1 I . INTRODUCTION AND QUALIFICATIONS
2 Q. Please state your name, business address , and current
3 position with PacifiCorp d/b/a Rocky Mountain Power
4 ("PacifiCorp" or the "Company") .
5 A. My name is Jeffrey M. Wagner. My business address is 825
6 NE Multnomah St . , Suite 1800, Portland, Oregon, and I am
7 a Renewable Development Manager.
8 Q. Please describe your education and professional
9 experience.
10 A. I have a Bachelor of Science Degree from Walla Walla
11 University and a Master of Business Administration from
12 the University of Wisconsin-Madison. My career in energy
13 began in 2005, including positions at PPM Energy, Eurus
14 Energy, Volkswind and WPD Wind Projects . Prior to
15 joining PacifiCorp in May 2022, I had various roles
16 including project manager, developer and managing
17 director of wind energy development. To date, I have
18 played a key role in developing over 3, 000 megawatts
19 ("MW") of wind facilities in eight states . In my current
20 role at PacifiCorp as a Renewable Development Manager,
21 my responsibilities encompass strategic planning,
22 regulatory support, stakeholder engagement, and
23 development and execution of major generation resource
24 additions .
Wagner, Di 1
Rocky Mountain Power
1 Q. Have you previously testified in regulatory proceedings?
2 A. Yes . I have previously filed testimony on behalf of the
3 Company in regulatory proceedings in Oregon.
4 II . PURPOSE OF TESTIMONY
5 Q. What is the purpose of your testimony in this case?
6 A. I provide a general description of the Rock Creek I Wind
7 Project ("Rock Creek I") that the company is requesting
8 rate recovery of in this proceeding, an update on
9 development and construction of the project, and discuss
10 general project costs .
11 Q. Why did the Company pursue Rock Creek I?
12 A. As further described in the testimony of Company witness
13 Thomas R. Burns, the Company' s 2021 Integrated Resource
14 Plan ("IRP") preferred portfolio and 2021 IRP Update
15 both identified a resource need based on a near-term
16 capacity deficit. The Company conducted the 2020 All-
17 Source Request for Proposal ("2020AS RFP") to identify
18 cost-effective resources to fill this need. Bids were
19 received from third parties for resources in the form of
20 build-transfer agreements ("BTAs") , power purchase
21 agreements, and tolling agreements . Rock Creek I was bid
22 by a third-party developer ("Invenergy") as a BTA, and
23 this bid was identified among the most economical assets
24 to meet the Company' s identified resource need.
Wagner, Di 2
Rocky Mountain Power
1 III . GENERAL DESCRIPTION
2 Q. Please describe the Rock Creek I project.
3 A. Invenergy developed and is constructing two separate
4 facilities—the 190 MW Rock Creek I and 400 MW Rock
5 Creek II facilities . Both resources were selected in the
6 2020AS RFP. The Company will also procure the Rock
7 Creek II facility from Invenergy, however that facility
8 is planned to reach commercial operation in 2025, beyond
9 the test period for this rate proceeding. My testimony
10 therefore is focused on Rock Creek I .
11 The Rock Creek I project is located in Carbon and
12 Albany counties, Wyoming and will include (without
13 limitation) : wind turbine generators ("WTGs") with
14 associated foundations and base pads, electrical
15 collector systems, collector substations, access roads,
16 operations and maintenance buildings, fiber optical
17 and/or microwave communication equipment, supervisory
18 control and operating status data acquisition control
19 systems, main power transformers, meteorological
20 evaluation towers, and overhead transmission tie-lines
21 from the collector substation to the point of
22 interconnection. The point of interconnection will be at
23 the existing Foote Creek substation in Carbon County in
24 southeast Wyoming and will interconnect at 230-
25 kilovolts . The site plan for Rock Creek I and Rock Creek
Wagner, Di 3
Rocky Mountain Power
1 II is shown in Exhibit No. 40 .
2 Q. Have preliminary evaluations of the wind potential been
3 performed for Rock Creek I?
4 A. Yes . Wind resource studies completed for the project
5 indicate that the Rock Creek I site is suitable for high
6 capacity factor wind facilities . ' Moreover, the site is
7 adjacent to the Company' s existing High Plains, McFadden
8 Ridge, and Foote Creek Rim wind facilities . Wind data
9 collected from the Company' s existing operating wind
10 projects in the area, and the operational history of
11 these projects, demonstrate that the Rock Creek I site
12 has a favorable wind regime suitable for a high
13 performance wind energy facility.
14 Q. What is the expected operational life of Rock Creek I?
15 A. Rock Creek I has an anticipated operational life of
16 30 years, which aligns with the Company' s currently
17 approved depreciable life for all of its existing wind
18 resources .
19 Q. Has the Company received a certificate of public
20 convenience and necessity ("CPCN") for Rock Creek I?
21 A. Yes . The Company filed a CPCN application with the
22 Wyoming Public Service Commission ("Wyoming Commission")
23 in August 2022, and the Wyoming Commission approved the
Confidential Exhibit No. 41 Energy Yield Assessment for Rock Creek.
Wagner, Di 4
Rocky Mountain Power
1 application during public deliberations held on
2 February 28, 2023 . 2
3 IV. DEVELOPMENT AND CONSTRUCTION STATUS
4 Q. What is the current status of Rock Creek I?
5 A. Development efforts at Rock Creek I have been completed
6 and the project is now in construction. Invenergy' s
7 development efforts included multiple years of wind
8 resource analysis, substantial wildlife and
9 environmental analyses used to design the project and
10 minimize environmental impacts, securing site control
11 through wind energy leases with site property owners,
12 and securing an interconnection agreement with
13 PacifiCorp' s transmission function. Invenergy also
14 received conditional use permits in Carbon and Albany
15 Counties and its permit from the Wyoming Department of
16 Environmental Quality, Industrial Siting Division, to
17 support the construction and ongoing operation of the
18 wind facilities . Invenergy is responsible for the final
19 development and construction of the project in
20 accordance with all permitting and technical
21 requirements .
22 As of December 2023, 90 percent of civil
23 construction was complete, and all turbine foundations
2 In re Rocky Mountain Power Rock Creek CPCN, Docket No. 20000-623-EN-
22, Record No. 17154, Order 29595 (Aug. 9, 2023) .
Wagner, Di 5
Rocky Mountain Power
1 were complete and backfilled. Turbine deliveries are
2 planned to begin in May 2024 . Construction remains on
3 track to enable the project to complete testing and
4 commissioning in the fourth quarter of 2024, and to be
5 placed in-service in December 2024 .
6 Q. Has PacifiCorp conducted due diligence to confirm the
7 development status of the project?
8 A. Yes . As part of the 2020AS RFP and throughout the
9 subsequent negotiations with Invenergy, PacifiCorp has
10 conducted due diligence to confirm the on-time
11 development of various items including interconnection
12 status, wind resource performance, production tax credit
13 ("PTC") eligibility, site control, permitting status,
14 and conformance to technical specifications . This due
15 diligence informed the Company' s negotiations with
16 Invenergy on the scope, schedule, cost, and other terms
17 to establish the BTA.
18 Q. Has the Company executed a BTA for Rock Creek I?
19 A. Yes . The Company and Invenergy executed a binding BTA
20 for Rock Creek I on March 24, 2023 . 3 The BTA includes
21 provisions for the supply of WTGs for the project,
22 balance of plant construction by a qualified wind energy
23 contractor, and ongoing management of the complete
3 Confidential Exhibit No. 42.
Wagner, Di 6
Rocky Mountain Power
REDACTED
1 construction of the project. The Company also executed
2 an operations and maintenance agreement with Invenergy
3 which provides for ongoing service and maintenance of
4 the project after it achieves commercial operation. 4
5 Q. Please explain the key terms and customer protections of
6 the BTA.
7 A. Under the BTA, Invenergy is obligated to develop,
8 engineer, procure equipment for, construct, and transfer
9 ownership of Rock Creek I to the Company. The planned
10 in-service date is December 2024 . PacifiCorp is
11 obligated to pay a defined purchase price to Invenergy
12 under the BTA. The purchase price is fixed, but can be
13 amended based on certain events . The BTA contains pre-
14 and post-start of construction risk and cost-sharing
15 mechanisms . As Rock Creek I started construction in
16 April 2023, the pre-construction protections served
17 their purpose and Invenergy' s construction activities
18 remain on track to achieve the in-service date of
19 December 2024 . Examples of cost mitigation protections
20 include:
21 a.
22
23
4 Confidential Exhibit No. 43.
Wagner, Di 7
Rocky Mountain Power
REDACTED
1
2
3
4 b .
5
6
7
8
9
10
11
12
13
14
15
16
17
18 C.
19
20
21
22
23
24
25
Wagner, Di 8
Rocky Mountain Power
REDACTED
1
2
3
4
5
6
7
8
9
10 d. Liquidated Damages : In the event that the project
11 is delayed, Invenergy is required to pay liquidated
12 damages to PacifiCorp.
13 Q. Who is responsible for construction of Rock Creek I?
14 A. Invenergy is responsible for construction of Rock
15 Creek I, and is utilizing and managing multiple
16 contractors that are engaged in different aspects of the
17 construction. Invenergy is managing the construction
18 progress with PacifiCorp oversight until construction is
19 complete .
20 Q. Who will be responsible for supplying WTGs for Rock
21 Creek I?
22 A. The WTGs will be purchased and delivered according to
23 the terms of a turbine supply agreement which was
Wagner, Di 9
Rocky Mountain Power
REDACTED
1 negotiated and executed by Invenergy. 5 The project is
2 installing WTGs manufactured by with a
3 nominal nameplate capacity of - MW each and rotor
4 diameter of - meters .
5 Q. When will construction begin and end?
6 A. Construction commenced in the second quarter of 2023,
7 with a planned in-service date of December 2024 for Rock
8 Creek I, assuming normal construction circumstances such
9 as weather conditions, labor availability, materials
10 delivery, and permit and agreement processing durations .
11 Q. How will the Company oversee construction of the project
12 to maintain the proposed in-service date?
13 A. PacifiCorp' s Owner' s Engineer oversees construction to
14 ensure the project will be completed on time. This
15 includes reviewing all design submittals to ensure
16 Invenergy meets the technical specification and
17 performance requirements outlined in the BTA, and making
18 periodic site visits to ensure that critical
19 infrastructure is installed per the design documents and
20 has passed acceptability testing.
21 PacifiCorp also uses full-time on-site inspector (s)
22 to ensure that Invenergy adheres to the project schedule
23 and builds the project consistent with the terms of the
5 Confidential Exhibit No. 44 (RC 1 Turbine Supply Agreement) .
Wagner, Di 10
Rocky Mountain Power
1 BTA. This includes monitoring Invenergy' s day-to-day
2 activities, attending daily site meetings, and providing
3 inspection services as needed. PacifiCorp is holding
4 weekly or bi-weekly project status meetings with
5 Invenergy, during which Invenergy reports on the status
6 of the project, discusses critical issues that impact
7 schedule, and addresses the status of any recovery plans
8 as needed.
9 Q. Who will operate and maintain Rock Creek I?
10 A. Once construction is complete, Invenergy will provide
11 certain operations and maintenance services for the
12 first five years of operation. During the initial five-
13 year period, the Company will oversee Invenergy to
14 ensure compliance with all relevant agreements and may
15 self-perform any operations and maintenance activities
16 that are not included in the scope of Invenergy' s work.
17 Beginning in the sixth year of operation, the
18 Company expects to assume responsibility for operations
19 and maintenance activities at Rock Creek I . The Company
20 has an experienced team of personnel that are qualified
21 to operate and maintain Rock Creek. The Company
22 currently owns, operates, and maintains an extensive
23 wind generation fleet that includes the High Plains,
24 McFadden Ridge, Foote Creek I, Seven Mile Hill I and II,
25 Ekola Flats, TB Flats I and II, and Dunlap projects in
Wagner, Di 11
Rocky Mountain Power
1 this region of Wyoming, amounting to over 1, 240 MW of
2 wind generation. Once construction is complete, the wind
3 turbine supplier will provide a warranty for Rock
4 Creek I for a period of time, during which any
5 significant repairs will be conducted by the wind
6 turbine supplier. In addition, the wind turbine supplier
7 or other third parties may be engaged from time to time
8 to help operate and maintain the project .
9 Q. Has Invenergy obtained the necessary local permits for
10 the project?
11 A. Yes . Carbon County issued a Conditional Use Permit for
12 the project on November 16, 2021, and Albany County
13 issued a Conditional Use Permit for the project on
14 January 18, 2022 . In addition, the Industrial Siting
15 Council approved Invenergy' s application for an
16 Industrial Siting Permit on April 15, 2022 . A CPCN was
17 granted to PacifiCorp by the Wyoming Commission on
18 February 28, 2023 . Invenergy has also been collaborating
19 with the U. S . Fish and Wildlife Service and the Wyoming
20 Game and Fish Department in developing and implementing
21 the project . Rock Creek I remains on-track for
Wagner, Di 12
Rocky Mountain Power
REDACTED
1 completion and an in-service date of December 2024 . 6
2 V. PROJECT COSTS
3 Q. What is the estimated capital cost for the project?
4 A. The estimated capital costs for Rock Creek I is
5 on a total-Company basis, which equates
6 to approximately I on an Idaho-allocated
7 basis . Company witness Shelley E . McCoy' s direct
8 testimony discusses these costs for Idaho rates in more
9 detail .
10 Q. How did the Company estimate construction and operations
11 and maintenance ("O&M") costs for the project?
12 A. Project costs are based on negotiations with Invenergy.
13 Interconnection costs were informed by the cost
14 estimates included in the executed Large Generator
15 Interconnection Agreement and interconnection study that
16 informed the interconnection agreement. ' The Company' s
17 costs for engineering, legal, internal project
6 See, e.g. , Carbon County Conditional Use Permit - Resolution No. 2021-
41, Wyoming County Clerk, Book 1381, p. 50 (November 16, 2021) ; Albany
County Conditional Use Permit - WEC-01-21 (January 18, 2022; to be
recorded) ; Wyoming Department of Environmental Quality, Industrial
Siting Council - Industrial Siting Permit - Docket No. DEQ/ISC 21-07
(April 15, 2022) ; Department of the Air Force, Siting and Mitigation
Agreement for Rock Creek Wind Project in Rock River, WY (February 18,
2021) ; Department of Defense, Mitigation Response Team Letter of No
Adverse Impact (February 24, 2021) ; Carbon County Road Use Agreement,
approved by Carbon County Board of County Commissioners (November 28,
2022) ; Albany County Road Use Agreement, approved by the Albany County
Board of County Commissioners (January 3, 2023) ; Wyoming Department of
Transportation Road Use Agreement, approved and executed by the
Transportation Commission of Wyoming and the Wyoming Department of
Transportation Chief Engineer (January 10, 2023) .
7 Confidential Exhibit No. 45 (RCI LGIA) .
Wagner, Di 13
Rocky Mountain Power
1 management, and allowance for funds used during
2 construction were estimated based on the Company' s
3 experience with development and construction of past
4 wind facilities . 0&M cost estimates are based on
5 negotiations with Invenergy and on the Company' s
6 experience with wind resource O&M budgets and third-
7 party contracts for the Company' s existing wind
8 facilities .
9 Q. Will Rock Creek I qualify for federal PTCs?
10 A. Yes . Under the Inflation Reduction Act ("IRA") , the
11 Company believes that Rock Creek I qualifies for
12 100 percent of the PTC available for projects placed
13 into service after 2021 . For projects placed in service
14 after 2022, the IRA also provides for an additional
15 10 percent bonus credit if the project is located in an
16 "energy community. " This definition includes census
17 tracts, or any directly adjoining census tracts, in
18 which (1) after 1999 a coal mine has closed, or (2) after
19 2009 a coal-fired electric generating unit has been
20 retired. With an expected in-service date of 2024 for
21 Rock Creek I the Company expects the project to qualify
22 for a PTC equal to 110 percent of the full credit
23 available . This credit will be returned to customers in
24 the Company' s annual Energy Cost Adjustment Mechanism
25 ("ECAM") filing.
Wagner, Di 14
Rocky Mountain Power
1 Q. Did the Company assess the customer benefits provided by
2 the project?
3 A. Yes . Company witness Burns provides a detailed economic
4 analysis of the significant customer benefits that
5 result from the acquisition of Rock Creek I in his
6 testimony.
7 VI . CONCLUSION
8 Q. Please summarize your testimony.
9 A. The Company successfully negotiated a BTA with Invenergy
10 that prudently manages risks, mitigates costs, allows
11 effective oversight, and ensures that Rock Creek I
12 remains on schedule . The project will provide
13 significant benefits to Idaho customers, and I recommend
14 the Commission approve the inclusion of Rock Creek I in
15 the Company' s retail rates .
16 Q. Does this complete your direct testimony?
17 A. Yes .
Wagner, Di 15
Rocky Mountain Power
Case No. PAC-E-24-04
Exhibit No. 40
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Site Layout for Rock Creek
May 2024
Rocky Mountain Power
Exhibit No.40 Page 1 of 2
Case No. PAC-E-24-04
R Witness:Jeffrey Wagner
ExhibitF—I-////��• RCI - Site Plan DofeS.ved:Tpe,d..A,i118.2023121120PM Pre oretlB Ce Cportlinpte Srsfe WGS 198d Web Merwfornoxilipry Sphere Po1h:\\pz 1gisacI\GRDOC3\-M% us\WY\Roc kcre'k ockc.eek_byopf_Ilxl]mx
21 22 23 24 19 22 19 20 21 22
of
LOB
U Lu ! 30903. 29 28 27
w 26 25 30
mU6 z7 T20N R78W I C �, 1 '^� T20N R 6W
acQ� I STATE Off`E DUNMIRE LAND DUNMIRE LAND o
WYOMING &LIVESTOCK '�L BUREAU &LIVESTOCK z~
cN lC O J OF LAND ¢w
C2 LLC A WY LLC LLC A WY LLC
MA GEMENT O w
33 34 35 °a�°°c 36 !z 0 31 V 31 2 33 34a Q
o I� I wQ
"EBAU _._.., -:..—...—.• —•i•���••,�•.•DUNMIRE' "' 'BUREAU' "DUNMIRE RANCH; ADLS-1 ��
FAMILY LIMITE l . LL ED
••�...�.....A:1.NERSHIP •,y�•••�••• 13 —' 'i••�•••�•••�•••�••• ...�...�...��..�
••• - as z C)O RANCH CO OF LAND CO OF WY
z $ OF WY MANAGEMENT T q 04 03 .—
03 o 6 0� g 0 0 03 02 I 06 05
•�U �W .
U7> 57 d.
J I h
_ r
' d
1 I 1 SIMS LAND 8 JOHN W �
' /I LNESTOCK GRAY
1 I 7 09 INC I 12 07 08 09 i 10
L NMIRE �J
Paci(iCorp 230 kV U
oD BUREAU
SIMS LAND&
U Q z 0o 1 �` LIVESTOCK INC OF LAND
ARROW 0 z ; g 0 U MANAGEMENT j
F LLC& a0 j �W18 o¢ 14J � 0 16 15 14 13 : 17 16 15
rr ¢
� � 'Pa T19N 77W
j 1J N—R BAN
a 101Lu
1 z
r 1001 c°cQa 1010 >O aI
ove « Y= 1 �� 19 21 22
00D of UO wo
STATE OF ¢m ,' 1 4012 �< 1 �O
WYOMING 1009
- 1 1UO2
O
1003 1006 1013 �a m o w z
1,008 , m - a z 2
j go
26 5 1 G� su 29 r�(D w�'27
�1004 �g 1007 : DILL m°a zIcai
1005 1016
a
LEBEAU FAMILY 1
WHEATLAND LIMITED 1017 IRRIGATION • -
DISTRICT PARTNERSHIP j a O 1014
- 2 34
34
w
EAU—1015
1018 ufND 019
II • � �or .i1 �...�.
15 vl... ...�...�...�. BOOTH LAND
LEBEAU FAMILY LIMITED BRIAN I 6 &LIVESTOCK
<. PARTNERSHIP WACHHOLTZ : }� 'io 1020 1 LLC ACOLLC
04 03 02 1 p 06 �z a � 1029, 0:' 03
BRADLEY
c�a�bO, o a 'Alz 27
�O• � U 1021 10 _
A HOLMES 's °� 1022 1030 ; rr r•.e
� 1028
1023 1031
09 10 11 12 1 0 1024 _ 1032 12 + 1
*EAU
\ p 5 w 1,025 1 OF LAND
MANAGEMENT
• v U U
j 1026 z' 1 a Y o
• UU
• o w ' x O Q
16 15 14 13 j 18 > w¢w o 13 1 ow
w
LL> m tLQ • m�
LLo J• T18N R77W °< 1
1-8 —R-7-8-W I a
21 22 23 24 19 i o N 24 j 20
jo 8N R76W
• Q z n p 1 BOOTH LAND
• o - - &LIVESTOCK
LLC ACO LLC
28 27 26 25 30 2-9
O1 =>ADLS
1
00�1' j z U ee a j
33 34 35 36 1 31 �I{ J°J
G�eeK c� ~`oJ
• O jm 0Lu 1
••�•••� •� `(jv •—•••—•' —•••—'••_ •OU N• LIVESTOCKLLC
CO LLC '
1
04 03 02 01 06 Ob 04 03 02 01 06 05 04 03
, � 1
1 _ I
T174 R78W T17N R 7W n T17N R 6W
09 10 11 12 i 07 0$ 09 10 12 1 p L `! 07 08 09 10
Rd Cf/° BOOTH LAND P 4
j e� e� &LIVESTOCK
kIgQ Ra LLC A CO LLC
° Sources:Esri,HERE,Garmin,1'Intermap,incre`ent P Cggrp GEBCOEsriiChina,U (Hong Krong SGS, FAO, NPS,NRCAN,
16 15 14 _F 13 18 16 �GeoBase, IGN,IKadaster NL,O�dnfpncepISurvey;, Esri Jai pan,METI, )9(1) 15
1 10penStreetMap contributors,and>the GIS Usei Community I I 99
Legend
_ Layout Temporary ••—ti Township/Range Transmission Line
O Turbine Location Intersection Landowner Parcel Status t.... Boundary 100- 161 kV
Improvements
0 o_ MET Tower Not Participating 0 Section Line 230-300 kV
Rock Creek I Project Road Classification
m` Collection 0 Boundary Participating-Wind
v Q Q) Agreement Interstate Highway
Access Road
Laramie E Laydown Yard Participating- US/State Route
0 Transmission = County Road
Agreement Wyoming Marshalling Yard A g Local Road 1 0 1
Jackson C o l o r a d o I O&M Building t•_•j County Boundary
Routt Larimer Project Substation Miles
RC I - Project Site Plan SUBJECT TO CHANGE AT SUBSTANTIAL COMPLETION
Rock Creek I Wind Energy Center I Albany & Carbon Counties, Wyoming April 19, 2023 Invenergy
Rocky Mountain Power
Exhibit No.40 Page 2 of 2
Case No. PAC-E-24-04
R
Witness:Jeffrey Wagner
Exhibit F-I-//•//��• RCII - Site Plan Date Sovetl ,d.yApiI18,2023 12 41 20 P rep—d By CLe Cpp tllnafe System WG51984 Web ercot.,Apx Vy Sp I 1F\\p1isacl\GISDOCSVXDs\US\WY\R.ckCrckV.pkc,eek_byppt_I 117—d
DUNMIRE LAND T Z O N 1 7 6 W BUREAU
&LIVESTOCK OF LAND
LLCA WY LLC \31FLAND
UREAU MANAGEMENT DUNMIR LAND
1 31 DUNMIRE 33 34 35 &LIVEgTOCK 36
EVENT LAND&LIVESTOCK LLC A WY LLC
�. LLC A WY LLC ADLS-1
1
to� bI1'WRE R�MrIlJW BUREAU DUNMIRE RANCH ,.2006 PI 2033
c o CO OF WY OF LAND CO OF WY 2013 usr 2027 2030
m MANAGEMENT
a' 2007 2014 9d 2031 2034
05 57 0 03 02 2023 04 0 01
2008 �9q3 2028 2032 0
2015 z Y U
N JOB
JOHN W 2009 2021 �Wi
GRAY 2001 2004 2024 2029 �' 2>a
SIMS LAND& �L 15 zDu
LIVESTOCK 2010 2016
os o9 INC 2002 ��2005 12 2011 2025 10 11 �
�2003 +. 2012 1 2017 2022 Rainey
2018 —2026
S S LAND& BUREAU L o�
LIVESTOCK INC OF LAND
MANAGEMENT j 2019 2020 9O•
�N
17L 16 15 14 13 11 ' 16 15 to 14 13
m h
> N T19N R77W j
I heatla d Irrigation District
Lu LuU
>z
20 Y= 24 1 21 23 9 24
U U • p
KK 1 �^
I' a
1 �Ja z
moQ ¢z�
29 27 2�9 20 29 3 Lu 27 26 5
=1LLQ
moz
2035
32 33 34 � 31 3 34 35 36
2036
.. 203 ... .._..._..._..._..._..._..._..._..._..._..._..._..._..._
2040 BOOTHLAND
&LIVESTOCK
2O3H 039 LLC A CO LLC
02
05 03 2041 03 02 01
2042
II 1
08 09 10 11 2I 43 1 OF BLAND
1 11 12
2144 MANAGEMENT
BUREAU 1
'1045 OF LAND
MANAGEMENT] BOOTH LAND
&LIVESTOCK
2059 LLC A CO LLC
z 2046
15 Q mz:5 17
LL a 2047 1 2060
m 0 z
W
2062 -
BOOTH LAND
2049 1 2061 2063 &LIVESTOCK
oT 1 8 N R7 7 2064 LLC A CO LLC
BOOTH LAND
20 22 = 23 2 &LIVESTOCK 2
2050 LLC A CO LLC 2065
o `2052 206_6
'w> 2053 BOOTH LAN
Y
&LIVESTOCK
:4 z LLC A CO LLC
29 27 __ 28 27 26
2054
OAULS-2' 2055
BOOTHLAND -
&LIVESTOCK 2056
LLC A CO LLC
Ce�Ao
2057
32 33 20�58 36
57
_..._. ..._..._ .._.:._. I i y'
T17N R � / VY BOOTH LAND&IVESTOCKLLC •.—••i_•..—.•.—..•—i•T17N R76W .•._.••—.••—••.�•••—••�mLL°•—..•
ACO LLC Sources:Esr�,HERE,Garmin,Intermap,Inc ement P Corp.,GEB'CO,USES, FAO, NPS,NRCAN,
05 04 0. 01 1 06 L5 I v4 6
GeOBase, IGN,Kadaster NL,Ordnance Surlvey, Esri Japan,METI`Esrl China(Hong g),(c)
j OpenStreetMap contrib i tors,and the GIS User Community /IX
Legend
Layout Rock Creek II Project Road Classification
m O Turbine Location 0 Boundary Interstate Highway
0 o MET Tower Landowner Parcel Status County Road
m Participating-Wind
m Collection Local Road
Agreement 3,300 0 3,300
Access Road „_ Transmission Line
Laramie E Participating- •. Township/Range
• m Project Substation -Transmission �•••� Boundary 100- 161 kV Feet
Temporary Agreement Section Line 230-300 kV
Wyoming Intersection
Jackson C o I o'r a d o Improvements - Not participating
Routt Larimer
RICH - Project Site Plan SUBJECT TO CHANGE AT SUBSTANTIAL COMPLETION
Rock Creek 11 Wind Energy Center I Albany & Carbon Counties, Wyoming April 19, 2023 Invenergy
REDACTED
Case No. PAC-E-24-04
Exhibit No. 41
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
REDACTED
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Energy Yield Assessment for Rock Creek
May 2024
THIS EXHIBIT IS CONFIDENTIAL IN ITS
ENTIRETY AND IS PROVIDED UNDER
SEPARATE COVER
REDACTED
Case No. PAC-E-24-04
Exhibit No. 42
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
REDACTED
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Rock Creek I BTA
May 2024
THIS EXHIBIT IS CONFIDENTIAL IN ITS
ENTIRETY AND IS PROVIDED UNDER
SEPARATE COVER
REDACTED
Case No. PAC-E-24-04
Exhibit No. 43
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
REDACTED
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Rock Creek I 0&M Management
May 2024
THIS EXHIBIT IS CONFIDENTIAL IN ITS
ENTIRETY AND IS PROVIDED UNDER
SEPARATE COVER
REDACTED
Case No. PAC-E-24-04
Exhibit No. 44
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
REDACTED
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Rock Creek I Turbine Supply Agreement
May 2024
THIS EXHIBIT IS CONFIDENTIAL IN ITS
ENTIRETY AND IS PROVIDED UNDER
SEPARATE COVER
REDACTED
Case No. PAC-E-24-04
Exhibit No. 45
Witness : Jeffrey Wagner
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
ROCKY MOUNTAIN POWER
REDACTED
Exhibit Accompanying Direct Testimony of Jeffrey Wagner
Rock Creek I LGIA
May 2024
THIS EXHIBIT IS CONFIDENTIAL IN ITS
ENTIRETY AND IS PROVIDED UNDER
SEPARATE COVER