Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
20240806IPC to Staff Response No. 31(c) - Attachment 6 - Schedule - Engineering Design.pdf
Response to Staff Request No. 31 c - Attachment 6 ID Task Name Duration Start Finish Predecessors 12020 Dec Jan Feb Mar Apr May Jun Jul AugSep Oct 1 Award of Contract 0 days Fri 12/20/19 Fri 12/20/19 ♦ Award of Contract 2 3 Planning&Preliminary Design 54 days Tue 1/14/20 Fri 3/27/20 Planning&Preliminary Design 4 0 Kickoff Meeting 1 day Tue 1/14/20 Tue 1/14/20 1/14 Kickoff Meeting 5 Surveying 10 days Wed 1/15/20 Tue 1/28/20 4 1115 6 Intake Inspection 3 days Wed 1/15/20 Fri 1/17/20 4 1/15 7 Geotechnical Investigation 20 days Wed 1/29/20 Tue 2/25/20 5 1/29 8 ® Site Visits 3 days Tue 1/21/20 Thu 1/23/20 1/21 Site Visits 9 Bioprogramming 15 days Fri 1/24/20 Thu 2/13/20 8 1/24 Bioprogramming 10 IPC Review of Bioprogram 5 days Fri 2/14/20 Thu 2/20/20 9 2/14 11 Draft Conceptual Design of Facilities 20 days Fri 2/14/20 Thu 3/12/20 9 2/14 12 IPC Review of Draft Conceptual Design 5 days Fri 3/13/20 Thu 3/19/20 11 3/13 13 Finalize Conceptual Design&Bioprogram 6 days Fri 3/20/20 Fri 3/27/20 12 3/20 14 Submit 10%Design and Final Bioprogram 0 days Fri 3/27/20 Fri 3/27/20 13 3/27 15 16 Final Design 147 days Mon 3/30/20 Tue 10/20/20 Fi 17 30%Design 30 days Mon 3/30/20 Fri 5/8/20 14 3/30 30%Design 18 IPC Review 10 days Mon 5/11/20 Fri 5/22/20 17 5/11 IPC Review 19 60%Design 45 days Mon 5/11/20 Fri 7/10/20 17 5/11 60%Design 20 IPC Review 10 days Mon 7/13/20 Fri 7/24/20 19 = 7/13 IPC Review 21 90%Design 42 days Mon 7/13/20 Tue 9/8/20 19 7/13 90%Design 22 IPC Review 10 days Wed 9/9/20 Tue 9/22/20 21 9/9 IPC Review 23 Bid Ready Documents 20 days Wed 9/23/20 Tue 10/20/20 22 9/23 Bid Figure 6.1 Oxbow Fish Hatchery Renovation Design Schedule