20240823PAC to Bayer 55 Attachment - Anticline Baseline Schedule.pdf
Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F1 MI A I M I J I J I A S1 01 N D J I F M I A M J I J I A I S O N D J F M A M J J A S O N D . • v 09-Oct-24,ANc-BL-3 Anticline Substation Baseli ANC$L-3.MS Project Major Milestones 503.50 22-Feb-23 09-Oct-24 19.00 p9-Oct-24,ANC-BL-0 MS Project Major Mifeston ANC-BL-3.MS.CM Contract Milestones 311.00 22-Feb-23 09-Oct-24 16.00 V 09-Oct-24,ANC-BL-3:MS.CM Contract Milestone MS.CM-01 Contract Execution 0.00 22-Feb-23* 16.00 Cpntract Execution„22--Feti-23" MS.CM-02 Full Notice To Proceed 0.00 10-Mar-23 20.00 ♦ Full:Notice To Proceed, 10-Mar-23 MS.CM-03 Period of Perfomance 299.00 10-Mar-23 09-Oct-24 16.00 Period 0 Pe6mance MS.CM-04 Final Completion 0.00 09 Oct-24* 16.00 ♦ Final Completion, O MS.CM-05 Detailed preliminary schedule (60) 0.00 01-May-23 40.00 ♦ Detailed:prelimiharyschedule (60.), O MS.CM-06 Detailed CPM Schedule 0.00 10-May-23 87.00 ♦ Detailed CPM Scried6le, O MS.CM-07 QA/QC Plan 0.00 25-Apr-23 20.00 QA/QC Plan: ;.... ......:......:.............:......;... . O MS.CM-08 Safety Plan 0.00 05-Apr-23 40.00 Safety Plan, O MS.CM-09 Environmental Assurance Program 0.00 13-Apr-23 30.00 ♦ EnVirohmentaiAssurance Program,; O MS.CM-10 345kVTerrporaryShocflyComplete 0.00 10-May-23 70.00 ♦ 345kVTerripor rry5h60flj CCompletd, O MS.CM-11 Phase shifter Foundations Complete 0.00 21,Jul-23 76.00 ♦ Phase shifter•.Foundations Complete, P P O MS.CM-12 Project Mechanical Completion 0.00 12 Jun-24 21.00 ♦ 'ProJect'Mechainic�al Completion, o MS.CM-13 Project Substantial Completion 0.00 13-Aug-24 16.00 1 ♦ Project;Substentioi Completion, y ANC-BL-3.MS.SAP Start 345kV yard Phaseshifter 1 .00 02-May-23 13,Jun-24 17.00 13-1un 24 ANC-8L-I.M8.SAP Stan 345kV yard Phaseshifter r.+ MS.SAP-01 Construction start 0.00 02-May-23 45.00 ♦ Construction start,02-May 23 a MS.SAP-02 Foundation start 0.00 30-May-23 28.00 Foundation;start,�O-May-�3 a MS.SAP-03 Dead End steel start 0.00 22 Aug-23 31.00 ♦ Dead End steel startt,22-Aug-�3 MS.SAP-04 Substation steel start 0.00 25-Sep-23 32.00 Srabstati6n steel; start,25-$ep-23 MS.SAP-05 Equipment install start 0.00 09-Oct-23 64.90 Equipment install ',start,09-0'ct-23 i MS.SAP-06 Bus installation start 0.00 06-May-24 43.00 Bus installatiori start,06-May 24 a MS.SAP-07 Cable install start 0.00 31,Jul-23 50.00 4 Gable install' start,31,)ul-23 O MS.SAP-08 Cable termination start 0.00 04,Jun-24 16.00 ♦ Cable termination:start,04,Jun-24 0 MS.SAP-09 Contractor testing start 0.00 13,Jun-24 17.00 ♦:Contractor testing start,13-dun-24 • ANC-BL-3.MS.FAP Finish 3451kV yard Phaseshifter 183.00 12,Jul-23 28-Aug-24 25.00 28 Aug-24,ANC-BL-3.MS.FAP Fnisli 345kV yard Pha O MS.FAP-01 Civil earthworks complete 0.00 19,Jul-23 32.00 ♦ Civil earthMrks complete, O MS.FAP-02 Underground piping complete 0.00 23-Aug-23 32.00 ♦ Urdetgraand pipingcomplete„ O MS.FAP-03 Underground conduits complete 0.00 27 Jul-23 21.00 Uhdeirground conduits Complete, a MS.FAP-04 Underground grounding complete 0.00 12,Jul-23 32.00 ♦ Underground grounding complete, 0 MS.FAP-05 Foundations complete 0.00 07-Sep-23 22.00 ♦ Eoundatioris complete, a MS.FAP-06 Dead End steel complete 0.00 19-Apr-24 39.00 ♦I Ddad:End steel corriplete, MS.FAP-07 Substation steel complete 0.00 19- r-24 18.00 ♦ Substation steel corn lete, i� P AP P a MS.FAP-08 Equipment install complete 0.00 03-May-24 43.00 Equipment install complete, - i MS.FAP-09 Bus installation complete 0.00 28-Aug-24 25.00 Bus installation complete, MS.FAP-10 Cable install complete 0.00 24-Apr-24 20.00 Cable install complete, MS.FAP-11 Cable termination complete 0.00 12,Jun-24 16.00 ♦ Cable terrninatiori complete,: MS.FAP-12 Contractor complete 0.00 23,Jul-24 16.00 Contractortesti com lete � P p9 P o MS.FAP-13 Forms submittal complete,testing&comssing 0.00 13-Aug-24 16.00 ♦ :Forms submittal complete,testing&corirssing, :.... ................_ ..........;............i..... 4 ANC-BL-3.MS.SAY Start 500kV-?aM1 219.00 14 Apr-23 24,Jul-24 17.0 v 24,Jui-24:ANC-BL-3.MS.S4Y Start 5pOkV Yard MS O MS.SAY-01 Civil earthworks Start 0.00 14-Apr-23 34.00 ♦ ;Civil earthworks Start, 14Apr 23 O MS.SAY-02 11 F37 Circuit Breaker Foundation Start 0.00 13-Sep-23 39.00 ♦ 11 F37 Circuit Breaker'Foundatidn Start;13Sep-23 O MS.SAY-03 11 E 33 Capacitor Bank Foundation Start 0.00 25-Sep-23 18.00 11::E 33 Capaci*Bank;Foundation Start,;25-Sep-23 MS.SAY-04 11 F37&Switches install Start 0.00 22- r-24 31.00 11 F37&Switches install Start 22-'0AP ?Pr-Apr o MS.SAY-05 11 E 33&Switches Start 0.00 22-Apr-24 31.00 ♦ 11 E 33&;Switches Start,22Apr-24 O MS.SAY-06 Capacitor Bank 2 Start 0.00 30-Apr-24 21.00 ♦ Capacitor Bank 2 Start,30,-Apr-24 0 MS.SAY-07 Construction Started 0.00 23-May-23 A34.00 ♦ Construction Stated,23-May-23 a MS.SAY-08 Dead End steel Start 0.00 02-Nov-23 Dead Erid stee(Start,p2-Nov=23MS.SAY-09Contractor testing Start 0.00 01-Jul-24 ♦ Contractor testing Start,01,Ju1-24 0 Critical(flaot less than 10) Actual Work Critical Remaining... Page 1 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J J A S O N D J F M A M I J I J A S O N D J F M A M J J ASO N D . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MS.SAY--10 Forms submittal complete,testing&comssing 0.00 24-Jul-24 17.00 ♦ Form$submittal;complete,testjing;&comssing,24-JuJ-24 ANC-BL-3.MS.FAY Finish MS 50OW Yard MS 160.00 28-Jul-23 13-Aug-24 16.00 V '13-Aug-24,ANC-8L-3.M5.FAY ;Finish MS 500kV Yard a MS.FAY.01 Civil earthworks complete 0.00 28,Jul-23 57.00 ♦ Civil earthworks icomplete, MS.FAY.02 11 F37 Circuit Breaker Foundation Complete 0.00 22-SSep-23 18.00 ♦ 11 P37.Circuit Breaker Foundation Com lete, � P P P . MS.FAY.03 11 E 33 Capacitor Bank Foundation Complete 0.00 29-SSep-23 46.00 11 E 33 Ca 2citbr Bank Foundation Complete, P P P � P, MS.FAY.04 11 F37&Switches install complete 0.00 03-May-24 21.00 ♦ 11 F37 8 Svtches install complete, MS.FAY.05 11 E 33&Switches complete 0.00 03-May-24 21.00 ' ♦ 11 E 33&Switches complete, a MS.FAY.06 Capacitor Bank 2 complete 0.00 30-Apr-24 25.00 ♦ Capacitor Bank2 complete, MS.FAY.07 Dead End steel complete 0.00 19-AP r-24 38.00 ♦ Dead:End steel corrtP lete, a MS.FAY.08 Construction Complete 0.00 05,Jun-24 21.00 ♦ Construotioh Complete, ..... ...._....... . MS.FAY.09 Contractor testing complete 0.00 23tilu1-24 16.00 ♦ Cpntmctortesting complete, O MS.FAY.10 Forms submittal complete,testing&comssing 0.00 13-Aug-24 16.00 ' ♦ ;Forms submittal complete,testing&comssing, ANC-BL-3.MS.OF Owner Furnished Materials MILESTONES 207.00 03-Apr-23 26,Ja77-24 0.00 26,Jan-24,ANCrBL 3.MS.OF Owher Furnished:Materials MILESTONES O MS.OF.01 345kV Temporary Shoo-fly materials 0.00 03-Apr-23* 0.00 345kV Temporary$hoo-fly materials,; O MS.OF.02 525kV Substation Steel&Anchor Bolts 0.00 15-Aug-23* 0.00 ' ♦ 525kV Substation:Steel&Anchor Bolts; O MS.OF.03 345kV Substation Steel&Anchor Bolts 0.00 15-Aug-23* 0.00 ♦ 345kV Substation;Steel&Anchor Bolts; a MS.OF.04 345kV CCVT(VT10) 0.00 26-Jan-24* 0.00 ' 345kV CCVT(V710), MS.OF.05 525kV CCVT NT9) 0.00 03,Jul-23* 0.00 's ♦ 525kV CCVT(VT9), MS.OF.06 525kV Circuit Breakers 1 No 0.00 10,Jul-23* 0.00 525kV Circuit Breakers 1 No, MS.OF.07 525kV Shunt Capacitor#2 0.00 01-Aug-23* 0.00 ♦ 525kV Shurit Capacitor#2, MS.OF.08 345kV Switches 0.00 01-Aug-23* 0.00 ♦ 345kV Switches, MS.OF.09 525kV Switches 0.00 15-Aug-23* 0.00 ♦ 525kV Switches, MS.OF.10 345kV Substation Dead Ends&Anchor Bolts 0.00 15-Aug-23* 0.00 ♦ :345kV Substation:Dead Ends&Anchor Bolts,; MS.OF.11 345kV Circuit Breakers (5 No) 0.00 02 Oct-23* 0.00 34514V Circuit Breakers (5 Na), MS.OF.12 PST Yard Control House 0.00 31-Oct-23* 0.00 ♦ PST Yard Control House, ............. a MS.OF.13 Control Panels 0.00 30-Nov-23* 0.00 ♦ Control Panels„ 0 MS.OF.14 Reactor Current limiting 525KV 0.00 30-Nov-23* 0.00 ' ♦ Reactor Current limiting 525KY, O MS.OF.24 345kV 533MVA PST#1 0.00 09-Oct-23* 0.00 ♦ 345kV 533MVA PST#1, O MS.OF.34 345kV 533MVA PST#2 0.00 16 Oct-23* 0.00 ♦;345kV 533MVA FIST#2, O MS.OF.44 345kV 533MVA PST#3 0.00 08-Nov-23* 0.00 ♦ 345kV 533MVA PST#3, O MS.OF.54 345kV 533MVA PST#4 0.00 22-Dec-23* 0.00 ♦ 345kV 533MVA PST#4 O MS.OF.64 Station Service Back Up Generator,480 VAC, 150OKW 0.00 11-Sep-23* 0.00 ' ♦ $tation'Service Back Up Gererator,480 VAC, 1500KW, 4 ANC$L3.PM Project Management .50 22-Feb-2" Aug-24 13 Aug-Aug ANC-BL-3.PM Project Management ANC-BL-3.PM.PC Project Control 44.00 10-Mar-23 10-May-23 88.0 P"7 10-May-23 ANC-BL3.PM.PC Project Control O PM.PC-01 Detailed preliminary schedule 23.00 10-Mar-23 11-Apr-23 40.00 � Detailed preliminary schedule O PM.PC-02 RA Detailed preliminary schedule 14.00 12Apr--23 01-May-23 40.00 p RAOetailed praliminaryschedule O PM.PC-03 Detailed Critical Path Method Schedule BL 30.00 10-Mar-23 20-Apr-23 88.00 Detailed Critical Patti Method Schedule BL Q PM.PC-04 RA Detailed Critical Path Method Schedule BL 14.00 21-Apr-23 10-May-23 88.00 RA Detailed Critical Path Method Schedule BL ANC-BL-3.PM.IFC Engineering IFC design packages 53.90 22-Feb-23 25-Apr-23 54.60 ' 25-A6r-23,ANC.BL3.F�M.IFC :Engineering IFC design packages O PM.IFC.01 Shoofly IFC package 1.00 25-Apr-23 25-Apr-23 44.00 1' Shoofly IFC package O PM.IFC.011 IFC Civil 1.00 10-Mar-23 10-Mar-23 20.00 ;I IFC;Civil O PM.IFC.02 Physical IFC package 1.00 22-Feb-23 22-Feb-23 17.30 ' Pf ysibal IFC package PM.IFC.021 345kV Steel/Foundations IFC 1.00 22-Feb-23 22-Feb-23 32.00 345kV Steel%Foundations:IFC PM.IFC.022 IFC PST Control BuildingFoundation 1.00 22-Feb-23 22-Feb-23 24.00 ' IFC PSTControi Buildin Foundation' 9 PM.IFC.023 IFC PEMB Foundation Design(Summit responsibility) 30.00 22-Feb-23 04-Apr-23 16.00 IFC PEMB Foundation Design(Summit responsibility) PM.IFC.024 AN 345kV DE,SM and 500kV Equip IFC 1.00 22-Feb-23 22-Feb-23 25.00 AN 345kV DF,SM and500kVEquip IFC; PM.IFC.025 AN CB,Shunt,Reactor Foundations IFC 1.00 22-Feb-23 22-Feb-23 35.00 ' AN CB,Shunt, Reactor:Foundations IFC PM.IFC.026 Generator Pad IFC 1.00 22-Feb-23 22-Feb-23 38.00 Generator Pad IFC PM.IFC.04 IFC Electrical 1.00 22-Feb-23 22-Feb-23 23.00 ' IFC Electrical PM.IFC.05 IFC PNC 1.00 10-Mar-23 10-Mar-23 45.00 1 iFCPNC 0 Critical(flaot less than 10) Actual Work Critical Remaining... Page 2 of 10 Baseline Actual Level of Effort 0 Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J JJAJSJ 01 NJ D J I F1 M A M I J I J I A I S 1 O 1 N I D J I F I M I A I M I J I J I A I S 1 O 1 N D ANC-BL-3.PM.PP Project Planning 455.50 22-Feb-23 13-Aug-24 19.00 13 Aug-24;,ANC-BL-3.PM.PP Project Planning O PM.PP.01 Submit Letter of Credit 7.00 22-Feb-23 02-Mar-23 20.00 1 Submit Letter of Credit' PM.PP.02 RA Letter of Credit 5.00 03-Mar-23 09-Mar-23 20.00 0 RA Letter of Credit PM.PP.03 Submit Safety Plan 10.00 16-Mar-23 29-Mar-23 40.00 0 Submit Saf : flan: � Y ?tI/ PM.PP.04 RA Safety Plan 5.00 30-Mar-23 05-Apr-23 40.00 RASafety Plan' ' PM.PP.05 Submit QA/QC Plan 25.00 10-Mar-23 13-Apr-23 20.00 p ;Submit QA/QC Plan PM.PP.06 RAQA/QC Plan 8.00 14 Apr-23 25-Apr-23 20.00 ❑ RAQA/QC Plan' PM.PP.07 Submit Environmental Assurance plan 14.00 10-Mar-23 29-Mar-23 30.00 ❑ Submit EnvironfnehtalAsSurahce'plan PM.PP.08 RA Environmental Assurance plan 11.00 30-Mar-23 13-Apr-23 30.00 0 RAEnvirorimzntal Assurance plan PM.PP.09 Submit Environmental Training Plan 32.00 22-Feb-23 06-Apr-23 32.00 Submit Environmental Training Plan PM.PP.10 RA Environmental Training Plan 7.00 07 Apr-23 17-Apr-23 32.00 0 ;RA Environmental Training Plant O PM.PP.11 Substation SSEP 30.00 22-Feb-23 04-Apr-23 28.00 Substation SSEP O PM.PP.12 RA Substation SSEP 13.00 05-Apr-23 21-Apr-23 28.00 ❑ RASUbstatioh SSEP O PM.PP.13 Submit SWPPP 30.00 22-Feb-23 04-Apr-23 40.00 Submit SWPPP O PM.PP.14 RASWPPP 13.00 05-Apr-23 21-Apr-23 50.00 ❑ 'RASWPPP O PM.PP.15 Submit Concrete Mix Design 20.00 22-Feb-23 21-Mar-23 63.00 =1 Submit Concrete Mix Design PM.PP.16 RA Concrete Mix Design 14.00 22-Mar-23 10-Apr-23 63.00a RACoricrete Mix Resign PM.PP.17 Submit Concrete Curing Methods Procedure 24.00 22-Feb-23 27-Mar-23 46.00 Submit Concrete Curing Methods'Prdcedure' a PM.PP.18 RA Concrete Curing Methods Procedure 14.00 28-Mar-23 14-Apr-23 46.00 p RgConcrete Curing Methods Procedure PM.PP.19 Submit Cold weather concreting Ian 20.00 22-Feb-23 21-Mar-23 50.00 Submit Cbld Weather cohcretin' tan (� P P 9 g a PM.PP.20 RA Cold weather concreting plan 14.00 22-Mar-23 10-Apr-23 50.00 p RAQold weattjereonCretng plan PM.PP.21 Submit Hot weather concreting plan 24.00 22-Feb-23 27-Mar-23 44.00 Siabriit Hot weather concreting plan PM.PP.22 RA Hot weather concreting plan 14.00 28-Mar-23 14-Apr-23 44.00 ❑ 'RA Hot weather done feting plan' PM.PP.23 Submit Drilled Pier Installation Plan 24.00 03- r-23 04-Ma 33.00 0 Submit grilled Pierinsiallatiori Plan aAP -23 Y PM.PP.24 RA Drilled Pier Installation Plan 12.00 05-May-23 22-May-23 33.00 ❑ RA Drilled'Pier Installation Plan' ................................... ...._........... ...._... a PM.PP.25 Submit Welding Procedures and plan 14.00 26-Apr-24 15-May-24 25.00 ;Suomi►Welding Progedures and plan PM.PP.26 RA Welding Procedures and plan 14.00 16-May-24 05tilun-24 25.00 RAWelding Procedures and plan O PM.PP.27 Insulators Plan 24.00 23-Feb-23 28-Mar-23 85.00 Irsulators Plan O PM.PP.28 RAlnsulatorsPlan 14.00 29-Mar-23 17- r-23 85.00 ❑ RAlnsulatorsPlan O PM.PP.29 Submit Foundation completion certificate 1.00 07Se -23 07Se -23 55.00 I Submit Fodndatior oam letidn certificate P P P P: O PM.PP.30 RA Foundation completion certificate 14.00 08Sep-Sep 27Sep-Sep 55.00 ❑ RAFoundation lompletioncertificate O PM.PP.31 Submit Project Mechanical Comp Certificate 1.00 20-May-24 20-May-24 18.00 I Submit Project Mechanical Comp Certificate O PM.PP.32 RA Project Mechanical Comp Certificate 14.00 21-May-24 10,Jun-24 18.00 IN RAProject Mechanical Comp Certificate PM.PP.33 Submit Mechanical Completion Test procedures 1.00 22- r-24 22- r-24 18.00 1: Submit M'bcf*anieal Corn Ietion Test iocedu6s O P P AP AP .P . . P. PM.PP.34 RA Mechanical Completion Test procedures 14.00 23- r-24 10-Ma -24 18.00 RA Mecharicat Com 'Ietion Test' rocedures O P P AP Y p P a PM.PP.35 Submit Substation completion certificate 1.00 24-Jul-24 24,Jul-24 16.00 1 Submit Substation complet9on cerpficate a PM.PP.36 RA Substation completion certificate. 14.00 25-Jul-24 13-Aug-24 16.00 IN RASubstation completion certificate. a PM.PP.37 Submit Pre-commissioning schedule and test plan 10.00 22-Apr-24 06-May-24 28.10 ❑ Submit Pre;commissidning schedule and test plan PM.PP.38 RA Pre commissioning schedule and test plan 14.00 06-May-24 24-May-24 28.10 ❑ RA Pre�mr Fission ng$ch.du1e af�d est plan PM.PP.39 Submit Final Equipment test reports 1.00 24,Jul-24 24,Jul-24 16.00 1' Subrriit Final'Equiprnent test reports PM.PP.40 RA Final Equipment test reports 14.00 25,Jul-24 13-Aug-24 16.00 RA Final Equipment fesfreports : : : i PM.PP.45 Submit Conductors 24.00 23-Feb-23 28-Mar-23 23.00 Submit Conductors: O PM.PP.46 RAConductors 12.00 29-Mar-23 13-Apr-23 23.00 ❑ RACohdubtors 0PM.PP.47 Submit Control and Power Cables 24.00 22-Feb-23 27-Mar-23 34.00 S bnnit Control MOPow riCableo O PM.PP.48 RA Control and Power Cables 14.00 28-Mar-23 14-Apr-23 34.00 ❑ RA Cohtral and Power Cables O PM.PP.49 Submit Battery 24.00 23-Feb-23 28-Mar-23 30.00 Submit Battery O PM.PP.50 RA Battery 14.00 29-Mar-23 17-Apr-23 30.00 ❑ RA Battery: O PM.PP.51 Submit Ground Grid 24.00 23-Feb-23 28-Mar-23 33.00 Submit Ground Grid O PM.PP.52 RA Ground Grid 14.00 29-Mar-23 17-Apr-23 33.00 o RA Ground Grid O PM.PP.52.1 Submit Cable Trench 24.00 23-Feb-23 28-Mar-23 23.00 Submit Cable Trend PM.PP.52.2 RA Cable Trench 14.00 29-Mar-23 17-Apr-23 23.00 z RA Cable:Trench: 0 Critical(fact less than 10) 111111l Actual Work Critical Remaining... Page 3 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J I J A I S 10 N D J F M A M J I J I A I S O N I D I J I F I M I A I M I J I J I A I S O N D PM.PP.53 Submit Bus Materials 24.00 23-Feb-23 28-Mar-23 48.90 : Submit Bus Materials i 0 PM.PP.54 RA Bus Materials 14.00 29-Mar-23 17-Apr-23 48.90 ❑ I RA Bus Materials; PM.PP.55 Submit Post insulator 24.00 23-Feb-23 28-Mar-23 43.00 Submit Post:insWlator PM.PP.56 RA Post insulator 14.00 29-Mar-23 17-Apr-23 43.00 t RP Post insulator PM.PP.57 Submit Arresters 24.00 23-Feb-23 28-Mar-23 43.00 Subr it Arresters PM.PP.58 RAArresters 14.00 29-Mar-23 17-Apr-23 43.00 ❑ :RA Arresters PM.PP.59 Submit Transformer 1500 KVA, 150 KVA,100KVA 24.00 23-Feb-23 28-Mar-23 25.00 =1 Submit Transformer 1500 KNA, 150 KVA 100KVA i PM.PP.69 RATransformer1500 KVA, 150 KVA,100KVA 14.00 29-Mar-23 17-Apr-23 25.00 ❑ RA Transformer 1500 KVA, 150KVA,100KVA PM.PP.70 Submit Rebar ShopDrawings 345kV Steel/Foundations IFC 13.00 13-Mar-23 29-Mar-23 20.00 Q Subriiit Rebar Sho Drawirt s 345kVSteel/Foundations IBC 9 p 9 . _...........- PM.PP.71 RA Rebar Shop Drawings 345kV Steel/Foundations IFC 26.00 30-Mar-23 04-May-23 20.00 O RA Reber Shop Drawings;345kV Steel/Foundatiohs IFC .............. .... 0 PM.PP.80 Submit Rebar SD PST Foundation 24.00 23-Feb-23 28-Mar-23 17.30 Submit Rebar SD PST Foundation O PM.PP.81 RA Rebar SD PST Foundation 14.00 29-Mar-23 17-Apr-23 17.30 ❑ RA Rebar SD PST F©uritlati0n O PM.PP.90 Submit Rebar SD Control Building Foundation 24.00 23-Feb-23 28-Mar-23 24.00 Submit Rebar SD Control Building Faundaticin O PM.PP.91 RA Rebar SD Control BuildingFoundation 14.00 29-Mar-23 17- r-23 24.00 ❑ RA Rebar SD Contrd BGildin Foundation; Ap . . . . .9 - _.: --_.......: - O PM.PP.92 Submit PEMB Foundation Rebar ShopDrawings 24.00 05- r-23 08-Ma -23 16.00 0 Submit PEMB Fodndation Rebar Shop'Drawn s 9 Ap Y p 9 O PM.PP.93 RA Submit PEMB Foundation Rebar Shop Drawings 14.00 09-May-23 26-May-23 16.00 :0: R 4Submk PEMB Foundation;Rebar Shop Drawing$ a PM.PP.94 Submit Rebar SD 345kV DE,SM and 500kV Equip IFC 24.00 23-Feb-23 28-Mar-23 25.00 Submit Rebar SD 345k.V DE,Wand 500kV Equip;IFC a PM.PP.95 RA Rebar SD 345k/DE,SM and 500kV Equipt 14.00 29-Mar-23 17-Apr-23 25.00 ❑ 'RA Rebar SD:345kV DE,SM and 500kV Equipt PM.PP.96 Submit Rebar SD CB,Shunt,Reactor Foundations 1 24.00 23-Feb-23 28-Mar-23 35.00 Submit Rebar SD CB,Shunt,Re6ct6,r Foundations l PM.PP.97 RA Rebar SD CB,Shunt,Reactor Foundations 14.00 29-Mar-23 17-Apr-23 35.00 ❑ RA Rebar SD CB,Shunt, Reactor Fouhdatioris : : : : : : : : PM.PP.98 Submit REabr SD Generator Pad 24.00 23-Feb-23 28-Mar-23 38.00 Submit REabr SD Generator Pad u PM.PP.99 RA Rebar SD Generator Pad 14.00 29-Mar-23 17-Apr-23 38.00 ❑ RA Rebar;SD Generator Pad ANC-BL-3.P Pemlittin 10-Mar-23W3,Jun-23 71.00 �:� 23,Jun-23,ANC=BL43.P Permitting ri 9 y' ANC-BL-3.P.SL State/Local 75.00 10-Mar-23 23-Jun-23 71.00 7 23Jun-23,ANC=BL»3.P;SL State/Local P.SLL.01 Provision of Storm WaterPdlution Prevention Permits 10.00 05 Apr-23 18-Apr-23 40.00 ❑ :Provision of Storm Vtei Pollution P2ventionPeEmts P.SLL.02 WY Process of reviewing the NOI,SWPPP,and site map 9.00 19-Apr-23 01-May-23 40.00 p WY Process of reviewing the NOI SWPPP,and;site map P.SLL.03 Building drawings from Sub 30.00 10-Mar-23 20-Apr-23 71.00 � Building drawings from Sub' P.SLL.04 RA Building drawings PC 30.00 21 Apr-23 02,Jun-23 71.00 � RABuild;ing'drawings PC P.SLL.05 APP Review and issue the Large Construction GP 15.00 05-Jun-23 23,Jun-23 71.00 ❑' APP Revi.ewand issue the'La e Con'strdction GP r9 r9: : : : : : : : : : : : ANC-BL-3.PROC Procurement 428.00 22-Feb-23 25-Apr-24,ANC BL-3.PROC Procurement ANC-BL-3.PROC.CF Contractor Fumished Mated 428.00 22-Feb-23 25-Apr-24 41.58 25-Apr-24,ANC: L 3.PROC.CF Contractor Furbished Material o PROC.CF-01 Ordering Conductors 16.00 13-Apr-23 29-Apr-23 33.58 ❑ Ordehng'Conductots O PROC.CF-02 ManufacturingConductors 80.00 29- r-23 18,Jul-23 33.58 O Manufacturin Conductors PROC.CF-03 Delivery Conductors 7.00 18-Jul-23 25-Jul-23 33.58 Delivery Condudtors i� ry ry . _ _ _ o PROC.CF-04 Ordering Control and Power Cables 22.00 14-Apr-23 06-May-23 49.54 Q Ordering Cgntrpl and Power Cables PROC.CF-05 Manufacturing Control and Power Cables 100.00 06-May-23 14-Aug-23 49.54 ] ;Manufacturing CQntrol and Rover Cables a PROC.CF-06 Delivery Control and Power Cables 7.00 14 Aug-23 21-Aug-23 49.54 0 Delivery Control and PoMrCable9 a PROC.CF-07 Ordering Conduits 24.00 22-Feb-23 18-Mar-23 66.58 Ordering Conduits a PROC.CF-08 ManufacturingConduits 10.00 18-Mar-23 28-Mar-23 66.58 ■' Mandfacturin Conduits 9 PROC.CF-09 Delivery Conduits 6.00 28-Mar-23 03-Apr-23 66.58 A belivery;Conduits a PROC.CF-10 Ordering Ground Grid 27.00 17 Apr-23 14-May-23 47.58 M 'Ordering Ground Grid a PROC.CF-11 Manufacturing Ground Grid 38.00 14-May-23 21,Jun-23 47.58 �' Manufacturing Ground Grid: PROC.CF-12 DeliveryGround Grid 6.00 21,Jun-23 27,Jun-23 47.58 0 Delivery Ground Grist a PROC.CF-12.1 Ordering Cable Trench 1.00 17 Apr-23 18-Apr-23 31.58 I :Orderin:g Cable Trench 0 PROC.CF-12.11 Manufacturing Cable Trench 70.00 18-Apr-23 27,Jun-23 31.58 �' Manufacturing Cable Trench . . . . . . . . . : O PROC.CF-12.21 Delivery Cable Trench 2.00 27-Jun-23 29,Jun-23 31.58 1 Delivery Cable Trench O PROC.CF-13 Ordering Bus Materials 28.00 17-Apr-23 15-May-23 69.96 p Ordering Bus Materials O PROC.CF-14 ManufacturingBus Materials 106.00 15-Ma -23 29-Au -23 69.96 0 Manufacturin Bus'IM erials Y 9 .9 PROC.CF-15 DeliveryBus Materials 2,00 29-Au -23 31-Au -23 69.96 Delive :Bus Materials i� I 9 9 ry 0 PROC.CF-16 Ordering Battery 5.00 17 Apr-23 22-Apr-23 43.58 1 Ordering Battery' 0 Critical(flaot less than 10) Actual Work Critical Remaining... Page 4 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J JI AlSIOI NJ D J F M A M J J A SIOI N D J I F I M I A M J I J I A I S 1 O 1 N D PROC.CF-17 Manufacturing Battery 166.00 22 Apr-23 05-Oct-23 43.58 Manufacturing Battery: a PROC.CF-18 Delivery Battery 201.00 05-Oct-23 23-Apr-24 43.58 Delivery Battery a PROC.CF-19 Ordering Post insulator 21.00 17 Apr-23 08-May-23 62.58 O Ordering Post insulator a PROC.CF-20 Manufacturing Post insulator 165.00 08-May-23 20-Oct-23 62.58 D Manufacturing Ppst jnsulat6r -------------- a PROC.CF-21 Delivery Post insulator 160.00 20-Oct-23 28-Mar-24 62.58 D'.elivery Post insulator PROC.CF-22 Ordering Arresters 22.00 17 Apr-23 09-May-23 60.58 p Ordering Arresters PROC.CF-23 Manufacturing Arresters 155.00 09-May-23 11-Oct-23 60.58 1 Manufactu ring:Arresters a PROC.CF-24 Delivery Arresters 171.00 11-Oct-23 30-Mar-24 60.58 DeliveryArresteis PROC.CF-25 Ordering Transformer 1500 KVA 150 KVA 100KVA(345kV YD) 33.00 17-Apr-23 20-May-23 35.58 0 :Or eririg 7ransfor�me r1500 KVA, 150 K.VA,10 KVA(345 V D): a PROC.CF-251 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 82.00 20-May-23 10-Aug-23 35.58 Mahufacturingi Transformer 1500 KVA, 150 KVA,100KVA ....... .... 0 PROC.CF-252 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 82.00 10-Aug-23 31-Oct-23 35.58 0011ft Manufacturing Transformer 1500 KVA, 150 KVA,100KVA O PROC.CF-253 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 40.00 31-Oct-23 10-Deo-23 35.58 Manufacturing Transf6rme:r 1500 KVA, 150 KVA,100KVA O PROC.CF-254 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 20.00 10-Deo-23 30-Deo-23 35.58 0 Manufacturing Transformer 15'00 KVA, 150 KVA,100KVA O PROC.CF-255 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 27.00 30-Deo-23 26,Jan-24 35.58 p; Manufacturing Transformer 1500 KVA, 150 KVA 1OQK\/A O PROC.CF-256 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 34.00 26-Jan-24 29-Feb-24 35.58 0 Manufacturing Trarisfoimeir 1500 KVA, 160 KVA,100KVA O PROC.CF-26 Manufacturing Transformer 1500 KVA, 150 KVA,100KVA 46.00 29-Feb-24 15-Apr-24 35.58 n Manufacturng Transformer 150Q K1/A„15Q KVA,100KVA o PROC.CF-27 Delivery Transformer 1500 KVA, 150 KVA,100KVA 10.00 15-Apr-24 25-Apr-24 35.58 ❑ Delivery transformer 1500 KVA, 150 kVA,100KVA PROC.CF-28 Ordering Rebar 345kV Steel/Foundations 2.00 04-May-23 06-May-23 29.58 :I Ordering Rebar 345kV Steel/Foundations: a PROC.CF-29 Manufacturing Rebar 345kV Steel/Foundations IFC 14.00 06-May-23 20-May-23 29.58 ■ Manufacturing Rebar 345kV Steel)Fe?undati6ns lFC a PROC.CF-30 Delivery Rebar 345kV Steel/Foundations IFC 2.00 20-May-23 22-May-23 29.58 1' Delivery Rebar 34514-V Steel/Foundations IFC a PROC.CF-31 Ordering Rebar PST Foundation 15.00 17 Apr-23 02-May-23 23.58 p Ordering: Rebar PST Foundat�ion PROC.CF 32 Rebar PST Foundation 20.00 02-May-23 22-May-23 23.58 1 ❑ Rebar P5T Foundation PROC.CF-33 Delivery Rebar PST Foundation 5.00 22-May-23 27-May-23 23.58 0 Delivory :Rebar PST Foundation PROC.CF-34 Orderin Rebar Control Building Foundation 5.00 17- r-23 22- r-23 33.58 0 Ordering Reb.ar00trol Buildin Foundatipn i 9 9 AP AP 9 . 9 PROC.CF-35 Manufacturing Rebar Control Building Foundation 15.00 22-Apr-23 07-May-23 33.58 ❑ Mad ufabturing Rebar Cohtrdi Building Foundation: a PROC.CF-36 Delivery Rebar Control Building Foundation 5.00 07-May-23 12-May-23 33.58 0 ;Delivery Rebar Control Building Foundation 0 PROC.CF-37 Ordering rebar PEMB Foundation 6.00 26-May-23 01,Jun-23 25.00 0 Ordering;rebar PEMB Foundation O PROC.CF-38 Manufacturing Rebar PEMB Foundation 15.00 01,Jun-23 16,Jun-23 25.00 Manufacturing Rebar PEMB Foundation O PROC.CF-48 Delivery Rebar PEMB Foundation 15.00 16,Jun-23 01,Jul-23 25.00 p Delivery Rebar PEMB Foundation :......:.......... .. ..:....:.._:..........P..:..' ' O PROC.CF-49 Ordering rebar 345kV DE,SM and 500kV Equip 30.00 17 Apr-23 17-May-23 35.00 p Ordering rebat 345kV DE,SM and 500kV Eq ui ...: O PROC.CF-50 Manufacturing rebar 345kV DE,SM and 500kV Equip 30.00 17-May-23 16,Jun-23 35.00 ;Manufacturing rebar345kV DE„SM and 500kV Equip O PROC.CF-51 Delivery Rebar 345kV DE,SM and 500kV Equip 5.00 16-Jun-23 21,Jun-23 35.00 0; Delivery kebar 345kV 0E,Wand 500kV Equip; O PROC.CF-52 Ordering Rebar CB,Shunt,Reactor Foundations IFC 25.00 17 Apr-23 12-May-23 50.00 O :Ordering Rebar CB,Shunt,Reactor Foundations:IFC PROC.CF-53 Manufacturin rebar CB,Shunt,Reactor Foundations IFC 15.00 12-Ma -23 27-Ma -23 50.00 ❑: Manufac(uriri rebar CB,Shunt, Reactor Foundatioi s IFC O 9 Y Y 9 . 0 PROC.CF-54 Delivery Rebar CB,Shunt,Reactor Foundations IFC 10.00 27-May-23 06,Jun-23 50.00 ❑ Delivery Rebar:CB,Shunt,Reactor Fouhdations IFC a PROC.CF-55 Ordering rebar Generator Pad 26.00 17 Apr-23 13-May-23 54.00 p Ordering rebar: Generator Pad a PROC.CF-56 Manufacturing rebar Generator Pad 15.00 13-May-23 28-May-23 54.00 0 Manufacturing rebai Generator Pad p PROC.CF-66 Delivery Rebar Generator Pad 5.00 28-May-23 02,Jun-23 54.00 1 Delivery:Rebar Generator Pad ANC$L-3.0 Construction 14-Apr-23 23-Sep-24 33.0 23'-Sep-24,ANG-BG3.0 Construction: ANC-BL-3.C.TL Transmission Line 234.00 02-May-23 29-Aug-24 24.00 : 29-Aug-24,ANC-BL-3.C.TL Transmission Line .. 1 0-May-23 40.00 0-May-23:ANC$1--3.C.TL.81-1 Shoofly install 6� C.TL.SH.01 Framing&install,and(Remove old one) 5.00 02-May-23 08-May-23 40.00 . Framing&install,2nd(Remove bid brie) o C.TL.SH.02 OPGW 2.00 09-May-23 10-May-23 40.00 I OPOW C.TL.SH.021 Fiber Optic Cable ADSS 1.00 09-Ma -23 09-Ma -23 41.00 1 fiber O tic Cable ADSS' o P Y Y P � C.TL.SH.03 Outage scheduled on 05/09/2023(6am}05/10/2023(6am). 1.00 10-May-23 10-May-23 40.00 I Outage scheduled on 05/09/2023(6arri)-05/10/2023(Sam). .. . • �V 2 Aug-24,ANC-BW.C.TL.SHR Shioof(y remove O C.TL.SHR.01 Shoofly removal,Final Span 19.00 05-Aug 24 29-Aug 24 24.00 Shod fly tembval,Final Span _ I I ANC-BL-3.C.SS Substatio 445.50 14-Apr-23 23Sep-Sep 33.00 ; 23Sep-24,ANC-BL;-3.C.S$ Substation •: rr •: -. : 23Sdp-24,ANC BLS 3.C.SS.TF MOBIDMOB : - - - v C.SS.TF.01 Temporary Office Facilities 6.00 02-May-23 09-May-23 74.00 : Temporary Office Facilities 0 Critical(flaot less than 10) I Actual Work Critical Remaining... Page 5 of 10 Baseline Actual Level of Effort Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J I J I A I S O N D J F M A M J I J I A I S1 01 N I D I J F M A M J J A S O N D 0 C.SS.TF012 Mobilization 15.00 02-May-23 22-May-23 74.00 0: Mobilization o C.SS.TF02 Staging Facilities 6.00 23-May-23 31-May-23 84.00 d Staging racilities O C.SS.TF03 Temporary Construction Facilities 4.00 25-May-23 31-May-23 84.00 0 Temporary Construction Facilities C.SS.TF04 Demobilization 8.00 12Se -24 23Se -24 28.00 ■ Demobilization fi P P .• •• • 23-Aug-24,ANC=BL-3.C.SS.CE Civil 5iWwork and Fini Q C.SS.CE.01 Dust suppression/Dust abatement 1 24.00 12-May-23 15-Jun-23 49.00 p ;Dust srappressiontDust abatement 1 O C.SS.CE.02 Dust suppression/Dust abatement 2 24.00 16,Jun-23 20,Jul-23 49.00 Dust suppression/Dust abatement 2 O C.SS.CE.03 Dust suppression/Dust abatement 3 24.00 21,Jul-23 23-Aug-23 49.00 p Dust suppression/Dust abatement 3 C.SS.CE.04 Dust suppression/Dust ression/Dust abatement 4 24.00 24 Au -23 27Se -23 49.00 0 Dust su : ression/Dust abatement 4 O PP 9 P PP O C.SS.CE.05 Dust suppression/Dust abatement 5 8.00 28Sep-23 09 Oct-23 49.00 ❑ Dust suppression/Dust abatement 5 O C.SS.CE.06 Dust suppression/Dust abatement 6 24.00 10-0ct-23 12-Apr-24 49.00 Dust suppression/Dust abatement O C.SS.CE.07 Installation of SWPPP Measurers 3.00 15-May-23 17-May-23 55.00 1 Installation ofSWPPP Measurers O C.SS.CE.08 Removal and site Restoration 8.00 14-Aug-24 23-Aug-24 28.00 ■ R2mdval'and site Restoration :• •• • 7 11-Aug=23 ANC-BL�.C.>S.CE AW Aritidine Wash - - o C.SS.CE.AW.01 Survey and Staking 4.00 14-Apr-23 19-Apr-23 34.00 1 SurveX and Staking C.SS.CE.AW.02 Excavation,NewAntidine Wash 1 20.00 16-Jun-23 14 Jul-23 57.00 ;Excavation, NewAntidine Wash1 C.SS.CE.AW.03 Excavation,NewAntidine Wash 2 20.00 17-Jul-23 11-Aug-23 57.00 Excavation,NewAnticline Wash 2 C.SS.CE.AW.04 Fill and Grading,Existing Anticline Wash 10.00 17-Jul-23 28 Jul-23 57.00 ■' Fill and Grading;Existing AhticlineWash • •.• p9-Ma) 24 ANC-E3L .C.SS.CE SP Substation Pad : SS.CE.SP.01 Mass Site Excavation 23.00 04-May-23 06 Jun-23 20.00 Mass Site Excavation SS.CE.SP.02 Fill,compaction and grading 23.00 09-May-23 09,Jun-23 20.00 0 Pill,compaction arid grading SS.CE.SP.03 General Excavation,Spread on site 29.00 23-May-23 03ti1u1-23 16.00 General Excavation,Spread on site SS.CE.SP.04 Crushed Rock,RG2 Fill 20.00 21,1un-23 19tilu1-23 32.00 0 Crushed Rock,RG-2 Fill SS.CE.SP.05 Crushed Rock Aggregate Base Course 10.00 20�Jul-23 02-Au -23 32.00 ❑ Crushed Rock A re ate Base Course' � 9 99 9 SS.CE.SP.06 Oil Containment Piping 25.00 20,Jul-23 23-Aug-23 32.00 i�; Oil Cdnta nment Piping SS.CE.SP.08 Site Drainage 9.00 24 Aug-23 06Sep-Sep 44.00 0 SiteDrainage SS.CE.SP.09 Crushed Rock,Rip Rap 10.00 23-Apr-24 06-May-24 43.00 0 Crushed Rodc,Rip Rap SS.CE.SP.091 Substation Insulating Rock 10.00 26-Apr-24 09-May-24 43.00 ❑ Substation lnsUlating'Rodk SS.CE.SP.11 Substation Yard Rock 6.00 26-A r-24 03-Ma -24 43.00 i] Substation Yard Rock p y : : : : : : . . . . . . . . • • 01-Nov-23,ANC-BL-3.C.SS.FND Fdundation • .. • • fad q9-Oct-23,ANCSL-3jC.SS.FND.Pa Concrete-slab On grade O SS FND.Pa.01 345KV 3000ACIRCUIT BREAKER 12.00 30-May-23 14-Jun-23 16.00 Q 345KV 3000ACIRCUIT BREAKER SS.FND.Pa.02 345KV CONTROL BUILDING FOU NDATION 10.00 06-Jun-23 19,Jun-23 28.00 � '345KV CONTROL BUILDINGFOUNDATION SS.FND.Pa.03 500KV CIRCUIT BREAKER, pad 8.00 13Sep-Sep 22Sep-Sep 18.00 0; 500KV CIRCUIT BREAKER, pad; SS.FND.Pa.04 500KV BREAKER CONTROL CABINET FOUNDATICN 3.00 25Sep-Sep 27Sep-Sep 31.00 I 500KV BREAKER CONTROL CABINET FOUNDATION SS.FND.Pa.05 500KV STORAGE BUILDING 8.00 28Sep-Sep 09-Oct-23 31.00 Q 500KV STORAGE BUILDING SS.FND.Pa.06 345 Generator Pad 7.00 29-Aug-23 07Sep-Sep 21.90 345 GeneratorPaii . . . • fa �I 21Aug-23,ANCBL;3.C.SS.FND.TY 345kVCorcrete-drilled pier FND O SS.FND.TY.01 345KVBUS SUPPORT Concrete 18.00 15-Jun-23 11-Jul-23 16.00 0 ;345KVBU$SUPPORT Concrete : SS.FND.TY.02 345KV CCVT SUPPORT 3.00 12,Jul-23 14,Jul-23 16.00 1 345KV CCVT SUPPORT SS.FND.TY.03 345KV PHASE SPACING 7.00 18,Jul-23 26,Jul-23 16.00 p; 345KV PHASE SPACING SS.FND.TY.04 345KV SURGE ARRESTER 9.00 25,Jul-23 04-Aug-23 16.00 (3 945KV SU RGE ARRESTER; SS.FND.TY.05 345KV STATIC SHIELD MAST 12.00 28,Jul-23 14-Aug-23 16.00 ■ 345KV;SWnC SHIELD MAST SS.FND.TY.06 STATION SERVICE STRUCTURE 3.00 28,Jul-23 01-Aug-23 16.00 1 STATION SERVICE STRt1C7UR6 SS.FND.TY.07 345KV JCT BOX POLE 3.00 28,Jul-23 01-Aug-23 16.00 0 345KV JCT BOAC POLE : . . . . . SS.FND.TY.08 345kV CCVT(VT10) 3.00 28,Jul-23 01-Aug-23 16.00 1 3454cV GCVT(VT1lj) SS.FND.TY.18 345kV Switches,Misc 7.00 11-Aug-23 21-Aug-23 16.00 ❑ 345kV SvstcFies, Misc • •.. -• �► :12Sep-23;ANC-BL-3.C.SS.'FND.DP Dead End Structures Piers O SS FND.DP.01 345KV 60'A-FRAME DE 15.00 22-Aug-23 12-Sep-23 16.00 345KV 60'A-FRAME;Dr r• . . -• -• 'TV 29Sep-23,ANC-BL-3.C.SS.FND,'PY 50DkV Concrete-drilled pier'FND SS.FND.PY.02 1525kV CCVT(V9) 1 2.00 13Sep-23 14Sep-23 16.00 1 ;525kV CC;VT(V9) 0 Critical(flaot less than 10) 111111l Actual Work Critical Remaining... Page 6 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J J A S O 1 N D J I F I M I A I M I J J A S O N D J IF I M I A M J I J A S O N D SS.FND.PY.03 525kV Circuit Breakers(5 No) 3.00 13Sep-23 15-Sep-23 16.00 I I52$kV;Circuit iBr akers(5 Nq) SS.FND.PY.04 Shunt Capacitor#2 I 5.00 25Sep-23 129Sep-23 I 18.00 I I I Shunt Capacitor#2 . - • rr • . :A 0.1-Nov-23,ANC-BL-3.C.SS.FND:RF Reactor fbundation: SS.FND.RF.01 525KV Reactor,Current Limiting I 9.00 18-Oct-23 I01-Nov-23 125.00 El 525KV Reactor Current Limiting SS.FND.RF.02 Crosshole Sonic Logging 1 2.00 27-Oct-23 01-Nov-23 25.00 I] Crosshole Sonic LOgging rr rr i• 1214,Jul-23,ANC-BL-3 C.$S.FNQ.TF Ttansformer;foundotion&oil Wntainrnent O SS FND.TF.01 345KV PST FOUNDATION&OIL CONTAINMENT 30.00 09-Jun-23 21-Jul-23 76.00 345KV PST FOUNDATION:&OIL CONTAINMENT • • -• Vmmm�.F 07-Sep=23,ANC-BL-3:C.SS.GG Ground Grid p C.SS.GG-01 Below Grade 345kV Yard 1 10.00 28-Jun-23 12-Jul-23 32.00 Below Grade 345kV Yard;1 O C.SS.GG-02 Above Grade 345kV Yard 2 10.00 13�Jul-23 26,Jul-23 81.00 ■ Above Grade 345kV Yard 2 O C.SS.GG-03 Below Grade 500kV Yard 1 10.00 27�1u1-23 09-Aug-23 81.00 0 Below Grade 500KV Yard1 O C.SS.GG-04 Below Grade 500kV Yard 2 10.00 10-Aug-23 23-Aug-23 81.00 ■ Below Grade;500kV Yard 2 p C.SS.GG-05 Above Grade 500kV Yard 3 10.00 24-Aug-23 07Sep-Sep 81.00 ■ Above Grade 500kV Yard:3 • . 0 0 lam :21=Aug-25,ANC-BL�.C�.SS.CT Ci3ble Trench a C.SS.CT.01 Cable Trench-345kV Yard 1 10.00 30-Jun-23 14-Jul-23 20.00 ❑ :Cable Trench 345kV Yard 1 0 C.SS.CT.02 Cable Trench-345kV Yard 2 10.00 17-Jul-23 28,Jul-23 20.00 ❑ Coble Trench-345kV Yard;2 0 C.SS.CT.03 Cable Trench-500kV Yard 1 8.00 10-Jul-23 19,Jul-23 51.00 Cable lTrench-500kV Yard I o C.SS.CT.04 Cable Trench-500kV Yard 2 8.00 10-Aug-23 21-Aug-23 36.00 ❑ CableTrencf -500kV Yard 2 :......:......:......:..........._:.. • rr '. . •f� 30-A0r-24,ANG-BW.C.SS.EC Electrical Conduit O C.SS.EC.01 Conduit Below Grade 345kV Yard 1 15.00 10-May-23 31-May-23 21.00 'M: Conduit Below Grade 345kV Yard 1 o C.SS.EC.02 Conduit Below Grade 345kV Yard 2 20.00 01-Jun-23 28,Jun-23 21.00 Wj Conduit Below Grade 345kV Yard;2 O C.SS.EC.03 Conduit Below Grade 345kV Yard 3 20.00 29,Jun-23 27,Jul-23 21.00 M C©nd ait Bel: Grade 345kV Yard:3 O C.SS.EC.04 Conduit above Grade 345kV Yard 25.00 05Sep-Sep 09-Oct-23 25.00 Conduit above Grade 345kV Yatd . O C.SS.EC.05 Conduit Below Grade 500kV Yard 1 25.00 18,Jul-23 21-Aug-23 36.00 � Conduit Below Grad6 500kV Yard.1 O C.SS.EC.06 Conduit Below Grade 500kV Yard 2 20.00 20Sep-Sep 17 Oct-23 16.00 O Conduit Below Grade 500kV Yard 2 . . : : i - C.SS.EC.07 Conduit Below Grade 500kV Yard 3 15.00 18-Oct-23 09-Nov-23 16.00 0 Conduit Below Grade 500kV Yapd 3 p C.SS.EC.08 Conduit Above Grade 500kV Yard 15.00 10-Nov-23 30-Apr-24 16.00 Conduit Ab©ve Grade!500kV Yarci . . • 25-Apr-24,ANC:BL3.C.SS.F FerJcing : C.SS.FF01 Fencing,Gates,Signs 13.00 02-Nov-23 18-Apr-24 Q-- -- O Fehcing,Gates,Signs Q C.SS.FF02 Ground Fence 5.00 19-Apr-24 25-Apr-24 p Ground Fence -. • • 02-Aug-24,ANC-BL-3 C.SS.SET Steel Erection �� . . �� 07-Nov23,iANC BL-3C.SS.SE7SE7 345kV Steel ErectionO SET.SET.01 345KV BUS SUPPORT 14.00 25Sep-23 12-Oct-23 1 . ■ 345KV'BUS SUPPORT-- ----- ---------;- - . ...._-.... --------- :..SET.SET.02 345KV,PHASE SPACING DISCONNECT SWITCH SUPPORT 10.00 13-Oct-23 26-Oct-23 18.00 ❑ 345KV/,PHASE SPACING DISCONNECT SWITCH;SUPPORT SET.SET.03 345KV PHASE CCVT SUPPORT 1.00 27-Oct-23 27-Oct-23 18.00 I 345KV PHASE CCVT SUPPORTSET.SET.04 345KV SURGE ARRESTER SUPPORT Insulators 1.00 27-Oct-23 27-Oct-23 19.00 1345KV SURGEARRESTERSUPPORTInsulators SET.SET.05 STATION SERVICE Structural Steel Substation Yard Lighting 1.00 01-Nov-23 01-Nov-23 18.00 1 STATION SERVICE Structural Steel Substation Yard Lighting SET.SET.06 345KV STATIC SHIELD MAST,and G Mat 5.00 01-Nov-23 07-Nov-23 18.00 0 345KV:STATIC SHIELD MAST,and G Mat SET.SET.07 345KV SURGE ARRESTER SUPPORT 1.00 01-Nov-23 01-Nov-23 18.00 I 345kV SURGEARREST RSUPPORTSET.SET.OS Structural Steel,STATION SERVICE 1.00 01-Nov-23 01-Nov-23 18.00 I Structural Steel;STATION SERVICE: . • . 4 19-Apj--24;,ANC-BL.3.0 SS SETDF-S Dead End:Structures Piors 345 SS SET.DES.01 345KV 60'A FRAME DEADEND 14.00 02-Nov-23 19-Apr-24 18.00 345KV 60'A-FRAME DEADEND . 23-Apr-24,ANCBL 3.G.SS.SETSTF 500kVSteel Erection:.SET.STF.01 525KV LOW SWITCH STRUCTURE 2.00 22Apr-24 23-Apr-24 20.00 1 525KV LOW SWITCH STRUCTURESET.STF.02 525kV,RELOCATION OF BUS SUPPORT 1.00 22Apr-24 22-Apr-24 20.00 1525kV',RELOCATION OF BUS:SUPPORT SET.STF.03 525KV,CCVT SUPPORT 1.00 22Apr-24 22-Apr-24 20.00 1; 525KV,CCVT SUPPORT SET.STF.04 525kV,SURGE ARRESTOR SUPPORT 2.00 22-Apr-24 23-Apr-24 25.00 1525kV,SURGE ARRESTOR SUPPORT• 02-Aug-24,ANC-BL�iC.SS.SET.STB StorageBuilidng P SET.STB.01 Building Structure 12.00 02-Nov-23 17-Apr-24 25.001 L Building Structure SET.STB.02 Building Erection 1 16.00 18-Apr-24 09-May-24 1 43.00 0 Building Erection 1 SET.STB.021 Building Erection 2 16.00 10-May-24 03-Jun-24 1 43.001 ❑ BuildingErection 2 0 Critical(flaot less than 10) 111111l Actual Work Critical Remaining... Page 7 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J I J A S O N D J I F I M A M I J I J I A I S 1 O 1 N I D J I F I M I A I M I J I J I A I S O N D -.j SETSTB.022 Building Erection 3 16.00 04-Jun-24 25,Jun-24 43.00 i ;I-]: Building Erection 3 SET.STB.03 Garage Doors 7.00 26-Jun-24 04 Jul-24 43.00 Garage Doors 0 SET.STB.04 Electrical 12.00 08-Jul-24 23,Jul-24 43.00 ■ Electrical 0 SET.STB.05 Pallet Racks 8.00 24-Jul-24 02-Aug-24 43.00 Pallet Racks • 11ECTITI i 0• : • 00 P'W-F-F 28 Aug-24,ANC-BL-3.C.SS.BW BusrWdrk Q SS BW.01 Strain Bus,Jumpers 1 20.00 06-Jun-24 03-Jul-24 25.00 p Strain Bus,Jumpers 1 SS.BW.011 Strain Bus,jumpers ers 2 20.00 04�Jul-24 31,Jul-24 25.00 Strain Bds,Jum'ers 2 o P P . . . . . . . . . . . O SS.BW.02 Solid Bus 20.00 01 Aug-24 I 28-Aug-24 25.00 =1 Solid Bus : : : : : . . . . - -. : • 17=May-24,ANC-01-3&C.SS.IE Installation Equipment •722-A�pr-24 17=May-24,ANC=BL=3.C.SS.IE;T 345KV Yard SS IE.T.01 345kV CCVT(VT10) 1.022-Apr-24 18.001 345kV CCVT(VT10) SS.IE.T.02 345kV Circuit Breakers 8.012-Oct-23 58.90 0 345kVCircuit Breakers SS.IE.T.03 345kV Switches 14.017-Apr-24 48.00 345kV Switches .............. :..... 0 SS.IE.T.04 345KV SURGE ARRESTER 1.00 24-Apr-24 24-Apr-24 44.00 I 345KVSURGEARkE$TEk 0 SS.IE.T.05 STATION SERVICE Substation Yard Lighting 3.00 24-Apr-24 26-Apr-24 44.00 0 STATION SERVICE Substatioh Y2rd Lighting SS.IE.T.06 345KV STAl1C SHIELD MAST 1.00 29-Apr-24 29-Apr-24 44.00 345t / STATICSHIELD IVIAST M SS.IE.T.07 345KV SURGE ARRESTER 6.00 29-Apr-24 06-May-24 44.00 345KV SURGE ARRESTER! - M SS.IE.T.08 STATION SERVICE 3.00 07-May-24 09-May-24 44.00 1 STATION SERVICE SS.IE.T.09 345kV 533MVA PST#1 4.00 09-0ct-23 13 Oct-23 64.90 345kV533MVA PST#1 SS.IE.T.19 345kV 533MVA PST#2 5.00 16-Oct-23 23-Oct-23 59.90 0:: 345kV 533MVA PST#2; SS.IE.T.29 345kV 533MVA PST#3 5.00 08-Nov-23 15-Apr-24 57.90 345kV,533MVA PST##3 SS.IE.T.39 345kV 533MVA PST#4 5.00 12 Apr-24 19-Apr-24 57.90 345kV 533MVA PST#4 SS.IE.T.40 345KV Yard Inspection and testing PacfiCorp Forms 5.00 13-May-24 17-May-24 18.00 0 345KV Yard Inspection and testing,PacifiCoo.Forms: • `. TO 17: ay-24,ANC: L=3.C.SS.IEF 525kvYard: O SS IE.F.01 525kV CCVT(VT9) 1.00 23-Apr-24 23-Apr-24 20.00 1 525kV CCVT(VT9) SS.IE.F.02 525kV Circuit Breakers(5 No) 5.00 23-Apr-24 29-Apr-24 20.00 R 525kV Circuit Breakers(5 No) SS.IE.F.03 525kV Shunt Capacitor#2 1.00 30-Apr-24 30-Apr-24 20.00 525kV Shunt Capacitor#2 SS.IE.F.04 525kV,SURGE ARRESTOR 5.00 01-May-24 07-May-24 20.00 0 525kV,SURGE ARRESTOR SS.IE.F.05 525kV Switches 10.00 22 Apr-24 03-May-24 21.00 0 525W Switches 0 SS.IE.F.15 525KV Yard Inspection and testing PacifiCo Forms 5.00 13-Ma -24 17-Ma -24 18.00 0 525KV Yard Iris ection and testin PacifiCo `Forms: P 9 rP Y Y P; g: rR •0 � 17=May-24,ANC-1BL 3.C.SS.IE;R Reactor O SS.IE.R.01 Reactor Current limiting 525KV 1.00 06-May-24 06-May-24 21.00 I ReactorCurrerit limiting 525KV SS.IE.R.11 525KV Reactor Inspection and testing PacifrCo Forms 5.00 13-Ma -24 17-Ma -24 18.00 1 525KV Reactor Iris ection and PacifiCo Forms' P 9 rP Y Y P 9 rP; • - 1 11 •. : • W► 17: ay-24,ANC:BL�.G.SS.IE P Protection&Control Equipment SS IE.P.01 345 kV Control and Relay Panels 2.00 06-May-24 07-May-24 21.00 1 3451kV Control and Relay Panels SS.IE.P.02 345 kV Annunciator and RTU Panels 1.00 06-May-24 06-May-24 21.00 1 345:kV Annunciator and RTQ Panels SS.IE.P.12 Forms Inspection and testing PacifrCo Forms 345KV Protection and Con 5.00 13-Ma -24 17-Ma -24 18.00 1 I Forms)Ins eetiori arid testin Pacific Porr s 345KV Protection P 9 rP $ Y Y P 9 o<P . 0 •. 4 4 0 0 w 17:May-24,ANC;BL;3.C.SS.IEiCH Control House O SS.IE.CH.01 Structure,internal fixtures 1.00 06-May-24 06-May-24 21.00 I Structure,iriterrral ,fixtures; SS.IE.CH.02 DC Batteries,racks,Chargers 1.00 07-May-24 07-May-24 21.00 1 DC Batteries,mck5,Chargers SS.IE.CH.03 Panel Installation 1.00 08-May-24 08-May-24 20.00 1 Panel Installation SS.IE.CH.13 CH Inspection and testing PacifiCo Forms 5.00 13-Ma -24 17-Ma -24 18.00 1 CH Ins ectior and testin PacifiCo Foms P 9 rP Y Y P 9 rP . • 17May-24,ANC;BL;3.C.SS.IE:SP Station Power SS.IE.SP.01 Transformer 1500KVA 4.00 26-Apr-24 01-May-24 24.00 0 Transformer 15OOKVP- SS.IE.SP.02 Transformer 150KVA 4.00 29-Apr-24 02-May-24 24.00 0 Transformer 150KVA SS.IE.SP.03 Transformer 100KVA 4.00 30-Apr-24 03-May-24 24.00 Transformer 1©OKVA SS.IE.SP.04 Manual Transfer Switch 4.00 02-May-24 07-May-24 24.00 1i MarivalTransfer Switch SS.IE.SP.05 Safety Switch 2.00 02-May-24 03-May-24 24.00 1 Safety Switch SS.IE.SP.06 Transformer 1001KVA 2.00 1 02-May-24 03-May-24 24.00 1 Traneormmer 1©OKVA SS.IE.SP.07 Circuit BreakerEncosure 2.00 02-May-24 03-May-24 24.00 1 Circuit BreakerEnclosure SS.IE.SP.08 Station Service Generator, 1500kW,480V 7.00 11-Sep-23 191 75.001 ■ Station Service Generator, 150QkW,4$OV 0 Critical(flaot less than 10) 111111l Actual Work Critical Remaining... Page 8 of 10 Baseline Actual Level of Effort m Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J J I A S1 01 N D J I F M A M J J A S 01 NJ D J I F M A M J J A S O N D SS.IE.SP.09 Panelboard,AC 1.00 02-May-24 02-May-24 24.00 I P:anolbaard;AC SS.IE.SP.10 Station Lighting Fbdures and Outlet Assemblies 1.00 03-May-24 03-May-24 24.00 I Station Lighting Futures and butletAssemblies SS.IE.SP.20 SP Inspection and testing PaafiCorp Forms 5.00 13-May-24 17-May-24 18.00 1 SP Inspection and testing PaciEiCoip Forms . 11 11 12-jun 24,ANC-BL-3.C.$S.CTF Cables Ten-niriation O SS.CET.01 Control wiring/Power cable 345kV Yard 1 Field Cable Installation 30.00 31-Jul-23• 11Sep-23 20.00 O Control wiring/Power Cable 345kV Yard 1 Field'Cable Installation' p SS.CET.011 Control wiring/Power cable 345kV Yard BW Field Cable Installation 25.00 12Sep-23 16-Oct-23 20.00 0 ;Control wining/Power cable 345kV Yard;BVV Feld Cable Installation p SS.CET.02 Control wiring/Power cable 345kV Yard 2 27.00 17-Oct-23 24-Apr-24 20.00 L Control wiring/P©wer cable 345kV Yard 2 : p SS.CET.03 Control wiring/Power cable 525kV Yard 1 7.00 01-May-24 091 16.00 0 Control:wiring/Power cable 525kV Yard 1 O SS.CET.04 Control wiring/Power cable 525kV Yard 2 9.00 10-May-24 22-May-24 16.00 ■ Contrpl wiring/Power cable 525kV Yard 2 O SS.CET.05 345kv Yard Cable Termination 1 7.00 23-May-24 03,Jun-24 16.00 0 345kv Yard;Cable Teniiinetion 1 O SS.CET.06 345kv Yard Cable Termination 2 7.00 04,1un-24 12tilun-24 16.00 0 345kv Yarn Cable Termination 2 . O SS.CET.07 Control House Cable Installation 10.00 14-May-24 28-May-24 21.00 ❑ Control Mouse Cable Installation O SS.CET.08 Control House Cable Terminations 6.00 29-May-24 05tilun-24 26.00 ? 0 Control House'Cable Terminations SS.CET.09 525kV Yard Cable Termination 6.00 29-May-24 05tilun-24 21.00 0 525kV Yard;Cable;Terinination 4 ANC$L-3.TST Testing &Commissioning 0 13-Jun-24� 09-Oct-24 6.00 �7 09-Oct-24,ANC-BL-3;TST Testing&Commission 9 ANC-BL-3.TSTS Substation 84.00 13-Jun-24 09-Oct 24 16.00 !'I 09 pct- 4,i4NC-BL�TS7S;Substation --..... ' • : • 11 R 20�Jun-24,ANC=BL-3.TST.S.ST 345kV Yard EquipMent Testin • 11 1 r TST.S.ST.01 SurgeArrestors2 1.00 13-Jun-24 13-Jun-24 16.00 1 ::Su' e Arrestors 2 i TST.S.ST.011 MOAB/Transrupter4 1.00 14,Jun-24 14,Jun-24 1 6.00 I 11 Transnapfer4 i TST.S.ST.012 Fiber Splicing 1.00 14-Jun-24 14,Jun-24 16.00 1 'Fiber Splicing I r 11 . 11 w;181un-24,ANC-BL .T$T.5.S702 Circuit Breakers TST.S.ST.022 SF6 Gas Charging CB(345kV)5 3.00 14,1un-24 18tilun-24 16.00 1 SF6 Gbs Charging CB(345kV):5 TST.S.ST.023 Vacuum Per CB(345kV)5 1.00 14-Jun-24 14,Jun-24 16.00 I Vacuum Per CB(345kV)5 r 11 . 11 ' ♦ 18�Juri-24,ANC-13L-3.TST831.03 Transfomiers: O TST.S.ST.032 Power Transformer(W/DETC)0 1.00 17-Jun-24 17-Jun-24 16.00 ' I Poin�r'Trahsformer(W/DETC)0 TST.S.ST.033 Station Service 4 1.00 18-Jun-24 18-Jun-24 16.00 1 Station Service 4 2Wun-24,ANC=BL-3.TST.S.ST.04 Instrurnent Transformers p TSTS.ST041 CCVT1 2.00 18-Jun-24 19-Jun-24 16.00 1 CGVT;1 TST.S.ST.042 CT(Transformers)0 1.00 20-Jun-24 20,Jun-24 16.00 1 CT ransformers 0: (T ) R: ) TST.S.ST.043 CT(CB's) 30 1.00 20-Jun-24 20,Jun-24 16.00 1 CT(CB's) 30 TST.S.ST.044 Current Circuit Secondaries 30 1.00 20,Jun-24 20,Jun-24 16.00 I Current Circuit Secondaries 30 TST.S.ST.045 Voltage Circuit Secondaries 1 1.00 20,Jun-24 20tilun-24 16.00 : : : : I Voltage Circuit Secondaries 1 r 11 1 1 . 11 T 20-Jun-24,ANC=BL-3.T$T.$.ST05; Grounding O TST.S.ST.051 Ground Grid Injection 1 1.00 20-Jun-24 20-Jun-24 16.00 1 Ground Grid Injection 1 r• 11 1 1 . 11 20,Juh-24,ANC4BL-3.TST.S.ST.06 Contrbls Circuits O TST.S.ST.061 Functional Testing(Per Breaker)5 1.00 20-Jun-24 20-Jun-24 16.00 1 Functional Testing(Per BreWe0 5 I I I I TST.S.ST.062 Functional Testing(Pe rXfmr)0 1.00 20,Jun-24 20,Jun-24 16.00 I Functional Testing(FbrXfmr)0 I I TST.S.ST.063 Point to Point wire verification(Per Breaker)5 1.00 20,Jun-24 20,Jun-24 16.00 I; Point to Point wire verification(PerSreaker)5; TST.S.ST.064 Point to Point wire verification(Per Transformer)4 1.00 20-Jun-24 20,Jun-24 16.00 I Point to Point wire verification(Per Transformer)4 r 11 1 1 . 0 V' 20-Jur-24,ANC BL-3.TST.S.ST.07 Cable Testing O TST.S.ST.071 VLF 5 1.00 20-Jun-24 20-Jun.24 16.00 1;VLF 5 I ' 1 1 . 11 ' 2Wur-24,ANC=BL-3.TST.S.ST.08 Ldw Voltage Sedtiori(Verifi ' ' ' p TSTS.ST081 LV Yard Panels 4 1.00 20-Jun-24 20-Jun-24 16.00 I; LV:Yaid Panels 4 TST.S.ST.082 LV Yard Panels Mod's 2 1.00 20-Jun-24 20 Jun-24 16.00 I LV Yaid Panel Mods 2 TST.S.ST.083 LV Safety Switches 5 1.00 20,Jun-24 20,Jun-24 16.00 I' LV Safety Switches 5 • • : • 11 • 11 R 28-Jun-24,ANC-BO-TST,S.CH Control House Testing&Co • � I I I ' TST.S.CH.01 Reports/Project Management 1.00 21-Jun-24 21-Jun-24 16.00 : : : : 1 Reports/Project Management TST.S.CH.02 Drawing Control(when customer requests)1 1.00 21,1un-24 21tilun-24 16.00 I; Drawing trontrol(when Customer requests)1 r 11 11 V. 21�Jun-24,ANCjBL-3.T8T8.CH.03 Battenes p TST.S.CH.031 Battery String Testing(1hrDischarge Rate)(1 25V)2 1.00 21-Jun-24 21-Jun-24 16.00 I Battery String Testing(1hrDischargeRate)(125V)21 0 Critical(flaot less than 10) Actual Work Critical Remaining... Page 9 of 10 Baseline Actual Level of Effort 0 Remaining Work ♦ ♦ Milestone Anticline Substation Classic Schedule Layout 01-Sep-23 15:20 Activity ID Activity Name Original Start Finish Total Float 2023 2024 2025 Duration F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D TSTS.CH.032 Battery String Testing(1 hr D ischarg e Rate)(48V)1 1.00 21-Jun-24 21-Jun-24 16.00 1 Battery String Testing(1 hr D ischarg e Rate)(48V)1 p TST.S.CH.033 Battery Charger 3 1.00 21-Jun-24 121,Jun-24 16.00 1 Battery Charger 8 r w 24,1un-24,ANC�-BL;3.TST.S.CH.04 Controls Circuits TST.S.CH.041 Point to Point wire verification(Per Panel)27 1.00 21-Jun-24 21,Jun-24 16.00 1; Point to Point wire verification(Per Panel)27 TST.S.CH.042 Point to Point wire verification(Per Cabinet)3 1.00 24-Jun-24 24,Jun-24 16.00 I Point'to Point wire verification(Per:Cabinet)3 TST.S.CH.043 DFR 1 1.00 24,Jun-24 24,Jun-24 16.00 I; DFR 1 TST.S.CH.044 Annuncaitor2 1.00 24,Jun-24 24,Jun-24 16.00 I An:nuncaitor2 -- r R 26,JUn-24,ANC:rBL 3.T:ST.S.CH.05 Miscellaneous Q TST.S.CH.051 HVAC 3 1.00 25,Jun-24 25,Jun-24 16.00 I HVAG 3 Q TST.S.CH.052 BuildingAlarms 1 1.00 26,Jun-Jun 26,Jun-24 16.00 I Buildih Alarms 1 . 9 . r. 27,1un-2 ,gNC-BL-3.TST.S.CH.g6 4owVolxaga Srrdicjn . _ . . TST.S.CH.061 DCLC 4 1.00 26,Jun-24 26,Jun-24 16.00 I DCLC 4 ....:..._:.. TST.S.CH.062 ACLC 2 1.00 27,Jun-24 27,Jun-24 16.00 11 ACLC 2 TST.S.CH.063 Fuse Disc 2 1.00 27,Jun-24 27-Jun-24 16.00 I FuseDisno 2 r •. rr28-Jun-24 28-Jun-24 16.00 ♦ 28-Jdn-24,ANC-BL'S.TSTS.CH.07 Post Energlzatlon IR Sca O TST.S.CH.071 IR Scan 1.00 28,Jun-24 28,Jun-24 16.00 1. A Scan TST.S.CH.072 Substation 1 1.00 28-Jun-24 28 Jun-24 16.00 Substation 1 TST.S.CH.073 Fuse Disco 2 1.00 28-Jun-24 28 Jun-24 16.00 I FuseDisco 2 - T► 2 ,Jul-24 ANC-BL .TST. .SF 525kV Yard Equlpmnt Te r ♦ 02,JW1-24,ANC=BL:3.TST.S.SF.01 Y2rd EgUipnient 1 TST.S.SF.011 Air Switch Testing 1.00 01,Ju1-24 01,Ju1-24 16.00 Air Switch Tostirng TST.S.SF.012 Surge Arrestors 2 1.00 02,Jul-24 02,Jul-24 16.00 I Surg.bArrestors2 . . . I 0 V 05-Jul-24,ANC-BLr3.TST,'S.SF.02 Circuit Breakers O TST.S.SF.021 SF6 CB(345kV)5 1.00 03,Jul-24 03,Jul-24 16.00 SF6 CB(345kV)5 TST.S.SF.022 SF6 Gas Charging CB 345kV 5 1.00 04,1u1-24 04,Ju1-24 16.00 I SF6 Gas Cha in CB 345kV 5 rsg ( ) gig: ( ) TST.S.SF.023 Vacuum Per CB(345kV)5 1.00 05,Jul-Jul 05,Jul-24 16.00 ;I Vacuum Per CB(345KV)5 r . 00 w 11,1ul-24,ANC-BL-3.TSTS.SF.03 Instrument Trarisformers TST.S.SF.031 CCVT 1 1.00 08,Ju1-24 08,Ju1-24 16.00 I CCVT 1 TST.S.SF.032 CT CB's 12 1.00 09,Jul-24 09,Jul-24 16.00 1 CT CB.'s 12 TST.S.SF.033 Current Circuit Secondaries 12 1.00 10,Jul-24 10,Jul-24 16.00 1 Current Circuit:Sebondaries 12 TST.S.SF.034 Voltage Circuit Secondaries 1 1.00 11,Jul-24 11,Jul-24 16.00 1 Volt a Circui Secondaries 1 a t 9 r- .. •-. rr . rf ♦ 12-Jul-24,ANC-BL-3.7StS.BF.©4 Capacitors✓Reactors; O TST.S.SF041 Capacitor Bank 1 1.00 12,Jul-24 12,Jul-24 16.00 1 :Capacitor Bank 1 p TST.S.SF.043 D Core Reactor 1.00 12-Jul-24 12,Jul-24 16.00 I D :Core keactor3 Dry rY r rr Orr ;♦:15;lul-24,ANC-BL-3.TSTS.SF.05 Grounding TST.S.SF.051 Ground Grid Injection 1 1.00 15-Jul-24 15,Ju1-24 16.00 ; 1 Ground Grid Injection;1 r. rr . Orr ♦ 17:Ju1 24,ANC-13L-TS7S.SF.06 Con:trofs Circuits O TST.S.SF.061 Functional Testing(Per Breaker]2 1.00 16,Jul-24 16-Jul-24 16.00 I Functional Testing(Per Breaker)2 TST.S.SF.062 Point to Point wire verification(Per Breaker 2 1.00 17,Jul-24 17,Jul-24 16.00 1 :Point to Point wire verification Per Breaker: 2 (. r •. rt R 23,Jul-24 ANC-BL-3.TST.S.SF.07 Circuit Breakers Post B Q TST.S.SF.071 SF6 Gas Charging(525kV)2 1.00 18,Jul-24 18,Jul-24 16.00 1 ::SF6 Gas Charging(525KV)2 Q TST.S.SF.072 Vacuum Per CB(525kV)2 3.00 19,1u1-24 23,Ju1-24 16.00 1 Vacuum Per CB(525kV)2 0 • . 00 i�I09-Oct-24,ANC-BL-3iTST.S.SP:Punchlist .. . 0• • . 0� . p9 pct-. ANC BLS TS7S.SP.0 addr?essin Pu 9 TSt.S.SP.C.01 Punchlist correction 1 20.00 14-Aug-24 11Sep-Sep 16.00 Punchlist dorrdction 1 TSt.S.SP.C.11 Punchlist correction 2 20.00 12Sep-24 09 Oct-24 16.00 ; ; Punchlist correction 2 0 Critical(flaot less than 10) Actual Work Critical Remaining... Page 10 of 10 Baseline Actual Level of Effort 0 Remaining Work ♦ ♦ Milestone