HomeMy WebLinkAbout20240415Decision Memo.pdf DECISION MEMORANDUM
TO: COMMISSIONER ANDERSON
COMMISSIONER HAMMOND
COMMISSIONER LODGE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: CHRIS BURDIN
DEPUTY ATTORNEY GENERAL
DATE: APRIL 16, 2024
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION FOR
A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR
THE BOISE BENCH BATTERY STORAGE FACILITY; CASE NO. IPC-E-
24-16.
On April 3, 2024, Idaho Power Company ("Company") filed an application
("Application") with the Idaho Public Utilities Commission ("Commission") requesting an order
granting the Company a Certificate of Public Convenience and Necessity ("CPCN") to acquire
new dispatchable energy storage with 150 megawatts ("MW") of operating capacity.
STAFF RECOMMENDATION
Commission Staff recommends the Commission issue a Notice of Application and Notice
of Intervention Deadline establishing a 21-day intervention period.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Intervention
Deadline establishing a 21-day intervention period?
Chris Burdin
Deputy Attorney General
IALega1\ELECTRIC\IPC-E-24-16_BBB storage\memos\IPCE2416_decl_cb.docx