HomeMy WebLinkAbout20240731IPC to Staff 17-30.pdf 0-10AM POWER.
LISA D. NORDSTROM RECEIVED
Lead Counsel Wednesday, July 31, 2024
InordstromCaDidahopower.com IDAHO PUBLIC
UTILITIES COMMISSION
July 31, 2024
VIA ELECTRONIC FILING
Commission Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg 8,
Suite 201-A (83714)
PO Box 83720
Boise, Idaho 83720-0074
Re: Case No. IPC-E-24-07
Application of Idaho Power Company for Authority to Increase Rates for
Electric Service to Recover Costs Associated with Incremental Capital
Investments and Certain Ongoing Operations and Maintenance Expenses
Dear Commission Secretary:
Attached for electronic filing, please find Idaho Power Company's Response to the
Fourth Production Request of the Commission Staff to Idaho Power Company.
Due to the collectively voluminous confidential and non-confidential information
provided in response to data requests in this case, the Company is posting the
attachments to these requests to the secure FTP site to allow parties to view the
requested information remotely unless otherwise noted in the response. Because certain
attachments contain confidential information, the FTP site is divided between confidential
and non-confidential information.
The login information for the non-confidential portion of the FTP site has been
provided to all parties that have intervened to date. The login information for the
confidential portion of the FTP site will be provided to the parties that execute the
Protective Agreement in this matter.
Given the significant time and resources required to individually label each
confidential document contained in the 390 MB of confidential attachments, Idaho Power
has instead marked the entirety of the contents contained within Production Response
Nos. 17(b) Attachment 3, 18(b) Attachment 3, 19(b) Attachment 4, 19(b) Attachment 5,
20(c) Attachment 7, 20(c) Attachment 8, 20(c) Attachment 9, 20(c) Attachment 10, 20(c)
Attachment 12, 20(c) Attachment 13, 20(c) Attachment 14, 20(c) Attachment 15, 20(c)
Attachment 16, 20(e) Attachment 4, 21(c) Attachment 4, 21(c) Attachment 5, 21(c)
Attachment 6, 21(c) Attachment 7, 21(e) Attachment 4, 22(c) Attachment 7, 22(c)
Attachment 8, 22(c) Attachment 9, 22(c) Attachment 10, 22(c) Attachment 11, and 22(e)
Commission Secretary
Idaho Public Utilities Commission
July 31, 2024
Page 2
Attachment 5, confidential by designating the Attachment folder and individual file name
as "CONFIDENTIAL".
If you have any questions about the attached filing, please do not hesitate to
contact me.
Very truly yours,
S. hen.,
Lisa D. Nordstrom
LDN:sg
Enclosures
CERTIFICATE OF ATTORNEY
ASSERTION THAT INFORMATION CONTAINED IN AN IDAHO PUBLIC UTILITIES
COMMISSION FILING IS PROTECTED FROM PUBLIC INSPECTION
Case No. IPC-E-24-07
Idaho Power Company's Application for Authority to Increase Rates for Electric
Service to Recover Costs Associated with Incremental Capital Investments and
Certain Ongoing Operations and Maintenance Expenses
The undersigned attorney, in accordance with Commission Rules of Procedure 67,
believes that some of the attachments to Request Nos. 17, 18, 19, 20, 21, 22, and 23 to
Idaho Power Company's Response to the Fourth Production Request of the Commission
Staff dated July 31, 2024, contain information that Idaho Power Company and/or a third
party claim are trade secrets, business records of a private enterprise required by law to
be submitted to or inspected by a public agency, and/or public records exempt from
disclosure by state or federal law (material nonpublic information under U.S. Securities
and Exchange Commission Regulation FD) as described in Idaho Code § 74-101, et seq.,
and/or § 48-801 , et seq. As such, it is protected from public disclosure and exempt from
public inspection, examination, or copying.
DATED this 31st day of July 2024.
LISA D. NORDSTROM
Attorney for Idaho Power Company
LISA D. NORDSTROM (ISB No. 5733)
DONOVAN E. WALKER (ISB No. 5921)
MEGAN GOICOECHEA ALLEN (ISB No. 7623)
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-5825
Facsimile: (208) 388-6936
Inordstrom(a)_idahopower.com
dwalker idahopower.com
mgoicoecheaallen(o)_idahopower.com
Attorneys for Idaho Power Company
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION )
OF IDAHO POWER COMPANY TO ) CASE NO. IPC-E-24-07
INCREASE RATES FOR ELECTRIC )
SERVICE TO RECOVER COSTS ) IDAHO POWER COMPANY'S
ASSOCIATED WITH INCREMENTAL ) RESPONSE TO THE FOURTH
CAPITAL INVESTMENTS AND ) PRODUCTION REQUEST OF THE
CERTAIN ONGOING OPERATIONS ) COMMISSION STAFF TO IDAHO
AND MAINTENANCE EXPENSES. ) POWER
COMES NOW, Idaho Power Company ("Idaho Power" or "Company"), and in
response to the Fourth Production Request of the Commission Staff ("Commission" or
"Staff") to Idaho Power Company dated July 10, 2024, herewith submits the following
information:
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 1
REQUEST FOR PRODUCTION NO. 17: Please provide the following
documentation for the 60 MW Franklin BESS project referenced by Hackett Direct at 8. If
any of the information requested below cannot be provided or is not available, please
explain why it is not available or cannot be provided.
a. Please provide the approved Initial Project Plan including the following:
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence the Initial Project Plan and budget was approved at the appropriate
level.
b. Please provide the Baseline Construction Project Plan including the following:
i. Baseline project scope;
ii. Baseline project budget broken down by Work-Breakdown Structure
("WBS").
iii. Baseline project schedule broken down by the WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
c. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 2
ii. Baseline construction schedule-to-actual comparison by WBS;
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 17:
a. Please note, the Company's ownership of the 60 megawatt (WW") Franklin
Battery Energy Storage System ("BESS") was obtained through a Build Transfer
Agreement ("BTA") with Duke Energy Solar ("Duke"), which included the purchase
of the BESS, co-located with the Franklin Solar 100 MW solar photovoltaic ("PV")
facility. The BTA provides for the transfer to Idaho Power from Duke Energy Solar
of 100 percent of the equity interests in the Franklin BESS once mechanical
completion is reached. Because Idaho Power is not constructing the project, the
Company did not develop the project plan. However, the Build Transfer Agreement
dated as of January 20, 2023, by and between Idaho Power Company and Duke
Energy Renewables Solar, LLC, ("Franklin BESS BTA"), provided as Response to
Request for Production No. 17(a) — Confidential Attachment 1, provides many of
the items typically discussed in a project plan.
i. Please see Appendix A, Section 3 of the Franklin BESS BTA for the scope of
work provided as Response to Request for Production No. 17(a) — Confidential
Attachment 1.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 3
ii. Please see Response to Request for Production No. 17(a) — Confidential
Attachment 2 for the Budget Update — Authorized to Spend spreadsheet that
identifies the original approved budget amount of$125 million.
iii. Please see Article 10 and Appendix B of the Franklin BESS BTA for the
preliminary project schedule.
iv. Capital projects begin with the creation of a capital budget ID ("BID"). Then
Idaho Power utilizes several approval processes throughout the life cycle of a
project. First, employees and leaders evaluate project requests and establish
a general conceptual level scope, estimate, and schedule incorporating
feedback from project sponsors, subject matter experts, and leadership. The
project requests are then evaluated amongst the many requests each year and
ultimately prioritized and approved through the annual capital budget process.
As part of that process, managers submit capital project proposals for senior
management review. Then capital projects are reviewed and approved by the
executive management team. Finally, the capital budget is then reviewed and
approved by the Idaho Power Board of Directors.
Once a project is approved, a work order ("WO") can then be created. A
WO is created in Asset Suite (an enterprise resource planning tool) with
required fields such as WO type, associated BID, capital indicator, location,
accounting string, project estimate, property units. Then the WO is submitted
for review and approval in Asset Suite, routing to the appropriate leader based
on designated approval thresholds tied to the project estimate. Once approved,
WO information is transferred to PeopleSoft Projects, the Company's financial
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-4
accounting software. Costs can then accumulate on WOs. Once the resulting
asset can be used, the WO is placed in-service.
BIDs may have a one-to-one association with a project (one BID to one
project/WO) or may have a one-to-many association (one BID to many
projects/WOs). Some BIDs are used to capture costs associated with a
category of capital spend rather than a specific project and are estimated based
on historic trends and growth projections. The BIDs are used to budget for and
accumulate costs associated either with a specific project or category of capital
spend. Throughout the year, projects are evaluated and re-forecasted as
necessary to increase or reduce forecasted spend during the remaining life of
the project. However, these updated forecasts are not retroactively used to
adjust the approved budget for that year, the original approved budget for that
year stays as originally approved.
Idaho Power monitors its capital budget monthly through variance analysis
reporting and quarterly through budget update analysis and reporting.
Additionally, the majority of capital spend is managed within the Planning,
Engineering, and Construction business unit which continuously manages and
scrutinizes changes in scope, budget, or schedule on a monthly basis through
MS Project Server scheduling software. These approvals happen in real-time
based on the overall portfolio limits and are approved or denied. The changes,
as appropriate, are documented by revising the scope, design drawings,
construction specifications, and other pertinent documents and the budget and
schedule are updated in MS Project related to forward action items that
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 5
overwrite previous plans. Baseline schedule comparisons to actual schedule
delivery are not compared due to the ever-changing landscape of the entire
portfolio of capital projects. Rather, projects are managed in real-time, and
schedules are regularly monitored in comparison to the entire portfolio of
projects to manage timeline and execution strategy, in conjunction with all other
capital project needs. Project schedules are updated at least monthly for
resource leaders to evaluate planned work across the matrixed organization.
Variances in budget forecasts are also regularly evaluated and monitored
within the overall portfolio of projects.
The creation of the BID FRBS230001 for the 60 MW Franklin BESS and
corresponding original approved budget reflected in the Response to Request
for Production No. 17(a) — Confidential Attachment 2, the Budget Update —
Authorized to Spend spreadsheet, is evidence of approval of the initial budget.
b. See part (a) above. Because Idaho Power is acquiring the 60 MW Franklin
BESS from Duke upon mechanical completion, there are no additional project
plans.
i. Not applicable. The project scope did not change from what was first identified
in the Franklin BESS BSA.
ii. As explained in part (a)(iv), the 60 MW Franklin BESS project is continuously
managed and scrutinized on a monthly basis through MS Project Server
scheduling software. Any changes in scope, budget, or schedule, are approved
in real-time based on the overall portfolio limits. The changes, as appropriate,
are documented by revising the scope, design drawings, construction
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 6
specifications, and other pertinent documents and the budget and schedule are
updated in MS Project related to forward action items that overwrite previous
plans. Therefore, the only WBS the Company can provide for the project is
reflective of the most recent budget and schedule. Please see the Response
to Request for Production No. 17(b) — Confidential Attachment 1 for the 60 MW
Franklin BESS project WBS.
iii. See part (b)(ii).
iv. Please see Appendix B of the Amendment to Build Transfer Agreement,
provided as the Response to Request for Production No. 17(b) — Confidential
Attachment 2, for the project schedule update amended as of April 26, 2023.
The baseline construction project scope and budget have not changed
significantly, but some schedule changes occurred, as detailed in part (c)(iv)
below.
v. Please see the Response to Request for Production No. 17(b) — Confidential
Attachment 3 for the Progress Reports associated with the 60 MW Franklin
BESS. Note, the Progress Reports are reporting on the status of the combined
100 MW solar PV facility and the 60 MW Franklin BESS.
vi. There have been no change orders associated with the Franklin BESS BTA.
Please note, the progress reports reference change orders however those are
change orders between Duke and their subcontractors, not change orders
associated with the agreement with Idaho Power.
c. i. As explained in part (a), because the 60 MW Franklin BESS is a full turn-key
project from design and engineering to procurement and construction, Idaho
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 7
Power is not constructing the project but rather makes payments to Duke for
the BESS in accordance with the Franklin BESS BTA. These are reflected on
the WBS in the Purchased Services category provided as the Response to
Request for Production No. 17(b) — Confidential Attachment 1 .
ii. Not applicable. See part (b)(ii).
iii. As explained in part (a)(iv), throughout the year, capital projects are evaluated
and re-forecasted as necessary to increase or reduce forecasted spend during
the remaining life of the project. The changes are monitored monthly through
variance analysis reporting and quarterly through budget update analysis and
reporting. The budget updates reflected in the Response to Request for
Production No. 17(a) — Confidential Attachment 2, the Budget Update —
Authorized to Spend spreadsheet are evidence of approval of the updated
budget amounts associated with the project. For the 60 MW Franklin BESS,
which was managed through MS Project Schedule, Idaho Power has pulled the
variance notes documenting the reason for the change in budget update, if one
occurred. See the Response to Request for Production No. 17(c) —Attachment
for the 60 MW Franklin BESS project budget update Variance Notes.
iv. The following table presents the adjustments to the Guaranteed Substantial
Completion Date and Final Acceptance Date, caused by unforeseen project
challenges. Specifically, complications from network equipment problems and
a failure of the site's auxiliary transformer, resulting in delays to the BESS site's
energization process. Consequently, this has deferred the commissioning
schedule of the BESS equipment. Presently, the site has entered the
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 8
commissioning phase, with the BESS undergoing active charge and discharge
cycles.
Construction Schedule
BTA Milestone Forecasted
Milestone Completion Date Completion Date
Guaranteed Substantial
Completion Date 6/1/2024 8/12/2024
Final Acceptance 8/1/2024 I 9/10/2024
The response to this Request is sponsored by Eric Hackett, Projects and Resource
Development Director, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 9
REQUEST FOR PRODUCTION NO. 18: Please provide the following
documentation for the 36 MW Hemingway station BESS project referenced by Hackett
Direct at 8. If any of the information requested below cannot be provided or is not
available, please explain why it is not available or cannot be provided.
a. Please provide the approved Initial Project Plan including the following:
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence that the Initial Project Plan and budget were approved at the
appropriate level.
b. Please provide the Baseline Construction Project Plan including the following:
i. Baseline project scope;
ii. Baseline project budget broken down by WBS;
iii. Baseline project schedule broken down by WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
c. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
ii. Baseline construction schedule-to-actual comparison by WBS;
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 10
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 18:
a. As described in Case Nos. IPC-E-23-05 and IPC-E-23-20, Idaho Power's requests
for a Certificate of Public Convenience and Necessity ("CPCN") associated with
the 36 MW Hemingway BESS, for which the Commission issued Certificate Nos.
544 and 547, the Company experienced a rapid change in the 2024 capacity
position, first identifying the June 2024 deficiency in May 2021 . To meet its
obligation to reliably serve customer load and fill the 2024 capacity deficiency, the
Company conducted a competitive solicitation through a Request for Proposal
("RFP") soliciting proposals for the acquisition of 85 MW of electric energy and
capacity to be online by June of 2024. The procurement process resulted in the
acquisition of least-cost, least-risk resources necessary to fill the 2024 capacity,
including the 36 MW Hemingway BESS. The scope and project plan are primarily
comprised of preliminary design drawings which were adapted throughout the
design and construction phase. The Energy Sales Agreement ("ESA") dated June
8, 2023, provided as Response to Request for Production No. 18(a)— Confidential
Attachment, provides many of the items typically discussed in a project plan. In
addition to the ESA, typical scope items include supporting infrastructure and
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 11
ancillary equipment such as foundations, conduit, grounding, medium-voltage
transformers, cables, and electrical equipment.
i. Please see Exhibit A to the Hemingway ESA for the initial project scope.
ii. Please see Response to Request for Production No. 17(a) — Confidential
Attachment 2 for the Budget Update — Authorized to Spend spreadsheet that
identifies the original approved budget amount of$28.6 million. Note, when the
BID was established, the project was initially envisioned as a 12 MW BESS and
the $28.6 million budget established. However, as described in the Company's
request in Case No. IPC-E-23-20,1 for which Idaho Power was granted a
CPCN, the capacity deficiency in 2024 increased, necessitating the 36 MW
Hemingway BESS, and an increase in the budget of approximately $36.9
million, for a total original approved budget of $65.5 million.
iii. Please see Exhibit D to the Hemingway ESA for the initial project schedule.
iv. Please see the Company's Response to Request for Production No. 17(a)(iv)
for the project budget approval process. The creation of the BID HMWY230003
for the 36 MW Hemingway BESS and corresponding approved budget amounts
reflected in the Response to Request for Production No. 17(a) — Confidential
Attachment 2, the Budget Update — Authorized to Spend spreadsheet, is
evidence of approval of the initial budget.
b. i. Not applicable. The project scope did not change from what was first identified
in the Hemingway ESA.
In the Matter of Idaho Power Company's Application for a Certificate of Public Convenience and
Necessity to Acquire Resources to be Online in Both 2024 and 2025 and for Approval of an Energy
Storage Agreement with Kuna BESS LLC, Case No. IPC-E-23-20, Application at 5 and Ellsworth DI
testimony.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 12
ii. As explained in part (a)(iv), the 36 MW Hemingway BESS project is
continuously managed and scrutinized on a monthly basis through MS Project
Server scheduling software. Any changes in scope, budget, or schedule, are
approved in real-time based on the overall portfolio limits. The changes, as
appropriate, are documented by revising the scope, design drawings,
construction specifications, and other pertinent documents and the budget and
schedule are updated in MS Project related to forward action items that
overwrite previous plans. Therefore, the only WBS the Company can provide
for the project is reflective of the most recent budget and schedule. Please see
the Response to Request for Production No. 18(b) — Confidential Attachment
1 for the 36 MW Hemingway BESS project WBS.
iii. See part (b)(ii).
iv. Aside from the delay in delivery discussed in part (c)(iv) below, there have been
no significant changes to the construction project scope, budget or schedule as
envisioned initially.
v. Please see the Response to Request for Production No. 18(b) — Confidential
Attachment 2 for status updates provided by Idaho Power personnel currently
managing the project as well as the Response to Request for Production No.
18(b) — Confidential Attachment 3 for the Powin contractor field logs.
vi. There have been no change orders associated with the Hemingway ESA.
c. i. Not applicable. See part (b)(ii).
ii. Not applicable. See part (b)(ii).
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 13
iii. As explained in part (a)(iv), throughout the year, capital projects are evaluated
and re-forecasted as necessary to increase or reduce forecasted spend during
the remaining life of the project. The changes are monitored monthly through
variance analysis reporting and quarterly through budget update analysis and
reporting. The budget updates reflected in the Response to Request for
Production No. 17(a) — Confidential Attachment 2, the Budget Update —
Authorized to Spend spreadsheet are evidence of approval of the updated
budget amounts associated with the project. For the 36 MW Hemingway BESS,
which was managed through MS Project Schedule, Idaho Power has pulled the
variance notes documenting the reason for the change in budget update, if one
occurred. See the Response to Request for Production No. 18(c) —Attachment
for the 36 MW Hemingway BESS project budget update Variance Notes.
iv. Delayed delivery of the battery equipment has resulted in delayed plant
operation. However, all battery equipment has now arrived at the project site,
with battery segment deliveries occurring between April 2, 2024, and May 20,
2024. Field commissioning activities by Powin continue and plant operation is
expected to occur late summer 2024.
The response to this Request is sponsored by Eric Hackett, Projects and Resource
Development Director, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 14
REQUEST FOR PRODUCTION NO. 19: Please provide the following information
for the 40 MW 2023 Peak Capacity Resource project referenced by Larkin Workpaper 3
at 11. Please include any available workpapers with formulas intact. If any of the
information requested below cannot be provided or is not available, please explain why it
is not available or cannot be provided.
a. Please provide the approved Initial Project Plan including the following:
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence that the Initial Project Plan and budget were approved at the
appropriate level.
b. Please provide the Baseline Construction Project Plan including the following:
i. Baseline project scope;
ii. Baseline project budget broken down by WBS;
iii. Baseline project schedule broken down by WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
c. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 15
ii. Baseline construction schedule-to-actual comparison by WBS;
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 19:
a. As described in Case No. IPC-E-22-13, Idaho Power's Application for a Certificate
of Public Convenience and Necessity to Acquire Resources to be Online by 2023
to Secure Adequate and Reliable Service to its Customers, for which the
Commission issued Certificate No. 538, the Company experienced a rapid change
in the 2023 capacity position, first identifying the June 2023 deficiency in May
2021 . To meet its obligation to reliably serve customer load and fill the 2023
capacity deficiency, the Company conducted a competitive solicitation through an
RFP seeking to acquire up to 80 MW of peak capacity resources, to be online by
June of 2023. The procurement process resulted in the acquisition of least-cost,
least-risk resources necessary to fill the 2023 capacity, including the 40 MW Black
Mesa BESS. The scope and project plan are primarily comprised of preliminary
design drawings which were adapted throughout the design and construction
phase. The Battery Energy Supply Agreement between Idaho Power Company,
as Buyer and Powin, LLC, as Supplier, Black Mesa Project, February 28, 2022,
("Black Mesa BESX), provided as Response to Request for Production No. 19(a)
— Confidential Attachment 1 , as well as Change Order#01, included as Response
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 16
to Request for Production No. 19(a) — Confidential Attachment 2, which define
additional contract provisions and provide general information requested. In
addition to the Black Mesa BESA, typical scope items include supporting
infrastructure and ancillary equipment such as foundations, conduit, grounding,
medium-voltage transformers, cables, and electrical equipment.
i. Idaho Power entered into agreements to purchase peak capacity resources for
up to 120 MW of electric generating capacity to be online by June of 2023.
Please see Exhibit A to the Black Mesa BESA, which is included in Change
Order#01 , for the initial project scope.
ii. The budget was established as a result of a Request for Quotes as well as
design estimates. Please see Response to Request for Production No. 17(a) —
Confidential Attachment 2 for the Budget Update — Authorized to Spend
spreadsheet that identifies the original approved budget amount of $68.9
million.
iii. The project was first identified in 2021 and was anticipated to be commercially
operational in the third quarter of 2023. Please see Exhibit D to the Black Mesa
BESA for the initial project schedule.
iv. Please see the Company's Response to Request for Production No. 17(a)(iv)
for the project budget approval process. The creation of the BID BMSU220002
for the 40 MW Black Mesa BESS and corresponding original approved budget
reflected in the Response to Request for Production No. 17(a) — Confidential
Attachment 2, the Budget Update — Authorized to Spend spreadsheet, is
evidence of approval of the initial budget.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 17
b. i. Not applicable. The project scope did not change from what was first
identified in the Black Mesa BESA.
ii. See the Company's Response to Request for Production No. 17(b)(ii). The only
WBS the Company can provide for the project is reflective of the most recent
budget and schedule. Please see the Response to Request for Production No.
19(b) — Confidential Attachment 1 for the 40 MW Black Mesa BESS project
WBS.
iii. Not applicable. See part (b)(ii).
iv. For the 40 MW Black Mesa BESS project, which was managed through MS
Project Server, Idaho Power has pulled the variance notes documenting the
reason for the change in budget update, if one occurred. See the Response to
Request for Production No. 19(b) — Attachment 2 for the 40 MW Black Mesa
BESS project budget update Variance Notes. Schedule deviation is discussed
in part (c)(iv).
v. Please see the Response to Request for Production No. 19(b) — Confidential
Attachment 3 for status updates provided by Idaho Power personnel currently
managing the project as well as Response to Request for Production No. 19(b)
— Confidential Attachment 4 for Powin contractor field logs.
vi. Please see the Response to Request for Production No. 19(a) — Confidential
Attachment 2 for the Black Mesa BESA Change Order No. 1. In addition, see
the Response to Request for Production No. 19(b) — Confidential Attachment
5 for additional change orders associated with the 40 MW Black Mesa BESS.
c. i. Not applicable. See part (b)(ii).
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 18
ii. Not applicable. See part (b)(ii).
iii. Not applicable. However, see the Variance Notes provided in part (b)(iv) for an
explanation of variances driving the budget updates.
iv. Delayed delivery of the battery equipment resulted in delayed plant
commissioning and full operation. As identified in Exhibit D to the Black Mesa
BESA, the anticipated operation date was in the third quarter 2023. The plant
operated in limited capacity throughout 2023 and is now fully operational.
The response to this Request is sponsored by Eric Hackett, Projects and Resource
Development Director, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 19
REQUEST FOR PRODUCTION NO. 20: Please provide the following information
for the "Rebuild of Line 423" project referenced by Colburn Direct at 4. Please include
any available workpapers with formulas intact. If any of the information requested below
cannot be provided or is not available, please explain why it is not available or cannot be
provided.
a. Please provide a detailed explanation for the need of the project including the
analysis justifying the need;
b. Please provide a list of all the potential alternatives the Company considered to
fulfill the need and explain why the project was selected among the alternatives
supported by the Company's economic analysis (costs and benefits) comparing
them;
c. If a Request for Proposal ("RFP") or Request for Quote ("RFQ") was submitted,
please provide the following information:
i. A copy of the RFP or RFQ that was submitted;
ii. A detailed explanation of the selection process including the scorecard and list
of the criteria used to select the project;
iii. The short-list bidder scorecard; and
iv. A copy of the winning bid.
d. Please provide the approved Initial Project Plan including the following:
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence that the Initial Project Plan and budget were approved at the
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 20
appropriate level.
e. Please provide the following for the Baseline Construction Project Plan including
the following:
i. Baseline project scope;
ii. Baseline project budget broken down by WBS;
iii. Baseline project schedule broken down by WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
f. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
ii. Baseline construction schedule-to-actual comparison by WBS;
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 20:
a. Line 423 is a 138-Kilovolt("kV") line that runs from Ontario to the Quartz substation,
south of Baker City in Oregon. This project rebuilt the Huntington to Quartz 138-
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 21
kV portion of Line 423 ("Huntington-Quartz line") due to the age of the existing line
and resulting reliability issues. When evaluating potential outage sources it was
noted that due to the age of the lines, shield wires had not been installed on the
lines and therefore lightning was likely contributing to the performance issues.
Thus, the Company engaged POWER Engineers, Inc. ("POWER Engineers"), to
perform a study to analyze the entire Ontario to Quartz 138-kV line, and specifically
the Huntington to Quartz section to determine if a rebuild on the line would increase
reliability.
POWER Engineers used a lightning performance software, analyzing three
cases, each with two different footing resistance assumptions: (1) the existing
wood structure with no shield wires, (2) a new wood structure with two shield wires,
and (3) a new steel structure with two shield wires. The results indicated that the
overall line performance would be significantly improved with the addition of shield
wires and further improvement is expected if steel structures were used in
combination with the addition of shield wires. Please see Response to Request for
Production No. 20(a) — Confidential Attachment for a copy of the POWER
Engineers study.
b. Absent the rebuild, the Company anticipated high maintenance and repair costs
and reduced reliability. In addition, equipment failure could lead to an extensive
outage and possible property damage. The Huntington-Quartz line rebuild involved
the replacement of 286 structures from the Huntington substation to the Quartz
substation with tubular steel 138-kV structures with shield wire and optical ground
wire for fiber optic communications. The majority of the existing wood structures
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 22
were installed in 1951 and therefore did not have space for the addition of shield
wires. Shield wires are installed above the conductors for the purpose of
channeling lightning strikes to ground, which helps to prevent or minimize damage
to power lines and equipment, avoid major outages on the line, and mitigate
maintenance and repair costs. Moreover, because the Huntington-Quartz line was
identified as being in a wildfire prone area, the project was prioritized, and grid
hardening performed as part of the rebuild. Grid hardening includes the use of
steel structures for resiliency against wildfires and improved customer reliability.
The project is identified in Table 13 of the Company's 2024 Wildfire Mitigation Plan,
which lists the transmission line rebuild projects planned over the next five years
and necessitating steel structures in wildfire prone areas.2 The rebuild of the
Huntington-Quartz line was necessary to ensure Idaho Power continues providing
safe, reliable electric service to its customers.
c. Numerous competitive solicitations exist for this project. Five key bid events were
conducted for services to be provided to Idaho Power including construction
services, design and engineering, environmental services, geotechnical services,
and materials. The Light Detection and Ranging ("LIDAR"), steel pole inspection
and hardline inspection services were sole sourced. The following bid events and
detailed information regarding specifications, requirements, and other pertinent
RFP information can be found in the following attachments:
i. See the Company's Response to Request for Production No. 20(c) —
Attachment 1 for a copy of the RFP for construction services, Company's
2 2024 Wildfire Mitigation Plan at 90 (filed in Case No. IPC-E-22-27).
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 23
Response to Request for Production No. 20(c) —Attachment 2 for a copy of the
Request for Bids for design and engineering services, Company's Response
to Request for Production No. 20(c) — Attachment 3 for a copy of the RFP for
environmental services, Company's Response to Request for Production No.
20(c) — Attachment 4 for a copy of the RFP for geotechnical services,
Company's Response to Request for Production No. 20(c) — Attachment 5 for
a copy of the RFP for steel poles, and Company's Response to Request for
Production No. 20(c)—Attachment 6 for a copy of the Sole Source Procurement
Justifications.
ii. For construction services, see the Response to Request for Production No.
20(c) — Confidential Attachment 7 for the summaries of the pricing and non-
pricing responses. For design and engineering services, see the Response to
Request for Production No. 20(c) — Confidential Attachment 8 for the
summaries of the pricing and non-pricing responses. For environmental
services, see the Response to Request for Production No. 20(c) — Confidential
Attachment 9 for the summaries of the pricing and non-pricing responses. For
geotechnical services, see the Response to Request for Production No. 20(c)
— Confidential Attachment 10 for the summaries of the pricing and non-pricing
responses. For steel poles, see the Response to Request for Production No.
20(c) — Confidential Attachment 11 for the bid evaluation results.
iii. See part (c)(ii).
iv. For construction services, see the Response to Request for Production No.
20(c) — Confidential Attachment 12. For design and engineering services, see
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 24
the Response to Request for Production No. 20(c) — Confidential Attachment
13. For environmental services, see the Response to Request for Production
No. 20(c) — Confidential Attachment 14. For geotechnical services, see the
Response to Request for Production No. 20(c) — Confidential Attachment 15.
For steel poles, see the Response to Request for Production No. 20(c) —
Confidential Attachment 16.
In addition to competitive bid events, Idaho Power purchases many minor and
ancillary materials and services in accordance with the Idaho Power Procurement
Policy and Procurement Standard, provided as Response to Request for
Production No. 20(c)— Confidential Attachment 17. Many goods are stock items in
Idaho Power warehouses and are not bid through an RFP on a project basis, but
rather as wholesale purchases.
d. A specific project plan document could not be located. However, the following
provides more information related to the project:
i. The Huntington-Quartz line rebuild involved the replacement of 286 structures
from the Huntington substation to the Quartz substation with tubular steel 138-
kV structures with shield wire and optical ground wire for fiber optic
communications. Please see Response to Request for Production No. 20(d) —
Attachments 1 , 2 and 3 for detailed scope associated with the Huntington-
Quartz line rebuild, the necessary foundation for the line, and the design of the
project.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 25
ii. Please see Response to Request for Production No. 17(a) — Confidential
Attachment 2 for the Budget Update — Authorized to Spend spreadsheet that
identifies the original approved budget amount of$26.2 million.
iii. The project was first identified in 2018 with permitting scheduled to begin in
2019, engineering and design work to occur in 2020, and construction to take
place in 2021 through 2022. Construction however was deferred until 2023.
iv. See the Company's Response to Request for Production No. 17(a)(iv) for an
explanation of the capital project budget approval processes. The creation of
the BID T423190001 for the Huntington-Quartz line rebuild and corresponding
original approved budget reflected in the Response to Request for Production
No. 17(a) — Confidential Attachment 2, the Budget Update — Authorized to
Spend spreadsheet, is evidence of approval of the initial budget.
e. There is no construction project plan document as construction plans have not
changed since the scope and design documents were created.
i. The project scope did not change following completion of the scope documents
provided in Response to Request for Production No. 20(d) — Attachments 1, 2
and 3.
ii. See the Company's Response to Request for Production No. 17(b)(ii). The only
WBS the Company can provide for the project is reflective of the most recent
budget and schedule. Please see the Response to Request for Production No.
20(e)—Attachment 1 for the Huntington-Quartz line rebuild project WBS. Note,
the remaining work, identified as Construction 2024 on the WBS, is primarily
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 26
related to the line construction costs which would fall in the Materials and Labor
categories upon completion.
iii. See part (e)(ii).
iv. See the Company's Response to Request for Production No. 17(a)(iv) and
(c)(iii). The budget updates reflected in the Response to Request for Production
No. 17(a) — Confidential Attachment 2, the Budget Update — Authorized to
Spend spreadsheet are evidence of approval of the updated budget amounts
associated with this project. For the Huntington-Quartz line rebuild, which was
managed through MS Project Schedule, Idaho Power has pulled the variance
notes documenting the reason for the change in budget update, if one occurred.
See the Response to Request for Production No. 20(e) — Attachment 2 for the
Huntington-Quartz line rebuild project budget update Variance Notes.
v. Please see the Response to Request for Production No. 20(e) — Attachment 3
for the inspection reports that have been prepared during construction.
vi. Please see the Response to Request for Production No. 20(e) — Confidential
Attachment 4 for the change orders associated with the project.
f. i. Not applicable. See part (e)(ii).
ii. Not applicable. See part (e)(ii).
iii. Not applicable. However, see the Variance Notes provided in part (e)(iv) for an
explanation of variances driving the budget updates.
iv. There have been no deviations in the schedule from the initial schedule which
identified commencement of construction in 2023.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 27
The response to this Request is sponsored by Mitch Colburn, Vice President of
Planning, Engineering and Construction, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 28
REQUEST FOR PRODUCTION NO. 21: Please provide the following information
for the "Rebuild of Line 902" project referenced by Colburn Direct at 7. Please include any
available workpapers with formulas intact. If any of the information requested below
cannot be provided or is not available, please explain why it is not available or cannot be
provided.
a. Please provide a detailed explanation for the need of the project including the
analysis justifying the need;
b. Please provide a list of all the potential alternatives the Company considered to
fulfill the need and explain why the project was selected among the alternatives
supported by the Company's economic analysis (costs and benefits) comparing
them;
c. If a RFP or RFQ was submitted, please provide the following information:
i. A copy of the RFP or RFQ that was submitted;
ii. A detailed explanation of the selection process including the scorecard and list
of the criteria used to select the project;
iii. The short-list bidder scorecard; and
iv. A copy of the winning bid.
d. Please provide the approved Initial Project Plan including the
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence that the Initial Project Plan and budget were approved at the
appropriate level.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 29
e. Please provide the following for the Baseline Construction Project Plan including
the following:
i. Baseline project scope;
ii. Baseline project budget broken down by WBS;
iii. Baseline project schedule broken down by WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
f. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
ii. Baseline construction schedule-to-actual comparison by WBS;
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 21:
a. Line 902 is one of the three 230-kV transmission lines that run from the Boise
Bench substation to the Midpoint substation in areas prone to wildfire. Line 902
has been connected to and split into many line sections by station additions over
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 30
the years, and is now comprised of the Midpoint to Justice, Justice to Mountain Air
Wind Tap, Mountain Air Wind Tap to Rattlesnake, Rattlesnake to DRAM, and
finally DRAM to Boise Bench segments. Line 902 was originally built over 70 years
ago, with 478 of the original structures from 1947 in place.
The Company follows transmission maintenance and inspection practices
in accordance with Western Electricity Coordinating Council and the North
American Electric Reliability Corporation ("NERC") requirements to ensure
compliance with applicable safety and reliability standards and takes proactive
steps to repair or replace transmission line components on an ongoing basis as
part of asset management and aging infrastructure assessments. Pursuant to its
Transmission Maintenance and Inspection Plan ("TMIP"), the Company performs
line inspections to identify conditions or defects and inform, prioritize, and schedule
maintenance activities. Routine line patrols are conducted annually and
comprehensive maintenance inspections are generally performed every 10 years,
and include a detailed inspection of all transmission line components and a pole
inspection and ground-line treatment of all wood poles in the line. When inspected,
many poles and cross arms on Line 902 were found to be in poor condition and as
a result of this process, Line 902 was identified as needing to be rebuilt. Please
see the Company's Response to Request for Production No. 21(a) — Attachment
for the Line 902 structures overview and the resulting maintenance
recommendations. The rebuild project will occur in four phases, the first of which
is included in the Company's request in this case, approximately 36-mile
Rattlesnake substation to DRAM substation section ("Rattlesnake to DRAM").
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 31
b. There were no alternatives to the rebuild of the line. Delaying the rebuild of Line
902 could result in higher maintenance and repair costs should the structures need
replacement individually, while also potentially reducing reliability. Further, the
Company's Integrated Resource Plan has repeatedly identified the need for
resource additions east of the Treasure Valley and rebuilding the line with larger
conductors is the most cost-effective way to integrate those resources. Further,
the Company's inspection and maintenance activities helps inform consideration
of wildfire risk and the resulting prioritization of transmission line rebuild projects.
All four phases of the Line 902 rebuild fall within the wildfire prone areas as
identified in Idaho Power's 2024 Wildfire Mitigation Plan, including the Rattlesnake
to DRAM section.3 Therefore, the line rebuild will utilize steel structures for
resiliency against wildfires and to improve customer reliability.
c. Several competitive solicitations exist for this project for material, design consulting
service, and construction. Two key bid events were conducted for services to be
provided to Idaho Power including design and construction services. The purchase
of steel poles was sole sourced.
i. See the Response to Request for Production No. 21(c) — Attachment 1 for the
RFP for construction services, the Response to Request for Production No.
21(c) — Attachment 2 for the RFP for design services, and the Response to
Request for Production No. 21(c) — Attachment 3 for the Sole Source
Procurement Justification for the steel poles.
3 2024 Wildfire Mitigation Plan at 90 (filed in Case No. IPC-E-22-27).
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 32
ii. For construction services, see the Response to Request for Production No.
21(c) — Confidential Attachment 4 for the summaries of the pricing and non-
pricing responses and an executive summary of the bid evaluation results. For
design services, see the Response to Request for Production No. 21(c) —
Confidential Attachment 5 for the summaries of the pricing and non-pricing
responses.
iii. See part (c)(ii).
iv. For construction services, see Response to Request for Production No. 21(c)
— Confidential Attachment 6 and for design services see Response to Request
for Production No. 21(c) — Confidential Attachment 7.
d. A specific project plan document could not be located. However, the following
provides more information related to the project:
i. Line 902, which runs from the Boise Bench substation to the Midpoint
substation, was originally built over 70 years ago through wildfire prone areas
and many poles and cross arms were found to be in poor condition. The
Rattlesnake to DRAM rebuild is the first phase of the Line 902 rebuild. Please
see Response to Request for Production No. 21(d) — Attachment for the
detailed scope and design associated with the Rattlesnake to Dram line rebuild
project.
ii. Please see Response to Request for Production No. 17(a) — Confidential
Attachment 2 for the Budget Update — Authorized to Spend spreadsheet that
identifies the original approved budget amount of$21.4 million.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 33
iii. The project was first identified in late 2021 with construction anticipated to
commence in 2023 and conclude in 2024.
iv. See the Company's Response to Request for Production No. 17(a)(iv) for an
explanation of the capital project budget approval processes. The creation of
the BID T902220002 for the Rattlesnake to DRAM line rebuild and
corresponding original approved budget reflected in the Response to Request
for Production No. 17(a) — Confidential Attachment 2, the Budget Update —
Authorized to Spend spreadsheet, is evidence of approval of the initial budget.
e. There is no construction project plan document as construction plans have not
changed since the scope and design document was created.
i. The project scope did not change following completion of the scope documents
provided in Response to Request for Production No. 21(d) — Attachment 1.
ii. See the Company's Response to Request for Production No. 17(b)(ii). The only
WBS the Company can provide for the project is reflective of the most recent
budget and schedule. Please see the Response to Request for Production No.
21(e) — Attachment 1 for the Rattlesnake to DRAM line rebuild project WBS.
iii. See part (e)(ii).
iv. See the Company's Response to Request for Production No. 17(a)(iv) and
(c)(iii). The budget updates reflected in the Response to Request for Production
No. 17(a) — Confidential Attachment 2, the Budget Update — Authorized to
Spend spreadsheet are evidence of approval of the updated budget amounts
associated with this project. For the Rattlesnake to DRAM line rebuild, which
was managed through MS Project Schedule, Idaho Power has pulled the
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 34
variance notes documenting the reason for the change in budget update, if one
occurred. See the Response to Request for Production No. 21(e)—Attachment
2 for the Rattlesnake to DRAM line rebuild project budget update Variance
Notes.
v. Please see Response to Request for Production No. 21(e) — Attachment 3 for
inspection reports prepared during construction.
vi. Please see Response to Request for Production No. 21(e) — Confidential
Attachment 4 for the change orders associated with the project.
f. i. Not applicable. See part (e)(ii).
ii. Not applicable. See part (e)(ii).
iii. Not applicable. However, see the Variance Notes provided in part (e)(iv) for an
explanation of variances driving the budget updates.
iv. Due to material availability, steel pole deliveries, initially scheduled for 2023
were delayed until 2024. In addition, construction contractors encountered a
significant amount of mud during the winter, delaying structure replacements in
January 2024 but have increased manpower and equipment to keep the project
on schedule.
The response to this Request is sponsored by Mitch Colburn, Vice President of
Planning, Engineering and Construction, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 35
REQUEST FOR PRODUCTION NO. 22: Please provide the following information
for the "Series Capacitor Bank Replacement" project referenced by Colburn Direct at 9.
Please include any available workpapers with formulas intact. If any of the information
requested below cannot be provided or is not available, please explain why it is not
available or cannot be provided.
a. Please provide a detailed explanation for the need of the project including the
analysis justifying the need;
b. Please provide a list of all the potential alternatives the Company considered to
fulfill the need and explain why the project was selected among the alternatives
supported by the Company's economic analysis (costs and benefits) comparing
them;
c. If a RFP or RFQ was submitted, please provide the following information:
i. A copy of the RFP or RFQ that was submitted;
ii. A detailed explanation of the selection process including the scorecard and list
of the criteria used to select the project;
iii. The short-list bidder scorecard; and
iv. A copy of the winning bid.
d. Please provide the approved Initial Project Plan including the following:
i. Initial project scope;
ii. Initial project budget;
iii. Initial proposed schedule; and
iv. Evidence that the Initial Project Plan and budget were approved at the
appropriate level.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 36
e. Please provide the following for the Baseline Construction Project Plan including
the following:
i. Baseline project scope;
ii. Baseline project budget broken down by WBS;
iii. Baseline project schedule broken down by WBS;
iv. If the baseline construction project scope, budget, and/or schedule deviated
from the Initial Project Plan, please explain the differences, explain the reason
for the change, and provide evidence that the changes were approved at the
appropriate level;
v. Project status reports and action items; and
vi. Contractor change orders.
f. Please provide the following related to completion of the project:
i. Baseline construction budget-to-actual comparison by WBS and by year;
ii. Baseline construction schedule-to-actual comparison by WBS;
iii. For any budget-to-actual cost overages by major WBS category that is over
5%, please explain the reason for the differences and provide evidence that the
amount was approved at the appropriate level; and
iv. Please explain any deviations in schedule from the baseline construction
schedule.
RESPONSE TO REQUEST FOR PRODUCTION NO. 22:
a. The series capacitor bank at the Midpoint Station was over 40 years old, having
been installed in 1980 and needed replacement. While the asset life of a series
capacitor bank can be longer, major components need to be replaced every 15 to
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 37
30 years, depending on the part. However, new parts for the series capacitor bank
at the Midpoint Station were difficult to procure and some parts had become
obsolete, including certain relay parts, control potential transformers, un-balance
current transformers, spark gaps, and the triggering circuit for the spark gap.
Further, a typical series capacitor replacement takes approximately 7 years to
complete, once the need is identified. Please see the Company's Response to
Request for Production No. 22(a) — Attachment for a report that summarizes the
results of the Powerflow case studies performed on the series capacitor bank prior
to replacement.
b. There were no alternatives to the replacement of the Midpoint Station series
capacitor bank. This series capacitor bank is necessary to achieve the path rating
and as such its continued reliability is critical. A failure of a trigger or spark gap or
a loss of a critical relay could disable either one or both of the series capacitor
bank segments indefinitely. The bank ensures the Midpoint Station transformer is
not overloaded and prevents derating the transmission paths at Midpoint up to 280
MW's, which is critical to the continued reliability.
c. Several competitive solicitations exist for this project. Three key bid events were
conducted for services to be provided to Idaho Power including for materials and
construction services, both for the capacitor bank and the control room. The
purchase of fencing and the bird abetment lasers was sole sourced.
i. See the Response to Request for Production No. 22(c) — Attachment 1 for the
RFP for the capacitor bank, the Response to Request for Production No. 22(c)
—Attachment 2 for the RFP for construction services, the Response to Request
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 38
for Production No. 22(c) — Attachment 3 for the RFQ for construction of the
control building, the Response to Request for Production No. 22(c) —
Attachment 4 for the Sole Source Procurement Justification for fencing, and the
Response to Request for Production No. 22(c) — Attachment 5 for the Sole
Source Procurement Justification for the bird abetment lasers.
ii. For the capacitor bank, see the Response to Request for Production No. 22(c)
— Confidential Attachment 6, for an executive summary of the bid evaluation
results. For construction services, see the Response to Request for Production
No. 22(c)—Confidential Attachment 7 for the summaries of the pricing and non-
pricing responses and an executive summary of the bid evaluation results. For
construction of the control room, see the Response to Request for Production
No. 22(c)—Confidential Attachment 8 for the summaries of the pricing and non-
pricing responses.
iii. See part (c)(ii).
iv. For the capacitor bank, see the Response to Request for Production No. 22(c)
— Confidential Attachment 9, for construction services, see the Response to
Request for Production No. 22(c) — Confidential Attachment 10 and for
construction of the control room, see the Response to Request for Production
No. 22(c) — Confidential Attachment 11.
d. A specific project plan document could not be located. However, the following
provides more information related to the project:
i. The existing capacitor bank will be removed in entirety and the new capacitor
bank will be installed in the same location. In addition, a new control building
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 39
will be constructed near the new capacitor bank. See the Response to Request
for Production No. 22(d)—Attachment for the series capacitor bank replacement
scope of work.
ii. Please see Response to Request for Production No. 17(a) — Confidential
Attachment 2 for the Budget Update — Authorized to Spend spreadsheet that
identifies the original approved budget amount of$8.5 million.
iii. Replacement of the series capacitor bank was first considered in 2015 but
deferred as work that required the bank to be out of service required
coordination with PacifiCorp to maintain reliability. In 2021 the initial scope was
completed, which identified design completion in late 2022, with construction
to commence in 2023 and completion to occur in 2024.
iv. See the Company's Response to Request for Production No. 17(a)(iv) for an
explanation of the capital project budget approval processes. The creation of
the BID MPSN210001 for the Midpoint Station series capacitor bank
replacement and corresponding original approved budget reflected in the
Response to Request for Production No. 17(a)— Confidential Attachment 2, the
Budget Update —Authorized to Spend spreadsheet, is evidence of approval of
the initial budget.
e. Please see the Response to Request for Production No. 22(e) — Attachment 1 for
the pre-construction summary document.
i. The project scope did not change following completion of the scope document
provided in Response to Request for Production No. 22(d) — Attachment.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-40
ii. See the Company's Response to Request for Production No. 17(b)(ii). The only
WBS the Company can provide for the project is reflective of the most recent
budget and schedule. Please see the Response to Request for Production No.
22(e) — Attachment 2 for the Midpoint Station series capacitor bank
replacement project WBS.
iii. See part (e)(ii).
iv. See the Company's Response to Request for Production No. 17(a)(iv) and
(c)(iii). The budget updates reflected in the Response to Request for Production
No. 17(a) — Confidential Attachment 2, the Budget Update — Authorized to
Spend spreadsheet are evidence of approval of the updated budget amounts
associated with this project. For the Midpoint Station series capacitor bank
replacement, which was managed through MS Project Schedule, Idaho Power
has pulled the variance notes documenting the reason for the change in budget
update, if one occurred. See the Response to Request for Production No. 22(e)
— Attachment 3 for the Midpoint Station series capacitor bank replacement
project budget update Variance Notes.
v. Please see Response to Request for Production No. 22(e) — Attachment 4 for
an inspection report prepared during construction.
vi. Please see Response to Request for Production No. 22(e) — Confidential
Attachment 5 for the change orders associated with the project.
f. i. Not applicable. See part (e)(ii).
ii. Not applicable. See part (e)(ii).
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-41
iii. Not applicable. However, see the Variance Notes provided in part (e)(iv) for an
explanation of variances driving the budget updates.
iv. As evidenced in the Variance Notes provided in part (e)(iv), there were no
deviations in the construction schedule.
The response to this Request is sponsored by Mitch Colburn, Vice President of
Planning, Engineering and Construction, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-42
REQUEST FOR PRODUCTION NO. 23: Please provide the following information
for the "Series Capacitor Bank Replacement" project referenced by Colburn Direct at 10.
If any of the information requested below cannot be provided or is not available, please
explain why it is not available or cannot be provided.
a. Please provide justification, with necessary documentation (including but not
limited to any communication or direct negotiations with the joint-owner PacifiCorp,
etc.), for why the replacement project was deferred several times although it was
identified in 2015; and
b. Please provide necessary documentation and workpapers (with formulas intact)
on any reliability issues the Company may have experienced (including but not
limited to outages, power interruption, etc.) during 2015 — 2023. Also provide
necessary information on Company's actions to remedy those reliability issues
during the same period.
RESPONSE TO REQUEST FOR PRODUCTION NO. 23:
a. In 2015, at 35 years old, the Company was experiencing difficulties keeping the
Midpoint Station series capacitor bank online when parts failed. Note, a typical
series capacitor replacement takes approximately 7 years to complete, once the
need is identified. Series capacitor banks supply line compensation, allowing for
the transmission of more electricity over the line. Only so much line compensation
at one location can occur, typically a maximum of 70 percent at one location, or
the line will be unstable. To increase the line compensation, series capacitor banks
are typically installed at both ends of the line.
At the time, it was thought that both Idaho Power and PacifiCorp would bid
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-43
the series capacitor banks for both the Midpoint Station and the Burns Station, the
capacitor bank at the other end of the Midpoint line. Because the existing Burns
series capacitor bank, owned entirely by PacifiCorp, was identical to the Midpoint
Station series capacitor bank, which had spark gaps and slow bypass breakers, it
was important that both were replaced, and both utilized the newer metal oxide
varistor technology with fast bypass breakers. The project was deferred to allow
time for PacifiCorp to budget for their series capacitor bank at Burns.
As discussions with PacifiCorp ("PAC") continued, Idaho Power determined
that requirements for the Midpoint to Burns series capacitor banks would differ with
the anticipated additions of B2H and Gateway West. The replacement of the
projects would need to coordinate with 500-kV buildout plans and allow for
optimized transfer capability. The additional budgeting time for PAC also allowed
time for Idaho Power's planning department to verify what configuration the new
series capacitor bank at the Midpoint Station would be, it was determined that, in
the interim, the Midpoint Station series capacitor bank bypass breakers could be
replaced because failures of the bypass breakers were 80 percent of the problem
with keeping the series capacitor bank online at the time.
The BID for the breaker replacement was established in 2016, with work
completed in 2018, and the complete replacement of the Midpoint Station series
capacitor bank was deferred until the 2023 to 2024 time period. In 2020, the
reconfigured series capacitor bank that more closely aligned with the requirements
determined by the planning department was identified and the project scheduled
for work to commence in 2023.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-44
Please see the Response to Request for Production No. 23 —Attachment 1
for the scoping kick-off meeting notes with Idaho Power and PacifiCorp that
discuss the replacement of the series capacitor bank bypass breakers as an
interim solution to the replacement of the series capacitor bank. Idaho Power does
not have any additional documentation that discusses the deferment of the project
however has included as the Response to Request for Production No. 23 —
Attachment 2 the request for approval sent to PacifiCorp in 2021 for the
replacement of the Midpoint Station series capacitor bank once the reconfigured
series capacitor bank was identified.
b. See part (a).
The response to this Request is sponsored by Mitch Colburn, Vice President of
Planning, Engineering and Construction, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-45
REQUEST FOR PRODUCTION NO. 24: Please provide the service level for the
Customer Service Center by month for the year 2023 and YTD 2024. "Service Level" is
the percentage of calls answered within a certain number of seconds, e.g., 80% of calls
answered within 60 seconds.
RESPONSE TO REQUEST FOR PRODUCTION NO. 24: Please see the table
below, which details the monthly service level of the Company's Customer Service Center
between 2023 and 2024 YTD. The provided monthly service level percentages reflect the
percentage of calls answered within 60 seconds.
Service Level
Month 2023 2024
Jan. 88.9% 85.1%
Feb. 84.6% 80.5%
Mar. 89.1% 82.9%
Apr. 86.3% 72.3%
May 80.8% 77.0%
Jun. 86.6% 76.6%
Jul. 86.7%
Aug. 84.3%
Sep. 89.4%
Oct. 81.5%
Nov. 87.8%
Dec. 90.9%
Year 86.3% 78.9%
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-46
REQUEST FOR PRODUCTION NO. 25: Please provide the number of incoming
calls handled by the Customer Service Center by month for the year 2023 and YTD 2024.
RESPONSE TO REQUEST FOR PRODUCTION NO. 25: Please see the table
below which details the number of monthly incoming calls between 2023 and 2024 YTD
that were handled by the Company's Customer Service Center.
Incoming calls
Month 2023 2024
Jan. 45,447 48,242
Feb. 44,556 47,632
Mar. 60,574 58,167
Apr. 50,628 57,138
May 54,893 56,125
Jun. 51,244 50,695
Jul. 48,411
Aug. 57,230
Sep. 53,305
Oct. 55,558
Nov. 47,565
Dec. 41,804
Year 611,215 317,999
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-47
REQUEST FOR PRODUCTION NO. 26: Please provide the number of abandoned
calls to the Customer Service Center by month for the year 2023 and YTD 2024.
"Abandoned calls" are calls that reach the Company's incoming telephone system, but
the calling party terminates the call before speaking with a customer service
representative.
RESPONSE TO REQUEST FOR PRODUCTION NO. 26: Please see the table
below, which details the number of monthly calls received between 2023 and 2024 YTD
that were routed to the Company's Customer Service Center but subsequently
abandoned prior to being connected with an agent.
Abandoned Calls
Month 2023 2024
Jan. 1,044 2,904
Feb. 1,461 2,147
Mar. 1,966 3,588
Apr. 1,810 3,605
May 2,346 3,972
Jun. 1,888 2,867
Jul. 1,431
Aug. 2,166
Sep. 1,546
Oct. 2,332
Nov. 1,600
Dec. 1,431
Year 21,021 19,083
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-48
REQUEST FOR PRODUCTION NO. 27: Please provide the average speed of
answer for the Customer Service Center by month for the year 2023 and YTD 2024.
"Average speed of answer" is the interval (typically measured in seconds) between when
a call reaches the Company's incoming telephone system and when the call is picked up
by a customer service representative.
RESPONSE TO REQUEST FOR PRODUCTION NO. 27: Please see the table
below, which details the Company's Customer Service Center's monthly average speed
of answer for calls received between 2023 and 2024 YTD.
Average Speed of
Answer
(in seconds)
Month 2023 2024
Jan. 31 49
Feb. 41 50
EMar. 30 58
Apr.E38 72
May 52 63
Jun. 38 62
Jul. 34
Aug. 38
Sep. 28
Oct. 46
Nov. 33
Dec. 24
Year 1 36 59
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER-49
REQUEST FOR PRODUCTION NO. 28: Please provide the average handling time
for the Customer Service Center by month for the year 2023 and YTD 2024. "Average
handling time" is the average amount of time (usually expressed in minutes) it takes for a
customer service representative to talk with a customer plus and additional "off-line" time
it takes to complete the transaction or fully resolve the customer's issue(s).
RESPONSE TO REQUEST FOR PRODUCTION NO. 28: Please see the table
below, which details the Company's Customer Service Center's monthly average
handling time, including all respective "off-line" work, for calls received between 2023 and
2024 YTD.
Average Handling
Time
(in seconds)
Month 2023 2024
Jan. 360 371
Feb. 374 384
Mar. 373 379
Apr. 372 386
May 376 379
Jun. 369 370
Jul. 357
Aug. 365
Sep. 361
Oct. 359
Nov. 360
Dec. 360
Year 360 371
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 50
REQUEST FOR PRODUCTION NO. 29: Please provide the first call resolution
rate for the Customer Service Center by month for the year 2023 and YTD 2024. "First
call resolution rate" is the percentage of calls where the transaction, inquiry, or complaint
is resolved upon initial contact with the Company.
RESPONSE TO REQUEST FOR PRODUCTION NO. 29: Please see the table
below, which details the Company's Customer Service Center's monthly first call
resolution rate for all calls received between 2023 and 2024 YTD. The Company's "first
call resolution rate" is defined as the percentage of phone numbers that do not place more
than one call to the Company's Customer Service Center within a 24-hour period
(midnight to midnight MST). The calculation collectively considers representative and IVR
handled calls.
First Call Resolution
Rate
Month 2023 2024
Jan. 77.2% 75.2%
Feb. 77.6% 76.3%
Mar. 75.3% 72.8%
Apr. 75.3% 74.6%
May 75.6% 74.7%
Jun. 75.5% 74.3%
Jul. 75.2%
Aug. 75.5%
rOct. 75.6%
75.6%
76.4%
Dec. 76.6%
Year 75.9% 74.6%
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 51
REQUEST FOR PRODUCTION NO. 30: Please provide the average response
time for email transactions for the Customer Service Center by month for the year 2023
and YTD 2024. "Average response time" is the average number of hours from receipt of
an e-mail by the Company to sending a substantive response; auto-response
acknowledgements do not count as a substantive response.
RESPONSE TO REQUEST FOR PRODUCTION NO. 30: Please see the table
below, which details the Company's Customer Service Center's average monthly
response time for email transactions received between 2023 and 2024 YTD. Of note, the
average response times provided below encompass the entire duration from the moment
an email is received, including times outside of the Customer Service Center's operating
hours.
Average Email
Response Time
(in hours:minutes:seconds)
Month 2023 2024
Jan. 5:30:48 13:49:08
Feb. 8:10:23 17:07:26
Mar. 4:27:42 21:38:04
Apr. 15:11:24 23:19:22
May 26:13:03 10:00:13
Jun. 16:52:59 8:11:03
Jul. 10:13:43
Aug. 9:41:21
Sep. 8:29:56
Oct. 19:47:30
Nov. 6:15:27
Dec. 6:57:35
Year 11:29:19 15:40:53
The response to this Request is sponsored by Tim Tatum, VP of Regulatory
Affairs, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 52
DATED at Boise, Idaho, this 31 st day of July 2024.
LISA D. NORDSTROM
Attorney for Idaho Power Company
DONOVAN E. WALKER
Attorney for Idaho Power Company
MEGAN GOICOECHEA ALLEN
Attorney for Idaho Power Company
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 53
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 31st day of July 2024, 1 served a true and correct
copy of Idaho Power Company's Response to the Fourth Production Request of the
Commission Staff to Idaho Power upon the following named parties by the method
indicated below, and addressed to the following:
Commission Staff Hand Delivered
Chris Burdin U.S. Mail
Deputy Attorney General Overnight Mail
Idaho Public Utilities Commission FAX
11331 W. Chinden Blvd., Bldg No. 8 FTP Site
Suite 201-A (83714) X Email Chris.Burdin(a-),puc.idaho.gov
PO Box 83720
Boise, ID 83720-0074
Industrial Customers of Idaho Power Hand Delivered
Peter J. Richardson U.S. Mail
Richardson Adams, PLLC Overnight Mail
515 N. 27t" Street FAX
Boise, Idaho 83702 FTP Site
X Email peter _richardsonadams.com
Dr. Don Reading Hand Delivered
280 Silverwood Way U.S. Mail
Eagle, Idaho 83616 Overnight Mail
FAX
FTP Site
X Email dread ing(@ mindsprinq.com
Idaho Irrigation Pumpers Association, Hand Delivered
Inc. U.S. Mail
Eric L. Olsen Overnight Mail
ECHO HAWK & OLSEN, PLLC FAX
505 Pershing Avenue, Suite 100 FTP Site
P.O. Box 6119 X Email elo(o)_echohawk.com
Pocatello, Idaho 83205
Lance Kaufman, Ph.D. Hand Delivered
2623 NW Bluebell Place U.S. Mail
Corvallis, OR 97330 Overnight Mail
FAX
FTP Site
X Email lance aegisinsight.com
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 54
Idaho Conservation League Hand Delivered
Matthew Nykiel U.S. Mail
710 N. 6t" Street Overnight Mail
Boise, Idaho 83702 FAX
FTP Site
X Email
Matthew.n kiel mail.com
Brad Heusinkveld Hand Delivered
Idaho Conservation League U.S. Mail
710 N. 6t" Street Overnight Mail
Boise, Idaho 83702 FAX
FTP Site
X Email
bheusinkveld(a)_idahoconservation.org
Micron Technology, Inc. Hand Delivered
Austin Rueschhoff U.S. Mail
Thorvald A. Nelson Overnight Mail
Austin W. Jensen FAX
Kristine A.K. Roach FTP Site
Holland & Hart LLP X Email
555 17t" Street, Suite 3200 darueschhoff(a)_hollandhart.com
Denver, CO 80202 tnelson hollandhart.com
awiensen(o)-hollandhart.com
karoach(ahol land hart.com
Jim Swier Hand Delivered
Micron Technology, Inc. U.S. Mail
8000 South Federal Way Overnight Mail
Boise, ID 83707 FAX
FTP Site
X Email
swierC@.micron.com
City of Boise Hand Delivered
Ed Jewell U.S. Mail
Deputy City Attorney Overnight Mail
Boise City Attorney's Office FAX
150 N. Capitol Blvd. FTP Site
P.O. Box 500 X Email
Boise, Idaho 83701 BoiseCityAttorney(a-).cityofboise.org
eiewel I(a)cityofboise.org
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 55
Steven Hubble Hand Delivered
Boise City Dept. of Public Works U.S. Mail
150 N. Capitol Blvd. Overnight Mail
P.O. Box 500 FAX
Boise, Idaho 83701-0500 FTP Site
X Email
shubble(a_cityofboise.org
Federal Executive Agencies Hand Delivered
Peter Meier U.S. Mail
Emily W. Medlyn Overnight Mail
U.S. Department of Energy FAX
1000 Independence Ave., S.W. FTP Site
Washington, DC 20585 X Email
Pete r.meier(cDhq.doe.gov
emily.medlyn(cD_hg.doe.gov
Stacy Gust
Regulatory Administrative Assistant
IDAHO POWER COMPANY'S RESPONSE TO THE FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER- 56