HomeMy WebLinkAbout20240610Notice_of_Modified_Procedure_Order_No_36220.pdf Office of the Secretary
Service Date
June 10,2024
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-24-14
COMPANY'S APPLICATION FOR AN )
ORDER AUTHORIZING INCLUSION IN ) NOTICE OF MODIFIED
THE BRIDGER BALANCING ACCOUNT OF ) PROCEDURE
ALL NON-FUEL OPERATIONS AND )
MAINTENANCE EXPENSES ASSOCIATED ) ORDER NO. 36220
WITH PLANT OPERATIONS )
On March 29, 2024, Idaho Power Company ("Company") filed an application
("Application") with the Idaho Public Utilities Commission ("Commission") requesting an order
authorizing inclusion of all non-fuel operations and maintenance ("O&M") expenses associated
with plant operations in the Jim Bridger Power Plant(`Bridger")balancing account.
On April 15, 2024, the Commission issued a Notice of Application and Notice of
Intervention Deadline. Order No. 36138. On May 10, 2024, a Notice of Parties was issued.
NOTICE OF MODIFIED PROCEDURE
YOU ARE HEREBY NOTIFIED that the Commission has determined that the public
interest may not require a formal hearing in this matter, and that it will proceed under Modified
Procedure pursuant to the Commission's Rules of Procedure 201-204, IDAPA 31.01.01.201-.204.
The Commission notes that Modified Procedure and written comments have proven to be an
effective means for obtaining public input and participation.
YOU ARE FURTHER NOTIFIED that persons desiring to state a position on this
Application may file a written comment explaining why the person supports or opposes the
Application. Persons who would like a hearing must specifically request a hearing in their written
comments and explain why written comments alone are insufficient. Persons interested in filing
written comments must do so by August 20, 2024. Comments must be filed through the
Commission's website or by e-mail unless computer access is unavailable. To comment
electronically, please access the Commission's website at http://www.puc.idaho.gov/. Click the
"Case Comment Form" and complete the form using the case number as it appears on the front of
this document.
NOTICE OF MODIFIED PROCEDURE
ORDER NO. 36220 1
To file by e-mail, persons must e-mail the comments to the Commission Secretary and all
parties at the e-mail addresses listed below. Persons submitting a comment by e-mail must provide
their name, address, and the Case Number under which they are commenting. Persons submitting
a comment by e-mail also acknowledge that submitting a comment in an open case constitutes a
public record under Idaho Code § 74-101(13), and all information provided by such person is
available for public and media inspection.
If computer access is unavailable, then comments may be mailed to the Commission and
the parties at the addresses below.Persons submitting a comment by mail must provide their name,
address, and the Case Number under which they are commenting. Persons submitting a comment
by mail also acknowledge that submitting a comment in an open case constitutes a public record
under Idaho Code§74-101(13),and all information provided by such person is available for public
and media inspection.
For the Idaho Public Utilities For the Company:
Commission:
Commission Secretary Lisa D. Nordstrom
Idaho Public Utilities Commission Idaho Power Company
P.O. Box 83720 1221 West Idaho Street(83702)
Boise, ID 83720-0074 P.O. Box 70
secretarykpuc.idaho.gov Boise, ID 83707
lnordstrom(a,idahopower.com
docketskidahopower.com
Street Address for Express Mail:
11331 W. Chinden Blvd. Tim Tatum
Building 8, Suite 201-A Idaho Power Company
Boise, ID 83714 1221 West Idaho Street(83702)
P.O. Box 70
Boise, ID 83707
ttatumgidahopower.com
YOU ARE FURTHER NOTIFIED that the Company must file any reply comments by
September 3, 2024.
YOU ARE FURTHER NOTIFIED that if no written comments or protests are received
within the time limit set, the Commission will consider this matter on its merits and enter its final
order without a formal hearing. If written comments are received within the time limit set, the
Commission will consider them and, in its discretion, may set the same for formal hearing.
NOTICE OF MODIFIED PROCEDURE
ORDER NO. 36220 2
ORDER
IT IS HEREBY ORDERED that the Application be processed by Modified Procedure,
Rules 201-204 (IDAPA 31.01.01.201-.204). Persons interested in filing written comments must
do so by August 20, 2024. The Company must file any reply comments by September 3, 2024.
IT IS FURTHER ORDERED that parties comply with Order No. 35375, issued April 21,
2022. Generally, all pleadings should be filed with the Commission electronically and will be
deemed timely filed when received by the Commission Secretary.See Rule 14.02. Service between
parties should continue to be accomplished electronically when possible. However, voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 101h day of
June 2024.
ERIC ANDERSON, PRESIDENT
HN R. HAMMOND JR., COMMISSIONERr
G
EDWARD LODGE, C ISSIONER
ATTEST:
icl Ba a he
Commission Secretary
IALega1\ELECTRIC\IPC-E-24-14_Bridger O&M\ordersUCE2414_Ntc_Mod_cb.docx
NOTICE OF MODIFIED PROCEDURE
ORDER NO. 36220 3