HomeMy WebLinkAbout20240806IPC to Staff Response No. 31(d) - Attachment 3 - Status Reports - Construction Inspection.pdfOxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1 of 1851
Form detail
Form detail report
Created on Aug 1, 2024, 6:46 AM MDT
Created by Zack Schaumburg (Idaho Power Company)
Total items 339
Sorted by Form date (Descending)
Filtered by Status (In progress|In review|Closed)
Response to Staff Request No. 31d - Attachment 3
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 2 of 1851
Contents
#385: Daily Report - Anderson ............................................................................................................................................9
#384: Daily Report -Standard ............................................................................................................................................15
#383: Daily Report -Standard ............................................................................................................................................20
#382: Daily Report - Anderson ..........................................................................................................................................26
#381: Daily Report - Anderson ..........................................................................................................................................32
#379: Daily Report -Standard ............................................................................................................................................37
#380: Daily Report - Anderson ..........................................................................................................................................40
#378: Daily Report -Standard ............................................................................................................................................45
#377: Daily Report -Standard ............................................................................................................................................51
#376: Daily Report -Standard ............................................................................................................................................56
#375: Daily Report -Standard ............................................................................................................................................60
#374: Daily Report -Standard ............................................................................................................................................66
#373: Daily Report -Standard ............................................................................................................................................71
#372: Daily Report -Standard ............................................................................................................................................77
#371: Daily Report -Standard ............................................................................................................................................82
#370: Daily Report - Anderson ..........................................................................................................................................85
#369: Daily Report - Anderson ..........................................................................................................................................90
#368: Daily Report -Standard ............................................................................................................................................96
#367: Daily Report -Standard ..........................................................................................................................................102
#366: Daily Report -Standard ..........................................................................................................................................107
#365: Daily Report -Standard ..........................................................................................................................................111
#364: Daily Report -Standard ..........................................................................................................................................116
#362: Daily Report - Anderson ........................................................................................................................................120
#360: Daily Report -Standard ..........................................................................................................................................127
#359: Daily Report - Anderson ........................................................................................................................................131
#358: Daily Report - Anderson ........................................................................................................................................138
#357: Daily Report -Standard ..........................................................................................................................................144
#356: Daily Report -Standard ..........................................................................................................................................150
#355: Daily Report -Standard ..........................................................................................................................................155
#354: Daily Report -Standard ..........................................................................................................................................159
#353: Daily Report -Standard ..........................................................................................................................................162
#352: Daily Report -Standard ..........................................................................................................................................167
#351: Daily Report -Standard ..........................................................................................................................................171
#350: Daily Report -Standard ..........................................................................................................................................177
#349: Daily Report - Anderson ........................................................................................................................................182
#348: Daily Report - Anderson ........................................................................................................................................188
#347: Daily Report -Standard ..........................................................................................................................................193
#346: Daily Report -Standard ..........................................................................................................................................198
#345: Daily Report -Standard ..........................................................................................................................................203
#344: Daily Report -Standard ..........................................................................................................................................208
#343: Daily Report -Standard ..........................................................................................................................................213
#342: Daily Report -Standard ..........................................................................................................................................218
#341: Daily Report - Anderson ........................................................................................................................................223
#340: Daily Report - Anderson ........................................................................................................................................229
#338: Daily Report -Standard ..........................................................................................................................................236
#339: Daily Report - Anderson ........................................................................................................................................241
#337: Daily Report -Standard ..........................................................................................................................................244
#336: Daily Report -Standard ..........................................................................................................................................249
#335: Daily Report -Standard ..........................................................................................................................................253
FORMS 328 - 385 WERE COMPLETED BY IDAHO POWER
COMPANY FIELD ENGINEER AND CONSTRUCTION
INSPECTOR. THEY HAVE BEEN REMOVED FROM THE
REPORT.
ZACK SCHAUMBURG
IDAHO POWER COMPANY
2024.08.01
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 3 of 1851
#334: Daily Report -Standard ..........................................................................................................................................256
#333: Daily Report -Standard ..........................................................................................................................................259
#330: Daily Report -Standard ..........................................................................................................................................261
#329: Daily Report -Standard ..........................................................................................................................................263
#327: Daily Report -Standard ..........................................................................................................................................268
#326: Daily Report -Standard ..........................................................................................................................................273
#325: Daily Report -Standard ..........................................................................................................................................281
#324: Daily Report -Standard ..........................................................................................................................................286
#323: Daily Report -Standard ..........................................................................................................................................292
#322: Daily Report -Standard ..........................................................................................................................................297
#320: Daily Report -Standard ..........................................................................................................................................303
#321: Daily Report -Standard ..........................................................................................................................................309
#319: Daily Report -Standard ..........................................................................................................................................314
#318: Daily Report -Standard ..........................................................................................................................................321
#317: Daily Report -Standard ..........................................................................................................................................328
#316: Daily Report -Standard ..........................................................................................................................................334
#315: Daily Report -Standard ..........................................................................................................................................338
#314: Daily Report -Standard ..........................................................................................................................................344
#313: Daily Report -Standard ..........................................................................................................................................354
#312: Daily Report -Standard ..........................................................................................................................................357
#311: Daily Report -Standard ..........................................................................................................................................364
#310: Daily Report -Standard ..........................................................................................................................................374
#308: Daily Report -Standard ..........................................................................................................................................377
#307: Daily Report -Standard ..........................................................................................................................................383
#306: Daily Report -Standard ..........................................................................................................................................389
#305: Daily Report -Standard ..........................................................................................................................................397
#304: Daily Report -Standard ..........................................................................................................................................404
#303: Daily Report -Standard ..........................................................................................................................................408
#302: Daily Report -Standard ..........................................................................................................................................414
#300: Daily Report -Standard ..........................................................................................................................................421
#299: Daily Report -Standard ..........................................................................................................................................426
#297: Daily Report -Standard ..........................................................................................................................................433
#296: Daily Report -Standard ..........................................................................................................................................439
#294: Daily Report -Standard ..........................................................................................................................................450
#293: Daily Report -Standard ..........................................................................................................................................455
#292: Daily Report -Standard ..........................................................................................................................................463
#291: Daily Report -Standard ..........................................................................................................................................470
#290: Daily Report -Standard ..........................................................................................................................................475
#289: Daily Report -Standard ..........................................................................................................................................480
#288: Daily Report -Standard ..........................................................................................................................................484
#287: Daily Report -Standard ..........................................................................................................................................489
#286: Daily Report -Standard ..........................................................................................................................................493
#285: Daily Report -Standard ..........................................................................................................................................499
#284: Daily Report -Standard ..........................................................................................................................................504
#283: Daily Report -Standard ..........................................................................................................................................509
#282: Daily Report -Standard ..........................................................................................................................................515
#281: Daily Report -Standard ..........................................................................................................................................521
#280: Daily Report -Standard ..........................................................................................................................................531
#279: Daily Report -Standard ..........................................................................................................................................543
#278: Daily Report -Standard ..........................................................................................................................................546
#277: Daily Report -Standard ..........................................................................................................................................552
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 4 of 1851
#276: Daily Report -Standard ..........................................................................................................................................560
#275: Daily Report -Standard ..........................................................................................................................................566
#274: Daily Report -Standard ..........................................................................................................................................573
#273: Daily Report -Standard ..........................................................................................................................................584
#272: Daily Report -Standard ..........................................................................................................................................593
#271: Daily Report -Standard ..........................................................................................................................................604
#270: Daily Report -Standard ..........................................................................................................................................614
#269: Daily Report -Standard ..........................................................................................................................................625
#268: Daily Report -Standard ..........................................................................................................................................636
#267: Daily Report -Standard ..........................................................................................................................................644
#266: Daily Report -Standard ..........................................................................................................................................646
#265: Daily Report -Standard ..........................................................................................................................................654
#264: Daily Report -Standard ..........................................................................................................................................660
#263: Daily Report -Standard ..........................................................................................................................................666
#262: Daily Report -Standard ..........................................................................................................................................672
#261: Daily Report -Standard ..........................................................................................................................................679
#259: Daily Report -Standard ..........................................................................................................................................684
#260: Daily Report -Standard ..........................................................................................................................................688
#258: Daily Report -Standard ..........................................................................................................................................693
#257: Daily Report -Standard ..........................................................................................................................................696
#256: Daily Report -Standard ..........................................................................................................................................701
#255: Daily Report -Standard ..........................................................................................................................................709
#254: Daily Report -Standard ..........................................................................................................................................714
#253: Daily Report -Standard ..........................................................................................................................................719
#252: Daily Report -Standard ..........................................................................................................................................729
#251: Daily Report -Standard ..........................................................................................................................................735
#250: Daily Report -Standard ..........................................................................................................................................742
#249: Daily Report -Standard ..........................................................................................................................................748
#248: Daily Report -Standard ..........................................................................................................................................754
#247: Daily Report -Standard ..........................................................................................................................................759
#245: Daily Report -Standard ..........................................................................................................................................763
#244: Daily Report -Standard ..........................................................................................................................................767
#243: Daily Report -Standard ..........................................................................................................................................773
#242: Daily Report -Standard ..........................................................................................................................................777
#241: Daily Report -Standard ..........................................................................................................................................784
#240: Daily Report -Standard ..........................................................................................................................................788
#239: Daily Report -Standard ..........................................................................................................................................798
#238: Daily Report -Standard ..........................................................................................................................................807
#237: Daily Report -Standard ..........................................................................................................................................813
#236: Daily Report -Standard ..........................................................................................................................................819
#235: Daily Report -Standard ..........................................................................................................................................824
#234: Daily Report -Standard ..........................................................................................................................................837
#233: Daily Report -Standard ..........................................................................................................................................847
#232: Daily Report -Standard ..........................................................................................................................................854
#231: Daily Report -Standard ..........................................................................................................................................856
#229: Daily Report -Standard ..........................................................................................................................................866
#230: Daily Report -Standard ..........................................................................................................................................868
#228: Daily Report -Standard ..........................................................................................................................................877
#227: Daily Report -Standard ..........................................................................................................................................881
#226: Daily Report -Standard ..........................................................................................................................................885
#225: Daily Report -Standard ..........................................................................................................................................893
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 5 of 1851
#224: Daily Report -Standard ..........................................................................................................................................898
#223: Daily Report -Standard ..........................................................................................................................................908
#222: Daily Report -Standard ..........................................................................................................................................913
#221: Daily Report -Standard ..........................................................................................................................................920
#220: Daily Report -Standard ..........................................................................................................................................927
#219: Daily Report -Standard ..........................................................................................................................................932
#218: Daily Report -Standard ..........................................................................................................................................935
#217: Daily Report -Standard ..........................................................................................................................................944
#216: Daily Report -Standard ..........................................................................................................................................950
#215: Daily Report -Standard ..........................................................................................................................................960
#214: Daily Report -Standard ..........................................................................................................................................966
#213: Daily Report -Standard ..........................................................................................................................................969
#212: Daily Report -Standard ..........................................................................................................................................979
#211: Daily Report -Standard ..........................................................................................................................................987
#210: Daily Report -Standard .......................................................................................................................................1001
#209: Daily Report -Standard .......................................................................................................................................1004
#207: Daily Report -Standard .......................................................................................................................................1007
#206: Daily Report -Standard .......................................................................................................................................1012
#205: Daily Report -Standard .......................................................................................................................................1018
#204: Daily Report -Standard .......................................................................................................................................1023
#203: Daily Report -Standard .......................................................................................................................................1031
#202: Daily Report -Standard .......................................................................................................................................1033
#201: Daily Report -Standard .......................................................................................................................................1040
#200: Daily Report -Standard .......................................................................................................................................1051
#199: Daily Report -Standard .......................................................................................................................................1067
#198: Daily Report -Standard .......................................................................................................................................1070
#197: Daily Report -Standard .......................................................................................................................................1075
#196: Daily Report -Standard .......................................................................................................................................1081
#195: Daily Report -Standard .......................................................................................................................................1089
#194: Daily Report -Standard .......................................................................................................................................1101
#193: Daily Report -Standard .......................................................................................................................................1113
#192: Daily Report -Standard .......................................................................................................................................1115
#190: Daily Report -Standard .......................................................................................................................................1123
#191: Daily Report -Standard .......................................................................................................................................1127
#189: Daily Report -Standard .......................................................................................................................................1134
#188: Daily Report -Standard .......................................................................................................................................1136
#187: Daily Report -Standard .......................................................................................................................................1140
#185: Daily Report -Standard .......................................................................................................................................1146
#186: Daily Report -Standard .......................................................................................................................................1152
#184: Daily Report -Standard .......................................................................................................................................1159
#183: Daily Report -Standard .......................................................................................................................................1165
#182: Daily Report -Standard .......................................................................................................................................1172
#181: Daily Report -Standard .......................................................................................................................................1177
#180: Daily Report -Standard .......................................................................................................................................1182
#179: Daily Report -Standard .......................................................................................................................................1189
#178: Daily Report -Standard .......................................................................................................................................1193
#177: Daily Report -Standard .......................................................................................................................................1200
#176: Daily Report -Standard .......................................................................................................................................1202
#174: Daily Report -Standard .......................................................................................................................................1209
#175: Daily Report -Standard .......................................................................................................................................1215
#173: Daily Report -Standard .......................................................................................................................................1221
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 6 of 1851
#172: Daily Report -Standard .......................................................................................................................................1224
#171: Daily Report -Standard .......................................................................................................................................1232
#170: Daily Report -Standard .......................................................................................................................................1239
#169: Daily Report -Standard .......................................................................................................................................1244
#168: Daily Report -Standard .......................................................................................................................................1250
#167: Daily Report -Standard .......................................................................................................................................1258
#166: Daily Report -Standard .......................................................................................................................................1263
#165: Daily Report -Standard .......................................................................................................................................1274
#164: Daily Report -Standard .......................................................................................................................................1280
#163: Daily Report -Standard .......................................................................................................................................1286
#162: Daily Report -Standard .......................................................................................................................................1291
#161: Daily Report -Standard .......................................................................................................................................1296
#159: Daily Report -Standard .......................................................................................................................................1302
#158: Daily Report -Standard .......................................................................................................................................1308
#157: Daily Report -Standard .......................................................................................................................................1316
#156: Daily Report -Standard .......................................................................................................................................1321
#155: Daily Report -Standard .......................................................................................................................................1323
#154: Daily Report -Standard .......................................................................................................................................1334
#153: Daily Report -Standard .......................................................................................................................................1341
#152: Daily Report -Standard .......................................................................................................................................1351
#151: Daily Report -Standard .......................................................................................................................................1357
#150: Daily Report -Standard .......................................................................................................................................1367
#149: Daily Report -Standard .......................................................................................................................................1376
#148: Daily Report -Standard .......................................................................................................................................1390
#147: Daily Report -Standard .......................................................................................................................................1397
#146: Daily Report -Standard .......................................................................................................................................1403
#145: Daily Report -Standard .......................................................................................................................................1409
#144: Daily Report -Standard .......................................................................................................................................1413
#143: Daily Report -Standard .......................................................................................................................................1417
#142: Daily Report -Standard .......................................................................................................................................1423
#141: Daily Report -Standard .......................................................................................................................................1428
#140: Daily Report -Standard .......................................................................................................................................1434
#139: Daily Report -Standard .......................................................................................................................................1440
#138: Daily Report -Standard .......................................................................................................................................1445
#137: Daily Report -Standard .......................................................................................................................................1452
#135: Daily Report -Standard .......................................................................................................................................1456
#134: Daily Report -Standard .......................................................................................................................................1460
#133: Daily Report -Standard .......................................................................................................................................1467
#132: Daily Report -Standard .......................................................................................................................................1472
#131: Daily Report -Standard .......................................................................................................................................1478
#130: Daily Report -Standard .......................................................................................................................................1481
#129: Daily Report -Standard .......................................................................................................................................1489
#128: Daily Report -Standard .......................................................................................................................................1494
#127: Daily Report -Standard .......................................................................................................................................1502
#126: Daily Report -Standard .......................................................................................................................................1506
#125: Daily Report -Standard .......................................................................................................................................1512
#124: Daily Report -Standard .......................................................................................................................................1517
#123: Daily Report -Standard .......................................................................................................................................1522
#122: Daily Report -Standard .......................................................................................................................................1529
#121: Daily Report -Standard .......................................................................................................................................1534
#120: Daily Report -Standard .......................................................................................................................................1539
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 7 of 1851
#119: Daily Report -Standard .......................................................................................................................................1543
#118: Daily Report -Standard .......................................................................................................................................1547
#117: Daily Report -Standard .......................................................................................................................................1550
#114: Daily Report -Standard .......................................................................................................................................1555
#113: Daily Report -Standard .......................................................................................................................................1561
#111: Daily Report -Standard .......................................................................................................................................1564
#109: Daily Report -Standard .......................................................................................................................................1566
#108: Daily Report -Standard .......................................................................................................................................1568
#107: Daily Report -Standard .......................................................................................................................................1572
#106: Daily Report -Standard .......................................................................................................................................1576
#105: Daily Report -Standard .......................................................................................................................................1578
#104: Daily Report -Standard .......................................................................................................................................1581
#103: Daily Report -Standard .......................................................................................................................................1586
#102: Daily Report -Standard .......................................................................................................................................1592
#101: Daily Report -Standard .......................................................................................................................................1595
#100: Daily Report -Standard .......................................................................................................................................1598
#99: Daily Report -Standard ..........................................................................................................................................1601
#98: Daily Report -Standard ..........................................................................................................................................1606
#96: Daily Report -Standard ..........................................................................................................................................1611
#95: Daily Report -Standard ..........................................................................................................................................1613
#94: Daily Report -Standard ..........................................................................................................................................1617
#92: Daily Report -Standard ..........................................................................................................................................1622
#91: Daily Report -Standard ..........................................................................................................................................1626
#90: Daily Report -Standard ..........................................................................................................................................1634
#89: Daily Report -Standard ..........................................................................................................................................1638
#88: Daily Report -Standard ..........................................................................................................................................1642
#87: Daily Report -Standard ..........................................................................................................................................1647
#86: Daily Report -Standard ..........................................................................................................................................1652
#85: Daily Report -Standard ..........................................................................................................................................1656
#84: Daily Report -Standard ..........................................................................................................................................1660
#83: Daily Report -Standard ..........................................................................................................................................1664
#82: Daily Report -Standard ..........................................................................................................................................1668
#81: Daily Report -Standard ..........................................................................................................................................1673
#80: Daily Report -Standard ..........................................................................................................................................1677
#79: Daily Report -Standard ..........................................................................................................................................1680
#78: Daily Report -Standard ..........................................................................................................................................1683
#77: Daily Report -Standard ..........................................................................................................................................1686
#76: Daily Report -Standard ..........................................................................................................................................1689
#75: Daily Report -Standard ..........................................................................................................................................1692
#73: Daily Report -Standard ..........................................................................................................................................1695
#72: Daily Report -Standard ..........................................................................................................................................1699
#71: Daily Report -Standard ..........................................................................................................................................1703
#70: Daily Report -Standard ..........................................................................................................................................1707
#69: Daily Report -Standard ..........................................................................................................................................1710
#67: Daily Report -Standard ..........................................................................................................................................1714
#68: Daily Report -Standard ..........................................................................................................................................1718
#66: Daily Report -Standard ..........................................................................................................................................1722
#65: Daily Report -Standard ..........................................................................................................................................1726
#64: Daily Report -Standard ..........................................................................................................................................1730
#63: Daily Report -Standard ..........................................................................................................................................1733
#62: Daily Report -Standard ..........................................................................................................................................1735
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 8 of 1851
#59: Daily Report -Standard ..........................................................................................................................................1738
#58: Daily Report -Standard ..........................................................................................................................................1742
#57: Daily Report -Standard ..........................................................................................................................................1746
#55: Daily Report -Standard ..........................................................................................................................................1750
#53: Daily Report -Standard ..........................................................................................................................................1755
#54: Daily Report -Standard ..........................................................................................................................................1760
#52: Daily Report -Standard ..........................................................................................................................................1764
#51: Daily Report -Standard ..........................................................................................................................................1768
#50: Daily Report -Standard ..........................................................................................................................................1772
#49: Daily Report -Standard ..........................................................................................................................................1776
#48: Daily Report -Standard ..........................................................................................................................................1779
#47: Daily Report -Standard ..........................................................................................................................................1782
#46: Daily Report -Standard ..........................................................................................................................................1786
#45: Daily Report -Standard ..........................................................................................................................................1791
#44: Daily Report -Standard ..........................................................................................................................................1796
#42: Daily Report -Standard ..........................................................................................................................................1799
#41: Daily Report -Standard ..........................................................................................................................................1802
#39: Daily Report -Standard ..........................................................................................................................................1805
#37: Daily Report -Standard ..........................................................................................................................................1808
#40: Daily Report -Standard ..........................................................................................................................................1812
#36: Daily Report -Standard ..........................................................................................................................................1814
#34: Daily Report -Standard ..........................................................................................................................................1817
#33: Daily Report -Standard ..........................................................................................................................................1821
#32: Daily Report -Standard ..........................................................................................................................................1825
#31: Daily Report -Standard ..........................................................................................................................................1827
#30: Daily Report -Standard ..........................................................................................................................................1830
#28: Daily Report -Standard ..........................................................................................................................................1833
#29: Daily Report -Standard ..........................................................................................................................................1836
#27: Daily Report -Standard ..........................................................................................................................................1838
#24: Daily Report -Standard ..........................................................................................................................................1840
#21: Daily Report -Standard ..........................................................................................................................................1842
#26: Daily Report -Standard ..........................................................................................................................................1844
#25: Daily Report -Standard ..........................................................................................................................................1846
#22: Daily Report -Standard ..........................................................................................................................................1848
#23: Daily Report -Standard ..........................................................................................................................................1850
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 268 of 1851
Form detail
#327: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, Strip Forms, set forms
Area 40, Form Walls, Bulkheads
Area 50, Set Structural Beams
IMCO, General Crew 1 10 Area 10, Install site piping
Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 60, Electrical Room, pull wire
Forms
Location
Form date Apr 4, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 4, 2024, 12:01 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 269 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, place 2nd half the 3rd lift
grout, set block
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Site piping
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Site grading
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Area 50, Set Beams
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Grout
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 270 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is getting ready to place the structural beams for the second floor of Area 50. Basin is onsite and
starting to set block on the single story side of Area 50.
9:00 am IMCO tried setting a beam but the bolts were slightly out of plumb. IMCO is working on reaming the
holes on the beams to slightly bigger so they will fit over the bolts.
10:00 am Vale is continuing to work in the electrical room along with the chiller room. They are installing
raceways and pulling wire.
12:00 pm IMCO has set beams for the second story of Area 50. Basin is working on setting block at the single
story side of Area 50. Left site to return cylinders, grout and unit prisms.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 271 of 1851
References
Photos (3)
20240404_071629
Taken on Apr 4, 2024, 7:16 AM MDT
Added on Apr 4, 2024, 11:27 AM MDT
Added by Chris Johnson
20240404_111051
Taken on Apr 4, 2024, 11:10 AM MDT
Added on Apr 4, 2024, 11:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 272 of 1851
20240404_084002
Taken on Apr 4, 2024, 8:40 AM MDT
Added on Apr 4, 2024, 11:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 273 of 1851
Form detail
#326: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
IMCO, General Crew 1 10 Area 10, Install site piping
Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Apr 3, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 4, 2024, 6:32 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 274 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, place half the 3rd lift
grout, set block
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Site piping
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Site grading
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Grout
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 275 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is starting to excavate for piping from the SS lift station along with storm lines in front of Area 60.
They are continuing to work on getting piping installed around the building so they can backfill and get up to
grade to begin the exterior slab placements.
9:00 am Attended weekly meeting.
10:00 am Basin is continuing to work on laying block. Ivan is waiting for his new line pump to arrive to grout what
is installed.
11:00 am Basin is working on installing the bolted embeds for the second story beams that support the pan
decking and second floor. They are cutting out the block and prepping for the plate installation. I spoke to Ivan
regarding the grout placement. He plans to grout half the bond beam today but is waiting for the pump to arrive.
They are getting a new pump delivered due to their current pump not working very well over the past two
placements.
1:00 pm IMCO is working on installing piping around Area 60. The grout pump has arrived on site. Basin plans to
grout in a few hours.
3:00 pm Basin has started placing grout. I took a sample for grout strength testing.
4:00 pm I met with Steve regarding the beam embeds in the CMU wall. They are checking them and adjusting
them as they are placing grout. Steve and I double checked the beams that are onsite to ensure the embeds are
getting placed in the correct locations.
5:00 pm Basin has completed the grout placement. They will place the rest of this bond beam tomorrow once the
block that was laid today sets up.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 276 of 1851
References
Photos (9)
20240403_150954
Taken on Apr 3, 2024, 3:09 PM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
20240403_115825
Taken on Apr 3, 2024, 11:58 AM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 277 of 1851
20240403_105511
Taken on Apr 3, 2024, 10:55 AM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
20240403_105047
Taken on Apr 3, 2024, 10:50 AM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 278 of 1851
20240403_105014
Taken on Apr 3, 2024, 10:50 AM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
20240403_104943
Taken on Apr 3, 2024, 10:49 AM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 279 of 1851
20240403_161815
Taken on Apr 3, 2024, 4:18 PM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
20240403_154432
Taken on Apr 3, 2024, 3:44 PM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 280 of 1851
20240403_131115
Taken on Apr 3, 2024, 1:11 PM MDT
Added on Apr 4, 2024, 6:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 281 of 1851
Form detail
#325: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, Place CIP Wall
Area 40, Form Walls, Bulkheads,
Place Concrete
IMCO, General Crew 1 10 Area 10, Batch concrete
Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Apr 2, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 3, 2024, 6:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 282 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, set block
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 40, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 283 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Pump truck is onsite and setting up. IMCO is starting to batch concrete.
9:00 am IMCO has batched concrete. Teddy Ertel, HMH Engineering, has taken the sample and tested. All passed
with no issues. IMCO is starting to place the retaining wall sections.
10:00 am Basin is continuing to install block at Area 50. They are still planning to place grout tomorrow.
12:00 pm IMCO is continuing to place concrete. They are placing wall sections at Area 40.
1:00 pm Vale is onsite continuing to pull wire and run raceways at Area 60.
3:00 pm IMCO is continuing to assemble the raceway crowders. Sawtooth is onsite helping.
4:30 pm IMCO is continuing to work on forming walls and bulkheads at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 284 of 1851
References
Photos (3)
20240402_124101
Taken on Apr 2, 2024, 12:41 PM MDT
Added on Apr 3, 2024, 6:47 AM MDT
Added by Chris Johnson
20240402_095701
Taken on Apr 2, 2024, 9:57 AM MDT
Added on Apr 3, 2024, 6:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 285 of 1851
20240402_142438
Taken on Apr 2, 2024, 2:24 PM MDT
Added on Apr 3, 2024, 6:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 286 of 1851
Form detail
#324: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
Area 60, Foundation Membrane
IMCO, General Crew 1 10 Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Apr 1, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 2, 2024, 7:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 287 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, place 2nd lift grout, set
block
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Grout
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 288 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:30 am IMCO is continuing to work on forming walls and bulkheads at Area 40. Steve informed me they are still
planning to have a concrete placement tomorrow. They are going to capture Area 40 walls along with Area 10 CIP
Retaining walls.
9:30 am I spoke to Ivan from Basin Masonry. He has reached the next grout placement and plans to pour grout
today.
12:00 pm Basin has batched a truck of grout for the next grout placement.
1:30 pm Basin had issues with their line pump. They are starting to place the grout in the block now. I have taken
my second grout sample for compressive strength testing. Vale is onsite working on pulling wire at Area 60.
3:30 pm Basin had to batch a small load of grout to finish the grout placement. They are finishing up the
placement now. Ivan casted 3 unit strength prims and filled them with grout. These are for the 8" block
requirement.
4:30 pm Basin has resumed setting block. They are working towards the next bond beam that is at second floor
level. IMCO has installed the waterproof membrane and drain fabric at the river side of Area 60. They plan to
backfill this tomorrow after it cures.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 289 of 1851
References
Photos (5)
20240401_144943
Taken on Apr 1, 2024, 2:49 PM MDT
Added on Apr 2, 2024, 7:10 AM MDT
Added by Chris Johnson
20240401_120622
Taken on Apr 1, 2024, 12:06 PM MDT
Added on Apr 2, 2024, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 290 of 1851
20240401_094120
Taken on Apr 1, 2024, 9:41 AM MDT
Added on Apr 2, 2024, 7:09 AM MDT
Added by Chris Johnson
20240401_092848
Taken on Apr 1, 2024, 9:28 AM MDT
Added on Apr 2, 2024, 7:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 291 of 1851
20240401_144947
Taken on Apr 1, 2024, 2:49 PM MDT
Added on Apr 2, 2024, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 292 of 1851
Form detail
#323: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads,
Place 2 Walls
IMCO, General Crew 1 10 Area 10, Excavate and compact for
mesa wall 3
Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Mar 28, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 29, 2024, 8:11 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 293 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, Setup for the 2nd lift
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Mesa Wall
Deere 644J Loader 1 5 Area 40, Batch Concrete
Hitachi 85 Excavator 1 5 Area 10, Mesa Wall 2 excavation
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 40, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 294 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is planning to place concrete today at Area 40. They are continuing to work on setting wall forms
and bulkheads.
9:00 am IMCO has batched the first truck. They will only be able to capture 2 wall sections today due to the
muddy conditions onsite. The pump truck does not want to take the risk of getting stuck in the mud to move to the
other side of Area 40 to reach the other wall sections. I tested the first truck, it passed with no issues.
11:00 am IMCO has completed the concrete placement for the day. Basin is onsite. I spoke to Ivan regarding his
schedule. He plans to setup scaffolding and layout block today. He wants to finish the grout placement that was
not completed yesterday due to line pump plugging up. He plans to continue setting block tomorrow with the next
grout placement on Monday.
2:00 pm IMCO is working on the foundation drain and backfilling along Area 60. Basin Masonry is mixing a small
batch of grout to finish the placement from yesterday. They are batching it with their mortar mixer and dumping it
in the wall with buckets.
4:00 pm IMCO is continuing to work on forming walls at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 295 of 1851
References
Photos (4)
20240328_145232
Taken on Mar 28, 2024, 2:52 PM MDT
Added on Mar 29, 2024, 8:10 AM MDT
Added by Chris Johnson
20240328_142709
Taken on Mar 28, 2024, 2:27 PM MDT
Added on Mar 29, 2024, 8:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 296 of 1851
20240328_074551
Taken on Mar 28, 2024, 7:45 AM MDT
Added on Mar 29, 2024, 8:10 AM MDT
Added by Chris Johnson
20240328_074549
Taken on Mar 28, 2024, 7:45 AM MDT
Added on Mar 29, 2024, 8:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 297 of 1851
Form detail
#322: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Wall Forming
Area 40, Form Walls, Bulkheads
IMCO, General Crew 1 10 Area 10, Excavate and compact for
mesa wall 3
Area 40, Crowder Rails, Crowder
Frame install
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Mar 27, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 28, 2024, 6:33 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 298 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonry 10 10 Area 50, Reinforced Masonry, First
Grout placement - Did not
complete entire placement
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Mesa Wall
Deere 644J Loader 1 10
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Grout Mixing
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 299 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work dig out in front of Area 60 to exposed the foundation wall. They are doing
this so they can install the waterproof membrane to the wall then the drainage fabric. They are taking care for this
work to avoid the alarm line Vale installed after the foundation was poured. Basin Masonry is starting to arrive to
begin work. They are getting ready to continue installing block walls. I asked Ivan if he planned to pour grout
today. He informed me they will see how today goes.
9:00 am Attended weekly meeting.
11:00 am Basin Masonry is continuing to work on installing the block. They have most of the first lift installed.
They are starting to batch grout using the batch plant and super sack bags of grout. It is starting to rain.
12:30 pm Basin has the first truck batched and starting to pump grout into the first lift. I have taken a sample and
casted 4 grout prisms. Basin has laid and grouted 3 unit strength prisms for strength testing. It is continuing to
rain. I had a discussion with Jeremey regarding the limits of rain and masonry work. He was unsure what the
allowable rain was for masonry work.
1:00 pm Basin has ran out of grout and needed to batch more. It is continuing to rain.
3:00 pm Basin had a line pump issue. They were not able to finish the grout placement today. They got majority of
the placement complete but was unable to finish. They are cleaning up for the day. IMCO Crews are continuing to
work on forming wall panels for tomorrows concrete placement. The heavy rain is continuing.
4:00 pm IMCO is continuing to work on forming walls at Area 40. They have also set one of the crowder frames
on the rails.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 300 of 1851
References
Photos (5)
20240327_102833
Taken on Mar 27, 2024, 10:28 AM MDT
Added on Mar 28, 2024, 6:31 AM MDT
Added by Chris Johnson
20240327_124435
Taken on Mar 27, 2024, 12:44 PM MDT
Added on Mar 28, 2024, 6:31 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 301 of 1851
20240327_124421
Taken on Mar 27, 2024, 12:44 PM MDT
Added on Mar 28, 2024, 6:31 AM MDT
Added by Chris Johnson
20240327_121700
Taken on Mar 27, 2024, 12:17 PM MDT
Added on Mar 28, 2024, 6:31 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 302 of 1851
20240327_121655
Taken on Mar 27, 2024, 12:16 PM MDT
Added on Mar 28, 2024, 6:31 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 303 of 1851
Form detail
#320: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Wall Forming
Area 40, Form Walls, Bulkheads
IMCO, General Crew 1 10 Area 10, Mesa Wall 2
Area 40, Crowder Rails
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Forms
Location
Form date Mar 26, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 26, 2024, 6:26 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 304 of 1851
Crew # Workers # Total
hours
Work performed
Stucco Systems 2 10 Area 60, Stucco Ceiling in
Incubation
Basin Masonry 10 10 Area 50, Reinforced Masonry
Totals 24 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Mesa Wall
Deere 644J Loader 1 10
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 305 of 1851
Equipment Quantity Hours
used
Comment
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
2:00 pm Arrived on site. IMCO is working on forming walls at Area 40 and CIP at Area 10. The masons have
started on Area 50.
3:00 pm I reviewed a bit of the plan with IMCO and the masons. They got a later start today than anticipated so
they are pushing the first grout placement back to Wednesday at noon. It was originally scheduled for tomorrow
(Tuesday) at 330. The masons are currently working on the corners and setting up scaffolding.
4:00 pm IMCO is continuing to work on the crowder rails at Area 50. The stucco ceiling is done in Area 60
Incubation Room.
5:00 pm IMCO is done for the day but the masons are continuing to work on laying block at Area 50. They are
setting the 12" wide block. There was a small rain squall that came through. They worked through the weather and
are continuing to work.
6:00 pm The masons are continuing to work on laying block.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 306 of 1851
References
Photos (6)
20240325_153027
Taken on Mar 25, 2024, 3:30 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
20240325_152753
Taken on Mar 25, 2024, 3:27 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 307 of 1851
20240325_163738
Taken on Mar 25, 2024, 4:37 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
20240325_163020
Taken on Mar 25, 2024, 4:30 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 308 of 1851
20240325_152747
Taken on Mar 25, 2024, 3:27 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
20240325_152739
Taken on Mar 25, 2024, 3:27 PM MDT
Added on Mar 26, 2024, 6:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 309 of 1851
Form detail
#321: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Wall Forming
Area 40, Form Walls, Bulkheads
IMCO, General Crew 1 10 Area 10, Complete Mesa Wall 2
Area 40, Crowder Rails
Vale Electric, Electricians 3 10 Area 50, Work with Masons on Box
Placement
Area 60, Electrical Room, pull wire
Basin Masonry 10 10 Area 50, Reinforced Masonry
Forms
Location
Form date Mar 26, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 27, 2024, 6:18 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 310 of 1851
Crew # Workers # Total
hours
Work performed
Totals 22 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Mesa Wall
Deere 644J Loader 1 10
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 311 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Basin Masonry is continuing to work on installing the block masonry at Area 50. IMCO is finishing up the
Mesa block wall 2 while other crews are continuing forming.
10:00 am I met with Basin Masonry Foreman regarding a missing CJ in the wall. I brought it to his attention while
the block layer started the first course so they did not have any rework to do. The crew is continuing to work on
installing the block. IMCO is finishing the installation of Wall 2 of the Mesa retaining wall. They still need to work on
the hand rail placement but the blocks and caps are set.
11:00 am IMCO carpenters are working on forming at Area 40 and Area 10 CIP wall.
1:00 pm Basin is continuing to install CMU block. I discussed the unit strength prisms with Kelly from Basin. He
said he would make them tomorrow along with grouting them.
3:00 pm Vale Electric is continuing to work on Area 60 Electrical.
5:00 pm IMCO has started clearing the material around Area 60 foundation to install the waterproof membrane.
They are done for the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 312 of 1851
References
Photos (4)
20240326_094927
Taken on Mar 26, 2024, 9:49 AM MDT
Added on Mar 27, 2024, 6:17 AM MDT
Added by Chris Johnson
20240326_144316
Taken on Mar 26, 2024, 2:43 PM MDT
Added on Mar 27, 2024, 6:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 313 of 1851
20240326_113643
Taken on Mar 26, 2024, 11:36 AM MDT
Added on Mar 27, 2024, 6:17 AM MDT
Added by Chris Johnson
20240326_080636
Taken on Mar 26, 2024, 8:06 AM MDT
Added on Mar 27, 2024, 6:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 314 of 1851
Form detail
#319: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
Area 50, Place concrete slab
IMCO, General Crew 1 10 Area 10, Mesa Wall 2
Area 50, Batch Concrete
Vale Electric, Electricians 3 10 Area 60, Electrical Room, pull wire
Stucco Systems 2 10 Area 60, Stucco Ceiling in
Incubation
Forms
Location
Form date Mar 21, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 22, 2024, 10:36 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 315 of 1851
Crew # Workers # Total
hours
Work performed
Totals 14 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Concrete Placement, Mesa
Wall
Area 50, Concrete Placement
Deere 644J Loader 1 10 Area 50, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 316 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is prepping to place concrete for the formalin storage room. I asked Steve to clean out the
thickened curb section to achieve clearance from ground to rebar. I also pointed out that the rebar dowels should
be rechecked for layout prior to placing.
9:00 am IMCO has batched concrete and started placing using the concrete bucket. IPC has made the
determination that the low quantity of concrete today did not require concrete testing.
10:00 am IMCO has completed the small slab placement, they also captured a thrust block.
11:00 am IMCO crew is continuing to work on installing the mesa block wall 2.
12:00 pm IMCO crew is starting to work on setting the door frames for Area 50. There is no detail for hollow metal
door frames at Area 50. IMCO is going to use a mix of the Storefront door details along with manufacture standard
installation recommendations. Left site to return cylinders from yesterdays placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 317 of 1851
References
Photos (7)
20240321_102550
Taken on Mar 21, 2024, 10:25 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
20240321_110012
Taken on Mar 21, 2024, 11:00 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 318 of 1851
20240321_105958
Taken on Mar 21, 2024, 10:59 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
20240321_103534
Taken on Mar 21, 2024, 10:35 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 319 of 1851
20240321_082712
Taken on Mar 21, 2024, 8:27 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
20240321_074623
Taken on Mar 21, 2024, 7:46 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 320 of 1851
20240321_074607
Taken on Mar 21, 2024, 7:46 AM MDT
Added on Mar 22, 2024, 10:28 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 321 of 1851
Form detail
#318: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Footing Placement
Area 40, Form Walls, Bulkheads
Area 50, Form CJs, Place concrete
slab
IMCO, General Crew 1 10 Area 10, Mesa Wall 2
Area 50, Batch Concrete
Vale Electric, Electricians 3 10 Area 60, Electrical Room, pull wire
Forms
Location
Form date Mar 20, 2024
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 21, 2024, 6:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 322 of 1851
Crew # Workers # Total
hours
Work performed
Stucco Systems 2 10 Area 60, Stucco Ceiling in
Incubation
Totals 14 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Concrete Placement, Mesa
Wall
Area 50, Concrete Placement
Deere 644J Loader 1 10 Area 50, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 323 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is making final checks for todays slab placement at Area 50. This will be the 3rd slab placement.
9:00 am IMCO has batched the concrete and I have taken my test. The concrete meets specifications and passed
with no issues. IMCO is starting to place the concrete at Area 50 for the interior slab using the concrete bucket.
11:00 am IMCO has completed the slab placement, they are now working on the retaining wall footing placement
behind Area 70.
1:00 pm IMCO has completed the concrete placement for today. IMCO general crew is working on installing Wall 2
of the Mesa retaining wall.
3:00 pm IMCO crews are continuing to work on setting wall panels at Area 40 for the next wall placement. They
are also working on Area 50 slab prep. They plan to place the last of the slabs tomorrow, in the formalin room.
5:00 pm IMCO is done for the day. They are continued working on the mesa wall 2. They have approx. 50% of it
done.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 324 of 1851
References
Photos (7)
20240320_142649
Taken on Mar 20, 2024, 2:26 PM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
20240320_131103
Taken on Mar 20, 2024, 1:11 PM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 325 of 1851
20240320_104600
Taken on Mar 20, 2024, 10:46 AM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
20240320_093027
Taken on Mar 20, 2024, 9:30 AM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 326 of 1851
20240320_081302
Taken on Mar 20, 2024, 8:13 AM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
20240320_105118
Taken on Mar 20, 2024, 10:51 AM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 327 of 1851
20240320_092045
Taken on Mar 20, 2024, 9:20 AM MDT
Added on Mar 21, 2024, 6:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 328 of 1851
Form detail
#317: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Footing Placement
Area 40, Form Walls, Bulkheads
Area 50, Form CJs, Place concrete
slab
IMCO, General Crew 1 10 Area 10, Begin Mesa Wall 2
Area 50, Batch Concrete
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
MB Welding 1 10 Area 30, Handrail
Forms
Location
Form date Mar 18, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 20, 2024, 6:45 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 329 of 1851
Crew # Workers # Total
hours
Work performed
Totals 13 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Concrete Placement
Area 50, Concrete Placement
Deere 644J Loader 1 10 Area 50, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 330 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to place the 2nd slab placement today at Area 50. They are also planning to capture the first
footing placement on the CIP wall behind Area 70.
10:00 am IMCO crew is continuing to work on bulkheads and trench drain at Area 50 in prep for todays
placement. The general crew has started to move Mesa block to Wall 2 to begin installing the retaining wall.
11:30 am IMCO has batched concrete. Today they are using the concrete bucket instead of a pump truck. I took
my sample out of the truck and tested for air. It was too high at 8.2%. Kirt asked if I would test it again after the
spin the truck for 20 mins. Which I did. The second test came high at 7.6%. The decided to reject this truck and
batch a second one with less air. I tested that truck and all passed with no issues. The crew is starting to place the
concrete at Area 50.
2:00 pm IMCO is placing concrete for the CIP wall footing near Area 70. IMCO crew is working on finishing the
concrete at Area 50. I met with Larry to discuss the installation process of the Mesa wall. They are working on
placing the first course of the block. He informed me of the process which matched the approved drawings.
3:00 pm IMCO is continuing to place concrete for the CIP wall footing. MB Welding is working on installing the
handrail for Area 30. Leaving site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 331 of 1851
References
Photos (5)
20240318_131602
Taken on Mar 18, 2024, 1:16 PM MDT
Added on Mar 20, 2024, 6:42 AM MDT
Added by Chris Johnson
20240318_144530
Taken on Mar 18, 2024, 2:45 PM MDT
Added on Mar 20, 2024, 6:42 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 332 of 1851
20240318_143510
Taken on Mar 18, 2024, 2:35 PM MDT
Added on Mar 20, 2024, 6:42 AM MDT
Added by Chris Johnson
20240318_132753
Taken on Mar 18, 2024, 1:27 PM MDT
Added on Mar 20, 2024, 6:42 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 333 of 1851
20240318_131545
Taken on Mar 18, 2024, 1:15 PM MDT
Added on Mar 20, 2024, 6:42 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 334 of 1851
Form detail
#316: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 10, CIP Footing Bulkheads
Area 40, Form Walls, Bulkheads
Area 50, Form CJs, Place concrete
IMCO, General Crew 1 10 Area 50, Batch Concrete
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
EOI 2 10 Area 10, Rebar
Forms
Location
Form date Mar 15, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 15, 2024, 11:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 335 of 1851
Crew # Workers # Total
hours
Work performed
Totals 14 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Clean up
Deere 644J Loader 1 10 Area 50, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 5 Area 50, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 336 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is preparing to place concrete today at Area 50. They are going to place 2 squares of the CJs for the
slab.
9:00 am Pump truck is onsite. IMCO has a truck batched and ready.
10:00 am I tested the first truck. It passed with no issues. IMCO is starting to place at Area 50.
11:00 am IMCO has completed the placement. They are working on finishing it now.
11:30 am EOI is working on installing the rebar for the CIP wall near Area 70. IMCO carpenters are working on
template for EOI and will start on bulkheads after EOI is done. Left site to return cylinders from yesterdays
placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 337 of 1851
References
Photos (1)
20240315_095953
Taken on Mar 15, 2024, 9:59 AM MDT
Added on Mar 15, 2024, 11:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 338 of 1851
Form detail
#315: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads,
Place Concrete
Area 50, Form CJs
Area 60, Paint rooms
IMCO, General Crew 1 10 Area 10, Well Water Supply line,
CIP Wall Excavation
Area 40, Batch Concrete
Area 50, Backfill for Slab
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
Forms
Location
Form date Mar 14, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 15, 2024, 6:35 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 339 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 10 Area 10, Rebar
Area 40, Rebar
Totals 14 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, CIP Wall Foundation
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, GW line
Area 50, Slab grade
Kobelco 1100G Crane 1 10 Area 40, Wall forms
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 340 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is preparing for todays concrete placement at Area 40. They have 6 wall sections ready to be placed
today.
9:00 am The pump truck is onsite. The crew is working on batching concrete.
10:30 am IMCO has batched the first truck. They had a plug in the cement line at the batch plant but they got it
cleared. I tested the first truck. It passed with no issues. The crew is starting to place in the wall forms.
1:30 pm IMCO is finishing up the concrete placement of the walls. They are going to move the pump truck over to
place concrete for the mesa grade slab. This concrete is not required to be tested as its only 3000 psi requirement.
3:00 pm IMCO has completed the grade slab for the mesa wall. They are working on finishing the concrete for the
sump at Area 50 along with the walls.
4:00 pm IMCO crew has been working on forming bulkheads at Area 50 for the slab. They plan to place concrete
tomorrow at the slab. EOI has moved to installing rebar on the CIP wall near Area 70.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 341 of 1851
References
Photos (6)
20240314_152818
Taken on Mar 14, 2024, 3:28 PM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
20240314_152814
Taken on Mar 14, 2024, 3:28 PM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 342 of 1851
20240314_135431
Taken on Mar 14, 2024, 1:54 PM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
20240314_135424
Taken on Mar 14, 2024, 1:54 PM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 343 of 1851
20240314_135117
Taken on Mar 14, 2024, 1:51 PM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
20240314_112151
Taken on Mar 14, 2024, 11:21 AM MDT
Added on Mar 15, 2024, 6:34 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 344 of 1851
Form detail
#314: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Walls, Bulkheads
Area 50, Backfill for slab
Area 60, Paint rooms
IMCO, General Crew 1 10 Area 10, Well Water Supply line,
CIP Wall Excavation
Area 50, Backfill for Slab
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
EOI 2 10 Area 50, Slab Rebar
Forms
Location
Form date Mar 13, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 13, 2024, 5:51 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 345 of 1851
Crew # Workers # Total
hours
Work performed
Totals 11 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, CIP Wall Foundation
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, GW line
Area 50, Slab grade
Kobelco 1100G Crane 1 10 Area 40, Wall forms
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 346 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am I walked the site noting what has been completed this week. The crews have backfilled portion of the
Area 50 slab. I walked it, it feels firm and I could not find any issues with compaction. EOI is onsite to install the
rebar in this location. IMCO crews are working on the rails for the raceway crowders.
9:00 am Attended weekly meeting.
11:00 am IMCO is continuing the painting operation inside Area 60. The carpenter crews are working on
bulkheads and setting forms at Area 40. They are planning the placement for tomorrow.
1:00 pm IMCO is working on grouting the bottom of the raceway gates. EOI is continuing to work on rebar at
Area 50 while IMCO works on grading for the slab.
3:00 pm Vale Electric is continuing to work on the electrical room re-install after the painting was complete.
5:00 pm EOI has majority of the rebar in the portion of Area 50 slab ready. IMCO needs to form up the trench
drain and CJs.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 347 of 1851
References
Photos (13)
20240313_140711
Taken on Mar 13, 2024, 2:07 PM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_135936
Taken on Mar 13, 2024, 1:59 PM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 348 of 1851
20240313_134338
Taken on Mar 13, 2024, 1:43 PM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_174123
Taken on Mar 13, 2024, 5:41 PM MDT
Added on Mar 13, 2024, 5:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 349 of 1851
20240313_082112
Taken on Mar 13, 2024, 8:21 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_082501
Taken on Mar 13, 2024, 8:25 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 350 of 1851
20240313_082102
Taken on Mar 13, 2024, 8:21 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_081554
Taken on Mar 13, 2024, 8:15 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 351 of 1851
20240313_081545
Taken on Mar 13, 2024, 8:15 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_081535
Taken on Mar 13, 2024, 8:15 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 352 of 1851
20240313_081529
Taken on Mar 13, 2024, 8:15 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
20240313_081322
Taken on Mar 13, 2024, 8:13 AM MDT
Added on Mar 13, 2024, 5:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 353 of 1851
20240313_174110
Taken on Mar 13, 2024, 5:41 PM MDT
Added on Mar 13, 2024, 5:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 354 of 1851
Form detail
#313: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Walls, Bulkheads
Area 50, Backfill for slab
Area 60, Paint rooms
IMCO, General Crew 1 10 Area 50, Backfill for Slab
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
Totals 9 30
Forms
Location
Form date Mar 8, 2024
Description Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 8, 2024, 9:25 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 355 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 50, Backfill Slab
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crews are working on backfilling Area 50 slab. I witnessed the crew placing material in large lifts. I
spoke to Larry regarding the lift size and compaction effort. He informed me the large plate compactor is broke
down so they will have to use the jumping jack compactor. I advised him he should be no more than 12" lifts. I also
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 356 of 1851
noted the material looked dry. He said he would spread the lifts out smaller and get the compactor on it.
9:30 am The crew is continuing to backfill the slab at Area 50. They are also working on painting the rooms at Area
60.
References
Photos (2)
20240308_080103
Taken on Mar 8, 2024, 8:01 AM MST
Added on Mar 8, 2024, 8:39 AM MST
Added by Chris Johnson
20240308_075654
Taken on Mar 8, 2024, 7:56 AM MST
Added on Mar 8, 2024, 8:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 357 of 1851
Form detail
#312: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
Area 50, Form and Pour grout at
electrical block outs in stem wall
IMCO, General Crew 7 10 Area 10, Site piping, Backfilling,
Mesa Wall excavation
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
MB Welding 1 10 Area 30, Handrail install
Forms
Location
Form date Mar 7, 2024
Description Area 10, Area 30, Area 50, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 8, 2024, 6:19 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 358 of 1851
Crew # Workers # Total
hours
Work performed
Totals 19 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10 - Mesa Wall excavation
Deere 644J Loader 1 10 Area 10, Backfill
Hitachi 85 Excavator 1 8 Area 10,
Kobelco 1100G Crane 1 10 Area 40, Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Place Material
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 359 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO general crew is working on excavating for the foundation of Wall 2 of the Mesa block wall. They
are currently stockpiling the material near the wall.
9:00 am IMCO carpenters are working on forming up the electrical blockouts in the stem wall at Area 50. They
plan to fill these blockouts with grout today.
11:00 am IMCO pipe crew is working on installing the sewer line from Area 50 to the sewer lift station. They are
also working on installing the piping inside the lift station.
1:00 pm IMCO has excavated for the foundation for wall 2. They are going to start hauling the material across
the river to the stockpile to make room onsite.
3:00 pm IMCO carpenters are continuing to work on forming and bulkheads at Area 40 while another crew is
working on grouting the blockouts at Area 50.
4:00 pm IMCO is continuing to work on grouting the blockouts in the stem wall.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 360 of 1851
References
Photos (8)
20240307_113841
Taken on Mar 7, 2024, 11:38 AM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
20240307_150126
Taken on Mar 7, 2024, 3:01 PM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 361 of 1851
20240307_133338
Taken on Mar 7, 2024, 1:33 PM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
20240307_133221
Taken on Mar 7, 2024, 1:32 PM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 362 of 1851
20240307_133053
Taken on Mar 7, 2024, 1:30 PM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
20240307_113829
Taken on Mar 7, 2024, 11:38 AM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 363 of 1851
20240307_084551
Taken on Mar 7, 2024, 8:45 AM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
20240307_084546
Taken on Mar 7, 2024, 8:45 AM MST
Added on Mar 7, 2024, 3:50 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 364 of 1851
Form detail
#311: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
IMCO, General Crew 7 10 Area 10, Site piping, Backfilling,
Mesa Wall excavation, SS Lift
Station
Vale Electric, Electricians 3 10 Area 50, Electrical Raceways
Totals 18 30
Forms
Location
Form date Mar 6, 2024
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 7, 2024, 7:23 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 365 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10 - Mesa Wall excavation
Deere 644J Loader 1
Hitachi 85 Excavator 1 8 Area 10, Pothole, Sewer install
Kobelco 1100G Crane 1 10 Area 40, Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is prepping to start painting in the two rooms, Electrical and Generator, that the texture is
complete. They have approved primer and paint. They have heaters running into each room.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 366 of 1851
9:00 am Attended weekly meeting.
11:00 am A crew is working on potholing the utilities near Mesa wall 2, along the Snake River. A locator is onsite
locating while the crew searches for them carefully. Jeremey is then surveying the exposed utilities. Vale Electric is
in area 50 installing the raceway conduit. I have been informed that the plumber has passed Baker County
inspection.
1:00 pm IMCO crew is working on installing the sewer lift station. They set the structure. I seen they were
backfilling in large lifts without compacting. I brought this to their attention. They were just getting material in
there so the pipe crew could start installing the pumps.
2:00 pm The IMCO crew removed the material around the lift station structure and compacted it in lifts. They
showed me photos of the operation and the material visually looked liked it had been compacted. The carpenter
crew is continuing to work on forming walls at Area 40. They have canceled the concrete placement for this week.
3:00 pm MB Welding is onsite working on the stairs at Area 30.
4:00 pm IMCO crew is working on installing the sewer line from Area 60 to the sewer lift station. The mesa crew is
back to excavating for the foundation of Wall 2.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 367 of 1851
References
Photos (14)
20240306_132316
Taken on Mar 6, 2024, 1:23 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_074040
Taken on Mar 6, 2024, 7:40 AM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 368 of 1851
20240306_162636
Taken on Mar 6, 2024, 4:26 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_162146
Taken on Mar 6, 2024, 4:21 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 369 of 1851
20240306_162143
Taken on Mar 6, 2024, 4:21 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_160439
Taken on Mar 6, 2024, 4:04 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 370 of 1851
20240306_133534
Taken on Mar 6, 2024, 1:35 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_133445
Taken on Mar 6, 2024, 1:34 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 371 of 1851
20240306_133441
Taken on Mar 6, 2024, 1:34 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_132543
Taken on Mar 6, 2024, 1:25 PM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 372 of 1851
20240306_113654
Taken on Mar 6, 2024, 11:36 AM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_080652
Taken on Mar 6, 2024, 8:06 AM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 373 of 1851
20240306_080635
Taken on Mar 6, 2024, 8:06 AM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
20240306_075203
Taken on Mar 6, 2024, 7:52 AM MST
Added on Mar 7, 2024, 7:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 374 of 1851
Form detail
#310: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls, Bulkheads
IMCO, General Crew 7 10 Area 10, Site piping, Backfilling
Area 30, Mechanical Piping and
bracing
Nations Roofing 6 5 Area 60, Roof
Totals 21 25
Forms
Location
Form date Mar 1, 2024
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 6, 2024, 6:17 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 375 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 10, Load Fill
Hitachi 85 Excavator 1 8 Area 10, Piping
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 8 Area 10, Import Fill
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on bulkheads and wall forming at Area 40 today. They also planned to do some site
cleanup.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 376 of 1851
10:00 am IMCO general crew is continuing to work on piping and backfilling. They are starting to import material
from the stockpile across the river.
11:00 am I have taken a sample of the general fill material to test the plastic and liquid limit of the material. This
is required for the mesa retaining wall specifications. I also have picked up my cylinders and leaving the site.
References
Photos (1)
20240301_082459
Taken on Mar 1, 2024, 8:24 AM MST
Added on Mar 6, 2024, 6:17 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 377 of 1851
Form detail
#308: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Place Concrete, Form
Walls
IMCO, General Crew 7 10 Area 30, Mechanical Piping and
bracing
Area 40, Batch Concrete
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 29, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 29, 2024, 4:52 PM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 378 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Excavate for Mesa Wall
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 379 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on batching concrete for todays placement. The crews are working on getting tents
built in preparation for todays placement in the rain.
9:00 am Pump truck is setup and IMCO has batched concrete. I have taken my sample after the pump truck
pumped approx. 1 cy into the eco pan. The test passed with no issues. While waiting for concrete I witnessed a
near miss safety issue. The roofing sub contractor, Nations Roofing, appeared to hit a pole or wire behind the
existing hatchery building. I notified IMCO, Jeremey, instantly as I witnessed it. He took action to stop the work
then he notified Kirt of the issue. Nothing looks to be damaged.
10:00 am IMCO is continuing to place concrete. Kirt and I spoke about the safety issue. He is going to work
through IMCO standard protocol regarding the near miss.
11:30 am IMCO has placed two wall sections. The pump truck cannot reach the other wall sections. The pump
truck is moving now to reset up where it can reach the rest of the wall section.
2:00 pm IMCO has completed the concrete placement. They are working on finishing the concrete now.
4:30 pm IMCO worked on installing piping from Area 60 to Area 30 to the end of the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 380 of 1851
References
Photos (5)
20240229_093613
Taken on Feb 29, 2024, 9:36 AM MST
Added on Feb 29, 2024, 4:43 PM MST
Added by Chris Johnson
20240229_160436
Taken on Feb 29, 2024, 4:04 PM MST
Added on Feb 29, 2024, 4:43 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 381 of 1851
20240229_160344
Taken on Feb 29, 2024, 4:03 PM MST
Added on Feb 29, 2024, 4:43 PM MST
Added by Chris Johnson
20240229_113538
Taken on Feb 29, 2024, 11:35 AM MST
Added on Feb 29, 2024, 4:43 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 382 of 1851
20240229_112827
Taken on Feb 29, 2024, 11:28 AM MST
Added on Feb 29, 2024, 4:43 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 383 of 1851
Form detail
#307: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
IMCO, General Crew 7 10 Area 30, Mechanical Piping and
bracing
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
YMC 2 8 Area 60, HVAC
Forms
Location
Form date Feb 28, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 29, 2024, 6:19 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 384 of 1851
Crew # Workers # Total
hours
Work performed
JC Drywall 4 10 Area 60, Tape drywall
Totals 30 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Excavate for Mesa Wall
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 385 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am I met with IMCO regarding the Mesa retaining wall. We discussed the base layer slab along with
requirements for the backfill material. They plan to pour a concrete foundation slab for the block. I also brought to
their attention the plastic and liquid limit specification on the General Fill material they plan to use. This test is
needed to verify the material can be used.
9:00 am Attended weekly meeting.
10:00 am IMCO is continuing to work on forming walls in preparation for tomorrows concrete placement at Area
40. Currently JC Drywall is taping the 3 rooms at Area 60 where the GWB was replaced. IMCO is also working on
backfilling the interior of Area 50. This allows the plumber to get in there and start installing the drain and water
piping.
12:00 pm Lacy Mechanical is onsite working on the plumbing at Area 50. IMCO is continuing to work on welding
the spray bars at Area 40. Nations Roofing is onsite working on capping the roof along with soffit.
2:00 pm IMCO is continuing to work on forming walls at Area 40. All the carpenters are working on them. Vale
Electric is working on installing the raceway conduit under the slab at Area 50.
4:00 pm JC Drywall is continuing to work on taping and mudding the seams and screw holes on the GWB in the
three rooms. Lacy is continuing the plumbing at Area 50. I noticed a spot where the plumbing could interfere with
compaction effort under the slab. I notified Jeremey of it and he said he would take a look.
5:00 pm IMCO is cleaning up for the day. They are ready to place walls tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 386 of 1851
References
Photos (5)
20240228_095200
Taken on Feb 28, 2024, 9:52 AM MST
Added on Feb 29, 2024, 6:13 AM MST
Added by Chris Johnson
20240228_094202
Taken on Feb 28, 2024, 9:42 AM MST
Added on Feb 29, 2024, 6:13 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 387 of 1851
20240228_094159
Taken on Feb 28, 2024, 9:41 AM MST
Added on Feb 29, 2024, 6:13 AM MST
Added by Chris Johnson
20240228_094032
Taken on Feb 28, 2024, 9:40 AM MST
Added on Feb 29, 2024, 6:13 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 388 of 1851
20240228_142654
Taken on Feb 28, 2024, 2:26 PM MST
Added on Feb 29, 2024, 6:13 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 389 of 1851
Form detail
#306: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Strip Stem Wall
IMCO, General Crew 7 10 Area 10, Backfill piping, Grout MH,
Clean Site
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 20, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 21, 2024, 9:30 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 390 of 1851
Crew # Workers # Total
hours
Work performed
YMC 2 8 Area 60, HVAC
Totals 26 38
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 391 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on forming walls at Area 40. The other crew is working on filling tie holes on Area 50
stem wall.
9:00 am IMCO dirt crew is working on installing the stem wall membrane behind the tie holes getting filled. JC
Drywall is onsite working on removing the DensGlass in the Chiller room. MB Welding is onsite starting the stairs
install of Area 30.
10:00 am IMCO is continuing to work on installing the underdrain for Area 50. After checking submittals on the
product I noticed the membrane they are using is incomplete. A 60 mil paint on product is also needed per the
Detail C 243 on GC-3. Its also stated in submittal 152. I have informed IMCO of this. They need to submit on this
product.
12:00 pm MB Welding is adding 8" to the existing stair way supports on Area 30. This is needed to make up the
difference for the metal siding that was added.
2:00 pm IMCO pipe crew is starting to install the under slab piping at Area 50.
3:00 pm Kirt informed me they will be installing the 60 mil membrane before proceeding any further. The crew is
working on piping inside Area 50.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 392 of 1851
References
Photos (10)
20240220_131301
Taken on Feb 20, 2024, 1:13 PM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
20240220_110656
Taken on Feb 20, 2024, 11:06 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 393 of 1851
20240220_090038
Taken on Feb 20, 2024, 9:00 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
20240220_090035
Taken on Feb 20, 2024, 9:00 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 394 of 1851
20240220_085941
Taken on Feb 20, 2024, 8:59 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
20240220_084927
Taken on Feb 20, 2024, 8:49 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 395 of 1851
20240220_084922
Taken on Feb 20, 2024, 8:49 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
20240220_084624
Taken on Feb 20, 2024, 8:46 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 396 of 1851
20240220_143148
Taken on Feb 20, 2024, 2:31 PM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
20240220_111539
Taken on Feb 20, 2024, 11:15 AM MST
Added on Feb 21, 2024, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 397 of 1851
Form detail
#305: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Strip Stem Wall
IMCO, General Crew 7 10 Area 10, Backfill piping, Grout MH,
Clean Site
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 19, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 20, 2024, 6:34 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 398 of 1851
Crew # Workers # Total
hours
Work performed
YMC 2 8 Area 60, HVAC
Totals 26 38
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 399 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is planning to start stripping the forms from the stem wall placement last week. Another crew is
going to start stripping walls at Area 40 as well.
10:00 am Nations Roofing is onsite continuing to install the roof on Area 60.
11:00 am JC Drywall is onsite. They are removing the DensGlass wall board from the electrical room, generator
room. They also need to remove it from the chiller room. I noticed they cut through the vapor barrier in a few
locations. This will need to be addressed prior to new GWB being installed. IMCO dirt crew is cleaning up the site
and backfilling areas. I spoke to Jeremey about the condition of the material. Everything is very wet onsite and the
material is not firm. I mentioned to him that if it is final compaction, they will need to perform a proof roll but how
the material is now, it will not pass a proof roll.
1:00 pm YMC is onsite continuing to install the HVAC in Area 60.
3:00 pm IMCO carpenters are working on stripping the forms. From what I have seen, the stem wall looks well
consolidated.
4:30 pm IMCO is continuing to form wall sections at Area 40. I am being told they are planning to make another
placement on Thursday at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 400 of 1851
References
Photos (7)
20240219_103041
Taken on Feb 19, 2024, 10:30 AM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
20240219_101710
Taken on Feb 19, 2024, 10:17 AM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 401 of 1851
20240219_131718
Taken on Feb 19, 2024, 1:17 PM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
20240219_134021
Taken on Feb 19, 2024, 1:40 PM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 402 of 1851
20240219_103034
Taken on Feb 19, 2024, 10:30 AM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
20240219_101559
Taken on Feb 19, 2024, 10:15 AM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 403 of 1851
20240219_101341
Taken on Feb 19, 2024, 10:13 AM MST
Added on Feb 20, 2024, 6:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 404 of 1851
Form detail
#304: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Place Walls
Area 50, Place Stem Wall
IMCO, General Crew 7 10 Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 15, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 19, 2024, 9:51 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 405 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10 concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 406 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is batching concrete for todays placement. The pump truck has arrived and is setting up. IMCO
crew is continuing to work on stem wall forms and dowel placement. They plan to pour the Area 40 walls first then
switch to the Area 50 stem wall.
9:00 am I have taken my first test from the first truck. All passed in spec with the slump a little high. IMCO is
going to proceed with placing the concrete considering the location in the forms will support better consolidation.
They are going to reduce the water in the consecutive trucks.
9:30 am The second truck has been batched and started placing. I witnessed the slump from the truck was lower.
The crew is continuing to place.
10:00 am IMCO crew is continuing to work on placing the dowels in the stem wall at Area 50. They are pushing
hard to make the placement today. Nations roofing is onsite working on Area 60 roof.
12:00 pm The crew finished the placement of the Area 40 walls. I tested the first truck to be placed in the Area 50
Stem walls. It tested in spec with no issues. Crew is going to start placing now.
1:00 pm Crew is continuing to place concrete at Area 50.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 407 of 1851
References
Photos (2)
20240215_111120
Taken on Feb 15, 2024, 11:11 AM MST
Added on Feb 19, 2024, 9:51 AM MST
Added by Chris Johnson
20240215_082927
Taken on Feb 15, 2024, 8:29 AM MST
Added on Feb 19, 2024, 9:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 408 of 1851
Form detail
#303: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Form Stem Wall
IMCO, General Crew 7 10 Area 10, Storm Pipe, Catch Basin
Install
Area 40, Fly Wall Panels
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Forms
Location
Form date Feb 14, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 15, 2024, 7:40 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 409 of 1851
Crew # Workers # Total
hours
Work performed
Nations Roofing 6 5 Area 60, Roof
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Catch basin, Storm Pipe
Install
Deere 644J Loader 1 10 Area 10, Load material at stockpile
Hitachi 85 Excavator 1 10 Area 10, Catch basin, Storm Pipe
Install
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Fill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 410 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on stem wall forms at Area 50. The crew is pushing to make tomorrows
concrete placement schedule. Another crew is working on Area 40 Wall forms. They are scheduled to place Area 40
walls and Area 50 stem wall tomorrow.
9:00 am Nations Roofing is onsite again to continue installing the roof on Area 60. Vale Electrical is also onsite
continuing to install what electrical they can without correct wall board to be installed. They have removed the
gear in the electrical room that will conflict with the wall board demo and reinstall.
11:00 am I met with Steve to go over some rebar issues I found at Area 50 Stem wall. Some clearances were not
to spec. He said he would get them fixed. We also reviewed the dowel layout. I spoke to him and Kirt regarding the
notes on the previous rebar submittal addressing MCJs proximity to the pan decking beams along with the MCJ
location to the pipe penetrations. They are going to look into it and verify.
1:00 pm The crew is continuing to work on the dowels and closing up the forms for the stem wall at Area 50.
2:00 pm IMCO crew is working in the incubation room. They are waiting on a flowmeter to arrive to finish the
piping but they are working on preliminary testing of the piping with water. They are plugging the saddles now so
they can test the line with water. A full test will need to be witnessed and documented once they are complete.
4:00 pm IMCO is continuing to layout the dowels for tomorrows stem wall pour.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 411 of 1851
References
Photos (6)
20240214_131527
Taken on Feb 14, 2024, 1:15 PM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
20240214_131229
Taken on Feb 14, 2024, 1:12 PM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 412 of 1851
20240214_130527
Taken on Feb 14, 2024, 1:05 PM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
20240214_130519
Taken on Feb 14, 2024, 1:05 PM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 413 of 1851
20240214_094812
Taken on Feb 14, 2024, 9:48 AM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
20240214_131430
Taken on Feb 14, 2024, 1:14 PM MST
Added on Feb 15, 2024, 7:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 414 of 1851
Form detail
#302: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Form Stem Wall
IMCO, General Crew 7 10 Area 10, Storm Pipe, Catch Basin
Install
Area 40, Fly Wall Panels
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Forms
Location
Form date Feb 13, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 14, 2024, 6:36 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 415 of 1851
Crew # Workers # Total
hours
Work performed
Nations Roofing 6 5 Area 60, Roof
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Catch basin, Storm Pipe
Install
Deere 644J Loader 1 10 Area 10, Load material at stockpile
Hitachi 85 Excavator 1 10 Area 10, Catch basin, Storm Pipe
Install
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Fill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 416 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am IMCO is continuing to install stem wall forms at Area 50. I noticed they have closed up the forms where
the electrical blockouts are. Steve walked me through the rebar they installed around the blockouts. I told him I
would review the drawings and get back to him. They are continuing to install the stem wall forms. They are
pushing to pour the stem wall Thursday of this week.
11:00 am Nations roofing is onsite continuing to install the roof on Area 60. IMCO has another carpenter crew
working on Area 40 wall forming. They are continuing the moving of the forms and placing from cold joint to cold
joint. They plan to place wall forms Thursday as well.
2:00 pm I met with Steve regarding the rebar at Area 50. It looks to be in accordance with the approved
drawings along with RFI 114. I have taken photos for backup. I did point out some clearance issues I observed. His
crew is going to get them fixed prior to the concrete placement on Thursday.
4:00 pm IMCO dirt crew has been working on installing Catch Basins and storm piping. They installed CB 11 this
morning and is currently working on installing the storm pipe to CB 8.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 417 of 1851
References
Photos (7)
20240213_151455
Taken on Feb 13, 2024, 3:14 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
20240213_145201
Taken on Feb 13, 2024, 2:52 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 418 of 1851
20240213_152319
Taken on Feb 13, 2024, 3:23 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
20240213_151521
Taken on Feb 13, 2024, 3:15 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 419 of 1851
20240213_151452
Taken on Feb 13, 2024, 3:14 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
20240213_145210
Taken on Feb 13, 2024, 2:52 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 420 of 1851
20240213_145204
Taken on Feb 13, 2024, 2:52 PM MST
Added on Feb 14, 2024, 6:35 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 421 of 1851
Form detail
#300: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Place Walls
Area 50, Form Stem Wall
IMCO, General Crew 7 10 Area 40, Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 8, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 9, 2024, 7:27 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 422 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Batch Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 423 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is starting to batch concrete for todays placement. They are getting the trucks warmed up and
warming the drums with hot water.
9:00 am The pump truck is setup and priming and the first truck is batched.
10:00 am The pump truck got clogged multiple times over the last hour. By the time it was cleared up there was
~1 CY left in the concrete truck. I performed an INFO ONLY air test on the mix to aid IMCO is batching the second
truck. The air test proved the concrete was in spec. They are rejecting the rest of the truck due to quantity.
10:30 am I tested the second truck. It all tested and passed in spec. IMCO is starting the placement.
11:00 am IMCO is installing the incubation room table. Some of the plumbing in the room required the table to
be installed. I have brought my concern to multiple IMCO management regarding installing more items that could
get damaged during the stucco ceiling installation in the coming weeks.
1:30 pm IMCO has completed the wall placement. They were able to capture 6 wall sections from CJ to CJ at Area
40.
2:30 pm Nations Roofing is continuing to install the roof on Area 60.
4:00 pm IMCO is covering the walls they poured today with blankets. Some of the crew has left for the weekend
while others are cleaning up around the site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 424 of 1851
References
Photos (4)
20240208_124610
Taken on Feb 8, 2024, 12:46 PM MST
Added on Feb 9, 2024, 7:24 AM MST
Added by Chris Johnson
20240208_123119
Taken on Feb 8, 2024, 12:31 PM MST
Added on Feb 9, 2024, 7:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 425 of 1851
20240208_123047
Taken on Feb 8, 2024, 12:30 PM MST
Added on Feb 9, 2024, 7:24 AM MST
Added by Chris Johnson
20240208_124603
Taken on Feb 8, 2024, 12:46 PM MST
Added on Feb 9, 2024, 7:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 426 of 1851
Form detail
#299: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Form Stem Wall
IMCO, General Crew 7 10 Area 10, Storm Lines
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 7, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 8, 2024, 7:13 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 427 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Storm Lines
Deere 644J Loader 1 10 Area 10, Load Dump Truck
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Wall Panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Fill
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 428 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Attended weekly meeting.
9:00 am IMCO has stripped the footing forms and the wall forms from last weeks placement. They are currently
working on forming the stem walls starting with the inside forms at Area 50.
10:00 am Nations roofing is onsite installing the metal roof on Area 60.
12:00 pm IMCO is continuing the piping inside the incubation room. They are installing the piping to the
incubators.
1:00 pm YMC is onsite installing the HVAC for Area 60.
2:00 pm Yale Electric is onsite working on installing block outs in the stem wall for electrical conduit at Area 50.
4:00 pm IMCO has been installing piping lines around Area 30. They are currently working on installing Catch
Basins and storm lines.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 429 of 1851
References
Photos (7)
20240207_094312
Taken on Feb 7, 2024, 9:43 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
20240207_100826
Taken on Feb 7, 2024, 10:08 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 430 of 1851
20240207_094647
Taken on Feb 7, 2024, 9:46 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
20240207_094252
Taken on Feb 7, 2024, 9:42 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 431 of 1851
20240207_100749
Taken on Feb 7, 2024, 10:07 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
20240207_094351
Taken on Feb 7, 2024, 9:43 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 432 of 1851
20240207_094323
Taken on Feb 7, 2024, 9:43 AM MST
Added on Feb 8, 2024, 6:57 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 433 of 1851
Form detail
#297: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Place Walls
Area 50, Place Footing
IMCO, General Crew 7 10 Area 40, Batch Concrete
Area 50, Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 5 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Feb 1, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 2, 2024, 6:24 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 434 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40,50 Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, 50 Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 435 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is planning to place concrete today at Area 50 footing. If they have time they plan to also place at
Area 40 raceway walls. They are working on getting the batch plant going now.
9:00 am IMCO has batched their first truck and I have tested it. All tested in spec with no issues. They are starting
to place in the footings at Area 50.
12:00 am IMCO has finished the placement at Area 50. They are going to start placing at Area 40 Raceway walls
now. I have tested the first truck after the pump truck moved. All tested in spec with no issues.
1:00 pm Nations roofing is onsite. They are working on the soffit on the gables. IMCO is continuing to place
concrete on the walls at Area 40.
2:30 pm IMCO is finishing the top of the walls, most of the crew has taken off for the weekend. Nations roofing is
onsite still working on siding and soffit.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 436 of 1851
References
Photos (6)
20240201_101605
Taken on Feb 1, 2024, 10:16 AM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
20240201_101132
Taken on Feb 1, 2024, 10:11 AM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 437 of 1851
20240201_141438
Taken on Feb 1, 2024, 2:14 PM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
20240201_141419
Taken on Feb 1, 2024, 2:14 PM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 438 of 1851
20240201_101602
Taken on Feb 1, 2024, 10:16 AM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
20240201_101501
Taken on Feb 1, 2024, 10:15 AM MST
Added on Feb 2, 2024, 6:23 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 439 of 1851
Form detail
#296: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Foundation Forming
IMCO, General Crew 7 10 Area 60, Mechanical Piping in
Chiller room, Underdrain and
backfill behind building
Vale Electric, Electricians 3 8 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Jan 31, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Feb 1, 2024, 9:51 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 440 of 1851
Crew # Workers # Total
hours
Work performed
EOI 3 8 Area 40, Wall Rebar
Area 50, Footing Rebar
Totals 27 41
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, Backfill
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 441 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on forming walls at Area 40. They have formed all the footings for Area 50
and EOI is finishing the rebar install in preparation for tomorrows concrete placement.
9:00 am Attended weekly meeting.
10:00 am Nations Roofing is onsite working on Area 60 and Area 30. They are installing the siding and gutters on
the two buildings.
11:00 am I met with Steve and walked the footing rebar and forms. He needed to adjust some rebar for some
clearance issues but all is good and ready to place concrete tomorrow.
1:00 pm IMCO is installing piping in the incubation room. I met with Bryce and provided him information
regarding clearance for the flow meters. The information came from Schnabel via email.
3:00 pm IMCO has been working on backfilling and installing the underdrain behind the building at Area 60. They
are getting the area up to grade so the HVAC concrete pads can be poured.
4:00 pm The crew is ready for tomorrow concrete placement. EOI has been onsite installing rebar at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 442 of 1851
References
Photos (15)
20240131_142754
Taken on Jan 31, 2024, 2:27 PM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_093825
Taken on Jan 31, 2024, 9:38 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 443 of 1851
20240131_093818
Taken on Jan 31, 2024, 9:38 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_093650
Taken on Jan 31, 2024, 9:36 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 444 of 1851
20240124_101834
Taken on Jan 24, 2024, 10:18 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_103236
Taken on Jan 31, 2024, 10:32 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 445 of 1851
20240131_102200
Taken on Jan 31, 2024, 10:21 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_102149
Taken on Jan 31, 2024, 10:21 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 446 of 1851
20240131_100631
Taken on Jan 31, 2024, 10:06 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_093821
Taken on Jan 31, 2024, 9:38 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 447 of 1851
20240131_093746
Taken on Jan 31, 2024, 9:37 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240131_093542
Taken on Jan 31, 2024, 9:35 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 448 of 1851
20240124_101830
Taken on Jan 24, 2024, 10:18 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
20240124_100728
Taken on Jan 24, 2024, 10:07 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 449 of 1851
20240124_100353
Taken on Jan 24, 2024, 10:03 AM MST
Added on Feb 1, 2024, 9:44 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 450 of 1851
Form detail
#294: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Foundation Forming
IMCO, General Crew 7 10 Area 10, Prepare for IPC line crew,
Transformer pad
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Nations Roofing 6 5 Area 60, Roof
Forms
Location
Form date Jan 24, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 26, 2024, 8:59 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 451 of 1851
Crew # Workers # Total
hours
Work performed
YMC Mechanical 3 4 Area 60, HVAC
EOI 2 8 Area 50, Footing Rebar
Totals 29 45
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, Backfill
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 452 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on forming walls at Area 40. They are going to start hand setting forms
where the large wall panels cannot be used. Last night they did not run heaters on the walls that were placed.
Instead they covered with insulated blankets.
9:00 am Attended weekly meeting.
11:00 am I spoke to Steve about the concrete temperatures without running heaters. He hadn't checked the
temperatures yet but he said he would. Later Kirt told me the temps were around 67 Degrees. He said he would
have Jeremey start recording temperatures for record. The electricians are continuing to work in the electrical
room on things that do not interfere with the wall sheeting. They are continuing to pull wire in the office area. IPC
is onsite working on the install of the conduit for the Pine Creek feed. IMCO is excavating for the conduit.
1:00 pm IMCO is continuing to work on forming wall sections at Area 40. Nations roofing is installing siding,
fascia and gutters on Area 60. EOI is onsite installing the rebar for the Area 50 Footing.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 453 of 1851
References
Photos (4)
20240124_101834
Taken on Jan 24, 2024, 10:18 AM MST
Added on Jan 26, 2024, 8:59 AM MST
Added by Chris Johnson
20240124_101830
Taken on Jan 24, 2024, 10:18 AM MST
Added on Jan 26, 2024, 8:59 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 454 of 1851
20240124_100728
Taken on Jan 24, 2024, 10:07 AM MST
Added on Jan 26, 2024, 8:59 AM MST
Added by Chris Johnson
20240124_100353
Taken on Jan 24, 2024, 10:03 AM MST
Added on Jan 26, 2024, 8:59 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 455 of 1851
Form detail
#293: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Place Concrete
Area 50, Foundation Forming
IMCO, General Crew 6 10 Area 40, Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Nations Roofing 3 5 Area 60, Roof
Forms
Location
Form date Jan 23, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 24, 2024, 7:24 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 456 of 1851
Crew # Workers # Total
hours
Work performed
YMC Mechanical 2 4 Area 60, HVAC
Totals 22 37
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3 10 Area 40, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 457 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached concrete field report and IMCO batch tickets.
8:00 am IMCO is working on getting the batch plant up and going in preparation for todays concrete placement
at Area 40.
9:00 am The pump truck is onsite and getting setup to pour. I checked in with the batch plant. The water line is
froze and they are working to get it thawed.
10:00 am IMCO is still working on thawing the water line. They are using the water truck until then. They are
getting the water heated up with the boiler and plan to start batching soon.
11:00 am IMCO has batched 4.5 CY for the first truck. I tested for air. It tested low. They dosed the truck. After
dosing the truck I tested again. It barley made it at 5.1%. They started placing.
11:30 am I tested the second truck which had 9 CY on it. The air test came in at 6.9%. I informed Kirt, he said he
would dial the air treatment back a little bit. I finished this test and casted cylinders. IMCO is continuing to place
concrete in the 6 wall sections they have formed up.
12:30 pm IMCOs second carpenter crew is continuing to work on Area 50 foundation. I informed Jeremy that
rebar dowels were missed in the fish lift walls that extend into the footing and stem wall of Area 50. He said they
are looking into the depth and size of the bars so they can epoxy them in.
3:00 pm IMCO has completed the concrete placement. They plan to continue working on forming for the next
placement.
4:00 pm IMCO is continuing to work on forming the footing for Area 50. Nations Roofing is continuing to work on
installing the fascia and soffit trim. They have also been working in the breezeway trimming around the block and
the doors. It was noted that Vale electric will stop working in the electrical room until the densglas material and the
coatings are approved.
4:30 pm YMC is continuing to work on the office area HVAC.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 458 of 1851
References
Photos (9)
20240123_143807
Taken on Jan 23, 2024, 2:38 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
20240123_111534
Taken on Jan 23, 2024, 11:15 AM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 459 of 1851
20240123_090748
Taken on Jan 23, 2024, 9:07 AM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
20240123_090736
Taken on Jan 23, 2024, 9:07 AM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 460 of 1851
20240123_144213
Taken on Jan 23, 2024, 2:42 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
20240123_144056
Taken on Jan 23, 2024, 2:40 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 461 of 1851
20240123_144053
Taken on Jan 23, 2024, 2:40 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
20240123_143843
Taken on Jan 23, 2024, 2:38 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 462 of 1851
20240123_133634
Taken on Jan 23, 2024, 1:36 PM MST
Added on Jan 24, 2024, 7:19 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 463 of 1851
Form detail
#292: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Form Walls
Area 50, Begin Foundation
Forming
IMCO, General Crew 6 10 Area 10, Electrical Piping
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Nations Roofing 3 5 Area 60, Roof
Forms
Location
Form date Jan 22, 2024
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 23, 2024, 7:28 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 464 of 1851
Crew # Workers # Total
hours
Work performed
YMC Mechanical 2 4 Area 60, HVAC
Totals 22 37
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 8 Area 10, Import General Fill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 465 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
2:00 pm IMCO carpenter crew is continuing to work on forming walls at Area 40. The are placing concrete
tomorrow with what they have done at end of today. They are closing up the 6th wall now.
3:00 pm IMCO has brough another carpenter crew onsite to start the foundation of Area 50. I met with Jeremey.
He has been checking the elevation and dimensions of the foundation forming.
4:00 pm Nations roofing is onsite to start the roof of Area 60. Jake informed me the penetration YMC installed
leaked over the weekend with the snow. They have fixed the issue and is drying the GWB out now. Jake informed
me it was minimal. IMCO is continuing to install chiller piping in the chiller room. IMCO pipe crew is working on the
incubation drain pipe from the building to MH-4. They informed me that the HDPE fuse machine has broke down
and they are working on getting a replacement.
4:30 pm Vale electric is onsite working in the electrical room. He informed me they are almost complete with the
raceway install in the room.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 466 of 1851
References
Photos (7)
20240122_154247
Taken on Jan 22, 2024, 3:42 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
20240122_153801
Taken on Jan 22, 2024, 3:38 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 467 of 1851
20240122_153710
Taken on Jan 22, 2024, 3:37 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
20240122_153707
Taken on Jan 22, 2024, 3:37 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 468 of 1851
20240122_153247
Taken on Jan 22, 2024, 3:32 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
20240122_153237
Taken on Jan 22, 2024, 3:32 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 469 of 1851
20240122_152818
Taken on Jan 22, 2024, 3:28 PM MST
Added on Jan 23, 2024, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 470 of 1851
Form detail
#291: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 40, Form Walls
IMCO, General Crew 6 10 Area 10, Electrical Piping
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 15 28
Forms
Location
Form date Jan 18, 2024
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 19, 2024, 11:00 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 471 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on forming walls at Area 60. They plan on placing concrete next Tuesday.
10:00 am IMCO piping crew is continuing to work on installing Chiller piping inside the Chiller room of Area 60.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 472 of 1851
12:00 pm IMCO dirt crew has been working with Vale Electric on installing the raceway piping from the
transformer to the electrical room. They are getting the raceways installed and backfilling with sand.
2:00 pm IMCO is continuing to fly panels with the crane and installing wall panels in preparation for next weeks
concrete placement.
References
Photos (6)
20240118_110546
Taken on Jan 18, 2024, 11:05 AM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
20240118_110535
Taken on Jan 18, 2024, 11:05 AM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 473 of 1851
20240118_140437
Taken on Jan 18, 2024, 2:04 PM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
20240118_110526
Taken on Jan 18, 2024, 11:05 AM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 474 of 1851
20240118_110520
Taken on Jan 18, 2024, 11:05 AM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
20240118_110515
Taken on Jan 18, 2024, 11:05 AM MST
Added on Jan 19, 2024, 10:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 475 of 1851
Form detail
#290: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 40, Form Walls
IMCO, General Crew 6 10 Area 10, Electrical Piping
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 15 28
Forms
Location
Form date Jan 17, 2024
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 18, 2024, 10:25 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 476 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Electrical pipe install
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am It is continuing to snow here which is slowing down production. IMCO is currently working on forming
wall sections at Area 40. They have decided to cancel the concrete placement for this week that was scheduled for
tomorrow. They will work through the week on forming wall sections to place next week.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 477 of 1851
9:00 am Attended weekly meeting.
10:00 am IPC was scheduled to be onsite today to install the feeder conduit from the Pine Creek Supply to the
duct bank. They were called off to work on an emergency job somewhere else. IMCO has the ditch excavated. I
suggested to IMCO they should set caution tape around the trench because the crew will not make it today.
12:00 pm IMCO is continuing to work on mechanical piping inside the chiller room.
2:00 pm IMCO is continuing to work on wall forms. Vale electric is onsite installing the secondary conduit and
working inside the electrical room.
References
Photos (5)
20240117_105003
Taken on Jan 17, 2024, 10:50 AM MST
Added on Jan 18, 2024, 10:25 AM MST
Added by Chris Johnson
20240117_104958
Taken on Jan 17, 2024, 10:49 AM MST
Added on Jan 18, 2024, 10:25 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 478 of 1851
20240117_103748
Taken on Jan 17, 2024, 10:37 AM MST
Added on Jan 18, 2024, 10:25 AM MST
Added by Chris Johnson
20240117_103519
Taken on Jan 17, 2024, 10:35 AM MST
Added on Jan 18, 2024, 10:25 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 479 of 1851
20240117_102554
Taken on Jan 17, 2024, 10:25 AM MST
Added on Jan 18, 2024, 10:25 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 480 of 1851
Form detail
#289: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Walls, Place
concrete
IMCO, General Crew 6 10 Area 50, Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 14 28
Forms
Location
Form date Jan 11, 2024
Description Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 15, 2024, 8:42 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 481 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is getting the batch plant warmed up. Today they are putting hot water inside the drums of the
concrete trucks and spinning them to warm the drums up.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 482 of 1851
9:30 am IMCO has batched its first truck. I tested the concrete from the pump. It all tested in spec. IMCO started
to place concrete in the forms.
11:00 am IMCO is working on placing concrete. They are placing 3 wall panels sections today.
1:00 pm IMCO mechanical piping crew is continuing to install piping in the chiller room.
2:00 pm IMCO has completed the concrete placement. They are getting the heaters setup and covering the walls.
4:00 pm IMCO has the heaters setup and the walls covered.
References
Photos (3)
20240111_125842
Taken on Jan 11, 2024, 12:58 PM MST
Added on Jan 15, 2024, 8:34 AM MST
Added by Chris Johnson
20240111_100721
Taken on Jan 11, 2024, 10:07 AM MST
Added on Jan 15, 2024, 8:34 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 483 of 1851
20240111_125850
Taken on Jan 11, 2024, 12:58 PM MST
Added on Jan 15, 2024, 8:34 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 484 of 1851
Form detail
#288: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Walls
IMCO, General Crew 6 10 Area 50, Piping, Grading
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 14 28
Forms
Location
Form date Jan 10, 2024
Description Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 11, 2024, 8:03 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 485 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on forming walls at Area 40. They have been moving walls from previous
placements and getting new sections formed and ready for concrete. They have been using heaters to melt the
snow prior to closing the wall up.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 486 of 1851
10:00 am IMCO crew is continuing to work on mechanical piping inside the chiller room. They set the buffer tank
yesterday. I noted to the crew that the buffer tank was scratched up and will need to be recoated.
12:00 pm IMCO dirt crew is continuing to work on the piping for the false floor basins in at Area 50. I have met
with Kirt to discuss the elevations of the pipes. He has informed me that the pipe elevations will conflict with the
structure concrete of the basins. He is lowering the pipes as much as he can to get the them out of the rebar but
there will be trim bar needed on some of them.
2:00 pm The crew is continuing to work on setting wall panels at Area 40. Steve informed me he will have 3 wall
sections ready this week. The snow slowed down production.
4:00 pm Vale Electric continues to install raceways and gear inside the Electrical room. The more gear they get
installed the more stuff that is in the way of the finishing of the room. It has not been textured nor painted yet. I
have brought this to the attention of IMCO multiple times and also talked to Vale about it. I have been told they
need to continue on with the schedule to meet the March milestone.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 487 of 1851
References
Photos (3)
20240110_094139
Taken on Jan 10, 2024, 9:41 AM MST
Added on Jan 11, 2024, 7:58 AM MST
Added by Chris Johnson
20240110_144838
Taken on Jan 10, 2024, 2:48 PM MST
Added on Jan 11, 2024, 7:58 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 488 of 1851
20240110_130755
Taken on Jan 10, 2024, 1:07 PM MST
Added on Jan 11, 2024, 7:58 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 489 of 1851
Form detail
#287: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Strip Forms, Form Walls
Area 60, Fascia
IMCO, General Crew 6 10 Area 50, Piping
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 14 28
Forms
Location
Form date Jan 9, 2024
Description Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 10, 2024, 8:14 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 490 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 4 Area 50, Batch Concrete
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3 4 Area 40, Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on forming walls at Area 40. It snowed last night and is currently snowing.
The crews are working on melting snow off the rebar in the wall sections they are working on.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 491 of 1851
10:00 am IMCO is continuing to work on the chiller room piping. Vale electric is also onsite working in the
electrical room.
2:00 pm IMCO is starting to batch concrete for a pipe encasement. They are encasing the rest of the drain piping
under Area 50.
4:00 pm IMCO continued to work on mechanical piping in the chiller room along with forming walls at Area 40.
References
Photos (4)
20240109_143041
Taken on Jan 9, 2024, 2:30 PM MST
Added on Jan 10, 2024, 8:13 AM MST
Added by Chris Johnson
20240109_141450
Taken on Jan 9, 2024, 2:14 PM MST
Added on Jan 10, 2024, 8:13 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 492 of 1851
20240109_084204
Taken on Jan 9, 2024, 8:42 AM MST
Added on Jan 10, 2024, 8:13 AM MST
Added by Chris Johnson
20240109_084200
Taken on Jan 9, 2024, 8:42 AM MST
Added on Jan 10, 2024, 8:13 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 493 of 1851
Form detail
#286: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Strip Forms, Form Walls
Area 60, Fascia
IMCO, General Crew 6 10 Area 50, Piping
Area 60, Mechanical Piping in
Chiller room
Vale Electric, Electricians 3 8 Area 60, Electrical
Totals 14 28
Forms
Location
Form date Jan 8, 2024
Description Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 9, 2024, 10:32 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 494 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 4 Area 50, Batch Concrete
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1 10 Area 40, Fly Panels
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3 4 Area 40, Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO is working on striping forms at Area 40. The poured the center wall of the fish lift along with 2
wall sections last Friday. They are also working on forming new walls for placement later this week.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 495 of 1851
1:00 pm IMCO has installed the piping for under the 2 holding basins of Area 50. They have installed the
reinforcement rebar for the pipe encasement. They plan on encasing this line in concrete today to lock it in so they
can continue installing the piping without it moving. I checked with IMCO QC, Jeremy. He said he has double
checked all locations and it is ready for placement.
3:00 pm IMCO has placed 2 CY of pipe encasement to lock in the Area 50 drain piping. IMCO carpenters are
continuing to work on forming walls for a potential placement this Thursday.
4:00 pm IMCO has one carpenter installing the fascia on Area 60. Another crew is continuing to work on
mechanical piping in the chiller room. Vale Electric is continuing to work on installing raceways in the electrical
room.
References
Photos (7)
20240108_143824
Taken on Jan 8, 2024, 2:38 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
20240108_143840
Taken on Jan 8, 2024, 2:38 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 496 of 1851
20240108_143831
Taken on Jan 8, 2024, 2:38 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
20240108_143820
Taken on Jan 8, 2024, 2:38 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 497 of 1851
20240108_142757
Taken on Jan 8, 2024, 2:27 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
20240108_141649
Taken on Jan 8, 2024, 2:16 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 498 of 1851
20240108_141642
Taken on Jan 8, 2024, 2:16 PM MST
Added on Jan 9, 2024, 10:31 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 499 of 1851
Form detail
#285: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Place Concrete
Nations Roofing 5 8 Area 60, Unload Siding
IMCO, General Crew 6 10 Area 40, Batch Concrete
Area 60, Mechanical Piping in
Chiller room
Totals 16 28
Forms
Location
Form date Jan 5, 2024
Description Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 8, 2024, 12:38 PM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 500 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am IMCO is batching concrete for todays placement.
9:30 am I have taken the first test. It was low on air. IMCO dosed the truck with air treatment. I tested again and
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 501 of 1851
all was in spec. IMCO started placing concrete.
10:30 am IMCO is placing concrete. They are placing multiple locations including the center wall for the fish lift,
and 3 separate CJ to CJ wall sections of Area 40. They are placing in lifts. Some metal siding has arrived and IMCO is
unloading it. Nations Roofing is onsite to help with unloading. It also appears they are taking measurements for
the siding of the Hatchery Building.
12:00 pm Jake informed me that Nations Roofing supplier sent the wrong material. They sent material for the
roof but not the siding for Area 30. They plan to start installing the roofing material next week.
1:00 pm IMCO is has completed the concrete placement.
References
Photos (5)
20240105_102704
Taken on Jan 5, 2024, 10:27 AM MST
Added on Jan 8, 2024, 11:53 AM MST
Added by Chris Johnson
20240105_101314
Taken on Jan 5, 2024, 10:13 AM MST
Added on Jan 8, 2024, 11:53 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 502 of 1851
20240105_101050
Taken on Jan 5, 2024, 10:10 AM MST
Added on Jan 8, 2024, 11:53 AM MST
Added by Chris Johnson
20240105_101017
Taken on Jan 5, 2024, 10:10 AM MST
Added on Jan 8, 2024, 11:53 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 503 of 1851
20240105_101013
Taken on Jan 5, 2024, 10:10 AM MST
Added on Jan 8, 2024, 11:53 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 504 of 1851
Form detail
#284: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Area 50, Grading for foundation
Area 60, Exterior Trim
YMC HVAC 3 10 Area 60, HVAC
Totals 6 20
2. Materials
Forms
Location
Form date Jan 2, 2024
Description Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jan 2, 2024, 4:33 PM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 505 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 50, Grading
Kobelco 1100G Crane 1
Bomag Roller 1 10 Area 50, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 50, Import Fill
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:30 am IMCO has a small crew onsite. They are working on grading the foundation for Area 50. Importing
material from the stockpile across the river.
1:30 pm I walked the site checking on progress. They have started the siding around beams. I checked the one
location that is ready for concrete placement. The corner wall at Area 40 in raceway 1. This has the blockout
change per RFI 140. The form savers are installed as well.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 506 of 1851
References
Photos (5)
20240102_124511
Taken on Jan 2, 2024, 12:45 PM MST
Added on Jan 2, 2024, 4:08 PM MST
Added by Chris Johnson
20240102_124439
Taken on Jan 2, 2024, 12:44 PM MST
Added on Jan 2, 2024, 4:08 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 507 of 1851
20240102_124434
Taken on Jan 2, 2024, 12:44 PM MST
Added on Jan 2, 2024, 4:08 PM MST
Added by Chris Johnson
20240102_123132
Taken on Jan 2, 2024, 12:31 PM MST
Added on Jan 2, 2024, 4:08 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 508 of 1851
20240102_123123
Taken on Jan 2, 2024, 12:31 PM MST
Added on Jan 2, 2024, 4:08 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 509 of 1851
Form detail
#283: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 7 Area 40, Wall Forms, Place
Concrete
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 8 10 Area 10, Piping, Pipe Encasement
Area 40, Batch Concrete
Area 60, Piping inside Incubation
room, Fix Door frames
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 20, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 21, 2023, 8:24 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 510 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 35
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 511 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is prepping the batch plant getting ready for concrete placement today. They plan on placing 5
wall sections at Area 40. The may also capture some pipe encasements.
9:00 am Pump truck is onsite and starting to place concrete. I tested the first truck. It was low on air at 4.5%. The
concrete looked very stiff. They added water and also dosed it with more air.
The crew decided to place concrete in the pipe encasement. After the dosing and adding water they poured out
approx. 1.5 CY and I took my second test on the same truck. The air was good at 6.8%. There is only about 1 CY of
concrete left in the truck so I informed the crew I would be testing the second truck. They placed the 1 CY in the
pipe encasement.
10:45 am The second truck came out with 9 CY on. I tested after the crew placed ~1CY in the pipe encasement.
The test was extreme low on air at 4%. They dosed the truck. I tested it again and got 5.6% air. They are going to
start placing in the wall forms.
11:00 am IMCO has a crew working on the chiller room piping.
12:00 pm IMCO is continuing to place concrete.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 512 of 1851
References
Photos (6)
20231220_114227
Taken on Dec 20, 2023, 11:42 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
20231220_114110
Taken on Dec 20, 2023, 11:41 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 513 of 1851
20231220_114103
Taken on Dec 20, 2023, 11:41 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
20231220_114056
Taken on Dec 20, 2023, 11:40 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 514 of 1851
20231220_113133
Taken on Dec 20, 2023, 11:31 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
20231220_113123
Taken on Dec 20, 2023, 11:31 AM MST
Added on Dec 21, 2023, 8:22 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 515 of 1851
Form detail
#282: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 7 Area 40, Wall Forms
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 8 10 Area 10, Piping, Pipe Encasement
Area 60, Piping inside Incubation
room, Fix Door frames
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 19, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 20, 2023, 6:21 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 516 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 35
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, 12" cross crowder channel
line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 6
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 517 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crew is continuing to work in the chiller room. The crew is starting the piping by laying out and
installing the pumps on the housekeeping pads.
9:00 am IMCO carpenters are continuing to set wall forms and bulkheads for Area 40.
11:00 am ACORE is onsite to core drill manholes. IMCO is continuing to layout pumps and mechanical piping for
the chiller room.
1:00 pm IMCO is working on installing the rebar around the 12" cross crowder channel pipe to be concrete
encased.
4:00 pm IMCO is reinstalling the GWB around the doors in the office area after removing them to fix the doors.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 518 of 1851
References
Photos (6)
20231219_143801
Taken on Dec 19, 2023, 2:38 PM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
20231219_102652
Taken on Dec 19, 2023, 10:26 AM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 519 of 1851
20231219_102143
Taken on Dec 19, 2023, 10:21 AM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
20231219_102148
Taken on Dec 19, 2023, 10:21 AM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 520 of 1851
20231219_100840
Taken on Dec 19, 2023, 10:08 AM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
20231219_100834
Taken on Dec 19, 2023, 10:08 AM MST
Added on Dec 19, 2023, 3:37 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 521 of 1851
Form detail
#281: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 7 Area 40, Wall Forms
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 8 10 Area 10, Piping, Pipe Encasement
Area 60, Piping inside Incubation
room, Set Chiller, Fix Door frames
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 18, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 19, 2023, 7:36 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 522 of 1851
Crew # Workers # Total
hours
Work performed
Totals 24 35
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 2 Area 10, Batch Concrete, pipe
encasement
Hitachi 85 Excavator 1 10 Area 10, 12" cross crowder channel
line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 5 Area 40, Concrete
Dump Truck 1 6
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 523 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. I walked the site. At Area 60, IMCO has exposed the door frames by removing GWB,
DenGlass and CMU block. See photos. It looks like the door frames were fixed and ready for doors to be hung.
IMCO has a crew working on the 4" drain line from the Fish lift at Area 10. This line was backfilled last week but
needed to have concrete pipe encasement. IMCO crew has exposed the line and is currently working on installing
the rebar for the concrete. They plan to place this concrete today.
10:30 am IMCO is currently working on setting the chiller on the housekeeping pad in the chiller room of Area 60.
11:00 am IMCO carpenters are working on bulkheads and wall forms at Area 40. They have stripped some of the
walls from last weeks placement.
1:00 pm IMCO is continuing to work on installing the chiller by anchoring it to the housekeeping pad.
4:00 pm The pipe crew has installed the rebar for the pipe encasement. They placed the concrete over the 4"
pipe. They also captured a couple thrust blocks with the same batch.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 524 of 1851
References
Photos (14)
20231218_142411
Taken on Dec 18, 2023, 2:24 PM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_143446
Taken on Dec 18, 2023, 2:34 PM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 525 of 1851
20231218_141737
Taken on Dec 18, 2023, 2:17 PM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_115956
Taken on Dec 18, 2023, 11:59 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 526 of 1851
20231218_115918
Taken on Dec 18, 2023, 11:59 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_113744
Taken on Dec 18, 2023, 11:37 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 527 of 1851
20231218_113720
Taken on Dec 18, 2023, 11:37 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_120925
Taken on Dec 18, 2023, 12:09 PM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 528 of 1851
20231218_143027
Taken on Dec 18, 2023, 2:30 PM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_115952
Taken on Dec 18, 2023, 11:59 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 529 of 1851
20231218_113954
Taken on Dec 18, 2023, 11:39 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_113951
Taken on Dec 18, 2023, 11:39 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 530 of 1851
20231218_113734
Taken on Dec 18, 2023, 11:37 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
20231218_113726
Taken on Dec 18, 2023, 11:37 AM MST
Added on Dec 19, 2023, 7:14 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 531 of 1851
Form detail
#280: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms, Place
Concrete
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 5 10 Area 10, Piping, Batch Concrete,
12" spray bar line
Area 60, Piping inside Incubation
room, Housekeeping equipment
pads
Forms
Location
Form date Dec 14, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 15, 2023, 7:20 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 532 of 1851
Crew # Workers # Total
hours
Work performed
YMC HVAC 3 10 Area 60, HVAC
EOI 2 8 Area 40, Rebar
Totals 23 46
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 5 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, 12" cross crowder channel
line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 5 Area 40, Concrete
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 533 of 1851
Equipment Quantity Hours
used
Comment
Dump Truck 1 6
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is batching concrete for todays placement of the wall sections at Area 40. They also plan to place
housekeeping pads in the chiller room of Area 60.
9:00 am I have tested the first truck. All passed with no issues. They are starting to place concrete walls.
9:30 am IMCO is also placing housekeeping pads in the chiller room.
11:30 am IMCO is batching a clean up truck of 3 yards to complete the pour. I noticed two interior doors were
installing in the hatchery building. Since they were installed after the GWB, tape and texture they had to cut holes
in the sheet rock to install the doors. See photos. The doors are not very sturdy either. The sheet rock is not locked
in behind the frames per the details on GA-6 of the project plans.
12:00 pm Vale Electric is installing the gear inside the electrical room of Area 60. I mentioned to them that it is
going to be very difficult to finish the wall behind the gear (texture and paint). They said they need to continue
installing the gear to stay on track for the March deadline to have the hatchery building complete. IMCO has
completed the concrete placement for the day.
2:00 pm I spoke to Jeremiah from IMCO. He said he would be the one fixing the doors in the hatchery building.
He was aware of my concerns and he is going to be working on fixing them.
4:30 pm IMCO pipe crew has been working on installing the 12" spray bar line from Area 30 to Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 534 of 1851
References
Photos (18)
20231214_153124
Taken on Dec 14, 2023, 3:31 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_152127
Taken on Dec 14, 2023, 3:21 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 535 of 1851
20231214_151444
Taken on Dec 14, 2023, 3:14 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_150230
Taken on Dec 14, 2023, 3:02 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 536 of 1851
20231214_110437
Taken on Dec 14, 2023, 11:04 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_110431
Taken on Dec 14, 2023, 11:04 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 537 of 1851
20231214_110134
Taken on Dec 14, 2023, 11:01 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_092541
Taken on Dec 14, 2023, 9:25 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 538 of 1851
20231214_091617
Taken on Dec 14, 2023, 9:16 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_150314
Taken on Dec 14, 2023, 3:03 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 539 of 1851
20231214_150308
Taken on Dec 14, 2023, 3:03 PM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_110452
Taken on Dec 14, 2023, 11:04 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 540 of 1851
20231214_110443
Taken on Dec 14, 2023, 11:04 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_110427
Taken on Dec 14, 2023, 11:04 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 541 of 1851
20231214_110143
Taken on Dec 14, 2023, 11:01 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_092546
Taken on Dec 14, 2023, 9:25 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 542 of 1851
20231214_092532
Taken on Dec 14, 2023, 9:25 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
20231214_091639
Taken on Dec 14, 2023, 9:16 AM MST
Added on Dec 15, 2023, 7:15 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 543 of 1851
Form detail
#279: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 5 10 Area 10, Piping
Area 60, Piping inside Incubation
room, Housekeeping equipment
pads
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 13, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 14, 2023, 10:04 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 544 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 40, Rebar
Totals 23 46
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, 12" cross crowder channel
line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 5
Dump Truck 1 6
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 545 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on bulkheads and wall forms. They plan to place a few sections of walls
tomorrow. A crew is working on the housekeeping pads in the chiller room. They plan to place those tomorrow as
well. YMC is onsite working on HVAC lines at Area 60 and EOI is onsite working on rebar at Area 40.
9:00 am Left site to return concrete cylinders.
References
Photos (2)
20231213_090448
Taken on Dec 13, 2023, 9:04 AM MST
Added on Dec 14, 2023, 9:59 AM MST
Added by Chris Johnson
20231213_090356
Taken on Dec 13, 2023, 9:03 AM MST
Added on Dec 14, 2023, 9:59 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 546 of 1851
Form detail
#278: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms, Place
concrete
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 5 10 Area 10, Piping
Area 60, Piping inside Incubation
room, Housekeeping equipment
pads
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 12, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 13, 2023, 7:21 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 547 of 1851
Crew # Workers # Total
hours
Work performed
Totals 21 38
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, 12" cross crowder channel
line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 5 Area 40, Concrete
Dump Truck 1 6
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 548 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is prepping to place concrete today at Area 40. They have 4 wall sections ready for placement.
9:00 am IMCO has batched their first truck. I took my sample from the end of the pump after they pumped out
approx. 1 CY. All passed with no issues. They are starting to place the concrete in the forms.
10:00 am Vale is onsite installing electrical gear in the electrical room of Area 60. IMCO is continuing to place
concrete. They are also continuing to form walls and bulkheads.
11:30 am IMCO has completed the concrete placement for the day. They were able to capture 4 wall sections and
a thrust block for the piping. They are going to continue working on bulkheads and wall forming for the next
placement.
2:00 pm IMCO has a crew working on installing the incubation piping in the incubation room. I spoke to the crew
about ensuring the pipes are clean on the inside before installing them. I wasnt sure how IMCO would clean them
after install. There is another crew working on installing the housekeeping pads in the chiller room. The forming
looks to be complete. They are now working on the rebar for the pads.
4:00 pm IMCO has installed another raceway gate. They are continuing to work on wall forming. The pipe crew
has started to install the 12" cross crowder line from Area 30 to the valve vault.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 549 of 1851
References
Photos (6)
20231212_110018
Taken on Dec 12, 2023, 11:00 AM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
20231212_161218
Taken on Dec 12, 2023, 4:12 PM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 550 of 1851
20231212_161213
Taken on Dec 12, 2023, 4:12 PM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
20231212_150312
Taken on Dec 12, 2023, 3:03 PM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 551 of 1851
20231212_144907
Taken on Dec 12, 2023, 2:49 PM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
20231212_144634
Taken on Dec 12, 2023, 2:46 PM MST
Added on Dec 13, 2023, 7:11 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 552 of 1851
Form detail
#277: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms
Vale Electric 3 8 Area 60 Electrical
IMCO, General Crew 5 10 Area 10, Piping
Area 60, Piping inside Incubation
room
YMC HVAC 3 10 Area 60, HVAC
Forms
Location
Form date Dec 11, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 12, 2023, 6:41 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 553 of 1851
Crew # Workers # Total
hours
Work performed
Totals 21 38
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 10
Hitachi 85 Excavator 1 10 Area 10, 4" drain line
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 10
Dump Truck 1 6
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 554 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is onsite working on wall forms at Area 40. Steve informed me he plans to place 4 maybe 5 wall
sections on Tuesday. I reviewed the wall sections they placed last week. Some are covered up with plastic still but
the sections I did see showed some areas that need attention. The areas were minor but I brought these to Steves
attention. See photos.
11:00 am IMCO pipe crew is currently working on installing the 4 inch drain line from the fish lift to MH 2.
1:00 pm The drywall crew finished the texturing last week. They sprayed an orange peel texture on all the ceilings
and the walls. IMCO has a crew in the chiller room laying out the housekeeping pads for the equipment. They
informed me they hope to place these pads by end of the week.
2:00 pm IMCO has a crew inside the incubation room working on the piping. The CMU crew finished last week.
The pipe crew is working on backfilling the 4" drain line from the fish lift to MH 2. I noticed they backfilled sections
that will be under the building footprint of Area 50. I asked Jake if that should be incased in concrete like the other
piping across the job. He said it probably should be and he will talk to Kirt about it.
4:00 pm IMCO is continuing to set bulkheads and wall forms at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 555 of 1851
References
Photos (9)
20231211_112051
Taken on Dec 11, 2023, 11:20 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
20231211_111001
Taken on Dec 11, 2023, 11:10 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 556 of 1851
20231211_110420
Taken on Dec 11, 2023, 11:04 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
20231211_110406
Taken on Dec 11, 2023, 11:04 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 557 of 1851
20231211_110335
Taken on Dec 11, 2023, 11:03 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
20231211_110138
Taken on Dec 11, 2023, 11:01 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 558 of 1851
20231211_110120
Taken on Dec 11, 2023, 11:01 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
20231211_153121
Taken on Dec 11, 2023, 3:31 PM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 559 of 1851
20231211_110958
Taken on Dec 11, 2023, 11:09 AM MST
Added on Dec 12, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 560 of 1851
Form detail
#276: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms
Vale Electric 2 8
IMCO, General Crew 5 10 Area 10, Piping
Area 60, Begin Piping inside
Incubation room
Basin Masonary 6 10 Area 60, CMU Masonry
Forms
Location
Form date Dec 6, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 7, 2023, 6:44 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 561 of 1851
Crew # Workers # Total
hours
Work performed
JC Drywall 6 10 Area 60, GWB, Taping
EOI 3 10 Area 40, Wall Rebar
Totals 32 58
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 10
Hitachi 85 Excavator 1 10
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10
Dump Truck 1 6
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 562 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on bulkheads for the next wall placements at Area 40. EOI is onsite
continuing to install wall rebar ahead of the carpenters.
9:00 am The mason crew is working on the CMU install inside the incubation room at Area 60. JC Drywall is onsite
to continue taping and mudding the seams of the GWB at Area 60. IMCO has been keeping heat blowing in the
building to achieve above 50 degree temps per the manufacture recommendations for the drywall mud. They also
have heat blowing in the incubation room for the masons. They are continuing to move heaters around to provide
heat in the other rooms to keep up with JC Drywall.
11:00 am The carpenter crew is continuing to work on bulkheads and installing the spray bar penetrations. JC
Drywall is continuing to tape the seams and screw holes on the DenGlass and GWB. Nations Roofing is onsite
working on installing the rest of the ice shield on the roof of Area 60. IMCO pipe crew is working on some HDPE
installation for the spray bar line.
12:00 pm Leaving site to return cylinders from yesterdays placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 563 of 1851
References
Photos (5)
20231206_103534
Taken on Dec 6, 2023, 10:35 AM MST
Added on Dec 7, 2023, 6:39 AM MST
Added by Chris Johnson
20231206_102124
Taken on Dec 6, 2023, 10:21 AM MST
Added on Dec 7, 2023, 6:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 564 of 1851
20231206_102122
Taken on Dec 6, 2023, 10:21 AM MST
Added on Dec 7, 2023, 6:39 AM MST
Added by Chris Johnson
20231206_080029
Taken on Dec 6, 2023, 8:00 AM MST
Added on Dec 7, 2023, 6:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 565 of 1851
20231206_080027
Taken on Dec 6, 2023, 8:00 AM MST
Added on Dec 7, 2023, 6:39 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 566 of 1851
Form detail
#275: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 10 10 Area 40, Wall Forms, Place
Concrete
Vale Electric 2 8
IMCO, General Crew 5 10 Area 60, Install partition walls
Area 40, Batch Concrete
Basin Masonary 6 10 Area 60, CMU Masonry
Forms
Location
Form date Dec 5, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 6, 2023, 7:26 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 567 of 1851
Crew # Workers # Total
hours
Work performed
JC Drywall 6 10 Area 60, GWB, Taping
EOI 3 10 Area 40, Wall Rebar
Totals 32 58
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10 Batch Concrete
Dump Truck 1 6
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 568 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is prepping to place concrete today at Area 10 and Area 40. They plan to place two retaining wall
sections near the hatchery building along with 4 raceway walls at Area 40.
8:00 am Pump truck is onsite. IMCO is starting to batch concrete.
9:00 am I have taken my first test. The concrete was low on air at 4.3%, by request I also tested the slump which
was 7 1/4". They dosed the truck and mixed it longer. I took my second test from the same truck. It was at 5.5% air
and 5 1/2" slump. They started to place concrete in the retaining walls behind Area 60.
10:00 am JC Drywall is onsite to tape the seams of the GWB in Area 60. They are installing ceiling GWB in the office
area as well. IMCO crew is installing the partitions in the office area to be drywalled as well. The crew is continuing
to place concrete in the retaining walls.
12:00 pm IMCO has started placing walls at Area 40. The masons have started placing CMU block inside the
incubation room. They have one wall to finish. IMCO has taken the overhead door down so the door can mount to
the CMU per plan. IMCO has heat running into the room for the mortar.
2:00 pm IMCO has completed the placement for today. All went well with no issues. EOI is onsite today installing
wall rebar at Area 40.
4:00 pm IMCO is continuing to install bulkheads for the next wall placements. JC Drywall has been working on
ceiling GWB in the office area along with mudding the seams and screw holes.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 569 of 1851
References
Photos (7)
20231205_094903
Taken on Dec 5, 2023, 9:49 AM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
20231205_133006
Taken on Dec 5, 2023, 1:30 PM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 570 of 1851
20231205_130558
Taken on Dec 5, 2023, 1:05 PM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
20231205_103247
Taken on Dec 5, 2023, 10:32 AM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 571 of 1851
20231205_094243
Taken on Dec 5, 2023, 9:42 AM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
20231205_150117
Taken on Dec 5, 2023, 3:01 PM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 572 of 1851
20231205_094411
Taken on Dec 5, 2023, 9:44 AM MST
Added on Dec 6, 2023, 6:32 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 573 of 1851
Form detail
#274: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Wall Forms
Vale Electric 2 8
IMCO, General Crew 5 10 Area 60, Finish HDs and anchor
bolts, Build Soffit for cabinets
Area 10, Irrigation Tank install
Basin Masonary 6 10 Area 60, Exterior Masonry
Forms
Location
Form date Dec 4, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 5, 2023, 12:27 PM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 574 of 1851
Crew # Workers # Total
hours
Work performed
JC Drywall 6 10 Area 60, GWB, Taping
Totals 27 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10
Hitachi 85 Excavator 1 10
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 6
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 575 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. Jake contacted me in route to check on my ETA. He is looking to get the hold downs
approved for completion. The taping crew is here to start taping the drywall at Area 60. As I walked the building
with Jake checking on the HDs we discovered a few that were not installed or were missing nuts and a few that
were not tightened. They are working on fixing them as we find them.
I noticed water on the concrete near the front door of the office area. I looked up and there was puddled water on
the vapor barrier for the ceiling. I mentioned this to Jake as he was standing there with me. I voiced my concern
with him regarding water ruining drywall or insulation. I told him I have a concern that if there is water damage it
could be difficult to see its extent with the drywall being installed.
I walked the incubation room where the CMU block has been completed. I pointed out to Jake a few issues I seen.
The reveal around the interior doors changes from bottom of the door to top of the door. The clips to secure the
door were not used, assuming because the door was installed post CMU installation. I also noticed some large
notches in the block where electrical conduit penetrates the block.
We then walked into the electrical room. As we were checking on HDs I noticed water inside the vapor barrier on
the corner of the room. The 2x was wet to the touch. It was a small gap between the DensGlass sheathing that I
am attempting to see through. See pictures.
I notified Zack of these issues.
1:00 pm Jake informed me they are working on the hold downs. JC drywall is onsite prepping to tape the seams of
the drywall. The masons are onsite working on the exterior stone.
2:00 pm IMCO general crew is continuing to get wall forms ready at Area 40. They plan on placing tomorrow.
They have 2 retaining wall sections ready for placement near Area 60 that they will place tomorrow with the Area
40 wall placement. The crew is prepping to install a gate for raceway 3.
4:00 pm Walked the hatchery building with Jake to perform a final on the hold downs. They were all complete. JC
Drywall is installing the drywall that was left off for the hold down installation.
4:30 pm IMCO installed the gate to raceway 3. They are continuing to work on wall forms at Area 40. I noticed
IMCO has is placing plastic on the roof of Area 60. The build outs on the building did not have any ice shield on it.
They are placing plastic where there is no ice shield.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 576 of 1851
References
Photos (17)
20231204_153153
Taken on Dec 4, 2023, 3:31 PM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_135047
Taken on Dec 4, 2023, 1:50 PM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 577 of 1851
20231204_133734
Taken on Dec 4, 2023, 1:37 PM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_110626
Taken on Dec 4, 2023, 11:06 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 578 of 1851
20231204_110601
Taken on Dec 4, 2023, 11:04 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_105528
Taken on Dec 4, 2023, 10:55 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 579 of 1851
20231204_104435
Taken on Dec 4, 2023, 10:44 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_104429
Taken on Dec 4, 2023, 10:44 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 580 of 1851
20231204_104426
Taken on Dec 4, 2023, 10:44 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_103217
Taken on Dec 4, 2023, 10:32 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 581 of 1851
20231204_103158
Taken on Dec 4, 2023, 10:31 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_110456
Taken on Dec 4, 2023, 11:04 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 582 of 1851
20231204_105539
Taken on Dec 4, 2023, 10:55 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_104322
Taken on Dec 4, 2023, 10:43 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 583 of 1851
20231204_103926
Taken on Dec 4, 2023, 10:39 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_103919
Taken on Dec 4, 2023, 10:39 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
20231204_103212
Taken on Dec 4, 2023, 10:32 AM MST
Added on Dec 5, 2023, 7:30 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 584 of 1851
Form detail
#273: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Wall Forms
Vale Electric 2 8 Area 20, Conduit for river sensor
Area 60, wiring
IMCO, General Crew 5 10 Area 10, Retaining wall placement
Basin Masonary 6 10 Area 60, Interior Masonry
JC Drywall 4 10 Area 60, GWB
Forms
Location
Form date Nov 30, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 4, 2023, 11:26 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 585 of 1851
Crew # Workers # Total
hours
Work performed
Totals 25 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, Backfill, load quarry spalls
Hitachi 85 Excavator 1 10 Area 10, Backfill Retaining Wall
Kobelco 1100G Crane 1 10 Area 40, fly wall panels, Set gate
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 6 Area 10, Import Quarry spalls
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 586 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to continue setting wall forms today. In the morning meeting I was asked when they could
strip the forms. I informed the crew, including Kirt and Jake, the requirement is 48 hours for stripping and 72 hours
for cold weather protection which requires the surface of the concrete to be above 50 degrees. I also suggested
that the temperature drop for the first 24 hours after the 72 hour protection should not drop dramatically (no
more than 40 degrees) per ACI 306.
9:00 am I walked the site. I noticed the crews moving heaters around. Steve informed me he would be checking
temperatures 3 times a day on the concrete surface. He also said he would be recording the temperatures. They
are working on filling them up with diesel now. I was informed that the heater was removed from the incubation
room last night to heat the retaining walls. I was told the 2 new heaters that were delivered yesterday were not
setup correctly so they could not use them last night. This means the incubation room CMU that was installed
yesterday when through the night without heat. I check the surface temperature of the mortar in the room. It
showed 24 degrees. This is well below the specifications. I informed Jake of the deficiency and I informed Zack of
the issue.
10:00 am IMCO is continuing to work on setting wall forms at Area 40. I also noticed they were setting up to
install grout under the raceway gate that they set yesterday. I informed the crew the metal needs to be above
freezing and the grout they mix needs to be within the specifications of the manufacture. There is a crew working
on backfilling the retaining wall behind Area 60.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 587 of 1851
References
Photos (12)
20231130_105417
Taken on Nov 30, 2023, 10:54 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_103052
Taken on Nov 30, 2023, 10:30 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 588 of 1851
20231130_102939
Taken on Nov 30, 2023, 10:29 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_084909
Taken on Nov 30, 2023, 8:49 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 589 of 1851
20231130_084648
Taken on Nov 30, 2023, 8:46 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_084644
Taken on Nov 30, 2023, 8:46 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 590 of 1851
20231130_084632
Taken on Nov 30, 2023, 8:46 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_084624
Taken on Nov 30, 2023, 8:46 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 591 of 1851
20231130_084620
Taken on Nov 30, 2023, 8:46 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_084504
Taken on Nov 30, 2023, 8:45 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 592 of 1851
20231130_084455
Taken on Nov 30, 2023, 8:44 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
20231130_083449
Taken on Nov 30, 2023, 8:34 AM MST
Added on Dec 4, 2023, 11:24 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 593 of 1851
Form detail
#272: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Wall Forms
Vale Electric 2 8 Area 20, Conduit for river sensor
Area 60, wiring
IMCO, General Crew 5 10 Area 10, Retaining wall placement
Basin Masonary 6 10 Area 60, Interior Masonry
JC Drywall 4 10 Area 60, GWB
Forms
Location
Form date Nov 29, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 29, 2023, 6:11 PM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 594 of 1851
Crew # Workers # Total
hours
Work performed
Totals 25 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, Backfill, load quarry spalls
Hitachi 85 Excavator 1 10 Area 10, Backfill Retaining Wall
Kobelco 1100G Crane 1 10 Area 40, fly wall panels, Set gate
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 6 Area 10, Import Quarry spalls
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 595 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am Ryan informed me that he laid out the missing HDs in Area 60 ahead of the drywall crew. He said they
worked on drilling some of them last night. After the sun comes up we will walk it together.
8:30 am After walking Area 60 Hold downs, Many were still missing along with some of the drywall being
installed. They will have to remove drywall to finish the punch list items of the framing. I walked the site to check
concrete temperatures from yesterdays placement. I noticed right away that the retaining wall placements were
only partially covered last night with insulated blankets. This is a deficiency in the cold weather concrete
placement. I checked the temperature of the outside of the forms. The average was ~32 degrees. It is unknown
what the internal temperature of the concrete is due to lack of internal thermometers.
9:00 am The drywall crew installed the cement board ceiling inside the incubation room yesterday. The block sub
contractor is starting to work on installing CMU block inside the incubation room. I informed IMCO they are still
missing structural HDs inside this room. The overhead door also needs to be removed so the block can be
installed. IMCO did run heaters on the Area 40 walls last night to prevent the concrete from dropping below 50
degrees.
1:00 pm IMCO is currently working on installing the second raceway gate at Area 40. IMCO has notified me that
all the HDs are complete and ready for inspection. We walked Area 60 again. I found multiple HDs that were not
installed or missing nuts. The block crew is continuing to install CMU blocking. I pointed out to IMCO that the CMU
block is not sitting flush with the concrete curb and a small lip is visible in some locations. Ryan informed me he
would talk to Kirt and come up with a solution. The drywall crew is also continuing to install GWB on the ceiling.
They are staying away from the bottom to allow IMCO to fix the HDs.
2:00 pm IMCO has been working on backfilling the retaining wall behind Area 60. They are using drain rock
around the perforated pipe. They are importing quarry spalls to the section above the pipe.
3:00 pm IMCO is getting a heater setup for the retaining wall sections. I checked the temperature of the outside
forms to compare to earlier today. They averaged ~48 degrees. This have been ~28 hours of cold weather
placement deficiency.
4:00 pm IMCO carpenters are continuing to install wall forms in preparation for the next Area 40 wall placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 596 of 1851
References
Photos (15)
20231129_143152
Taken on Nov 29, 2023, 2:31 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_142456
Taken on Nov 29, 2023, 2:24 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 597 of 1851
20231129_142446
Taken on Nov 29, 2023, 2:24 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_140438
Taken on Nov 29, 2023, 2:04 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 598 of 1851
20231129_124407
Taken on Nov 29, 2023, 12:44 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_124123
Taken on Nov 29, 2023, 12:41 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 599 of 1851
20231129_124111
Taken on Nov 29, 2023, 12:41 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_123850
Taken on Nov 29, 2023, 12:38 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 600 of 1851
20231129_083840
Taken on Nov 29, 2023, 8:38 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_083715
Taken on Nov 29, 2023, 8:37 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 601 of 1851
20231129_083711
Taken on Nov 29, 2023, 8:37 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_081712
Taken on Nov 29, 2023, 8:17 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 602 of 1851
20231129_140448
Taken on Nov 29, 2023, 2:04 PM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
20231129_083831
Taken on Nov 29, 2023, 8:38 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 603 of 1851
20231129_081719
Taken on Nov 29, 2023, 8:17 AM MST
Added on Nov 29, 2023, 3:17 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 604 of 1851
Form detail
#271: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Concrete placement
Vale Electric 2 8 Area 20, Conduit for river sensor
Area 60, wiring
IMCO, General Crew 5 10 Area 40 Batch Concrete
Basin Masonary 6 10 Area 60, Exterior Masonry
JC Drywall 4 4 Area 60, Ceiling durarock
Forms
Location
Form date Nov 28, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 29, 2023, 7:42 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 605 of 1851
Crew # Workers # Total
hours
Work performed
Totals 25 42
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, Backfill Retaining Wall
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10 Area 40, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 606 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is planning to place concrete today at 4 locations. Two retaining wall sections and 2 holding facility
wall sections. The current temp outside is ~20 degrees. I did not see any heaters on the forms/ rebar. I asked Ryan
if he could look into it.
8:30 am I noticed the pump truck onsite and getting setup. I still do not see any heaters on the forms/ rebar. I
went and talked with IMCO regarding the heaters. I referenced the spec which refer to ACI 306.
9:30 am IMCO is batching concrete. The water lines are frozen and they are getting it all thawed out. They have
placed a heater on the retaining wall sections to warm up the rebar and forms.
10:00 am IMCO has batched 4.5 CY. As they were priming the pump it was determined that the concrete was
below the spec of temp at 50 degrees. The concrete was coming out of the truck at ~44 degrees. After some
discussion with Zack and IMCO it was determined to adhere to the specifications of 50 degrees minimum. They are
dumping the concrete in the washout.
11:00 am I have taken my second test. The air was low so they dosed the truck and I took a second test. The
second test passed with no issues. The concrete temp was at 57 degrees. IMCO is starting to place concrete in the
retaining wall forms.
12:00 pm IMCO is continuing to place concrete at the retaining wall. The block sub contractor is continuing to
install the block to the exterior of the hatchery building. They are working under a tent with a heater.
12:30 pm IMCO has moved the heater to the holding facility wall forms after I checked the temperatures of the
rebar and forms. They were ~25 degrees. They are heating the forms now.
1:00 pm IMCO is moving to placing the holding facility walls. They have completed the retaining wall placement.
Attended weekly meeting.
2:00 pm While placing the wall sections at Area 40, a form started to blow out. I notified Steve who was on the
scaffolding. He immediately stopped placing. They moved the pump to the other wall while the crew started
working on reinforcing the forms where they started to fail.
3:00 pm IMCO crew was able to push the forms back in to within 3/4". Steve notified me they were not able to get
it back in so they will be grinding it after they remove the forms.
3:30 pm IMCO has completed the placement.
4:30 pm While they were placing concrete the operator crew set the irrigation tank. They have it secured with a
strap for now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 607 of 1851
References
Photos (14)
20231128_155542
Taken on Nov 28, 2023, 3:55 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_143706
Taken on Nov 28, 2023, 2:37 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 608 of 1851
20231128_143656
Taken on Nov 28, 2023, 2:36 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_140442
Taken on Nov 28, 2023, 2:04 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 609 of 1851
20231128_121239
Taken on Nov 28, 2023, 12:12 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_113008
Taken on Nov 28, 2023, 11:30 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 610 of 1851
20231128_113004
Taken on Nov 28, 2023, 11:30 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_112717
Taken on Nov 28, 2023, 11:27 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 611 of 1851
20231128_112714
Taken on Nov 28, 2023, 11:27 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_112732
Taken on Nov 28, 2023, 11:27 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 612 of 1851
20231128_155531
Taken on Nov 28, 2023, 3:55 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_141314
Taken on Nov 28, 2023, 2:13 PM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 613 of 1851
20231128_112409
Taken on Nov 28, 2023, 11:24 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
20231128_112401
Taken on Nov 28, 2023, 11:24 AM MST
Added on Nov 29, 2023, 7:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 614 of 1851
Form detail
#270: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Set Wall Forms
Vale Electric 2 8 Area 20, Conduit for river sensor
Area 60, wiring
IMCO, General Crew 5 10 Area 10 Backfill Retaining Wall
Basin Masonary 6 10 Area 60, Exterior Masonry
Totals 21 38
Forms
Location
Form date Nov 27, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 28, 2023, 7:46 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 615 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Backfill Retaining Wall
Kobelco 1100G Crane 1 10 Area 40, fly wall panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Quarry Spalls
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO is continuing to place wall forms in preparation for a placement tomorrow at Area 40.
1:00 pm They have stripped the forms from last weeks wall placement. There are many deficiencies in the wall
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 616 of 1851
finish. They used a form liner (1/4 Masonite Panels) in an attempt to create a smooth finish. The panels swelled
which created many dimples and lines in the concrete finish. See pictures. IMCO is no longer using the liner. I also
noticed two areas of unconsolidated concrete. See pictures.
2:00 pm The masonry contractor has been onsite working. They are continuing to install block on the hatchery
building. They are working under tented plastic with a heater running. Zack and I spoke to Jake regarding the
deficiencies in the concrete walls. He said they would sack and patch the entire wall along with fixing any issues
with it. Zack and I also expressed concern with the tolerance for the crowder.
4:00 pm IMCO is importing quarry spalls for the backfill of the retaining wall. The carpenter crew is continuing to
close up the forms for tomorrows wall placement.
References
Photos (17)
20231127_125136
Taken on Nov 27, 2023, 12:51 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_130034
Taken on Nov 27, 2023, 1:00 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 617 of 1851
20231127_125917
Taken on Nov 27, 2023, 12:59 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125715
Taken on Nov 27, 2023, 12:57 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 618 of 1851
20231127_125645
Taken on Nov 27, 2023, 12:56 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125637
Taken on Nov 27, 2023, 12:56 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 619 of 1851
20231127_125625
Taken on Nov 27, 2023, 12:56 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125620
Taken on Nov 27, 2023, 12:56 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 620 of 1851
20231127_125606
Taken on Nov 27, 2023, 12:56 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125558
Taken on Nov 27, 2023, 12:55 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 621 of 1851
20231127_125552
Taken on Nov 27, 2023, 12:55 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125445
Taken on Nov 27, 2023, 12:54 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 622 of 1851
20231127_125428
Taken on Nov 27, 2023, 12:54 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_125132
Taken on Nov 27, 2023, 12:51 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 623 of 1851
20231127_124845
Taken on Nov 27, 2023, 12:48 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
20231127_124831
Taken on Nov 27, 2023, 12:48 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 624 of 1851
20231127_124827
Taken on Nov 27, 2023, 12:48 PM MST
Added on Nov 28, 2023, 7:45 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 625 of 1851
Form detail
#269: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Place
concrete
Vale Electric 2 8 Area 20, Conduit for river sensor
Area 60, wiring
IMCO, General Crew 5 10 Area 40 batch concrete
Forms
Location
Form date Nov 21, 2023
Description Area, 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 22, 2023, 6:54 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 626 of 1851
Crew # Workers # Total
hours
Work performed
Basin Masonary 6 10 Area 60, Exterior Masonry
Totals 23 46
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, unload rebar, fly wall
panels
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 627 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is getting the batch plant fired up and starting to batch concrete.
8:00 am IMCO plans to place 2 wall sections at Area 40. They also will place the 2nd fish lift wall and the irrigation
tank pad.
8:30 am I have taken my first test. The air was too low. They dosed the truck and I tested again. It passed.
9:30 am The second truck is finally batched. I tested it. It was also low on air. They dosed it and I tested it again. It
passed with the low of 5%. I advised Ryan to add more air to the future trucks. They are placing all three walls in
lifts.
10:00 am The masons are onsite working on scratch coat at Area 60. I advised IMCO they should have the soffit
material installed along with the gable end vents prior to the block being installed. Jake agreed.
11:00 am The masons have installed the scratch coat at multiple locations around the building. I noticed they
were using a weed burner in an attempt to dry out the scratch coat so they could start installing the block. I
notified IMCO of this action. Kirt and Jake both said they would go talk to them.
12:00 pm IMCO has completed the wall placements and is working on the Irrigation tank pad.
3:00 pm IMCO is starting to set more panels for the next wall placement at Area 40. Idaho Insulation is onsite
installing insulation in Area 40. IMCO still has not installed all the HDs. I informed Jake Self, IMCO, that he will need
to now remove insulation and vapor barrier to exposed the HDs to provide evidence that they are installed. Many
of them still need to be installed and IMCO did not document which ones are still needed.
3:30 pm IMCO was about to close up some forms for the next area 40 wall placement. While the crane was about
to set the forms I asked Steve if they got all the trim bar installed around the blockouts for the spray bars along
with the shroud. Steve asked his crew and it was determined that they missed some. The crane put the wall forms
back down and the team went to work on finding the proper bent bar to be installed.
4:30 pm The masons are still working. In review of the mortar they are using, it shall be protected from freezing
and for best performance should not be used below 40 degrees. I advised IMCO they need to protect all mortar
from getting below 40 degrees. They said they would tent it and get heaters over to them. IMCO has installed the
proper bent trim bar around the blockout.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 628 of 1851
References
Photos (15)
20231121_110618
Taken on Nov 21, 2023, 11:06 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_100630
Taken on Nov 21, 2023, 10:06 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 629 of 1851
20231121_095842
Taken on Nov 21, 2023, 9:58 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_160155
Taken on Nov 21, 2023, 4:01 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 630 of 1851
20231121_151156
Taken on Nov 21, 2023, 3:11 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_150849
Taken on Nov 21, 2023, 3:08 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 631 of 1851
20231121_150748
Taken on Nov 21, 2023, 3:07 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_150725
Taken on Nov 21, 2023, 3:07 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 632 of 1851
20231121_150712
Taken on Nov 21, 2023, 3:07 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_145637
Taken on Nov 21, 2023, 2:56 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 633 of 1851
20231121_121311
Taken on Nov 21, 2023, 12:13 PM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_100635
Taken on Nov 21, 2023, 10:06 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 634 of 1851
20231121_100018
Taken on Nov 21, 2023, 10:00 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
20231121_095909
Taken on Nov 21, 2023, 9:59 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 635 of 1851
20231121_095839
Taken on Nov 21, 2023, 9:58 AM MST
Added on Nov 22, 2023, 6:51 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 636 of 1851
Form detail
#268: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Form
Retaining walls, Strip Forms
Vale Electric 2 8 Area 40, Conduit for Gates
IMCO, General Crew 5 10 Area 10 CDF Primary Power
Basin Masonary 6 10 Area 60, Exterior Masonry
Forms
Location
Form date Nov 20, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 21, 2023, 7:27 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 637 of 1851
Crew # Workers # Total
hours
Work performed
Totals 23 46
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 638 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is continuing to work on wall forms at Area 40. Jake informed me they would like to accelerate
their schedule and have a concrete placement tomorrow for the walls. They would also include the irrigation tank.
11:00 am IMCO is starting to place CDF over the feeder conduit from the new power supply's per IPC directive.
2:00 pm IMCO has placed the CDF for the primary power lines. Basin Masonry has been onsite today working on
installing the block masonry to the exterior of Area 60.
3:00 pm EOI has been onsite installing rebar for the retaining wall behind Area 60. I am told the irrigation tank
rebar is installed and ready for inspection. They plan to place the irrigation pad tomorrow.
4:30 pm IMCO is ready to place the fish lift, raceway walls and the irrigation tank foundation tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 639 of 1851
References
Photos (10)
20231120_154535
Taken on Nov 20, 2023, 3:45 PM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
20231120_144016
Taken on Nov 20, 2023, 2:40 PM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 640 of 1851
20231120_122050
Taken on Nov 20, 2023, 12:20 PM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
20231120_112515
Taken on Nov 20, 2023, 11:25 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 641 of 1851
20231120_111748
Taken on Nov 20, 2023, 11:17 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
20231120_111743
Taken on Nov 20, 2023, 11:17 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 642 of 1851
20231120_110200
Taken on Nov 20, 2023, 11:02 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
20231120_110155
Taken on Nov 20, 2023, 11:01 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 643 of 1851
20231120_110150
Taken on Nov 20, 2023, 11:01 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
20231120_105134
Taken on Nov 20, 2023, 10:51 AM MST
Added on Nov 21, 2023, 7:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 644 of 1851
Form detail
#267: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 40, Set Wall forms
IMCO, General Crew 1 10 Area 40, Set wall forms
Totals 9 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Nov 17, 2023
Description Area 40
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 20, 2023, 10:46 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 645 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site, Set
Forms
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
12:00 pm IMCO is onsite working on wall forms at Area 40. Left site to return concrete cylinders.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 646 of 1851
Form detail
#266: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Form
Retaining walls, Strip Forms, Install
Windows and Doors
Vale Electric 3 8 Area 60
IMCO, General Crew 5 10 Area 10 Excavation for Primary
Power, Irrigation Tank Removal
Forms
Location
Form date Nov 16, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 20, 2023, 10:43 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 647 of 1851
Crew # Workers # Total
hours
Work performed
Totals 18 36
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill Site
Deere 644J Loader 1 8 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, Excavate trench for
primary power
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3 8 Area 40, Concrete
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 648 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is starting to batch concrete. They are going to place 2 retaining wall sections along with the first
of the fish lift walls.
8:30 am I have taken my first test. It tested at 6.9% air. I informed Ryan and Kole they can place the concrete but
need to make adjustments to do the proximity of being out of spec. I told them i would be testing the second truck
as well.
9:00 am I have taken my second test. All passed with no issues.
12:00 pm IPC Line crew is working on finishing up the new pole install for the Oxbow feed. IMCO is finishing up
the concrete placement and starting to work on wall forms at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 649 of 1851
References
Photos (9)
20231116_120328
Taken on Nov 16, 2023, 12:03 PM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
20231116_110816
Taken on Nov 16, 2023, 11:08 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 650 of 1851
20231116_110651
Taken on Nov 16, 2023, 11:06 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
20231116_102139
Taken on Nov 16, 2023, 10:21 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 651 of 1851
20231116_075952
Taken on Nov 16, 2023, 7:59 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
20231116_075948
Taken on Nov 16, 2023, 7:59 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 652 of 1851
20231116_075944
Taken on Nov 16, 2023, 7:59 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
20231116_114408
Taken on Nov 16, 2023, 11:44 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 653 of 1851
20231116_100711
Taken on Nov 16, 2023, 10:07 AM MST
Added on Nov 20, 2023, 10:38 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 654 of 1851
Form detail
#265: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Form
Retaining walls, Strip Forms, Install
Windows and Doors
Vale Electric 3 8 Area 60
IMCO, General Crew 5 10 Area 10 Excavation for Primary
Power, Irrigation Tank Removal
Forms
Location
Form date Nov 15, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 16, 2023, 6:42 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 655 of 1851
Crew # Workers # Total
hours
Work performed
Totals 18 36
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill Site
Deere 644J Loader 1 8 Area 10, Irrigation Tank Removal
Hitachi 85 Excavator 1 10 Area 10, Excavate trench for
primary power
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 656 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is prepping to remove the irrigation tank. They are waiting on IPC to arrive on site to being the
power outage of the power lines.
9:00 am IPC is onsite and going to kill the power starting the outage. IMCO is continuing to work on excavating
the trench for the power feed to the transformers. The IPC crew is onsite to install the conduit and poles.
11:00 am IMCO has removed the irrigation tank and hauled it down onsite. They will smash up the tank and load
it in a metal bin to be recycled. IPC crew is starting to install conduit in the trench that is excavated.
12:00 pm IMCO carpenters are continuing to work on bulkheads and waterstop at Area 40. Another crew is
working on the retaining wall behind Area 60. They have finished the forming of the fish lift. It is ready for a
placement tomorrow.
2:00 pm EOI has been onsite working on wall rebar at Area 40. Vale is also onsite working inside Area 60.
4:00 pm IMCO is continuing to work on excavating the trench for the IPC crew. The IPC crew will be onsite again
tomorrow to set the pole and install the rest of the conduit.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 657 of 1851
References
Photos (6)
20231115_133727
Taken on Nov 15, 2023, 1:37 PM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
20231115_100205
Taken on Nov 15, 2023, 10:02 AM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 658 of 1851
20231115_082251
Taken on Nov 15, 2023, 8:22 AM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
20231115_135340
Taken on Nov 15, 2023, 1:53 PM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 659 of 1851
20231115_133139
Taken on Nov 15, 2023, 1:31 PM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
20231115_092127
Taken on Nov 15, 2023, 9:21 AM MST
Added on Nov 16, 2023, 6:41 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 660 of 1851
Form detail
#264: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Form
Retaining walls, Strip Forms, Install
Windows and Doors
Vale Electric 5 8 Area 60
IMCO, General Crew 5 10 Area 10 Backfill Site, Start
excavation for Primary Power
Forms
Location
Form date Nov 14, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 15, 2023, 9:04 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 661 of 1851
Crew # Workers # Total
hours
Work performed
Totals 21 36
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill Site
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Excavate trench for
primary power
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Native fill
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 662 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is going to continue forming for the fish lift placement. They also have a crew working on the
forming the retaining wall behind Area 60. I performed a rebar inspection on the retaining wall before they closed
up the forms. All was per the approved submittal.
9:00 am Attended weekly meeting.
11:00 am IMCO is working on setting the first raceway gate. They need to get it installed before EOI can finish the
rebar.
12:00 pm IMCO has set the gate and braced it off. Vale is onsite working on electrical at Area 60.
3:00 pm Baker Co. Building Inspector was onsite today. I am told he passed the electrical inspection.
4:00 pm EOI is continuing to install rebar for Area 40. They are continuing to wall rebar. IMCO is starting to put
together wall forms. Steve hopes to start setting all forms tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 663 of 1851
References
Photos (5)
20231114_123003
Taken on Nov 14, 2023, 12:30 PM MST
Added on Nov 15, 2023, 9:04 AM MST
Added by Chris Johnson
20231114_122953
Taken on Nov 14, 2023, 12:29 PM MST
Added on Nov 15, 2023, 9:04 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 664 of 1851
20231114_104317
Taken on Nov 14, 2023, 10:43 AM MST
Added on Nov 15, 2023, 9:04 AM MST
Added by Chris Johnson
20231114_082433
Taken on Nov 14, 2023, 8:24 AM MST
Added on Nov 15, 2023, 9:04 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 665 of 1851
20231114_080935
Taken on Nov 14, 2023, 8:09 AM MST
Added on Nov 15, 2023, 9:04 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 666 of 1851
Form detail
#263: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40, 60 Form CJs, Form
Retaining walls, Strip Forms, Install
Windows and Doors
Vale Electric 5 8 Area 60
IMCO, General Crew 5 10 Area 10 Backfill Site, Start
excavation for Primary Power
Forms
Location
Form date Nov 13, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 14, 2023, 6:50 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 667 of 1851
Crew # Workers # Total
hours
Work performed
Totals 21 36
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill Site
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Excavate trench for
primary power
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Compaction
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Import Native fill
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 668 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is excavating for the primary power duct bank.
11:00 am I spoke to Jake and Ryan. They informed me the concrete placement for tomorrow is canceled. They
were unsure when they would be placing concrete this week. I informed them I will need 48 Hours notice per the
contract prior to any concrete placements.
1:00 pm IMCO carpenters are working on stripping forms on the foundation of Area 40. They are also starting
bulkheads at the CJs for the wall placement at Area 40. Another crew is working on the fish lift walls from CJ to CJ.
And another crew is working on the retaining wall behind Area 60. They are stripping and moving the forms to get
ready for another wall placement.
3:00 pm Vale electric is onsite working on the electrical inside Area 60. Jake, IMCO, is also working on Area 60 by
installing windows.
4:30 pm IMCO is continuing to form bulkheads for the CJs along with finishing the wall forms for the fish lift. EOI
has been onsite working on wall rebar at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 669 of 1851
References
Photos (6)
20231113_135922
Taken on Nov 13, 2023, 1:59 PM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
20231113_135752
Taken on Nov 13, 2023, 1:57 PM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 670 of 1851
20231113_135730
Taken on Nov 13, 2023, 1:57 PM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
20231113_134600
Taken on Nov 13, 2023, 1:46 PM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 671 of 1851
20231113_134530
Taken on Nov 13, 2023, 1:45 PM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
20231113_104741
Taken on Nov 13, 2023, 10:47 AM MST
Added on Nov 14, 2023, 6:50 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 672 of 1851
Form detail
#262: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 4 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 10, 40 Place Concrete
Vale Electric 5 8 Area 60
IMCO, General Crew 5 10 Area 10, 40 Batch Concrete
Totals 22 36
Forms
Location
Form date Nov 9, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 10, 2023, 9:24 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 673 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, 40 Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10 Area 10, 40 Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is getting the batch plant up fired up.
8:00 am IMCO is ready for concrete. The batch plant crew is currently batching.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 674 of 1851
9:00 am I have taken my first test. All passed with no issues. The crew is continuing to place.
10:00 am Dusty B framing crew is onsite working on the punch list items. They informed me they will be done
today.
11:00 am I have taken my second test. The air was too low. They dosed the truck and I pulled another sample
from the truck. It passed. The crew is going to making adjustments to the rest of the trucks. They are almost done
with the foundation at Area 40. They are going to move the pump truck and also place 2 wall sections and 2 footing
sections of the retaining wall behind Area 60.
1:00 pm The crew has placed the two wall sections. They placed at a rate of 3 foot lifts.
2:00 pm I was asked to perform a walkthrough with the framing crew and IMCO. Jake and I walked with the
framers. Most items were taken care of. Others will be performed by IMCO. Jake is tracking the items on the Issues
tab of Build.
3:00 pm EOI has been onsite all day working on installing wall rebar at Area 40. The concrete crew is continuing to
finish the concrete slabs.
4:30 pm Vale, Lacy Mechanical and YMC have been onsite today working on Area 60.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 675 of 1851
References
Photos (7)
20231109_143047
Taken on Nov 9, 2023, 2:30 PM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
20231109_124038
Taken on Nov 9, 2023, 12:40 PM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 676 of 1851
20231109_085411
Taken on Nov 9, 2023, 8:54 AM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
20231109_085217
Taken on Nov 9, 2023, 8:52 AM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 677 of 1851
20231109_084906
Taken on Nov 9, 2023, 8:49 AM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
20231109_143040
Taken on Nov 9, 2023, 2:30 PM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 678 of 1851
20231109_085954
Taken on Nov 9, 2023, 8:59 AM MST
Added on Nov 10, 2023, 9:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 679 of 1851
Form detail
#261: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 14 8 Area 10, 40 Install Rebar
IMCO, Carpenters 8 10 Area 40 Bulkheads and Waterstop
Vale Electric 5 8 Area 60
IMCO, General Crew 5 10 Area 20, River Sensor
Crux Diving 3 8 Area 20, River Sensor
Forms
Location
Form date Nov 8, 2023
Description Area 20, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 10, 2023, 9:00 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 680 of 1851
Crew # Workers # Total
hours
Work performed
Totals 35 44
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 20, River Sensor
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 681 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day compressive break reports for the 5th Foundation placement at Area 40.
8:00 am IMCO is working on installing bulkheads and waterstop for the last 2 squares of the foundation for Area
40.
9:00 am EOI is onsite and working on installing rebar at Area 40 for walls along with retaining wall. Dusty B is
onsite working on the punch list items at Area 60. Attended weekly meeting.
10:00 am Crux is onsite and in the water working on the river sensor. They have one brace to weld in the water.
12:00 pm IMCO is continuing to work on the river sensor. MB Welding is performing the welding of the braces
above water.
2:00 pm IMCO carpenters are continuing to work on bulkheads and waterstop. Left site to deliver cylinders.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 682 of 1851
References
Photos (3)
20231108_112147
Taken on Nov 8, 2023, 11:21 AM MST
Added on Nov 8, 2023, 1:53 PM MST
Added by Chris Johnson
20231108_094404
Taken on Nov 8, 2023, 9:44 AM MST
Added on Nov 8, 2023, 1:53 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 683 of 1851
20231108_085854
Taken on Nov 8, 2023, 8:58 AM MST
Added on Nov 8, 2023, 1:53 PM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 684 of 1851
Form detail
#259: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 1 8 Area 40 Install Rebar
IMCO, Carpenters 5 10 Area 40 Forming, Waterstop
Vale Electric 1 8 Area 60
IMCO, General Crew 5 10 Area 10, Backfill MH 5, Prep
transformer pad
Totals 12 36
Forms
Location
Form date Nov 7, 2023
Description Area 10, Area 40,Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 7, 2023, 7:21 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 685 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill MH 5,
Transformer pad
Deere 644J Loader 1 10 Area 10, Load General Fill
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Backfill MH 5
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1 10 Area 10, Haul General Fill
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO is continuing to work on waterstop and bulkheads from CJ to CJ. They have installed the tail
screen drain for the cross crowder channel. They had to modify the drain. I asked Sean what the process is to weld
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 686 of 1851
it back together. He said after they pour the walls they will anchor and weld the 2nd and third sides to the
concrete.
12:00 pm Vale is onsite working on electrial conduit inside Area 60.
2:00 pm I walked the 3 squares at Area 40 that IMCO plans to place tomorrow. All rebar and clearances look
good. They are still working on installing the waterstop and embeds on one of the squares.
4:00 pm IMCO is continuing to work on the embeds and water stop. Sam from EOI checked with me regarding
the rebar. The best I can tell it is installed per the approved submittal and the contract drawings.
References
Photos (3)
20231106_153721
Taken on Nov 6, 2023, 3:37 PM MST
Added on Nov 7, 2023, 7:20 AM MST
Added by Chris Johnson
20231106_155133
Taken on Nov 6, 2023, 3:51 PM MST
Added on Nov 7, 2023, 7:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 687 of 1851
20231106_130532
Taken on Nov 6, 2023, 1:05 PM MST
Added on Nov 7, 2023, 7:20 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 688 of 1851
Form detail
#260: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 1 8 Area 40 Install Rebar
IMCO, Carpenters 8 10 Area 40 Concrete Placement
Vale Electric 5 8 Area 60
IMCO, General Crew 5 10 Area 40, Batch Concrete
Area 20, Begin River Sensor
Totals 19 36
Forms
Location
Form date Nov 7, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 8, 2023, 10:19 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 689 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 20, River Sensor
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3 10 Area 40, Concrete
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day compressive break reports for the 4th Foundation placement at Area 40. Also attached is
Concrete Field report from todays placement of the 6th foundation placement of Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 690 of 1851
7:00 am IMCO is starting to work on batching concrete for todays placement. They are going to place 3 squares
of the foundation at Area 40.
8:00 am IMCO is ready for concrete. I have walked the 3 squares to verify. All waterstop is installed and the rebar
is per the approved submittal.
8:30 am I have taken my first test. All passed with no issues. They are starting to place.
10:00 am Vale is onsite working on electrical at Area 60. They are continuing to install the conduit along with
setting boxes for switches and lights.
11:30 am IMCO has reached 50 CY. I tested the concrete truck at 50 CY. The air did not pass. It was low at 4.2%.
They dosed the truck with more air entrainment. I tested it again and it passed at 5.1%. I informed Sean of the
results and he directed his crew to add more air to the next trucks. IMCO believes they need to add more air as the
temp of the concrete goes up. This concrete was at 76 degrees.
1:00 pm IMCO has moved the crane over to Area 20. They are going to install the river sensor that was delivered
today.
2:00 pm IMCO has reached 100 CY. They area currently placing on the third and last square. I took my 3rd sample
for the day and tested it. The air was low again. I informed Sean. He dosed the truck. I tested it again and it was at
5.0%. The concrete temp was at 79 degrees. They continued to place. Ryan and I spoke about adding more air
entrainment for future placements.
3:00 pm IMCO is done placing and is now finishing the concrete. They are experiencing some some rain showers.
4:00 pm Jake asked if I could walk through the punch list again for the framing at Area 60.
5:00 pm We walked Area 60 framing punchlist again. Jake took notes. Zack has requested Jake add each of the
deficiencies to the issues tap on Build.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 691 of 1851
References
Photos (4)
20231107_164348
Taken on Nov 7, 2023, 4:43 PM MST
Added on Nov 8, 2023, 6:48 AM MST
Added by Chris Johnson
20231107_124735
Taken on Nov 7, 2023, 12:47 PM MST
Added on Nov 8, 2023, 6:48 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 692 of 1851
20231107_085438
Taken on Nov 7, 2023, 8:54 AM MST
Added on Nov 8, 2023, 6:48 AM MST
Added by Chris Johnson
20231107_093924
Taken on Nov 7, 2023, 9:39 AM MST
Added on Nov 8, 2023, 6:48 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 693 of 1851
Form detail
#258: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 1 8 Area 40 Install Rebar
IMCO, Carpenters 5 10 Area 40 Forming
Vale Electric 1 8 Area 60
IMCO, General Crew 5 10 Area 10, Backfill MH 5
Totals 12 36
Forms
Location
Form date Nov 2, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 6, 2023, 11:08 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 694 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Backfill MH 5
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1 10 Area 10, Backfill MH 5
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on forming at Area 40. They are prepping for next weeks continued placement of the
foundation at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 695 of 1851
12:00 pm Zack, John Anderson and myself performed a punch list walkthrough with Ryan and Jake from IMCO at
Area 60 Hatchery Building. The punch list was for the framing of the building. Multiple deficiencies were found in
the framing that did not match contract drawings. Ryan is going to compile all deficiencies in a document and send
over for review.
1:30 pm Left site to return concrete cylinders.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 696 of 1851
Form detail
#257: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 10 Area 40/Area 10, Install Rebar
IMCO, Carpenters 5 10 Area 40 place concrete
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
IMCO, General Crew 5 10 Area 40, Batch Concrete
Forms
Location
Form date Nov 1, 2023
Description Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 2, 2023, 7:26 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 697 of 1851
Crew # Workers # Total
hours
Work performed
Totals 22 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 698 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached concrete test report from todays Area 40 5th Foundation placement with IMCO batch tickets.
8:00 am IMCO is making final preparations for todays placement. They are finishing up the bulkheads and
stripping forms to be poured up too.
9:00 am IMCO is starting to batch concrete. The temps are above 40 this morning.
10:00 am I have taken my first test on the first truck. It all passed with no issues. They are starting to place
concrete for an Area 40 Square. They are placing from CJ to CJ in a checkerboard sequence.
11:00 am The framers are onsite. They have finished the roof sheeting along with soffit backers.
1:00 pm I have taken a second test on the concrete. It passed with no issues. The crew is about finished with the
second and last square. Vale is onsite working on running conduit in the Hatchery Building. The framers have left.
There is a punchlist walkthrough scheduled for tomorrow morning. I have pulled the temp recording device from
the placement yesterday. I checked and at no point over the night did it record under 40 degrees.
3:00 pm The crew is continuing to work on finishing the concrete. They are also cleaning up the site. Jake is
working on the retaining wall. He is hanging closing forms on the wall. EOI has been onsite tying rebar for the fish
lift.
5:00 pm The crew informed me the concrete is too wet to get covered tonight. The weather shows above 40
degrees so the concern for blankets is not applicable. Sean informed me he plans to use the rain over the next few
days as a curing plan.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 699 of 1851
References
Photos (3)
20231101_153908
Taken on Nov 1, 2023, 3:39 PM MDT
Added on Nov 2, 2023, 7:26 AM MDT
Added by Chris Johnson
20231101_123544
Taken on Nov 1, 2023, 12:35 PM MDT
Added on Nov 2, 2023, 7:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 700 of 1851
20231101_103451
Taken on Nov 1, 2023, 10:34 AM MDT
Added on Nov 2, 2023, 7:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 701 of 1851
Form detail
#256: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 10 Area 40/Area 10, Install Rebar
IMCO, Carpenters 5 10 Area 40 place concrete
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Overhead Door Company 2 8 Area 60, Roll up doors
Forms
Location
Form date Oct 31, 2023
Description Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 1, 2023, 7:48 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 702 of 1851
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Area 40, Batch Concrete
Totals 24 56
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 703 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day compressive break reports from the Area 40 2nd Foundation placement. Also concrete test
report from todays Area 40 4th Foundation placement with IMCO batch tickets.
7:00 am IMCO is planning to place concrete today at area 40. They are wanting to place 2 "squares" from CJ to CJ.
8:00 am IMCO is batching concrete currently. It is very cold this morning at about 25 degrees. I requested to Sean
and Steve to get the rebar covered and get heat going since the rebar is frozen. They both agreed that they
needed to do this and got right on it.
9:00 am IMCO has batched their first truck. While priming the pump truck, the pump developed a clog. The little
but of concrete that came out in the ECO pan I spot checked the temperature. It was around 46 degrees. This tells
me the pump truck hoses are cold and is cooling the concrete through the pump. Kole informed me they have the
burner fired up and heating the water to around 120 degrees. After they got the clog cleared and the pump was
pumping concrete above 50 degrees there was hardly any concrete left in the truck. I told IMCO this would not be
a fair represented sample of the concrete for my test. I did however check the air for them. It was at 7.3% which is
high. They decided to ditch the last of that concrete and make a new 4.5 CY batch.
9:30 am The second truck tested all in spec. They are starting the placement.
11:00 am IMCO is continuing to place concrete for the foundation. The framing sub is onsite continuing to work
on the hatchery building. I noticed the eaves on the Incubation room build out were a little short. I asked what
dimension they said they used. It was under the 2'3" planned dimension. They asked if they could scab on to it to
make it proper length. I advised not and it should be built per plan. They area going to get it fixed.
12:45 pm IMCO is continuing to place concrete. I have taken a second test at 50 CY. All passed with no issues.
1:00 pm Attended weekly meeting.
2:30 pm Walked the site with Zack, Jake and Kirt. IMCO has had Overhead door company onsite installing the two
overhead doors in the hatchery building. The detail shows the doors to be mounted to the outside of the CMU.
They did not do this. They mounted it to the framing. I pointed out several issues with trimming out the doors
under the current install. I also noticed some dents and defects in the doors. They are going to think more on it.
IMCO is continuing to place concrete. They have a 3rd square ready. Since it is ready they are going to place it
today.
4:00 pm IMCO placed approx. 80 CY today. They are working on finishing it now. I have been asked to do a
walkthrough for all the framing. This is scheduled for Thursday morning. I walked a little bit of it today and noticed
a few things. Including a door header being cut and scapped with plywood. IMCO has also placed the manhole
section for MH 5.
5:30 pm IMCO is still working on finishing the concrete. They informed me it is taking forever to setup. Sean
asked about adding an accelerant to the concrete for future pours. I advised him to have a mix design drafted and
submitted. I have placed a recording thermometer near the top of the slab. It will record temps through the night.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 704 of 1851
References
Photos (9)
20231031_163409
Taken on Oct 31, 2023, 4:34 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
20231031_161509
Taken on Oct 31, 2023, 4:15 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 705 of 1851
20231031_141833
Taken on Oct 31, 2023, 2:18 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
20231031_124550
Taken on Oct 31, 2023, 12:45 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 706 of 1851
20231031_115219
Taken on Oct 31, 2023, 11:52 AM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
20231031_105508
Taken on Oct 31, 2023, 10:55 AM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 707 of 1851
20231031_163412
Taken on Oct 31, 2023, 4:34 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
20231031_143743
Taken on Oct 31, 2023, 2:37 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 708 of 1851
20231031_141829
Taken on Oct 31, 2023, 2:18 PM MDT
Added on Nov 1, 2023, 7:45 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 709 of 1851
Form detail
#255: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 10 Area 40/Area 10, Install Rebar
IMCO, Carpenters 5 10 Area 40, Forms Area 10, Retaining
Wall Forms
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Overhead Door Company 2 8 Area 60, Roll up doors
Forms
Location
Form date Oct 30, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 31, 2023, 7:02 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 710 of 1851
Crew # Workers # Total
hours
Work performed
Totals 19 46
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 3 Area 10, Unload MH
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 711 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
12:00 pm IMCO is continuing to work on bulkheads and waterstop at the CJs of Area 40 foundation slab.
1:00 pm Dusty B framers are continuing to work on area 60 framing. I noticed right away that the sub fascia on
the roll up window build out did not look right. After reviewing the drawings it is not built per plan. The framers
asked what I was seeing and I informed them what I was seeing. I told them I need to get with Sean and Kirt
regarding the eave and they would direct accordingly. I also noticed that an interior wall between the mud room
and the incubation room is a 2x6 framed wall. Per plan it should be a 2x4. With the 2x6, the framing is overhanging
the concrete curb by approx. 2".
2:00 pm EOI is onsite working on rebar for the retaining wall.
3:00 pm I walked the framing issues with Kirt and Sean. Kirt and I talked in length regarding the interior wall and
the overhang. He said he would like to leave the 2x6 wall and pour grout under the wood to provide a smooth
finish for the GWB. I asked about the door frames and how they would wrap the larger wall. He said he was going
to look into it. He said he also wants to check the finishes for the room.
5:00 pm I have walked the squares to be poured in tomorrows placement. All looks ready for concrete. Sean has
informed me that he wants to move Thursdays pour to Wednesdays due to weather.
6:00 pm IMCO is ready for the placement tomorrow. They plan to start around 8am.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 712 of 1851
References
Photos (4)
20231030_164946
Taken on Oct 30, 2023, 4:49 PM MDT
Added on Oct 31, 2023, 6:59 AM MDT
Added by Chris Johnson
20231030_171700
Taken on Oct 30, 2023, 5:16 PM MDT
Added on Oct 31, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 713 of 1851
20231030_171655
Taken on Oct 30, 2023, 5:16 PM MDT
Added on Oct 31, 2023, 6:59 AM MDT
Added by Chris Johnson
20231030_164940
Taken on Oct 30, 2023, 4:49 PM MDT
Added on Oct 31, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 714 of 1851
Form detail
#254: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 10 Area 40/Area 10, Install Rebar
IMCO, Carpenters 5 10 Area 40, Forms Area 10, Retaining
Wall Forms
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Basin Masonry 4 5 Area 30, veneer siding
Forms
Location
Form date Oct 27, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 27, 2023, 11:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 715 of 1851
Crew # Workers # Total
hours
Work performed
Totals 21 43
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 6 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
IMCO Concrete Truck 3
Dump Truck 1
Bomag BW 124 PD SD Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 716 of 1851
Equipment Quantity Hours
used
Comment
JLG G5-18A Boom Forklift (Basin
Masonry Rental)
1 2 Move Material around the site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:30 am Talked to Andrew about the heaters from yesterdays Pour (I looked under the tarp and didn't see/hear
any heaters, Andrew said they were under the tarp on the far corner
where I couldn't see). Andrew told me that the heaters had run out of propane overnight. I looked at the
spec and told him they need to heat the Pour for 3 days and hold a
temperature of 50 degrees. They do not have a way to check temps. Chris Johnson previously had a
conversation with Sean about a cold weather plan (Sean was here for
the pour today). Basin Masonry is grouting the stone work the wall on the Area 30 Aeration Tower.
Framers/Vale Electric are working in Area 60. EOI working on installing
rebar in Area 40 and Area 10 Retaining Wall.
10:30 am Pine Creek Weather Station (2 mi south of Oxbow) shows a current temperature of 36f. Andrew left to
get more propane. He said there will be someone to keep the heaters
running over the weekend.
11:00 am 1 Propane heater running on 1 on the squares poured yesterday. Talked to Jake about getting a heater
on both sections poured yesterday.
11:30 am Picking up Cylinders to run them back to the Meridian Office. Basin Masonry Tarping the stone on the
Aeration Tower Area 30. Cleaning up materials.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 717 of 1851
References
Photos (5)
TC_00312
Taken on Oct 27, 2023, 10:42 AM MDT
Added on Oct 27, 2023, 11:21 AM MDT
Added by Chris Johnson
TC_00311
Taken on Oct 27, 2023, 10:42 AM MDT
Added on Oct 27, 2023, 11:21 AM MDT
Added by Chris Johnson
TC_00309
Taken on Oct 27, 2023, 10:39 AM MDT
Added on Oct 27, 2023, 11:21 AM MDT
Added by Chris Johnson
TC_00308
Taken on Oct 27, 2023, 10:27 AM MDT
Added on Oct 27, 2023, 11:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 718 of 1851
TC_00310
Taken on Oct 27, 2023, 10:40 AM MDT
Added on Oct 27, 2023, 11:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 719 of 1851
Form detail
#253: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 3 10 Area 40, Install Rebar
IMCO, Carpenters, Finishers 8 10 Area 40, Forms Area 10, Retaining
Wall Forms
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Basin Masonry 4 10 Area 30, veneer siding
Forms
Location
Form date Oct 26, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 30, 2023, 3:48 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 720 of 1851
Crew # Workers # Total
hours
Work performed
Lacey Mechanical 1 8 Area 60, Plumbing
Totals 25 56
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 6 Move material around the site
Deere 210 Excavator 1 2 Area 10
Deere 644J Loader 1 2 Moved materials around the
project site
Hitachi 85 Excavator 1
Kobelco 1100G Crane 1 6 Area 40, Fly Rebar/Area 60, Fly
Lumber
Bomag Roller 1
Water Truck 1 2 Clean Concrete Trucks
IMCO Concrete Truck 3 Area 40 Concrete Pour (3rd truck
used for 1 load)
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 721 of 1851
Equipment Quantity Hours
used
Comment
Bomag BW 124 PD SD Roller 1
JLG G5-18A Boom Forklift (Basin
Masonry Rental)
1 4 Move Material around the site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Testing Report along with IMCO Batch Tickets. Also Attached is 28 Day Compressive Break
Report for the Tail Screen 1st Wall Placement and the 7 Day 1st upper foundation placement at Area 40.
8:00 am IMCO working on Area 40 Form work and batching concrete for pour today. EOI working on Area 40
rebar. Basin Masonry has 4 guys onsite to work on the veneer siding
Area 30. Framers working in Area 60. Brundage Bone onsite for pour.
8:45 am 1st Concrete truck backed up to the pump to pour Area 40 Foundation (Pour #3) . I sampled the 1st
truck, test was good
11:20 am I sampled the 6th truck, test was good
12:30 pm IMCO done batching. Finishing the pour.
4:00 pm Talked to Kirt about covering and heating todays Pour as it is forecast to be 36 degrees overnight. He
said he would tarp it and use propane heaters. Basin Masonry is tarping the wall on the Area 30 Aeration Tower.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 722 of 1851
References
Photos (13)
TC_00307
Taken on Oct 26, 2023, 3:55 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00304
Taken on Oct 26, 2023, 12:50 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 723 of 1851
TC_00303
Taken on Oct 26, 2023, 12:50 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00302
Taken on Oct 26, 2023, 12:43 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 724 of 1851
TC_00301
Taken on Oct 26, 2023, 12:42 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00300
Taken on Oct 26, 2023, 12:42 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 725 of 1851
TC_00299
Taken on Oct 26, 2023, 12:41 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00298
Taken on Oct 26, 2023, 10:27 AM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 726 of 1851
TC_00297
Taken on Oct 26, 2023, 10:27 AM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00296
Taken on Oct 26, 2023, 10:27 AM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 727 of 1851
TC_00295
Taken on Oct 26, 2023, 9:55 AM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
TC_00306
Taken on Oct 26, 2023, 3:53 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 728 of 1851
TC_00305
Taken on Oct 26, 2023, 3:53 PM MDT
Added on Oct 26, 2023, 4:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 729 of 1851
Form detail
#252: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 4 10 Area 40, Install Rebar
IMCO, Carpenters 8 10 Area 40, Forms Area 10, Retaining
Wall Forms
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Basin Masonry 4 10 Area 30, veneer siding
Forms
Location
Form date Oct 25, 2023
Description Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 30, 2023, 3:42 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 730 of 1851
Crew # Workers # Total
hours
Work performed
Lacey Mechanical 1 8 Area 60, Plumbing
Totals 26 56
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 8 Area 10
Deere 644J Loader 1 2 Moved materials around the
project site
Hitachi 85 Excavator 1 6 Area 10 Grading, Backfill,
stockpiling concrete Aggs
Kobelco 1100G Crane 1 6 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 4 Dust control, Area 10 Water for
Compaction
IMCO Concrete Truck 3
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 731 of 1851
Equipment Quantity Hours
used
Comment
Bomag BW 124 PD SD Roller 1
JLG G5-18A Boom Forklift (Basin
Masonry Rental)
1 8 Move Material around the site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am IMCO working on Area 40 Form work. EOI working on Area 40 rebar. Basin Masonry has 4 guys onsite to
work on the veneer siding Area 30. Framers
working in Area 60.
9:30 am Jake sent me the concrete batch tickets from yesterday. They only placed 67.5 cy, not 76.5 cy per
yesterdays diary (i was told verbally the yardage placed yesterday).
4:30 pm Spoke to Sean about the truss detail for the Area 60 Hatchery Building. Framers worked on installing
door frames, Rough Framing and the dormer for Area 60.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 732 of 1851
References
Photos (5)
TC_00294
Taken on Oct 25, 2023, 2:42 PM MDT
Added on Oct 26, 2023, 1:02 PM MDT
Added by Chris Johnson
TC_00293
Taken on Oct 25, 2023, 2:42 PM MDT
Added on Oct 26, 2023, 1:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 733 of 1851
TC_00292
Taken on Oct 25, 2023, 11:32 AM MDT
Added on Oct 26, 2023, 1:02 PM MDT
Added by Chris Johnson
TC_00291
Taken on Oct 25, 2023, 10:02 AM MDT
Added on Oct 26, 2023, 1:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 734 of 1851
TC_00290
Taken on Oct 25, 2023, 10:02 AM MDT
Added on Oct 26, 2023, 1:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 735 of 1851
Form detail
#251: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 4 10 Area 40, Install Rebar
IMCO, Carpenters/Finishers 8 10 Area 40, Forms/Pour
Dusty B Framers 8 10 Area 60
Vale Electric 1 8 Area 60
Basin Masonry 3 10 Area 30, veneer siding
Forms
Location
Form date Oct 24, 2023
Description Area 10, Area 30, Area 60
Due date Oct 24, 2023
Submitted by Chris Johnson
Status Closed
Last update Oct 30, 2023, 3:40 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 736 of 1851
Crew # Workers # Total
hours
Work performed
Lacey Mechanical 1 8 Area 60, Plumbing
Totals 25 56
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 8 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1 2 Moved materials around the
project site
Hitachi 85 Excavator 1 6 Area 10 Grading, Backfill,
stockpiling concrete Aggs
Kobelco 1100G Crane 1 6 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 4 Dust control, Area 10 Water for
Compaction
IMCO Concrete Truck 2 6 Area 40
Dump Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 737 of 1851
Equipment Quantity Hours
used
Comment
Bomag BW 124 PD SD Roller 1 2 Area 10, Retaining wall Footing
JLG G5-18A Boom Forklift (Basin
Masonry Rental)
1 8 Move Material around the site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Test Report along with IMCO Batch Tickets.
7:30 am IMCO working on Area 40 Form work. EOI working on Area 40 rebar. Vale Electric on-site. Basin Masonry
has 3 guys onsite to work on the veneer siding Area 30. Framers
working in Area 60. IMCO getting ready to place Area 40 Foundation. Welder on-site to work on columns
for Area 60, Hatchery Building.
8:30 am IMCO placing concrete for Area 40 Foundation.
12:00 pm IMCO done placing concrete. 76.5 cy placed today. 2 sets of cylinders made.
4:00 pm I spoke to Kirt and Sean about covering the concrete from todays placement as it is supposed to rain
from tonight-Thursday Morning. They said they planned to cover it with plastic.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 738 of 1851
References
Photos (8)
TC_00289
Taken on Oct 24, 2023, 3:15 PM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
TC_00285
Taken on Oct 24, 2023, 1:47 PM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 739 of 1851
TC_00284
Taken on Oct 24, 2023, 9:40 AM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
TC_00283
Taken on Oct 24, 2023, 9:38 AM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 740 of 1851
TC_00288
Taken on Oct 24, 2023, 3:15 PM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
TC_00287
Taken on Oct 24, 2023, 1:48 PM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 741 of 1851
TC_00286
Taken on Oct 24, 2023, 1:48 PM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
TC_00282
Taken on Oct 24, 2023, 9:38 AM MDT
Added on Oct 25, 2023, 9:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 742 of 1851
Form detail
#250: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
EOI 4 10 Area 40, Install Rebar
IMCO, Carpenters 4 Area 40, Forms
Dusty B Framers 8 8 Area 60
Vale Electric 2 10 Area 10
Basin Masonry 4 10 Area 30, veneer siding
Forms
Location
Form date Oct 23, 2023
Description Area, 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 24, 2023, 7:21 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 743 of 1851
Crew # Workers # Total
hours
Work performed
Totals 22 38
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 8 Move material around the site
Deere 210 Excavator 1 2 Area 10, Backfill between Area
40/60
Deere 644J Loader 1 4 Moved materials around the
project site
Hitachi 85 Excavator 1 6 Area 10 Grading, Backfill,
stockpiling concrete Aggs
Kobelco 1100G Crane 1 2 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 4 Dust control, Area 10 Water for
Compaction
IMCO Concrete Truck 3
Dump Truck 1 4 Hauled in Concrete Aggs
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 744 of 1851
Equipment Quantity Hours
used
Comment
Bomag BW 124 PD SD Roller 1 2 Area 10, Retaining wall Footing
JLG G5-18A Boom Forklift (Basin
Masonry Rental)
1 8 Move Material around the site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO working on Area 40 Form work. EOI working on Area 40 Top Mat and Verts. Vale Electric on-site.
Delivery of colored grout and scaffolding from Basin Masonry. Basin Masonry has 4 guys onsite to work on the
veneer siding Area 30. Delivery of Cement.
9:00 am IMCO had 2 guys working on the Area 10 backfill for the retaining wall. Framers not onsite. IMCO,
getting forms and floor drains to grade in Area 40.
10:30 am Framers working on Area 60, Hatchery building.
11:00 am Welder showed up to rotate plates on the top of the columns Area 60, Hatchery building.
2:00 pm IMCO plans to pour at 8:00am tomorrow morning (70cy).
4:00 pm Ryan with IMCO doing his rebar inspection. I told him there were a couple clearance issues and some
bar that needed to be tied for tomorrows pour.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 745 of 1851
References
Photos (6)
TC_00281
Taken on Oct 23, 2023, 3:19 PM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
TC_00280
Taken on Oct 23, 2023, 3:18 PM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 746 of 1851
TC_00279
Taken on Oct 23, 2023, 2:59 PM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
TC_00278
Taken on Oct 23, 2023, 2:58 PM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 747 of 1851
TC_00277
Taken on Oct 23, 2023, 2:38 PM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
TC_00276
Taken on Oct 23, 2023, 10:08 AM MDT
Added on Oct 24, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 748 of 1851
Form detail
#249: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 4 10 Area 40, Forming
Dusty B Framers 8 8 Area 60, Framing, Roof sheathing
on the South side of the Building
EOI 4 10 Area 40, Install Rebar
Totals 16 28
Forms
Location
Form date Oct 20, 2023
Description Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 20, 2023, 11:53 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 749 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 4 Area 10 Grading, Backfill
Kobelco 1100G Crane 1 10 Area 30, Fly Piping/fittings/Area 40,
Fly Rebar/Area 60 Fly Lumber
Bomag Roller 1
Water Truck 1 4 Dust control
IMCO Concrete Truck 3
Dump Truck 1
Bomag BW 124 PD SD Roller 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 750 of 1851
Notes
8:00 am IMCO working on Area 40 Form work. EOI working on Area 40 Top Mat and Verts. Crane moving material
for the framers in Area 60. I noticed the contractor installed brackets and luminaire's to the handrail on the river
intake Area 20 (work done yesterday sometime).
9:00 am 1 operator running Hitachi 85 Excavator grading around MH-4 Area 10 for 1 hour
10:30 am 8 sticks (20') of 12" SDR 17 HDPE delivered. IMCO working on piping inside of the Aeration Tower Area
30
11:45 am Spoke to James (EOI) about Area 40 rebar inspection. The rebar for the concrete pour on Tuesday 10/24
will be ready for inspection Monday.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 751 of 1851
References
Photos (5)
TC_00275
Taken on Oct 20, 2023, 11:09 AM MDT
Added on Oct 20, 2023, 11:38 AM MDT
Added by Chris Johnson
TC_00274
Taken on Oct 20, 2023, 11:08 AM MDT
Added on Oct 20, 2023, 11:38 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 752 of 1851
TC_00273
Taken on Oct 20, 2023, 10:18 AM MDT
Added on Oct 20, 2023, 11:38 AM MDT
Added by Chris Johnson
TC_00272
Taken on Oct 20, 2023, 8:40 AM MDT
Added on Oct 20, 2023, 11:38 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 753 of 1851
TC_00271
Taken on Oct 20, 2023, 8:40 AM MDT
Added on Oct 20, 2023, 11:38 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 754 of 1851
Form detail
#248: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Batch Concrete
IMCO, Carpenters 7 10 Area 40, Concrete Placement,
Forming
Dusty B Framers 8 8 Area 60, Framing
EOI 4 10 Area 40, Install Rebar
Forms
Location
Form date Oct 19, 2023
Description Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 30, 2023, 3:53 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 755 of 1851
Crew # Workers # Total
hours
Work performed
MB Welding 1 10 Area 30, Stair Install
Area 60, Fix Columns
Totals 25 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10 rip rap
IMCO Concrete Truck 2 8 Area 40, Concrete Placement
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 4 Area 10 retaining wall footing
Backfill, Rip Rap placement
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 4 Dust control
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 756 of 1851
4. Signature
Chris Johnson, HMH Engineering
Name
-
Date and time
Oct 19, 2023 at 3:32 PM MDT
4.1
Notes
See attached Concrete test report along with IMCO Batch Tickets.
See attached Welding Inspection Reports for Area 30 and Area 40 work to date.
8:00 am IMCO is batching concrete for placement at Area 40. They plan to place 2 squares from CJ to CJ.
8:20 am I have tested the first truck. All tests passed with no issues. IMCO is continuing to place and batch.
11:15 am I tested the second truck. Test passed. IMCO continuing to place and batch.
1:oo pm Done placing concrete for the day. 1 operator on the Hitachi 85 excavator working on grading the area
10 retaining wall and grading the slope from the retaining wall to the
bank of the river. Placed rip rap along the slope. Andrew, the welding inspector showed up.
2:00 pm Andrew done inspecting the welds inside of the aeration tower and the hatchery building.
2:30 pm 1 operator and the JD 210 excavator working on placing rip rap on the east side of the retaining wall.
3:30pm EOI working on the verts and top mat in area 40. IMCO crew finishing concrete from the placement today.
Randy Inselman, HMH Engineering
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 757 of 1851
References
Photos (4)
20231019_112557
Taken on Oct 19, 2023, 11:25 AM MDT
Added on Oct 19, 2023, 12:07 PM MDT
Added by Chris Johnson
20231019_112614
Taken on Oct 19, 2023, 11:26 AM MDT
Added on Oct 19, 2023, 12:07 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 758 of 1851
20231019_091424
Taken on Oct 19, 2023, 9:14 AM MDT
Added on Oct 19, 2023, 12:07 PM MDT
Added by Chris Johnson
20231019_112621
Taken on Oct 19, 2023, 11:26 AM MDT
Added on Oct 19, 2023, 12:07 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 759 of 1851
Form detail
#247: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 5
IMCO, Carpenters 7 10 Area 40, Forming
Dusty B Framers 8 8 Area 60, Framing
EOI 4 10 Area 40, Install Rebar
Totals 24 38
Forms
Location
Form date Oct 18, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 19, 2023, 6:06 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 760 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 5 discharge pipe
IMCO Concrete Truck 3
Deere 644J Loader 1 10 Area 10, Access to Retaining wall
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached concrete compressive strength repot.
8:00 am IMCO is working on forming for foundation placements at Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 761 of 1851
9:00 am Attended weekly meeting.
10:00 am IMCO is continuing to work on CJs and bulkheads. The framing crew is sheeting the roof of Area 60.
1:00 pm I performed a walk through on the rebar for the 2 sections of foundation they plan to place tomorrow
morning. Everything looked to be per plan and ready for placement. The pipe crew has completed the new
discharge pipe to the river. They are backfilling it all now.
3:00 pm The pipe crew is continuing to backfill and compact around MH 5. EOI has been working on top mat of
the rebar at Area 40.
4:00 pm IMCO crews are continuing to installing bulkheads at the CJs along with waterstop.
References
Photos (4)
20231018_151817
Taken on Oct 18, 2023, 3:18 PM MDT
Added on Oct 19, 2023, 6:01 AM MDT
Added by Chris Johnson
20231018_151748
Taken on Oct 18, 2023, 3:17 PM MDT
Added on Oct 19, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 762 of 1851
20231018_134903
Taken on Oct 18, 2023, 1:49 PM MDT
Added on Oct 19, 2023, 6:01 AM MDT
Added by Chris Johnson
20231018_134856
Taken on Oct 18, 2023, 1:48 PM MDT
Added on Oct 19, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 763 of 1851
Form detail
#245: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 5
IMCO, Carpenters 7 10 Area 40, Forming
Dusty B Framers 8 8 Area 60, Framing
EOI 4 10 Area 40, Install Rebar
Totals 24 38
Forms
Location
Form date Oct 17, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 18, 2023, 6:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 764 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 5
IMCO Concrete Truck 3
Deere 644J Loader 1 10 Area 10, MH 5
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly Rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO carpenters are planning to continue the forming of the foundation sections at Area 40. They are
also going to continue working on forming the fish lift walls.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 765 of 1851
10:00 am EOI is onsite. They are working on the top mat rebar for Area 40.
12:00 pm The framing crew has been working on sheeting the roof. I met with Bert from the crew. I noticed a few
missing structural Simpson brackets. He said he would get someone working on them as he did miss them in the
plans. IMCO has a crew working on setting MH 5.
2:00 pm IMCO has set MH 5 with the crane. They also made the connection to the old steel drain pipe along with
the connection to MH 4. They are grouting it in now.
3:00 pm IMCO is continuing to form up the fish lift and the foundation section. They plan on pouring some of the
foundations from CJ to CJ on Thursday.
5:00 pm IMCO is working on installing the discharge pipe out of MH 5 to the river. They are installing it per IPC
direction to stay above the OHW elevation of 1692.
References
Photos (4)
20231017_092457
Taken on Oct 17, 2023, 9:24 AM MDT
Added on Oct 18, 2023, 6:47 AM MDT
Added by Chris Johnson
20231017_155139
Taken on Oct 17, 2023, 3:51 PM MDT
Added on Oct 18, 2023, 6:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 766 of 1851
20231017_153506
Taken on Oct 17, 2023, 3:35 PM MDT
Added on Oct 18, 2023, 6:47 AM MDT
Added by Chris Johnson
20231017_110250
Taken on Oct 17, 2023, 11:02 AM MDT
Added on Oct 18, 2023, 6:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 767 of 1851
Form detail
#244: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 5
IMCO, Carpenters 7 10 Area 40, Forming
Dusty B Framers 8 8 Area 60, Framing
Totals 20 28
2. Materials
Forms
Location
Form date Oct 16, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 17, 2023, 6:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 768 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 3
Deere 644J Loader 1 10 Area 10, MH 5
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Break report from 10/12.
11:00 am IMCO pipe crew is working on installing MH 5. They have cut the existing pipe they need to tie into for
the year square and will need to swing the manhole over it.
12:00 pm The framing crew is onsite. They have framed the outriggers on the gables per the direction provided
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 769 of 1851
in an email. See Correspondence. Schnabel is requiring a 2x4 on edge to stiffen the 2x4 laid flat. The framers are
working on sheeting the roof now.
1:00 pm IMCO carpenters are working on forming the thickened edge of the raceways. They also have a crew
working on the fish lift forming.
3:00 pm IMCO has set the base for MH 5. They are waiting for their crane operator to set the manhole sections of
the structure. The framing crew is finishing up for the day.
5:00 pm IMCO is cleaning up for the day. They worked on forming for the next concrete placement all day.
References
Photos (8)
20231016_111029
Taken on Oct 16, 2023, 11:10 AM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
20231016_153908
Taken on Oct 16, 2023, 3:39 PM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 770 of 1851
20231016_111127
Taken on Oct 16, 2023, 11:11 AM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
20231016_153959
Taken on Oct 16, 2023, 3:39 PM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 771 of 1851
20231016_153856
Taken on Oct 16, 2023, 3:38 PM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
20231016_114406
Taken on Oct 16, 2023, 11:44 AM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 772 of 1851
20231016_114400
Taken on Oct 16, 2023, 11:44 AM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
20231016_111033
Taken on Oct 16, 2023, 11:10 AM MDT
Added on Oct 17, 2023, 6:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 773 of 1851
Form detail
#243: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Batch Concrete
IMCO, Carpenters 7 10 Area 40, Concrete Placement
EOI 4 10 Area 40, Rebar
Dusty B Framers 8 8 Area 60, Framing
Totals 24 38
Forms
Location
Form date Oct 11, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 12, 2023, 7:50 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 774 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 8 Area 40, Batch Concrete
IMCO Concrete Truck 1 8 Area 40, Batch Concrete
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, 12" D Line
Dump Truck 1 10 Area 10, Import Structural Fill
Kobelco 1100G Crane 1 10
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 775 of 1851
Notes
7:00 am IMCO is working on batching concrete for todays placement.
8:30 am The pump truck is onsite and they are getting ready to start placing concrete. They are going to start with
the footings for the retaining wall.
9:30 am IMCO has starting placing. I have taken a test and it passed with no issues. IMCO is starting to batch
their second truck.
10:30 am IMCO has informed me the batch plant is plugged up and they are still working on making the second
truck.
11:30 am It has been discussed that they will not be able to batch any more concrete today as the cement hopper
is plugged up. IMCO is going to leave the concrete in the forms for the retaining wall. Sean, Zack and I discussed
flatting the concrete in the forms to be between the two rebar matts. IMCO has already done this. The next
placement is scheduled for Monday.
12:30 pm IMCO is going to work on fixing the batch plant. Left site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 776 of 1851
References
Photos (1)
20231011_095621
Taken on Oct 11, 2023, 9:56 AM MDT
Added on Oct 12, 2023, 7:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 777 of 1851
Form detail
#242: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Weld HDPE piping, install
12 D to MH 7
IMCO, Carpenters 7 10 Area 40, Template for Rebar, CJ
bulkheads
Totals 12 20
2. Materials
Forms
Location
Form date Oct 10, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 11, 2023, 6:56 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 778 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 8
IMCO Concrete Truck 1 8
Deere 644J Loader 1 10 Area 10, 12 D to MH 7
Hitachi 85 Excavator 1 10 Area 10, 12" D Line
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly trusses
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to continue working on CJs bulkheads and water stop at Area 40. EOI will not be onsite today
so they are going to continue working on CJs to stay ahead of them. EOI is scheduled to be onsite Wednesday now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 779 of 1851
9:00 am The framing crew is continuing to install the trusses.
10:00 am IMCO pipe crew is working on bedding and backfilling the 12 D line to MH 7.
12:00 pm I have walked through the lower raceway drain foundation. All looks good and is ready to be poured.
2:00 pm I noticed the framers notched the top chord on the gable truss for the outrigger eaves. After looking
through the submittal I confirmed this is correct per the submittal. This however does not match the details on
GS-2. I have brought this to IMCOs attention and also composed an email to the engineer. It has started to rain
onsite. The framing crew has left.
4:30 pm IMCO has continued to work on CJs at Area 40.
References
Photos (10)
20231010_143023
Taken on Oct 10, 2023, 2:30 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
20231010_143018
Taken on Oct 10, 2023, 2:30 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 780 of 1851
20231010_143015
Taken on Oct 10, 2023, 2:30 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
20231010_142118
Taken on Oct 10, 2023, 2:21 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 781 of 1851
20231010_142016
Taken on Oct 10, 2023, 2:20 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
20231010_142008
Taken on Oct 10, 2023, 2:20 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 782 of 1851
20231010_122143
Taken on Oct 10, 2023, 12:21 PM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
20231010_094412
Taken on Oct 10, 2023, 9:44 AM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 783 of 1851
20231010_092852
Taken on Oct 10, 2023, 9:28 AM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
20231010_092845
Taken on Oct 10, 2023, 9:28 AM MDT
Added on Oct 11, 2023, 6:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 784 of 1851
Form detail
#241: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Weld HDPE piping, install
12 D to MH 7
IMCO, Carpenters 7 10 Area 40, Template for Rebar, CJ
bulkheads
Totals 12 20
2. Materials
Forms
Location
Form date Oct 9, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 10, 2023, 7:25 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 785 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 8
IMCO Concrete Truck 1 8
Deere 644J Loader 1 10 Area 10, 12 D to MH 7
Hitachi 85 Excavator 1 10 Area 10, 12" D Line
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly trusses
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached compressive strength report.
10:00 am Arrived on site. I noticed the framers are installing roof trusses with the help of the crane. I noticed
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 786 of 1851
right away that 4 trusses do not match the Structural and Architectural plans. The 4 trusses span near the
breezeway. I brought this up the Kirt.
12:00 pm IMCO is working on the bulkheading the CJs along with laying out wall templates for EOI. IMCO also has
a crew working on HDPE fusing for the 12" D line from the crowder drain to MH 7.
2:00 pm IMCO pipe crew is working on installing the 12 D line from the cross crowder drain to MH 7. The framers
are currently working on moving the two window openings. One window was approx. 10" offset to the south and
the other window was approx. 2" offset to the south. The HDs are in the wrong location which IMCO will need to
submit a plan on how to drill and epoxy new HDs.
4:30 pm IMCO is continuing to work on bulkheading the CJs and install waterstop for Area 40. They have also
been removing the bulkheads from last weeks placement.
References
Photos (4)
20231009_154354
Taken on Oct 9, 2023, 3:43 PM MDT
Added on Oct 10, 2023, 7:10 AM MDT
Added by Chris Johnson
20231009_111226
Taken on Oct 9, 2023, 11:12 AM MDT
Added on Oct 10, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 787 of 1851
20231009_154402
Taken on Oct 9, 2023, 3:44 PM MDT
Added on Oct 10, 2023, 7:10 AM MDT
Added by Chris Johnson
20231009_111247
Taken on Oct 9, 2023, 11:12 AM MDT
Added on Oct 10, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 788 of 1851
Form detail
#240: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Weld HDPE piping, Install
8" GW line into hatchery building
Area 40 Batch Concrete
IMCO, Carpenters 7 10 Area 30, Mechanical Piping
Area 40, Place Concrete, Template
for Rebar, CJ bulkheads
EOI 4 10 Area 40 Install Top Mat
Forms
Location
Form date Oct 5, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 6, 2023, 8:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 789 of 1851
Crew # Workers # Total
hours
Work performed
MB Welding 1 10 Area 30, Welding pipe supports,
Grating Framing
Totals 17 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 8 Area 40,10, Concrete
IMCO Concrete Truck 1 8 Area 40,10, Concrete
Deere 644J Loader 1 8 Area 40,10, Concrete
Hitachi 85 Excavator 1 10 Area 10, 8" GW Line
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 790 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached compressive strength reports, concrete field report and IMCO batch tickets.
7:00 am IMCO is prepping to batch concrete.
8:00 am IMCO is batching concrete. They are going to place two sections of the raceway drain channel
foundation.
8:20 am First concrete truck is at the pump. They primed the pump and dumped approx. 1 CY in the washout. I
took my sample and tested air. The air was low. IMCO is going to dose the truck.
8:40 am IMCO has dosed the truck for more air and I have taken my second test. This tested at 5% air. They are
going to adjust the second truck. They started to place concrete.
9:45 am The second truck is batched and I have taken my sample. The air was low again at 4.6%. They dosed this
truck as well. I took a second test and it passed with 5.2%.
11:00 am The crew is continuing to place and finish concrete. EOI is onsite working on top mat of rebar at Area 40.
11:20 am IMCO has completed the Area 40 placement and is moved to place a small pipe encasement and then
the retaining wall foundation 3 sections.
11:50 am I tested the truck before they started placing for the retaining wall foundation. It tested a bit high on air
at 7.2%. Due to the location of the placement we all decided to pour it out and make the adjustment on the next
and last truck.
12:20 pm IMCOs last truck has backed up to the pump and starting placing. This will finish the 3rd section of the
retaining wall foundation.
2:00 pm EOI is done for the day and leaving. IMCO is continuing to work on finishing the concrete. They are
placing a U4 finish, Light Broom, on the finished slab per the specifications.
3:00 pm The framers have been working with a larger crew today. They are continuing to stand interior walls and
also started on the beam pockets of the breezeway. IMCO has set the river pump aerator with the crane.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 791 of 1851
5:30 pm IMCO is done for the day. They have sprayed cure on the retaining wall foundation and will be placing
water on the lower drain foundation.
References
Photos (14)
20231005_170528
Taken on Oct 5, 2023, 5:05 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_113522
Taken on Oct 5, 2023, 11:35 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 792 of 1851
20231005_091844
Taken on Oct 5, 2023, 9:18 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_145651
Taken on Oct 5, 2023, 2:56 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 793 of 1851
20231005_170627
Taken on Oct 5, 2023, 5:06 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_170520
Taken on Oct 5, 2023, 5:05 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 794 of 1851
20231005_170502
Taken on Oct 5, 2023, 5:05 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_122421
Taken on Oct 5, 2023, 12:24 PM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 795 of 1851
20231005_113519
Taken on Oct 5, 2023, 11:35 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_111702
Taken on Oct 5, 2023, 11:17 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 796 of 1851
20231005_101331
Taken on Oct 5, 2023, 10:13 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_083802
Taken on Oct 5, 2023, 8:38 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 797 of 1851
20231005_083753
Taken on Oct 5, 2023, 8:37 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
20231005_083743
Taken on Oct 5, 2023, 8:37 AM MDT
Added on Oct 6, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 798 of 1851
Form detail
#239: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Weld HDPE piping, Install
8" GW line into hatchery building
IMCO, Carpenters 7 10 Area 30, Mechanical Piping
Area 40, Template for Rebar, CJ
bulkheads
EOI 4 10 Area 40 Install Top Mat
MB Welding 1 10 Area 30, Welding pipe supports
Forms
Location
Form date Oct 4, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 5, 2023, 6:32 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 799 of 1851
Crew # Workers # Total
hours
Work performed
Totals 17 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, 8" GW Line
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 800 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached compressive strength report
8:00 am IMCO is continuing to work on installing CJ bulkheads and waterstop at Area 40. They plan to place
concrete tomorrow in the lower sections of the foundation slab.
10:00 am IMCO has formed up a small pipe encasement they plan to place tomorrow. It is the last section of pipe
encasement for the 14 cross crowder drains.
12:00 pm EOI has been onsite installing the top matt for Area 40. IMCO has put a small crew on bulkheads at the
retaining wall. They are following the approved rebar plan and installing CJs every 20'.
2:00 pm IMCO has pulled the lid off the large aerator. See attached photos of the media in bags.
4:00 pm The framers have been working on installing the generator room exterior walls along with interior walls.
IMCO is working on a solution for the missing HD and large window location.
5:30 pm IMCO is ready for the placement tomorrow. The pump truck is scheduled to be onsite at 8am.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 801 of 1851
References
Photos (11)
20231004_141158
Taken on Oct 4, 2023, 2:11 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
20231004_082108
Taken on Oct 4, 2023, 8:21 AM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 802 of 1851
20231004_153032
Taken on Oct 4, 2023, 3:30 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
20231004_164604
Taken on Oct 4, 2023, 4:46 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 803 of 1851
20231004_153348
Taken on Oct 4, 2023, 3:33 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
20231004_153042
Taken on Oct 4, 2023, 3:30 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 804 of 1851
20231004_141322
Taken on Oct 4, 2023, 2:13 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
20231004_141204
Taken on Oct 4, 2023, 2:12 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 805 of 1851
20231004_141149
Taken on Oct 4, 2023, 2:11 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
20231004_141106
Taken on Oct 4, 2023, 2:11 PM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 806 of 1851
20231004_104124
Taken on Oct 4, 2023, 10:41 AM MDT
Added on Oct 4, 2023, 5:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 807 of 1851
Form detail
#238: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 3 10 Area 10, Weld HDPE piping
Area 40, Backfill Cross Crowder
Drain
IMCO, Carpenters 7 10 Area 30, Mechanical Piping
Area 40, Template for Rebar, CJ
bulkheads
EOI 4 10 Area 10 Install retaining wall rebar
MB Welding 1 10 Area 30, Welding pipe supports
Forms
Location
Form date Oct 3, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 4, 2023, 7:51 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 808 of 1851
Crew # Workers # Total
hours
Work performed
Totals 15 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 40, Backfill around cross
crowder tail screen
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 809 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on installing waterstop and bulkheads at all the CJs in the Area 40 slab.
9:00 am The framing crew is continuing to work on framing walls. EOI is onsite installing the rebar for the
retaining wall behind Area 60.
11:00 am IMCO is continuing to work on installing mechanical piping inside Area 30. MB welding is also working
on mechanical piping.
1:30 pm Attended weekly meeting.
3:00 pm The framing crew has lifted and set walls earlier today. I will perform an inspection of those walls once
the crew is done for the day. EOI is continuing to work on retaining wall rebar.
5:30 pm All crews are done for the day. I walked the framing and checked for deficiencies. See list below.
9/28
-Breezeway Beam Pockets in wrong location, One not installed at all
-Breezeway HD on single door, Seal plate is cut and missing bottom plate
-Split wood in few locations
-Door header is furred out due to header being installed at wrong elevation, IPC will Accept
-Gaps in blocking
-Nails missing studs, not per shear nailing patter
-Holes in sheathing from picking the walls with crane
10/3
- Large door is missing SP6 brackets, plywood will need to be removed to install bracket
-Large window is missing SPH6 brackets, plywood will need to be removed to install bracket
-Nails missing studs, not per shear nailing pattern
-Drilled holes in slab for bracing
-Window on front wall missing HD
-Window on front wall is approx. 2" offset to the South
-Large window is approx. 10" offset to the South
-Large door is approx. 2" offset to the South
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 810 of 1851
References
Photos (5)
20231003_153123
Added on Oct 4, 2023, 7:04 AM MDT
Added by Chris Johnson
20231003_091550
Added on Oct 4, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 811 of 1851
20231003_105418
Added on Oct 4, 2023, 7:04 AM MDT
Added by Chris Johnson
20231003_091546
Added on Oct 4, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 812 of 1851
20231003_091641
Added on Oct 4, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 813 of 1851
Form detail
#237: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 3 10 Area 10, Retaining wall Foundation
Area 40, Backfill Cross Crowder
Drain
IMCO, Carpenters 7 10 Area 10, Retaining Wall Foundation
Area 30, Mechanical Piping
Area 40, Template for Rebar, CJ
bulkheads
EOI 4 10 Area 40 Install rebar
Forms
Location
Form date Oct 2, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 2, 2023, 5:33 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 814 of 1851
Crew # Workers # Total
hours
Work performed
MB Welding 1 10 Area 30, Welding pipe supports
Totals 15 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 40, Backfill around cross
crowder tail screen
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 815 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO is working on installing the waterstop for the CJ joints in Area 40. EOI is onsite installing rebar in
the lower drain section of Area 40. IMCO is also working on installing the 36" drain pipe penetration for the lower
drain section. The framers are continuing to work framing Area 60.
1:00 pm Kevin, EOI, had some questions regarding the pipe penetration rebar. After reviewing the approved
submittal I located a detail showing what was approved for the rebar reinforcement around the large pipe
penetration. He plans to install it per the detail. A team has moved over and started to form up the retaining wall
foundation behind Area 60.
3:00 pm IMCO is working on installing the pipe penetrations for each raceway drain. These are set at ~4" below
finished floor height. I spoke to Steve regarding the 1/5 slope to the drain. He was aware of it.
4:00 pm IMCO is continuing to work on the CJs at area 40. EOI has moved a couple of guys over to tie the rebar for
the retaining wall foundation behind Area 60.
5:00 pm IMCO is done for the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 816 of 1851
References
Photos (6)
20231002_112729
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
20231002_151943
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 817 of 1851
20231002_153709
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
20231002_112817
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 818 of 1851
20231002_112656
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
20231002_151938
Added on Oct 2, 2023, 5:06 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 819 of 1851
Form detail
#236: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 3 10 Area 10, Retaining wall foundation
IMCO, Carpenters 6 10 Area 30, Mechanical Piping
Area 40, Template for Rebar,
Forming of Fish lift walls
EOI 4 10 Area 40 Install rebar
Totals 13 30
Forms
Location
Form date Sep 29, 2023
Description Area 10, Area 30, Area 40
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 29, 2023, 3:04 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 820 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 10, Excavate for Retaining
Wall
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 821 of 1851
Notes
9:00 am IMCO is working on installing a template for the back wall for the rebar guys to install the vertical bars.
EOI is onsite working on top mat of the lower slab at Area 40 along with finishing the lower mat of the rest of Area
40.
11:00 am IMCO has a small operator crew working on retaining wall foundation behind Area 60.
12:00 pm Left site to return concrete cylinders to lab.
References
Photos (5)
20230929_105725
Added on Sep 29, 2023, 3:03 PM MDT
Added by Chris Johnson
20230929_091826
Added on Sep 29, 2023, 3:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 822 of 1851
20230929_092018
Added on Sep 29, 2023, 3:03 PM MDT
Added by Chris Johnson
20230929_092016
Added on Sep 29, 2023, 3:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 823 of 1851
20230929_105731
Added on Sep 29, 2023, 3:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 824 of 1851
Form detail
#235: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Retaining wall foundation
Area 40, Batch Concrete
IMCO, Carpenters 6 10 Area 30, Metal framing, Aerator
install
Area 40, Cross Crowder Tail Screen
Wall placement, Forming of Fish lift
walls
Dusty B Framing 6 10 Area 60, Framing
Forms
Location
Form date Sep 28, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 29, 2023, 8:51 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 825 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 10 Area 40 Install rebar
MB Welding 1 10 Area 30, Metal Framing
Totals 20 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Retaining wall foundation
IMCO Concrete Truck 1 4 Area 40, Concrete
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 10, Retaining wall foundation
Area 40, Batch Concrete
Hitachi 85 Excavator 1 10 Area 10, Excavate for Retaining
Wall
Dump Truck 1 10 Area 10, Retaining wall foundation
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 826 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is prepping to start batching concrete. The framers are onsite to continue framing walls at Area
60.
9:00 am IMCO has batched 5 CY. I tested the truck and all was in spec with the exception of the slump. The slump
was at 7". It was allowed to be placed due to the location of placement. They are placing the first lift of the tail
screen for the cross crowder walls. This will bring the elevation of the concrete to the bottom of foundation to
allow backfilling. Once backfilled they can finish the rebar for the foundation.
10:00 am IMCO has completed the placement. They are going to work on installing the water stop and finish the
concrete.
11:00 am EOI is onsite continuing to install rebar for the foundation. They are starting to install the top mat on the
lower foundation of Area 40.
1:00 pm The framing crew has left for the week. I have walked the work they have completed and compiled a list
of deficiencies. I will add to the bottom of this report with photos.
3:00 pm EOI is continuing to install rebar at Area 40.
5:00 pm Most of the IMCO crew has left for the day. A small crew will be onsite tomorrow working on fish lift
forming.
Framing Deficiencies as of 9/28
-Breezeway Beam Pockets in wrong location, One not installed at all
-Breezeway HD on single door, Seal plate is cut and missing bottom plate
-Split wood in few locations
-Door header is furred out due to header being installed at wrong elevation
-Gaps in blocking
-Nails missing studs, not per shear nailing patter
-Holes in sheathing from picking the walls with crane
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 827 of 1851
References
Photos (20)
20230928_135003
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_140107
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 828 of 1851
20230928_135139
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_135008
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 829 of 1851
20230928_091535
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_135005
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 830 of 1851
20230928_133945
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_134951
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 831 of 1851
20230928_135137
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_135232
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 832 of 1851
20230928_134919
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_154924
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 833 of 1851
20230928_135145
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_135213
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 834 of 1851
20230928_134317
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_134508
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 835 of 1851
20230928_140052
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_140358
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 836 of 1851
20230928_140019
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
20230928_134313
Added on Sep 28, 2023, 4:05 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 837 of 1851
Form detail
#234: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, Retaining wall foundation
IMCO, Carpenters 6 10 Area 30, Metal framing, Aerator
install
Area 40, Cross Crowder Tail Screen
Wall Forming
Dusty B Framing 2 10 Area 60, Framing
EOI 2 10 Area 40 Install rebar
Forms
Location
Form date Sep 27, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 28, 2023, 9:39 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 838 of 1851
Crew # Workers # Total
hours
Work performed
MB Welding 1 10 Area 30, Metal Framing
Totals 16 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 4 to MH5
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 10, Retaining wall foundation
Hitachi 85 Excavator 1 10 Area 10, Excavate for Retaining
Wall
Dump Truck 1 10 Area 10, MH 4 to MH 5
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 839 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day Compressive Break report from Area 60 Incubation Slab.
8:00 am IMCO is continuing to work on forming the tail screen 1st wall section for a placement tomorrow. This
will bring the walls up to the bottom of foundation slab grade to allow them to backfill in preparation for the
foundation placement.
9:00 am Attended weekly meeting.
10:00 am The framers are continuing to work on framing walls at Area 60. Yesterday they used the crane to pick
and set exterior walls.
12:00 pm MB Welding is onsite and continuing to work on Area 30 support framing.
1:00 pm EOI is onsite working on installing the bottom mat foundation rebar for Area 40. Kevin and I spoke
regarding Schnabel's response on the CJ detail and clearances. The detail calls for 4" of clearance but they have
allowed up to 2". After laying out the rebar he will have to cut multiple bars a few inches to provide this clearance
away from the CJs. See GCOR-1-1 for email correspondence.
2:00 pm IMCO is continuing to work on forming for the tail screen drain for the cross crowder. They have all the
rebar including the trim bar installed.
4:00 pm IMCO is having to lift some of the rebar and set it with a laser level to ensure it is at the right elevation.
They are using concrete blocks to keep the rebar at the right elevation. I have noticed a few locations where there
is less than 3" of clearance between rebar and ground. I have asked Kole if he would walk it with me tomorrow
after the concrete placement to discuss fixing this before more rebar is installed.
5:00 pm IMCO has filled the spray bar line with water for an initial informational only test to check for leaks.
IMCO has placed the aerator for the well pumps on Area 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 840 of 1851
References
Photos (14)
20230927_171926
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_154216
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 841 of 1851
20230927_154229
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_154213
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 842 of 1851
20230927_160331
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_163848
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 843 of 1851
20230927_155636
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_160335
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 844 of 1851
20230927_155702
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_163909
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 845 of 1851
20230927_160455
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_154218
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 846 of 1851
20230927_155639
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
20230927_170908
Added on Sep 27, 2023, 6:10 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 847 of 1851
Form detail
#233: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 4 to MH 5
IMCO, Carpenters 6 10 Area 40, Cross Crowder Tail Screen
Wall Forming
Dusty B Framing 2 10 Area 60, Framing
EOI 2 10 Area 40 Install rebar
Totals 15 40
Forms
Location
Form date Sep 25, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 27, 2023, 6:56 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 848 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 4 to MH5
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 10, Retaining wall foundation
Hitachi 85 Excavator 1 10 Area 10, Excavate for Retaining
Wall
Dump Truck 1 10 Area 10, MH 4 to MH 5
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 849 of 1851
Notes
11:00 am IMCO is continuing to excavate for the run of pipe from MH 4 to MH 5. EOI is onsite working on
installing the rebar for Area 40 foundation.
12:00 pm The framing crew is onsite and continuing to work on framing walls at Area 60.
1:00 pm IMCO is working on forming the walls of the tail screen for the cross crowder. While checking the
clearances of the tail screen embed frame, I noticed there was no way to attach the back of it to the wall. I asked
Jake Kreglo to check into it. We walked it and determined something will need to be done to attach it.
2:00 pm IMCO has a crew working on excavating for the foundation of the retaining wall. The carpenter crew is
continuing to work on forming the first lift of the cross crowder tail screen walls. They are currently working on
installing the piping through the walls.
3:00 pm IMCO is continuing to work on excavating for MH 5. They have found existing drainage steel pipe. Kirt
said it was very corroded and broke very easy. He removed a section of it with ease. You can clearly see the steel is
pitted with holes and very rusty.
4:30 pm IMCO is starting to clean up for the day. The crew will continuing forming for the first lift of the tail
screen walls tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 850 of 1851
References
Photos (7)
20230925_111434
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
20230925_140130
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 851 of 1851
20230925_140137
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
20230925_132011
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 852 of 1851
20230925_132016
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
20230925_135326
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 853 of 1851
20230925_135330
Added on Sep 27, 2023, 6:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 854 of 1851
Form detail
#232: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Forms
Location
Form date Sep 22, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 22, 2023, 12:31 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 855 of 1851
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Water Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day Concrete compressive strength report for Area 60 Office Area Slab.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 856 of 1851
Form detail
#231: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 4 to MH 5
IMCO, Carpenters 6 10 Area 40, Weld Waterstop
Dusty B Framing 2 10 Area 60, Framing
EOI 2 10 Area 40 Install rebar
Totals 15 40
Forms
Location
Form date Sep 21, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 22, 2023, 9:06 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 857 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 4 to MH5
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 10, Retaining wall foundation
Hitachi 85 Excavator 1 10 Area 10, Excavate for Retaining
Wall
Dump Truck 1 10 Area 10, MH 4 to MH 5
Kobelco 1100G Crane 1 10 Area 40, Fly rebar
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 858 of 1851
Notes
8:00 am I noticed IMCO was starting to strip the forms from yesterdays placement. I informed Sean that the
forms should not be stripped for 48 hours per the specifications.
9:00 am I spoke to the framing crew. They stood up a few of the walls and I noticed multiple exposed nails
"shiners" on both the sheathing and framing. I informed them these shiners were will not be accepted. They said
they will make it right. I then told them because these are shear walls they will need to remove the Tyvek they
installed so a proper shear nailing inspection can be done. I also informed Kurt as well.
9:30 am I noticed IMCO has installed a few of the drains for the for cross crowder. IMCO was working on a
solution to connect the 6" drains they submitted on to the 8" pipe, which was part of the submittal comments on
approval. I noticed they used mastic to seal the gap between 8" and 6". I have sent an email to Bryant and Zack for
comments on the use of this method. See attached photos.
10:00 am While doing some rebar inspection as EOI was installing the bottom mat for Area 40, I noticed they
were not meeting the 4" clear space on splices from the CJs. I brought this up to Kevin. He said he would fix them.
He is continuing to install rebar for both the cross crowder tail screen drain and the holding facility base slab.
12:00 pm The crews are starting to form up the small walls for the cross crowder tail screen drain. They want to
pour the walls up the bottom of the base slab elevation. This will allow them to backfill and compact in preparation
for the base slab rebar.
1:00 pm IPC troubleman is onsite to move the power for the existing hatchery building. This will allow IMCO to
remove the pole that is in conflict with the retaining wall. Kurt informed me that nobody will be onsite tomorrow. I
am leaving the site to return concrete cylinders from yesterdays placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 859 of 1851
References
Photos (14)
20230921_092135
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_084114
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 860 of 1851
20230921_082532
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_092153
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 861 of 1851
20230921_084119
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_083857
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 862 of 1851
20230921_084108
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_092109
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 863 of 1851
20230921_091223
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_122521
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 864 of 1851
20230921_083844
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_092111
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 865 of 1851
20230921_092143
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
20230921_091124
Added on Sep 21, 2023, 12:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 866 of 1851
Form detail
#229: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Sep 20, 2023
Description Area 60, Area 40
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 20, 2023, 6:42 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 867 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Compressive Strength report.
Not on site today.
I was informed that IMCO plans 3 separate placements tomorrow. They plan to place the generator room slab, the
upper fish lift slab and the lower slab for the cross crowder drain.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 868 of 1851
Form detail
#230: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10, MH 4 to MH 5
Area 40,60 Batch concrete
IMCO, Carpenters 6 10 Area 40, 60 Place Concrete, Weld
Waterstop
Dusty B Framing 2 10 Area 60, Framing
MB Welding 1 10 Area 30, Welding Platform Frame
Forms
Location
Form date Sep 20, 2023
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 21, 2023, 8:12 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 869 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 10 Area 40 Install rebar
Totals 16 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, MH 4 to MH5
IMCO Concrete Truck 1 5 Area 40, 60 concrete
IMCO Concrete Truck 1 5 Area 40, 60 concrete
Deere 644J Loader 1 5 Area 40, 60 Batch concrete
Hitachi 85 Excavator 1 Area 10, Excavate for Retaining
Wall
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Platform Frame
Area 40, Fly rebar
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 870 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is Concrete testing report and IMCO batch tickets.
7:00 am IMCO plans to place the Generator room slab at Area 60 along with the Cross crowder drain slab and the
upper fish lift slab at Area 40. The crews are still working on the drain slab and fish lift slab. I started my inspection
of the rebar for the drain slab. I noticed some rebar was missing. I spoke to Kevin at EOI and he started to get
working on it. IMCO is still working on the water stop install for the placement as well.
8:00 am The detailed drawings from the rebar submittal do not clearly show the slab rebar correctly. IMCO and
EOI had to make some revisions to what they think it should be. After looking it over and speaking to them they
added a few more bars as we did our best to interpret the plans the best we could. I have taken multiple photos for
documentation.
9:00 am The crew is still working on the water stop for the upper fish lift slab. They have batched concrete for the
generator room.
9:30 am I have tested the concrete for the generator room. The concrete tested in spec at the low end on air. It
was a lower than allowed on temp as well. They started to place the concrete. Once I was done with my test I
checked the temp of the concrete once it was placed. It was 62. I spoke to IMCO regarding the concrete temps for
future pours. They informed me they are working on getting a boiler out here to warm the water.
11:00 am IMCO has placed the lower cross crowder slab and they are currently working on placing the upper fish
lift slab.
12:00 pm IMCO came up approx. 2 cy short. They batched one additional truck to finish off the slab placement.
2:00 pm IMCO is working on finishing the concrete now. The framers are on site. They have stood some walls and
continuing to frame others. EOI is working on installing rebar for Area 40 slab. They are working on the bottom
mat now. IMCO has a small crew working on excavating for the pipe line from MH 4 to MH 5. They have also
started to excavate for the retaining wall behind Area 60.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 871 of 1851
References
Photos (12)
20230920_095451
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_095503
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 872 of 1851
20230920_095347
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_095338
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 873 of 1851
20230920_095516
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_084136
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 874 of 1851
20230920_102751
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_095422
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 875 of 1851
20230920_095410
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_095402
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 876 of 1851
20230920_093127
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
20230920_074513
Added on Sep 21, 2023, 7:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 877 of 1851
Form detail
#228: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Excavate grade
IMCO, Carpenters 6 10 Area 40, Form for foundation, Weld
Waterstop
Dusty B Framing 2 10 Area 60, Framing
MB Welding 1 10 Area 30, Welding Platform Frame
EOI 2 10 Area 40 - 60, Unload rebar
Forms
Location
Form date Sep 18, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 18, 2023, 9:36 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 878 of 1851
Crew # Workers # Total
hours
Work performed
Totals 16 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 40, Foundation
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Platform Frame
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 879 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See Attached HMH Compressive Strength Report.
9:30 am IMCO carpenters are working on welding waterstop for the Area 40 Construction Joints. EOI is onsite
unloading rebar shipment. The rebar is for Area 40.
11:00 am IMCO operators are working on grading the upper fish lift slab. They completed the generator room fill,
vapor barrier and sand. It is ready for rebar to be installed.
12:00 pm The framing crew is onsite continuing to work on framing walls at Area 60.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 880 of 1851
References
Photos (2)
20230918_103700
Added on Sep 18, 2023, 9:26 PM MDT
Added by Chris Johnson
20230918_093747
Added on Sep 18, 2023, 9:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 881 of 1851
Form detail
#227: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Excavate grade, Pipe
Encasement
IMCO, Carpenters 6 10 Area 40, Form for foundation
Dusty B Framing 2 10 Area 60, Framing
MB Welding 1 10 Area 30, Welding Platform Frame
Totals 14 40
Forms
Location
Form date Sep 14, 2023
Description Area 10, Area 30, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 15, 2023, 11:51 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 882 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 3 Area 40, Pipe Encasement
IMCO Concrete Truck 1
Deere 644J Loader 1 3 Batch Concrete
Hitachi 85 Excavator 1 10 Area 40, Foundation
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Platform Frame
Bomag Roller 1
Water Truck 1 10 Dust Control, Compaction
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 883 of 1851
Notes
See Attached HMH Compressive Strength Reports.
8:00 am The framing crew is continuing to work on framing walls for the hatchery building.
9:00 am IMCO is stripping forms from the piers at Area 60. The carpenter crews are cleaning up the site. IMCO
dirt crew has batched 1 CY of concrete for a small pipe encasement for under the upper fish lift slab. Due to the
small quantity the concrete was not tested.
11:30 pm IMCO is starting to backfill the generator room. Vale has completed the conduit install for the room.
IMCO is placing general fill at 12" lifts and compacting.
1:00 pm A carpenter crew is continuing to work on forming the perimeter of Area 40 foundation. Another crew is
installing rigid insulation on the interior stem wall of the generator room.
4:00 pm IMCO has been working on backfilling the generator room for the slab.
References
Photos (4)
20230914_081619
Added on Sep 15, 2023, 11:49 AM MDT
Added by Chris Johnson
20230914_130039
Added on Sep 15, 2023, 11:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 884 of 1851
20230914_125513
Added on Sep 15, 2023, 11:49 AM MDT
Added by Chris Johnson
20230914_095700
Added on Sep 15, 2023, 11:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 885 of 1851
Form detail
#226: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, CDF Spray bar line,
Excavate grade
IMCO, Carpenters 6 10 Area 40, Form for foundation
Dusty B Framing 2 10 Area 60, Framing
MB Welding 1 10 Area 30, Welding Platform Frame
Vale Electric, Electricians 1 10 Area 60, Generator Room Conduit
Forms
Location
Form date Sep 13, 2023
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 14, 2023, 7:53 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 886 of 1851
Crew # Workers # Total
hours
Work performed
Totals 15 50
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Spray Bar line
IMCO Concrete Truck 1 4 Area 40, CDF
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 40, Foundation
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Platform Frame
Bomag Roller 1
Water Truck 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 887 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 Day compressive break report from Area 60 Incubation Drain
7:00 am IMCO is planning to continue forming for the foundation of Area 40. They are going to get the perimeter
foundation in then have EOI onsite to tie the rebar.
10:00 am The frame crew is continuing to work on framing the walls of the office area at Area 60. Vale is onsite to
install the conduit for the generator room. IMCO has backfilled to top of footing for the conduit grade.
12:00 pm IMCO has installed the two pipes to the upper fish lift slab. These pipes have been switched from SS to
Sch 80 PVC. They are working on the rebar for the pipe encasement.
2:00 pm IMCO has started to place CDF for the pipe encasement of the spray bar line under Area 40.
4:30 pm IMCO has completed the CDF placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 888 of 1851
References
Photos (9)
20230913_131755
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
20230913_140747
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 889 of 1851
20230913_152625
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
20230913_133345
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 890 of 1851
20230913_140739
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
20230913_150234
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 891 of 1851
20230913_150325
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
20230913_131749
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 892 of 1851
20230913_090202
Added on Sep 14, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 893 of 1851
Form detail
#225: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Spray bar line
IMCO, Carpenters 6 10 Area 40, Form for foundation
Dusty B Framing 2 10 Area 60, Framing
MB Welding 1 10 Area 30, Welding Platform Frame
Totals 14 40
Forms
Location
Form date Sep 12, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 13, 2023, 7:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 894 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Spray Bar line
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 40, Foundation
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Platform Frame
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 895 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day compressive break report for the Incubation Drain Slab.
8:00 am IMCO is working on setting the spray bar line in place. They have informed me they plan to encase this
line with CDF once they get it set and in final placement. IMCO is also working on setting the two pipes for the
upper fish lift slab.
10:00 am The framing crew is continuing to work on the walls for the office side of the hatchery building. They are
sheeting these walls per W2 shear wall on GS-3. MB Welding is onsite today to continue welding the platform
framing to the embeds at Area 30.
1:00 pm IMCO carpenters have been working on forming the foundation for Area 40.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 896 of 1851
References
Photos (4)
20230912_082726
Added on Sep 13, 2023, 7:54 AM MDT
Added by Chris Johnson
20230912_093946
Added on Sep 13, 2023, 7:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 897 of 1851
20230912_113849
Added on Sep 13, 2023, 7:54 AM MDT
Added by Chris Johnson
20230912_082721
Added on Sep 13, 2023, 7:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 898 of 1851
Form detail
#224: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Spray bar line
Area 60, Batch Concrete
IMCO, Carpenters 6 10 Area 40, Form for foundation
Area 60, Place Generator room
stem wall, place piers
Dusty B Framing 2 10 Area 60, Framing
Totals 13 30
Forms
Location
Form date Sep 11, 2023
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 12, 2023, 7:34 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 899 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Spray Bar line
IMCO Concrete Truck 1 6 Area 60, Concrete
IMCO Concrete Truck 1 6 Area 60, Concrete
Deere 644J Loader 1 6 Area 60, Concrete
Hitachi 85 Excavator 1 10 Area 40, Foundation
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 900 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached HMH Concrete Field Report and IMCO batch tickets from todays placement.
7:30 am Arrived on site. IMCO crew is making preparations for the concrete placement of the generator room
stem wall and the piers at Area 60. They are also hoping to place pipe encasement of the last 3 drains of the cross
crowder channel. They are starting to batch concrete now.
9:00 am I tested the first truck with everything in spec. The crew is continuing to place concrete. These were
formed over the weekend. As they were pouring I tried to check measurements. They all seem to be per plan.
11:00 am IMCO was able to capture the stem wall, piers and the pipe encasement today. They are working on
setting the embeds for the piers now.
1:00 pm IMCO is done with finishing the concrete. They are starting to work on forming for Area 40 slab
foundation now. Meanwhile the framers are continuing to frame walls for the office side of the hatchery building.
2:00 pm Sean has informed me they want to start excavating for the retaining wall this week. I checked with Zack
and the power pole is scheduled to be removed on Thursday of this week.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 901 of 1851
References
Photos (14)
20230911_114838
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_093933
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 902 of 1851
20230911_095740
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_090842
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 903 of 1851
20230911_120026
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_082220
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 904 of 1851
20230911_082304
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_134118
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 905 of 1851
20230911_082306
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_090743
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 906 of 1851
20230911_090812
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_090823
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 907 of 1851
20230911_082228
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
20230911_090837
Added on Sep 12, 2023, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 908 of 1851
Form detail
#223: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Spray bar line
Area 50, Fish lift piping
IMCO, Carpenters 6 10 Area 60, Form Piers, Form Stem
wall
Dusty B Framing 3 10 Area 60, Framing
Totals 14 30
Forms
Location
Form date Sep 8, 2023
Description Area 10, Area 40, Area 50, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 11, 2023, 11:09 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 909 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Spray Bar line
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 910 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am The framers are onsite and they are starting to frame exterior walls for Area 60. IMCO is going to work on
drain piping for the cross crowder. They have discovered that the pipe encasement they placed Tuesday was set to
high and interferes with the drain line. They will have to chip our concrete for the drain piping to clear.
9:00 am IMCO carpenters are working on laying out the piers at Area 60. They also are working on forming the
stem wall for the generator room. I am told they will be here tomorrow as well prepping for the Monday pour.
11:00 am I spoke to Kirt regarding the green cutting of the slab. He said he would get someone working on it
today.
1:00 pm Jake and Steve came and spoke to me regarding the locations they thought were good for the green cuts.
We marked up a plan sheet and I asked them to make sure Kirt was ok with it before they started working on it.
Left site to return concrete cylinders.
I was informed a crew will be here tomorrow finishing the forming for Mondays concrete placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 911 of 1851
References
Photos (3)
20230908_114806
Added on Sep 11, 2023, 11:09 AM MDT
Added by Chris Johnson
20230908_095248
Added on Sep 11, 2023, 11:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 912 of 1851
20230908_095244
Added on Sep 11, 2023, 11:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 913 of 1851
Form detail
#222: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Excavate cross drain
channel
Area 60, Batch Concrete
IMCO, Carpenters 6 10 Area 30, Interior piping
Area 60, Place slab, form piers
Dusty B Framing 3 10 Area 60, Laying out walls
Totals 14 30
Forms
Location
Form date Sep 7, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 8, 2023, 7:02 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 914 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Excavate for Lower Cross
Drain Channel
IMCO Concrete Truck 1 5 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Batch Concrete
Deere 644J Loader 1 10 Area 60, Batch Concrete
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Dynapac Roller 1 10 Compaction onsite
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 915 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is going to be finishing the CJ, Checkerboard concrete slab at Area 60 today. They have one more
for the generator room once they get the stem wall poured. Pump truck is onsite and they are going to start
batching concrete.
9:00 am I have tested the first truck and it failed on slump. See concrete test form.
10:00 am After testing the second truck it failed on air. I tested the third truck and it was in spec so they poured it
out.
11:00 am I spot checked the 4th and last truck. It tested in spec. IMCO is working on finishing the concrete now.
The framing crew is onsite and working on laying out the walls. There was discussion this morning regarding the
double seal plate at the bottom of the walls. I checked their stud length and I noticed it was 1.5" too long. The crew
was unaware of the double plate at the bottom. It clearly shows the double plate on 60 S 1. The crew is going to
make the adjustments to accommodate double bottom plates.
2:00 pm IMCO is continuing to work on piping inside Area 30. MB welding is onsite welding the brackets to the
embeds for the suspended floor.
4:00 pm IMCO is starting to work on the layout for Area 40 foundation.
5:00 pm IMCO is done for the day. They have placed burlap over the concrete and sprayed it all with water for
curing.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 916 of 1851
References
Photos (8)
20230907_125557
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
20230907_100949
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 917 of 1851
20230907_154932
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
20230907_100940
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 918 of 1851
20230907_132543
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
20230907_132555
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 919 of 1851
20230907_132558
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
20230907_133150
Added on Sep 8, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 920 of 1851
Form detail
#221: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Fuse HDPE pipe for the
Spray Bar line
Area 60, Batch Concrete
IMCO, Carpenters 6 10 Area 30, Interior piping
Area 40, Excavate for Lower Cross
Drain, Concrete pipe encasement
Area 60, Place slab and footing
Dusty B Framing 3 10 Area 60, Laying out walls
Forms
Location
Form date Sep 6, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 7, 2023, 6:08 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 921 of 1851
Crew # Workers # Total
hours
Work performed
Totals 14 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 40, Excavate for Lower Cross
Drain Channel
IMCO Concrete Truck 1 5 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Batch Concrete
Deere 644J Loader 1 10 Area 60, Batch Concrete
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Dynapac Roller 1 10 Compaction onsite
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 922 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day compressive break report from Area 60 1st Incubation Slab placement.
7:30 am IMCO is getting ready for the concrete placement. Pump truck is onsite.
8:00 am IMCO is continuing to work on interior piping at Area 30. They area currently getting the 24" overflow box
secured to the wall.
9:00 am IMCO has batched the first truck. I tested the truck and all passed. They are going to place concrete in the
pipe encasement then start placing the slab.
11:00 am IMCO has completed the pour for today. They captured a pipe encasement at Area 40, Slab and Footing
at Area 60. The footing is for the generator room. The framing crew is onsite to continue laying out walls.
1:00 pm IMCO is continuing to work on finishing the concrete. Another crew is working on excavating for the
cross drain channel and stairs.
2:00 pm IMCO crew is continuing to install interior piping inside Area 30.
3:00 pm IMCO crew is completing the finish on the slab. They are going to start working on prepping for
tomorrow concrete placement. They want to finish the slab tomorrow. They are also working on prepping the
sonotube piers. Dusty B framers are working on laying out the walls and checking HD points.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 923 of 1851
References
Photos (8)
20230906_081154
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
20230906_124350
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 924 of 1851
20230906_105628
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
20230906_105754
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 925 of 1851
20230906_104755
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
20230906_091743
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 926 of 1851
20230906_105625
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
20230906_101851
Added on Sep 7, 2023, 6:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 927 of 1851
Form detail
#220: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 40, Fuse HDPE pipe for the
Spray Bar line
IMCO, Carpenters 6 10 Area 30, Interior piping
Area 40, Slab Forming
Area 60, Set Sonotubes for Piers
MB Welding 1 10 Area 30, Pipe Supports
Dusty B Framing 3 3 Area 60, Start laying out walls
Forms
Location
Form date Sep 5, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 6, 2023, 6:38 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 928 of 1851
Crew # Workers # Total
hours
Work performed
Totals 15 33
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Install piping
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 40, Spray Bar Line
Hitachi 85 Excavator 1 10 Area 40, Spray Bar Line
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Dynapac Roller 1 10 Compaction onsite
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 929 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is working on fusing the HDPE pipe for the spray bar lines.
11:00 am MB Welding is onsite. I spoke to him about keeping an eye on the embeds while he was welding the
supports on them. We spoke about not overheating the embeds to prevent spalling and cracking of the concrete
from the heat. IMCO is working inside Area 30 getting the overflow box set and installed.
1:00 pm IMCO carpenters are working on setting the sono tubes for the piers. I asked them if they set the grade
elevation yet. They were not sure and thought they could cut the tubes. I informed them the drawings call for 48"
of sono tube foundation so the grade will need to be excavated and the sono tubes not to be cut.
3:00 pm As IMCO was forming the foundation on the NE corner of Area 40, for the stairs, I noticed the valves
were inside the foundation. This is not per plan IMCO is checking measurements. The framing sub contractor is
onsite and is working on laying out walls on the foundation at Area 60
4:00 pm It was determined that the valves were not installed in the correct location. They are holding off on
working at this location.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 930 of 1851
References
Photos (4)
20230905_101643
Taken on Sep 5, 2023, 10:16 AM MDT
Added on Sep 6, 2023, 6:35 AM MDT
Added by Chris Johnson
20230905_144220
Taken on Sep 5, 2023, 2:42 PM MDT
Added on Sep 6, 2023, 6:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 931 of 1851
20230905_144312
Taken on Sep 5, 2023, 2:43 PM MDT
Added on Sep 6, 2023, 6:35 AM MDT
Added by Chris Johnson
20230905_144306
Taken on Sep 5, 2023, 2:43 PM MDT
Added on Sep 6, 2023, 6:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 932 of 1851
Form detail
#219: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 2 Batch Attempt
IMCO, Carpenters 6 2
Totals 16 4
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Sep 1, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 1, 2023, 9:28 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 933 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 934 of 1851
Notes
Attached is the Area 60 Office Slab 7 day compressive break report.
7:00 am IMCO is prepping for concrete. Pump truck is onsite.
9:00 am IMCO was unable to fill the cement silo from the cement storage due to missing a fitting. They are
cancelling the placement today. The crew is leaving for the weekend.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 935 of 1851
Form detail
#218: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 10 Area 10, Install Piping from Fish lift
to vault
Area 40, Excavate for thickened
sections
IMCO, Carpenters 6 10 Area 30, Interior piping
Area 40, Begin pipe encasement
for fish lift piping
Area 60, Install bulkheads at CJs,
Form Curb
Forms
Location
Form date Aug 31, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 1, 2023, 5:59 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 936 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 8 Area 60, Generator room footing
and stem wall rebar
Area 40, Pipe encasement, fish lift
Totals 18 28
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Install piping
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 40, Thickened edges
excavation
Hitachi 85 Excavator 1 Area 40, Thickened edges
excavation
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 937 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1
Dynapac Roller 1 10 Compaction onsite
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is stripping the bulkheads from yesterdays concrete placement. They placed burlap and plastic
over the concrete last night to cure.
8:30 am EOI is onsite to install the rebar for the generator room footing and stem wall.
10:00 am IMCO has a crew inside Area 30 continuing to install the piping. They are currently working on laying
out and drilling the anchors for the 24" overflow box.
12:00 pm IMCO is continuing to work on curbs and bulkheads for tomorrow planned concrete placement at Area
60.
2:00 pm EOI is done for the day. They were able to also install the rebar for the pipe encasement for the supply
like to the fish lift. IMCO crew is working on installing the weir piping as well.
4:00 pm IMCO is continuing to work on interior piping at Area 30. The holes are being drilled and prepped for
epoxy set. IMCO carpenters are ready for tomorrows placement. They have moved over to start setting batter
boards for Area 40. IMCO operators have started excavating for the spray bar line.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 938 of 1851
References
Photos (12)
20230831_162018
Taken on Aug 31, 2023, 4:20 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_162006
Taken on Aug 31, 2023, 4:20 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 939 of 1851
20230831_141156
Taken on Aug 31, 2023, 2:11 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_090125
Taken on Aug 31, 2023, 9:01 AM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 940 of 1851
20230831_080506
Taken on Aug 31, 2023, 8:05 AM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_161957
Taken on Aug 31, 2023, 4:19 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 941 of 1851
20230831_160101
Taken on Aug 31, 2023, 4:01 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_160032
Taken on Aug 31, 2023, 4:00 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 942 of 1851
20230831_141152
Taken on Aug 31, 2023, 2:11 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_131744
Taken on Aug 31, 2023, 1:17 PM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 943 of 1851
20230831_090128
Taken on Aug 31, 2023, 9:01 AM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
20230831_080519
Taken on Aug 31, 2023, 8:05 AM MDT
Added on Sep 1, 2023, 5:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 944 of 1851
Form detail
#217: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 10 Area 10, Fuse HDPE drain piping
from fish lift
Area 40, Excavate for thickened
sections
Area 60, Batch concrete
IMCO, Carpenters 6 10 Area 30, Interior piping
Area 40, Form Cross Channel Trail
Screen Slab
Area 60, Form Generator room,
Place Concrete Slab
Forms
Location
Form date Aug 30, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 31, 2023, 7:54 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 945 of 1851
Crew # Workers # Total
hours
Work performed
Totals 16 20
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Set Drain vault from Fish
Lift
Area 60, Backfill Generator Room
Area
IMCO Concrete Truck 1 5 Area 40 Slab Placement
IMCO Concrete Truck 1 5 Area 40 Slab Placement
Deere 644J Loader 1 10 Area 40, Batch Concrete
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 40, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 946 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1 10 Compaction onsite
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1 8 Area 10, Grade subgrade
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Field Report and IMCO batch tickets from todays placement.
7:30 am IMCO is starting to batch concrete. They are going to place between CJs in the Incubation area and
chiller room at Area 60. They will also capture half of the breezeway slab.
10:00 am IMCO is placing WRDA concrete now with a pump truck.
12:00 pm IMCO placed ~20 CY of concrete. The first test the air was to low. They dosed the truck and I tested
again. The second test was in spec but at the low end. They poured it out. I tested the second truck to check for any
modifications. The concrete air was in spec at 6%. They continued to place concrete.
1:30 pm IMCO has a crew inside Area 30 working on the overflow box install for the drain inside the river intake
chamber. The crew is continuing to work on finishing the concrete they placed.
2:00 pm IMCO carpenter crew is continuing to work on forming the generator room footing. They are hoping to
get it poured Friday when they place the other side of the CJs in the Area 60 slab.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 947 of 1851
References
Photos (5)
20230830_110140
Taken on Aug 30, 2023, 11:01 AM MDT
Added on Aug 31, 2023, 7:54 AM MDT
Added by Chris Johnson
20230830_104058
Taken on Aug 30, 2023, 10:40 AM MDT
Added on Aug 31, 2023, 7:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 948 of 1851
20230830_102107
Taken on Aug 30, 2023, 10:21 AM MDT
Added on Aug 31, 2023, 7:54 AM MDT
Added by Chris Johnson
20230830_082222
Taken on Aug 30, 2023, 8:22 AM MDT
Added on Aug 31, 2023, 7:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 949 of 1851
20230830_133642
Taken on Aug 30, 2023, 1:36 PM MDT
Added on Aug 31, 2023, 7:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 950 of 1851
Form detail
#216: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 10 Area 10, Set Drain vault from fish
lift
Area 40, Excavate for thickened
sections
Area 60, Backfill for Generator
room
IMCO, Carpenters 6 10 Area 30, Chip Surface defects,
Begin interior piping
Area 40, Form Cross Channel Trail
Screen Slab
Area 60, Bulkhead for CJ in slab,
Form Curbs
Forms
Location
Form date Aug 29, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 30, 2023, 6:10 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 951 of 1851
Crew # Workers # Total
hours
Work performed
Totals 16 20
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 10, Set Drain vault from Fish
Lift
Area 60, Backfill Generator Room
Area
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 40, Load General Fill
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 40, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 952 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1 10 Compaction onsite
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1 8 Area 10, Grade subgrade
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 Day compressive break report from the Fish Lift Wall Pour at Area 40.
8:00 am IMCO is continuing to get ready for the slab placement at Area 60 which is scheduled for tomorrow. They
area forming the interior curbs and installing bulkheads at the CJs.
10:00 am IMCO is starting to form up the lower tail screen slab for the cross channel. They are also excavating for
the thickened concrete edges at Area 40. IMCO has a crew inside Area 30. They are chipping and repairing surface
defects and another crew is working on installing the mechanical piping inside the structure.
12:00 pm IMCO has brought to my attention that the electrical lines under the Area 60 slab in the Electrical room
were not installed in the correct location. They are 5" off from where they should be. It was stated a
miscommunication to Vale with a dimension was the reason. IMCO is requestion to make the Chiller room 5" larger
to accommodate for the electrical line locations that penetrate the slab.
3:00 pm IMCO is continuing to work on bulkheads at the CJs at Area 60.
4:30 pm IMCO is setting the valve vault from the drain and weir piping from the fish lift.
5:00 pm Sean informed me that the slab is ready for concrete and asked if I would perform my final check on the
rebar and forms. Ryan, IMCO, is also checking. Everything looked to be per plan. IMCO is done for the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 953 of 1851
References
Photos (14)
20230829_162938
Taken on Aug 29, 2023, 4:29 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_161909
Taken on Aug 29, 2023, 4:19 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 954 of 1851
20230829_161843
Taken on Aug 29, 2023, 4:18 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_135331
Taken on Aug 29, 2023, 1:53 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 955 of 1851
20230829_135329
Taken on Aug 29, 2023, 1:53 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_135320
Taken on Aug 29, 2023, 1:53 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 956 of 1851
20230829_113037
Taken on Aug 29, 2023, 11:30 AM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_113025
Taken on Aug 29, 2023, 11:30 AM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 957 of 1851
20230829_162852
Taken on Aug 29, 2023, 4:28 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_162007
Taken on Aug 29, 2023, 4:20 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 958 of 1851
20230829_161848
Taken on Aug 29, 2023, 4:18 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_161826
Taken on Aug 29, 2023, 4:18 PM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 959 of 1851
20230829_111825
Taken on Aug 29, 2023, 11:18 AM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
20230829_083609
Taken on Aug 29, 2023, 8:36 AM MDT
Added on Aug 30, 2023, 6:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 960 of 1851
Form detail
#215: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 10 Area 40, Excavate for North
Crowder slab
Area 60, Backfill for Generator
room
IMCO, Carpenters 6 10 Area 30, Chip Surface defects,
Begin interior piping
Area 40, Form North Crowder Slab
Area 60, Bulkhead for CJ in slab
EOI 3 6 Area 60, Install Slab Rebar
Forms
Location
Form date Aug 28, 2023
Description Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 29, 2023, 7:22 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 961 of 1851
Crew # Workers # Total
hours
Work performed
Totals 19 26
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 60, Backfill Generator Room
Area
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1 10 Area 40, Load General Fill
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 40, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Fly piping, Safety
extraction standby
Bomag Roller 1
Dynapac Roller 1 10 Compaction onsite
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 962 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Compaction onsite
CAT D5 Dozer 1 8 Area 40, Grade subgrade
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day compressive break report from Area 40 Diffuser Walls and fish lift slab.
11:30 am IMCO is working on laying out the north cross crowder slab. They have excavated down to the bottom
of slab elevation at approx. -14.5. I have walked the compaction and the subgrade is firm and unyielding.
12:00 pm EOI is onsite and working on the rebar for the Area 60 slab.
2:00 pm IMCO is working on finishing the subgrade preparation for Area 40. They have been importing general
fill to bring the grade up to subgrade. IMCO has a crew inside Area 30 Well side chipping on surface defects. I am
told they are also flying in piping and beginning to install them.
4:30 pm IMCO has been working on backfilling and compacting the subgrade for the generator room. EOI has
left the site. I noticed a few missing pieces of rebar and notified IMCO.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 963 of 1851
References
Photos (5)
20230828_150513
Taken on Aug 28, 2023, 3:05 PM MDT
Added on Aug 29, 2023, 7:09 AM MDT
Added by Chris Johnson
20230828_144021
Taken on Aug 28, 2023, 2:40 PM MDT
Added on Aug 29, 2023, 7:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 964 of 1851
20230828_144013
Taken on Aug 28, 2023, 2:40 PM MDT
Added on Aug 29, 2023, 7:09 AM MDT
Added by Chris Johnson
20230828_143931
Taken on Aug 28, 2023, 2:39 PM MDT
Added on Aug 29, 2023, 7:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 965 of 1851
20230828_123656
Taken on Aug 28, 2023, 12:36 PM MDT
Added on Aug 29, 2023, 7:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 966 of 1851
Form detail
#214: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 10 10 Area 60, Slab Pour
Vale Electric, Electricians 1 10 Area 10, Alarm Cable
Totals 11 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 25, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 28, 2023, 1:22 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 967 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1
IMCO Concrete Truck 1 10 Area 60, concrete pour
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
Concrete Pump Truck 1 5 Area 60, concrete pour
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 968 of 1851
Notes
8:30am Matt Kovacs, HMH Engineering, arrived on site. The pump truck was already here and set up. The batch
plant was getting ready to mix up the first load.
9:00am The first load came out from the batch plant
9:17am Pulled the first sample of concrete and proceeded to test. The test was unable to be fully completed
because the air pot kept leaking. Tried 4 separate times to get it to seal but each time air bubbling from the side
was visible. The problem is identified and will be fixed. All other portions of the concrete test were completed
without issue.
11:30am Tester left the site
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 969 of 1851
Form detail
#213: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 30, Grind, and Rock Chip
surface defects, Continue patching
Area 40, Strip Forms, Lay out area
limits
Area 60 Cut, Remove rebar, Fix
interior wall thickened concrete
locations, replace and splice rebar
back
IMCO, Operators and Labors 10 10 Area 60, Backfill and compact
under slab, vapor barrier, sand
Forms
Location
Form date Aug 24, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 25, 2023, 1:27 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 970 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 1 10 Area 10, Alarm Cable
Lacy Mechanical 1 10 Area 60, Install floor drains
Totals 20 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 60, Place material for under
slab backfill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 60, Place material for
underslab
Dump Truck 1 10 Area 60, Import Structural fill
Kobelco 1100G Crane 1 10 no operator onsite
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 971 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Pipe Testing
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached IMCO pipe testing reports.
8:00 am IMCO is working on fixing the interior wall thickened slab locations. Yesterday it was discovered while
the rebar was being installed that many of the thickened slab locations were not per plan and needed to be
moved. The rebar sub elected to continue placing the bar in locations that were not prepped or in the wrong
location. The crew is having to cut out the rebar in sections and fix the grade under the slab and excavate out
areas where the thickened slab should be. They plan to fly the rebar sections back in and splice bars to form a
continuous mat again.
10:00 am IMCO has tested the diffuser lines to Raceway 3 & 4. They both passed with no issues. They are going to
start working on 2 and 1 next. The other crews are continuing to work on removing rebar and and excavating the
thickened slab areas per plan. Sam, IPC, is onsite to check the alarm wires with Vale Elec. Vale has ran a new cable
for the alarms.
12:00 pm IMCO crew is continuing to work on fixing the locations of the thickened slab. They have started to
replace the rebar and install splice pieces for cutting the rebar in sections. They dirt crew is working on under slab
grade on the incubation side of Area 60.
2:00 pm IMCO crew has started to excavate for the base slab at the end of the crowder per Section B on 40 S 7.
Meanwhile IMCO crews continue to work on installing the rebar for the hatchery office slab. The pipe testing crew
has started another test on Raceway lines 2 & 1.
3:30 pm The Raceway lines have passed test. This concludes all the diffuser lines passed.
4:30 pm A soft spot has presented itself under the utility room slab. As I walked on it the grade pumped up and
down approx. 2". It was brought to Sean and Kirts attention. The crew is finishing up the rebar repairs and laying
out the walls for the anchor bolts.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 972 of 1851
5:00 pm Sean has informed me they will make the call on pouring it or not tomorrow morning. Kirt also
suggested blocking out the room and pouring it after the ground heals up. I have picked up my cylinders and
leaving the site. Matt Kovacs, HMH, will be onsite tomorrow for the concrete testing.
References
Photos (14)
20230824_155347
Taken on Aug 24, 2023, 3:53 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
20230824_154833
Taken on Aug 24, 2023, 3:48 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 973 of 1851
20230824_154337
Taken on Aug 24, 2023, 3:43 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
20230824_154329
Taken on Aug 24, 2023, 3:43 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 974 of 1851
20230824_154316
Taken on Aug 24, 2023, 3:43 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
20230824_132939
Taken on Aug 24, 2023, 1:29 PM MDT
Added on Aug 24, 2023, 4:59 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 975 of 1851
20230824_104238
Taken on Aug 24, 2023, 10:42 AM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
20230824_091407
Taken on Aug 24, 2023, 9:14 AM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 976 of 1851
20230824_082242
Taken on Aug 24, 2023, 8:22 AM MDT
Added on Aug 24, 2023, 4:59 PM MDT
Added by Chris Johnson
20230824_154832
Taken on Aug 24, 2023, 3:48 PM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 977 of 1851
20230824_142802
Taken on Aug 24, 2023, 2:28 PM MDT
Added on Aug 24, 2023, 4:59 PM MDT
Added by Chris Johnson
20230824_104750
Taken on Aug 24, 2023, 10:47 AM MDT
Added on Aug 24, 2023, 4:59 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 978 of 1851
20230824_091438
Taken on Aug 24, 2023, 9:14 AM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
20230824_091417
Taken on Aug 24, 2023, 9:14 AM MDT
Added on Aug 24, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 979 of 1851
Form detail
#212: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 30, Grind, and Rock Chip
surface defects, Continue patching
Area 40, Begin Stripping forms,
Stopped after discussing the 48
Hour waiting period
Area 60 Layout walls for dirt crew
to backfill
IMCO, Operators and Labors 10 10 Area 60, Backfill and compact
under slab, vapor barrier, sand
Chip on Concrete Trucks
Forms
Location
Form date Aug 23, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 24, 2023, 7:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 980 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 1 10 Area 10, Alarm Cable
Lacy Mechanical 1 10 Area 60, Install plumbing lines,
Trap Primers
EOI 3 8 Area 60, Install slab rebar for office
and breezeway
Totals 23 48
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 60, Place material for under
slab backfill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1 10 Area 60, Place material for
underslab
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 981 of 1851
Equipment Quantity Hours
used
Comment
Dump Truck 1 10 Area 60, Import Structural fill
Kobelco 1100G Crane 1 10 no operator onsite
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached IMCO pipe testing reports.
8:00 am IMCO has started stripping the forms from yesterdays concrete placement at the fish lift. I notified Kirt
that it has not been 48 hours and the forms should be full supported. He said the guys will stop. They informed me
that they will reinstall the ties to support the forms. EOI is onsite to start installing rebar in the hatchery building
office side. I was informed by them that the thickened concrete for the interior walls are not per plan. I reviewed
the drawings with Steve and he agreed. They need to dig out some more in one location. In another location they
dug out for thickened concrete where it is not needed.
9:00 am Attended meeting
10:30 am The crew is continuing to place fill under slab at Area 60. I noticed the rebar mat was being tied over
the thickened edge area that is not needed. IMCO plans to pour that thickened area with no additional rebar. I also
noticed there is not enough rebar thickened edge pieces to be installed through the doorway sections. The rebar
submittal did not show any rebar where the doors are to be placed so they did not have enough pieces made
(A4006 per the approved rebar submittal). They also plan to fill these areas in with concrete instead of grading the
subgrade to match.
1:30 pm EOI has left the site. I checked the rebar they installed. I noticed multiple issues with the rebar. They
were missing lap bars to extend the East West mat. They did not cut the trim bar according to the approved
drawings. Instead they laid extra A4006 bars in near the pipe penetrations. The trim bar should be installed per
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 982 of 1851
S216 on GS-6. The clearances from ground to rebar shall be 3" per the standard drawings and approved submittal,
Some places the rebar is touching the ground. I notified Steve, Kirt and Kole of these issues. It was also determined
that they did not excavate out an area of the thickened concrete enough. They are going to get started on digging
that out. Kelly has been testing the raceway supply lines. He has the line to Raceway 5 under test now. It was
agreed on in the meeting to test the lines to 15 PSI.
2:30 pm The line to Raceway 5 has passed testing. The crew is going to prep line 4 for testing now. The dirt crew
is working on excavating out the thickened slab area that was missed.
4:00 pm After the carpenters started laying out the anchor bolts for the interior walls it was discovered that more
thickened areas were in the wrong location. The crew has chosen to cut the rebar and remove it in sections. They
will splice the rebar back together once they fix the thickened slab locations. They are starting that now.
4:30 pm The crew is leaving for the day. They have rescheduled the concrete placement for Friday.
References
Photos (9)
20230823_160317
Taken on Aug 23, 2023, 4:03 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
20230823_140440
Taken on Aug 23, 2023, 2:04 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 983 of 1851
20230823_133354
Taken on Aug 23, 2023, 1:33 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
20230823_133351
Taken on Aug 23, 2023, 1:33 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 984 of 1851
20230823_085049
Taken on Aug 23, 2023, 8:50 AM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
20230823_084045
Taken on Aug 23, 2023, 8:40 AM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 985 of 1851
20230823_140319
Taken on Aug 23, 2023, 2:03 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
20230823_140314
Taken on Aug 23, 2023, 2:03 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 986 of 1851
20230823_140307
Taken on Aug 23, 2023, 2:03 PM MDT
Added on Aug 24, 2023, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 987 of 1851
Form detail
#211: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 8 10 Area 30, Grind, and Rock Chip
surface defects, Begin patching
Area 40, Form and place concrete
for lower fish lift walls
Area 60 Layout walls for dirt crew
to backfill
IMCO, Operators and Labors 10 10 Area 40, Batch concrete
Area 60, Backfill and compact
under slab, vapor barrier, sand
Vale Electric, Electricians 1 10 Area 10, Alarm Cable
Forms
Location
Form date Aug 22, 2023
Description Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 22, 2023, 5:04 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 988 of 1851
Crew # Workers # Total
hours
Work performed
Lacy Mechanical 1 10 Area 60, Install plumbing lines,
Trap Primers
Totals 20 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10 Move material around the site
Deere 210 Excavator 1 10 Area 60, Place material for under
slab backfill
IMCO Concrete Truck 1 5 Area 40, Batch Concrete
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Safety Extraction Standby
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 989 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Field Report, IMCO batch ticket and 7 day compressive strength report from Area 60
Incubation Drain slab.
8:00 am IMCO is working on forming up the lower fish lift walls. They plan to place concrete today. There has
been discussion regarding what is needed for rebar. Discissions last week lead to the final approval of the rebar
needed. This is documented in email correspondence and will be uploaded to Build. Rebar drawings markup from
8-9-23 R3.
9:00 am IMCO has asked if I would witness some pipe testing. I made them aware that the pipe testing plan has
not been approved and all these tests they plan to do really could be a waste of time. They asked to gamble this
time because of the time crunch they are under waiting for the approval. They are testing the diffuser box lines
from Area 30 to Area 40. They are using a blind flange with a gauge on it on the high end ( Aeration Tower) and an
inflatable test ball on the low end ( diffuser box). They are performing a hydrostatic test with water. They used the
water truck to pressure the line to 20 psi. Note the current plans call for a 125 psi test. Per submittal 168 IMCO has
asked to lower the test pressure. The first line to the Raceway #6 is under 20 psi pressure. The test needs to hold
for 1 hour.
10:00 am The test has held for one hour with no issues. They area going to get line 5 ready for testing now. While
I was inside the aeration tower I looked at the work that has been performed on the chipping of surface defects. I
brought one area to concern that it looked like it needed to be chipped out more. I let Sean know and he directed
his crew to chip on it more. The area still had voids. IMCO is getting ready to start batching concrete for the fish lift
walls.
11:00 am The crew has pressured up the raceway 5 line. IMCO is batching concrete.
11:30 am I have test the concrete truck and the concrete had to high of air at 9%. They are letting it spin for 5
minutes and asked if I would test it again. The second test had even higher air at 9.5%. They are going to reject the
truck and batch another load.
12:30 pm IMCO is working on batching another 5 CY for the fish lift. They are going to not put any air in this load
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 990 of 1851
to see what the concrete it without air. The pressure testing failed as the test ball blew out.
1:30 pm I have tested the second truck that they did not add any air too. The no air mix tested at 4.5% air. They
decided to add 2 oz of Air Entrainment. I tested again after they mixed. It tested at 5.0%. The crew is starting to
place the concrete in the forms.
2:00 pm The crew has set and compacted the general fill grade and dug out the thickened concrete at the interior
walls. They placed the vapor barrier and currently are working on placing the 2" sand layer.
2:30 pm IMCO has completed the concrete placement. During the placement they added water to the concrete to
help to get it down the concrete shoot. This was done without consolation with me. They also had to adjust the
forms because the forms started to bow with lack of a whaler and ties at the top.
4:30 pm The crew is continuing to work on place sand over the vapor barrier. I am told EOI is scheduled to be
onsite tomorrow to install the rebar with plan to place the hatchery building slab Thursday.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 991 of 1851
References
Photos (20)
20230822_162234
Taken on Aug 22, 2023, 4:22 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_142455
Taken on Aug 22, 2023, 2:24 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 992 of 1851
20230822_141018
Taken on Aug 22, 2023, 2:10 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_105111
Taken on Aug 22, 2023, 10:51 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 993 of 1851
20230822_105042
Taken on Aug 22, 2023, 10:50 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_093632
Taken on Aug 22, 2023, 9:36 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 994 of 1851
20230822_093623
Taken on Aug 22, 2023, 9:36 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_093607
Taken on Aug 22, 2023, 9:36 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 995 of 1851
20230822_093539
Taken on Aug 22, 2023, 9:35 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_084320
Taken on Aug 22, 2023, 8:43 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 996 of 1851
20230822_084248
Taken on Aug 22, 2023, 8:42 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_084241
Taken on Aug 22, 2023, 8:42 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 997 of 1851
20230822_084333
Taken on Aug 22, 2023, 8:42 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_162219
Taken on Aug 22, 2023, 4:22 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 998 of 1851
20230822_142446
Taken on Aug 22, 2023, 2:24 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_142427
Taken on Aug 22, 2023, 2:24 PM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 999 of 1851
20230822_105113
Taken on Aug 22, 2023, 10:51 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_093610
Taken on Aug 22, 2023, 9:36 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1000 of 1851
20230822_084643
Taken on Aug 22, 2023, 8:46 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
20230822_084402
Taken on Aug 22, 2023, 8:43 AM MDT
Added on Aug 22, 2023, 4:52 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1001 of 1851
Form detail
#210: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 4 Area 60, Finish Stripping forms
IMCO, Operators and Labors 4 4 Area 60, Backfill and Compact
General Fill
Totals 9 8
2. Materials
Forms
Location
Form date Aug 21, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 22, 2023, 7:10 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1002 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1
Deere 210 Excavator 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
Deere 644J Loader 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1003 of 1851
Notes
11:00 am IMCO is leaving for the day. They were working on backfilling inside Area 60 so EOI could get onsite and
begin installing the rebar for the slab placement. There is heavy rain today and some lighting strikes were within 5
miles. This was enough for IMCO to call it a day and come back tomorrow.
3:00 pm Walked the site. I was informed my IMCO that the plumbing was tested and approved by Baker Co.
Inspector. The crew has backfilled the lines with pipe bedding and backfilled everywhere else with general fill. They
have a larger plate compactor on site and looks as if they were using it to achieve compaction. The crew
References
Photos (2)
20230821_135901
Taken on Aug 21, 2023, 1:59 PM MDT
Added on Aug 21, 2023, 3:29 PM MDT
Added by Chris Johnson
20230821_135753
Taken on Aug 21, 2023, 1:57 PM MDT
Added on Aug 21, 2023, 3:29 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1004 of 1851
Form detail
#209: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10 Search for Control Wire
Area 60 Backfill
IMCO, Carpenters 11 10 Area 60 Strip Forms
Totals 16 20
2. Materials
Forms
Location
Form date Aug 18, 2023
Description Area 10, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 18, 2023, 9:09 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1005 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Search for Control Wire
Deere 644J Loader 1 10 Area 60, Load Fill
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place Backfill
Dump Truck 1 10 Area 60, Haul in Fill
Kobelco 1100G Crane 1 10 Area 30 Standby for emergency
extraction
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1006 of 1851
Notes
7:00 am Matt Kovacs, HMH Engineering, is taking over as Inspector again. IMCO is planning on stripping the forms
from yesterday's pour. They have switched to hauling in the backfill material for Area 60 which they plan to place
today. They also plan on continuing the preliminary pipe pressure tests which HMH will not witness.
9:30 am I am leaving the site to bring back the Cylinders from yesterday's pour.
References
Photos (1)
IMG_0037
Taken on Aug 18, 2023, 8:50 AM MDT
Added on Aug 18, 2023, 9:08 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1007 of 1851
Form detail
#207: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 5 10 Area 10 Search for Control Wire
IMCO, Carpenters 11 10 Area 60 Pour concrete for
Incubation Drain Walls
Totals 16 20
2. Materials
Forms
Location
Form date Aug 17, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 21, 2023, 11:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1008 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Search for Control Wire
Deere 644J Loader 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Concrete pour
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 40, Bring in Fill for Subgrade
Kobelco 1100G Crane 1 10 Area 30 Standby for emergency
extraction, Area 60 Concrete Pour
Bomag Roller 1
Dynapac Roller 1 10 Area 40 Compacting Subgrade
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1009 of 1851
Notes
See attached HMH Concrete Compressive Break Report from the Diffuser Base slabs 28 day. Also attached is
Concrete Field report from todays placement and IMCO batch ticket.
7:00 am Matt Kovacs, HMH Engineering, is taking over as Inspector again. IMCO is placing the incubation drain
and sumps walls this morning. They are going to continue placing and compacting fill for the Area 40 Subgrade.
8:00 am Concrete for the walls is being batched and will be placed soon.
10:00 am Incubation Drain and Sump walls are placed. They are continuing to place fill for Area 40 Subgrade.
1:00 pm IMCO is doing preliminary pressure tests on the pipes in the Aeration Tower, this was not witnessed by
HMH.
3:00 pm Lift for Area 40 Subgrade is completed and compacted. Will be proof rolled.
3:30 pm IMCO proof rolled the first lift for the Area 40 Subgrade. Proof roll passed and they are continuing onto
the next lift.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1010 of 1851
References
Photos (3)
IMG_0033
Taken on Aug 17, 2023, 9:42 AM MDT
Added on Aug 17, 2023, 4:17 PM MDT
Added by Chris Johnson
IMG_0034
Taken on Aug 17, 2023, 12:37 PM MDT
Added on Aug 17, 2023, 4:17 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1011 of 1851
IMG_0036
Taken on Aug 17, 2023, 3:33 PM MDT
Added on Aug 17, 2023, 4:18 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1012 of 1851
Form detail
#206: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 11 10 Area 60 Form for Incubation Walls
IMCO, Operators and Labors 5 10 Area 10 Search for Control Wire
Totals 16 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 16, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 16, 2023, 5:19 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1013 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Search for Control Wire
Deere 644J Loader 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Concrete pour
IMCO Concrete Truck 1 5 Area 60, Concrete pour
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Standby for emergency
extraction
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1014 of 1851
Notes
7:00 am IMCO is working on forming the incubation drain walls. They plan to place this concrete tomorrow
morning.
9:00 am Attended weekly meeting.
11:00 am Walked the site with Ryan and Jake. We discussed the fish lift rebar and what was not detailed in the
drawings. Left site, Matt Kovacs, HMH Engineering, is taking over.
1:00 pm Checked rebar for the incubation drain walls. The lap for the corner bar was too short and was corrected.
The dirt crew finished excavating the clay layer for Area 40 subgrade.
2:00 pm Granular fill from the stockpile is being placed and compacted for the Area 40 subgrade.
3:00 pm Incubation drain wall forms and rebar were finished and are ready to pour tomorrow. Ran out of fill and
switched to a source across the river for Area 40 subgrade.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1015 of 1851
References
Photos (6)
20230816_101501
Taken on Aug 16, 2023, 10:15 AM MDT
Added on Aug 16, 2023, 10:43 AM MDT
Added by Chris Johnson
IMG_0022
Taken on Aug 16, 2023, 2:22 PM MDT
Added on Aug 16, 2023, 5:08 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1016 of 1851
IMG_0024
Taken on Aug 16, 2023, 4:58 PM MDT
Added on Aug 16, 2023, 5:08 PM MDT
Added by Chris Johnson
20230816_101454
Taken on Aug 16, 2023, 10:14 AM MDT
Added on Aug 16, 2023, 10:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1017 of 1851
20230816_080327
Taken on Aug 16, 2023, 8:03 AM MDT
Added on Aug 16, 2023, 10:43 AM MDT
Added by Chris Johnson
IMG_0020
Taken on Aug 16, 2023, 1:33 PM MDT
Added on Aug 16, 2023, 5:08 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1018 of 1851
Form detail
#205: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 11 10 Area 30 Grind Walls, Surface
Defects
Area 40, Place Concrete for
Diffuser Box Walls
Area 60 Place Concrete for
Incubation Drain
IMCO, Operators and Labors 5 10 Area 10 Search for Control Wire
Area 60 Batch Concrete
Totals 16 20
Forms
Location
Form date Aug 15, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 16, 2023, 7:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1019 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Search for Control Wire
Deere 644J Loader 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Concrete pour
IMCO Concrete Truck 1 5 Area 60, Concrete pour
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Standby for emergency
extraction
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1020 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Field Report and IMCO batch tickets.
7:00 am Pump truck is onsite and starting to setup. They are going to place the incubation drain and the last
diffuser box walls.
8:30 am The first truck is batched. I let the pump truck prime out and dump some concrete in the washout. I took
my sample and all tested in spec. They started to pour.
10:00 am IMCO batched a second truck and finished the placement. They are working on finishing it now. A crew
is in Area 30 working on chipping surface defects.
12:00 pm IMCO is looking for the control wire that was cut during the excavation. They have one side exposed
but they are looking for the other side so they can be repair it.
2:00 pm IMCO is starting to lay out the incubation drain walls for the next pour. They have informed me they plan
to pour Thursday.
4:00 pm IMCO is still searching for the control wire. We have pulled up old photos in an attempt to find the wire
location. The carpenters are continuing to lay out the walls and cut forms for the wall placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1021 of 1851
References
Photos (4)
20230815_164209
Taken on Aug 15, 2023, 4:42 PM MDT
Added on Aug 16, 2023, 7:02 AM MDT
Added by Chris Johnson
20230815_084958
Taken on Aug 15, 2023, 8:49 AM MDT
Added on Aug 16, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1022 of 1851
20230815_164151
Taken on Aug 15, 2023, 4:41 PM MDT
Added on Aug 16, 2023, 7:02 AM MDT
Added by Chris Johnson
20230815_084949
Taken on Aug 15, 2023, 8:49 AM MDT
Added on Aug 16, 2023, 7:02 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1023 of 1851
Form detail
#204: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 11 10 Area 30 Grind Walls, Surface
Defects
Area 60 Attempt to pour concrete,
could not get concrete in spec
IMCO, Operators and Labors 5 10 Area 40 Excavate Clay layer
Area 60 Batch Concrete
Totals 16 20
Forms
Location
Form date Aug 14, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 15, 2023, 6:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1024 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate Clay material
Deere 644J Loader 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 5 Area 60, Attempt Concrete pour
IMCO Concrete Truck 1 5 Area 60, Attempt Concrete pour
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 40, Haul Clay material,
Stockpile onsite
Kobelco 1100G Crane 1 10 Area 60, Place concrete with
bucket
Area 30 Standby for emergency
extraction
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1025 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. Crew is prepping to pour the Incubation Drain, Formalin Sump and the last diffuser wall.
I have looked at all three locations. I asked the crew to finish the trim bar around the drain in the incubation
trench. He added a trim bar immediately. The crew is going to start batching concrete.
11:00 am Concrete has been batch. After filling the concrete bucket the crew started placing concrete in the forms
for the incubation drain. I tested the concrete and the air was 8.5%, I notified IMCO and they stopped placing
concrete. Sean directed his crew to remove the concrete from the forms. The crew went to batch another truck.
12:30 pm The second truck is batched and ready. They filled the concrete bucket and before they started placing
any I tested the concrete. It was exactly the same at 8.5% air. Sean directed his crew to mix 1 CY of concrete with
no air into the truck on top of the high air concrete.
1:30 pm They have added one CY to the truck with no air. As they were dumping the concrete in the bucket Sean
noticed the slump was not right and he tested the temperature of the concrete. It was over 90 degrees. Before I
tested it he rejected the truck and said they would pour tomorrow morning when its cooler. The crew is going to
clean off the rebar and have it ready to pour tomorrow morning.
2:00 pm The crew is continuing to remove the concrete and clean off the rebar. The dirt crew has moved to
excavating the clay layer out of the subgrade at Area 40. They are stockpiling it onsite for now.
4:00 pm The dirt crew is continuing to excavate out the clay material at Area 40. IMCO also has a small crew
working on grinding and chipping surface defects at Area 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1026 of 1851
References
Photos (9)
20230814_152252
Taken on Aug 14, 2023, 3:22 PM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
20230814_113700
Taken on Aug 14, 2023, 11:37 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1027 of 1851
20230814_111053
Taken on Aug 14, 2023, 11:10 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
20230814_111040
Taken on Aug 14, 2023, 11:10 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1028 of 1851
20230814_152937
Taken on Aug 14, 2023, 3:29 PM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
20230814_152301
Taken on Aug 14, 2023, 3:23 PM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1029 of 1851
20230814_111338
Taken on Aug 14, 2023, 11:13 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
20230814_111034
Taken on Aug 14, 2023, 11:10 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1030 of 1851
20230814_111029
Taken on Aug 14, 2023, 11:10 AM MDT
Added on Aug 15, 2023, 6:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1031 of 1851
Form detail
#203: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Forms
Location
Form date Aug 11, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 11, 2023, 11:07 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1032 of 1851
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See Attached Concrete Compressive Report from Area 60 Stem Wall Placement 28 day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1033 of 1851
Form detail
#202: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Grind Walls
Area 60 Form incubation Drain
IMCO, Operators and Labors 5 10 Area 10, Backfill MH4
Area 40, Excavate soft material
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Vale Electric, Electricians 1 10 Area 60, Raceway Install
Forms
Location
Form date Aug 10, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 11, 2023, 9:31 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1034 of 1851
Crew # Workers # Total
hours
Work performed
Totals 12 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate soft spot
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Backfill under slab,
Compact with Hoe Pack
Dump Truck 1 10 Area 60, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Standby for safety
extraction
Bomag Roller 1
Dynapac Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1035 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on installing the rebar in the incubation trench drain. They plan to place this concrete
tomorrow.
9:00 am IMCO dirt crew is working on placing and compacting material near MH 4. They also have a crew
excavating out the soft clay material under Area 40. The clay seems to be in a vane through the subgrade. They are
currently stockpiling the unsuitable material onsite.
11:00 am In review of the preliminary rebar detail sent over from Harris I noticed the rebar they installed is not
correct. I also have noticed that the preliminary detailing is incomplete. I have composed an email to IPC and
Schnabel to discuss the findings onsite.
1:00 pm The crew is continuing to excavate out the soft material under Area 40.
3:00 pm It was brought to my attention that the trench drain will not be ready for pouring tomorrow. They have
moved the placement to Monday. The dirt crew is going to clean up what they have under Area 40. They are going
to use the existing Pit Run material to level off what they have exposed and compact it and have it ready for a
proof roll Monday. Left site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1036 of 1851
References
Photos (10)
20230810_130350
Taken on Aug 10, 2023, 1:03 PM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_131510
Taken on Aug 10, 2023, 1:15 PM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1037 of 1851
20230810_085813
Taken on Aug 10, 2023, 8:58 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_085829
Taken on Aug 10, 2023, 8:58 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_085937
Taken on Aug 10, 2023, 8:59 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_085924
Taken on Aug 10, 2023, 8:59 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1038 of 1851
20230810_085917
Taken on Aug 10, 2023, 8:59 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_131508
Taken on Aug 10, 2023, 1:15 PM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1039 of 1851
20230810_090005
Taken on Aug 10, 2023, 9:00 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
20230810_085848
Taken on Aug 10, 2023, 8:58 AM MDT
Added on Aug 11, 2023, 9:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1040 of 1851
Form detail
#201: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Grind Walls
Area 40 Form Fish Lift, Install rebar
Area 60 Form incubation Drain
IMCO, Operators and Labors 5 10 Area 10, Backfill MH4
Area 40, Excavate soft material
Area 60, Backfill under slab
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Forms
Location
Form date Aug 9, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 10, 2023, 6:59 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1041 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 1 10 Area 60, Raceway Install
Totals 12 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate soft spot
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Backfill under slab,
Compact with Hoe Pack
Dump Truck 1 10 Area 60, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Standby for safety
extraction
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1042 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to continue grinding inside Area 30. The carpenters are starting to form Area 60 Incubation
drain.
9:00 am IMCO crew has installed rebar in the lower fish lift walls. This rebar is not detailed on the shop drawings.
The have been working with Harris to get the detail done and sent over for submittal. Attended weekly meeting
10:00 am Lacy has installed the domestic water line that goes under the slab. He has pressure tested it.
12:00 pm Vale has made the conduit fix to the 480V line near MH 4.
1:00 pm IMCO is continuing to work on the incubation trench at Area 60.
3:00 pm IMCO is rounding up all the rebar for the incubation trench. Some of it is way to rusty to install. The crew
plans to replace it or remove the rust.
4:30 pm IMCO has all the forms up for the incubation trench. They have sloped them all to the trench drain.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1043 of 1851
References
Photos (16)
20230809_163020
Taken on Aug 9, 2023, 4:30 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_162710
Taken on Aug 9, 2023, 4:27 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1044 of 1851
20230809_083526
Taken on Aug 9, 2023, 8:35 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_080636
Taken on Aug 9, 2023, 8:06 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1045 of 1851
20230809_080154
Taken on Aug 9, 2023, 8:01 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_080050
Taken on Aug 9, 2023, 8:00 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1046 of 1851
20230809_083358
Taken on Aug 9, 2023, 8:33 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_163011
Taken on Aug 9, 2023, 4:30 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1047 of 1851
20230809_162718
Taken on Aug 9, 2023, 4:27 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_152948
Taken on Aug 9, 2023, 3:29 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1048 of 1851
20230809_151602
Taken on Aug 9, 2023, 3:16 PM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_100250
Taken on Aug 9, 2023, 10:02 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1049 of 1851
20230809_080644
Taken on Aug 9, 2023, 8:06 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_080629
Taken on Aug 9, 2023, 8:06 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1050 of 1851
20230809_080141
Taken on Aug 9, 2023, 8:01 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
20230809_080016
Taken on Aug 9, 2023, 8:00 AM MDT
Added on Aug 10, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1051 of 1851
Form detail
#200: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Grind Walls
Area 40 Form Fish Lift, Install rebar
Area 60 Lay out incubation Drain
IMCO, Operators and Labors 5 10 Area 10, Grout MH 4
Area 60, Grout holes in stem wall,
backfill under slab
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Forms
Location
Form date Aug 8, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 9, 2023, 7:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1052 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 1 10 Area 60, Raceway Install
Totals 12 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate soft spot
Area 10, Set trench box for
grouting at MH 4, Grout MH4
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Backfill under slab,
Compact with Hoe Pack
Dump Truck 1 10 Area 60, Import General Fill
Kobelco 1100G Crane 1 10 Area 30, Standby for safety
extraction
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1053 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 56 day Compressive Break Report from Area 30 1st Wall placement. The 28 Day breaks were low so
we used the 3 holds to verify at 56 days. They met strength.
8:00 am IMCO plans to work on the grinding of fins on Area 30 walls. The plan is to let Zack and I take a look at
the walls prior to any surface defect repairs are made.
9:00 am IMCO carpenters are working on laying out the incubation trench. The dirt crew needs to add material
and compact it before they can begin installing the forms.
11:00 am IMCO is continuing to work on the Area 30 grinding.
1:00 pm There has been discussion on the rebar for the fish lift. It seems as if the supplier did not detail
horizontal rebar on the lower fish lift walls. IMCO is working with their supplier to sort it out.
3:00 pm IMCO is going to be submitting a rebar detail regarding the lower fish lift walls. For now they have spoke
to the supplier and they have given IMCO direction on what they need to install there. IMCO is working on cutting
and bending the bar per their suppliers direction. I notified them I cannot inspect the rebar without approved
drawings. I noticed some cracking in the stem wall at Area 60. See attached photos
4:00 pm Zack and I along with Sean have entered Area 30 River Intake side to inspect the inside finish of the
concrete. Please see photos attached. There are multiple surface defects that need attention. Sean stated he
agreed and he would get the crew working on exposing the defects. The plan is to allow Zack and I to see the
exposed defects prior to any repairs being made.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1054 of 1851
References
Photos (25)
20230808_130523
Taken on Aug 8, 2023, 1:05 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145349
Taken on Aug 8, 2023, 2:53 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1055 of 1851
20230808_143336
Taken on Aug 8, 2023, 2:33 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_130611
Taken on Aug 8, 2023, 1:06 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1056 of 1851
20230808_130527
Taken on Aug 8, 2023, 1:05 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_130515
Taken on Aug 8, 2023, 1:05 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1057 of 1851
20230808_130122
Taken on Aug 8, 2023, 1:01 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145942
Taken on Aug 8, 2023, 2:59 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1058 of 1851
20230808_145844
Taken on Aug 8, 2023, 2:58 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145749
Taken on Aug 8, 2023, 2:57 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1059 of 1851
20230808_145507
Taken on Aug 8, 2023, 2:55 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145439
Taken on Aug 8, 2023, 2:54 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1060 of 1851
20230808_145427
Taken on Aug 8, 2023, 2:54 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145418
Taken on Aug 8, 2023, 2:54 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1061 of 1851
20230808_145331
Taken on Aug 8, 2023, 2:53 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145323
Taken on Aug 8, 2023, 2:53 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1062 of 1851
20230808_145315
Taken on Aug 8, 2023, 2:53 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145236
Taken on Aug 8, 2023, 2:52 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1063 of 1851
20230808_145230
Taken on Aug 8, 2023, 2:52 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_145227
Taken on Aug 8, 2023, 2:52 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1064 of 1851
20230808_130741
Taken on Aug 8, 2023, 1:07 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_130734
Taken on Aug 8, 2023, 1:07 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1065 of 1851
20230808_130643
Taken on Aug 8, 2023, 1:06 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
20230808_130638
Taken on Aug 8, 2023, 1:06 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1066 of 1851
20230808_130615
Taken on Aug 8, 2023, 1:06 PM MDT
Added on Aug 8, 2023, 3:31 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1067 of 1851
Form detail
#199: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40 Install Waterstop and form
Fish lift
Area 60 Core drill for trench drain
IMCO, Operators and Labors 5 10 Area 40, Excavate soft spot
Area 10, Grout MH 4
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Vale Electric, Electricians 1 10 Area 60, Raceway Install
Forms
Location
Form date Aug 7, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 8, 2023, 7:45 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1068 of 1851
Crew # Workers # Total
hours
Work performed
Totals 12 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate soft spot
Area 10, Set trench box for
grouting
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1069 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control
CAT D5 Dozer 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 Day compressive strength report from the Diffuser, Fish Lift Slab and pipe encasement placement.
10:00 am IMCO informed me they will not be placing concrete today. They are currently waiting on some
materials to finish forming the the fish lift.
1:00 pm The dirt crew used the rippers on the dozer last week through the soft spot under Area 40. They hope it
will aerate the material and allow it to dry out.
3:00 pm It was determined that the soft / wet spot under Area 40 will need further excavation. The material is very
soft. I was able to probe it down to approx. 2.5' deep. The material I probed was very wet and of clay like material.
Sean and I discussed actions on this. He said that area still needs to be excavated down to subgrade so we will take
a look at it when they get to that. A lighting storm has came in and the crew is standing down.
4:00 pm The rain is picked up. The crew is leaving for the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1070 of 1851
Form detail
#198: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 40 Install Waterstop and form
Fish lift
Area 60 Core drill for trench drain
IMCO, Operators and Labors 5 10 Area 40, Excavate for Raceways
Area 60, Backfill inside Building
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Vale Electric, Electricians 1 10 Area 60, Raceway Install
Forms
Location
Form date Aug 4, 2023
Description Area 10, Area 40 Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 7, 2023, 10:36 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1071 of 1851
Crew # Workers # Total
hours
Work performed
Totals 16 40
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate for Raceways
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place and compact
General Fill
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1072 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control
CAT D5 Dozer 1 10 Area 40, Slab grading
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO planned to place concrete for the 6th diffuser box walls. They are unsure if they will be performing
this work now. Currently they are working on water stop welding for the fish lift walls along with laying out the
location for the core drill for the drain line at Area 60.
9:00 am There is concern of a soft spot in the grade under Area 40. Brett and I discussed ripping the native
material up and letting it dry out over the weekend. We will see how it looks next week after it has time to dry out.
10:00 am IMCO has decided not to place concrete. They plan to place on Monday. I was informed next week they
plan to make the repairs to the 480 conduit line. Left Site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1073 of 1851
References
Photos (3)
20230804_082332
Taken on Aug 4, 2023, 8:23 AM MDT
Added on Aug 7, 2023, 10:36 AM MDT
Added by Chris Johnson
20230804_082540
Taken on Aug 4, 2023, 8:25 AM MDT
Added on Aug 7, 2023, 10:36 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1074 of 1851
20230804_082343
Taken on Aug 4, 2023, 8:23 AM MDT
Added on Aug 7, 2023, 10:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1075 of 1851
Form detail
#197: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 40 Backfill and Compact
around diffuser boxes
Area 60 Form Column Piers
IMCO, Operators and Labors 5 10 Area 60, Import, Place and
Compact General fill under slab
Area 40, Excavate for Raceways,
Fuse spray bar line
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Forms
Location
Form date Aug 3, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 4, 2023, 7:06 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1076 of 1851
Crew # Workers # Total
hours
Work performed
Totals 15 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate for Raceways
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place and compact
General Fill
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1077 of 1851
Equipment Quantity Hours
used
Comment
Water Truck 1 10 Dust Control
CAT D5 Dozer 1 10 Area 40, Slab grading
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 Day Compressive Report for Area 30 2nd Wall Placement.
8:00 am IMCO is continuing to place general fill under area 40. They are using a jumping jack compactor and the
two rollers to achieve compaction. They are continuing to place the material in 12" lifts and adding water.
10:00 am Lacy Mechanical is onsite working on the waste lines in Area 60. Vale Electric is also working on the
raceway conduit in Area 60.
12:00 pm IMCO is continuing to work on grading around the diffuser boxes and Area 40 base slab grade.
2:00 pm A crew is starting to work on the drain inside the trench for the incubation room. They will need to core a
new hole through the stem wall for the drain location.
4:00 pm A crew pulled layout on the raceways and determined the dirt crew needs to excavate out farther. They
are moving material around so they can finish the excavation.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1078 of 1851
References
Photos (5)
20230803_162525
Taken on Aug 3, 2023, 4:25 PM MDT
Added on Aug 4, 2023, 7:00 AM MDT
Added by Chris Johnson
20230803_162623
Taken on Aug 3, 2023, 4:26 PM MDT
Added on Aug 4, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1079 of 1851
20230803_162547
Taken on Aug 3, 2023, 4:25 PM MDT
Added on Aug 4, 2023, 7:00 AM MDT
Added by Chris Johnson
20230803_162452
Taken on Aug 3, 2023, 4:24 PM MDT
Added on Aug 4, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1080 of 1851
20230803_124330
Taken on Aug 3, 2023, 12:43 PM MDT
Added on Aug 4, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1081 of 1851
Form detail
#196: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 40 Form Last diffuser box
walls, Install Grade Embeds, Form
fish lift walls
Area 60 Layout and core drill holes
for the Plumber, Grout back stem
wall blockouts
IMCO, Operators and Labors 5 10 Area 60, Import, Place and
Compact General fill under slab
Area 40, Excavate for Raceways,
Begin Welding spray bar line
Forms
Location
Form date Aug 2, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 3, 2023, 7:36 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1082 of 1851
Crew # Workers # Total
hours
Work performed
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Totals 15 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate for Raceways
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place and compact
General Fill
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1083 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1
Water Truck 1 10 Dust Control
CAT Dozer 1 10 Area 40, Slab grading
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Zack, Sean and I went inside the well intake side of Area 30 to discuss the finish on the walls. It was
determined that the larger surface defects needed to be chipped out and inspected prior to any repairs being
done.
9:00 am Attended weekly meeting.
10:00 am IMCO crews are working on setting the diffuser grate embeds to grade on the forms to be casted into
the next concrete placement. They have a couple guys working on core drilling holes for the plumber as well.
11:00 am A crew is continuing to work on forming the fish lift walls. There was discussion regarding the wall rebar
in this fish lift.
12:00 pm Lacy Mechanical is continuing to install waste pipe at Area 60 under slab.
1:00 pm Vale Electric is also onsite today. They are working on raceway conduit under slab in Area 60.
2:00 pm IMCO pipe crew is beginning to weld the HDPE pipe for the spray bar feed to be casted under Area 40.
4:00 pm IMCO grade crew has been continuing to cut the raceway slab grade. They have a dozer onsite now to
perform this work.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1084 of 1851
References
Photos (9)
20230802_162943
Taken on Aug 2, 2023, 4:29 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
20230802_161909
Taken on Aug 2, 2023, 4:19 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1085 of 1851
20230802_145522
Taken on Aug 2, 2023, 2:55 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
20230802_140154
Taken on Aug 2, 2023, 2:01 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1086 of 1851
20230802_135923
Taken on Aug 2, 2023, 1:59 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
20230802_135833
Taken on Aug 2, 2023, 1:58 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1087 of 1851
20230802_135824
Taken on Aug 2, 2023, 1:58 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
20230802_135816
Taken on Aug 2, 2023, 1:58 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1088 of 1851
20230802_145532
Taken on Aug 2, 2023, 2:55 PM MDT
Added on Aug 3, 2023, 7:35 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1089 of 1851
Form detail
#195: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 30, Grind Wall fins, Begin
Sacking
Area 40 Form Last diffuser box
walls, Weld water stop at the fish
lift
Area 60 Layout and core drill holes
for the Plumber
IMCO, Operators and Labors 5 10 Area 60, Import, Place and
Compact General fill under slab
Area 40, Excavate for Raceways
Forms
Location
Form date Aug 1, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 2, 2023, 7:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1090 of 1851
Crew # Workers # Total
hours
Work performed
Lacy Mechanical 1 10 Area 60, Lay out sewer and water
plumbing
Totals 15 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate for Raceways
Deere 644J Loader 1 10 Area 60, Load General Fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place and compact
General Fill
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1091 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to work on excavating native material for the 6 raceways. They are loading trucks up
and dumping onsite to stockpile the material.
10:00 am IMCO missed installing vertical water stop at the fish lift bottom slab. They are going to cut and install
the vertical Ts to meet their concrete pour sequence. Another crew has started to core drill holes for the plumber
to install waste piping through the stem walls.
11:00 am It has been determined that at Area 60 the water line and sewer line penetrations will not meet
plumbing code. Lacy informed IPC and myself of the plumbing code violation to have the pipes encased and not
having them sleeved through the concrete stem wall. Lacy has proposed to use the sewer line as the water line
sleeve and to core drill a new hole for a water line sleeve. He intends to use link seal to seal the ends of the sleeves
around the new piping. A direction was given to from IPC to IMCO to proceed with meeting the building code
requirements.
2:00 pm IMCO is continuing to work on installing the vertical water stop that was missed in the first fish lift
placement per their placement sequence. They are also starting to build forms for the fish lift walls.
3:00 pm IMCO is continuing to work on excavating for the raceways and stockpiling the material onsite. They
have been also placing general fill under slab at Area 60. They are using the hoepack attachment and a jumping
jack to compact the material. Lacy is laying out the waste lines for them to excavate too.
4:30 pm Zack, IPC, and I went into Area 30 to inspect the finish of the walls. We were only able to access the Well
pump chamber side. A crew has been in there grinding and sacking. Zack and I noticed multiple surface defects.
The crew was currently attempting to repair an area that was approx. 15" by 13" in size with spots as deep as 2.25"
deep. They were attempting to fix the defect with a sacking mixture of cement, sand and water. The mixture was
not sticking very well. Other areas they attempted to sack the sacking mixture was able to be rubbed off easily.
Multiple deviations in the surface finish was seen with one particular spot extruding over 1/2". See photos for
photo documentation.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1092 of 1851
References
Photos (18)
20230801_161508
Taken on Aug 1, 2023, 4:15 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_161456
Taken on Aug 1, 2023, 4:14 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1093 of 1851
20230801_161324
Taken on Aug 1, 2023, 4:13 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_132142
Taken on Aug 1, 2023, 1:21 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1094 of 1851
20230801_102538
Taken on Aug 1, 2023, 10:25 AM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_102532
Taken on Aug 1, 2023, 10:25 AM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1095 of 1851
20230801_161857
Taken on Aug 1, 2023, 4:18 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_161516
Taken on Aug 1, 2023, 4:15 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1096 of 1851
20230801_161500
Taken on Aug 1, 2023, 4:15 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_161451
Taken on Aug 1, 2023, 4:14 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1097 of 1851
20230801_161419
Taken on Aug 1, 2023, 4:14 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_160902
Taken on Aug 1, 2023, 4:09 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1098 of 1851
20230801_160859
Taken on Aug 1, 2023, 4:09 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_134623
Taken on Aug 1, 2023, 1:46 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1099 of 1851
20230801_134612
Taken on Aug 1, 2023, 1:46 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_134548
Taken on Aug 1, 2023, 1:45 PM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1100 of 1851
20230801_095743
Taken on Aug 1, 2023, 9:57 AM MDT
Added on Aug 2, 2023, 7:10 AM MDT
Added by Chris Johnson
20230801_134602
Taken on Aug 1, 2023, 1:46 PM MDT
Added on Aug 2, 2023, 7:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1101 of 1851
Form detail
#194: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 30, Grind Wall fins
Area 40, Concrete Placement 5 dif.
box walls, 1 slab, lower fish lift slab
Area 60 Pipe encasement
IMCO, Operators and Labors 5 10 Area 40, 60, Batch Concrete
Area 40, Excavate for Raceways
Totals 11 20
Forms
Location
Form date Jul 31, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 1, 2023, 7:29 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1102 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, Excavate for Raceways
Deere 644J Loader 1 10 Area 40, Batch Concrete, Excavate
for Raceways
IMCO Concrete Truck 1 5 Area 40, Concrete placement
IMCO Concrete Truck 1 5 Area 40, Concrete placement
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1103 of 1851
-
Notes
IMCO has made the adjustments to the 36" pipe from MH 2 to MH 4. The pipe had a belly in it and was not straight.
I was informed they did not have to remove it, they just exposed the pipe and lifted it with a strap. The crews have
also imported material inside Area 60 for under slab fill. They are using general fill. It looks to be compacted well.
8:00 am Pump truck is onsite and setting up. IMCO plans to place concrete at multiple locations. They area
planning to place 5 diffuser box walls, 1 diffuser box slab, lower fish lift slab and pipe encasements at Area 60.
9:00 am I have tested the first truck, All passed. IMCO is continuing to pour pipe encasement of the 14 drains.
12:00 pm IMCO has completed the placements. The crew is working on finishing the concrete. They placed 22.5
CY today.
2:00 pm IMCO has started to excavate for the raceways. They are stockpiling the material near holding ponds.
The crew is also working on laying out the drains inside Area 60 to begin installing that pipe.
4:00 pm IMCO has sprinklers going to cure the concrete from todays placement. A crew is inside Area 30 grinding
the concrete fins and imperfections.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1104 of 1851
References
Photos (18)
20230731_164745
Taken on Jul 31, 2023, 4:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_164718
Taken on Jul 31, 2023, 4:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1105 of 1851
20230731_164654
Taken on Jul 31, 2023, 4:46 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_144756
Taken on Jul 31, 2023, 2:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1106 of 1851
20230731_144751
Taken on Jul 31, 2023, 2:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_144715
Taken on Jul 31, 2023, 2:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1107 of 1851
20230731_103318
Taken on Jul 31, 2023, 10:33 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_093504
Taken on Jul 31, 2023, 9:35 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1108 of 1851
20230731_092716
Taken on Jul 31, 2023, 9:27 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_092712
Taken on Jul 31, 2023, 9:27 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1109 of 1851
20230731_083207
Taken on Jul 31, 2023, 8:32 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_083131
Taken on Jul 31, 2023, 8:31 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1110 of 1851
20230731_082400
Taken on Jul 31, 2023, 8:24 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_082336
Taken on Jul 31, 2023, 8:23 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1111 of 1851
20230731_144708
Taken on Jul 31, 2023, 2:47 PM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_093447
Taken on Jul 31, 2023, 9:34 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1112 of 1851
20230731_092756
Taken on Jul 31, 2023, 9:27 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
20230731_092725
Taken on Jul 31, 2023, 9:27 AM MDT
Added on Aug 1, 2023, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1113 of 1851
Form detail
#193: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Forms
Location
Form date Jul 27, 2023
Description Area 40
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 27, 2023, 1:42 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1114 of 1851
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day HMH Concrete Compressive Report from the Area 40 5 Diffuser Box Placements.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1115 of 1851
Form detail
#192: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Diffuser Boxes,
Install Water stop
IMCO, Operators and Labors 3 10 Area 10, MH 4 grout, Fix backfall in
pipe
Area 60, Chiller Room Piping and
Encasement Rebar
Totals 8 20
Forms
Location
Form date Jul 26, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 27, 2023, 7:32 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1116 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 4, 36" pipe backfall
repair
Deere 644J Loader 1 10 Area 10, MH 4
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 10, Stack MH 2 and MH 4
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1117 of 1851
-
Notes
8:00 am IMCO was scheduled to pour the fish lift slab along with the 6th diffuser box but it is still missing water
stop and the rebar needs to be cleaned up. Most of it is not plumb. I noticed the main 480 feed conduit was
broken. The crew informed me it happened yesterday while backfilling the 36" pipe at MH 4.
8:30 am Mitch and Rick, IPC, were onsite to review the broken main feed conduit.
9:00 am Attended weekly meeting.
10:00 am IMCO will not be placing the fish lift slab today. IMCO crew is also working on the pipe encasement
inside Area 60. In todays meeting Ray reviewed the pipe encasement and it was determined no vertical
encasement is needed. IMCO has grouted tie holes on the interior stem wall at Area 60.
11:00 am I was informed that the 36" drain pipe has backfall in it. I have taken a picture from MH 4 looking to MH
2. You can see the water backed up in the pipe about halfway down the pipe run. It also has an angle point in the
line that should not be there. Kirt is starting to excavate around the pipe so he can remove it and replace it.
1:00 pm IMCO has submitted a new material for Structural Fill. I drove to the pit in Halfway and taken a sample
for a Gradation and Proctor. I spoke to IMCO regarding how they plan to place the concrete in the fish lift. They
cannot dump it from a truck because the rebar is in the way and the concrete will fall to far from the shoot. They
are working on a plan to place the concrete.
3:00 pm IMCO is starting to work on the water stop in the fish lift. The overhead doors were delivered and IMCO
unloaded them.
5:00 pm IMCO has canceled the concrete placement for tomorrow. They are going to place on Monday with
hopes they can get a pump truck and place multiple small pours using the pump truck.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1118 of 1851
References
Photos (10)
20230726_143432
Taken on Jul 26, 2023, 2:34 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
20230726_143347
Taken on Jul 26, 2023, 2:33 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1119 of 1851
20230726_143332
Taken on Jul 26, 2023, 2:33 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
20230726_143045
Taken on Jul 26, 2023, 2:30 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1120 of 1851
20230726_104912
Taken on Jul 26, 2023, 10:49 AM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
20230726_102539
Taken on Jul 26, 2023, 10:25 AM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1121 of 1851
20230726_163215
Taken on Jul 26, 2023, 4:32 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
20230726_152807
Taken on Jul 26, 2023, 3:28 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1122 of 1851
20230726_143338
Taken on Jul 26, 2023, 2:33 PM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
20230726_073630
Taken on Jul 26, 2023, 7:36 AM MDT
Added on Jul 27, 2023, 7:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1123 of 1851
Form detail
#190: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30, Remove Wall Forms,
Begin installing Plugs at tie holes
IMCO, Operators and Labors 3 10 Area 10, 24" overflow drain
Totals 6 20
2. Materials
Forms
Location
Form date Jul 25, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 25, 2023, 7:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1124 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, 24" Overflow Drain
Deere 644J Loader 1 10 Area 10, 24" Overflow drain
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Strip Forms
Bomag Roller 1 8 Area 10, 24" Overflow Drain
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1125 of 1851
Notes
10:30 am IMCO is continuing to remove forms on the inside of Area 30. The crane is being used to pick items
from the inside.
12:00 pm IMCO pipe crew is working on finishing the 24" overflow pipe run from Area 30 to MH 2. This run was
changed from the original design per RFI #053.
2:00 pm IMCO is backfilling the 24" pipe with pipe bedding. They are leaving space for a thrust block on the 45
bend.
4:00 pm IMCO is working on setting the riser section on the intake valve vault. They intend to start backfilling
around Area 30.
References
Photos (3)
20230724_164358
Taken on Jul 24, 2023, 4:43 PM MDT
Added on Jul 25, 2023, 7:46 AM MDT
Added by Chris Johnson
20230724_124617
Taken on Jul 24, 2023, 12:46 PM MDT
Added on Jul 25, 2023, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1126 of 1851
20230724_151522
Taken on Jul 24, 2023, 3:15 PM MDT
Added on Jul 25, 2023, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1127 of 1851
Form detail
#191: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 40, Form Diffuser Boxes
IMCO, Operators and Labors 8 10 Area 10, MH 4
Area 60, Chiller Room Piping
Totals 13 20
2. Materials
Forms
Location
Form date Jul 25, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 26, 2023, 6:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1128 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 4
Deere 644J Loader 1 10 Area 10, MH 4
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 10, MH 4
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1129 of 1851
Notes
8:00 am IMCO is working on moving the MH 4 base that was previously installed per plan. The move is to allow
room for clearance from the retaining wall and MH 4. They moved it approx. 4 feet. It has been asked to As Built it
once complete.
10:00 am IMCO carpenters are working on forming the vertical walls of the diffuser boxes.
12:00 pm IMCO has placed MH 4 base at the new location. Another pipe crew has been working on the chiller
piping at Area 60.
2:00 pm The pipe crew has installed the 36" drain pipe to MH 4. They are now working on setting the manhole
sections.
3:00 pm I have reviewed with the IMCO crew the pipe encasement details for the chiller room piping.
4:30 pm IMCO carpenters have continued to work on installing the vertical walls for the diffuser boxes. IMCO was
able to place MH 4 sections.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1130 of 1851
References
Photos (7)
20230725_153521
Taken on Jul 25, 2023, 3:35 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
20230725_144155
Taken on Jul 25, 2023, 2:41 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1131 of 1851
20230725_144148
Taken on Jul 25, 2023, 2:41 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
20230725_125122
Taken on Jul 25, 2023, 12:51 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1132 of 1851
20230725_124356
Taken on Jul 25, 2023, 12:43 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
20230725_153617
Taken on Jul 25, 2023, 3:36 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1133 of 1851
20230725_144203
Taken on Jul 25, 2023, 2:42 PM MDT
Added on Jul 26, 2023, 6:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1134 of 1851
Form detail
#189: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Forms
Location
Form date Jul 21, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 21, 2023, 1:34 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1135 of 1851
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day HMH Concrete Compressive Report from the Area 60 Stem Wall Placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1136 of 1851
Form detail
#188: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Strip Stem Walls
Area 30 Strip Wall Forms
Area 40, Weld Waterstop, Place 5
Diffuser Box Slabs
IMCO, Operators and Labors 3 10 Area 10, Yard piping
Area 40, Batch Concrete
Vale Electric, Electricians 3 10 Area 60, Under Slab Raceways
Totals 12 30
Forms
Location
Form date Jul 20, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 21, 2023, 1:31 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1137 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 4
Deere 644J Loader 1 5 Area 40, Batch Concrete
IMCO Concrete Truck 1 3 Area 40, Batch Concrete
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Strip Forms
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1138 of 1851
Notes
See attached 28 day HMH Concrete Compressive Report from the Area 60 Footing Placement.
8:00 am IMCO is continuing to work on the waterstop for the diffuser boxes and the bottom fish lift slab. There is
rebar that needs to be adjusted and some rebar that needs to be added before they can place the fish lift slab.
They are still planning to place concrete today.
10:00 am Vale Electric is continuing to install raceway piping at Area 60 while IMCO continues to strip the forms
off Area 60 and Area 30. IMCO planned to install a inserta T for the 6" drain line outside Area 30. I asked Jake
Kreglo to ensure this was submitted. It was not so he sent it in this morning. I have a concern it will not meet the
test pressures per the specification.
12:00 pm IMCO is continuing to work on removing forms at Area 30 and Area 60.
1:00 pm Jake informed me they are getting ready to start batching concrete to pour the 6 diffuser box slabs.
2:00 pm I have tested the concrete and all was in spec. The crew is pouring the diffuser slabs now.
4:00 pm IMCO has completed the pour and is working on finishing the slabs now. They ran out of concrete so
they did not place the 6th slab on the North End of the raceways
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1139 of 1851
References
Photos (2)
20230720_143334
Taken on Jul 20, 2023, 2:33 PM MDT
Added on Jul 21, 2023, 7:19 AM MDT
Added by Chris Johnson
20230720_143327
Taken on Jul 20, 2023, 2:33 PM MDT
Added on Jul 21, 2023, 7:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1140 of 1851
Form detail
#187: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Strip Stem Walls
Area 30 Strip Wall Forms
Area 40, Weld Waterstop
IMCO, Operators and Labors 3 10 Area 10, Yard piping
Area 60, Under Slab piping
Vale Electric, Electricians 3 10 Area 60, Under Slab Raceways
Totals 12 30
Forms
Location
Form date Jul 19, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 20, 2023, 7:04 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1141 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 2 to MH 4
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Strip Forms
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1142 of 1851
Notes
8:00 am IMCO is continuing to work on the 36" drain line from MH 2 to MH 4. They are currently setting grade for
MH 4.
9:00 am IMCO is continuing stripping the forms off the stem wall at Area 60. Vale Electric is onsite to install the
raceway conduit under the slab/ through the stem wall. Attended weekly meeting.
10:00 am IMCO carpenters are continuing stripping the wall forms from the interior of Area 30. IMCO has set the
base section for MH 4.
12:00 pm A small crew is working on the water stop for the diffuser boxes. In the meeting it was discussed that
they would be placing that concrete tomorrow. IMCO is waiting for the crane to free up so they can set the
manhole sections at MH 4.
2:00 pm IMCO is still waiting for the crane to free up to set the rest of MH4. The other crews are continuing to
work on stripping wall forms at both Area 30 and Area 60.
4:00 pm IMCO has removed the stump from the tree that was in conflict with MH 4. IMCO had survey onsite
checking locations and scanning the site to ensure location compliance. He notified everyone that MH 4 will be in
conflict with the retaining wall footing. IMCO has submitted an RFI looking for direction.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1143 of 1851
References
Photos (6)
20230719_161656
Taken on Jul 19, 2023, 4:16 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
20230719_161512
Taken on Jul 19, 2023, 4:15 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1144 of 1851
20230719_125316
Taken on Jul 19, 2023, 12:53 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
20230719_161606
Taken on Jul 19, 2023, 4:16 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1145 of 1851
20230719_125320
Taken on Jul 19, 2023, 12:53 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
20230719_125313
Taken on Jul 19, 2023, 12:53 PM MDT
Added on Jul 20, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1146 of 1851
Form detail
#185: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Strip Stem Walls
Area 30 Strip Wall Forms
IMCO, Operators and Labors 3 10 Area 10, Yard piping
Totals 9 20
2. Materials
Forms
Location
Form date Jul 18, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 18, 2023, 7:13 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1147 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Area 30 to MH 2
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Strip Forms
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1148 of 1851
Notes
10:00 am IMCO is working on removing the stem wall forms at Area 60 and the the wall forms at Area 30.
12:00 pm I am continuing to check the surface as they remove forms. I have not seen any rock pockets or
unconsolidated concrete yet.
2:00 pm IMCO pipe crew is working on installing romac fittings and pipe leaving Area 30. The carpenters are
continuing to strip forms.
5:00 pm IMCO was able to strip the exterior wall forms from Ara
References
Photos (8)
20230717_154932
Taken on Jul 17, 2023, 3:49 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
20230717_140816
Taken on Jul 17, 2023, 2:08 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1149 of 1851
20230717_140525
Taken on Jul 17, 2023, 2:05 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
20230717_155715
Taken on Jul 17, 2023, 3:57 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1150 of 1851
20230717_155042
Taken on Jul 17, 2023, 3:50 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
20230717_140717
Taken on Jul 17, 2023, 2:07 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1151 of 1851
20230717_140639
Taken on Jul 17, 2023, 2:06 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
20230717_140540
Taken on Jul 17, 2023, 2:05 PM MDT
Added on Jul 18, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1152 of 1851
Form detail
#186: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Strip Stem Walls
Area 30 Strip Wall Forms
Area 40, Weld Waterstop
IMCO, Operators and Labors 3 10 Area 10, Yard piping
Area 60, Under Slab piping
Totals 9 20
2. Materials
Forms
Location
Form date Jul 18, 2023
Description Area 10, Area 30, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 19, 2023, 7:01 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1153 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Area 30 to MH 2
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30 Strip Forms
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1154 of 1851
Notes
8:00 am IMCO is continuing to strip the forms on Area 30 and Area 60. The pipe crew is continuing to excavate for
the drain line from MH 2 to MH 4.
9:00 am IPC was onsite to notify IMCO that the alarms have been going off at the shop. IMCO must of hit the
alarm line while installing the drain pipe to MH 4. I asked IMCO to make sure and mark the location of lines to be
spliced back together before the hatchery operations start up again.
12:00 pm IMCO is continuing to work on stripping the forms on both Area 60 and Area 30.
2:00 pm IMCO crew has started to weld water stop for the diffuser boxes.
4:00 pm IMCO is continuing to work on excavating for MH 4 and the pipe run to it. They have exposed all the
utilities in the trench. They have hit ground water as well.
5:00 pm IMCO informed me they plan to place concrete for the diffuser boxes and the fish lift along with pipe
encasement Thursday. The crew has been working on the interior piping in the incubation room at Area 60. Vale
Electrical has also been installing the conduit through the block outs in the stem wall.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1155 of 1851
References
Photos (7)
20230718_165009
Taken on Jul 18, 2023, 4:50 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
20230718_164947
Taken on Jul 18, 2023, 4:49 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1156 of 1851
20230718_164943
Taken on Jul 18, 2023, 4:49 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
20230718_151327
Taken on Jul 18, 2023, 3:13 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1157 of 1851
20230718_151208
Taken on Jul 18, 2023, 3:12 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
20230718_151155
Taken on Jul 18, 2023, 3:11 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1158 of 1851
20230718_164937
Taken on Jul 18, 2023, 4:49 PM MDT
Added on Jul 19, 2023, 7:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1159 of 1851
Form detail
#184: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Form stem walls
IMCO, Operators and Labors 5 10 Area 60, Batch Concrete
Totals 11 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 14, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 15, 2023, 10:59 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1160 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Area 30 to MH 2
Deere 644J Loader 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 10 Area 60, Batch Concrete
IMCO Concrete Truck 1 10 Area 60, Batch Concrete
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is making final preparations for the stem wall placement today.
8:00 am Pump truck is onsite and the crew is starting to batch concrete.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1161 of 1851
9:00 am The first truck is batched. They primed the pump and placed ~1 CY in the forms. I took my sample and
tested the air. The air was too high at 7.9%. Sean used the 4 CY truck in a pipe encasement for the cross crowder
floor drains. They are pouring the concrete in piles over the drain pipe to hold it down and prevent it from floating.
They will come back later and pour the entire encasement.
10:00 am The second truck has started to pour out. I took my sample and the concrete tested all in spec. They
continued to place in the stem walls.
12:30 pm. IMCO has finished the placement of the stem walls. The crew is now working on finishing the concrete
to grade.
References
Photos (7)
20230714_122719
Taken on Jul 14, 2023, 12:27 PM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
20230714_093602
Taken on Jul 14, 2023, 9:36 AM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1162 of 1851
20230714_122514
Taken on Jul 14, 2023, 12:25 PM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
20230714_122446
Taken on Jul 14, 2023, 12:24 PM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1163 of 1851
20230714_085402
Taken on Jul 14, 2023, 8:54 AM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
20230714_075610
Taken on Jul 14, 2023, 7:56 AM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1164 of 1851
20230714_075607
Taken on Jul 14, 2023, 7:56 AM MDT
Added on Jul 14, 2023, 12:40 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1165 of 1851
Form detail
#183: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 7 10 Area 60 Form stem walls
IMCO, Operators and Labors 5 10 Area 10, Piping from Area 30 to
MH 2
Totals 12 20
2. Materials
Forms
Location
Form date Jul 13, 2023
Description Area 10, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 14, 2023, 6:53 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1166 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Area 30 to MH 2
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1 10 Trench Compaction
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1167 of 1851
Notes
See attached HMH Compressive Strength Report from the 7 day 2nd Wall placement.
8:00 am IMCO is continuing to work on installing the stem wall forms. The crew has started to lay out the hold
downs and the anchor bolts and installing them.
9:00 am IMCO has removed most of the tree that is in conflict with MH4. The stump is still there but the rest is
gone. They are waiting on pins for the stacker trench box before they can continue installing the pipe and
manhole. They have exposed the power and is waiting for IPC to deenergize the line.
11:00 am RFI 114 has been answered and the crew is going to work on blocking out for the electrical conduit at
Area 60. The RFI included rebar modifications.
2:00 pm IMCO has made the rebar modifications per RFI 114. Photos are attached. The crew is continuing to work
on closing up the forms and preparing to place the stem wall concrete tomorrow.
3:00 pm IMCO is working on installing the 24" drain pipe from Area 30 to MH2.
5:00 pm IMCO has installed the Romac coupler and one bell piece for the double joint connection outside a
strucuture on the drain pipe from Area 30 to MH 2. The carpenter crew is finishing up the forming and prepping
for the placement tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1168 of 1851
References
Photos (7)
20230713_155912
Taken on Jul 13, 2023, 3:59 PM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
20230713_135246
Taken on Jul 13, 2023, 1:52 PM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1169 of 1851
20230713_111043
Taken on Jul 13, 2023, 11:10 AM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
20230713_135257
Taken on Jul 13, 2023, 1:52 PM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1170 of 1851
20230713_135250
Taken on Jul 13, 2023, 1:52 PM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
20230713_125151
Taken on Jul 13, 2023, 12:51 PM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1171 of 1851
20230713_111034
Taken on Jul 13, 2023, 11:10 AM MDT
Added on Jul 14, 2023, 6:53 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1172 of 1851
Form detail
#182: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 7 10 Area 60 Form stem walls
IMCO, Operators and Labors 5 10 Area 10, Piping from MH 2 to MH 4
EOI 2 10 Area 40, Tie Rebar for fish lift slab
Totals 14 30
2. Materials
Forms
Location
Form date Jul 12, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 12, 2023, 5:00 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1173 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 2 to MH 4
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control, Fill Irrigation tank
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1174 of 1851
Notes
8:00 am IMCO is backfilling the drain pipe now. They are using the water truck to apply water to the pipe bedding
and native fill. The carpenter crew is continuing to work on the stem wall at Area 60.
9:00 am Attended weekly meeting.
11:00 am Sean and I reviewed the locations and clearances for the HDs on Area 60. They are currently laying
them out now. The pipe crew is starting to excavate for existing utilities near MH 4.
1:00 pm EOI is onsite to tie the bar for the fish lift.
4:00 pm IMCO has located some utilities. They are now working on removing the tree that is encroaching on the
retaining wall and MH 4. IMCO carpenters are continuing to work on the stem wall forming. Part of the pipe crew
has started to weld HDPE fittings together for the spray bars.
4:30 pm EOI is continuing to install the rebar for the fish lift. As I make periodic spot checks I noticed they had the
IF and OF dowel bars reversed. They agreed and is starting to fix it now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1175 of 1851
References
Photos (4)
20230712_161116
Taken on Jul 12, 2023, 4:11 PM MDT
Added on Jul 12, 2023, 4:59 PM MDT
Added by Chris Johnson
20230712_161021
Taken on Jul 12, 2023, 4:10 PM MDT
Added on Jul 12, 2023, 4:59 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1176 of 1851
20230712_161012
Taken on Jul 12, 2023, 4:10 PM MDT
Added on Jul 12, 2023, 4:59 PM MDT
Added by Chris Johnson
20230712_111415
Taken on Jul 12, 2023, 11:14 AM MDT
Added on Jul 12, 2023, 4:59 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1177 of 1851
Form detail
#181: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 7 10 Area 60 Form stem walls
Area 40, Form fish lift slab
IMCO, Operators and Labors 4 10 Area 10, Piping from MH 2 to MH 4
Area 20, Pull irrigation pump,
Reinstall
Totals 11 20
2. Materials
Forms
Location
Form date Jul 11, 2023
Description Area 10, Area 40, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 12, 2023, 7:10 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1178 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, MH 2 to MH 4
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 5 Area 20 Irrigation Pump
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control, Fill Irrigation tank
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1179 of 1851
Notes
See attached HMH Compressive Strength Test Report from the 28 Day 1st Wall Placement at Area 30.
8:00 am IMCO is continuing to work on the stem walls at the Hatchery Building. They also are working on the slab
for the fish lift. EOI is onsite today to tie rebar for the fish lift slab along with piers for the hatchery building.
9:00 am IMCO pipe crew is going to continue to install the drain pipe from MH 2 to MH 4. They are using a trench
box.
11:00 pm IMCO has installed 1 stick of pipe from MH 2 to MH 4. The wall crew is continuing to work on bracing the
stem wall forms. I have noticed a few locations where the rebar is in need of attention. I spoke to the 2 foreman,
Tyler and Jake, about fixing some of them. They got right on it and fixed the rebar per DC16A. EOI is working on
tying rebar for the post piers at Area 60.
2:00 pm IMCO has reinstalled the irrigation pump. They are working on plumbing it together now.
4:30 pm IMCO has excavated and installed a stick of pipe from MH 2 to MH4. The wall crew continues to install
the stem wall forms. They are still planning to place that Friday.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1180 of 1851
References
Photos (4)
20230711_154708
Taken on Jul 11, 2023, 3:47 PM MDT
Added on Jul 12, 2023, 7:08 AM MDT
Added by Chris Johnson
20230711_105737
Taken on Jul 11, 2023, 10:57 AM MDT
Added on Jul 12, 2023, 7:08 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1181 of 1851
20230711_135129
Taken on Jul 11, 2023, 1:51 PM MDT
Added on Jul 12, 2023, 7:08 AM MDT
Added by Chris Johnson
20230711_095637
Taken on Jul 11, 2023, 9:56 AM MDT
Added on Jul 12, 2023, 7:08 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1182 of 1851
Form detail
#180: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 6 10 Area 60 Form stem walls
IMCO, Operators and Labors 4 10 Area 10, Begin piping from MH 2 to
MH 4
Area 20, Pull irrigation pump
Area 50, Excavate for fish lift
platform
Totals 10 20
Forms
Location
Form date Jul 10, 2023
Description Area 10, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 11, 2023, 7:57 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1183 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 50, Fish Lift Floor Excavation
Area 10, MH 2 to MH 4
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 110 Move material around
site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 5 Area 20 Irrigation Pump
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control, Fill Irrigation tank
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1184 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:30 am IMCO is continuing to work on form the stem walls at Area 60, Hatchery Building. They are starting to
close up the walls. I noticed the a foam block out mid wall that they had to cut a vertical rebar for. I did not see any
trim bar around the block out. I showed Jake, Foreman, the detail in the drawings and he installed rebar per the
detail and continued closing up the walls. The crew is also pulling the irrigation pump again. I was informed that
over the weekend the pump stopped working. They are pulling it now to see what the issue is.
12:00 pm IMCO is waiting for some ladders before they begin removing the forms from the Area 30 placement
from last week. Once the forms are down they have no way to climb the wall to access the inside. A runner went to
town to pick up some longer extension ladders. Jake Kreglo informed me EOI will be onsite tomorrow to fix the
rebar that was tied for the 14 drains pipe encasement. The rebar was tied to high above the top of pipe and it
protruding into the slab of the structure.
1:00 pm IMCO performed a safety demonstration and practice for using the safety man basket with the crane.
2:00 pm IMCO is continuing to work on forming the stem walls. The operators are excavating for the bottom of
the fish lift
4:00 pm IMCO has placed structural fill to grade for the fish lift base slab. They are now working on excavating for
the drain pipe from MH 2 to MH 4. They are working on setting a trench box. Rick and Casey, IPC, were onsite to
discuss killing the power from the main feeds to allow a safer excavation while installing the drain line and MH 4.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1185 of 1851
References
Photos (7)
20230710_155558
Taken on Jul 10, 2023, 3:55 PM MDT
Added on Jul 11, 2023, 7:57 AM MDT
Added by Chris Johnson
20230710_155547
Taken on Jul 10, 2023, 3:55 PM MDT
Added on Jul 11, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1186 of 1851
20230710_155441
Taken on Jul 10, 2023, 3:54 PM MDT
Added on Jul 11, 2023, 7:57 AM MDT
Added by Chris Johnson
20230710_110334
Taken on Jul 10, 2023, 11:03 AM MDT
Added on Jul 11, 2023, 7:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1187 of 1851
20230710_155848
Taken on Jul 10, 2023, 3:58 PM MDT
Added on Jul 11, 2023, 7:57 AM MDT
Added by Chris Johnson
20230710_155608
Taken on Jul 10, 2023, 3:56 PM MDT
Added on Jul 11, 2023, 7:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1188 of 1851
20230710_132043
Taken on Jul 10, 2023, 1:20 PM MDT
Added on Jul 11, 2023, 7:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1189 of 1851
Form detail
#179: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 60 Form stem walls
IMCO, Operators and Labors 4 10 Area 20 Reinstall Irrigation Pump
Totals 13 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 7, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 10, 2023, 11:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1190 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 5 Area 20 Irrigation Pump
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control, Fill Irrigation tank
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1191 of 1851
Notes
8:00 am IMCO is continuing to work on the Irrigation pump at Area 20. The carpenters are forming stem walls at
Area 60.
10:00 am IMCO has the pump installer onsite to fix the irrigation pump. I have been told it was a wire that got
exposed during the install last summer.
12:00 pm IMCO has reset the irrigation pump and was able to turn it back on. The fittings were leaking so they
are working on tightening up now.
1:30 pm IMCO is breaking down the wall scaffolding and prepping to remove the forms Monday. They are also
continuing to set the stem wall forms for the Hatchery building.
References
Photos (3)
20230707_115758
Taken on Jul 7, 2023, 11:57 AM MDT
Added on Jul 10, 2023, 10:59 AM MDT
Added by Chris Johnson
20230707_103428
Taken on Jul 7, 2023, 10:34 AM MDT
Added on Jul 10, 2023, 10:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1192 of 1851
20230707_094049
Taken on Jul 7, 2023, 9:40 AM MDT
Added on Jul 10, 2023, 10:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1193 of 1851
Form detail
#178: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 9 10 Area 30 Concrete placement
Area 60 Form stem walls
IMCO, Operators and Labors 4 10 Area 30 Batch concrete
Totals 13 20
2. Materials
Forms
Location
Form date Jul 6, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 7, 2023, 9:24 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1194 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 30 Batch Concrete
IMCO Concrete Truck 1 10 Area 30 Batch Concrete
IMCO Concrete Truck 1 10 Area 30 Batch Concrete
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60 Excavate for under slab
piping
Dump Truck 1
Kobelco 1100G Crane 1 5 Area 20 Pull Irrigation Pump
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control, Fill Irrigation tank
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1195 of 1851
-
Notes
See attached HMH Concrete Field Report.
8:00 am The pump truck is onsite and setting up. IMCO is going to place concrete for the second wall pour at the
Aeration tower. I was informed that the irrigation pump at Area 20 is not working. IMCO has been working with
Heath, IPC, to check for issues in the control panel. IMCO is has decided to pull the pump from the intake structure.
9:00 am IMCO is starting to place WRDA concrete at Area 30. IMCO has the crane pulling the pump from the
intake structure.
9:30 am I have taken a test on the first concrete truck. All passed. The slump was low so they are going to adjust
at the plant.
11:00 am IMCO is continuing to place concrete. They are placing at 2 foot lifts with a stinger for consolidation.
They are also using wall vibrators for the first few lifts. IMCO has a second crew working on forming the stem walls
at Area 60. They have cut the rebar per DC 16A. They have installed the extra vertical bar in the 6" curb as well.
12:00 pm I noticed the diffuser boxes at Area 40 along with the drains for the cross crowder have the rebar
installed. I noticed the rebar on the drains was 12" over the pipe. The detail calls for 6". I asked IMCO to double
check that. They informed me that it should be 6" and they will have it fixed.
1:00 pm I have performed a second concrete test on the wall placement. Slump was high at 7". Sean is going to
adjust at the plant.
2:30 pm IMCO has completed the placement. They will not work on finishing the top.
3:30 pm I noticed that IMCO carpenters blocked out the door thresholds at Area 60 only top of slab, 6". I asked
IMCO if that was the intent because I was under the impression that it should be blocked out to 12" or bottom of
slab, and the slab will wrap over the stem wall for a nice clean finish. After discussing with Kurt, Sean and Jake. It
was determined that they need to re build the block outs to 12".
5:00 pm IMCO is done for the day. They have placed curing compound on top of the wall.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1196 of 1851
References
Photos (7)
20230706_084647
Taken on Jul 6, 2023, 8:46 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
20230706_110749
Taken on Jul 6, 2023, 11:07 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1197 of 1851
20230706_154504
Taken on Jul 6, 2023, 3:45 PM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
20230706_091238
Taken on Jul 6, 2023, 9:12 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1198 of 1851
20230706_111749
Taken on Jul 6, 2023, 11:17 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
20230706_085517
Taken on Jul 6, 2023, 8:55 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1199 of 1851
20230706_110720
Taken on Jul 6, 2023, 11:07 AM MDT
Added on Jul 7, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1200 of 1851
Form detail
#177: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Jun 29, 2023
Description Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 29, 2023, 9:04 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1201 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day Concrete Compressive Strength report from Area 60 footing placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1202 of 1851
Form detail
#176: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 7 10 Area 30 Continue installing forms,
blockouts, sleeves
Area 60 Form stem walls
IMCO, Operators and Labors 5 10 Area 10 Lay out drain piping for
cross crowder
Totals 12 20
2. Materials
Forms
Location
Form date Jun 28, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 29, 2023, 6:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1203 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Drains for cross crowder
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60 Excavate for under slab
piping
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1204 of 1851
-
Notes
8:00 am IMCO is continuing to set the 14 drains for the cross crowder channel. They are continuing to block it up
to allow 6 inches below for concrete encasement.
9:00 am IMCO has the rest of the crew back from vacation. They area working on finishing the forming for Area
30. The plan is to pour this tomorrow. Attended weekly meeting.
10:00 am Sean informed me during the meeting that they will not be ready for the wall placement tomorrow. He
is pushing it to Wednesday of the holiday. Schnabel has issued a Design Clarification for Area 60. The DC changes
the stem wall to support a 6" wide 6" tall curb to allow for the floor slab to be installed to the framing, for a better
finished product.
12:00 pm IMCO has is continuing to work on stem wall forming. They are getting a game plan together to being
cutting the rebar for the DC. The Area 30 crew is working on bracing and finishing the forming of the walls.
1:00 pm Jake has emailed me a change in the pour date for Area 30. They were unable to get a pump truck for
Wednesday of next week so they will pour on Thursday of next week now.
2:00 pm Lighting has been detected within 5 miles so the crew is shutting down until the storm goes away.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1205 of 1851
References
Photos (8)
20230628_125815
Taken on Jun 28, 2023, 12:58 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
20230628_125758
Taken on Jun 28, 2023, 12:57 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1206 of 1851
20230628_125309
Taken on Jun 28, 2023, 12:53 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
20230628_125257
Taken on Jun 28, 2023, 12:52 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1207 of 1851
20230628_124746
Taken on Jun 28, 2023, 12:47 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
20230628_124742
Taken on Jun 28, 2023, 12:47 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1208 of 1851
20230628_124737
Taken on Jun 28, 2023, 12:47 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
20230628_124733
Taken on Jun 28, 2023, 12:47 PM MDT
Added on Jun 29, 2023, 6:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1209 of 1851
Form detail
#174: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Continue installing forms,
blockouts, sleeves
Area 60 Strip footings
IMCO, Operators and Labors 5 10 Area 10 Pour pipe encasements for
drains
Totals 8 20
2. Materials
Forms
Location
Form date Jun 27, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 27, 2023, 7:04 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1210 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10 Batch Concrete
IMCO Concrete Truck 1 10 Area 10 Pipe Encasement
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60 Excavate for under slab
piping
Dump Truck 1
Kobelco 1100G Crane 1 8 Area 10 Place Concrete
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1211 of 1851
-
Notes
10:00 am IMCO is prepping to place concrete for the pipe encasements of the drains from the diffuser box to MH
7.
11:00 am I pointed out to IMCO that the rebar was not per plan for the pipe encasements. They needed to extend
the rebar to the limits of the concrete to be place. They area going to start working on adding rebar to meet the
plan detail.
12:00 pm IMCO has batched concrete and is starting to place with the crane and concrete bucket. I spoke to Zack,
IPC, and it was decided not to test the concrete today.
2:00 pm IMCO has placed the pipe encasements. They also encased the fish lift drain as well. They held the
concrete down on all placements to allow forming for the structures themselves. These elevations were
determined my IMCO.
3:00 pm IMCO is continuing to work on Area 30 in preparation for a concrete placement Wednesday. I noticed an
embed not installed. I asked Jake Kreglo about it. He informed me an embed was missed on the first placement.
They are still working on a plan to submit as a fix for the missed embed.
5:00 pm IMCO has been working on stripping Area 60 forms from last weeks footing placement. They have also
picked the mini excavator and placed it inside the footings to begin excavating for the under slab piping.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1212 of 1851
References
Photos (6)
20230626_152256
Taken on Jun 26, 2023, 3:22 PM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
20230626_152249
Taken on Jun 26, 2023, 3:22 PM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1213 of 1851
20230626_152344
Taken on Jun 26, 2023, 3:22 PM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
20230626_131921
Taken on Jun 26, 2023, 1:19 PM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1214 of 1851
20230626_115438
Taken on Jun 26, 2023, 11:54 AM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
20230626_105146
Taken on Jun 26, 2023, 10:51 AM MDT
Added on Jun 27, 2023, 7:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1215 of 1851
Form detail
#175: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Continue installing forms,
blockouts, sleeves
Area 60 begin forming stem walls
IMCO, Operators and Labors 5 10 Area 10 Lay out drain piping for
cross crowder
Totals 10 20
2. Materials
Forms
Location
Form date Jun 27, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 28, 2023, 7:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1216 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Drains for cross crowder
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60 Excavate for under slab
piping
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 10 Dust Control
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1217 of 1851
-
Notes
8:30 am IMCO is laying out the drain piping for the cross crowder channel. I noticed them backfilling some
exposed rebar from the pipe encasements yesterday. I informed them the rebar needs to be fully encased in
concrete and not in contact with the ground. They are going to begin removing the material they placed to expose
the rebar.
10:30 am IMCO is laying out the stem wall at Area 60. Sean and I reviewed the drawings and I pointed out to him
that the breezeway framing walls are on the center of the stem walls. He is going to inform his crew of that. They
have snapped lines on the concrete and starting to pin down forms.
12:00 pm IMCO has anchored down a 2x4 and they are ripping form boards to add to a full sheet of form board
to make up the wall height of 4'2" for the stem wall. The pipe crew is working on grading for the 14 cross crowder
drains.
1:30 pm I have reviewed the raceway wall penetrations with Vale and Jake. It seems that some of the vertical
rebar needs to be cut out of the way. Unfortunately the elevation of the conduits is right on top of the footing. This
does not allow room for trim bar to be installed because the footing is already poured. Jake is going to RFI this
issue to see how they can address it.
4:00 pm IMCO is continuing to set up forms for the the stem walls. The pipe crew has set the grade for the drains
including the pipe encasement. They area setting the drain pipe to elevation now and blocking up with concrete
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1218 of 1851
References
Photos (5)
20230627_164401
Taken on Jun 27, 2023, 4:44 PM MDT
Added on Jun 28, 2023, 7:19 AM MDT
Added by Chris Johnson
20230627_164314
Taken on Jun 27, 2023, 4:43 PM MDT
Added on Jun 28, 2023, 7:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1219 of 1851
20230627_164303
Taken on Jun 27, 2023, 4:43 PM MDT
Added on Jun 28, 2023, 7:19 AM MDT
Added by Chris Johnson
20230627_130527
Taken on Jun 27, 2023, 1:05 PM MDT
Added on Jun 28, 2023, 7:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1220 of 1851
20230627_130521
Taken on Jun 27, 2023, 1:05 PM MDT
Added on Jun 28, 2023, 7:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1221 of 1851
Form detail
#173: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Operators and Labors 3 10 Area 10 Backfill pipe encasements,
Import General fill
Totals 3 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jun 23, 2023
Description Area 10
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 23, 2023, 10:52 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1222 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Backfill
Deere 644J Loader 1 10 Area 10 Load General fill
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1
Hitachi 85 Excavator 1 10 Area 10 Hoepack Compaction
Dump Truck 1 10 Area 10 Import general fill
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1 3 Area 10, Compaction moisture,
Dust Control
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1223 of 1851
Notes
8:00 am IMCO is going to work on backfilling the pipe encasements, They have a small crew onsite today.
9:30 am IMCO is also moving sprinklers around for the curing of the footings from yesterdays placement. I talked
to Berny regarding the dust control as they are hauling material onsite from the stockpile across the river.
10:00 am Berny asked me about backfilling near the drains for the diffuser boxes. I advised him that entire pipe
should be encased in concrete and he will need the limits of the diffuser box to determine the height of the pipe
encasement. He said he would wait for Kirt to be here on Monday to provide the limits and elevations.
11:00 am Left site to return concrete cylinders from yesterdays placement.
References
Photos (2)
20230623_104457
Taken on Jun 23, 2023, 10:44 AM MDT
Added on Jun 23, 2023, 10:51 AM MDT
Added by Chris Johnson
20230623_104446
Taken on Jun 23, 2023, 10:44 AM MDT
Added on Jun 23, 2023, 10:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1224 of 1851
Form detail
#172: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 60 Pour concrete footings
IMCO, Operators and Labors 5 10 Area 10 Pour pipe encasements for
drains
Area 60 Pour footings
Totals 8 20
2. Materials
Forms
Location
Form date Jun 22, 2023
Description Area 10, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 22, 2023, 4:42 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1225 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1 10 Area 10, 60 Batch Concrete
IMCO Concrete Truck 1 10 Area 60 Footing placement
IMCO Concrete Truck 1 10 Area 60 Footing Placement
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1226 of 1851
Notes
See attached IMCO batch tickets and HMH Concrete Field Report.
7:30 am IMCO is working on the last preparations for the footing placement today at Area 60. They also plan to
place concrete for the pipe encasements on Area 10 drains from the diffuser boxes to MH7.
10:00 am The pump truck is onsite and IMCO is batching concrete.
11:00 am IMCO has started to place concrete at Area 60 Footings. I have tested the first truck and all was in spec.
I casted 9 cylinders for compressive testing.
1:30 pm IMCO has completed the footing placement and is now working for the pipe encasements of the 6
diffuser drain lines. They also are placing concrete behind the 12" manifold as a thrust block.
2:30 pm IMCO has completed the placing of concrete for the day.
4:30 pm IMCO is going to keep sprinklers running on the footings as a curing method.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1227 of 1851
References
Photos (9)
20230622_134651
Taken on Jun 22, 2023, 1:46 PM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
20230622_122444
Taken on Jun 22, 2023, 12:24 PM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1228 of 1851
20230622_103719
Taken on Jun 22, 2023, 10:37 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
20230622_101523
Taken on Jun 22, 2023, 10:15 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1229 of 1851
20230622_100113
Taken on Jun 22, 2023, 10:01 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
20230622_100049
Taken on Jun 22, 2023, 10:00 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1230 of 1851
20230622_100035
Taken on Jun 22, 2023, 10:00 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
20230622_100009
Taken on Jun 22, 2023, 10:00 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1231 of 1851
20230622_100000
Taken on Jun 22, 2023, 10:00 AM MDT
Added on Jun 22, 2023, 4:25 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1232 of 1851
Form detail
#171: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 10 Area 60 Form pipe encasements
IMCO, Operators and Labors 5 10 Area 10 Continue installing drain
piping from diffuser floor inlet to
MH 7
Totals 7 20
2. Materials
Forms
Location
Form date Jun 21, 2023
Description Area 10, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 21, 2023, 5:03 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1233 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Drain piping
Deere 644J Loader 1 10 Area 10 Backfilling
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Drain Pipe install
Dump Truck 1 8 Area 10 Import pipe bedding
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1234 of 1851
Notes
8:00 am IMCO is making the final pipe encasement forms for Area 60 footing pour tomorrow.
9:00 am Attended weekly meeting.
10:00 am IMCO pipe crew is finishing up the drain piping from the diffuser boxes to MH 7.
12:00 pm I received an email from Schnabel regarding some clarifications at Area 60. I went over the
clarifications with Kirt and Jake. They included no curb in the office area at all, including exterior walls. They also
said IMCO may lap the slap over the stem wall at door thresholds and at the walkway. These are shown in the
Architectural drawings. They also addressed sawcutting the control joints in the office building. They stated IMCO
can do this by sawcutting at a depth of 1 1/2 deep and filling it with a good caulk.
1:00 pm IMCO is continuing to work on pipe encasements at Area 60. The pipe crew is completing the drain
piping and they plan to prepare some rebar cages for the encasement of the drain piping. Vale electric has
installed the grounding loop in the footing along the rebar. Please see photos.
4:00 pm IMCO and I have checked the dimensions of Area 60 footings. Only a couple minor adjustments were
needed. They are making the adjustments now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1235 of 1851
References
Photos (8)
20230621_163701
Taken on Jun 21, 2023, 4:37 PM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
20230621_163731
Taken on Jun 21, 2023, 4:37 PM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1236 of 1851
20230621_163720
Taken on Jun 21, 2023, 4:37 PM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
20230621_163651
Taken on Jun 21, 2023, 4:36 PM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1237 of 1851
20230621_110710
Taken on Jun 21, 2023, 11:07 AM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
20230621_110701
Taken on Jun 21, 2023, 11:07 AM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1238 of 1851
20230621_110648
Taken on Jun 21, 2023, 11:06 AM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
20230621_110641
Taken on Jun 21, 2023, 11:06 AM MDT
Added on Jun 21, 2023, 5:00 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1239 of 1851
Form detail
#170: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Prep for wall placement
Area 60 Form pipe encasements
IMCO, Operators and Labors 5 10 Area 10 Continue installing drain
piping from diffuser floor inlet to
MH 7
Totals 10 20
2. Materials
Forms
Location
Form date Jun 20, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 21, 2023, 7:54 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1240 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Drain piping
Deere 644J Loader 1 10 Area 10 Backfilling
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Drain Pipe install
Dump Truck 1 8 Area 10 Import pipe bedding
Kobelco 1100G Crane 1 10 Area 30 Fly in forms for the wall
placement, Standby for safety
rescue from inside the forms
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1241 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is going to continue prepping the walls for the next wall placement. They have embeds and pipe
sleeves to finish along with some bracing. They still plan to pour these sections of the wall next Wednesday.
10:00 am IMCO pipe crew is continuing the drain piping from the diffusers boxes to the 12" manifold to MH 7.
12:00 pm IMCO is also working on the pipe encasements for Area 60. Because the pipes are encased in the
footing they are having to pour them at the same time as the footing pour. They are still planning to pour
Thursday of this week.
2:00 pm IMCO is continuing to work on drain piping to MH 7.
4:00 pm IMCO is continuing to get the pipe penetrations through the footings and forming around them.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1242 of 1851
References
Photos (4)
20230620_090831
Taken on Jun 20, 2023, 9:08 AM MDT
Added on Jun 21, 2023, 7:20 AM MDT
Added by Chris Johnson
20230620_161021
Taken on Jun 20, 2023, 4:10 PM MDT
Added on Jun 21, 2023, 7:20 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1243 of 1851
20230620_144007
Taken on Jun 20, 2023, 2:40 PM MDT
Added on Jun 21, 2023, 7:20 AM MDT
Added by Chris Johnson
20230620_143956
Taken on Jun 20, 2023, 2:39 PM MDT
Added on Jun 21, 2023, 7:20 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1244 of 1851
Form detail
#169: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Prep for wall placement
Area 60 Lay out doors for EOI,
Finish framing footing forms
IMCO, Operators and Labors 7 10 Area 10 Begin installing drain
piping from diffuser floor inlet to
MH 7
EOI 3 10 Area 60, Tie Rebar
Totals 15 30
Forms
Location
Form date Jun 19, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 20, 2023, 7:05 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1245 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Drain Pipe install
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
Water Truck 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1246 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
9:30 am IMCO is working on forming the footings at Area 60. EOI is onsite working on the rebar for Area 60. They
are installing all the bar for the stem wall now as well.
11:00 am IMCO carpenters are working on Area 30 walls. They worked this weekend hanging forms and getting it
ready for placement. Sean informed me they will not be ready to pour tomorrow and he is losing a couple a guys
to vacation time so he is pushing the pour back to next Wednesday. He informed me he still plans on placing the
footings at Area 60 on Thursday.
2:00 pm IMCO is continuing to work on prepping the wall forms at Area 30. The IMCO pipe crew is working on
installing the 4" drain pipes from the inlet floor diffusers to MH7. They are setting the stainless pipe to grade and
installing the butterfly valve. From the butterfly valve it switches to SDR pipe.
4:00 pm Jake Self and I checked some dimensions on the hatchery building. All checked per plan. EOI is
continuing to install the rebar for the hatchery building as well. IMCO laid out the door locations so EOI could
install the higher vertical bars and the lower vertical bars where needed per the approved rebar submittal.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1247 of 1851
References
Photos (6)
20230619_155928
Taken on Jun 19, 2023, 3:59 PM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
20230619_155904
Taken on Jun 19, 2023, 3:59 PM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1248 of 1851
20230619_155853
Taken on Jun 19, 2023, 3:58 PM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
20230619_155548
Taken on Jun 19, 2023, 3:55 PM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1249 of 1851
20230619_110613
Taken on Jun 19, 2023, 11:06 AM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
20230619_110601
Taken on Jun 19, 2023, 11:06 AM MDT
Added on Jun 20, 2023, 7:03 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1250 of 1851
Form detail
#168: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Strip wall forms
Area 60 Footing Forms
IMCO, Operators and Labors 7 10 Area 10 Place thrust blocking and
CDF encasement of raceway piping
EOI 3 10 Area 60, Tie Rebar
Totals 15 30
Forms
Location
Form date Jun 15, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 15, 2023, 4:39 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1251 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Place CDF and Thrust
Blocking
Deere 644J Loader 1 10 Area 10, Batch Concrete
IMCO Concrete Truck 1 10 Area 10 Batch Concrete
IMCO Concrete Truck 1 10 Area 10, Batch Concrete
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 5 Area 30, Remove Wall forms
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1252 of 1851
-
Notes
9:00 am IMCO is continuing to work on forming at Area 60 wall footings. EOI is onsite to tie the rebar.
10:00 am I noticed the rebar drawings show a curb in the office area. A note in the drawings call out for no curb
in the office area. The rebar was cut and bent to curb height so IMCO will need to cut the rebar to make it per plan.
I notified Zack of the issue.
12:00 pm IMCO is continuing to work on footings. They have also started placing concrete for thrust blocking
behind the raceway piping. They are going to switch to CDF soon.
3:00 pm IMCO has been placing CDF to encase the raceway pipes. They also have started to remove the wall
forms on Area 30.
4:30 pm IMCO has removed two wall forms. They are going to cure the walls with a sprinkler running.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1253 of 1851
References
Photos (10)
20230615_163132
Taken on Jun 15, 2023, 4:31 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
20230615_163129
Taken on Jun 15, 2023, 4:31 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1254 of 1851
20230615_163119
Taken on Jun 15, 2023, 4:31 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
20230615_163106
Taken on Jun 15, 2023, 4:31 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1255 of 1851
20230615_163101
Taken on Jun 15, 2023, 4:31 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
20230615_161152
Taken on Jun 15, 2023, 4:11 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1256 of 1851
20230615_152107
Taken on Jun 15, 2023, 3:21 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
20230615_152100
Taken on Jun 15, 2023, 3:21 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1257 of 1851
20230615_132952
Taken on Jun 15, 2023, 1:29 PM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
20230615_102531
Taken on Jun 15, 2023, 10:25 AM MDT
Added on Jun 15, 2023, 4:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1258 of 1851
Form detail
#167: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 prep walls for stripping
forms, cure top of the wall with
soaker hose
Area 60 Start forming footings
IMCO, Operators and Labors 7 10 Area 10 Continue forming thrust
blocking for raceway piping
Totals 12 20
Forms
Location
Form date Jun 14, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 15, 2023, 8:40 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1259 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Prep for Thrust Block
pours on raceway piping
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 no operator onsite
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1260 of 1851
-
Notes
See attached 28 Day compressive strength report for the Area 30 North Half Slab Placement.
7:00 am I was informed that IMCO was here until around 930pm last night getting a finish on the top of the wall.
8:00 am IMCO is starting to form the hatchery building footings. They are tearing down what they can off the wall
forms without removing the forms. They will wait until tomorrow to start removing forms.
10:00 am IMCO is continuing to work on forming trust blocking for the raceway piping.
12:00 pm IMCO has been curing the top of the wall with a soaker hose.
2:30 pm IMCO is continuing to work on footings at Area 60 and forming the thrust blocking for the raceway
piping.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1261 of 1851
References
Photos (3)
20230614_143759
Taken on Jun 14, 2023, 2:38 PM MDT
Added on Jun 15, 2023, 8:39 AM MDT
Added by Chris Johnson
20230614_143903
Taken on Jun 14, 2023, 2:39 PM MDT
Added on Jun 15, 2023, 8:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1262 of 1851
20230614_124200
Taken on Jun 14, 2023, 12:42 PM MDT
Added on Jun 15, 2023, 8:39 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1263 of 1851
Form detail
#166: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Place WRDA concrete for 2
of 4 sections of walls
IMCO, Operators and Labors 7 10 Area 10 Pour trust blocking, Prep
for next thrust block pour on
raceway piping
Totals 12 20
2. Materials
Forms
Location
Form date Jun 13, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 14, 2023, 7:53 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1264 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Prep for Thrust Block
pours on raceway piping
Deere 644J Loader 1 10 Area 10 Load general fill at dump
site
IMCO Concrete Truck 1 10 Area 30, Wall Placement
IMCO Concrete Truck 1 10 Area 30, Wall Placement
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 no operator onsite
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1 4 Area 10, Compact native fill
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1265 of 1851
Notes
7:00 am IMCO is prepping for the wall placement. They are also working on forming for thrust blocking on the
raceway piping.
9:00 am I have checked the top of the wall. As much as I can see everything is installed per plan and is ready for
concrete.
9:30 am The pump truck is onsite and getting ready. IMCO is starting to batch concrete.
10:30 am IMCO is batching 4.5 CY trucks for now. The first truck came out extremely dry. Luke, Connect
Engineering, is onsite and helping IMCO through the issue.
11:00 am IMCO found an error in the spreadsheet and is adding the water in that is needed. They have decided
to put this concrete in the trust blocking instead of the walls to ensure good concrete is going into the walls.
12:00 pm I have tested IMCOs first truck for the walls, second truck on the day. All tested in spec. After testing
and cleaning up I climbed the wall to witness the lift determination and consolidating effort. They are dropping a
tape measure down the forms to ensure they are getting a 2' lift. Then they are stinging the concrete behind the
concrete pump. They have a piece of tape on the stinger and the operator is wearing a headlamp to see when the
tape is at the proper level in the concrete. After the lift is brought up they are also turning the wall vibrators on for
approx. 10 seconds.
2:00 pm IMCO is continuing to place concrete in the walls at 2' lifts. The IMCO pipe crew is working on the 4"
drain pipe from the fish lift to the drainage to MH 7. Jake Self, IMCO Foreman, and I walked around the forms using
the laser to check plumbness of the walls. He is making adjustments with the ties to get the wall plumb.
3:00 pm IMCO is continuing to place concrete. I have tested a second truck at approx. 45 CY. The concrete was in
spec and they are continuing to place.
5:00 pm IMCO is finishing the placement. They are using the left over concrete for thrust blocking at the raceway
piping.
6:00 pm IMCO is done for the day. The concrete crew is going to put a broom finish on top of the wall.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1266 of 1851
References
Photos (15)
20230613_170555
Taken on Jun 13, 2023, 5:05 PM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_104958
Taken on Jun 13, 2023, 10:49 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1267 of 1851
20230613_095913
Taken on Jun 13, 2023, 9:59 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_091707
Taken on Jun 13, 2023, 9:17 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1268 of 1851
20230613_091645
Taken on Jun 13, 2023, 9:16 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_091638
Taken on Jun 13, 2023, 9:16 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1269 of 1851
20230613_091307
Taken on Jun 13, 2023, 9:13 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_091255
Taken on Jun 13, 2023, 9:12 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1270 of 1851
20230613_091251
Taken on Jun 13, 2023, 9:12 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_091245
Taken on Jun 13, 2023, 9:12 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1271 of 1851
20230613_091240
Taken on Jun 13, 2023, 9:12 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_170559
Taken on Jun 13, 2023, 5:06 PM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1272 of 1851
20230613_120431
Taken on Jun 13, 2023, 12:04 PM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
20230613_091650
Taken on Jun 13, 2023, 9:16 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1273 of 1851
20230613_091236
Taken on Jun 13, 2023, 9:12 AM MDT
Added on Jun 14, 2023, 7:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1274 of 1851
Form detail
#165: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 4 10 Area 30 Continue Forming for Wall
Placement, Install Embeds, prep
sleeves for handrail
IMCO, Operators and Labors 7 10 Area 10 Prep for next thrust block
pour on raceway piping
Totals 11 20
2. Materials
Forms
Location
Form date Jun 12, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 13, 2023, 6:40 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1275 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Prep for Thrust Block
pours on raceway piping
Deere 644J Loader 1 10 Area 10 Load general fill at dump
site
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 10, Haul General fill to the site
Kobelco 1100G Crane 1 10 Area 30, Hang wall forms
Deere 470 Excavator 1
Bomag Roller 1 10 Area 10, Compact native material
Dynapac Roller 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1276 of 1851
Notes
10:00 am Arrived on site. The crew is continuing to finish up the wall forms for Area 30. They all all the wall forms
closed up and are working on the final preparations of bracing and ensuring forms are tight. I was informed the
crew worked all weekend. They set the embeds on the closing forms and flew them into place. The crew is
currently working on setting the pipe sleeves.
11:00 am IMCO operators have finished the install of the 12" drain line from MH 7 to MH 2. ACORE was onsite
Thursday core drilling the hole in the correct location.
2:00 pm Attended weekly pre pour meeting.
4:00 pm IMCO is continuing to work on the wall forms on Area 30. They are also working on forming for more
trust blocking on the raceway piping. They are continuing to fill the lines with water to check for leaks at the
couplers.
References
Photos (8)
20230612_132503
Taken on Jun 12, 2023, 1:25 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
20230612_162218
Taken on Jun 12, 2023, 4:22 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1277 of 1851
20230612_132508
Taken on Jun 12, 2023, 1:25 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
20230612_132416
Taken on Jun 12, 2023, 1:24 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1278 of 1851
20230612_132408
Taken on Jun 12, 2023, 1:24 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
20230612_132332
Taken on Jun 12, 2023, 1:23 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1279 of 1851
20230612_131717
Taken on Jun 12, 2023, 1:17 PM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
20230612_102224
Taken on Jun 12, 2023, 10:22 AM MDT
Added on Jun 13, 2023, 6:37 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1280 of 1851
Form detail
#164: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Continue Forming for Wall
Placement, Install Embeds, prep
sleeves for handrail
IMCO, Operators and Labors 9 10 Area 10 Pour CDF Encasement
Totals 14 20
2. Materials
Forms
Location
Form date Jun 8, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 12, 2023, 10:18 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1281 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, CDF pipe encasement
Deere 644J Loader 1 10 Area 10, CDF Batching
IMCO Concrete Truck 1 10 Area 10, CDF Placement
IMCO Concrete Truck 1 10 Area 10, CDF Placement
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 0
Kobelco 1100G Crane 1 10 Area 30, Hang wall forms
Area 10, CDF placement
Deere 470 Excavator 1
Bomag Roller 1
Dynapac Roller 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1282 of 1851
Notes
8:00 am IMCO is continuing to work on hanging wall forms and preparing for the wall placement next week. The
excavation crew is prepping to begin CDF pipe encasement and thrust blocking.
9:00 am IMCO is starting to batch concrete for the thrust blocking behind two of the raceway piping 90s.
11:00 am IMCO has placed concrete for the trust blocking. They are switching to CDF batching to encase the
pipes near Area 30. The first load is 4 CY.
12:30 pm IMCO is continuing to batch CDF. They are currently at 20 CY. They are going to continue placing to
encase the pipes. The carpenters are working on closing up the wall forms.
References
Photos (7)
20230608_120936
Taken on Jun 8, 2023, 12:09 PM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
20230608_113930
Taken on Jun 8, 2023, 11:39 AM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1283 of 1851
20230608_092839
Taken on Jun 8, 2023, 9:28 AM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
20230608_125026
Taken on Jun 8, 2023, 12:50 PM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1284 of 1851
20230608_121618
Taken on Jun 8, 2023, 12:16 PM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
20230608_110926
Taken on Jun 8, 2023, 11:09 AM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1285 of 1851
20230608_094737
Taken on Jun 8, 2023, 9:47 AM MDT
Added on Jun 12, 2023, 10:17 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1286 of 1851
Form detail
#163: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Continue Forming for Wall
Placement, Install Embeds, prep
sleeves for handrail
IMCO, Operators and Labors 9 10 Area 10 Install 4" drain pipe from
Area 50 to MH7, Backfill pipe and
manhole, work on forming for CDF
encasement
Totals 14 20
Forms
Location
Form date Jun 7, 2023
Description Area 10, Area 30, Area 50
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 8, 2023, 7:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1287 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, CDF pipe encasement
prep
Deere 644J Loader 1 0
IMCO Concrete Truck 1 5 Area 10, CDF pipe encasement
attempt
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10, Compact material with
hoe pack
Dump Truck 1 0
Kobelco 1100G Crane 1 10 Area 30, Hang wall forms
Deere 470 Excavator 1 10 Area 10, 4" drain pipe bedding
Bomag Roller 1
Dynapac Roller 1 Area 10, compact around manhole
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1288 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Concrete Strength report for the Area 30 South Half Slab 28 day.
8:00 am IMCO is working on the wall forms at Area 30.
9:00 am Attended weekly meeting
10:00 am Jake and I checked the embeds that are on the inside face of the walls. They all look to be per plan or
submittal. IMCO is continuing to work on the wall forms and bulkheads for the placement. Pipe crew is working on
finalizing the thrust block and pipe encasement for the raceway pipe.
1:00 pm IMCO is prepping to begin batching CDF.
4:00 pm IMCO batched two loads of CDF. Neither of the loads were flowable. The CDF was very thick. They worked
on adding more water but it did not help much. Jake is going to talk to the mix designer and they will try again
tomorrow.
5:00 pm IMCO was able to start closing up forms on Area 30 and they will continue to work on that tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1289 of 1851
References
Photos (4)
20230607_165634
Taken on Jun 7, 2023, 4:56 PM MDT
Added on Jun 8, 2023, 6:57 AM MDT
Added by Chris Johnson
20230607_165523
Taken on Jun 7, 2023, 4:55 PM MDT
Added on Jun 8, 2023, 6:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1290 of 1851
20230607_165547
Taken on Jun 7, 2023, 4:55 PM MDT
Added on Jun 8, 2023, 6:57 AM MDT
Added by Chris Johnson
20230607_131314
Taken on Jun 7, 2023, 1:13 PM MDT
Added on Jun 8, 2023, 6:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1291 of 1851
Form detail
#162: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Continue Forming for Wall
Placement, Install Embeds, prep
sleeves for handrail
IMCO, Operators and Labors 9 10 Area 10 Install 4" drain pipe from
Area 50 to MH7, Backfill pipe and
manhole, work on forming for CDF
encasement
Vale Electric, Electricians 3 10 Area 30, Install raceways and
boxes for lights and switches in the
Forms
Location
Form date Jun 6, 2023
Description Area 10, Area 30, Area 40
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 7, 2023, 7:03 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1292 of 1851
Crew # Workers # Total
hours
Work performed
walls, Install low water alarm for
the holding ponds
Totals 17 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 40, CDF pipe encasement
prep
Deere 644J Loader 1 10 Area 10 Backfill manhole
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10, Compact material with
hoe pack
Dump Truck 1 10 Area 10. Import structural fill / pipe
bedding
Kobelco 1100G Crane 1 no operator onsite
Deere 470 Excavator 1 10 Area 10, 4" drain pipe bedding
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1293 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1
Dynapac Roller 1 Area 10, compact around manhole
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Density Test Report for the 4" drain pipe bedding.
8:00 am IMCO is continuing to work on Area 30 forming and embeds.
9:00 am IMCO informed me they would be ready for a compaction test on the 4" drain pipe bedding soon. The
crew has been working on backfilling and compacting the bedding.
11:00 am I have taken a density shot on the pipe bedding for the 4" drain near MH 7. It passed with no issues.
The crew is going to continuing backfilling the manhole and the pipe.
12:00 pm IMCO carpenters are continuing to install the bulk heads at the CJs in Area 30.
3:00 pm I have climbed the wall and checked the embeds on the East wall. They all look to be per plan and per
the approved submittals.
4:00 pm IMCO operators and labors are working in a thrust block CDF form to encase one of the raceway pipes.
The HDPE pipe continues to move throughout the day with the heat expansion of the pipe. They are looking to lock
it in with a CDF placement.
5:00 pm IMCO continued to work on bulkheads and wall forms for Area 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1294 of 1851
References
Photos (4)
20230606_164123
Taken on Jun 6, 2023, 4:41 PM MDT
Added on Jun 7, 2023, 6:56 AM MDT
Added by Chris Johnson
20230606_164032
Taken on Jun 6, 2023, 4:40 PM MDT
Added on Jun 7, 2023, 6:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1295 of 1851
20230606_163843
Taken on Jun 6, 2023, 4:38 PM MDT
Added on Jun 7, 2023, 6:56 AM MDT
Added by Chris Johnson
20230606_130258
Taken on Jun 6, 2023, 1:02 PM MDT
Added on Jun 7, 2023, 6:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1296 of 1851
Form detail
#161: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 4 10 Area 30 Continue Forming for Wall
Placement, Install Embeds, prep
sleeves for handrail
IMCO, Operators and Labors 9 10 Area 10 Install 4" drain pipe from
Area 50 to MH7, Move and
compact native material onsite
Vale Electric, Electricians 3 10 Area 30, Install raceways and
boxes for lights and switches in the
walls
Forms
Location
Form date Jun 5, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 6, 2023, 7:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1297 of 1851
Crew # Workers # Total
hours
Work performed
Totals 16 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Move native material
Deere 644J Loader 1 10 Area 10 Place native material
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10, Install 4" drain pipe
Dump Truck 1
Kobelco 1100G Crane 1 no operator onsite
Deere 470 Excavator 1 10 Area 10, 4" drain pipe bedding
Bomag Roller 1
Dynapac Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1298 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. IMCO set MH7 on Friday 6/2. They have installed the 12" pipe from MH 2 into MH 7.
They mudded the opening around the pipe this morning. They are currently working on installing the 4" drain pipe
from MH7 to Area 50 under the lift system.
11:00 am IMCO carpenters are continuing to install the bulkheads at the CJs in the walls. They are also working
on laying out the embeds. Vale Electric has 3 electricians onsite working on installing raceway conduit in the walls
for lights and switches.
2:00 pm IMCO is continuing to work on the 4" drain pipe. Jake informed Vale per RFI 94 and email with Zack that a
light that was in conflict with the stair landing will be moved to the North side.
4:00 pm IMCO carpenters are continuing to work on installing the waterstop and the bulkheads. They are also
making the sleeves for the handrail that will be set in the top of the wall.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1299 of 1851
References
Photos (6)
20230605_162623
Taken on Jun 5, 2023, 4:26 PM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
20230605_162608
Taken on Jun 5, 2023, 4:26 PM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1300 of 1851
20230605_162557
Taken on Jun 5, 2023, 4:25 PM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
20230605_161637
Taken on Jun 5, 2023, 4:16 PM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1301 of 1851
20230605_112208
Taken on Jun 5, 2023, 11:22 AM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
20230605_111716
Taken on Jun 5, 2023, 11:17 AM MDT
Added on Jun 6, 2023, 7:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1302 of 1851
Form detail
#159: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Continue Forming for Wall
Placement
IMCO, Operators and Labors 8 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40, begin excavating for
12" drain line from MH7 to MH 2
Totals 11 20
Forms
Location
Form date Jun 1, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 1, 2023, 4:58 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1303 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Excavate from MH2 to
MH7
Deere 644J Loader 1 10 Area 10 Load Pipe Bedding from
Stockpile
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 10 Import Pipe Bedding
Kobelco 1100G Crane 1 10 Area 30 Fly in Rebar and Wall
Forms
Deere 470 Excavator 1 10 Area 10, Set HDPE piping
Bomag Roller 1
Dynapac Roller 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1304 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Density Field Report.
8:00 am IMCO is continuing to work on the 12" drain line from MH 7 to MH 2. The water in the trench is down and
hardly noticeable. They have removed the pipe and is working on regrading the subgrade and compacting it
without the water in the trench.
10:30 am IMCO is continuing to fly in wall forms for Area 30. The pipe crew has placed 40 LF of pipe. They are
going to make the connection to MH 2 once ACORE cores the hole at the correct elevation. They are currently
holding the pipe back from the manhole. I have take two density shots on the pipe bedding. They were low. I
informed the crew the water percentage was well below optimum. They sprayed the bedding down and
recompacted it with a jumping jack compactor. After some effort the tests passed both above required 92%. I
discussed with the crew to introduce water to the material before compaction.
1:00 pm IMCO is continuing to fly in the wall forms and place them. The pipe crew has pipe installed up to
manhole 7. They are starting to excavate for it now.
4:00 pm The water has risen in the trench. They have decided to try and set the manhole tomorrow morning in
hopes the water will go down. They have the hole excavated but need to work on the final grade. IMCO carpenters
are working on welding the water stop together on the CJs. Vale Electric is onsite. He has been installing the boxes
in the walls of Area 30. They informed me of a conflict with the location of one of the lights. Jake was going to
respond to the RFI 94 that provided direction on where to place the lights.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1305 of 1851
References
Photos (5)
20230601_160650
Taken on Jun 1, 2023, 4:06 PM MDT
Added on Jun 1, 2023, 4:26 PM MDT
Added by Chris Johnson
20230601_112044
Taken on Jun 1, 2023, 11:20 AM MDT
Added on Jun 1, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1306 of 1851
20230601_095221
Taken on Jun 1, 2023, 9:52 AM MDT
Added on Jun 1, 2023, 4:26 PM MDT
Added by Chris Johnson
20230601_160824
Taken on Jun 1, 2023, 4:08 PM MDT
Added on Jun 1, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1307 of 1851
20230601_143036
Taken on Jun 1, 2023, 2:30 PM MDT
Added on Jun 1, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1308 of 1851
Form detail
#158: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Continue Forming for Wall
Placement
IMCO, Operators and Labors 8 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40, begin excavating for
12" drain line from MH7 to MH 2
EOI 3 10 Area 30, Install Rebar
Totals 14 30
Forms
Location
Form date May 31, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 1, 2023, 8:25 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1309 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Excavate from MH2 to
MH7
Deere 644J Loader 1 10 Area 10 Load Pipe Bedding from
Stockpile
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 10 Import Pipe Bedding
Kobelco 1100G Crane 1 10 Area 30 Fly in Rebar and Wall
Forms
Deere 470 Excavator 1 10 Area 10, Set HDPE piping
Bomag Roller 1
Dynapac Roller 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1310 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is continuing to prep Area 30 for the wall placement. They are shooting to pour next Wednesday.
EOI is onsite and they are going to fly in the rebar mats that they tied yesterday. IMCO has a crane operator onsite
today to fly in the mats and wall forms. I noticed the pipe crew is starting to prep the grade to install pipe. They are
working on the pipe run from MH 2 to MH7. There is about 1.5' of water in the trench. I witness the crew place
structural fill / pipe bedding for subbase grade. It looked to me to be very soft.
9:00 am Attended weekly meeting. Discussed laying pipe in the water with high clay materials. Concluded Zack,
Jake and I would walk the site after the meeting.
11:00 am Zack, Jake and I walked the site after the meeting and discussed the process for laying the pipe in the
water. The subgrade under the pipe was very soft. I was able to push a probe through it fairly easy. Jake said he
would revaluate the process for installing the pipe run. I was informed that the core in the manhole was performed
at the wrong elevation. I was told the plan was to bring ACORE back onsite to core the hole and the proper
elevation but they are going to continue installing pipe and make the connection later.
1:00 pm EOI has been flying in the rebar that they tied on the ground. IMCO carpenters have been working on
installing embeds and getting the bulkheads for the CJs in the walls. I noticed an embed was missing. After
checking with the crew they were not aware of the embed needing to be installed for the L4 bracket of the
distribution box. I spoke to Sean regarding the embed. He said he would review it.
4:00 pm IMCO carpenters are continuing to work on wall forms. The L4 embeds were located and I discussed
with IMCO foreman the location of the embeds. All rebar has been installed. I walked Area 30 with Kevin, EOI, to
review any rebar that was missing. There were a few areas that needed adjustment, his crew got right on it and
fixed them. The rebar looks to be per the recent submittal dated 3/16/23.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1311 of 1851
References
Photos (9)
20230531_141350
Taken on May 31, 2023, 2:13 PM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
20230531_135043
Taken on May 31, 2023, 1:50 PM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1312 of 1851
20230531_101301
Taken on May 31, 2023, 10:13 AM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
20230531_141307
Taken on May 31, 2023, 2:13 PM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1313 of 1851
20230531_141241
Taken on May 31, 2023, 2:12 PM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
20230531_135025
Taken on May 31, 2023, 1:50 PM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1314 of 1851
20230531_102437
Taken on May 31, 2023, 10:24 AM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
20230531_101231
Taken on May 31, 2023, 10:12 AM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1315 of 1851
20230531_075425
Taken on May 31, 2023, 7:54 AM MDT
Added on Jun 1, 2023, 8:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1316 of 1851
Form detail
#157: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Continue Forming for Wall
Placement
IMCO, Operators and Labors 8 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40, begin excavating for
12" drain line from MH7 to MH 2
EOI 3 10 Area 30, Install Rebar
Totals 14 30
Forms
Location
Form date May 30, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 31, 2023, 7:15 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1317 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Excavate from MH2 to
MH7
Deere 644J Loader 1
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1 No Operator onsite
Deere 470 Excavator 1 10 Area 10, Set HDPE piping
Bomag Roller 1
Dynapac Roller 1
4. Signature
Chris Johnson, HMH Engineering4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1318 of 1851
-
Notes
10:00 am Arrived on site. IMCO is continuing to work on wall forms for Area 30. EOI is onsite tying rebar.
11:00 am I was informed there is no crane operator onsite today. He called in. EOI cannot fly in and rebar so they
are going to continue tying bar on the ground and fly them in when a crane operator is onsite. IMCO wall crew is
continuing to work on wall forms. They are placing waterstop and getting the nelson stud embeds screwed to the
wall forms.
1:00 pm IMCO pipe crew is working on placing the 90 bends that discharge inside each of the 6 raceways.
2:00 pm IMCO has another pipe crew working on excavating for the 12" drain line from MH7 to MH2. They are
not setting the pipe yet, they are just excavating for the pipe run. They are encountering ground water on this run.
4:00 pm IMCO is continuing to work on prepping for the wall pour at Area 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1319 of 1851
References
Photos (4)
20230530_153545
Taken on May 30, 2023, 3:35 PM MDT
Added on May 31, 2023, 7:13 AM MDT
Added by Chris Johnson
20230530_153518
Taken on May 30, 2023, 3:35 PM MDT
Added on May 31, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1320 of 1851
20230530_153454
Taken on May 30, 2023, 3:34 PM MDT
Added on May 31, 2023, 7:13 AM MDT
Added by Chris Johnson
20230530_153433
Taken on May 30, 2023, 3:34 PM MDT
Added on May 31, 2023, 7:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1321 of 1851
Form detail
#156: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date May 24, 2023
Description Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 24, 2023, 2:11 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1322 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See Attached Concrete Compressive 7 Day report for the North Half Slab Pour at Area 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1323 of 1851
Form detail
#155: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Continue Forming for Wall
Placement
IMCO, Operators and Labors 8 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40,
Area 60 Import General Fill, Place
and Compact General Fill
EOI 3 10 Area 30, Install Rebar
Forms
Location
Form date May 23, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update May 24, 2023, 8:52 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1324 of 1851
Crew # Workers # Total
hours
Work performed
Totals 14 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Grizzly native material at
pit
Deere 644J Loader 1
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place General Fill
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, Set wall forms
Deere 470 Excavator 1 10 Area 10, Excavate for HDPE piping
Bomag Roller 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1325 of 1851
Equipment Quantity Hours
used
Comment
Dynapac Roller 1 10 Area 10, Compact Native Fill
Area 60, Compact General Fill
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crews are working on setting wall forms. They are treating the forms with form seal then planning
to fly them into place and begin setting them.
9:00 am EOI is onsite to continue installing the rebar at Area 30. IMCO grade crew is working on placing general
fill at Area 60. They are placing and compacting near the existing hatchery building.
10:00 am IMCO pipe crew is working on installing the HDPE pipe from the valves to the 6 raceways. The
carpenters have set the first half wall panel at Area 30.
12:00 pm IMCO is continuing to work on grading at Area 60. They are grading to the bottom of the footing for
now.
1:00 pm The carpenters are continuing to build wall forms and fly them in place. EOI has set a mat of bar as well.
2:00 pm Attended weekly meeting.
4:00 pm IMCO has set to walls. They are working on building more walls to fly into place. The pipe crew has
moved to working on the 36" drain pipe to MH 2.
5:00 pm IMCO is cleaning up for the day. EOI has set another matt of rebar for the walls.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1326 of 1851
References
Photos (15)
20230523_110116
Taken on May 23, 2023, 11:01 AM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_142826
Taken on May 23, 2023, 2:28 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1327 of 1851
20230523_135210
Taken on May 23, 2023, 1:52 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_133247
Taken on May 23, 2023, 1:32 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1328 of 1851
20230523_110822
Taken on May 23, 2023, 11:08 AM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_105006
Taken on May 23, 2023, 10:50 AM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1329 of 1851
20230523_163521
Taken on May 23, 2023, 4:35 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_110717
Taken on May 23, 2023, 11:07 AM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1330 of 1851
20230523_151330
Taken on May 23, 2023, 3:13 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_094524
Taken on May 23, 2023, 9:45 AM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1331 of 1851
20230523_145650
Taken on May 23, 2023, 2:56 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_164817
Taken on May 23, 2023, 4:48 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1332 of 1851
20230523_164439
Taken on May 23, 2023, 4:44 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
20230523_153110
Taken on May 23, 2023, 3:31 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1333 of 1851
20230523_134832
Taken on May 23, 2023, 1:48 PM MDT
Added on May 24, 2023, 8:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1334 of 1851
Form detail
#154: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Grout back chipped
concrete, Begin forming for walls,
prep wall forms
IMCO, Operators and Labors 8 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40,
Area 60 Import General Fill
Totals 11 20
Forms
Location
Form date May 22, 2023
Description Area 10, Area 30, Area 60, Area 20
Due date
Submitted by Chris Johnson
Status Closed
Last update May 23, 2023, 7:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1335 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Grizzly native material at
pit
Deere 644J Loader 1 10 Area 10, Grizzly native material at
pit
Area 60, Load general fill in dump
truck
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10, Excavate for Raceway
piping
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 10, Set HDPE pipes
Deere 470 Excavator 1 10 Area 10, Excavate for HDPE piping
Bomag Roller 1
Dynapac Roller 1 10 Area 10, Compact Native Fill
Area 60, Compact General Fill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1336 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Exterior Foundation issue at Area 60, Attached 28 Day compressive strength report from the Well
pump pipe encasement.
10:00 am Arrived on site. I noticed IMCO crew was working on Area 30. They are grouting back the chipped out
areas. They informed me they took pictures of the bad spots before placing the grout because I did not verify they
extents of the unconsolidated concrete. I asked if they chipped on it after I left Thursday afternoon. They said yes.
11:00 am IMCO is working on placing general fill at Area 60 to building up to footing subgrade. They have two
operators at the pit across the river generating and screening native material. IMCO is also working on excavating
for the 6 raceway piping runs. They are using the mini excavator for now because the 470 excavator is being
serviced.
12:00 pm IMCO has potholed the foundation of the existing hatchery building. This allows us to see and verify if
there is a conflict with the new hatchery building foundation. The two foundations are approx. 5' different in
elevation but only ~1 foot apart north south. I spoke to Kirt regarding my concerns with undermining the new
foundation when they demo the old one. Another concern we discussed was the North face of the new retaining
wall and foundation will not be able to be backfilled. I said its worth asking if the wall can withstand only having
one side backfilled as they build the building.
1:00 pm I spoke to Jeff, IDFG, regarding the schedule to water up the ponds for chinook. He said they want to
turn the pump on on June 2nd and water up the ponds. They plan to be trapping June 5.
2:00 pm IMCO is continuing to work on the wall forms for Area 30. They are having to build custom forms around
the pipe penetrations.
4:00 pm The crew is continuing to work on fusing HDPE pipe for the raceways. They are excavating for the install.
5:00 pm The roofers were onsite working on Area 20. They were able to finish trimming around the hatches and
the last of the roofing was installed.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1337 of 1851
References
Photos (8)
20230522_155106
Taken on May 22, 2023, 3:51 PM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
20230522_155054
Taken on May 22, 2023, 3:50 PM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1338 of 1851
20230522_152324
Taken on May 22, 2023, 3:23 PM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
20230522_152319
Taken on May 22, 2023, 3:23 PM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1339 of 1851
20230522_152317
Taken on May 22, 2023, 3:23 PM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
20230522_115226
Taken on May 22, 2023, 11:52 AM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1340 of 1851
20230522_103902
Taken on May 22, 2023, 10:39 AM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
20230522_103853
Taken on May 22, 2023, 10:38 AM MDT
Added on May 23, 2023, 6:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1341 of 1851
Form detail
#153: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Strip Forms, Chip concrete
IMCO, Operators and Labors 7 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40,
Area 60 Import, Grade and
compact general fill to bottom of
footing
Totals 10 20
Forms
Location
Form date May 18, 2023
Description Area 10, Area 30, Area 60
Due date
Submitted by Chris Johnson
Status Closed
Last update May 19, 2023, 3:39 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1342 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10, Grizzly native material at
pit
Deere 644J Loader 1 10 Area 10, Grizzly native material at
pit
Area 60, Load general fill in dump
truck
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 60, Place general fill
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 10, Set HDPE pipes
Deere 470 Excavator 1 10 Area 10, Excavate for HDPE piping
Bomag Roller 1
Dynapac Roller 1 10 Area 10, Compact Native Fill
Area 60, Compact General Fill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1343 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is stripping forms from Area 30. They placed cure on the slab last night before the left.
9:00 am IMCO is continuing to work on installing the HDPE piping to Area 50. They have started to import general
fill to build the subgrade up for Area 60.
10:30 am I worked with the IMCO crew on what is expected for compaction of the subgrade fill material at Area
60. They are adding water to the material and compacting. I asked for 4 to 5 passes of the roller to achieve
adequate compaction. This material is to granular to test compaction with a nuclear densometer. I do continue to
witness proof rolling from the loaded dump truck backing over the material. The fill looks to be firm.
12:00 pm IMCO is continuing to import, place and compact general fill for Area 60.
2:00 pm IMCO has stripped the forms from Area 30 Slab placement. I spoke to Kirt regarding areas than need
attention. We also discussed curing methods. They did place cure on the slab last night. He said he would like to
put a sprinkler on the slab for the weekend. Because of all the rebar they are unable to achieve a good seal with
plastic which is why he wants to have a sprinkler run all weekend keeping it wet. I asked him and Jake to submit the
plan per the specifications.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1344 of 1851
References
Photos (16)
20230518_122508
Taken on May 18, 2023, 12:25 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_122241
Taken on May 18, 2023, 12:22 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1345 of 1851
20230518_122049
Taken on May 18, 2023, 12:20 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_122040
Taken on May 18, 2023, 12:20 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1346 of 1851
20230518_121815
Taken on May 18, 2023, 12:18 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_121741
Taken on May 18, 2023, 12:17 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1347 of 1851
20230518_121729
Taken on May 18, 2023, 12:17 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_121601
Taken on May 18, 2023, 12:16 PM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1348 of 1851
20230518_100450
Taken on May 18, 2023, 10:04 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_092613
Taken on May 18, 2023, 9:26 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1349 of 1851
20230518_091257
Taken on May 18, 2023, 9:12 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_091139
Taken on May 18, 2023, 9:11 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_091124
Taken on May 18, 2023, 9:11 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_091057
Taken on May 18, 2023, 9:10 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1350 of 1851
20230518_091047
Taken on May 18, 2023, 9:10 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
20230518_091029
Taken on May 18, 2023, 9:10 AM MDT
Added on May 19, 2023, 3:33 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1351 of 1851
Form detail
#152: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Pour North Slab, chip out
unconsolidated concrete
IMCO, Operators and Labors 7 10 Area 10 Excavate and continue
installing HDPE pipe from Area 30
to Area 40, Help with wall forms
Vale Electric, Electricians 1 10 Area 10, Temp Power
Totals 11 30
Forms
Location
Form date May 17, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 18, 2023, 8:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1352 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1 8 Area 30, North Slab Placement
IMCO Concrete Truck 1 8 Area 30, North Slab Placement
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Excavate and install HDPE
pipe to raceways
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, On standby for man
retrieval from inside aeration
tower, Help with HDPE fusing
Deere 470 Excavator 1 10 Area 30, Batch Concrete
Bomag Roller 1
Dynapac Roller 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1353 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached HMH Concrete Field Report along with 7 Day breaks from the Area 30 South Slab placement and the
28 day breaks from the 12" river intake pipe encasement.
7:30 am IMCO is making the final preparations for the concrete placement today.
9:00 am I have done a final check on the rebar. All looks to be per the submittal and ready for placement. IMCO is
continuing to work on installing the HDPE pipe from Area 30 to Area 40.
11:00 am IMCO has started to batch concrete. The pump truck is onsite and ready for the placement.
12:00 pm I have tested the first truck and all was in spec. While pumping the first truck the mix seemed to be very
stiff. The slump on my test was 5". The crew had to bring out a larger concrete vibrater to consolidate the concrete
around the rebar. They placed this concrete around the deep pipe on the NE corner of the slab. Sean relayed this
info to the batch plant and they increased the water for the next batch.
12:30 pm The second truck batched had 8 CY on it. This truck tested low on air at 3.8%. Connect Engineer is onsite
testing as well. He had very similar numbers. IMCO decided to dose the truck with more air. I tested a second time
and the truck was on the fringe of being in spec. After some discussion IMCO decided to pour the truck. The slump
was much better on this truck and the concrete flowed well in the forms.
1:30 pm The third truck is batched. I have taken my sample and all was in spec. I casted my cylinders from this
truck.
3:00 pm IMCO has poured out ~27 CY. They are finishing the concrete now. IMCO is continuing to work on
installing the HDPE piping.
5:00 pm I spoke to the crew regarding placing cure on the finished slab when they are done working it. They still
need to trowel it one more time then they will place the cure.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1354 of 1851
References
Photos (5)
20230517_170800
Taken on May 17, 2023, 5:08 PM MDT
Added on May 18, 2023, 8:15 AM MDT
Added by Chris Johnson
20230517_170508
Taken on May 17, 2023, 5:05 PM MDT
Added on May 18, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1355 of 1851
20230517_170319
Taken on May 17, 2023, 5:03 PM MDT
Added on May 18, 2023, 8:15 AM MDT
Added by Chris Johnson
20230517_082155
Taken on May 17, 2023, 8:21 AM MDT
Added on May 18, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1356 of 1851
20230517_080513
Taken on May 17, 2023, 8:05 AM MDT
Added on May 18, 2023, 8:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1357 of 1851
Form detail
#151: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Form curb for North slab
placement, Remove forms to fix
rebar, adjust pipe, Replace Forms,
final prep for slab placement, chip
out unconsolidated concrete,
Begin building wall forms
IMCO, Operators and Labors 7 10 Area 10 Excavate and begin
installing HDPE pipe from Area 30
to Area 40, Help with wall forms
Vale Electric, Electricians 1 10 Area 10, Temp Power
Forms
Location
Form date May 16, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 16, 2023, 5:02 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1358 of 1851
Crew # Workers # Total
hours
Work performed
Totals 11 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Excavate and install HDPE
pipe to raceways
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, On standby for man
retrieval from inside aeration
tower, Help with HDPE fusing
Deere 470 Excavator 1 10 Area 10, Excavate for raceway
piping, Help with HDPE fusing
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1359 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1 10 Area 10, Compact trench
Dynapac Roller 1 3 Area 10, Compact trench from 18"
pipe removal
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO plans to continue working on forming for the next slab placement. They are also going to start
working on chipping out the unconciliated concrete pockets from the first placement.
9:00 am I have reviewed the areas of concern with Sean. He is going to get the crew to start working on chipping
the areas. EOI is onsite to aid in moving the rebar that is in conflict with a pipe.
10:30 am EOI has moved the rebar and IMCO has moved the pipe back up to where it needs to be. IMCO will
close up the forms. IMCO is continuing to work on forming for the slab placement. I have brought to their
attention they need to address the unconsolidated concrete that is on along the CJ of the slab. They want to pour
the slab tomorrow. These areas need to be addressed prior to the pour.
12:00 pm IMCO has chipped out the CJ areas of concern. There has been discussion on what should be used to fill
the void. After discussing with Zack and Bill it is determined that non shrink grout is the best solution for this.
IMCO is going to start that work now.
1:00 pm IMCO is working on grading and installing the HDPE pipes for the raceways.
2:00 pm Attended weekly meeting.
3:00 pm IMCO has grouted back the two areas of concern on the CJ. It looks as they are ready for the pour
tomorrow. They are continuing to work on building the wall forms. Idaho Survey Group was onsite laying out the
Area 60. There is concern that the building is to close to the existing hatchery building.
4:00 pm IMCO is done for the day. There is lighting in the area so they shut down. I have laid out areas that still
need chipping with paint.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1360 of 1851
References
Photos (15)
20230516_164305
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_093753
Taken on May 16, 2023, 9:37 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1361 of 1851
20230516_164356
Taken on May 16, 2023, 4:43 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_164342
Taken on May 16, 2023, 4:43 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1362 of 1851
20230516_164247
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_164243
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_164310
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_164317
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1363 of 1851
20230516_164325
Taken on May 16, 2023, 4:42 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_144031
Taken on May 16, 2023, 2:40 PM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1364 of 1851
20230516_114244
Taken on May 16, 2023, 11:42 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_114252
Taken on May 16, 2023, 11:42 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1365 of 1851
20230516_114218
Taken on May 16, 2023, 11:42 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
20230516_114150
Taken on May 16, 2023, 11:41 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1366 of 1851
20230516_093742
Taken on May 16, 2023, 9:37 AM MDT
Added on May 16, 2023, 5:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1367 of 1851
Form detail
#150: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 10 Area 30 Form curb for North slab
placement, Remove forms to fix
rebar, adjust pipe
IMCO, Operators and Labors 7 10 Area 10 Remove 18" PVC pipes
from under proposed hatchery
building, Expose septic pump tank,
begin removal
Vale Electric, Electricians 1 10 Area 10, Temp Power
Forms
Location
Form date May 15, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 16, 2023, 7:26 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1368 of 1851
Crew # Workers # Total
hours
Work performed
Totals 10 30
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Remove 18" PVC lines,
Backfill Trench, Expose sewer
pump tank, begin removal
Dump Truck 1
Kobelco 1100G Crane 1 10 Area 30, On standby for man
retrieval from inside aeration
tower
Deere 470 Excavator 1 10 Area 10, Excavate for raceway
piping, Help with HDPE fusing
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1369 of 1851
Equipment Quantity Hours
used
Comment
Bomag Roller 1 10 Area 10, Compact trench
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached Compressive Break Report from Area 30 South Half Slab Placement 5 day breaks. An early break was
requested from IMCO.
10:00 am Arrived on site. IMCO is working at Area 30 on forming for the next slab placement. They are currently
forming the curb around pipes.
11:00 am Sean and I spoke about the pockets of unconsolidated concrete. He will be submitting a procedure
today. He would like to chip out the pockets of honeycomb concrete to a limit of 1.5" inches into confident
concrete. He then plans to pour this back with the next pour which will be a wall pour.
12:00 pm I spoke to Sean and Kirt regarding the areas of honeycomb that needs to be addressed prior to the next
slab placement. These areas will be poured into the slab so they will need to be addressed prior to the placement.
They were both aware of them. I have attached photos.
1:00 pm IMCO crews are working on removing the 2 18" PVC pipes that run under the proposed hatchery building
Area 60. They have most of it removed from the weir box to the spawning shed. That is as far as they are going to
go for now. They are going to start working on the septic pump tank now.
2:00 pm A crew is working on the the raceway piping. These pipes have changed per RFI 92. The valves have been
moved. The crew is working on fusing the HDPE pipe for these runs. Kole laid them out with the GPS. I noticed a
slight skew in the runs. I have asked him to double check this before he gets to far into the install.
3:00 pm IMCO crew has brought to my attention a rebar conflict issue. While prepping the 2 pipes, raceway 1 and
cross crowder, they noticed they were to low. They tried to raise them but the rebar was in the way. The crew is
having to remove forms fix the rebar issue. Sean informed me this might push the pour back to next week.
4:30 pm IMCO continued to prep for the slab placement along with fusing HDPE pipe and removing the septic
pump tank.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1370 of 1851
References
Photos (12)
20230515_163248
Taken on May 15, 2023, 4:32 PM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_163223
Taken on May 15, 2023, 4:32 PM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1371 of 1851
20230515_145704
Taken on May 15, 2023, 2:57 PM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_114505
Taken on May 15, 2023, 11:45 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1372 of 1851
20230515_111857
Taken on May 15, 2023, 11:18 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_111829
Taken on May 15, 2023, 11:18 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1373 of 1851
20230515_125203
Taken on May 15, 2023, 12:52 PM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_112142
Taken on May 15, 2023, 11:21 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1374 of 1851
20230515_112125
Taken on May 15, 2023, 11:21 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_112123
Taken on May 15, 2023, 11:21 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1375 of 1851
20230515_112058
Taken on May 15, 2023, 11:20 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
20230515_111808
Taken on May 15, 2023, 11:18 AM MDT
Added on May 16, 2023, 6:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1376 of 1851
Form detail
#149: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Strip Forms from curb
IMCO, Operators and Labors 6 10 Area 10 Expose 2 18" PVC pipes at
Weir box location, Grizzly native
material at pit
Vale Electric, Electricians 1 10 Area 10, Temp Power
Totals 10 30
Forms
Location
Form date May 11, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 12, 2023, 8:36 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1377 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Excavate native material at
pit
Deere 644J Loader 1 10 Area 10 Grizzly material at pit
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Expose 18" PVC lines near
weir box
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1378 of 1851
Notes
See attached 28 day Compressive Strength Report from the River Intake Pipe Encasement Placement.
7:00 am IMCO placed Area 30 South Half Foundation Slab yesterday. They stayed late to finish the concrete. I was
informed a rain storm came in as they were finishing and standing water was on the new slab. They told me the
crew let the rain pass by and they came back and finished the concrete. When I arrived this morning they had
plastic sheeting over top the vertical rebar. There was no plastic on the concrete itself.
8:00 am IMCO started stripping the curb forms. I noticed right away on the outside curb pockets of
unconsolidated concrete. I spoke to Kirt and Jake regarding their plan to cure the concrete. They have not placed
any curing compound on the concrete. I also noticed the smooth steel trowel finish on the slab.
10:00 am After reviewing the specifications I spoke to Jake regarding the curing of the concrete. I reviewed spec
section 03310 with him. He was going to review it as well. I also brought to his attention that the finish in the
specifications call out for a broom finish. I notified Zack of the deficiencies.
11:00 am Jake informed me they plan to place water and plastic to cure the concrete. I informed him that is not
what the specifications call out and if he would like to use a different method he needs to submit to engineer for
approval. The crew is still working on stripping the curb and center control joint bulkhead.
1:00 pm Kirt is continuing to expose the 18" PVC pipes to be removed. He has not removed any yet. They are
continuing to excavate to the top of pipe carefully. They have exposed the sewer line along with some phone line.
2:30 pm IMCO is working on generating material at the pit across the river. They have a grizzly screen setup to
screen material 8" and under. They are stockpiling the material generated. The carpenters are continuing to work
on stripping the forms. More locations are visible of unconsolidated concrete. They are starting to spray water on
the concrete as the temperatures continue to rise.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1379 of 1851
References
Photos (22)
20230511_130924
Taken on May 11, 2023, 1:09 PM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_112016
Taken on May 11, 2023, 11:20 AM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1380 of 1851
20230511_111425
Taken on May 11, 2023, 11:14 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_141415
Taken on May 11, 2023, 2:14 PM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1381 of 1851
20230511_132945
Taken on May 11, 2023, 1:29 PM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_131443
Taken on May 11, 2023, 1:14 PM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1382 of 1851
20230511_131134
Taken on May 11, 2023, 1:11 PM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
20230511_130934
Taken on May 11, 2023, 1:09 PM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1383 of 1851
20230511_130907
Taken on May 11, 2023, 1:09 PM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_113223
Taken on May 11, 2023, 11:32 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1384 of 1851
20230511_113218
Taken on May 11, 2023, 11:32 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_112132
Taken on May 11, 2023, 11:21 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1385 of 1851
20230511_111917
Taken on May 11, 2023, 11:19 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_111524
Taken on May 11, 2023, 11:15 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1386 of 1851
20230511_111447
Taken on May 11, 2023, 11:14 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_092958
Taken on May 11, 2023, 9:29 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1387 of 1851
20230511_090410
Taken on May 11, 2023, 9:04 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_085921
Taken on May 11, 2023, 8:59 AM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1388 of 1851
20230511_085701
Taken on May 11, 2023, 8:57 AM MDT
Added on May 12, 2023, 8:30 AM MDT
Added by Chris Johnson
20230511_085357
Taken on May 11, 2023, 8:53 AM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1389 of 1851
20230511_085352
Taken on May 11, 2023, 8:53 AM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
20230511_085343
Taken on May 11, 2023, 8:53 AM MDT
Added on May 12, 2023, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1390 of 1851
Form detail
#148: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Place South half of
concrete slab and curbs
IMCO, Operators and Labors 6 10 Area 10 Pothole and excavate 2 18"
steel pipes from weir box, Backfill
and compact trench from 18" steel
pipe removal
Vale Electric, Electricians 1 10 Area 10, Temp Power
ACORE 1 5 Area 10 Core MH1 and MH2
Forms
Location
Form date May 10, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 11, 2023, 6:49 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1391 of 1851
Crew # Workers # Total
hours
Work performed
Totals 13 35
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Prep material for import
Deere 644J Loader 1 10 Area 10 place backfill, proof roll
IMCO Concrete Truck 1 8 Area 30 Pour South side of slab
IMCO Concrete Truck 1 8 Area 30 Pour South side of slab
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Remove 18" pipe, Backfill
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1392 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached HMH Concrete Field Report and IMCO batch tickets from todays placement.
7:00 am Attended IMCO morning safety brief and stretch and flex.
8:00 am Sean and I discussed the testing frequency and plan for todays placement. We agreed that he would
prime the pump then I could sample for my test and they would wait on results before placing any concrete in the
forms.
9:00 am The pump truck is onsite and getting setup.
10:00 am IMCO is working on batching 8 CY in the first truck. They are using the WRDA mix.
10:30 am IMCO has started to pour our the first truck. After the pump was primed and a small amount is
discharged in the forms I took my sample from the truck. Testing results were out of spec on air, it was too high at
11.5%. The decided to spin the drum for ~10 mins. I took a second sample from the truck. The air was still too high
at 9%. Sean, IMCO, asked if would take a third sample but he requested I take the sample from the end of the
pump truck. I agreed but told him if it passes I will be taking my sample from the end of the pump from here on
out. He agreed. I took my third sample from the pump truck. The concrete was in spec. My assumption is that the
pump truck knocked some air out of it and the concrete sat for long enough to loose air as well. Because of this I
decided to not take concrete cylinders from this truck and to test the second truck. IMCO started to pour out the
truck.
12:00 pm IMCO has batched a second truck. I let them pour out approx. 1/2 yard then I took my sample from the
end of the pump. The concrete was in spec on air at 6%. The slump was way under at 2". I notified Kirt and Sean.
This truck I casted 12 Cylinders. 3 for 3 day, 7 Day, 28 Day and holds.
12:45 pm IMCO has batched a third truck. I decided to test this truck as well to check the air and slump. They
were both in spec at 5.5" and 5.7%.
2:30 pm IMCO has batched two more trucks for a total of 5 on the day. They are estimating the pour took 22
yards total. This matches my calculations.
3:30 pm IMCO is working on finishing the concrete. Area 10 IMCO has been working on backfilling the 18" steel
pipe trench. Kirt informed me they are doing this to allow room to excavate for the 2 18" PVC pipes that also need
to be removed.
4:00 pm ACORE was onsite today coring MH1 and MH 2. MH1 had a grade bust that needed to be fixed. MH 2 and
a bust in the precast that needed to be fixed.
4:30 pm IMCO has picked up the grizzly screen from IPC. Zack has taken photos of the screen to document the
condition of it before IMCO starts using it. IMCO needs to remove some bars off the screen to allow up to 8" rock.
They are continuing to work on finishing the concrete.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1393 of 1851
References
Photos (7)
20230510_093157
Taken on May 10, 2023, 9:31 AM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
20230510_141700
Taken on May 10, 2023, 2:17 PM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1394 of 1851
20230510_093137
Taken on May 10, 2023, 9:31 AM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
20230510_093133
Taken on May 10, 2023, 9:31 AM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1395 of 1851
20230510_093129
Taken on May 10, 2023, 9:31 AM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
20230510_104854
Taken on May 10, 2023, 10:48 AM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1396 of 1851
20230510_141706
Taken on May 10, 2023, 2:17 PM MDT
Added on May 10, 2023, 4:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1397 of 1851
Form detail
#147: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 5 10 Area 30 Form for slab placement,
Install Water stop, set pipe
penetrations
IMCO, Operators and Labors 6 10 Area 10 Import and place general
fill, Pothole and excavate 2 18"
steel pipes from weir box, Locate
18" PVC pipes and utilities
Totals 11 20
Forms
Location
Form date May 9, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 10, 2023, 7:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1398 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Load General fill
Deere 644J Loader 1 10 Area 10 place backfill, proof roll
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Remove 18" pipe, Pot Hole
Dump Truck 1 10 Area 10 Import General Fill
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is planning on continuing the curb forming and water stop install in preparation for the slab
placement tomorrow. They also plan to start on potholing and possibly removing the 18" lines that run under the
new hatchery building.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1399 of 1851
8:00 am IMCO has started to pothole the 18" lines. Kurt is running the 85 excavator.
9:00 am Kurt has discovered multiple utilities in the trench. One cable was direct bury and very shallow. He kicked
it. They have notified IPC.
12:00 pm IMCO is continuing to work on forming for the curb and getting the water stop set for tomorrows
placement. Kurt is continuing to excavate for the 18" steel line demo.
2:00 pm Attended weekly meeting. It was determined that only one layer of trim bar is needed in the center wall
around the pipe penetrations.
4:00 pm IMCO is making final adjustments for the concrete placement tomorrow. There is 2 more carpenters
onsite to help out. Kurt has exposed 2 18" PVC lines. He has notified me and Zack that he believes its extra work. I
have asked him to track his time to discuss it further.
5:00 pm IMCO hauled general native fill from the pit all day. They are placing the material in the location of the
north holding ponds.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1400 of 1851
References
Photos (6)
20230509_172530
Taken on May 9, 2023, 5:25 PM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
20230509_172522
Taken on May 9, 2023, 5:25 PM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1401 of 1851
20230509_123722
Taken on May 9, 2023, 12:37 PM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
20230509_081337
Taken on May 9, 2023, 8:13 AM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1402 of 1851
20230509_172622
Taken on May 9, 2023, 5:26 PM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
20230509_172611
Taken on May 9, 2023, 5:26 PM MDT
Added on May 10, 2023, 7:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1403 of 1851
Form detail
#146: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Form for slab placement,
Install Water stop, set pipe
penetrations
IMCO, Operators and Labors 6 10 Area 10 Import and place general
fill
Vale Electric, Electricians 1 10 Area 10, Work on Temp Power
Totals 10 30
Forms
Location
Form date May 8, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 9, 2023, 7:50 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1404 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Load General fill
Deere 644J Loader 1 10 Area 10 place backfill, proof roll
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 Remove 18" pipe, Pot Hole
Dump Truck 1 10 Area 10 Import General Fill
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 Concrete Compressive Strength Report from the 6" drain Placement.
11:00 am IMCO is working on installing water stop in the curb along with installing the pre fabricated pipe pieces
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1405 of 1851
through the wall penetrations. They have removed the cured concrete from the concrete wash out and replaced
the plastic.
12:00 pm Jake, Kurt, Zack and I spoke to Jeff about switching to the Pine Creek Well feed to prevent any issues
with disturbing the power while removing the 18" pipes that run parallel to the Oxbow Power Feed.
1:00 pm Jeff has decided to turn both wells on to prevent any issues with hitting lines and running out of water.
4:00 pm IMCO is starting to excavate for the 18" pipes. He is starting at the weir box. He located the two pipes
and is now working on exposing them so they can be removed.
5:00 pm Kirt is done for the day. He has exposed the 18" pipes for approx. 30'. He has found 3 separate unmarked
utilities but has not damaged any of them. He plans to continue tomorrow.
References
Photos (8)
20230508_164857
Taken on May 8, 2023, 4:48 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
20230508_163858
Taken on May 8, 2023, 4:38 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1406 of 1851
20230508_163918
Taken on May 8, 2023, 4:38 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
20230508_163850
Taken on May 8, 2023, 4:38 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1407 of 1851
20230508_154411
Taken on May 8, 2023, 3:44 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
20230508_154401
Taken on May 8, 2023, 3:44 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1408 of 1851
20230508_140947
Taken on May 8, 2023, 2:09 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
20230508_124203
Taken on May 8, 2023, 12:42 PM MDT
Added on May 9, 2023, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1409 of 1851
Form detail
#145: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Form for slab placement
IMCO, Operators and Labors 2 10 Area 10 clean up around job, help
EOI
EOI 3 10 Area 30 Tie Rebar for the slab
placement
Totals 8 30
Forms
Location
Form date May 5, 2023
Description Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 5, 2023, 3:03 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1410 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am EOI and a small IMCO crew are onsite. EOI is going to continue to tie the rebar for the slab placement.
IMCO is here to build and set forms for the slab placement. They are currently working on getting the pipe
penetrations to correct elevation so EOI can get their rebar tied around it.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1411 of 1851
12:00 pm EOI brought a conflict to my attention. The center wall is 12" thick and it does not provide enough room
for all the rebar and the seepage ring of the pipe. I have checked the measurements and confirmed that there is
not enough room. I notified Zack of the conflict.
2:00 pm Zack has sent an RFI regarding the rebar in the center wall.
3:00 pm EOI is continuing to install rebar. IMCO is done for the day.
References
Photos (3)
20230505_145342
Taken on May 5, 2023, 2:53 PM MDT
Added on May 5, 2023, 3:03 PM MDT
Added by Chris Johnson
20230505_145152
Taken on May 5, 2023, 2:51 PM MDT
Added on May 5, 2023, 3:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1412 of 1851
20230505_145139
Taken on May 5, 2023, 2:51 PM MDT
Added on May 5, 2023, 3:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1413 of 1851
Form detail
#144: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 10 Area 30 Build rebar stands for
vertical bars
IMCO, Operators and Labors 6 50 Area 10 clean up site, build level
pad for wall forms, prep grade for
pipe install
EOI 3 10 Area 30 Tie Rebar for the slab
placement
Totals 11 70
Forms
Location
Form date May 4, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 5, 2023, 7:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1414 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Clean up site, load
concrete debris
Deere 644J Loader 1 10 Area 10 Load Concrete Debris
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 grade for level pad
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1
Deere 470 Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day Compressive Strength Report from the 4" Hydrant Line Concrete Placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1415 of 1851
7:30 am EOI is onsite and starting to work on the vertical bars for the walls. IMCO is working on laying out the
curbs so EOI can begin laying out and installing the vertical dowels.
8:00 am IMCO operators are continuing to load and haul off the concrete demo debris. They are also working on
grading and compacting the native material at the base of the holding ponds after demo.
12:00 pm EOI is continuing to install the vertical dowels. IMCO has been working on build braces so ensue the
vertical dowels are sturdy and in the correct location.
3:00 pm EOI is continuing to work on the rebar. IMCO has been grading for the 36" pipe from MH 1 to MH 2. They
do not have the pipe onsite so they are just prepping the grade. The pipe is due onsite tomorrow.
5:00 pm EOI will come back tomorrow to finish the dowel bars. IMCO will have a small crew onsite to help out and
to start forming the curbs.
References
Photos (4)
20230504_154048
Taken on May 4, 2023, 3:40 PM MDT
Added on May 5, 2023, 7:16 AM MDT
Added by Chris Johnson
20230504_153957
Taken on May 4, 2023, 3:39 PM MDT
Added on May 5, 2023, 7:16 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1416 of 1851
20230504_101336
Taken on May 4, 2023, 10:13 AM MDT
Added on May 5, 2023, 7:16 AM MDT
Added by Chris Johnson
20230504_101355
Taken on May 4, 2023, 10:13 AM MDT
Added on May 5, 2023, 7:16 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1417 of 1851
Form detail
#143: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Build and set forms for
Slab Placement
IMCO, Operators and Labors 6 50 Area 10 Set MH 2
EOI 3 10 Area 30 Tie Rebar for the slab
placement
Totals 12 70
Forms
Location
Form date May 3, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 3, 2023, 5:04 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1418 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Excavate for MH 2
Deere 644J Loader 1 10 Area 10 Load Concrete Debris
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 10 Excavate for MH 2
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1 10 Area 10 Set MH 2
Deere 470 Excavator 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am MH 2 is onsite. IMCO plans to set MH 2 today. The grade is under water and they will have to set the MH
with approx. 2' of water. The water is river influenced and IPC does not intended to lower the reservoir for over a
month.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1419 of 1851
8:00 am EOI is continuing to work on installing the rebar for Area 30 slab placement. IMCO is continuing to work
on excavating for MH 2.
10:00 am I have double checked the numbers with Kole for MH 2. They are working on setting the base now. They
are using the crane to set it.
12:00 pm IMCO has set the base for MH2. They are going to take lunch then continue stacking the manhole after.
1:30 pm EOI is working on the top mat of rebar now.
2:00 pm IMCO has set the second section of MH 2. I asked the crew to check the elevations of the holes. The 36"
outfall pipe is per plan. The 24" inlet and the 36" inlet are both approximately 0.80' low. I double checked the
submittal with IMCO. It does not show this change.
3:30 pm Kole checked the invert of the holes and confirmed with his GPS that the two holes are low and the
outfall is per plan. EOI is continuing to work on installing the top mat of rebar.
5:00 pm EOI has completed the rebar install. Tomorrow they will work on the vertical bar for the curbs and walls.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1420 of 1851
References
Photos (6)
20230503_165436
Taken on May 3, 2023, 4:54 PM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
20230503_115657
Taken on May 3, 2023, 11:56 AM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1421 of 1851
20230503_115641
Taken on May 3, 2023, 11:56 AM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
20230503_165524
Taken on May 3, 2023, 4:55 PM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1422 of 1851
20230503_165454
Taken on May 3, 2023, 4:54 PM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
20230503_134222
Taken on May 3, 2023, 1:42 PM MDT
Added on May 3, 2023, 5:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1423 of 1851
Form detail
#142: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Build and set forms for
Slab Placement
IMCO, Operators and Labors 6 50 Area 10 Demo North holding
ponds, Backfill and compact
Vale Electric, Electricians 1 10 Area 10 Temp Power
EOI 2 10 Area 30 Tie Rebar for the slab
placement
Forms
Location
Form date May 2, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 3, 2023, 6:58 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1424 of 1851
Crew # Workers # Total
hours
Work performed
Totals 12 80
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Demo
Deere 644J Loader 1 10 Area 10 Load Concrete Debris
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1
Deere 470 Excavator 1 10 Area 10 Demo
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1425 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day Concrete Compressive Strength Report for the 24" Discharge Pipe Encasement Placement.
7:00 am Attended IMCO morning safety brief.
8:00 am IMCO is going to continue to work on demoing the north holding ponds. EOI is onsite to begin installing
rebar for Area 30.
12:00 pm IMCO has encountered water in the bottom of the holding ponds. They are continuing to demo and
remove all concrete. EOI has found that some of the bars do not fit around the pipe with the seepage ring. Jake has
sent an RFI regarding this.
1:00 pm Schnabel has given direction to cut the bars in conflict with the pipe. EOI is continuing to work on
installing the rebar.
4:00 pm EOI is continuing to work on installing the bottom mat of rebar for the slab placement. IMCO is helping
by cutting the rebar per Schnabel direction.
5:00 pm The crews are cleaning up for the day. They will continue working on rebar and curb forming tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1426 of 1851
References
Photos (4)
20230502_124622
Taken on May 2, 2023, 12:46 PM MDT
Added on May 3, 2023, 6:56 AM MDT
Added by Chris Johnson
20230502_124556
Taken on May 2, 2023, 12:45 PM MDT
Added on May 3, 2023, 6:57 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1427 of 1851
20230502_162354
Taken on May 2, 2023, 4:23 PM MDT
Added on May 3, 2023, 6:56 AM MDT
Added by Chris Johnson
20230502_162347
Taken on May 2, 2023, 4:23 PM MDT
Added on May 3, 2023, 6:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1428 of 1851
Form detail
#141: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Build and set forms for
Slab Placement
IMCO, Operators and Labors 5 50 Area 10 Demo North holding
ponds
Area 30 Backfill and compact fill
around pipe encasements, Bolt on
couplers and valves
Vale Electric, Electricians 1 10 Area 10, Temp power to the
crowders to demo could continue
Forms
Location
Form date May 1, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 2, 2023, 7:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1429 of 1851
Crew # Workers # Total
hours
Work performed
Totals 9 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Demo
Deere 644J Loader 1 10 Area 10 Load General fill at
stockpile
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1
Deere 470 Excavator 1 0
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1430 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 28 day Concrete Compressive Strength Report for the Raceway Pipe Encasement Placement and 7
day Well Pump Pipe Encasement.
10:00 am IMCO is working on demoing the north holding ponds. They are using a hammer attachment on the
excavator to break up the concrete and the loader is loading the concrete debris in the dump truck and hauling it
offsite. Vale is onsite to disconnect the power to the crowders which run through the center wall. They are also
setting slab forms for Area 30.
12:00 pm IMCO is working on bolting up the butterfly valves and couplers for the raceway pipes leaving area 30.
While checking the pipes it was determined that the butterfly valves will not fit in the current configuration. The
valves are V 10.20 through V 10.25. I have sent Zack and Bryant an email regarding these valves.
2:00 pm Bryant is looking at solutions for the valves, IMCO has sent an RFI regarding the conflict. IMCO is
continuing to work on demoing the north holding ponds. Vale has removed the power and they are working on the
center wall as well now.
4:30 pm IMCO is setting the pipe to the cross crowder channel through the slab forms. This pipe encasement will
be part of the slab pour.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1431 of 1851
References
Photos (6)
20230501_152415
Taken on May 1, 2023, 3:24 PM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
20230501_103750
Taken on May 1, 2023, 10:37 AM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1432 of 1851
20230501_160948
Taken on May 1, 2023, 4:09 PM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
20230501_160926
Taken on May 1, 2023, 4:09 PM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1433 of 1851
20230501_152437
Taken on May 1, 2023, 3:24 PM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
20230501_134354
Taken on May 1, 2023, 1:43 PM MDT
Added on May 1, 2023, 4:20 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1434 of 1851
Form detail
#140: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Pre fabricate water stop,
weld water stop
IMCO, Operators and Labors 5 50 Area 10 Demo North holding
ponds
Area 30 Backfill and compact fill
around pipe encasements
Steel Building Systems 4 10 Area 20 Install flashing around
hatches
Forms
Location
Form date Apr 27, 2023
Description Area 10, Area 20, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update May 1, 2023, 10:14 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1435 of 1851
Crew # Workers # Total
hours
Work performed
Totals 12 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Demo
Deere 644J Loader 1 10 Area 10 Load General fill at
stockpile
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 10 Area 10 Import general fill from
stockpile
Kobelco 1100G Crane 1
Deere 470 Excavator 1 10 Area 10 Backfill
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1436 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on backfilling around Area 30. They are prepping to begin forming for the slab
placement. Heath, IPC, is onsite to start the irrigation pump.
10:00 am The irrigation pump was tripping a reset. Heath checked the amps and determined the set point was
set to low for the new pump. IMCO had some leaks on the irrigation pump line so they are going to get those
tightened up before Heath turns the irrigation pump back on for the season.
12:00 pm IMCO is continuing to work on demoing the north hold ponds, mainly near the weir box. The roofers
are finishing up for the day. They have one flashing that needs to be added but they did not have it with them.
They also need to finish a few small pieces in the vented soffit. They plan to finish this next week.
1:00 pm Kirt informed me that he may have a couple guys work tomorrow demoing the north holding ponds. Left
site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1437 of 1851
References
Photos (6)
20230427_110419
Taken on Apr 27, 2023, 11:04 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
20230427_082716
Taken on Apr 27, 2023, 8:27 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1438 of 1851
20230427_082647
Taken on Apr 27, 2023, 8:26 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
20230427_110408
Taken on Apr 27, 2023, 11:04 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1439 of 1851
20230427_111309
Taken on Apr 27, 2023, 11:13 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
20230427_082532
Taken on Apr 27, 2023, 8:25 AM MDT
Added on May 1, 2023, 10:13 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1440 of 1851
Form detail
#139: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 form pipe encasement for
6" formalin carrier pipe, Pour
encasement
IMCO, Operators and Labors 5 50 Area 10 Install Fused pipe from MH
1 to drain at area 30, Backfill fused
pipe
Area 30 Backfill and compact fill
around pipe encasements
Steel Building Systems 4 10 Area 20, Install soffit on Intake
Structure
Forms
Location
Form date Apr 26, 2023
Description Area 10, Area 20, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 27, 2023, 7:08 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1441 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 2 Onsite for temp power plan
Totals 14 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Backfill
Deere 644J Loader 1 10 Area 10 Load truck with native
material at stockpile
IMCO Concrete Truck 1
IMCO Concrete Truck 1 1 Area 30 pipe encasement
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 10 Area 10 Import native material
from stockpile
Kobelco 1100G Crane 1 3 Area 20, Pick roof for soffit could
be installed
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1442 of 1851
Equipment Quantity Hours
used
Comment
Deere 470 Excavator 1 10 Area 10 Install Yard piping, Drains
to MH 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is IMCO Batch Ticket and 7 day Compressive Strength Report for the 12" River Intake Placement.
7:30 am IMCO is going to work on backfilling around the pipe encasements. They also plan to form for the 6"
conduit pipe that is for the formalin lines to be pulled through.
10:00 am The roofing company is working on installing the vented soffit. IMCO is continuing to work on placing
and compacting around the concrete pipe encasements.
12:00 pm IMCO has installed the HDPE pipe from the well pump drain and overflow to MH 1. They are working on
backfilling it now.
2:00 pm IMCO is continuing to work on forming for the 6" formalin pipe encasement.
3:00 pm IMCO made a last minute decision to place concrete to encase the 6" Formalin conduit. I did not test the
concrete. See attached batch ticket.
5:00 pm The roofing company plans to be back tomorrow to finish the soffit. IMCO is going to place the roof back
on the structure tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1443 of 1851
References
Photos (3)
20230426_145404
Taken on Apr 26, 2023, 2:54 PM MDT
Added on Apr 27, 2023, 7:08 AM MDT
Added by Chris Johnson
20230426_111257
Taken on Apr 26, 2023, 11:12 AM MDT
Added on Apr 27, 2023, 7:08 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1444 of 1851
20230426_090933
Taken on Apr 26, 2023, 9:09 AM MDT
Added on Apr 27, 2023, 7:08 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1445 of 1851
Form detail
#138: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 form grout placement
around pipes in river intake vault,
remove forms from yesterdays
placement
IMCO, Operators and Labors 5 50 Area 10 Begin demo on 1/3 of the
holding ponds, Area 30 Backfill and
compact fill around pipe
encasements, Fuse HDPE pipe to
MH 1
Forms
Location
Form date Apr 25, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 26, 2023, 7:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1446 of 1851
Crew # Workers # Total
hours
Work performed
Steel Building Systems 4 10 Area 20, Install roof on Intake
Structure
Totals 12 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Demo North Holding
ponds, Area 30 Backfill
Deere 644J Loader 1 10 Area 10 Load concrete debris and
Metal Debris
IMCO Concrete Truck 1
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 4 Area 10 Export concrete debris
Kobelco 1100G Crane 1 3 Area 20, Remove roof for roofers
to install metal roofing
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1447 of 1851
Equipment Quantity Hours
used
Comment
Deere 470 Excavator 1 10 Area 10 Install Yard piping, Drains
to MH 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO plans to form and place grout around 12" river intake pipes that penetrate the valve vault. They
are going build forms to hold the grout in. Usually this is done by hand but the holes were oversized to fit the
flange end of the spools. They are going to wait until 24 hrs from the placement to strip the forms from yesterdays
pipe encasement placement.
9:00 am Steel Building Structures is onsite working on the roofing for Area 20 Intake Structure.
11:00 am IMCO has started to demo the holding ponds. I confirmed with the operator that he needs to stay away
from the center wall along with the 2/3rds of the holding ponds adjacent to the ponds that are holding fish. He was
aware of this. While demoing he found a power conduit and broke it. I contacted Reid, IDFG, who is onsite in Jeffs
place. He checked the hatchery building and everything is working and fine. The wires are most likely going to the
breaker panel that runs the crowders. The crowders were locked out tagged out yesterday by IPC.
12:00 pm IMCO will have Vale Electric onsite tomorrow to fix the hit power so the fish hatchery can operate as
usual on Thursday. IMCO is continuing to place grout. They are getting set up to start installing the drain line to
MH 1. This is HDPE pipe that is fused.
1:00 pm IMCO is placing structural fill over the river intake pipes that will be under Area 30 slab. Using a nuclear
gauge I tested the material. First test was 93%, I advised them to add more water and compact again. The second
test was average of 96%.
2:00 pm Attended weekly meeting.
3:00 pm Steel Building Systems is continuing to work on the metal roofing for the intake structure. IMCO is
working on fusing the HDPE pipe for the drain piping.
4:30 pm IMCO is continuing to work on stripping the forms from yesterdays placement. They are also backfilling
and compacting around the pipe encasements.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1448 of 1851
References
Photos (7)
20230425_160514
Taken on Apr 25, 2023, 4:05 PM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
20230425_160411
Taken on Apr 25, 2023, 4:04 PM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1449 of 1851
20230425_144038
Taken on Apr 25, 2023, 2:40 PM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
20230425_133408
Taken on Apr 25, 2023, 1:34 PM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1450 of 1851
20230425_100024
Taken on Apr 25, 2023, 10:00 AM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
20230425_095628
Taken on Apr 25, 2023, 9:56 AM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1451 of 1851
20230425_092428
Taken on Apr 25, 2023, 9:24 AM MDT
Added on Apr 25, 2023, 4:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1452 of 1851
Form detail
#137: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Finish forming for the well
pump and drain encasement, Place
concrete for pipe encasement
IMCO, Operators and Labors 5 50 Area 10 Demo Head Box and haul
offsite, Area 30 Backfill and
compact fill around pipe
encasements, Import general fill to
site
Totals 8 60
Forms
Location
Form date Apr 24, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 24, 2023, 5:17 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1453 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 demo head box, Area 30
Backfill
Deere 644J Loader 1 10 Area 30, Load general fill for
import
IMCO Concrete Truck 1 4 Area 30, Pipe encasement
placement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 3 Area 30, Compact general fill
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1 3 Area 20, Remove roof for roofers
to install metal roofing
Deere 470 Excavator 1 10 Area 30 Batch Concrete
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1454 of 1851
Notes
Attached HMH Concrete Field Report for 6" well pumps, 12" drain, 6" drain Pipe encasement placement, IMCO
Batch Tickets.
10:00 am Arrived on site. IMCO is prepping to place concrete for the pipe encasement of the 2 6" well pump pipes
along with the 12" drain and 6" drain. Last Thursday they installed the river intake manifold in the ground and
connected the 4 12" river intake pipes with couplers to the manifold outside the valve vault.
11:00 pm I have checked all rebar and clearances. IMCO is batching concrete now for the pipe encasement. The
crane has lifted the roof off of Area 20 Intake Structure. The roofers are onsite to begin installing the metal roofing.
They are doing this on the ground in a effort to increase efficiency and safety.
2:00 pm IMCO has placed 10 CY of concrete for pipe encasement. I tested the first truck and all tested in spec.
See concrete field report. There was discussion regarding the elevation of the 6" floor drain. The drain is was too
low and had negative fall that would cause water to be backed up in the pipe. Bill and Zack, IPC, are onsite. They
requested to raise to pipe to ensure positive flow to prevent water from backing up.
4:00 pm IMCO is importing material from the stockpile. They have started backfilling in the center of Area 30 and
compacting with the hoepack. Another crew is working on grouting the 12" intake pipes in the valve vault.
4:30 pm IMCO is continuing to work on grouting the holes around the vault.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1455 of 1851
References
Photos (2)
20230424_131350
Taken on Apr 24, 2023, 1:13 PM MDT
Added on Apr 24, 2023, 4:54 PM MDT
Added by Chris Johnson
20230424_131628
Taken on Apr 24, 2023, 1:16 PM MDT
Added on Apr 24, 2023, 4:54 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1456 of 1851
Form detail
#135: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Prep and Form for pipe
encasement of 2 6" well pump
pipes
IMCO, Operators and Labors 6 60 Area 10 Demo Head Box
Totals 9 70
2. Materials
Forms
Location
Form date Apr 20, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 21, 2023, 9:42 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1457 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 demo head box
Deere 644J Loader 1 10 Area 10, Clean up dumpsite
IMCO Concrete Truck 1
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 10 Area 30 Set Pipes into the vault
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is the 7 day compressive strength report from the 12" river intake, and 12" spray bar concrete placement.
7:30 am IMCO is starting to work on setting the couplers and pipes into the valve vault for the river intake piping.
9:30 am IMCO is continuing to work on demoing the head box. They are breaking up the concrete and hauling it
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1458 of 1851
offsite. IMCO is also working on installing the Romac 501 couplings and the stainless pipe spools into the valve
vault. I talked to the crew about the torque requirements needed for the couplings. They are using dissimilar metal
isolation kits for the flange valve to flange spool connections. We talked about using anti seize on all stainless
bolts.
12:00 pm IMCO is continuing to work on demoing the weir box. The pipe crew is continuing to bolt up the fittings
and the valves in the vault. While checking the the vault lid it was determined that the round lids for the valve key
stems do not line up with the butterfly valves. I have asked IMCO to provide a solution for the issue. Jake and Kirt
are working on this.
1:00 pm Left site to deliver concrete cylinders to the lab. John Anderson arrived onsite.
References
Photos (4)
20230420_110007
Taken on Apr 20, 2023, 11:00 AM MDT
Added on Apr 21, 2023, 9:36 AM MDT
Added by Chris Johnson
20230420_105851
Taken on Apr 20, 2023, 10:58 AM MDT
Added on Apr 21, 2023, 9:36 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1459 of 1851
20230420_105838
Taken on Apr 20, 2023, 10:58 AM MDT
Added on Apr 21, 2023, 9:36 AM MDT
Added by Chris Johnson
20230420_105815
Taken on Apr 20, 2023, 10:58 AM MDT
Added on Apr 21, 2023, 9:36 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1460 of 1851
Form detail
#134: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Prep to pour 12" river
intake encasements, Place 8 CY of
concrete for pipe encasement
IMCO, Operators and Labors 6 60 Area 10 Place and compact fill near
Area 70
Area 30 Batch concrete
Totals 9 70
Forms
Location
Form date Apr 19, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 19, 2023, 4:53 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1461 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 backfill abandoned
raceways, demo head box
Deere 644J Loader 1 10 Area 10, Backfill chinook raceways
IMCO Concrete Truck 1 4 Area 30, Place pipe encasement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 Move material around site
Hitachi 85 Excavator 1 10 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 Export concrete debris
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 10 Area 30 Batch concrete
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1462 of 1851
Notes
7:30 am IMCO is prepping to place concrete for the rest of the 12" river intake pipe encasement. They are also
going to place and compact fill near area 70. They are using native material for fill.
10:00 am IMCO is starting to batch concrete. I have checked the rebar and forms. I asked Jake to make a few
adjustments to the rebar to match the rebar submittal.
12:00 pm IMCO placed 8 CY of concrete. They used the .40 WRDA mix design. This design is a higher slump with
the admixture for water reducing. The first truck had 6.5 CY batched. I tested the truck for air and it came back
high at 10.5%. They decided to let the concrete sit before placing in hopes some air would come out of it. After
letting it sit I tested the truck again and got 9%. IMCO decided to continue pouring the truck out so I finished my
test and casted 9 cylinders. They ran out of concrete and batched 1.5 CY to finish the placement.
1:30 pm Jake informed me that the roofers will be onsite Monday to install the roof on Area 20, River intake. They
are going to pick the roof off put on the ground so the roofers do not have to work over the water. Jake and I put
our fall protection on and got on the roof to inspect the condition of the plywood. I used my pocket knife to check
for any soft wood and or rotting. All the sheeting looked sun beaten but was still very firm and no rotting was
observed. The fasteners did not show any rusting either. Jake showed the photos to Zack who also agreed that
they could proceed with roofing without further attention need to the sheeting.
3:00 pm IMCO is working on demoing the head box. They are also getting the string lines up again at Area 30 to
start installing the pipes to the well pumps.
4:30 pm IMCO is setting forms for the well pump pipe encasement. They are continuing to demo the head box
and hauling concrete debris offsite.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1463 of 1851
References
Photos (8)
20230419_115709
Taken on Apr 19, 2023, 11:57 AM MDT
Added on Apr 19, 2023, 4:11 PM MDT
Added by Chris Johnson
20230419_141048
Taken on Apr 19, 2023, 2:10 PM MDT
Added on Apr 19, 2023, 4:44 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1464 of 1851
20230419_102132
Taken on Apr 19, 2023, 10:21 AM MDT
Added on Apr 19, 2023, 4:44 PM MDT
Added by Chris Johnson
20230419_115724
Taken on Apr 19, 2023, 11:57 AM MDT
Added on Apr 19, 2023, 4:11 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1465 of 1851
20230419_115712
Taken on Apr 19, 2023, 11:57 AM MDT
Added on Apr 19, 2023, 4:11 PM MDT
Added by Chris Johnson
20230419_163152
Taken on Apr 19, 2023, 4:31 PM MDT
Added on Apr 19, 2023, 4:44 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1466 of 1851
20230419_140959
Taken on Apr 19, 2023, 2:09 PM MDT
Added on Apr 19, 2023, 4:44 PM MDT
Added by Chris Johnson
20230419_140425
Taken on Apr 19, 2023, 2:04 PM MDT
Added on Apr 19, 2023, 4:44 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1467 of 1851
Form detail
#133: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Form for pipe encasement
of the 12" river intake pipes
IMCO, Operators and Labors 6 60 Area 10 Install 36" drain pipe from
MH 1 to MH 2, Area 30 Set river
intake vault
Totals 9 70
2. Materials
Forms
Location
Form date Apr 18, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 19, 2023, 7:14 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1468 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 8 Area 10 Excavate and install 36"
drain pipe from MH 1 to MH 2
Deere 644J Loader 1 8 Area 10, Backfill chinook raceways,
load general fill in dump truck
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 8 Area 30 set pipes
Hitachi 85 Excavator 1 8 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 8 Area 10 Haul structural fill and
general fill from stockpile
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 8 Area 10, Excavate and install 36"
drain pipe from MH1
Area 30 Excavate and set river
intake vault
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1469 of 1851
Notes
8:00 am The large vault for the 4 river intake pipes is onsite. IMCO plans to set this vault today. Area 10 crew is
continuing to work on excavating and setting 36" drain pipe from MH1 to MH2. They will install the pipe to the wall
of the holding ponds and stop until they can demo the walls next week. Area 30 crew is working on forming the 12"
intake pipes for a placement later today.
10:00 am I have confirmed with IMCO that the Rim Elevation of the vault has not changed and they are going to
install the vault to that elevation. Kirt informed me they checked the invert elevation of the 4 river intake pipes and
they were good so the vault should line up correctly.
1:00 pm IMCO has set 2 sticks of 20' 36" drain pipe towards MH 2. They cannot install any more without demoing
the North holding ponds. They have set the river intake valve vault and they are double checking the elevations
and placement location.
2:00 pm Attended weekly meeting.
3:00 pm IMCO is importing General Fill from the stockpile. They are placing and compacting the general fill over
the 36" drain pipe from MH 1 to MH 2.
3:30 pm IMCO is done for the day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1470 of 1851
References
Photos (4)
20230418_144329
Taken on Apr 18, 2023, 2:43 PM MDT
Added on Apr 18, 2023, 3:26 PM MDT
Added by Chris Johnson
20230418_131139
Taken on Apr 18, 2023, 1:11 PM MDT
Added on Apr 18, 2023, 3:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1471 of 1851
20230418_125941
Taken on Apr 18, 2023, 12:59 PM MDT
Added on Apr 18, 2023, 3:26 PM MDT
Added by Chris Johnson
20230418_105307
Taken on Apr 18, 2023, 10:53 AM MDT
Added on Apr 18, 2023, 3:26 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1472 of 1851
Form detail
#132: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Remove forms from
Thursdays concrete placement,
Form pipe encasement for the 2
well pipes, Form pipe encasement
for the river intake pipes, tie rebar
IMCO, Operators and Labors 6 60 Area 10 Demo abandoned
raceways and haul concrete offsite,
Install 36" drain pipe from MH 1,
Area 20 install air vac on irrigation
line
Forms
Location
Form date Apr 17, 2023
Description Area 10, Area 20, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 17, 2023, 4:59 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1473 of 1851
Crew # Workers # Total
hours
Work performed
Totals 9 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Abandoned raceway
demo, Backfill
Deere 644J Loader 1 10 Area 10, Backfill chinook raceways,
Load pipe bedding
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 set pipes
Hitachi 85 Excavator 1 10 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 haul concrete debris
offsite, haul pipe bedding onsite
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 8 Area 10, Excavate and install 36"
drain pipe from MH1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1474 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached 7 day compressive break report from the 6" drain pipe encasement and the 28 day break report from
the Trial Batch.
9:00 am Arrived on site. IMCO carpenters are working on removing the forms from Thursdays concrete
placement, others are working on moving material around the site. Another crew is working on mudding the
outfall pipe in MH1.
12:00 pm IMCO is backfilling the abandoned raceways with native material. They are placing the material in 12"
lifts and compacting with a hoe pack attachment. They are continuing to tie the rebar and form for the next pipe
encasement placement. IMCO as installed the air vac on the irrigation line on Area 20. IMCO needs to complete the
plumbing. I contacted Heath Phelps, IPC, regarding turning the irrigation line on. He said he wants to wait another
week due to the temps this week.
2:00 pm IMCO is excavating to continue installing 36" drain pipe from MH 1.
4:30 pm We have double checked the numbers of the 36" pipe elevation. The crew is setting the pipe to grade
now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1475 of 1851
References
Photos (5)
20230417_140802
Taken on Apr 17, 2023, 2:08 PM MDT
Added on Apr 17, 2023, 4:53 PM MDT
Added by Chris Johnson
20230417_135752
Taken on Apr 17, 2023, 1:57 PM MDT
Added on Apr 17, 2023, 4:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1476 of 1851
20230417_133023
Taken on Apr 17, 2023, 1:30 PM MDT
Added on Apr 17, 2023, 4:53 PM MDT
Added by Chris Johnson
20230417_131002
Taken on Apr 17, 2023, 1:10 PM MDT
Added on Apr 17, 2023, 4:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1477 of 1851
20230417_152346
Taken on Apr 17, 2023, 3:23 PM MDT
Added on Apr 17, 2023, 4:53 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1478 of 1851
Form detail
#131: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 0
IMCO, Operators and Labors 1 10 Area 10, Demo and export
abandoned raceways
Totals 1 10
2. Materials
Forms
Location
Form date Apr 14, 2023
Description Area 10
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 17, 2023, 10:44 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1479 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 0
Deere 644J Loader 1
IMCO Concrete Truck 1
IMCO Concrete Truck 1
JCB 510 Boom Forklift 1
Hitachi 85 Excavator 1
Dump Truck 1 10 Area 10 haul concrete debris
offsite
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 8 Area 10, Abandoned Raceway
Demo
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO has one operator onsite working on demoing the the abandoned raceway. He is loading the truck
and hauling it off site.
12:30 pm I have picked up the concrete cylinders, the one operator is still working on demo and hauling off site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1480 of 1851
References
Photos (2)
20230414_121506
Taken on Apr 14, 2023, 12:15 PM MDT
Added on Apr 17, 2023, 10:44 AM MDT
Added by Chris Johnson
20230414_121521
Taken on Apr 14, 2023, 12:15 PM MDT
Added on Apr 17, 2023, 10:44 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1481 of 1851
Form detail
#130: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Micro adjust pipes prior to
placing concrete, Place concrete
pipe encasement for the 4 river
intake 12" pipes, place concrete for
pipe encasement for the 12" spray
bar pipe and rest of 4" hydrant line
IMCO, Operators and Labors 6 60 Area 10 Demo chinook raceways,
load out concrete, backfill and
compact chinook raceways, Install
one 20' 36" stick of pipe from the
outfall of MH 1
Forms
Location
Form date Apr 13, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 14, 2023, 11:50 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1482 of 1851
Crew # Workers # Total
hours
Work performed
Totals 9 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Abandoned raceway demo
Deere 644J Loader 1 10 Area 10, Backfill chinook raceways
IMCO Concrete Truck 1 5 Area 30, Pipe encasement
placement
IMCO Concrete Truck 1 5 Area 30, Pipe encasement
placement
JCB 510 Boom Forklift 1 10 Area 30 set pipes
Hitachi 85 Excavator 1 10 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 haul concrete debris
offsite
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 8 Area 30, Batch concrete
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1483 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached HMH Concrete Field Report, IMCO batch tickets and 7 day compressive break report from the 4"
hydrant line placement.
8:00 am IMCO is going to make the final preparations for the concrete placement today. They will be placing
approx. 20 CY for pipe encasement of the 4 12" river intake pipes along with the 12" spray bar pipe and the rest of
the 4" hydrant line pipe. They are fine tuning the pipes and bracing the forms.
9:00 am IMCO is continuing to work on Area 10 demo of the abandoned raceways. They are hauling that material
off site. They are also working on backfilling the chinook raceway hole. They are placing native material in 12" lifts
and compacting with the hoe pack attachment.
10:00 am IMCO is prepping to start batching concrete.
12:00 pm IMCO has place one 4 yard load. They are batching the second load at 8 yards.
12:30 pm I have taken my concrete sample out of the second truck. See concrete field report. They crew is still
fine tuning the mix to meet the slump requirement. They are having a hard time getting the 3" slump mix down
the shoot of the truck. I have suggest they may need to switch to the water reducing admixture where a 7" slump
is allowed. They are using a stinger to consolidate the concrete around the pipes and rebar.
2:00 pm IMCO has placed 20 CY of concrete. They top of the placement is approx. bottom of our structure slab.
IMCO is going to start working on forming for the next placement. They have been continuing to work on demoing
Area 10 abandoned raceways and hauling the concrete off site.
4:00 pm IMCO has been working on cleaning up the site for the weekend and laying out for the next pipe install
and concrete placement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1484 of 1851
References
Photos (10)
20230413_160205
Taken on Apr 13, 2023, 4:02 PM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
20230413_134049
Taken on Apr 13, 2023, 1:40 PM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1485 of 1851
20230413_124557
Taken on Apr 13, 2023, 12:45 PM MDT
Added on Apr 14, 2023, 8:58 AM MDT
Added by Chris Johnson
20230413_104402
Taken on Apr 13, 2023, 10:44 AM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1486 of 1851
20230413_095156
Taken on Apr 13, 2023, 9:51 AM MDT
Added on Apr 14, 2023, 8:58 AM MDT
Added by Chris Johnson
20230413_091208
Taken on Apr 13, 2023, 9:12 AM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1487 of 1851
20230413_091155
Taken on Apr 13, 2023, 9:11 AM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
20230413_160224
Taken on Apr 13, 2023, 4:02 PM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1488 of 1851
20230413_160100
Taken on Apr 13, 2023, 4:01 PM MDT
Added on Apr 14, 2023, 8:59 AM MDT
Added by Chris Johnson
20230413_095208
Taken on Apr 13, 2023, 9:52 AM MDT
Added on Apr 14, 2023, 8:58 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1489 of 1851
Form detail
#129: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Install 12" pipe for spray
bars, Form 12" encasement for
spray bars, Install 4 12" pipes from
river intake, form for pipe
encasement
IMCO, Operators and Labors 6 60 Area 10 Demo chinook raceways,
load out concrete, backfill and
compact chinook raceways, Install
one 20' 36" stick of pipe from the
outfall of MH 1
Forms
Location
Form date Apr 12, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 13, 2023, 7:34 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1490 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 5 Area 30 Tie rebar for pipe
encasements
Totals 11 75
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 Abandoned raceway demo
Deere 644J Loader 1 10 Area 10, Backfill chinook raceways
IMCO Concrete Truck 1
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Area 30 set pipes
Hitachi 85 Excavator 1 10 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 haul concrete debris
offsite, Import pipe bedding to site
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 0 Area 10, Install pipe from MH 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1491 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am IMCO is working on forming for the 4 river intake pipe encasement placement.
12:00 pm EOI is onsite to tie the rebar for the river intake pipe encasement. IMCO has the forms up and is
starting to set the river intake pipes. IMCO is also working on setting the outfall pipe from MH 1. It is a 36" pipe.
The crew is using pipe bedding under the pipe that they compacted with a jumping jack.
3:00 pm EOI is done for the day. They installed the rebar form the first placement of the pipe encasement for the
4 river intake pipes. IMCO plans to pour this tomorrow.
4:00 pm IMCO is fine tuning the pipes and bracing the forms in preparation for the pipe encasement placement
tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1492 of 1851
References
Photos (4)
20230412_150824
Taken on Apr 12, 2023, 3:08 PM MDT
Added on Apr 13, 2023, 7:33 AM MDT
Added by Chris Johnson
20230412_142853
Taken on Apr 12, 2023, 2:28 PM MDT
Added on Apr 13, 2023, 7:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1493 of 1851
20230412_134625
Taken on Apr 12, 2023, 1:46 PM MDT
Added on Apr 13, 2023, 7:33 AM MDT
Added by Chris Johnson
20230412_134444
Taken on Apr 12, 2023, 1:44 PM MDT
Added on Apr 13, 2023, 7:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1494 of 1851
Form detail
#128: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 3 10 Area 30 Install 12" pipe for spray
bars, Form 12" encasement for
spray bars
IMCO, Operators and Labors 6 60 Area 10 Demo chinook raceways,
load out concrete, backfill and
compact chinook raceways
Excavate and install MH1
Area 30 Install 12" pipe to spray
bars
Forms
Location
Form date Apr 11, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 12, 2023, 9:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1495 of 1851
Crew # Workers # Total
hours
Work performed
EOI 2 5 Area 30 Tie rebar for pipe
encasements
Totals 11 75
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 raceway demo with
hammer attachment, Load out
concrete debris
Deere 644J Loader 1 10 Area 10, Backfill chinook raceways
IMCO Concrete Truck 1
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Moving material around the site
Hitachi 85 Excavator 1 10 Area 10 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 haul concrete debris
offsite, Import general fill to site
Kobelco 1100G Crane 1 4 Area 10, set MH 1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1496 of 1851
Equipment Quantity Hours
used
Comment
Deere 470 Excavator 1 0 Area 10, Excavate for MH 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is the 7 day compressive break report for the 4/4 24" discharge pipe encasement placement.
8:00 am IMCO is prepping to continue work on Area 10 and Area 30. Area 10 they are going to continue working
on the chinook raceway demo. They also plan to use the native spoils from the excavation of MH 1 to backfill the
chinook raceways. Area 30 they will continue working on installing the 12" pipe to the spray bars and form for the
pipe encasement. EOI is onsite to tie the rebar for the pipe encasement.
10:00 am IMCO has started excavating for MH 1. They have been hauling concrete debris offsite from the chinook
raceway demo. They are going to take the native spoils from the excavation of MH 1 and install in 12" lifts to fill the
hole in from the chinook raceway demo. They are using the hoepack attachment to compact the 12" lifts.
12:00 pm IMCO has set the grade for MH 1. I have probed the subgrade after compaction. Soil was firm and
unyielding. The native material has been good looking mix of rocks and fine material. At the bottom of the
excavation of MH 1 a clay material layer was observed. We checked the elevation and it was determined they did
not need to go any deeper.
2:00 pm IMCO has placed MH 1. They are going to backfill around part of the structure to provide more room for
Jeff, IDFG, to access his house safely. Attended weekly meeting.
4:00 pm IMCO has backfilled around MH 1 where they could. They have set the 12" pipe for the spray bars and
micro adjusting it now.
4:30 pm IMCO has continued working on demoing the abandoned raceways.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1497 of 1851
References
Photos (9)
20230411_162256
Taken on Apr 11, 2023, 4:22 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
20230411_162209
Taken on Apr 11, 2023, 4:22 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1498 of 1851
20230411_162104
Taken on Apr 11, 2023, 4:21 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
20230411_124301
Taken on Apr 11, 2023, 12:43 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1499 of 1851
20230411_123201
Taken on Apr 11, 2023, 12:32 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
20230411_123122
Taken on Apr 11, 2023, 12:31 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1500 of 1851
20230411_110904
Taken on Apr 11, 2023, 11:09 AM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
20230411_104341
Taken on Apr 11, 2023, 10:43 AM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1501 of 1851
20230411_162134
Taken on Apr 11, 2023, 4:21 PM MDT
Added on Apr 11, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1502 of 1851
Form detail
#127: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 Finish bracing form for 6"
drain line pipe encasement, pour 1
CY pipe encasement.
IMCO, Operators and Labors 6 60 Area 30 Demo area 10 raceways /
chinook raceways Export broken
concrete, compact and proof roll
Area 30, Pour pipe encasement,
set backfill and compact, start
working on 12" pipe encasement
for raceway spray bars.
Forms
Location
Form date Apr 10, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 11, 2023, 11:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1503 of 1851
Crew # Workers # Total
hours
Work performed
Totals 7 70
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 raceway demo with
hammer attachement
Deere 644J Loader 1 0
IMCO Concrete Truck 1 3 Area 30 pipe encasement
placement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10
Hitachi 85 Excavator 1 10 Area 30 backfill and compact with
hoe pack attachment
Dump Truck 1 10 Area 10 haul concrete debris
offsite
Kobelco 1100G Crane 1 0
Deere 470 Excavator 1 0 Area 30, Batch concrete
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1504 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
See attached IMCO batch ticket, HMH Concrete Field Report, HMH Compressive break report for the Trial Batching
21 day and Raceway pipe encasement 7 day.
9:30 am Arrived on site. IMCO is working on the final preparation for the 6" drain line pipe encasement pour.
They are also continuing the work on demoing area 10 chinook raceways.
11:00 am IMCO is ready for the pipe encasement pour. They are prepping to start batching concrete.
12:00 pm IMCO has batched 1 CY of concrete. Looking at the slump from the truck it looked way to wet. I asked
Kole to check with Kirt but I recommended they try another batch of concrete. They agreed. They used the 1 CY for
eco blocks.
2:00 pm IMCO batched another 1 CY of concrete. I tested it and everything was in spec. See attached report. They
poured the 6" drain pipe encasement.
4:00 pm IMCO is working on forming for the 12" pipe encasement of the spray bars. This will also include a
section of the 4" hydrant line. The crew also worked on putting the crane together.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1505 of 1851
References
Photos (2)
20230410_120021
Taken on Apr 10, 2023, 12:00 PM MDT
Added on Apr 11, 2023, 10:00 AM MDT
Added by Chris Johnson
20230410_151739
Taken on Apr 10, 2023, 3:17 PM MDT
Added on Apr 11, 2023, 10:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1506 of 1851
Form detail
#126: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 Place concrete
encasement for 4" hydrant line,
form 6" drain line
IMCO, Operators and Labors 6 60 Area 30 Form for 4" hydrant line,
Set 4" hydrant line place concrete
for 4" hydrant line encasement.
Demo area 10 raceways / chinook
raceways Export broken concrete,
compact and proof roll
Totals 7 70
Forms
Location
Form date Apr 6, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 6, 2023, 4:52 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1507 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 raceway demo, Area 30
Batch Concrete
Deere 644J Loader 1 10 Area 10 Backfill and proof roll
abandoned raceways
IMCO Concrete Truck 1 3 Area 30 pipe encasement
placement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 10 Set up crane
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Area 30 install 4" hydrant line, aid
with placing concrete for 4" pipe
encasement
Dump Truck 1 10 Area 10 haul concrete debris
offsite
Kobelco 1100G Crane 1 0 Mobilized on site
Deer 470 Excavator 1 0 Mobilized to site
4. Signature
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1508 of 1851
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is IMCO Batch Ticket and Concrete Field Report.
8:00 am IMCO is working on setting the 4" hydrant line. They have used restraint mechanical joints with C900 pipe
to connect to the ductile iron T. The vertical pipe out of the ductile iron tee is a flange to stainless steel stand pipe
that will penetrate the slab floor. Kirt needs to block out a section of this pour to accommodate for the 12" pipe to
raceway spray bars.
9:00 am I asked the IMCO crew to proof roll the second lift of native material at the abandoned raceways. I watch
the rubber tire loader with a bucket of material drive over the lift. The lift was firm and unyielding.
11:00 am IMCO is prepping to batch 3 CY of concrete for the 4" hydrant line encasement placement.
1:00 pm IMCO has placed 3 CY. See attached concrete field report.
2:00 pm IMCO is starting to work on the 6" drain line. They are hoping to pour this one today as well.
3:30 pm Manhole #1 has been delivered onsite.
4:30 pm Jake informed me they will not make the second placement today. The crew is working on grading for
the raceway spray bar pipe and demoing the chinook raceways.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1509 of 1851
References
Photos (6)
20230406_154352
Taken on Apr 6, 2023, 3:43 PM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
20230406_143542
Taken on Apr 6, 2023, 2:35 PM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1510 of 1851
20230406_142317
Taken on Apr 6, 2023, 2:23 PM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
20230406_141941
Taken on Apr 6, 2023, 2:19 PM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1511 of 1851
20230406_095059
Taken on Apr 6, 2023, 9:50 AM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
20230406_095037
Taken on Apr 6, 2023, 9:50 AM MDT
Added on Apr 6, 2023, 4:30 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1512 of 1851
Form detail
#125: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 Set and Form 4" hydrant
line, Strip 24" encasement forms
IMCO, Operators and Labors 6 60 Area 30 Remove 24" encasement
forms, Form for 4" hydrant line, Set
4" hydrant line. Demo area 10
raceways / chinook raceways
Export broken concrete, compact
and proof roll
Totals 7 70
Forms
Location
Form date Apr 5, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 6, 2023, 7:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1513 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Area 10 raceway demo
Deere 644J Loader 1 10 Area 10 Backfill and proof roll
abandoned raceways
IMCO Concrete Truck 1 0
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Area 30 excavate for 4" hydrant
line, Area 10 hoe pack native
material in 12" lifts
Dump Truck 1 10 Area 10 haul concrete debris
offsite
Kobelco 1100G Crane 1 0 Mobilized on site
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1514 of 1851
Notes
8:00 am IMCO is working on the 4" hydrant line. They were able to get it bolted together yesterday. They used an
dielectric isolation kit to bolt the ductile iron T to the stainless steel stand pipe that penetrates the slab floor.
10:00 am IMCO has the hammer attachment on the excavator and is currently working on breaking up the
abandoned raceways. They are loading the concrete debris in the dump truck and hauling offsite.
12:00 pm IMCO is working on backfilling the hole that was created from the abandoned raceways. I have asked
to meet the native backfill requirements of screening 8" and larger rocks out and compacting.
2:00 pm IMCO is continuing to work on installing and forming the 4" hydrant line and the rebar cage around it.
3:30 pm IMCO has placed one 12" lift at the abandoned raceways and compacted it with the hoepack. I asked to
proof roll the material. They used the rubber tire loader with a full bucket of material. I witnessed a firm and
unyielding proof roll. They are going to start working on the second lift.
References
Photos (5)
20230405_152631
Taken on Apr 5, 2023, 3:26 PM MDT
Added on Apr 5, 2023, 3:42 PM MDT
Added by Chris Johnson
20230405_151201
Taken on Apr 5, 2023, 3:12 PM MDT
Added on Apr 5, 2023, 3:42 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1515 of 1851
20230405_134100
Taken on Apr 5, 2023, 1:41 PM MDT
Added on Apr 5, 2023, 3:42 PM MDT
Added by Chris Johnson
20230405_133405
Taken on Apr 5, 2023, 1:34 PM MDT
Added on Apr 5, 2023, 3:42 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1516 of 1851
20230405_133353
Taken on Apr 5, 2023, 1:33 PM MDT
Added on Apr 5, 2023, 3:42 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1517 of 1851
Form detail
#124: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 Pour Pipe Encasement of
24" Discharge Pipe, help set 4"
hydrant line
IMCO, Operators and Labors 6 60 Area 30 Pour Pipe Encasement of
24" Discharge pipe, Excavate for 4"
hydrant line , Demo area 10
raceways / chinook raceways
Export broken concrete
Totals 7 70
Forms
Location
Form date Apr 4, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 4, 2023, 4:59 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1518 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Batch Concrete, Area 10 raceway
demo
Deere 644J Loader 1
IMCO Concrete Truck 1 5 Area 30, Pour pipe encasement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Area 30 excavate for 4" hydrant
line
Dump Truck 1 10 Area 10 haul concrete debris
offsite
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached Todays concrete placement field report and IMCO batch tickets.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1519 of 1851
7:30 am IMCO is prepping to pour the pipe encasement for the 24" discharge pipe. They need to complete the
forming and bracing and micro adjust the pipe.
9:30 am IMCO has the pipe and forms ready, they are batching concrete now.
12:30 pm IMCO has placed 9 CYs with 3 loads. I tested the first truck for air only. It was at 6.5%. I then tested the
second truck for acceptance. Air was at 7%. See attached concrete field report. They had to batch a third load to
finish the placement.
2:00 pm Attended weekly meeting.
3:00 pm One IMCO crew is working on Area 10 demo and export of concrete debris. The other has started to
excavate for the 4" hydrant line.
5:00 pm IMCO is finishing up for the day. The got the 4" line excavated and ready to set for tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1520 of 1851
References
Photos (5)
20230404_164109
Taken on Apr 4, 2023, 4:41 PM MDT
Added on Apr 4, 2023, 4:58 PM MDT
Added by Chris Johnson
20230404_130607
Taken on Apr 4, 2023, 1:06 PM MDT
Added on Apr 4, 2023, 4:58 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1521 of 1851
20230404_105418
Taken on Apr 4, 2023, 10:54 AM MDT
Added on Apr 4, 2023, 4:58 PM MDT
Added by Chris Johnson
20230404_164124
Taken on Apr 4, 2023, 4:41 PM MDT
Added on Apr 4, 2023, 4:58 PM MDT
Added by Chris Johnson
20230404_130557
Taken on Apr 4, 2023, 1:05 PM MDT
Added on Apr 4, 2023, 4:58 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1522 of 1851
Form detail
#123: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 Pour Pipe Encasement of 6
Raceway Pipes, brace forming for
24" discharge pipe encasement,
Micro adjust pipe
IMCO, Operators and Labors 6 60 Area 30 Pour Pipe Encasement of 6
Raceway pipes, Demo area 10
raceways / chinook raceways
Export broken concrete
Totals 7 70
Forms
Location
Form date Apr 3, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Apr 3, 2023, 4:52 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1523 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Batch Concrete, Area 10 raceway
demo
Deere 644J Loader 1
IMCO Concrete Truck 1 5 Area 30, Pour pipe encasement
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Area 10 Break and load concrete
debris
Dump Truck 1 10 Area 10 haul concrete debris
offsite
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached Todays concrete placement field report, IMCO batch tickets and 14 compressive breaks from the Trial
batch
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1524 of 1851
8:30 am Arrived on site. IMCO is prepping for the concrete placement for pipe encasement at Area 30. The pipe
encasement is for the 6 Raceway pipes.
9:30 am IMCO is getting ready to batch 4 CY. They are going to batch the rest on a second load.
11:30 am IMCO has batched 4 CY. I took a sample after approx. 1 CY was placed. The air tested at 3%. They dosed
the truck. They then poured out approx. 1/2 CY and I took a second sample. The air was at 6%. They proceeded to
pour and I proceeded with the testing. I casted 12 4x8 cylinders. See Field Report. A second crew is working on
demoing and hauling off concrete from Area 10 abandoned raceways. They are hauling the concrete debris to a
dump site.
2:00 pm IMCO has stated to break up the Chinook Raceways with the Excavator. Per previously discussed they
are taking care not to affect the water or power lines to the hatchery building.
4:30 pm IMCO is working on setting the 24" discharge pipe to grade. IMCO and I discussed RFI 53 that changed
the pipe invert and also changed its direction. We verified those changes were updated in IMCOs GPS model and
they are setting the pipe per the RFI.
4:45 pm IMCO informed me they plan to place concrete tomorrow. They are going to encase the 24" discharge
pipe.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1525 of 1851
References
Photos (7)
20230403_160605
Taken on Apr 3, 2023, 4:06 PM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
20230403_125830
Taken on Apr 3, 2023, 12:58 PM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1526 of 1851
20230403_125601
Taken on Apr 3, 2023, 12:56 PM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
20230403_111845
Taken on Apr 3, 2023, 11:18 AM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1527 of 1851
20230403_101719
Taken on Apr 3, 2023, 10:17 AM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
20230403_094733
Taken on Apr 3, 2023, 9:47 AM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1528 of 1851
20230403_094640
Taken on Apr 3, 2023, 9:46 AM MDT
Added on Apr 3, 2023, 4:43 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1529 of 1851
Form detail
#122: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 form for pipe encasement
pour of 6 12" raceway pipes, Form
encasements for 1 24" discharge
pipe
IMCO, Operators and Labors 6 60 Area 30 excavate for discharge
pipe, set grade for discharge pipe,
help with forms and setting pipe,
Demo area 10 with excavator
hammer attachement
Totals 7 70
Forms
Location
Form date Mar 30, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 30, 2023, 1:59 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1530 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 area 10 demo
Deere 644J Loader 1
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1
Dump Truck 1 0
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am IMCO informed me no pour today and they will not be working tomorrow. They are planning on pouring
the encasements on Monday morning. They are currently reinforcing the forms and micro adjusting the pipes and
bracing them off.
11:00 am Kirt is working with the crew to get the pipes set per plan and braced off so they will not move during
the pour.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1531 of 1851
12:00 pm The crew is continuing to work on bracing forms for the pour Monday. IMCO has installed the hammer
attachment to the excavator and is starting to demo the floor of the abandoned raceways. The slab looks to be
about 6" thick with wire mesh.
2:00 pm I noticed some rebar missing from the 24" discharge pipe. The crew added the bar needed and now it is
per the submitted plan. The are continuing to work on bracing forms and micro adjusting the 24" pipe per plan.
References
Photos (6)
20230330_132941
Taken on Mar 30, 2023, 1:29 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
20230330_132652
Taken on Mar 30, 2023, 1:26 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1532 of 1851
20230330_132553
Taken on Mar 30, 2023, 1:25 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
20230330_132541
Taken on Mar 30, 2023, 1:25 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1533 of 1851
20230330_132521
Taken on Mar 30, 2023, 1:25 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
20230330_132516
Taken on Mar 30, 2023, 1:25 PM MDT
Added on Mar 30, 2023, 1:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1534 of 1851
Form detail
#121: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 form for pipe encasement
pour of 6 12" raceway pipes, Form
encasements for 1 24" discharge
pipe
IMCO, Operators and Labors 6 60 Area 30 excavate for discharge
pipe, set grade for discharge pipe,
help with forms and setting pipe
EOI 2 8 Tie Rebar for Pipe Encasements, 6
12" Raceway pipes, 1 24" discharge
pipe
Forms
Location
Form date Mar 29, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 30, 2023, 9:49 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1535 of 1851
Crew # Workers # Total
hours
Work performed
Totals 9 78
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Area 30
Deere 644J Loader 1 10 Excavate for Area 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Set new office Trailer
Dump Truck 1 0
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1536 of 1851
Notes
8:00 am IMCO is planning to set the 24" discharge pipe today. EOI is onsite to tie the rebar around the pipe
encasements.
10:00 am IMCO is working on verifying the dimensions of the batter board strings. I asked if Cole, IMCO, could
verify the corners with the GPS.
11:30 am IMCO has the strings correct and square. They are going to continue working on the 24" discharge
pipe.
2:30 pm EOI has tied the rebar for the raceway pipes. IMCO is wanting to pour this tomorrow. I checked the rebar
and all looks good and ready to pour. They need to close up the forms and brace it off. They are setting the 24"
discharge pipe now.
4:30 pm IMCO is working on setting up the new office trailer. They are also getting the 24" discharge pipe to
grade and building the forms around it. EOI has tired the rebar for it and has left the site. They also pre tied the bar
for the 6" line.
5:30 pm IMCO is done for the day. They are still hoping to pour concrete tomorrow but they will make the final
call tomorrow morning.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1537 of 1851
References
Photos (4)
20230329_172858
Taken on Mar 29, 2023, 5:28 PM MDT
Added on Mar 30, 2023, 9:48 AM MDT
Added by Chris Johnson
20230329_172840
Taken on Mar 29, 2023, 5:28 PM MDT
Added on Mar 30, 2023, 9:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1538 of 1851
20230329_172912
Taken on Mar 29, 2023, 5:29 PM MDT
Added on Mar 30, 2023, 9:48 AM MDT
Added by Chris Johnson
20230329_172829
Taken on Mar 29, 2023, 5:28 PM MDT
Added on Mar 30, 2023, 9:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1539 of 1851
Form detail
#120: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 Area 30 form for pipe encasement
pour of 6 raceway pipes
IMCO, Operators and Labors 6 60 Area 30 excavate for discharge
pipe, set grade for discharge pipe,
help with forms and setting pipe
Totals 7 70
2. Materials
Forms
Location
Form date Mar 28, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 29, 2023, 7:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1540 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Area 30
Deere 644J Loader 1 10 Excavate for Area 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 area 10 demo abandoned raceway
demo, hoe pack native and general
fill for area 30
Dump Truck 1 0
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is going to continue to work on Area 30 pipe encasements. They also have a crew working on Area
10 demo. They are breaking up the abandoned raceways behind the hatchery building.
12:00 pm Area 30 they are working on excavating and grading for the 24" discharge pipe. The demo crew is
continuing to work on the abandoned raceways.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1541 of 1851
2:00 pm Attended weekly meeting.
3:00 pm Sam, IPC, has been onsite locating the power feeds to the hatchery building. He is unable to find the
water line since there is no way to locate it. He has cut power to the chinook raceways to allow IMCO to start
demoing it. He has located the power near the raceway. IMCO will need to stay away from the end of the raceway
near pump 2, which Kirt had planned to do anyways until the hatchery operations was complete for the year. Jeff
estimates this to be around the second week of May.
5:00 pm The crew has hoe packed the native material under the discharge pipe. They placed approximately 6" of
general fill over the native. I took a compaction shot on this lift. The numbers looked good. I took a sample of the
material and determined that it had approx. 32% retained on the 3/4 sieve. This is considered to course for testing.
The material is firm and compacted well.
5:30 pm IMCO is done and plans to set the 24" discharge pipe tomorrow.
References
Photos (4)
20230328_151547
Taken on Mar 28, 2023, 3:15 PM MDT
Added on Mar 29, 2023, 7:22 AM MDT
Added by Chris Johnson
20230328_151517
Taken on Mar 28, 2023, 3:15 PM MDT
Added on Mar 29, 2023, 7:22 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1542 of 1851
20230328_151539
Taken on Mar 28, 2023, 3:15 PM MDT
Added on Mar 29, 2023, 7:22 AM MDT
Added by Chris Johnson
20230328_151504
Taken on Mar 28, 2023, 3:15 PM MDT
Added on Mar 29, 2023, 7:22 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1543 of 1851
Form detail
#119: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 1 10 set up batter boards for area 30,
set concrete forms for raceway
pipe encasements
IMCO, Operators and Labors 6 60
Totals 7 70
2. Materials
Forms
Location
Form date Mar 27, 2023
Description Area 10, Area 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 28, 2023, 9:24 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1544 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Area 30
Deere 644J Loader 1 10 Excavate for Area 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 5 set raceway pipes
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 silt fence for Area 10
Dump Truck 1 0
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached is 7 Day Compressive Strength Report from the Trial Batching. The average of 3 cylinders is 3480 psi.
10:00 am Arrived on site. IMCO is working on area 30 and area 10. The crew working on Area 10 is installing silt
fence to the limits of the walkway up the intake structure. The crew working on area 30 is pulling strings from the
batter boards. They are checking to make sure it is square and right.
11:30 am IMCO has started working on setting the forms for the 6 raceway pipes.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1545 of 1851
1:00 pm IMCO and I have worked together to set the forms per the plans. We noticed a large change in the floor
slab for the 7th pipe, for the raceway sprinklers. The pipe required a thickened slab with extra reinforcement. This
was noticed on the rebar submittal #59 Aeration Tower Rebar Drawings. Kurt is having to rethink how he will form
and pour this.
3:00 pm IMCO is continuing to work on the 6 raceway pipe encasements. They are going to pour the 5
northwestern pipes in one pour, then the 6th and 7th pipes will be in the slab pour.
4:30 pm I have been double checking the dimensions of the pipes in reference to IMCO supplied hubs for
elevation, and IMCO supplied batter boards and string lines. All is looking per plan.
References
Photos (4)
20230327_140040
Taken on Mar 27, 2023, 2:00 PM MDT
Added on Mar 28, 2023, 8:19 AM MDT
Added by Chris Johnson
20230327_114316
Taken on Mar 27, 2023, 11:43 AM MDT
Added on Mar 28, 2023, 8:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1546 of 1851
20230327_162405
Taken on Mar 27, 2023, 4:24 PM MDT
Added on Mar 28, 2023, 8:19 AM MDT
Added by Chris Johnson
20230327_140050
Taken on Mar 27, 2023, 2:00 PM MDT
Added on Mar 28, 2023, 8:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1547 of 1851
Form detail
#118: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 20 Concrete Forms, set batter boards
for area 30
IMCO, Operators and Labors 6 60 Excavate area 30 Piping, Demo
area 10 Concrete
Totals 8 80
2. Materials
Forms
Location
Form date Mar 23, 2023
Description Area 10 Demo, Area 30 excavation
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 23, 2023, 1:05 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1548 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Area 30
Deere 644J Loader 1 10 Excavate for Area 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 0
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Demo for Area 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crews are going to continue working on area 30 and area 10 today. Kirt plans on having the area
30 batter boards set and start checking measurements. He would like to have the pipe encasement forms up for
the 7 raceway pipes.
10:00 am IMCO has placed some general fill to fine grade under the pipe encasements for the 7 raceway pipes.
They are compacting it with a plate compactor. After a few passes I shot it with my nuke gauge to check. The
number seemed low compared to the 3 proctors I have on the material. The moisture was also low compared to
the 3 proctors I have. I took a sample of the material under my gauge. I sieved that material out over the 3/4 sieve
here onsite. I calculated 36% retained. Per ASTM D6938 any material over 30% cannot be tested with a nuclear
gauge. This material will need to be documented by compaction effort. The crew continued to compact it with a
plate compactor and they added water.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1549 of 1851
11:30 am I have taken a second shot on the material to document compaction effort. The numbers have gone up.
I have taken a sample of the shot once again and I will take this sample back to the lab to sieve out over the 3/4.
IMCO is done for the day. They have discovered an issue with their GPS or an issue with the coordinates on the
plans. Jake is working on submitting an RFI to the Engineer.
1:00 pm Left site.
References
Photos (1)
20230323_094628
Taken on Mar 23, 2023, 9:46 AM MDT
Added on Mar 23, 2023, 1:03 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1550 of 1851
Form detail
#117: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 20 Concrete Forms
IMCO, Operators and Labors 6 60 Excavate Fac. 30 Piping, Demo Fac.
10 Concrete
Totals 8 80
2. Materials
Forms
Location
Form date Mar 22, 2023
Description Facility 10, Facility 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 23, 2023, 11:19 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1551 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Fac. 30
Deere 644J Loader 1 10 Excavate for Fac. 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 0
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Demo for Fac. 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crew is going to continue to excavate for the Fac. 30 piping. They are going to continue to
stockpile the native material onsite to be used as fill later. They are also going to continue to work on exposing the
abandoned raceways behind the hatchery building so they can demo the concrete.
11:00 am Ryan and I drove over to the stockpile material site on the other side of the river. Ryan took a sample of
the structural fill material. They are going to drop the material off to have the electrical resistivity and pH of the soil
tested to determine its potential corrosivity. Jake informed me that Allwest will be performing this work. The IMCO
crews are continuing to work on excavation and demo work.
2:00 pm The Fac. 10 IMCO crew is switching gears and working on removing the rest of the chain link fence along
the Snake river so they can finish the silt fence per John Andersons comments.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1552 of 1851
4:30 pm IMCO crews are cleaning up for the day. Some of the required silt fence got installed.
References
Photos (5)
20230322_162252
Taken on Mar 22, 2023, 4:22 PM MDT
Added on Mar 23, 2023, 11:18 AM MDT
Added by Chris Johnson
20230322_152938
Taken on Mar 22, 2023, 3:29 PM MDT
Added on Mar 23, 2023, 11:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1553 of 1851
20230322_115429
Taken on Mar 22, 2023, 11:54 AM MDT
Added on Mar 23, 2023, 11:18 AM MDT
Added by Chris Johnson
20230322_115236
Taken on Mar 22, 2023, 11:52 AM MDT
Added on Mar 23, 2023, 11:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1554 of 1851
20230322_115219
Taken on Mar 22, 2023, 11:52 AM MDT
Added on Mar 23, 2023, 11:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1555 of 1851
Form detail
#114: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 20 Concrete Forms
IMCO, Operators and Labors 6 60 Excavate Fac. 30 Piping, Demo Fac.
10 Concrete
Totals 8 80
2. Materials
Forms
Location
Form date Mar 21, 2023
Description Facility 10, Facility 30
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 21, 2023, 4:51 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1556 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 10 Excavate for Fac. 30
Deere 644J Loader 1 10 Excavate for Fac. 30
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 0
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10 Demo for Fac. 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to excavate for Fac. 30 piping. They are setting up the laser for grade. They are going to
store the native spoils onsite for now with the intent to use onsite for fill. They are also working on building forms
for building foundations. Another crew is working on excavating and demoing concrete near the hatchery building.
10:30 am I was notified that IMCO has found some buried wires while excavating for Fac. 30 discharge pipe. One
wire is cut and has been cut for awhile. The crew stopped excavating until it gets figured out.
11:30 am Itsy and Caleb are onsite working on confirming the wire and its purpose. The crew is going to start
working on excavating for other pipes at Fac. 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1557 of 1851
1:00 pm It was determined that the wire that was damaged is dead and is unknow, IPC was able to determine
that there are live wires that feed the crowders are in the same vicinity. IMCO crew has agreed to proceed
carefully.
1:30 pm IMCO crew quickly found the second set of wires and IPC was able to determine they are live and in use
for the crowders. IMCO will have to work around these wires to keep the hatchery operational.
2:00 pm Attended weekly meeting.
3:00 pm Kurt has informed me both excavation crews have found wires and or conduit that is not marked or
shown. One wire and one conduit was found while excavating for the piping at Fac. 30. Another was found while
demoing the abandoned raceways behind the hatchery building. I informed Kurt that Sam will not be able to locate
anything until Monday of next week so Kurt is having his crews work on other areas until Sam is available.
4:30 pm The crews were able to continue working on excavation and demoing. Kurt has a truck coming at the
end of the week to load out concrete so he is trying to get enough demo concrete for a full load.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1558 of 1851
References
Photos (5)
20230321_111157
Taken on Mar 21, 2023, 11:11 AM MDT
Added on Mar 21, 2023, 4:41 PM MDT
Added by Chris Johnson
20230321_161043
Taken on Mar 21, 2023, 4:10 PM MDT
Added on Mar 21, 2023, 4:41 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1559 of 1851
20230321_152314
Taken on Mar 21, 2023, 3:23 PM MDT
Added on Mar 21, 2023, 4:41 PM MDT
Added by Chris Johnson
20230321_150432
Taken on Mar 21, 2023, 3:04 PM MDT
Added on Mar 21, 2023, 4:41 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1560 of 1851
20230321_150356
Taken on Mar 21, 2023, 3:03 PM MDT
Added on Mar 21, 2023, 4:41 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1561 of 1851
Form detail
#113: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, Carpenters 2 20 Concrete Forms, Pour Concrete
IMCO, Operators and Labors 6 60 Help with Trail Batching, install
BMPs, Pour Concrete
Totals 8 80
2. Materials
Forms
Location
Form date Mar 20, 2023
Description Facility 10, Facility 30, Trail Batching
Due date
Submitted by Chris Johnson
Status Closed
Last update Mar 21, 2023, 4:14 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1562 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Deere 210 Excavator 1 0
Deere 644J Loader 1 0
IMCO Concrete Truck 1 5
IMCO Concrete Truck 1 0
JCB 510 Boom Forklift 1 0
JCB 510 Boom Forklift 1 0
Hitachi 85 Excavator 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:00 am Arrived on site. I set up for the concrete trial batching pour. IMCO is going to use the trial batching
concrete for eco blocks. They plan to make 3 CY at a time.
10:00 am Connect Engineering is onsite to perform concrete testing on behalf of IMCO.
11:00 am IMCO has produced the first batch. Connect and I both sampled. We both tested air and slump. Air was
at 5.0 for both of us and slump was at 8.5 which is out of spec. IMCO decided to make another batch so I did not
cast cylinders for the first pour. Connect decided to cast cylinders to see how strong the concrete would be at 8"
slump.
12:00 pm IMCO has batched another 3 CY and I sampled and tested the mix. See concrete test report. The slump
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1563 of 1851
and air was in so I casted 12 4x8 cylinders. I plan to have our lab break cylinders at 7, 14, 21 and 28 days.
3:00 pm IMCO is working on cleaning the site and setting up to start excavating for facility 30.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1564 of 1851
Form detail
#111: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Dec 5, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Dec 5, 2022, 8:53 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1565 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
56 day compressive report for the platform pour on 10/5/22.
The 28 Day breaks were under the spec of 4000 psi. The 3 holds were used to break and verify at 56 days. They are
within spec.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1566 of 1851
Form detail
#109: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Nov 21, 2022
Description Facility 20, Hatchery Intake, 28 day compressive strength
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 21, 2022, 9:42 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1567 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Attached are the 28 day compressive day reports on the walkway and platform concrete pours.
The platform pour compressive strength average was 3910 PSI. This is 98% of the 4000 PSI required. We will break
the 3 holds at 56 days to verify they meet the 4000 PSI requirement.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1568 of 1851
Form detail
#108: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Install Security Gate
Sawtooth Welding 1 8 Cut handrail, reinstall around
security gate
Totals 3 18
2. Materials
Forms
Location
Form date Nov 16, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Nov 21, 2022, 9:28 AM MST
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1569 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:30 am Arrived on site. Jake, IMCO, informed me they were going to be setting the security gate today. Sawtooth
is onsite cutting the handrail to allow the gate to be installed on the walkway.
11:00 am Sawtooth has the wrong 90 bends to weld to the handrail. He brought 1 1/4" but the hand rail is 1 1/2".
Sawtooth is sending someone out with the proper 90 bends.
2:30 pm Sawtooth is still working on welding the handrail together. Jake informed me instead of me waiting he
would send me a photo of the final product install. We went over the dimensions of the install and I left the site.
5:00 pm I spoke to Jake after he sent me a photo of the final install. He said he was not able to get all the anchors
in to secure the plates to the concrete. They ran into issues with the outriggers being in the way. He plans to
discuss this with Bill.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1570 of 1851
References
Photos (4)
20221116_142050.jpg
Taken on Nov 16, 2022, 2:20 PM MST
Added on Nov 21, 2022, 9:27 AM MST
Added by Chris Johnson
20221116_094727.jpg
Taken on Nov 16, 2022, 9:47 AM MST
Added on Nov 21, 2022, 9:27 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1571 of 1851
Resized_20221116_144658.jpeg
Added on Nov 21, 2022, 9:28 AM MST
Added by Chris Johnson
Resized_20221116_144704.jpeg
Added on Nov 21, 2022, 9:28 AM MST
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1572 of 1851
Form detail
#107: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 install irrigation line, clean up site,
install roof on posts
Totals 3 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Oct 25, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 26, 2022, 8:41 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1573 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on installing the roof on the posts. They are prepping to fly it in.
9:30 am IMCO has installed the roof on the posts and are bolting it on. A couple of the bolts are not lining up.
They will need to drill them out.
12:00 pm IMCO is working on cleaning up the site.
2:00 pm Attended weekly meeting. Jake is still waiting on a design for the gate to prevent access to the structure.
3:00 pm IMCO is pulling the silt curtain out of the river.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1574 of 1851
References
Photos (4)
20221025_085753.jpg
Taken on Oct 25, 2022, 8:57 AM MDT
Added on Oct 25, 2022, 2:20 PM MDT
Added by Chris Johnson
20221025_124240.jpg
Taken on Oct 25, 2022, 12:42 PM MDT
Added on Oct 25, 2022, 2:20 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1575 of 1851
20221025_124303.jpg
Taken on Oct 25, 2022, 12:43 PM MDT
Added on Oct 25, 2022, 2:20 PM MDT
Added by Chris Johnson
20221025_124611.jpg
Taken on Oct 25, 2022, 12:46 PM MDT
Added on Oct 25, 2022, 2:21 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1576 of 1851
Form detail
#106: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 install irrigation line, install roof
posts, load pile hammer, clean up
site
MB Welding 1 10 modify roof posts
Totals 4 20
2. Materials
Forms
Location
Form date Oct 24, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 25, 2022, 1:13 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1577 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
3:00 pm IMCO is working on the roof posts. The post foot plate are not welded on correctly. MB Welding is
cutting and re welding the plate on the correct direction. They are also working on cleaning up the site and
preparing for the winter shut down.
5:00 pm The crew has installed all 4 posts for the roof.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1578 of 1851
Form detail
#105: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Weld last beam, install irrigation
line
MB Welding 1 10 weld last support beam
Totals 4 20
2. Materials
Forms
Location
Form date Oct 20, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 24, 2022, 3:02 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1579 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is working on installing the irrigation line. They will finish the core drill for the penetration
through the slab. They are waiting on another core bit.
12:00 pm IMCO is going to set the roof next week. They are waiting on a crane operator availability.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1580 of 1851
References
Photos (1)
20221020_093829.jpg
Taken on Oct 20, 2022, 9:38 AM MDT
Added on Oct 24, 2022, 3:01 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1581 of 1851
Form detail
#104: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Irrigation pump install, Remove
temp piles, fly last beam to be
welded
MB Welding 1 10 dismantling crane pad, weld last
support beam
Vale Electric, Electricians 2 8 wire and turn on irrigation pump
Totals 8 28
Forms
Location
Form date Oct 19, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 20, 2022, 8:50 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1582 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is prepping a level crane pad to being removing the temp piles.
11:00 am IMCO is setup and is starting to remove the temp piles.
2:00 pm The temp piles have been removed. They have set the irrigation pump and Vale is onsite to wire it in.
3:30 pm After switching the wires Vale has confirmed the pump is spinning the correct way.
5:00 pm IMCO and MB have place the last support now that the piles are out of the way.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1583 of 1851
References
Photos (6)
20221019_155435.jpg
Taken on Oct 19, 2022, 3:54 PM MDT
Added on Oct 20, 2022, 8:48 AM MDT
Added by Chris Johnson
20221019_111832.jpg
Taken on Oct 19, 2022, 11:18 AM MDT
Added on Oct 20, 2022, 8:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1584 of 1851
20221019_120022.jpg
Taken on Oct 19, 2022, 12:00 PM MDT
Added on Oct 20, 2022, 8:47 AM MDT
Added by Chris Johnson
20221019_130700.jpg
Taken on Oct 19, 2022, 1:07 PM MDT
Added on Oct 20, 2022, 8:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1585 of 1851
20221019_134310.jpg
Taken on Oct 19, 2022, 1:43 PM MDT
Added on Oct 20, 2022, 8:48 AM MDT
Added by Chris Johnson
20221019_152841_video
Taken on Oct 19, 2022, 9:28 PM MDT
Added on Oct 20, 2022, 8:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1586 of 1851
Form detail
#103: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 temp renovations for Jeff, remove
crane pad, place rip rap, prepare
irrigation pump
MB Welding 1 10 dismantling crane pad
Totals 6 20
2. Materials
Forms
Location
Form date Oct 18, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 20, 2022, 8:27 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1587 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO plans to remove the rest of the crane pad today. The hammer is scheduled to be onsite today to
remove the piles. They might get to it today or tomorrow.
11:00 am Kirt has removed most of the crane pad and backfilled and placed rip rap along the shore. Sam, IPC,
was onsite and turned the pump on. The ponds are filling up and plan to keep the pump running for rest of the
season.
2:00 pm Attended weekly meeting. The pile hammer is onsite to remove the temp piles. They will perform this
work tomorrow.
5:00 pm Motor Works has put together the column, motor, pump and shroud for the irrigation can. They plan to
set this tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1588 of 1851
References
Photos (8)
20221018_144657.jpg
Taken on Oct 18, 2022, 2:46 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
20221018_123619.jpg
Taken on Oct 18, 2022, 12:36 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1589 of 1851
20221018_123631.jpg
Taken on Oct 18, 2022, 12:36 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
20221018_150452.jpg
Taken on Oct 18, 2022, 3:04 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1590 of 1851
20221018_085955.jpg
Taken on Oct 18, 2022, 8:59 AM MDT
Added on Oct 19, 2022, 9:14 AM MDT
Added by Chris Johnson
20221018_105250.jpg
Taken on Oct 18, 2022, 10:52 AM MDT
Added on Oct 19, 2022, 9:14 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1591 of 1851
20221018_123647.jpg
Taken on Oct 18, 2022, 12:36 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
20221018_144650.jpg
Taken on Oct 18, 2022, 2:46 PM MDT
Added on Oct 19, 2022, 9:15 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1592 of 1851
Form detail
#102: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Install pond transducer, temp
renovations for Jeff, being
dismantling crane pad
Vale Electric, Electricians 3 8 work on pump panels, installing
switch
MB Welding 1 10 dismantling crane pad
Totals 7 28
Forms
Location
Form date Oct 17, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 19, 2022, 9:07 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1593 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
12:00 pm IMCO is working on the transducer for the ponds. Vale has wired it up and IMCO is installing it in the
pond with the direction of Jeff.
Attached is the grout cube breaks for the 48 hour
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1594 of 1851
References
Photos (1)
20221017_152142.jpg
Taken on Oct 17, 2022, 3:21 PM MDT
Added on Oct 19, 2022, 9:06 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1595 of 1851
Form detail
#101: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Work on pond renovations for Jeff
Vale Electric, Electricians 3 8 Run pumps for start up
Totals 5 18
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Oct 13, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 18, 2022, 9:33 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1596 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Vale is onsite to check the motors before running them and testing.
12:00 pm Bill, Kelby and CH Spencer have been onsite working on running the pumps and testing.
Attached is the grout cube breaks for the 48 hour
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1597 of 1851
References
Photos (2)
20221013_085827.jpg
Taken on Oct 13, 2022, 8:58 AM MDT
Added on Oct 18, 2022, 9:32 AM MDT
Added by Chris Johnson
20221013_085837.jpg
Taken on Oct 13, 2022, 8:58 AM MDT
Added on Oct 18, 2022, 9:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1598 of 1851
Form detail
#100: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Grout pump can base, clean up
around platform and walkway,
install airvac piping,
MB Welding 1 10 welding stilling well brackets, weld
nut for mud valve, clean up
Sawtooth Welding 2 8 Re drill kick plate holes, install
airburst line brackets
Forms
Location
Form date Oct 12, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 18, 2022, 9:29 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1599 of 1851
Crew # Workers # Total
hours
Work performed
Vale Electric, Electricians 5 8 land wires in motors, bump motors
for rotation
Totals 13 36
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Sawtooth is onsite to work on the kick plates and air bust line brackets. The kick plates need to be re
drilled because they pre drilled the holes for a 12" concrete deck instead of the walkway 6" deck.
9:00 am IMCO is working on grouting the pump can base that they did not have time to do yesterday.
12:00 pm MB Welding is working on welding various brackets for the stilling well and the mud valve.
3:00 pm Vale has landed the wires for the motors.
Attached is the grout cube breaks for the 24 hour
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1600 of 1851
References
Photos (2)
20221012_105953.jpg
Taken on Oct 12, 2022, 10:59 AM MDT
Added on Oct 18, 2022, 9:26 AM MDT
Added by Chris Johnson
20221012_110019.jpg
Taken on Oct 12, 2022, 11:00 AM MDT
Added on Oct 18, 2022, 9:26 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1601 of 1851
Form detail
#99: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Grout pump can base, clean up
around platform and walkway,
install airvac piping,
MB Welding 1 10 welding stilling well brackets, weld
nut for mud valve, clean up
Totals 6 20
2. Materials
Forms
Location
Form date Oct 11, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 12, 2022, 7:19 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1602 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on grouting the second pump can base. MB Welding is working on welding the brackets
for the stilling well and the level sensor.
12:00 pm Kirt, Jake and I met with Jeff to go over what all is need for the hatchery to operate this year. Kirt has a
plan to get water to the sorting room along with drains and pipe to get the fish to the far pond. IMCO is working
on cleaning the concrete and grease off the pieces under the walkway. They are also working on the piping for the
air vacs.
2:00 pm Attended meeting
3:00 pm IMCO is continuing to clean and double check bolts are tight.
Attached is the 24 hour grout cube compressive strength report.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1603 of 1851
References
Photos (5)
20221011_102303.jpg
Taken on Oct 11, 2022, 10:23 AM MDT
Added on Oct 12, 2022, 7:16 AM MDT
Added by Chris Johnson
20221011_132707.jpg
Taken on Oct 11, 2022, 1:27 PM MDT
Added on Oct 12, 2022, 7:16 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1604 of 1851
20221011_132712.jpg
Taken on Oct 11, 2022, 1:27 PM MDT
Added on Oct 12, 2022, 7:16 AM MDT
Added by Chris Johnson
20221011_132723.jpg
Taken on Oct 11, 2022, 1:27 PM MDT
Added on Oct 12, 2022, 7:16 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1605 of 1851
20221011_132745.jpg
Taken on Oct 11, 2022, 1:27 PM MDT
Added on Oct 12, 2022, 7:16 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1606 of 1851
Form detail
#98: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Grout pump can base, bolt up
valves help MB Welding
MB Welding 1 10 Weld Pipe Braces back on
Vale Electric, Electricians 5 8 Pull wire for pumps
Totals 11 28
Forms
Location
Form date Oct 10, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 11, 2022, 7:32 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1607 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
2:00 pm Arrived on site. The pumps have been installed and one motor is installed. The other motor is missing a
bushing that should be here tomorrow.
2:30 pm I noticed that the DMJ (Dismantling joints) on both heads did not have the restraint bolts installed. I
spoke to Jake and Kirt about this. They told me that both the 90 bend and the discharge head are restraint so the
bolts were not needed.
3:00 pm The crew is starting to mix grout for under the pump cans. They are mixing it in a bucket but the
consistency is dry packing. I have taken 6 cubes for compressive strength breaking.
4:30 pm The crew was not able to get to the other grout pad today. They will do it first thing tomorrow morning.
MB welding has been working on the pipe brackets under the walkway. Now that everything is solid and in place
he can weld the brackets back on. Vale Electric has been onsite. They are working on pulling wires and installing
boxes to power the pumps.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1608 of 1851
References
Photos (5)
20221010_135951.jpg
Taken on Oct 10, 2022, 1:59 PM MDT
Added on Oct 11, 2022, 7:30 AM MDT
Added by Chris Johnson
20221010_135958.jpg
Taken on Oct 10, 2022, 1:59 PM MDT
Added on Oct 11, 2022, 7:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1609 of 1851
20221010_140006.jpg
Taken on Oct 10, 2022, 2:00 PM MDT
Added on Oct 11, 2022, 7:30 AM MDT
Added by Chris Johnson
20221010_145339.jpg
Taken on Oct 10, 2022, 2:53 PM MDT
Added on Oct 11, 2022, 7:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1610 of 1851
20221010_154438.jpg
Taken on Oct 10, 2022, 3:44 PM MDT
Added on Oct 11, 2022, 7:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1611 of 1851
Form detail
#96: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Oct 8, 2022
Description Facility 20, Hatchery Intake, Compressive Strength Report
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 10, 2022, 3:20 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1612 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Compressive Strength Report for 3 day break on the Platform Concrete Pour
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1613 of 1851
Form detail
#95: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 6 10 Pour housekeeping pad, help
pump installers, store material in
connexs
Totals 6 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Oct 7, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 10, 2022, 2:21 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1614 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is onsite and getting ready for the concrete pour for the housekeeping pad.
8:00 am IMC concrete is onsite.
9:00 am I tested the truck when it arrived for air. The air was 3.2%. Jake dosed it with master air. I took a second
test and it was 5%. They are starting to pour.
9:30 am The crew has completed the pour and are now working on finishing it.
10:00 am The pump installers are onsite.
12:00 pm The pump installers are working on installing the pump columns in the pump cans now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1615 of 1851
References
Photos (4)
20221007_082501.jpg
Taken on Oct 7, 2022, 8:25 AM MDT
Added on Oct 10, 2022, 2:18 PM MDT
Added by Chris Johnson
20221007_112156.jpg
Taken on Oct 7, 2022, 11:21 AM MDT
Added on Oct 10, 2022, 2:19 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1616 of 1851
20221007_120747.jpg
Taken on Oct 7, 2022, 12:07 PM MDT
Added on Oct 10, 2022, 2:19 PM MDT
Added by Chris Johnson
20221007_115956.jpg
Taken on Oct 7, 2022, 11:59 AM MDT
Added on Oct 10, 2022, 2:19 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1617 of 1851
Form detail
#94: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 6 10 Clean up platfrom from concrete
pour, remove discharge heads for
pump install, form housekeeping
pad, grout temp pond for water
seal
Idaho Testing and Inspection 1 2 Inspect Welds
Totals 7 12
Forms
Location
Form date Oct 6, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 7, 2022, 7:22 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1618 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am Crew is onsite and starting to clean up after yesterdays pour.
8:00 am Idaho Testing and Inspection is onsite to perform the structural weld inspection on the welds for the
platform and walkway.
9:00 am IMCO has removed both discharge heads from the pump cans. This is so they can install the pumps
when the pump sub arrives.
10:00 am Jake informed me that the pump guys called and will not be here today. They plan to install the pumps
Friday and Saturday. The weld inspection is complete. He did not find any deficiencies.
12:00 pm IMC called and they had a cancelation for tomorrow. Jake and Kirt have ordered concrete for tomorrow
to pour the housekeeping pad. The pour is at 8am.
3:00 pm IMCO is working on forming the housekeeping pad along with pouring the grout in the seam to make a
watertight seal in the holding ponds.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1619 of 1851
References
Photos (6)
20221006_121946.jpg
Taken on Oct 6, 2022, 12:19 PM MDT
Added on Oct 7, 2022, 7:21 AM MDT
Added by Chris Johnson
20221006_121957.jpg
Taken on Oct 6, 2022, 12:19 PM MDT
Added on Oct 7, 2022, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1620 of 1851
20221006_094058.jpg
Taken on Oct 6, 2022, 9:40 AM MDT
Added on Oct 7, 2022, 7:20 AM MDT
Added by Chris Johnson
20221006_094107.jpg
Taken on Oct 6, 2022, 9:41 AM MDT
Added on Oct 7, 2022, 7:20 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1621 of 1851
20221006_121940.jpg
Taken on Oct 6, 2022, 12:19 PM MDT
Added on Oct 7, 2022, 7:20 AM MDT
Added by Chris Johnson
20221006_134118.jpg
Taken on Oct 6, 2022, 1:41 PM MDT
Added on Oct 7, 2022, 7:21 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1622 of 1851
Form detail
#92: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 7 10 Pour Platform Concrete
Totals 7 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Oct 5, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 6, 2022, 8:32 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1623 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is making the final preparation for the concrete pour.
9:30 am I have checked all the rebar again along with the penetrations and conduit. I believe everything is ready
for concrete.
10:00 am The pump truck and first truck are onsite. IMC QC is working on dosing the mud for air.
10:30 am I have tested the concrete. Air is in spec. Slump was high. I notified the QC.
11:00 am The second truck is poured out. The platform is full so the third truck is not needed. They are going to
use the third truck to pour the walls in the holding ponds. I have casted 3 extra cylinders for a field cure 3 day
break. They will cure on the walkway.
1:00 pm IMCO is continuing to work on finishing the concrete.
5:00 pm IMCO has opened up the hatches and has set them on the roof to check the fit. I have asked Jake and
Kirt if they are to be set at the 1/12 angle or sit level on the roof. They did not see anything in the plans regarding
sitting the hatches level. It did raise the question of the hatches are large enough to pull the discharge head out.
After checking dimensions it looks like it will fit.
Attached is the 7 day Compressive Field Report for the 9/28/22 walkway pour
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1624 of 1851
References
Photos (3)
20221005_110626.jpg
Taken on Oct 5, 2022, 11:06 AM MDT
Added on Oct 6, 2022, 8:32 AM MDT
Added by Chris Johnson
20221005_120828.jpg
Taken on Oct 5, 2022, 12:08 PM MDT
Added on Oct 6, 2022, 8:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1625 of 1851
20221005_111640.jpg
Taken on Oct 5, 2022, 11:16 AM MDT
Added on Oct 6, 2022, 8:32 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1626 of 1851
Form detail
#91: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Prep for concrete pour tomorrow.
MB Welding 1 10 roof welding
Vale Electric, Electricians 5 8 Raceway install, control room
install
EOI, Iron workers 3 10 Tie platform rebar
Totals 14 38
Forms
Location
Form date Oct 4, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 5, 2022, 12:36 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1627 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am MB Welding is onsite working on welding the picking eyes on the platform roof. IMCO is working on
sealing up the pan decking before the rebar guys arrive.
10:00 am EOI is onsite to install the rebar. I went over the approved submittal plans with them.
12:00 pm EOI has installed the bottom matt of the platform. After checking measurements, it is not possible to fit
all the rebar in vertically and provide the clearance for top and bottom to concrete. Jake has sent an email to Sarah
Dolin regarding moving the rebar trim bars around the penetrations to the bottom mat. This will gain 1.75” of
vertical clearance.
1:00 pm It has been approved to move the trim bars to the bottom mat only. EOI is continuing to tie the bar. Vale
is onsite running the conduit. They are running it in between the two mats. IMCO is working on forming a wall
pour in the holding ponds for the temp structure. They plan to pour this tomorrow.
4:30 pm EOI is done with the rebar. I have checked it and asked to make a couple corrections. The pumps are
onsite.
5:30 pm The rebar is ready for tomorrows pour.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1628 of 1851
References
Photos (12)
20221004_121623.jpg
Taken on Oct 4, 2022, 12:16 PM MDT
Added on Oct 5, 2022, 11:49 AM MDT
Added by Chris Johnson
20221004_145702.jpg
Taken on Oct 4, 2022, 2:57 PM MDT
Added on Oct 5, 2022, 12:02 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1629 of 1851
20221004_164418.jpg
Taken on Oct 4, 2022, 10:44 PM MDT
Added on Oct 5, 2022, 12:01 PM MDT
Added by Chris Johnson
20221004_164430.jpg
Taken on Oct 4, 2022, 4:44 PM MDT
Added on Oct 5, 2022, 12:04 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1630 of 1851
20221004_164442.jpg
Taken on Oct 4, 2022, 4:44 PM MDT
Added on Oct 5, 2022, 12:08 PM MDT
Added by Chris Johnson
20221004_164527.jpg
Taken on Oct 4, 2022, 4:45 PM MDT
Added on Oct 5, 2022, 12:13 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1631 of 1851
20221004_081202.jpg
Taken on Oct 4, 2022, 8:12 AM MDT
Added on Oct 5, 2022, 11:45 AM MDT
Added by Chris Johnson
20221004_121635.jpg
Taken on Oct 4, 2022, 12:16 PM MDT
Added on Oct 5, 2022, 11:52 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1632 of 1851
20221004_132145.jpg
Taken on Oct 4, 2022, 1:21 PM MDT
Added on Oct 5, 2022, 11:53 AM MDT
Added by Chris Johnson
20221004_145647.jpg
Taken on Oct 4, 2022, 2:56 PM MDT
Added on Oct 5, 2022, 11:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1633 of 1851
20221004_164448.jpg
Taken on Oct 4, 2022, 4:44 PM MDT
Added on Oct 5, 2022, 12:11 PM MDT
Added by Chris Johnson
20221004_164614.jpg
Taken on Oct 4, 2022, 4:46 PM MDT
Added on Oct 5, 2022, 12:15 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1634 of 1851
Form detail
#90: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Install discharge head, valves and
DMJ, Sawcut walkway control joints
MB Welding 1 10 roof welding
Vale Electric, Electricians 5 8 Raceway install, control room
install
Totals 10 28
Forms
Location
Form date Oct 3, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Oct 4, 2022, 8:45 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1635 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO is working on lining up the 90 bends to match the discharge heads. They are working on getting
the valve bolt holes to line up. MB Welding is welding the roof steel framing on along with the picking eyes that
were moved.
12:00 pm Kurt and I spoke about the picking eyes. He asked if he could leave them on. As previously spoke about
with Bill, the eyes will need to be removed because they are not galvanized.
2:00 pm Vale is working on running the conduit for the platform. Tomorrow the rebar guys will be onsite to tie
the bar for the platform. Vale will then tie their raceways to the bar to allow for proper clearance.
4:00 pm IMCO has installed the valves for the second discharge head. They are going to work on sawcutting the
walkway control joints now.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1636 of 1851
References
Photos (4)
20221003_122913.jpg
Taken on Oct 3, 2022, 12:29 PM MDT
Added on Oct 4, 2022, 8:29 AM MDT
Added by Chris Johnson
20221003_123446.jpg
Taken on Oct 3, 2022, 12:34 PM MDT
Added on Oct 4, 2022, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1637 of 1851
20221003_105051.jpg
Taken on Oct 3, 2022, 4:50 PM MDT
Added on Oct 4, 2022, 8:30 AM MDT
Added by Chris Johnson
20221003_104746.jpg
Taken on Oct 3, 2022, 10:47 AM MDT
Added on Oct 4, 2022, 8:30 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1638 of 1851
Form detail
#89: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 fuse temp pipe, clean up walkway
from pour
MB Welding 1 10 platform welding
Vale Electric, Electricians 5 8 Raceway install, control room
install
Totals 10 28
Forms
Location
Form date Sep 29, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 30, 2022, 9:44 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1639 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO and MB Welding are onsite. IMCO is going to continue working on fusing the HDPE pipe today. MB
is going to continue finishing welding the platform.
11:00 am Vale is onsite. They are installing conduit in the slab. They screwed it to the pandecking. I mentioned
that was not per spec. Jake and I reviewed pan decking details. There are some questions regarding the welding
schedule so Jake setup a meeting with Bryant and Sarah.
12:00 pm Attended meeting regarding the pandecking details. I also mentioned the raceway install in the slab.
Bryant agreed the conduit should be off the pandecking and tied to the rebar. They are going to get back to Jake
regarding the pandecking welding schedule.
3:00 pm IMCO has finished fusing the pipe and is working on installing it in the ground and bolting it to the
piping.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1640 of 1851
References
Photos (3)
20220929_134943.jpg
Taken on Sep 29, 2022, 1:49 PM MDT
Added on Sep 30, 2022, 9:44 AM MDT
Added by Chris Johnson
20220929_141638.jpg
Taken on Sep 29, 2022, 2:16 PM MDT
Added on Sep 30, 2022, 9:44 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1641 of 1851
20220929_142121.jpg
Taken on Sep 29, 2022, 2:21 PM MDT
Added on Sep 30, 2022, 9:44 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1642 of 1851
Form detail
#88: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 pour walkway, fuse temp pipe
MB Welding 1 10 Roof welding
Vale Electric, Electricians 5 8 Raceway install
Totals 10 28
2. Materials
Forms
Location
Form date Sep 28, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 29, 2022, 7:35 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1643 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am Concrete pump truck is onsite and setting up.
8:00 am Concrete truck is onsite. IMC also has a QC here. The mix code matches the approved mix design. The
QC is dosing the concrete with superplasticizer. He tested the air at 5%. He added 4 oz of master air. They are
going to start pouring.
8:30 am After the pump truck was primed I took my sample. Air was at 5.5%, they started pouring. I casted 9
cylinders. See attached test report.
9:30 am They have finished the pour and IMCO is working on finishing the concrete. IMCO is also continuing to
work on fusing the HDPE pipe.
11:00 am Vale is onsite to continue working on raceway install. The second discharge head is onsite. They plan to
install it tomorrow.
2:00 pm IMCO is continuing to work on fusing the HDPE pipe.
3:00 pm MB Welding is working on welding the last members of the roof structure.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1644 of 1851
References
Photos (5)
20220928_073811.jpg
Taken on Sep 28, 2022, 7:38 AM MDT
Added on Sep 29, 2022, 7:18 AM MDT
Added by Chris Johnson
20220928_073817.jpg
Taken on Sep 28, 2022, 7:38 AM MDT
Added on Sep 29, 2022, 7:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1645 of 1851
20220928_091844.jpg
Taken on Sep 28, 2022, 9:18 AM MDT
Added on Sep 29, 2022, 7:18 AM MDT
Added by Chris Johnson
20220928_140648.jpg
Taken on Sep 28, 2022, 2:06 PM MDT
Added on Sep 29, 2022, 7:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1646 of 1851
20220928_102712.jpg
Taken on Sep 28, 2022, 10:27 AM MDT
Added on Sep 29, 2022, 7:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1647 of 1851
Form detail
#87: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 sheet roof, fuse temp pipe
MB Welding 1 10 Temp structure for ponds
Vale Electric, Electricians 5 8 Raceway install
Totals 10 28
2. Materials
Forms
Location
Form date Sep 27, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 28, 2022, 10:24 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1648 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is still waiting on the discharge head to arrive. The HDPE fusion machine will be delivered soon so
they plan to start on that today.
10:00 am IMCO crew has started on sheeting the roof. They installed the blocking last week. Jake informed me
they will also install the metal roofing on the ground before they fly it in place.
12:00 pm IMCO is working on fusing the HDPE pipe.
3:00 pm Everything is ready for tomorrows concrete pour. IMCO is continuing to work on sheeting the roof and
welding the HDPE pipe.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1649 of 1851
References
Photos (6)
20220927_123032.jpg
Taken on Sep 27, 2022, 12:30 PM MDT
Added on Sep 28, 2022, 10:23 AM MDT
Added by Chris Johnson
20220927_142507.jpg
Taken on Sep 27, 2022, 2:25 PM MDT
Added on Sep 28, 2022, 10:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1650 of 1851
20220927_083830.jpg
Taken on Sep 27, 2022, 8:38 AM MDT
Added on Sep 28, 2022, 10:22 AM MDT
Added by Chris Johnson
20220927_123058.jpg
Taken on Sep 27, 2022, 12:30 PM MDT
Added on Sep 28, 2022, 10:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1651 of 1851
20220927_123105.jpg
Taken on Sep 27, 2022, 12:31 PM MDT
Added on Sep 28, 2022, 10:23 AM MDT
Added by Chris Johnson
20220927_153321.jpg
Taken on Sep 27, 2022, 3:33 PM MDT
Added on Sep 28, 2022, 10:23 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1652 of 1851
Form detail
#86: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 prep for temp pipe install, clean up
yard
MB Welding 1 10 Install nelson studs
Totals 3 20
2. Materials
Forms
Location
Form date Sep 26, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 27, 2022, 8:11 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1653 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO and MB Welding are onsite. IMCO is working on cleaning up the yard. Friday they worked on
excavating the trench for the temp pipe. They found the phone line and did not hit it. They did however find a cable
line and went through it. Sam is onsite taking a look. Sam has determined that it is just an abandoned cable.
2:00 pm MB Welding is continuing to work on the nelson studs for the platform. IMCO is cleaning up the area in
preparation for the concrete pour Wednesday.
4:00 pm IMCO is waiting on the discharge head to arrive. It was scheduled to be here today but has not shown up
yet. Over the weekend they tied the rebar for the walkway. I noticed it was laying on the decking with no clearance.
I notified Jake the rebar needed to be lifted up to approx. 1” from the top of concrete. He said they planed on it
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1654 of 1851
References
Photos (3)
20220926_134640.jpg
Taken on Sep 26, 2022, 1:46 PM MDT
Added on Sep 27, 2022, 8:00 AM MDT
Added by Chris Johnson
20220927_074926.jpg
Taken on Sep 27, 2022, 7:49 AM MDT
Added on Sep 27, 2022, 8:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1655 of 1851
20220927_075001.jpg
Taken on Sep 27, 2022, 7:49 AM MDT
Added on Sep 27, 2022, 8:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1656 of 1851
Form detail
#85: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 install mechanical piping
MB Welding 1 10 Install nelson studs
Totals 4 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Sep 22, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 27, 2022, 7:28 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1657 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is going to continue to work on bolting the piping to the 90s and discharge head. MB welding is
continuing to work on the nelson studs along the platform.
12:00 pm IMCO has installed the second 90 bend on the manifold. They are working on bolting them tight.
2:00 pm IMCO is continuing to work on bolting the valves to the 90s.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1658 of 1851
References
Photos (4)
20220922_132249.jpg
Taken on Sep 22, 2022, 1:22 PM MDT
Added on Sep 27, 2022, 7:28 AM MDT
Added by Chris Johnson
20220922_133355.jpg
Taken on Sep 22, 2022, 1:33 PM MDT
Added on Sep 27, 2022, 7:28 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1659 of 1851
20220922_081105.jpg
Taken on Sep 22, 2022, 8:11 AM MDT
Added on Sep 27, 2022, 7:27 AM MDT
Added by Chris Johnson
20220922_091131.jpg
Taken on Sep 22, 2022, 9:11 AM MDT
Added on Sep 27, 2022, 7:27 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1660 of 1851
Form detail
#84: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 prep 90 bends for coatings, coat
90s, install mechanical piping
MB Welding 1 10 Install nelson studs
Totals 4 20
2. Materials
Forms
Location
Form date Sep 21, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 22, 2022, 8:05 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1661 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO and MB are onsite working on the walkway. MB is continuing to weld the nelson studs to the
walkway beams.
9:00 am IMCO is working on prepping the 90s for coatings. They need to prep and recoat where the seep ring
was welded. The heat from the welding ruined the coatings near the ring.
10:00 am IMCO is working on installing the check valve, butterfly valve and the DMJ. These all bolt up between
the discharge head and the 90 bend. They are getting these installed to ensure the 90 bends line up correctly and
they can re attach the pipe supports under the walkway.
2:00 pm IMCO has coated the interior of the 90 bends where the heat from welding damaged them. They plan to
install the 90 once it is setup.
6:00 pm IMCO is done. They have installed the 90 on the manifold are braced it off. They will continue to the next
90 tomorrow and work on lining everything up.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1662 of 1851
References
Photos (3)
20220921_091806.jpg
Taken on Sep 21, 2022, 9:18 AM MDT
Added on Sep 22, 2022, 7:56 AM MDT
Added by Chris Johnson
20220921_145837.jpg
Taken on Sep 21, 2022, 2:58 PM MDT
Added on Sep 22, 2022, 7:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1663 of 1851
20220921_164220.jpg
Taken on Sep 21, 2022, 4:42 PM MDT
Added on Sep 22, 2022, 7:56 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1664 of 1851
Form detail
#83: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Framing, metal decking install,
prep 90 bends for coatings
MB Welding 1 10 Install nelson studs
Totals 4 20
2. Materials
Forms
Location
Form date Sep 20, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 21, 2022, 10:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1665 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am MB Welding plans on continuing to work on installing the nelson studs on the walkway.
9:00 am IMCO is working on cutting and placing the metal decking on the platform. They are going to cut out for
the 90 bends later. For now they want to get the decking up and in place.
12:00 pm IMCO and MB are continuing to work on the studs and metal decking.
1:30 pm IMCO has cut the final piece of the decking. The bearing surface is less than 1.5 inches. I notified Jake that
per the detail S 404 a flat plate needs to be added and welded to support the edge.
2:00 pm Attended meeting.
3:00 pm MB is continuing to work on the studs. IMCO is going to prep the 90 bends for coating.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1666 of 1851
References
Photos (3)
20220920_083610.jpg
Taken on Sep 20, 2022, 8:36 AM MDT
Added on Sep 21, 2022, 10:00 AM MDT
Added by Chris Johnson
20220920_083651.jpg
Taken on Sep 20, 2022, 8:36 AM MDT
Added on Sep 21, 2022, 10:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1667 of 1851
20220920_083616.jpg
Taken on Sep 20, 2022, 8:36 AM MDT
Added on Sep 21, 2022, 10:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1668 of 1851
Form detail
#82: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 8 Framing
MB Welding 1 10 Install nelson studs, 12" Channel
for concrete pour
Totals 3 18
2. Materials
Forms
Location
Form date Sep 19, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 20, 2022, 10:33 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1669 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:30 am IMCO and MB Welding are onsite. IMCO is working on framing the roof and hatches while MB is
working on the supports for the platform concrete pour. One of the discharge heads has arrived.
12:00 pm IMCO is continuing to work on the roof framing. I have sent Bryant a message regarding the roof
blocking but have not heard back yet.
3:00 pm MB Welding is continuing to work on the 12” c channel for the concrete pour.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1670 of 1851
References
Photos (5)
20220919_103813.jpg
Taken on Sep 19, 2022, 10:38 AM MDT
Added on Sep 20, 2022, 9:40 AM MDT
Added by Chris Johnson
20220919_103829.jpg
Taken on Sep 19, 2022, 10:38 AM MDT
Added on Sep 20, 2022, 9:41 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1671 of 1851
20220919_103923.jpg
Taken on Sep 19, 2022, 10:39 AM MDT
Added on Sep 20, 2022, 9:41 AM MDT
Added by Chris Johnson
20220919_103837.jpg
Taken on Sep 19, 2022, 10:38 AM MDT
Added on Sep 20, 2022, 9:41 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1672 of 1851
20220919_125657.jpg
Taken on Sep 19, 2022, 12:56 PM MDT
Added on Sep 20, 2022, 9:41 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1673 of 1851
Form detail
#81: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 8 Framing and layout
MB Welding 1 10 Install nelson studs, weld seepage
ring on 90
Totals 3 18
2. Materials
Forms
Location
Form date Sep 15, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 16, 2022, 7:44 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1674 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am MB Welding is starting to work on the nelson studs and puddle welds for the walkway decking. He is able
to blow a hole though the decking then weld the stud the metal beam then puddle weld around the stud to lock in
the metal decking.
9:00 am IMCO has been helping MB layout the studs. They are now going to work on the roof framing.
12:00 pm IMCO is continuing to work on the roof framing, MB is continuing on the studs.
4:00 pm IMCO is done for the day but MB is going to work on welding the seepage ring on the 90 bends.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1675 of 1851
References
Photos (4)
20220915_150245.jpg
Taken on Sep 15, 2022, 3:02 PM MDT
Added on Sep 15, 2022, 3:37 PM MDT
Added by Chris Johnson
20220915_115838.jpg
Taken on Sep 15, 2022, 11:58 AM MDT
Added on Sep 15, 2022, 3:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1676 of 1851
20220915_150237.jpg
Taken on Sep 15, 2022, 3:02 PM MDT
Added on Sep 15, 2022, 3:37 PM MDT
Added by Chris Johnson
20220915_150851.jpg
Taken on Sep 15, 2022, 3:08 PM MDT
Added on Sep 15, 2022, 3:37 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1677 of 1851
Form detail
#80: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Help MB Welding, check
measurements to pump can
MB Welding 1 10 Weld pile bracing, Weld Pile Caps,
remove pump clamps
Totals 3 20
2. Materials
Forms
Location
Form date Sep 13, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 15, 2022, 7:48 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1678 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am MB welding and IMCO are onsite. MB is going to continue working on welding on the platform.
11:00 am MB Welding has removed the pipe clamps under the walkway. Once they have the discharge head in
place they can accurately adjust the elevation of the pipe clamps to support the pipe. MB will reweld it once that
has been determined.
1:00 pm Kirt has talked to me about using grout to seal the bottom of the temp structure in the fish ponds. I have
taken photos for the meeting.
2:00 pm Attended weekly meeting.
4:00 pm Kirt and I have gone over the nelson stud layout for the metal decking. MB and IMCO are working on the
irrigation pump can stiffeners for the metal decking.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1679 of 1851
References
Photos (2)
20220913_131928.jpg
Taken on Sep 13, 2022, 1:19 PM MDT
Added on Sep 15, 2022, 7:48 AM MDT
Added by Chris Johnson
20220913_113401.jpg
Taken on Sep 13, 2022, 11:34 AM MDT
Added on Sep 15, 2022, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1680 of 1851
Form detail
#79: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Help MB Welding
MB Welding 1 10 Weld pile bracing, Weld Pile Caps
Totals 3 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Sep 12, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 13, 2022, 7:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1681 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 0
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am MB Welding is onsite along with a short crew with IMCO. MB is working on welding the pile caps and
the pile bracing.
1:00 pm I spoke to Kirt. He informed me that this week will be a short crew of guys. He wants to get caught up
with the welding and try to adjust the pipe bracing under the walkway. Currently the 90 bends that connect to the
valves are 2" low. Since the pipe bracing is not adjustable, he needs to cut the bracing and reweld them to the
supports.
4:00 pm MB Welding is continuing to work on welding the bracing.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1682 of 1851
References
Photos (2)
20220912_123905.jpg
Taken on Sep 12, 2022, 12:39 PM MDT
Added on Sep 13, 2022, 7:43 AM MDT
Added by Chris Johnson
20220912_113420.jpg
Taken on Sep 12, 2022, 11:34 AM MDT
Added on Sep 13, 2022, 7:43 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1683 of 1851
Form detail
#78: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Help MB Welding, Fly in braces to
be welded, work on pan decking
MB Welding 1 10 Weld pile bracing
Totals 6 20
2. Materials
Forms
Location
Form date Sep 9, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 12, 2022, 10:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1684 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is going to continue working on pile bracing. MB is here to continue welding the bracing.
12:00 pm Kirt and I have discussed the irrigation line along with the pan decking. We reviewed the submittal and
the layout plan in the submittal. He has MB Welding working on the bracing for the pipe support to connects to the
submerged manifold. He said the holes did not line up so he is having MB Welding weld the cross members for the
bracing instead of bolting it per plan.
1:00 pm IMCO is continuing to work on pile bracing. They are also laying out the pan decking for the platform.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1685 of 1851
References
Photos (2)
20220909_075741.jpg
Taken on Sep 9, 2022, 7:57 AM MDT
Added on Sep 12, 2022, 10:54 AM MDT
Added by Chris Johnson
20220909_121243.jpg
Taken on Sep 9, 2022, 12:12 PM MDT
Added on Sep 12, 2022, 10:54 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1686 of 1851
Form detail
#77: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Help MB Welding, Fly in braces to
be welded, Work on airbust line,
frame roof
MB Welding 1 10 Weld pile bracing
Totals 6 20
2. Materials
Forms
Location
Form date Sep 8, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 9, 2022, 8:11 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1687 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
1:00 pm IMCO and MB Welding are working on the pile bracing. IMCO is also working on the rough carpentry for
the roof. They are putting the 2x12s on roof frame.
3:00 pm IMCO is working on installing the 4” air burst line under the walkway. They are just going to get the pipe
in place and lose bolted until they get all pieces together. They will tighten all flanges once they have it all in place.
5:00 pm MB Welding has one more brace to get tacked in, then he needs to fully weld a few locations and he will
be done with the pile bracing. He is hoping to have it welded out by tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1688 of 1851
References
Photos (2)
20220908_143635.jpg
Taken on Sep 8, 2022, 2:36 PM MDT
Added on Sep 9, 2022, 8:11 AM MDT
Added by Chris Johnson
20220908_163908.jpg
Taken on Sep 8, 2022, 4:39 PM MDT
Added on Sep 9, 2022, 8:11 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1689 of 1851
Form detail
#76: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Help MB Welding, Fly in braces to
be welded, temp support pump
cans with all thread
MB Welding 1 10 Weld pile bracing
Totals 6 20
2. Materials
Forms
Location
Form date Sep 7, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 8, 2022, 3:38 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1690 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is helping MB Welding with the stiffeners around the pipes.
11:00 am Sam, IPC, is onsite to locate the power around the air burst building. IMCO will have to excavate around
here to temp pipe in for this years fish season.
1:00 pm Sam was not able to locate the power very well. He was going to continue doing more digging and see if
he could find a plan. IMCO has added all thread to the pump cans to support it so they can remove the temp
bracing. I spoke to Jake about what was needed to support the pump cans per the pump manufacture. The detail
on the drawings (20 S 4) call out 4 holes on the pump cans to coordinate anchors with pump. I have checked all
submittals and have come up empty. Jake is going to find out what is expected. Kirt is going to use the all thread
for now so he can continue working on building the platform.
5:00 pm IMCO and MB welding have been working
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1691 of 1851
References
Photos (2)
20220907_091205.jpg
Taken on Sep 7, 2022, 9:12 AM MDT
Added on Sep 8, 2022, 3:38 PM MDT
Added by Chris Johnson
20220907_125027.jpg
Taken on Sep 7, 2022, 12:50 PM MDT
Added on Sep 8, 2022, 3:38 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1692 of 1851
Form detail
#75: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Install handrails, lay out pan
decking, help welder
MB Welding 1 10 Weld stiffeners around pipes, weld
pile caps
Totals 4 20
2. Materials
Forms
Location
Form date Sep 6, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 7, 2022, 8:06 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1693 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO has a small crew today. MB Welding is onsite and working on the various welding including the
pile caps. IMCO is working on getting the handrail in place.
12:00 pm IMCO is working on the pan decking. They are getting it in place along the walkway so you can walk out
to the platform.
1:00 pm Kirt and Jake are taking measurements to ensure the pipes will line up with the discharge head. They
need to make some adjustments.
2:00 pm Attended meeting.
5:00 pm MB has been working on welding the stiffeners around
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1694 of 1851
References
Photos (2)
20220907_072837.jpg
Taken on Sep 7, 2022, 7:28 AM MDT
Added on Sep 7, 2022, 8:05 AM MDT
Added by Chris Johnson
20220906_152347.jpg
Taken on Sep 6, 2022, 3:23 PM MDT
Added on Sep 7, 2022, 8:06 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1695 of 1851
Form detail
#73: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Fly bracing and pipe in for divers
and welders
MB Welding 1 10 Weld bracing on pile, weld
walkway
Crux Diving 3 10 Weld and Splash Zone welds, final
cleanup, video document
Totals 7 30
Forms
Location
Form date Sep 1, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 6, 2022, 10:35 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1696 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is working on the manifold and 90s. They need to unbolt and flip the 90s so the long side points
down, through the deck of the platform. They will also need to fix the coatings around the bolt heads that were
damaged due to lack of washers.
10:30 am Crux is working on finishing all the underwater welding. I spoke to them about video documenting all
work they have done underwater for future reference. Ken said he would get that done for us today because today
is the last day they will be onsite. IMCO has bolted the upper manifold to the pipe under the walkway.
1:00 pm Jake and I worked on the dimensions for the 2 valves and DMJ so they can set the 24” pipe to the correct
location. The crew is working on moving the pipe into place.
3:00 pm Crux is done with all underwater work. They have video documented everything. Jake said he would
submit the video as a submittal for everyone to watch. MB Welding is working on welding the end cap for the stairs
to bolt too.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1697 of 1851
References
Photos (5)
20220901_073753.jpg
Taken on Sep 1, 2022, 7:37 AM MDT
Added on Sep 1, 2022, 3:11 PM MDT
Added by Chris Johnson
20220901_074627.jpg
Taken on Sep 1, 2022, 7:46 AM MDT
Added on Sep 1, 2022, 3:11 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1698 of 1851
20220901_084629.jpg
Taken on Sep 1, 2022, 8:46 AM MDT
Added on Sep 1, 2022, 3:11 PM MDT
Added by Chris Johnson
20220901_090716.jpg
Taken on Sep 1, 2022, 9:07 AM MDT
Added on Sep 1, 2022, 3:11 PM MDT
Added by Chris Johnson
20220901_100100.jpg
Taken on Sep 1, 2022, 10:01 AM MDT
Added on Sep 1, 2022, 3:11 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1699 of 1851
Form detail
#72: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Fly bracing and pipe in for divers
and welders
MB Welding 1 10 Weld bracing on pile
Crux Diving 3 10 Weld underwater bracing, bolt 22
bend/ T Screen to manifold, bolt
airburst, irrigation and stilling well
Totals 7 30
Forms
Location
Form date Aug 31, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Sep 1, 2022, 9:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1700 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO and Crux are working on installing the 22 bend with T Screen. It is currently in the water and the
divers are working on installing the bolts.
9:00 am IMCO is flying in the SS pipe for the airburst. MB Welding is working on welding the bracing to the pile.
12:00 pm MB Welding is continuing to work on the X Bracing for the pile. Crux is working on welding out all
bracing under water. IMCO has been working on laying the 24” water pipe under the platform.
2:00 pm IMCO is continuing to fly in all pieces needed for the divers. This includes the stilling well, irrigation
pump can and airburst lines. Crux is bolting them up under water.
5:00 pm IMCO bolted the 90 bends to the manifold without washers on the bolt side. The coatings around the
bolts got damaged. They will need to unbolt, re coat then re bolt the 90s to the manifold and use washers on both
sides. They plan on doing this tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1701 of 1851
References
Photos (4)
20220831_075023.jpg
Taken on Aug 31, 2022, 7:50 AM MDT
Added on Sep 1, 2022, 9:46 AM MDT
Added by Chris Johnson
20220831_095942.jpg
Taken on Aug 31, 2022, 9:59 AM MDT
Added on Sep 1, 2022, 9:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1702 of 1851
20220831_110530.jpg
Taken on Aug 31, 2022, 11:05 AM MDT
Added on Sep 1, 2022, 9:46 AM MDT
Added by Chris Johnson
20220831_125335.jpg
Taken on Aug 31, 2022, 12:53 PM MDT
Added on Sep 1, 2022, 9:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1703 of 1851
Form detail
#71: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Fly bracing in for welders, prep
flanges on pipe, repair coatings
MB Welding 1 10 Weld bracing on pile, Modify
braces for manifold
Crux Diving 3 10 Weld underwater bracing
Totals 8 30
Forms
Location
Form date Aug 30, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 31, 2022, 8:56 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1704 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO has 2 more guys onsite today. They are going to work on the prepping the pipe to be installed
under the walkway.
8:30 am Crux is in the water working on welding the bracing to the piles. They also need to weld the bracing to
the pump cans. Sawtooth welding is onsite. He is going to help MB with all the welding that is needed.
11:00 am IMCO is starting to fly in the pipe under the walkway. Jake and I walked and checked the coatings on
the pipe. The DFT gauge was all over 30 mils. They knocked down an overrun area that Bill had a concern with.
They need to touch up a couple of locations. These locations are not on the pipes that are being installed. MB
Welding has cut and shortened the other tube brace. The divers are continuing to work on welding underwater.
1:00 pm MB Welding has finished shortening the other brace for the manifold. IMCO is flying it in for the divers to
bolt up now.
2:00 pm IMCO is continuing to work on pile bracing.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1705 of 1851
References
Photos (3)
20220830_091422.jpg
Taken on Aug 30, 2022, 9:14 AM MDT
Added on Aug 31, 2022, 8:55 AM MDT
Added by Chris Johnson
20220830_095152.jpg
Taken on Aug 30, 2022, 9:51 AM MDT
Added on Aug 31, 2022, 8:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1706 of 1851
20220830_122710.jpg
Taken on Aug 30, 2022, 12:27 PM MDT
Added on Aug 31, 2022, 8:55 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1707 of 1851
Form detail
#70: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Fly frame in for Crux to Weld, Set
pump cans to elevation
MB Welding 1 10 Weld bracing on pile, Modify
braces for manifold
Crux Diving 3 10 Weld underwater bracing, help set
pump cans
Totals 6 30
Forms
Location
Form date Aug 29, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 31, 2022, 8:53 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1708 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
12:00 pm IMCO is onsite with MB Welding and Crux Diving. They have set the pump cans to elevation using the
pump deck to support the cans. Crux is in the water working on the bracing to the flange on the cans that support
from the middle pile. They will be welding this connection then covering the welds with splash zone.
1:30 pm IMCO has tried to set the tube bracing to the manifold. They were way to long. They took a
measurement and are brainstorming ideas on how to modify the brace length.
4:00 pm Jake contacted Bryant regarding the tube bracing. He was asking if they could have a welded connection
to the deck instead of a bolted one. Bryant has asked to modify the tube bracing to meet the plans. MB Welding is
starting that now.
5:00 pm MB has cut the bracing and will finish it tomorrow. Crux has tacked the flange bracing in place and will
continue to weld on it tomorrow
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1709 of 1851
References
Photos (2)
20220829_160609.jpg
Taken on Aug 29, 2022, 4:06 PM MDT
Added on Aug 30, 2022, 8:24 AM MDT
Added by Chris Johnson
20220829_160007.jpg
Taken on Aug 29, 2022, 4:00 PM MDT
Added on Aug 30, 2022, 8:24 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1710 of 1851
Form detail
#69: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 5 Help Crux
MB Welding 1 5 Weld temp structure in holding
ponds
Crux Diving 3 4 Anchor picking eye to grout bags
Totals 6 14
Forms
Location
Form date Aug 26, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 29, 2022, 2:55 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1711 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am Crux and IMCO have removed 3 bags so far this morning. They think they have 2 more to go and they
should get their elevation needed. Jake and Kirt checked the bottom elevation by dipping a grade rod.
10:00 am Crux has removed all grout bags they think are in the way. I spoke to Jake about checking elevation
with a grade rod and the using the diver to find the high spots. They are going to work on that now.
11:00 am IMCO has confirmed they have the proper clearance to install the pump cans now. Crux is leaving for
the week. IMCO is now going to work on setting the middle walkway.
12:00 pm IMCO has set the middle walkway. Bill Lynch and I walked the site. Bill noticed some deficiencies in the
coatings from Stabb / Cobelco.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1712 of 1851
References
Photos (4)
20220826_075950.jpg
Taken on Aug 26, 2022, 7:59 AM MDT
Added on Aug 29, 2022, 2:50 PM MDT
Added by Chris Johnson
20220826_083209.jpg
Taken on Aug 26, 2022, 8:32 AM MDT
Added on Aug 29, 2022, 2:50 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1713 of 1851
20220826_113322.jpg
Taken on Aug 26, 2022, 11:33 AM MDT
Added on Aug 29, 2022, 2:51 PM MDT
Added by Chris Johnson
20220826_114311.jpg
Taken on Aug 26, 2022, 11:43 AM MDT
Added on Aug 29, 2022, 2:51 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1714 of 1851
Form detail
#67: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 bolt 22 to t screen, help Crux
MB Welding 1 10 temp structure in holding ponds
Crux Diving 3 10 chip grout
Totals 7 30
Forms
Location
Form date Aug 25, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 25, 2022, 8:45 AM MDT
Last updated by Chris Johnson
Included references Photos
Comments
Chris Johnson
Aug 26, 2022, 7:37 AM MDT This report is for Aug 24th.C
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1715 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO and Crux have setup the air compressor for the chipping gun. They plan to start chipping on the
grout bags that are in the way of the pump cans and pump manifold.
9:00 am Crux has a diver in the water and he is working on chipping. They informed me it is going pretty slow
because the grout is not flaking off. IMCO is working on bolting the 22 bend to the T screen. They are using
insulating kit that is causing them trouble. The sleeves are not wanting to fit nicely in the flange holes. Rocky,
IMCO, is making it work but it is taking extra effort.
12:00 pm I checked in with Crux. I asked for an update on how much was done. It sounded like it was about 0.1
cubic feet had been chipped out in 3 hours. That rate of production will not work. I have informed Jake of the
progress. We both agreed a new method is needed.
1:00 pm Jake and I double checked the elevations of the piles, pumps cans, deck and Invert. Everything was done
per plan and all numbers match.
2:00 pm Crux got their video feed fixed and recorded a video of the issues with the grout bags. It was determined
that anchoring a 18” x 18” plate with a picking eye to a grout bag, then lifting with the crane was the best method.
4:00 pm Crux informed me that the anchor bolts and drill will be here tomorrow. They informed me they think 4
bags need to be removed. They hope that will get the pump cans low enough. MB Welding has been working on
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1716 of 1851
the temp structure for the holding ponds.
References
Photos (4)
20220824_151016.jpg
Taken on Aug 24, 2022, 3:10 PM MDT
Added on Aug 25, 2022, 8:04 AM MDT
Added by Chris Johnson
20220824_151036.jpg
Taken on Aug 24, 2022, 3:10 PM MDT
Added on Aug 25, 2022, 8:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1717 of 1851
20220824_151258.jpg
Taken on Aug 24, 2022, 3:12 PM MDT
Added on Aug 25, 2022, 8:04 AM MDT
Added by Chris Johnson
20220824135722_1
Added on Aug 25, 2022, 8:42 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1718 of 1851
Form detail
#68: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Help Crux
MB Welding 1 10 Weld Pile Caps, Weld temp
structure in holding ponds
Crux Diving 3 10 Anchor picking eye to grout bags
Totals 6 30
Forms
Location
Form date Aug 25, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 26, 2022, 7:42 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1719 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO and Crux are waiting on the rock drills and anchor bolts to arrive so Crux and start working on
removing the grout bags. In the meantime, IMCO and MB Welding are going to work on welding the pile cap
plates for the platform. First they need to secure the pump cans.
10:00 am IMCO has bolted the platform to the pile cap plates and MB Welding is not working on welding the
plates to the piles.
2:00 pm Crux has received the anchor bolts and rock drills. They are entering the water to install them in the
grout bags.
3:30 pm They were able to move one bag about 5’ before it broke. They lifted the broken section out of the water
and have it on shore. They are going to install the plate in the other part of the bag that broke now.
5:00 pm The crews were able to remove 2 full bags. The last bag came out in one piece. They will continue
tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1720 of 1851
References
Photos (4)
20220825_151232.jpg
Taken on Aug 25, 2022, 3:12 PM MDT
Added on Aug 26, 2022, 7:40 AM MDT
Added by Chris Johnson
20220825_163130.jpg
Taken on Aug 25, 2022, 4:31 PM MDT
Added on Aug 26, 2022, 7:40 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1721 of 1851
20220825_151157.jpg
Taken on Aug 25, 2022, 3:11 PM MDT
Added on Aug 26, 2022, 7:39 AM MDT
Added by Chris Johnson
20220825_160353.jpg
Taken on Aug 25, 2022, 4:03 PM MDT
Added on Aug 26, 2022, 7:40 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1722 of 1851
Form detail
#66: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Help MB Welding, Install bracing,
Set Pump Cans, Set platform
MB Welding 1 10 Weld Bracing
Crux Diving 3 10 Weld Bracing
Totals 7 30
Forms
Location
Form date Aug 23, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 24, 2022, 8:07 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1723 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO, MB Welding and Crux diving are onsite. The plan today is to set the pump cans in the water at
approx. location then install the platform. They plan to use the platform to brace the pumps to proper location and
elevation.
11:30 am IMCO has picked and set the pump cans. They are now going to work on picking and setting the
platform.
12:30 pm IMCO has picked and set the platform. After checking measurements, the pump cans are sitting to
high. The divers are going to investigate.
1:00 pm Crux has confirmed that the pump cans are sitting on the grout bags previously placed with the last
project. Jake is going to get a chipping gun out here for them to chip out the grout to make way for the pump cans.
2:00 pm Attended weekly meeting.
4:00 pm MB welding is working on welding the platform to the piles. Crux has left for the day. They need the
chipping gun to continue work. IMCO is going to work on bolting the 22 bend to the t screen.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1724 of 1851
References
Photos (4)
20220823_110439.jpg
Taken on Aug 23, 2022, 11:04 AM MDT
Added on Aug 24, 2022, 8:04 AM MDT
Added by Chris Johnson
20220823_111330.jpg
Taken on Aug 23, 2022, 11:13 AM MDT
Added on Aug 24, 2022, 8:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1725 of 1851
20220823_120749.jpg
Taken on Aug 23, 2022, 12:07 PM MDT
Added on Aug 24, 2022, 8:04 AM MDT
Added by Chris Johnson
20220823_121243.jpg
Taken on Aug 23, 2022, 12:12 PM MDT
Added on Aug 24, 2022, 8:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1726 of 1851
Form detail
#65: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Re-bolt intake piping, walkway
install
MB Welding 1 10 Weld walkway
Totals 4 20
2. Materials
Forms
Location
Form date Aug 22, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 23, 2022, 8:20 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1727 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 10
Kobelco 1100G Crane 1 10
Manlift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
3:00 pm IMCO has bolted the manifold to the pump cans. The pump cans had to get recoated with the proper
coating. This was done last week and they were delivered Thursday. IMCO has torqued the fasteners. They are now
working on the walkway. MB Welding is here working on the walkway platform.
5:00 pm While installing the walkway it was found that a field weld piece of the walkway was cut and coped to be
bolted. After some research, Jake informed me that the piece was never revised from a previous revision of the
submittal. It was sized to be a bolt on. This leaves a large gap around all sides of the channel iron. This could be
extremely difficult to weld / fill. Jake and I spoke about having the corner clips fabricated and galvanized and bolt it
on. He is going to check with Bryant on that.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1728 of 1851
References
Photos (3)
20220822_155337.jpg
Taken on Aug 22, 2022, 3:53 PM MDT
Added on Aug 23, 2022, 8:18 AM MDT
Added by Chris Johnson
20220822_155253.jpg
Taken on Aug 22, 2022, 3:52 PM MDT
Added on Aug 23, 2022, 8:18 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1729 of 1851
20220823_081909_photo
Taken on Aug 23, 2022, 8:18 AM MDT
Added on Aug 23, 2022, 8:19 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1730 of 1851
Form detail
#64: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 1 3 Unload Pipe
Totals 1 3
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 16, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 17, 2022, 8:41 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1731 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
JCB 510 Boom Forklift 1 2
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
2:00 pm Attended weekly meeting.
3:00 pm Jake is here to unload the pipe that was sent off because of insufficient coating DFT. I have spot checked
the pipe with my DFT instrument. All locations are over 30 mils DFT. Jake has unloaded the pipe. I also noticed that
they finished the temporary steel structure to separate the holding ponds.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1732 of 1851
References
Photos (2)
20220816_132831.jpg
Taken on Aug 16, 2022, 1:28 PM MDT
Added on Aug 16, 2022, 1:59 PM MDT
Added by Chris Johnson
20220816_133336.jpg
Taken on Aug 16, 2022, 1:33 PM MDT
Added on Aug 16, 2022, 1:59 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1733 of 1851
Form detail
#63: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Holding pond steel dam
Totals 3 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 9, 2022
Description Facility 40, temporary steel dam for holding ponds
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 15, 2022, 10:23 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1734 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 0
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on the steel temporary dam structure that will separate the holding ponds in half. This
will allow IMCO to demo half the ponds while allowing hatchery operations to continue in the other half.
12:00 pm IMCO is continuing to work on the temporary steel structure.
2:00 pm Attended weekly meeting.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1735 of 1851
Form detail
#62: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 1 10 Load up pipe to get recoated
Totals 1 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 8, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 9, 2022, 8:18 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1736 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 0
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. Talked with Jake. They have a slow day today. They are going to work on loading up the
pipe as trucks arrive.
5:00 pm All pipe has been loaded on trucks and is getting hauled to coatings shops to have either the proper
thickness applied or the proper product applied. The pump cans were not coated with proper coatings. the off
white pipe was not thick enough.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1737 of 1851
References
Photos (2)
20220808_122014.jpg
Taken on Aug 8, 2022, 12:20 PM MDT
Added on Aug 9, 2022, 7:48 AM MDT
Added by Chris Johnson
20220808_163920.jpg
Taken on Aug 8, 2022, 4:39 PM MDT
Added on Aug 9, 2022, 7:48 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1738 of 1851
Form detail
#59: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Clean up flanges on Irrigation
pump can, Load pipe
Totals 2 10
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Aug 4, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 5, 2022, 10:13 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1739 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 0
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO has a short crew today. They are working on cleaning up the flanges on the irrigation pump can
now. They plan to work on bolting some of it together today and do site clean up.
9:00 am Jake informed me that Cobelco is picking up the off white pipe that has insufficient DFT. They are going
to take it to their shop and get it recoated to the proper thickness of 30 mils. Yesterday the 22 bend arrived freshly
coated and ready to be installed.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1740 of 1851
References
Photos (3)
20220804_082039.jpg
Taken on Aug 4, 2022, 8:20 AM MDT
Added on Aug 5, 2022, 10:12 AM MDT
Added by Chris Johnson
20220804_082048.jpg
Taken on Aug 4, 2022, 8:20 AM MDT
Added on Aug 5, 2022, 10:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1741 of 1851
20220804_081923.jpg
Taken on Aug 4, 2022, 8:19 AM MDT
Added on Aug 5, 2022, 10:12 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1742 of 1851
Form detail
#58: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Piping prep, walkway
prep
MB Welding 1 10 Welding Bracing
Totals 5 20
2. Materials
Forms
Location
Form date Aug 3, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 4, 2022, 7:58 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1743 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 0
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is continuing to work on the channel on the platform. MB Welding is welding the channel to the
platform beams.
11:00 am IMCO is working on torquing the walkway platform and pipe support bolts.
2:00 pm MB Welding has completed the channel welding on the platform.
3:00 pm IMCO has set the first walkway section on the piles. They are just strapping it down for now and waiting
until they have the other platform and walkway on the piles to ensure everything is square before welding the
plates to the piles.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1744 of 1851
References
Photos (4)
20220803_113402.jpg
Taken on Aug 3, 2022, 11:34 AM MDT
Added on Aug 4, 2022, 7:51 AM MDT
Added by Chris Johnson
20220803_113412.jpg
Taken on Aug 3, 2022, 11:34 AM MDT
Added on Aug 4, 2022, 7:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1745 of 1851
20220803_123855.jpg
Taken on Aug 3, 2022, 12:38 PM MDT
Added on Aug 4, 2022, 7:51 AM MDT
Added by Chris Johnson
20220803_141906.jpg
Taken on Aug 3, 2022, 2:19 PM MDT
Added on Aug 4, 2022, 7:51 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1746 of 1851
Form detail
#57: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Piping prep, walkway
prep
MB Welding 1 10 Welding Bracing
Totals 5 20
2. Materials
Forms
Location
Form date Aug 2, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 3, 2022, 9:55 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1747 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is working with MB welding to continue getting the pile bracing installed.
9:00 am MB Welding is continuing to weld pile bracing. IMCO is working installing the bolts for the Manifold to
pump cans. The are using SS hardware with anti-seize. They are torquing them to 436 ft lbs per the chart on GM1.
They are marking them as they go so they don’t forget any.
1:00 pm MB Welding and IMCO has started to work on installing the channel to supports the concrete on the
platform. IMCO is also working on installing the mud valve. The mud valve bolt pattern is the same as the flange
with the exception of two bolt holes are missing. See attached photos.
2:00 pm Attended meeting.
4:00 pm IMCO and MB Welding is continuing to work on the channel on the platform.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1748 of 1851
References
Photos (4)
20220802_122129.jpg
Taken on Aug 2, 2022, 12:21 PM MDT
Added on Aug 3, 2022, 8:33 AM MDT
Added by Chris Johnson
20220802_122119.jpg
Taken on Aug 2, 2022, 12:21 PM MDT
Added on Aug 3, 2022, 8:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1749 of 1851
20220802_123041.jpg
Taken on Aug 2, 2022, 12:30 PM MDT
Added on Aug 3, 2022, 8:33 AM MDT
Added by Chris Johnson
20220802_161852.jpg
Taken on Aug 2, 2022, 4:18 PM MDT
Added on Aug 3, 2022, 8:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1750 of 1851
Form detail
#55: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Piping prep, walkway
prep
MB Welding 1 10 Welding Bracing
Idaho Testing & Inspection 1 10 Weld Inspector, Platform and Pile
Bracing Weld Inspection
Totals 6 30
Forms
Location
Form date Aug 1, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Aug 2, 2022, 1:45 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1751 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:30 am IMCO is working on bolting up the walkway platform. MB is onsite continuing to weld the pile bracing.
10:30 am Idaho Testing and Inspection is onsite to perform the welding inspection on the platform and pile
bracing. Not all the bracing is done on the piles so we are going to get what we can done today and they will need
to make another trip at a later date.
1:00 pm Idaho Testing has completed the welding inspection. He found a few issues with the platform welds. Jake
had MB Welding go back and fix them right away. Idaho Testing then reinspected them and approved them. This
marks all field welding to date is tested and approved. IMCO has gotten the SS washers onsite for the intake
manifold. They are working on installing those along with a picking plan to lift the pump cans and manifold.
4:00 pm MB Welding is continuing to work on welding the pile bracing. IMCO is also working on bolting up the
walkway and pipe supports. I noticed a few bolts missing washers. I asked the guys if they would please inspect all
bolts and washers and let me know before they start torquing them to spec. I said once torqued, they should mark
the bolt head to document that the bolt was torqued. This will prevent them from missing any.
See Attached Weld Inspection Reports
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1752 of 1851
References
Photos (5)
20220801_161254.jpg
Taken on Aug 1, 2022, 4:12 PM MDT
Added on Aug 2, 2022, 7:46 AM MDT
Added by Chris Johnson
20220801_104433.jpg
Taken on Aug 1, 2022, 10:44 AM MDT
Added on Aug 2, 2022, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1753 of 1851
20220801_094744.jpg
Taken on Aug 1, 2022, 9:47 AM MDT
Added on Aug 2, 2022, 7:46 AM MDT
Added by Chris Johnson
20220801_113918.jpg
Taken on Aug 1, 2022, 11:39 AM MDT
Added on Aug 2, 2022, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1754 of 1851
20220801_094719.jpg
Taken on Aug 1, 2022, 9:47 AM MDT
Added on Aug 2, 2022, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1755 of 1851
Form detail
#53: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Demo, drive last pile
MB Welding 1 10 Welding Bracing, Cut Piles
Sawtooth Welding 2 8 Weld Platform together
Totals 7 28
2. Materials
Forms
Location
Form date Jul 28, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 28, 2022, 9:05 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1756 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO is going to work on installing the last pile. This pile is for the pump column support. Sawtooth is
onsite again to continue welding on the platform.
12:00 pm IMCO has removed the last pile of the temp structure and drove the last pile for the pump can support.
This pile was driven 20’ per the drawings. Sawtooth is continuing to work on welding the platform together and MB
is going to continue welding the bracing together to the piles.
5:00 There has been lots of discussion regarding the coatings on the piping. The off white pipe coatings
inspection showed insufficient DFT. Bryant is working on a response to the coatings inspection submittal. It was
also discussed that IMCO needs to sandblast and coat the salvaged 22 bend that bolts to the T Screen. A coatings
inspection report is still needed for the pump cans, Jake is continuing to work on that.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1757 of 1851
References
Photos (6)
20220727_105418.jpg
Taken on Jul 27, 2022, 10:54 AM MDT
Added on Jul 28, 2022, 8:59 AM MDT
Added by Chris Johnson
20220727_093601.jpg
Taken on Jul 27, 2022, 9:36 AM MDT
Added on Jul 28, 2022, 8:59 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1758 of 1851
20220727_105427.jpg
Taken on Jul 27, 2022, 10:54 AM MDT
Added on Jul 28, 2022, 8:59 AM MDT
Added by Chris Johnson
20220727_131432.jpg
Taken on Jul 27, 2022, 1:14 PM MDT
Added on Jul 28, 2022, 9:04 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1759 of 1851
20220727_140928.jpg
Taken on Jul 27, 2022, 2:09 PM MDT
Added on Jul 28, 2022, 9:04 AM MDT
Added by Chris Johnson
20220727_140905.jpg
Taken on Jul 27, 2022, 2:09 PM MDT
Added on Jul 28, 2022, 9:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1760 of 1851
Form detail
#54: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Demo, layout new
piping
MB Welding 1 10 Welding Bracing
Sawtooth Welding 2 8 Weld Platform together, Weld
Bracing
Totals 7 28
Forms
Location
Form date Jul 28, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 29, 2022, 9:03 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1761 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am I spoke to Jake regarding the coatings, Bryant responded to the coatings inspection. It is required coat
the insufficient DFT pieces. Jake is going to start looking for a local coatings company to either spray onsite or they
will have to ship it to a shop to be done. I reminded him to check the temperature requirements for the coatings if
they plan to do it onsite. He is also working on getting the coatings inspection report for the pump cans and the
irrigation can. This will determine if a recoat is needed for these pieces as well, also he is working on getting the
submittal for the pump can and irrigation can to check the type of product that was used so they can touch up the
spots that were damaged during shipment. MB welding is going to continue welding on bracing and sawtooth is
onsite and plans to finish welding the platform together today.
12:00 pm I have been discussing with Bryant and Bill regarding the 22 bend that IMCO is going to reuse. They are
going to have it sand blasted and recoated. The existing condition was the bend had a clamp and frame on it that
was welded to 2 piles underwater. I have asked Bryant if this is needed. He requested asbuilts so they can check to
see if the additional bracing is needed. Sawtooth has finished welding up the platform and is now working on
welding the bracing on the piles. MB is continuing to work on welding on the piles. Some discussion regarding
connecting the mechanical piping flanges together has come up the question has been if washers are needed.
2:00 pm After talking to Bryant it is determined that washers should be provided to protect the coatings. All
anchor hardware should be stainless steel. Jake is working on getting SS washers onsite. They have loaded the 22
bend up to have it sand blasted and coated.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1762 of 1851
4:30 pm I received an email from Bryant regarding the clamp on the 22 bend. He ran the numbers and they
recommended not to use the clamp. I called Bill and verified with him that we should not use the clamp. He
agreed. I called Jake and notified him that the clamp was not needed.
References
Photos (3)
20220728_091609.jpg
Taken on Jul 28, 2022, 9:16 AM MDT
Added on Jul 29, 2022, 9:00 AM MDT
Added by Chris Johnson
20220728_132342.jpg
Taken on Jul 28, 2022, 1:23 PM MDT
Added on Jul 29, 2022, 9:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1763 of 1851
20220728_134514.jpg
Taken on Jul 28, 2022, 1:45 PM MDT
Added on Jul 29, 2022, 9:00 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1764 of 1851
Form detail
#52: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Pile Bracing, Demo
MB Welding 1 10 Welding Bracing, Cut Piles
Sawtooth Welding 2 8 Weld Platform together
Totals 7 28
2. Materials
Forms
Location
Form date Jul 26, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 27, 2022, 8:33 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1765 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
Deere 225D Excavator 1 5
JCB 510 Boom Forklift 1 10
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am MB Welding is onsite and continuing to weld braces on the piles.
9:00 am Sawtooth is onsite. They are also working on welding members together. They have two welders. They
are working on the platform and also the pile bracing. IMCO took delivery of the irrigation pump can.
12:00 pm MB Welding is working on cutting the piles to proper height. Sawtooth is still working on welding the
platform together.
2:00 pm Attended weekly meeting. Bryant provided some insight on the needed additional bracing for the piles.
4:00 pm MB has cut all piles to height and they are working on removing the temp structure used to guide the
piles during driving
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1766 of 1851
References
Photos (3)
20220726_151711.jpg
Taken on Jul 26, 2022, 3:17 PM MDT
Added on Jul 27, 2022, 8:33 AM MDT
Added by Chris Johnson
20220726_093434.jpg
Taken on Jul 26, 2022, 9:34 AM MDT
Added on Jul 27, 2022, 8:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1767 of 1851
20220726_123825.jpg
Taken on Jul 26, 2022, 12:38 PM MDT
Added on Jul 27, 2022, 8:33 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1768 of 1851
Form detail
#51: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Lay out walkway pieces
MB Welding 1 10 Weld bracing on pile
Totals 3 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 25, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 26, 2022, 7:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1769 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
9:30 am IMCO is onsite along with MB Welding. MB is working on welding brackets to the H piles for the support
beams.
11:00 am The Intake pump cans arrived on site. They have some scuff marks from shipping that need to be
touched up. I asked Jake if he could find the coatings inspection report for the pump cans and also verify what
coating needs to be used to touch up the markings left from the shipping straps.
12:00 pm Jake, Kirt and I discussed the elevation of the river bottom where the pump cans sit. They came up with
a plan to check the bottom elevation without divers to get an estimate of the clearance the pump cans would have.
They are working on a plan to suspend the pump cans until they can be secured in place.
4:00 pm MB Welding is continuing to work on welding brackets to the piles. IMCO has two labors onsite that are
working on laying out the walkway and also cleaning up flanges on the water pipe.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1770 of 1851
References
Photos (4)
IMG_0045
Taken on Jul 25, 2022, 11:17 AM MDT
Added on Jul 26, 2022, 7:46 AM MDT
Added by Chris Johnson
IMG_0043
Taken on Jul 25, 2022, 11:17 AM MDT
Added on Jul 26, 2022, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1771 of 1851
IMG_0042
Taken on Jul 25, 2022, 11:16 AM MDT
Added on Jul 26, 2022, 7:46 AM MDT
Added by Chris Johnson
IMG_0046
Taken on Jul 25, 2022, 11:20 AM MDT
Added on Jul 26, 2022, 7:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1772 of 1851
Form detail
#50: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Bracing for platform structure
MB Welding 1 10 Weld bracing on pile
Totals 5 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 20, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 21, 2022, 2:56 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1773 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO and MB Welding are onsite. They plan to start installing the bracing for the platform.
10:00 am Jake, Kevin and I shot in the pile trip elevations using a rotary laser and the benchmark provided onsite.
I have provided that information to Bill and Bryant. IMCO and MB are continuing to work on bracing the structure
per the drawings.
12:00 pm IMCO is marking out the pile cut off heights and working with MB Welding. They are continuing to work
on welding the plates to the piles.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1774 of 1851
References
Photos (4)
20220720_103406.jpg
Taken on Jul 20, 2022, 10:34 AM MDT
Added on Jul 21, 2022, 2:55 PM MDT
Added by Chris Johnson
20220720_103455.jpg
Taken on Jul 20, 2022, 10:34 AM MDT
Added on Jul 21, 2022, 2:55 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1775 of 1851
20220720_103521.jpg
Taken on Jul 20, 2022, 10:35 AM MDT
Added on Jul 21, 2022, 2:55 PM MDT
Added by Chris Johnson
20220720_111504.jpg
Taken on Jul 20, 2022, 11:15 AM MDT
Added on Jul 21, 2022, 2:56 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1776 of 1851
Form detail
#49: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 help divers, Prep bracing, Drive
Pile
Crux Diving 3 10 Weld bracing clips
MB Welding 1 10 Weld Platform Steel
Totals 7 30
Forms
Location
Form date Jul 19, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 20, 2022, 8:02 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1777 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am The divers are in the water installing the bracing for the structure. IMCO is flying the pieces in with the
crane and a diver is tack welding them in place.
9:00 am MB Welding is onsite working on welding the platform frame together. The divers are continuing to work
on installing the bracing.
12:30 pm IMCO is going to drive the offshore walkway pile downstream.
2:00 pm Attended the weekly meeting. IMCO was able to drive the pile to 32’ depth. Crux is done welding the
beams and is packing up. They will be back in a couple weeks.
4:00 pm IMCO was able to drive the onshore downstream pile to 30 depth. They are going to work on the
onshore upstream one now.
5:30 pm IMCO has driven the onshore downstream pile to a 30’ depth as well. Don, crane operator, reported to
me that he had a significant amount of weight on it, relaying to me that it is at a reasonable refusal.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1778 of 1851
References
Photos (2)
20220719_163255.jpg
Taken on Jul 19, 2022, 4:32 PM MDT
Added on Jul 20, 2022, 7:56 AM MDT
Added by Chris Johnson
IMG_0040
Taken on Jul 19, 2022, 10:34 AM MDT
Added on Jul 20, 2022, 8:01 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1779 of 1851
Form detail
#48: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 help divers, Prep bracing
Crux Diving 3 10 Weld bracing clips
Totals 6 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 18, 2022
Description Facility 20, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 19, 2022, 8:29 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1780 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO and Crux are onsite working on welding the clips to the piles underwater. They used a laser level
to set the elevation of the top clip bracket then the divers are using a tape underwater to measure the other two.
2:00 pm Crux is continuing to work on welding the brackets underwater. Watching on the screen in the dive
shack, it looks they are achieving all welds per the drawings. IMCO is prepping the beams that will be welded to
these brackets to make up the supports.
5:00 pm Crux and IMCO are done for the day. They were able to get all brackets welded to the 4 piles that make
up the platform.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1781 of 1851
References
Photos (1)
20220718_141102.jpg
Taken on Jul 18, 2022, 2:11 PM MDT
Added on Jul 19, 2022, 8:29 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1782 of 1851
Form detail
#47: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Recycle Metal, help divers, drive
pile
Crux Diving 3 10 Torch steel members
Totals 6 20
2. Materials
Forms
Location
Form date Jul 14, 2022
Description Facility 20, Hatchery Intake Removal, Pile Driving
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 15, 2022, 9:02 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1783 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am IMCO and Crux are working on removing the rest of the existing intake structure.
9:30 am IMCO has driven the Off shore upstream platform pile to 20’ depth before it started to bounce.
12:00 pm Bill, IPC, was onsite to discuss the pile driving. A meeting is setup for 430 pm today to discuss the pile
driving pile tip embedment.
1:00 pm IMCO and Crux has remove the last of the structure. The last piece was the intake box and piping.
2:00 pm IMCO has driven the shore side upstream pile to 20’ embedment.
3:00 pm IMCO attempted to drive the platform piles again to see if they can get any more out of them. They all
reacted about same. They bounce hard once the full weight of the hammer is on them but the piles do not go
down any further. They then went to the walkway off shore pile downstream. This pile was only down about 8’
embedment. They let the hammer go slack and it broke through whatever was stopping it. It went down easy and
got hard again around 32’ embedment. They were able to achieve 34’ embedment. They checked the plumpness
and it was out about 1.5” over 6’. They attempted to fix it but was not able to achieve plumb. They pulled the pile
out. They decided to move this pile to the walkway off shore upstream side. They drove it to 34.5’ embedment.
4:30 pm Attended Pile drive meeting, where it was discussed to add additional bracing to support the piles
without the 30’ embedment.
6:00 pm I was notified that they are not working tomorrow. Everyone will be back Monday.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1784 of 1851
References
Photos (4)
20220714_124019.jpg
Taken on Jul 14, 2022, 12:40 PM MDT
Added on Jul 15, 2022, 8:46 AM MDT
Added by Chris Johnson
20220714_122116.jpg
Taken on Jul 14, 2022, 12:21 PM MDT
Added on Jul 15, 2022, 8:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1785 of 1851
20220714_131742.jpg
Taken on Jul 14, 2022, 1:17 PM MDT
Added on Jul 15, 2022, 8:46 AM MDT
Added by Chris Johnson
20220714_161214.jpg
Taken on Jul 14, 2022, 4:12 PM MDT
Added on Jul 15, 2022, 8:46 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1786 of 1851
Form detail
#46: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Recycle Metal, help divers, drive
pile
Crux Diving 3 10 Torch steel members
Totals 6 20
2. Materials
Forms
Location
Form date Jul 13, 2022
Description Facility 20, Hatchery Intake Removal
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 14, 2022, 7:31 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1787 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am Divers are prepping to enter the water to finishing cutting off braces to remove the downstream, shore
side leg of the existing structure. This will allow IMCO to install that pile.
11:00 am IMCO noticed the irrigation pump was not running. We checked Jeffs yard and the sprinklers were not
running but the valve was open. I contacted Heath, IPC, to make him aware that the pump was continuing to trip.
IMCO tried running it in HAND and AUTO and the motor logic continued to trip. Heath arrived and checked the
amps on all three legs. They were between 14 and 15.5 amps. The motor logic is set to trip around 15 which makes
sense. IMCO shut it all down and will diagnose the issue once the crane is free. They suspect the pump screen has
some kind of debris blocking it.
2:00 pm IMCO was able to drive the shore side, downstream pile for the platform to 20’ embedment. They are
going to remove the off shore leg now.
3:00 pm IMCO drove the offshore downstream pile for the platform to 18’. Both piles today drove until they
started to bounce up and down hard. IMCO is going to now pull the irrigation pump to check and see what the
issue is.
3:30 pm Heath is onsite to check on the progress of the pump. IMCO has pulled the pump and inspected the
screen, all looks fine. It was decided to switch two legs of the pump to make sure it is spinning in the correct
direction. It was not. After the wires were flipped the amps were back to normal and the pump is running fine now.
5:00 pm Crux and IMCO was able to remove more the structure before calling it a day. They will go after the rest
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1788 of 1851
of the structure tomorrow and continue with the pile driving.
References
Photos (5)
20220713_132633.jpg
Taken on Jul 13, 2022, 1:26 PM MDT
Added on Jul 13, 2022, 4:20 PM MDT
Added by Chris Johnson
20220713_135523.jpg
Taken on Jul 13, 2022, 1:55 PM MDT
Added on Jul 13, 2022, 4:20 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1789 of 1851
20220713_115408.jpg
Taken on Jul 13, 2022, 11:54 AM MDT
Added on Jul 13, 2022, 4:21 PM MDT
Added by Chris Johnson
20220713_143145.jpg
Taken on Jul 13, 2022, 2:31 PM MDT
Added on Jul 13, 2022, 4:21 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1790 of 1851
20220713_111112.jpg
Taken on Jul 13, 2022, 11:11 AM MDT
Added on Jul 13, 2022, 4:22 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1791 of 1851
Form detail
#45: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Recycle Metal, help divers
Crux Diving 3 10 Torch steel members
Totals 6 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 12, 2022
Description Facility 20, Hatchery Intake Removal
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 13, 2022, 7:46 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1792 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:30 am The Divers and IMCO are working on demo of the existing structure.
11:00 am Heath, IPC, was onsite regarding the irrigation pump not running. We checked and the breakers were
off. After checking with IMCO he turned the pump back on. It tripped twice. Kevin had the divers swim over to the
pump and check the screen. It seemed a little dirty but not bad. Heath turned the pump on again and it seems to
be running fine. Kevin and I spoke about checking to make sure its running every hour or so.
1:00 pm IDFG power washed the T screen so we could inspect the coating on it. It seems to have rubbed off on a
couple of spots but overall not bad at all. I have taken photos and so has Jeff.
2:00 pm Attended weekly meeting.
4:00 pm The divers are retrieving cut off pieces. IMCO is continuing to work on removing pieces of the structure
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1793 of 1851
References
Photos (5)
20220712_093214.jpg
Taken on Jul 12, 2022, 9:32 AM MDT
Added on Jul 12, 2022, 1:16 PM MDT
Added by Chris Johnson
20220712_112808.jpg
Taken on Jul 12, 2022, 11:28 AM MDT
Added on Jul 12, 2022, 1:16 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1794 of 1851
20220712_130503.jpg
Taken on Jul 12, 2022, 1:05 PM MDT
Added on Jul 12, 2022, 1:16 PM MDT
Added by Chris Johnson
20220712_131137.jpg
Taken on Jul 12, 2022, 1:11 PM MDT
Added on Jul 12, 2022, 1:17 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1795 of 1851
20220712_131202.jpg
Taken on Jul 12, 2022, 1:12 PM MDT
Added on Jul 12, 2022, 1:17 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1796 of 1851
Form detail
#44: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 Recycle Metal, help divers
Crux Diving 3 10 Remove T Screen, Torch steel
members
IMCO, General Crew 1 10 Eagle Island Loop brush clearing
Totals 7 30
Forms
Location
Form date Jul 11, 2022
Description Facility 20, Hatchery Intake Removal, Eagle Island Loop
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 12, 2022, 7:57 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1797 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is working on taking apart the existing structure that is removed and recycling the metal. Crux
Diving is onsite and prepping to enter the water.
12:00 pm Crux has a diver in the water who is looking at the structure and developing a game plan. Jayden,
IMCO, is at EIL working on rocking the shoulders of the access road and plans to clear brush for sight distance.
2:00 pm The diver has came out and informed all of us of his findings, IMCO is having him start to torch off
pieces of the structure around the pipe so they can start to remove pieces.
5:00 pm IMCO had Crux unbolt the T Screen and they removed it, it is on the bank. They also dropped a plumb
bob to check the location of the outside upstream pile. The worry is it will hit the existing pile that is encased in
concrete. The frame of the structure is in the way to get an exact location but it looks like it will be in the concrete
but not in conflict with the pile.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1798 of 1851
References
Photos (2)
20220711_114908.jpg
Taken on Jul 11, 2022, 11:49 AM MDT
Added on Jul 12, 2022, 7:52 AM MDT
Added by Chris Johnson
20220711_160832.jpg
Taken on Jul 11, 2022, 4:08 PM MDT
Added on Jul 12, 2022, 7:52 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1799 of 1851
Form detail
#42: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Drive Pile
Vale Electric, Electricians 2 5 Disconnect and reconnect
irrigation pump
Totals 6 15
2. Materials
Forms
Location
Form date Jul 8, 2022
Description Drive Pile, Temp bracing
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 11, 2022, 10:47 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1800 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am Arrived on site. Crew is prepping to drive the pile on the North West corner, down stream.
8:00 am After placing the pile in the temp jig, Kirt realizes that the pile is making contact with the existing
structure at the very bottom. Its kicking the pile out about 4”. They will not be able to drive this pile. Vale electric is
onsite and is working on shutting down the irrigation pump.
9:00 am They decided they need to work on bracing the existing structure. Once its braced they will start
removing the pieces of the structure that is in the way of the pile driving. All piles are going to make contact with
the existing structure, since they have built their template or jig on the existing structure, they will need to keep it
intact while driving the permanent piles. The divers are due onsite next week and they will utilize them to remove
the members that are in conflict with the new piles.
10:00 am The crew has pulled the second pile installed yesterday and attempting to reset it. It twisted on them
while driving it yesterday so they are attempting to fix it.
10:30 am Attended meeting for pile driving.
12:00 pm IMCO has reset the irrigation pump. They used fine metal mesh as a screen. The plan is to continue
working on bracing the structure in preparation for the divers to be onsite Monday.
2:00 pm IMCO is planning to work on installing some more temp piles to brace off the temp jig so the divers can
start cutting apart the existing structure.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1801 of 1851
References
Photos (1)
20220708_122227.jpg
Taken on Jul 8, 2022, 12:22 PM MDT
Added on Jul 11, 2022, 10:47 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1802 of 1851
Form detail
#41: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Drive Pile
MB Welding 1 10 Drive Pile
Totals 5 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jul 7, 2022
Description Facility 20 Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 7, 2022, 5:08 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1803 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO is prepping to start installing permanent piles. They have the clips in place to guide the pile in the
location that they surveyed.
8:00 am IMCO has the first pile in the clips and is starting to use the APE 200 vibratory hammer to install it.
9:30 am The pile made it to 15’ of bury. They have been hammering on it for around 20 minutes and it has moved
maybe 6 inches. They are going to move to the next one.
11:00 am IMCO has placed the second pile and it has buried to 7.5’. They have been hitting on it for over 20
minutes and it is not going any deeper. They both have seemed to hit the same layer of hard ground as they both
are at approx. same pile tip elevation (Approx. 1680.5) . They are going to work on building the rest of their jig to
guide the piles. They want to drive a pile out in the water father before making any adjustments.
3:00 pm They are still working on the pile jig, MB welding is working on welding the temp braces for the jig.
5:00 pm The crew has installed the rest of the jig. They are done for the day and will be back tomorrow to
continue driving pile.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1804 of 1851
References
Photos (2)
IMG_0037
Taken on Jul 7, 2022, 8:00 AM MDT
Added on Jul 7, 2022, 4:47 PM MDT
Added by Chris Johnson
IMG_0035
Taken on Jul 7, 2022, 7:55 AM MDT
Added on Jul 7, 2022, 4:47 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1805 of 1851
Form detail
#39: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 10 Prep for Pile Driving, Clean up site,
recycle existing iron
MB Welding 1 10 Recycle Iron, weld on guides for
new piles
Boise River Fence 2 Install Gates and fabric
Totals 7 20
Forms
Location
Form date Jul 6, 2022
Description Hatchery Intake, EIL Fencing
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 7, 2022, 9:11 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1806 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1 10
JCB 510 Boom Forklift 1 10
Deere 225D Excavator 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Boise River Fence is onsite installing the fabric and gates at EIL.
11:00 am IMCO is continuing to work on disassembling the existing intake structure. They hope to be driving
piles today.
1:00 pm IMCO is waiting on the most updated pile locations. They have made some changes because of the
location of the screen piles. They are waiting on the updated coordinates and the surveyor will shoot them in.
Meantime they are breaking down the pieces of the existing structure to fit it into the recycle bin.
4:30 pm The updated coordinates are uploaded and the surveyor is marking them now. They are welding on the
guides to help
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1807 of 1851
References
Photos (2)
20220706_162614.jpg
Taken on Jul 6, 2022, 4:26 PM MDT
Added on Jul 7, 2022, 9:09 AM MDT
Added by Chris Johnson
20220706_162603.jpg
Taken on Jul 6, 2022, 4:26 PM MDT
Added on Jul 7, 2022, 9:09 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1808 of 1851
Form detail
#37: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10
IMCO, General Crew 5 10 temp crane pad
MB Welding 1 10 Temp crane pad
Durham Gravel, Paving 7 6 Paved Access Road
Totals 16 36
Forms
Location
Form date Jun 30, 2022
Description Eagle Island Loop, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 1, 2022, 9:49 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1809 of 1851
2. Materials
Material Quantity Unit Comment
1/2" Superpave SP3 HMA 98 tons
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1
Deere 225D Excavator 1
JCB 510 Boom Forklift 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am IMCO and I have checked the grade one more time on the EIL Access road. All looks good and is ready
for paving. They are currently saw cutting the existing edges now.
8:00 am Pavers are onsite. Mix is due onsite at 9am.
9:00 am I have laid out the edge of pavement with Durham. Kevin Z. is here and he agreed with the limits. Mix is
onsite.
1:00 pm The crew is done with paving. The total was 98 tons. IPC has been onsite at EIL to install the meters on
the lower loop. He has it all installed and energized.
3:30 pm The mat has cooled enough for me to take the two density cores. I will put these in the oven tonight and
run them tomorrow. I have also taken a sample for Rice determination. I was not able to get to the hatchery today.
Kevin informed me that the IMCO crew completed the temp crane pad today.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1810 of 1851
References
Photos (3)
20220630_083827.jpg
Taken on Jun 30, 2022, 8:38 AM MDT
Added on Jul 1, 2022, 9:49 AM MDT
Added by Chris Johnson
20220630_095105.jpg
Taken on Jun 30, 2022, 9:51 AM MDT
Added on Jul 1, 2022, 9:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1811 of 1851
20220630_092719.jpg
Taken on Jun 30, 2022, 9:27 AM MDT
Added on Jul 1, 2022, 9:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1812 of 1851
Form detail
#40: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Jun 30, 2022
Description Eagle Island Loop Access Road HMA Density Report
Due date
Submitted by Chris Johnson
Status Closed
Last update Jul 6, 2022, 1:48 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1813 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
Density Report from the the 2 cores taken from the access road.
Rice Snip to show how the Rice was determined for calculating density. Rice sample was taken from the auger.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1814 of 1851
Form detail
#36: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 grading road base, clearing sight
distance
IMCO, General Crew 5 10 temp crane pad
MB Welding 1 10 Temp crane pad
Totals 9 30
Forms
Location
Form date Jun 29, 2022
Description Temp Crane pad, EIL Access Road grading
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 30, 2022, 7:11 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1815 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Kobelco 1100G Crane 1
Deere 225D Excavator 1
JCB 510 Boom Forklift 1
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:30 am IMCO is working on grading the access road. The pavers are scheduled for tomorrow. I discussed with
Kevin and his crew about sawcutting the existing asphalt to have clean lines to pave too. They plan on doing that.
9:00 am IMCO has placed the three stringers for the temp crane pad. MB Welding is currently welding these
stringers. They plan to get the temp crane pad done today and start removing more of the intake structure.
12:00 pm IMCO is continuing to work on setting up the temp crane pad. Kevin and I spoke about the asphalt
quantity for tomorrows paving. I have concerns they will not be brining enough mix considering the limits of the
paving have extended to match wings.
3:00 pm I have checked in at EIL where Jayden and the crew are still working on grading and prepping the edges
of existing for tomorrows paving. Since he is still working on grading we agreed to meet at 4pm to paint out the
limits of the paving, approve grade and perform a asphalt take off for quantity.
5:00 pm I recalculated the tonnage HMA. I came up with 93 tons. I notified Kevin H. with the notion that he
should also do a take off and compare to mine.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1816 of 1851
References
Photos (2)
IMG_0033
Taken on Jun 29, 2022, 8:33 AM MDT
Added on Jun 30, 2022, 7:05 AM MDT
Added by Chris Johnson
IMG_0034
Taken on Jun 29, 2022, 3:36 PM MDT
Added on Jun 30, 2022, 7:05 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1817 of 1851
Form detail
#34: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 3 10 grading road base, clearing sight
distance
IMCO, General Crew 5 10 temp crane pad
Vale Electric, Electricians 4 5 hook up job trailer
MB Welding 2 10 Temp crane pad
Totals 14 35
Forms
Location
Form date Jun 28, 2022
Description Temp crane pad, EIL access road
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 28, 2022, 6:45 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1818 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on the access road grading. I checked in with Jayden and we discussed taking the
density test.
9:00 am I performed two density tests on the road grade by direct transmission with nuclear density gauge (see
external report). Both tests passed. The crew is going to continue to get the grade set and also start trimming the
trees for the sight distance.
10:00 am IMCO is working on the temp crane pad. Kirt is starting to excavate into the side of the bank for the
stringers to span to the temp piles. MB Welding is onsite working on the temp crane pad as well. Vale Electric
arrived on site. They plan to get the office trailer powered up and also be here for the meeting at 1230 to go over
the primary feeds.
12:30 pm A conduit was found during excavation for the crane pad. It was determined that the conduit had been
drilled through by sub contractor prior to construction starting. Bentonite chips were used to backfill the
exploratory bore. This was done many months ago so it is assumed that it is an old conduit. Attended primary feed
meeting.
1:30 pm The meeting went over the new locations of the transformers for both primary power feeds. It was also
discussed to add spare conduits, this request from Derrek VanderMeer. Sam (IPC) is going to be onsite in next
week to locate the existing power locations.
3:00 pm At EIL, IMCO has brushed out the extents of what they can, without major tree falling. Bill and I met with
Jayden and asked him to clean up the bank on the North side a little more and call it good. If IPC needs to do more
we will reapproach it then.
4:00 pm IMCO has started to set the stringer beams for the temp crane pad.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1819 of 1851
References
Photos (3)
20220628_083809.jpg
Taken on Jun 28, 2022, 8:38 AM MDT
Added on Jun 28, 2022, 6:40 PM MDT
Added by Chris Johnson
IMG_0031
Taken on Jun 28, 2022, 10:43 AM MDT
Added on Jun 28, 2022, 11:06 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1820 of 1851
IMG_0032
Taken on Jun 28, 2022, 3:20 PM MDT
Added on Jun 28, 2022, 6:40 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1821 of 1851
Form detail
#33: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 EIL Access Road Grading,
compacting
IMCO, General Crew 5 10 Setup Temp Crane Pad on piles
MB Welding 2 10 Weld on Temp crane pad
Totals 9 30
Forms
Location
Form date Jun 27, 2022
Description Temp crane pad, EIL access road
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 28, 2022, 7:51 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1822 of 1851
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am IMCO is working on EIL access road. They are placing the gravel for the base and grading it to slope to
one side. The plans call for a crown but after discussing with Bill, it was decided to grade to one side to produce a
better product so the paver can make one 14’ wide pull.
11:00 pm IMCO is working at the hatchery. Last week they were able to drive 4 temp piles. MB is onsite and
welding caps on them now. This is the start of the temp crane pad.
2:00 pm I spoke with Jayden regarding the access road grading. I showed him the proctor sheet on the material
he is grading. It calls for 8.1% moisture. They had not applied any water to the base yet. After a short talk he
started placing water on the grade. We spoke about testing the grade prior to paving. He is going to continue to
apply water and start rolling the material for compaction.
3:00 pm I noticed the Intake Mechanical piping was onsite. This piping has a protective coating on it in “off white”.
I dug through the submittals and could not find the coatings inspection report. I did however find in the coatings
submittal that the inspection would be submitted at a later date. I spoke to Kevin H. regarding this. He said he
would get the inspection report and get it submitted before they install it. MB Welding is working on reinforcing
the crane pad stringer beam.
4:00 pm Jayden is continuing to work on applying water and compacting the EIL access road.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1823 of 1851
References
Photos (5)
20220627_115358.jpg
Taken on Jun 27, 2022, 11:53 AM MDT
Added on Jun 28, 2022, 7:48 AM MDT
Added by Chris Johnson
20220627_120450.jpg
Taken on Jun 27, 2022, 12:04 PM MDT
Added on Jun 28, 2022, 7:49 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1824 of 1851
20220627_120501.jpg
Taken on Jun 27, 2022, 12:05 PM MDT
Added on Jun 28, 2022, 7:50 AM MDT
Added by Chris Johnson
20220627_153142.jpg
Taken on Jun 27, 2022, 3:31 PM MDT
Added on Jun 28, 2022, 7:50 AM MDT
Added by Chris Johnson
20220627_153156.jpg
Taken on Jun 27, 2022, 3:31 PM MDT
Added on Jun 28, 2022, 7:50 AM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1825 of 1851
Form detail
#32: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
Forms
Location
Form date Jun 22, 2022
Description Sawtooth Welding Crowder Mock up
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 27, 2022, 2:09 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1826 of 1851
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
12:00 pm Attended mockup crowder demo at Sawtooth Welding. Schnabel representatives are onsite. Randy, SW,
operated the crowder multiple times while Schnabel witnessed and went over concerns.
References
Photos (1)
IMG_0030
Taken on Jun 22, 2022, 12:28 PM MDT
Added on Jun 27, 2022, 2:09 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1827 of 1851
Form detail
#31: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 10 Installing Silt Curtain, Prep Crane
pad
Vale Electric, Electricians 2 5 Deenergize intake, remove
disconnect and cables
IMCO, General Crew 2 10 Eagle Island Loop access road,
clearing for fence
MB Welding 1 10 Weld temp crane pad
Forms
Location
Form date Jun 21, 2022
Description Eagle Island Loop, Hatchery Intake
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 27, 2022, 1:59 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1828 of 1851
Crew # Workers # Total
hours
Work performed
Boise River Fence 3 10 EIL Fence
Totals 13 45
2. Materials
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO crew is working at EIL on grading the access road along with prepping for Boise River Fence to be
onsite. They are working on clearing for the new fence.
9:00 am Boise River fence is onsite. I spoke with Heath regarding the gate locations. I laid out the gate locations
from Heaths direction. We also discussed the clearing for sight distance for the access road. Kevin and I discussed
last night to clear as much as they could with the tools they have. If more clearing is needed it would discussed and
a quantity would be generated accordingly. Itsy is asking to make the corner safe to be used.
10:00 am IMCO is working at the hatchery site. Vale Electric is onsite and working on deenergizing the intake
structure.
12:00 pm The crew is continuing to work on installing the silt curtain. Vale is done for the day. They were able to
pull the cable out of conduit. Bill Lynch is onsite and went over the salvage and recycle of the existing material. Rick
also made a stop. We discussed the irrigation pump. Kevin H. is going to work on a plan for the irrigation pump.
2:00 pm Attended weekly meeting. I spoke to BRF and Heath regarding switching the gates to a single gate
instead of the double. Heath agreed it was a good idea. BRF did not care either way. So a single gate was decided.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1829 of 1851
3:00 pm IMCO is going to work on getting the silt curtain installed.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1830 of 1851
Form detail
#30: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Eagle Island loop access road
IMCO, General Crew 3 10 Inventory material
MB Welding 1 10 Weld temp crane pad
Totals 6 30
2. Materials
Forms
Location
Form date Jun 20, 2022
Description Eagle Island Loop, Hatchery Inventory
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 21, 2022, 1:41 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1831 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
11:00 am IMCO crew is working at EIL on the access road. They are currently installing the culvert and getting it
backfilled. I spoke to Jayden about clearing out more brush to help with the sight distance.
12:00 pm IMCO at the hatchery is working on moving the rest of the materials under the tent. They have been
issued NTP for the intake work. They plan to install the silt curtain tomorrow once their crane operator is onsite.
3:00 pm IMCO is continuing to work on EIL. The crew has been shifted to clear out the brush around the trees
along the fence. Boise River Fence is due to be onsite tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1832 of 1851
References
Photos (1)
20220620_113535.jpg
Taken on Jun 20, 2022, 11:35 AM MDT
Added on Jun 20, 2022, 12:16 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1833 of 1851
Form detail
#28: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
MB Welding 2 10 Fabricating crane pad
IMCO, General Crew 3 10 Material tent
IMCO, General Crew 2 10 Eagle Island access road
Totals 7 30
2. Materials
Forms
Location
Form date Jun 15, 2022
Description Eagle Island Loop, Hatchery Inventory, Crane Pad
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 17, 2022, 7:59 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1834 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on the access road. Jayden plans to knock the tree down that is in the proposed
shoulder today.
12:00 pm At the hatchery, MB welding is onsite working on the temp crane pad. They are welding the frame
together now. IMCO is working on installing their GPS base station along with putting the inventory tent up.
3:00 pm IMCO is still working on the access road. They are using the mini and the backhoe to load and haul
woody debris to the dump site.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1835 of 1851
References
Photos (2)
20220615_100801_photo
Taken on Jun 15, 2022, 10:07 AM MDT
Added on Jun 15, 2022, 10:08 AM MDT
Added by Chris Johnson
20220615_123929_photo
Taken on Jun 15, 2022, 12:38 PM MDT
Added on Jun 15, 2022, 12:41 PM MDT
Added by Chris Johnson
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1836 of 1851
Form detail
#29: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Access Road
IMCO, General Crew 3 10 Inventory, Lay out for MB Welding,
Tent
Totals 5 20
2. Materials
Forms
Location
Form date Jun 14, 2022
Description Eagle Island Loop, Hatchery Inventory
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 15, 2022, 11:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1837 of 1851
Material Quantity Unit Comment
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
8:00 am IMCO is working on the access road at EIL. Jayden has started cutting to subgrade. It looks to me that a
few trees need to be removed. I will talk to Heath about those.
9:00 am IMCO is working on laying out the tent to cover the material. They are also working on setting up the
office trailer. Vale is dropping off their office trailer and hooking up power to both.
12:00 pm Kirt has laid out two beams to be welded. These beams are for the crane structure to install the piles.
MB Welding will be onsite tomorrow to start welding.
1:00 pm It was discussed to remove the trees in the way for the access road at EIL. Jayden is continuing to cut to
subgrade. Heath and I discussed the gate locations. He is running on the assumption for Itsy, IPC, that the fence is
wrapping around the corner. I told him I would discuss this all in the meeting.
2:00 pm Attended weekly meeting.
5:00 pm The crew has mobilized the backhoe back to EIL and using it to transport woody debris to the dump pile.
They will continue the access road tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1838 of 1851
Form detail
#27: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 2 10 Access Road
IMCO, General Crew 3 10 Tent Setup, Inventory, Office Setup
Totals 5 20
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jun 13, 2022
Description Eagle Island Loop, Hatchery Inventory
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 14, 2022, 4:35 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1839 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:30 am Arrived at Eagle Island Loop. Crew is working on trimming trees and getting ready to start the access
road. They have been compacting the rock placed at the sites.
12:00 pm The crew is setting up the office at the hatchery. They have been working on setting containers and
leveling out a place for the tent. They plan to import rock starting tomorrow.
5:00 pm The crew started on the access road. It looks like the existing asphalt is less than 1” thick. They will
continue working on it tomorrow.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1840 of 1851
Form detail
#24: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 5 50 Grading, Inventory
Totals 5 50
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jun 7, 2022
Description Eagle Island Loop, Hatchery Inventory
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 7, 2022, 5:17 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1841 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Mini Excavator
Backhoe
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
7:00 am The crew is starting to work at Eagle Island Loop. Today they plan to work on clearing the rest of the
sites and backfilling around all the hydrants.
12:00 pm IMCO has one laborer and one operator at the hatchery working on inventorying material that has
been delivered. They are also working on taking material that is being delivered. There has been multiple loads of
keystone retaining wall blocks delivered.
5:00 pm IMCO has had a truck hauling rock from Brownlee most of the day. The rock is for the bottom sites. The
truck has been dumping in place and IMCO has been using the mini to spread the rock. The crew is done for the
day.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1842 of 1851
Form detail
#21: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
IMCO, General Crew 4 44 Water Tie-Ins, New Hydrants
installed
Totals 4 44
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jun 6, 2022
Description Eagle Island Loop
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 7, 2022, 9:16 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1843 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
Mini Excavator
Backhoe
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Notes
10:00 am Arrived on site. IMCO crew is shutting off the water to make the multiple tie ins. Derrick, IPC, has moved
his motorhome to the upper loop to allow the crew to work on his site. Today they plan to just get the water
hydrants installed, cap the irrigation line, and make the tie in for the last two spots on the upper loop.
3:00 pm The crew is still working on making the tie in at the upper last two spots. They have installed all the
hydrants and capped the couple of saddles that did not need new hydrants.
5:00 pm The crew is working on capping the irrigation and the water line. They did not have the correct gaskets
so they are having to use the ones they have and will need to replace them once they get the new ones which
should be Thursday.
6:00 pm The crew has capped the line and is now working on getting the water back on.
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1844 of 1851
Form detail
#26: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
Sawtooth Welding
Totals 0 0
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date Jun 6, 2022
Description Sawtooth Welding, Welding Inspection
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 9, 2022, 9:00 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1845 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1846 of 1851
Form detail
#25: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
Sawtooth Welding
Totals 0 0
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date May 31, 2022
Description Sawtooth Welding, Welding Inspection
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 9, 2022, 8:59 AM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1847 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1848 of 1851
Form detail
#22: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
Sawtooth Welding Welding Inspection
Totals 0 0
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date May 16, 2022
Description Sawtooth Welding, Welding Inspection Report
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 7, 2022, 1:46 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1849 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1850 of 1851
Form detail
#23: Daily Report -Standard
1. Work Log
Crew # Workers # Total
hours
Work performed
Sawtooth Welding Welding Inspection
Totals 0 0
2. Materials
Material Quantity Unit Comment
Forms
Location
Form date May 9, 2022
Description Sawtooth Welding, Welding Inspection
Due date
Submitted by Chris Johnson
Status Closed
Last update Jun 7, 2022, 1:47 PM MDT
Last updated by Chris Johnson
Included references Photos
Oxbow Hatchery Renovation Form detail report
Created by Zack Schaumburg with Autodesk® Construction Cloud™ on Aug 1, 2024 at 6:47 AM MDT Page 1851 of 1851
3. Equipment
Equipment Quantity Hours
used
Comment
4. Signature
Chris Johnson, HMH Engineering
-
4.1