RE: COMPLIANCE FILING IN CASE NO. PAC-E-24-05
IN THE MATTER OF THE APPLICATION OF ROCKY MOUNTAIN POWER
REQUESTING APPROVAL OF $62.4 MILLION ECAM DEFERRAL
Attention: Commission Secretary
Rocky Mountain Power, a division of PacifiCorp, hereby files its compliance filing in
accordance with Order No. 36207 in Case No. PAC-E-24-05.
The Company is providing clean and legislative copies of the following revised schedule
reflecting Order No. 36207:
• Electric Service Schedule No. 94—Energy Cost Adjustment
In addition, the Company also provides the workpaper"ID 2024 ECAM Rate Design-Workpaper
—Order"with the calculations used to arrive at the adjustments included in the revised Schedule
No. 94.
The Company respectfully requests that the Commission approve the requested tariff changes
with an effective date of June 1, 2024. If you have any questions, please contact Mark Alder by
phone at(801) 220-2313 or email mark.alder(a�pacificorp.com.
Very truly yours,
.J G.�
Joe Steward
Senior Vice President, Regulation
_ROCKY MOUNTAIN
POWER
A DIVISION OF PACIFICORP
Fifteenth Fourteenth Revision of Sheet No. 94.1
I.P.U.C.No. 1 Canceling Thirteenth Fourteenth Revision of Sheet No. 94.1
ROCKY MOUNTAIN POWER
ELECTRIC SERVICE SCHEDULE NO. 94
STATE OF IDAHO
Energy Cost Adjustment
AVAILABILITY: At any point on the Company's interconnected system.
APPLICATION: This Schedule shall be applicable to all retail tariff Customers taking service under the
Company's electric service schedules.
ENERGY COST ADJUSTMENT: The Energy Cost Adjustment is calculated to collect the
accumulated difference between total Company Base Net Power Cost and total Company Actual Net Power Cost
calculated on a cents per kWh basis.
MONTHLY BILL: In addition to the Monthly Charges contained in the Customer's applicable
schedule,all monthly bills shall have applied the following cents per kilowatt-hour rate by delivery voltage.
Delivery Voltage
Secondary Primary Transmission
Schedule 1 0.9341.8090 per kWh
Schedule 6 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 6A 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 7 0.9341.8090 per kWh
Schedule 7A 0.9341.8090 per kWh
Schedule 9 0- 61.717¢per kWh
Schedule 10 0.9341.8090 per kWh
Schedule 11 0.9341.8090 per kWh
Schedule 12 0.9341.8090 per kWh
Schedule 23 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 23A 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 24 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 35 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 35A 0.9341.8090 per kWh 0.9171.7760 per kWh
Schedule 36 0.9341.8090 per kWh
Schedule 400 0- 1.733¢per kWh
Submitted Under Case No. PAC-E-24-3-059
ISSUED: June 04afeh 30, 20243 EFFECTIVE: June 1,20243
_ROCKY MOUNTAIN
POWER
A DIVISION OF PACIFICORP
Fifteenth Revision of Sheet No. 94.1
I.P.U.C.No. 1 Canceling Fourteenth Revision of Sheet No. 94.1
ROCKY MOUNTAIN POWER
ELECTRIC SERVICE SCHEDULE NO. 94
STATE OF IDAHO
Energy Cost Adjustment
AVAILABILITY: At any point on the Company's interconnected system.
APPLICATION: This Schedule shall be applicable to all retail tariff Customers taking service under the
Company's electric service schedules.
ENERGY COST ADJUSTMENT: The Energy Cost Adjustment is calculated to collect the
accumulated difference between total Company Base Net Power Cost and total Company Actual Net Power Cost
calculated on a cents per kWh basis.
MONTHLY BILL: In addition to the Monthly Charges contained in the Customer's applicable
schedule,all monthly bills shall have applied the following cents per kilowatt-hour rate by delivery voltage.
Delivery Voltage
Secondary Primary Transmission
Schedule 1 1.809¢per kWh
Schedule 6 1.809¢per kWh 1.776¢per kWh
Schedule 6A 1.809¢per kWh 1.776¢per kWh
Schedule 7 1.809¢per kWh
Schedule 7A 1.809¢per kWh
Schedule 9 1.7170 per kWh
Schedule 10 1.809¢per kWh
Schedule 11 1.8090 per kWh
Schedule 12 1.8090 per kWh
Schedule 23 1.8090 per kWh 1.7760 per kWh
Schedule 23A 1.809¢per kWh 1.776¢per kWh
Schedule 24 1.809¢per kWh 1.776¢per kWh
Schedule 35 1.809¢per kWh 1.776¢per kWh
Schedule 35A 1.809¢per kWh 1.776¢per kWh
Schedule 36 1.809¢per kWh
Schedule 400 1.733¢per kWh
Submitted Under Case No. PAC-E-24-05
ISSUED: June 6,2024 EFFECTIVE: June 1,2024