HomeMy WebLinkAbout20240524Petition to Intervene.pdf RECEIVED
Friday, May 24, 2024 11:50:54 AM
IDAHO PUBLIC
UTILITIES COMMISSION
Austin Rueschhoff, ISB No. 10592
Thorvald A. Nelson
Austin W. Jensen, ISB No. 11947
HOLLAND&HART LLP
555 17th Street, Suite 3200
Denver, CO 80202
Telephone: (303) 295-8000
Facsimile: (720) 235-0229
Email: darueschhoff@hollandhart.com
tnelson@hollandhart.com
awiensen@hollandhart.com
Attorneys for Micron Technology, Inc.
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-24-18
COMPANY'S APPLICATION FOR )
APPROVAL OF A CLEAN ENERGY YOUR ) PETITION TO INTERVENE
WAY CONSTRUCTION AGREEMENT ) OF MICRON TECHNOLOGY, INC.
WITH THE CITY OF BOISE AND THE )
FIRST AMENDMENT THERETO )
Micron Technology, Inc. ("Micron" or "Intervenor"), pursuant to the Commission's
Rules of Procedure 71 through 74,1 hereby petitions the Commission for leave to intervene and
to appear and participate in this proceeding as a parry, and as grounds therefore states:
1. The name and address of this Intervenor is:
Micron Technology, Inc.
c/o Austin Rueschhoff
Thorvald A. Nelson
Austin W. Jensen
Holland& Hart LLP
555 17th Street, Suite 3200
Denver, CO 80202
Telephone: 3 03-295-8000
Fax: 720-235-0229
1 Idaho Admin. Code 31.01.01.071—.074.
1
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18
darueschhoff@hollandhart.com
tnelson@hollandhart.com
awjensen@hollandhart.com
Copies of all pleadings, production requests, production responses, Commission orders,
and other documents should be provided to:
Jim Swier Austin Rueschhoff
Micron Technology, Inc. Thorvald A. Nelson
8000 South Federal Way Austin W. Jensen
Boise, ID 83707 Holland&Hart, LLP
jswier@micron.com 555 17th Street, Suite 3200
Denver, CO 80202
(303) 295-8000
Fax: (720) 235-0229
darueschhoff@hollandhart.com
tnelson@hollandhart.com
awjensen@hollandhart.com
aclee@hollandhart.com
mamcmillen@hollandhart.com
2. Micron receives electric utility services from Idaho Power Company ("Idaho
Power") and is Idaho Power's single largest customer. Micron is also an Idaho Power Special
Contract customer. Micron's revised Special Contract was approved by this Commission in
Case No. IPC-E-22-06 along with Idaho Power's Power Purchase Agreement with Black Mesa
Energy, LLC ("Black Mesa"), entered into in part to serve Micron under the Clean Energy Your
Way ("CEYW") program. As discussed in Idaho Power's Application in this proceeding,
Micron's Special Contract contains a provision that allows for another Idaho Power customer to
purchase a share of Black Mesa electric generation.2 In this proceeding, Idaho Power seeks
Commission approval to effectuate that provision in Micron's Special Contract to enter into a
new Renewable Construction Agreement between the City of Boise and Idaho Power utilizing a
portion of Black Mesa electric generation.
2 Application,p. 3.
2
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18
3. This proceeding will impact Micron's Special Contract and the portion of
Micron's electric load that is served from Black Mesa's output. Therefore, Micron has a direct
and substantial interest in this proceeding.
4. Micron intends to participate herein as a party, and if necessary, to introduce
evidence, cross-examine witnesses, call and examine witnesses, and be heard in argument. The
nature and quality of evidence Micron will introduce is dependent upon the nature and effect of
other evidence in this proceeding.
5. Granting Micron's Petition to Intervene will not unduly broaden the issues, nor
will it prejudice any party to this case.
6. Without the opportunity to intervene, Micron would be without adequate means to
participate in this proceeding that may have a material impact on its electric service rates.
WHEREFORE, Micron Technology, Inc. respectfully requests that the Commission
grant its Petition to Intervene in this proceeding and to appear and participate in all matters as
may be necessary and appropriate; and to present evidence, call and examine witnesses, present
argument and to otherwise fully participate in this proceeding.
3
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18
Respectfully submitted May 24, 2024.
HOLLAND &HART, LLP
By:
ustin Rueschhoff, ISB No. 10
Thorvald A. Nelson
Austin W. Jensen, ISB No. 11947
555 17th Street, Suite 3200
Denver, CO 80202
Telephone: (303) 295-8000
Facsimile: (720) 235-0229
Email: darueschhoff@hollandhart.com
tnelson@hollandhart.com
awjensen@hollandhart.com
Attorneys for Micron Technology, Inc.
4
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18
CERTIFICATE OF SERVICE
I hereby certify that on May 24, 2024, a true and correct copy of the within and foregoing
PETITION TO INTERVENE OF MICRON TECHNOLOGY, INC. IN CASE NO. IPC-E-24-18
was served in the manner shown to:
Electronic Mail
Idaho Power Company
Donovan E. Walker Timothy E. Tatum
Idaho Power Company Alison Williams
1221 W. Idaho Street(83702) Idaho Power Company
PO Box 70 1221 West Idaho Street(83702)
Boise, ID 83707-0070 P.O. Box 70
dwalker&idahopower.com Boise, Idaho 83707
dockets(d),idahopower.com Telephone: (208) 388-5515
Facsimile: (208) 388-6449
ttatum(a,idahopower.com
awilliams kidahopower.com
Commission Staff Boise City
Monica Barrios-Sanchez Ed Jewell
Commission Secretary Steven Hubble
Idaho Public Utilities Commission Boise City Attorney's Office
11331 W. Chinden Blvd., Building 8, 150 N. Capitol Blvd.
Suite 201-A P.O. Box 500
Boise, ID 83714 Boise, ID 83701-0500
secretga(d),puc.idaho.gov BoiseCityAttorney(a),cityofboise.org
eiewellkcityofboise.org
shubble(d),cityofboise.org
Micron Technology, Inc.
Jim Swier Austin Rueschhoff
Micron Technology, Inc. Thorvald A. Nelson
8000 South Federal Way Austin W. Jensen
Boise, ID 83707 Holland& Hart, LLP
jswierkmicron.com 555 17th Street, Suite 3200
Denver, CO 80202
darueschhoff khollandhart.com
tnelson(d,hollandhart.com
awj ensen(khollandhart.c om
aclee(a,hollandhart.com
mamcmillenkhollandhart.com
5
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18
s/Adele Lee
32004334 vl
6
MICRON TECHNOLOGY, INC. PETITION TO INTERVENE
IPC-E-24-18