/24
52 If no shoo-fly span transmission line back into substation 5 days Wed 9/4/24 Tue 9/10/24
53 Energize 0 days Wed 12/11/2 Wed 12/11/2 12/11
54
55
56 Collector 80 days Thu 4/18/24 Wed 8/7/24 G
57 IFC available 0 days Thu 4/18/24 Thu 4/18/24 4 4/18
58 Mobilize 20 days Thu 4/18/24 Wed 5/15/24
59 Material 0 days Mon 6/17/2z Mon 6/17/21 a 6/17
60 Control house foundation available 0 days Mon 6/17/24 Mon 6/17/24 1/17
61 Control house available 0 days Mon 6/17/24 Mon 6/17/24 17
62 Line and Metering panels available 0 days Mon 6/17/24 Mon 6/17/24 e 17
63 Install pre poured foundation 2 days Mon 6/24/24Tue 6/25/24
64 Install Control House 1 day Wed 6/26/24 Wed 6/26/24
65 Install Fence 10 days Thu 6/27/24 Wed 7/10/24
66 Install conduit 10 days Thu 6/27/24 Wed 7/10/24
67 Install grounding 5 days Thu 7/11/24 Wed 7/17/24
68 Dress control house 10 days Thu 7/18/24 Wed 7/31/24
69 Finish yard 5 days Thu 8/1/24 Wed 8/7/24
Task Project Summary F Manual Task Y 0 Start-only C Deadline b
Project: Boswell project schedu Split Inactive Task Duration-only Finish-only 7 Progress
Date: Fri 4/19/24 Milestone ♦ Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary 0 J Manual Summary I I External Milestone <t>
Page 2