0 Mode Oct Nov Dec Jan Feb Mar Apr May Jun Jul Au Se Oct Nov Dec Jan Feb Mar Apr May Jun Jul AugSe Oct Nov Dec Jan Feb I Mar Apr
1 !W Oxbow Hatchery Renovation Anticipated Schedule 537 days Mon 11/9/20
2 Permitting and Clearances 400 days Mon 11/9/20 W Permitting and Clearances
3 Outages/Key Dates 360 days Mon 5/17/21
4 Well/Incubation Outage 55 days Mon 5/17/21 Well/Incubation Outage
5 Intake/Ponds Outage 66 days Thu 7/1/21 Intake/Ponds Outage
6 Well/Incubation Outage 77 days Mon 11/1/21 Well/Incubation Outage
7 Well/Incubation Outage 55 days Mon 5/16/22 Well/Incubation Outage
8 ® !; Intake/Ponds Outage 110 days Mon 5/2/22 Intake/Ponds Outage
9 Anticipated Construction Window 432 days Mon 4/5/21 0 0
10 Mobilize 1 day Mon 4/5/21 Mobilize
11 Demo old Raceways (not ponds) 60 days Mon 4/12/21 Demo old Raceways (not ponds)
12 ® !; Civil and Yard Piping 385 days Mon 4/12/21 Civil and Yard Piping
13 New Adult Holding Building 385 days Mon 4/12/21 New Adult Holding Building
14 Sorting and Spawning Building 385 days Mon 4/12/21 Sorting and Spawning Buildi
15 Warehouse Building 385 days Mon 4/12/21 Warehouse Building
16 Aeration Tower 385 days Mon 4/12/21 Aeration Tower
17 ® !} Chiller, Incubation, and Office Building 215 days Mon 4/12/21 Chiller, Incubation, and Office Building
18 Demo Existing Incubation 77 days Mon 11/1/21 Demo Existing Incubation
19 *Chiller and Incubation Fully Commissioned Milestone 0 days Fri 2/4/22 <` 2/4
20 Intake Structure Window 110 days Mon 5/2/22 Intake Structure Window
21 ® !; Adult Holding, Aeration Tower, and Intake Fully 0 days Fri 9/30/22 O 9/30
Commissioned Milestone
22 ® !} Demo Adult Ponds 50 days Mon 5/2/22 Demo Adult Ponds
23 ® !; Finish Site Work 130 days Mon 5/2/22 Finish Site Work
24 Substantial Completion 0 days Fri 10/28/22 10/28
25 Final Completion 0 days Wed 11/30/22 11/30
Task Project Summary 9 I Manual Task Start-only E Deadline
Project: Anticipated Constructio Split Inactive Task Duration-only Finish-only _ Progress
Date: Fri 1122121 Milestone A Inactive Milestone Manual Summary Rollup I External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone