HomeMy WebLinkAbout20240501Staff Comments.pdf RECEIVED
Wednesday, May 1, 2024 2:10:02 PM
IDAHO PUBLIC
UTILITIES COMMISSION
DAYN HARDIE
DEPUTY ATTORNEY GENERAL
IDAHO PUBLIC UTILITIES COMMISSION
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0312
IDAHO BAR NO. 9917
Street Address for Express Mail:
11331 W CHINDEN BLVD, BLDG 8, SUITE 201-A
BOISE, ID 83714
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF AVISTA'S ANNUAL )
RATE ADJUSTMENT FILING FOR ) CASE NO. AVU-E-24-05
ELECTRIC LINE EXTENSION SCHEDULE )
51 )
COMMENTS OF THE
COMMISSION STAFF
COMMISSION STAFF ("STAFF") OF the Idaho Public Utilities Commission, by and
through its Attorney of record, Dayn Hardie, Deputy Attorney General, submits the following
comments.
BACKGROUND
On March 29, 2024, Avista Corporation dba Avista Utilities ("Company") applied for
Commission approval of an update in costs and administrative changes to the Company's
Electric Line Extension Schedule 51 ("Application"). The Company requested a May 15, 2024
effective date and that its Filing be processed by Modified Procedure.
On April 24, 2024, the Company submitted a revision that corrected the cost for
Overhead and Padmount transformer costs along with updated tariffs.
Schedule 51 incorporates average costing for electrical facilities commonly used to
extend service. Schedule 51 sets forth "Basic and Exceptional Costs"that have a fixed and
STAFF COMMENTS 1 MAY 1, 2024
variable component, with the variable component stated on a cost-per-foot basis. Basic and
Exceptional Costs apply to facilities like transformers and conduit and are based on recent
average costs. The Company represents average costing works well and does not propose to
change the conceptual structure of the tariff in the Application.
In compliance with Order No. 35757 the Company included workpapers detailing the
"hours, materials, and vehicle support for each job." Application at 3. Actual work order
estimates were also included for each job type.
STAFF ANALYSIS
Staff recommends approval of the update in average costs and construction allowances to
Schedule 51. Staff reviewed the Company's Application, revision, workpapers,proposed tariffs,
and responses to Staff production requests. Because of its investigation, Staff concludes the
Company's method for calculating average costs is consistent with past Schedule 51 filings and
believes that the proposed construction allowances are reasonable and based on embedded line
extension costs from the last general rate case. In addition, Staff believes the workpapers
provided with additional cost details and actual work order estimates satisfy Order No. 35757.
Update Calculation
Construction Allowances
The Company updated the allowances applicable to new residential, commercial, and
industrial customers' services. The Company continues to use an embedded cost method for
calculating the revised allowances that is designed to ensure similar investment in
distribution/terminal facilities as those in current facilities reflected in base rates. Table No. 1,
below, summarizes the proposed allowance changes.
STAFF COMMENTS 2 MAY 1, 2024
Table No. 1. Proposed Allowance Changes
Service Schedule Existing Proposed
Schedule 1 Individual Customer(per unit) $ 2,095 $ 2,475
Schedule 1 Duplex(per unit) $ 1,675 $ 1,980
Schedule 1 Multiplex (per unit) $ 1,260 $ 1,490
Schedule 11/12 (per kWh) $ 0.16986 $ 0.19321
Schedule 21/22 (per kWh) $ 0.15731 $ 0.17749
Schedule 31/32 (per kWh) $ 0.27217 $ 0.31838
Staff verified that the Company utilized its Cost-of-Service study from its most recent
general rate case filing,1 which is updated with the base rates approved in Order No. 35909 as
the basis of the embedded costs calculation. Staff reviewed the calculations for the proposed
allowances and believes the allowances are accurate.
Average Costs
In its Application and revision, the Company proposed updates to primary and secondary
service and transformer average costs. These costs were calculated using recent average actual
costs for components including transformers and PVC Sweeps which are commonly used for line
extensions. The Company has used this method to update its Schedule 51 line extension costs
previously.2 The Company proposes to update both overhead and underground circuit line
extensions for primary and secondary voltages, as well as service for either underground or
overhead installations. Padmount and overhead transformer costs were also updated through the
revision filed on April 24, 2024. Subsequently, residential development costs were updated to
reflect these revised costs.
The Company included workpapers that include hours, materials, and vehicle costs for
each job, along with examples of actual work order estimates for each job type. Workpapers
were included to comply with Order No. 35757 that ordered the Company to clearly identify the
detailed information requested by Staff in Case No. AVU-E-23-03. Staff reviewed the
workpapers and believe the information in the workpapers satisfies Order No. 35757.
'See Case No.AVU-E-23-01.
2 See Case No.AVU-E-00-1;Order No.28562.
STAFF COMMENTS 3 MAY 1, 2024
The major drivers affecting the increase in average costs were increases in labor and
transformer costs. The driver of reduced costs for some underground work stems from a
reduction in conduit costs. Application at 5. Transformer shortages and high demand continue
to drive increased average costs, indicated by the 39.0% increase in Overhead Transformer costs
and a 10.7% increase in Padmount Transformer cost. A comparison of actual transformer costs
over the last several years highlights these increases in Table No. 2 below.
Table No. 2. Summary of Actual Transformer Cost Increases
Dec 2021 Dec 2022 Dec 2023 22-23 % Change
Transformer—25KVA $1,700 $4,820 $7,095 47.2%
Transformer—50KVA $2,255 $5,660 $8,021 41.7%
Staff believes the Company's basis for the increases and decreases in costs are
reasonable. Both the present and proposed costs including the percentage change are shown in
Table No. 3 below.
Table No. 3. Summary of Proposed Cost Changes
Present Proposed % Change
Overhead Primary Circuit
Fixed Cost $ 4,875 $ 5,379 10.3%
Variable Cost $ 9.63 $ 10.69 11.0%
Underground Primary Circuit
Fixed Cost $ 2,232 $ 2,516 12.7%
Variable Cost $ 13.07 $ 13.48 3.1%
Underground Secondary Circuit
Fixed Cost $ 600 $ 666 11.0%
Variable Cost $ 14.38 $ 14.17 -1.5%
Overhead Secondary Circuit
Fixed Cost $ 1,976 $ 2,212 11.9%
Overhead Service Circuit $ 4.04 $ 5.02 24.3%
Underground Service Circuit $ 11.41 $ 10.46 -8.3%
STAFF COMMENTS 4 MAY 1, 2024
Overhead Transformer $ 3,615 $ 5,025 39.0%
Padmount Transformer $ 7,598 $ 8,413 10.7%
Staff analyzed the Company's method for calculating residential development costs and
determined it follows the method authorized in Order No. 28562. The present and proposed
residential amounts are found in Table No. 4 below.
Table No. 4. Residential Development Cost Chanj4es
Residential Developments Present Proposed
Total Cost per Lot $ 2,947 $ 3,358
Less: Service Cost $ 572 $ 525
Developer Responsibility $ 2,375 $ 2,833
Developer Refundable Payment $ 2,095 $ 2,475
Builder Non-Refundable Payment $ 852 $ 883
Allowance $ 2,095 $ 2,475
Customer Notice
The Company's customer notice was included with its Application. Staff reviewed it and
determined that it meets the requirements of Rule 125 of the Commission's Rules of Procedure
(IDAPA 31.01.01.125). The notice was mailed to the relevant customers on April 11, 2024,
providing a reasonable opportunity to file timely comments with the Commission by the May 1,
2024, comment deadline. As of April 30, 2024, the Commission has received no customer
comments.
STAFF RECOMMENDATION
Staff believes the Company's proposals are reasonable and conform with
Order Nos. 28562 and 35757. Staff recommends the Company's proposed costs and allowance
be approved. In addition, Staff recommends the revised tariff sheets in the Application
STAFF COMMENTS 5 MAY 1, 2024
and revision be approved, as filed.
Respectfully submitted this 1st day of May 2024.
1
ayn Har e
Deputy Attorney General
Technical Staff. Michael Eldred
Ty Johnson
Curtis Thaden
I:\Utility\UMISC\COMMENTS\AVU-E-24-05 Comments.docx
STAFF COMMENTS 6 MAY 1, 2024
1
1 CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS 1st DAY OF MAY 2024, SERVED
THE FOREGOING COMMENTS OF THE COMMISSION STAFF, IN CASE NO. AVU-
E-24-05, BY E-MAILING A COPY THEREOF TO THE FOLLOWING:
PATRICK EHRBAR DAVID J MEYER
DIR OF REGULATORY AFFAIRS VP & CHIEF COUNSEL
AVISTA CORPORATION AVISTA CORPORATION
PO BOX 3727 PO BOX 3727
SPOKANE WA 99220-3727 SPOKANE WA 99220-3727
E-mail: patrick.ehrbarOmavistacorpxom E-mail: david.me er_,avistacorp.com
l o9nda��
PATRICIA JORDA , SECRETARY
CERTIFICATE OF SERVICE