Loading...
HomeMy WebLinkAbout20240814Formal Complaint.pdf CASE No.: IPC-E-24-34 110 Larkspur Rd. h;ECEIVED Hailey, ID 83333 August 11,2024 LQf4CI� PM 05 liter' r i:) U' LIC Idaho Public Utilities Commission 11331 W.Chinden Blvd., Bldg. 8,suite 201-A Boise,ID 83714 Dear Commissioners: The 180 sq.ft.addition to our one car garage was almost complete, permits from the building department,fire department and sanitary district were approved. It was time to move wires 35 inches from the old meter box to the new one which would take 15 minutes according to the electrician. Idaho Power came and said a new power line was required from the street to the house, 160 feet. I was in Iowa on our farm for planting and was not available to look into this demand. The contractor could not delay so the power line was put in at a cost of$5,000 plus other costs for a total of over$10,000; power line damage is still being replaced. Had we known in advance of this unnecessary demand and cost we would not have started the addition. We later found from the efforts of Utilities Commission representative Mr.Thaden that Idaho Power claimed that the existing power line was too short and that a prohibited splice was needed and that the wires were in concrete. Both claims were FALSE. The new meter was 35 inches closer to the distribution box thus no splice was needed and the wires were in conduit the same as the new wires; the original conduit is still in place. Idaho Power told Mr.Thaden that Rule H was the reason for the demand. Neither the architect or contractor, both very experienced people,were aware of this requirement until the project was almost complete. The trenching for the required conduit destroyed part of a sprinkler system and an 8 X 100 maintained area of old sage that is irreplaceable. A new sprinkler area is required for the sod that will replace the sage.All the above is a great abuse of bureaucratic power for a nonsensical demand and is a reason for unaffordable housing. It is impossible to budget for a project when an outside influence can interrupt at the last minute. Mr.Thaden has done a fine job with this situation but is up against a bureaucratic powerhouse,thus this FORMAL COMPLAINT is necessary. The outcome should be financial compensation from Idaho Power for the for the unneeded work and cost due to Idaho Power. Sincerely, Jim Naumann /1"w/L Idaho Public Utilities Commission Brad Little,Governor P.O. Box 83720, Boise, ID 83720-0074 Eric Anderson,President �.� John R.Hammond,Jr.,Commissioner Edward Lodge,Commissioner August 6, 2024 Mr.Jim Naumann 110 Larkspur Road Hailey, ID 83333 RE: Relocation of Meter Dear Mr. Naumann, Thank you for your most recent correspondence regarding your ongoing objection to Idaho Power's position with the relocation of your garage meter. The Company believes it is following Rule H of its Tariff. I was unable to resolve your issue informally, therefore there will be no further action taken on my part to help resolve it. When an individual is dissatisfied with the outcome of their informal complaint,they may file a formal complaint for review by the Commission under its Rules of Procedure, IDAPA 31.01.01.000 et seq" - Rule 054. Formal Complaints—Defined—Contents and Process, available online at: https://adminrules.idaho.goy/rules/current/31/310101.pdf A formal complaint can be filed when the outcome of an informal complaint is not satisfactory. The formal complaint must be in writing, state the facts and specify how you would like the problem to be resolved. Unlike an informal complaint, which is handled by the Commission's staff, the Commissioners must consider a formal complaint. The Commissioners will decide whether it is appropriate to accept the formal complaint. If it is accepted, a formal legal proceeding will be started. If the Commission does not accept the formal complaint, then nothing further will be done by the Commission. In summary, your formal complaint should state: • The name of the utility or person the complaint is against. • A full statement of the facts constituting the acts or omissions of the utility or person against whom the complaint is filed, and the dates when the acts or omissions occurred. • The specific provision of statute, rule, order, notice, tariff or other controlling law that the utility or person has violated. • What action or outcome should be taken to resolve the complaint. The address to send the formal complaint to the Commission is: 11331 W.Chinden Blvd.,Building 8 Suite 201-A,Boise ID 83714 Telephone:(208)334-0300 Facsimile:(208)334-3762 Mr. Naumann Page 2 8-6-24 Idaho Public Utilities Commission PO Box 83720 Boise, ID 83720-0074 In lieu of mailing the complaint,the complaint may be electronically submitted to the Commission Secretary by emailing it to secretary@puc.idaho.gov Please know that a formal complaint becomes part of the Commission's public records for anyone to view. If you have any questions, please let me know. My contact information is listed below. Sincerely, Curtis Thaden Utilities Compliance Investigator I Idaho PUC curtis.thaden@puc.idaho.gov 800-432-0369 or 208-334-0322 (direct) Fax: 208-334-3762 IIdaho Public Utilities Commission Brad Uttle,Governor P.0.Box 83720,Boise,ID 83720-0074 Eric Anderson,President John R.Hammond,Jr.,Commissioner Edward Lodge,Cammissioner June 6, 2024 Mr_Jim Naumann 110 Larkspur Road Hailey, ID 83333 RE: Idaho Power. Dear Mf. Naumann, Thank you for contacting the Idaho Public Utilities Commission(IPUC) regarding your issue with Idaho Power. Upon receipt of your letter dated June 15, 2024, 1 contacted Idaho Power informing the Company of your objection to what transpired in relocating your garage meter. Idaho Power informed me that the new meter base had to be relocated from the inside of your new garage addition to the outside due to the Company's construction standards. Because the concrete pad and footings were poured over a direct buried line, Idaho Power claimed it made it impossible to pull the' -wire to reach the new meter base location without splicing the line, which-could'compromise the integrity of the wire. This is why a new line was required. Additionally, Idaho Power said any upgrades, or alternations to direct buried lines must be placed in conduit. The Company s standard process is to have all wire in conduit for enhanced reliability and safety. Regarding the cost. I asked Idaho Power why anew line from the transformer to the new meter base would cost approximately$5,000. Idaho Power confirmed you provided the trench and installed 3-inch conduit and that the cost to install 166 feet of new service was$838.74. 1 assume a misunderstanding may have occurred regarding the cost of$5,000. If you have any questions, please let me know. My contact information is listed below. Sincerely, i. Curtis Thaden Utilities Compliance investigator I Idaho-PUC curtis.thaden(@puc.idaho.gov! 800-432-0369 ar208-334-0322 (direct) Fax: 208-334-3762 11331 W.Chinden Blvd.,Building 8 suite 201-A,Boise ID 83714 Telephone:(208)334-0300 Facsimile:(208)334-3762 NAD11ApNN B©ISE ID RPDC 837 110 Larkspur Rd. 13 AUG 2024 PM 1 L Halley, ID 83333 �( 3 W, ' �}77� ' Zol�- ii1lli0011"iiil�iiiil11iil'lHll"i11,�11�;,i :� 1