HomeMy WebLinkAbout20240709Decision Memo.pdf DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER HAMMOND
COMMISSIONER LODGE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: CHRIS BURDIN
DEPUTY ATTORNEY GENERAL
DATE: JULY 9, 2024
SUBJECT: IN THE MATTER OF THE APPLICATION OF IDAHO POWER
COMPANY FOR APPROVAL OF A SECOND AMENDMENT TO THE
ENERGY SALES AGREEMENT FOR THE SALE AND PURCHASE OF
ELECTRIC ENERGY FROM THE LOWLINE #2 HYDRO PROJECT;
CASE NO. IPC-E-24-28.
On July 1, 2024, Idaho Power Company("Company")filed an application("Application")
with the Idaho Public Utilities Commission ("Commission") requesting an order approving the
Second Amendment("Second Amendment")to the Energy Sales Agreement("ESA")between the
Company and Lower Lowline LLC("Seller")for electric energy generated by the Seller's Lowline
#2 Hydro Project("Facility" or"Project"), which is a PURPA Qualifying Facility("QF").
STAFF RECOMMENDATION
Commission Staff recommends the Commission issue a Notice of Application and Notice
of Modified Procedure establishing an August 22, 2024, initial comment deadline, and an August
29, 2024, reply comment deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure establishing an August 22, 2024, initial comment deadline, and an August 29, 2024,
reply comment deadline?
0, 1� A-
Chris Burdin
Deputy Attorney General
IALega1\ELECTRIC\IPC-E-24-28_Low1ineNo2\memos\IPCE2428_dec 1_cb.docx
DECISION MEMORANDUM 1