HomeMy WebLinkAbout20201211Decision Memo.pdfDECISION MEMORANDUM 1
DECISION MEMORANDUM
TO: COMMISSIONER KJELLANDER
COMMISSIONER RAPER
COMMISSIONER ANDERSON
COMMISSION SECRETARY
COMMISSION STAFF
FROM: DAYN HARDIE
DEPUTY ATTORNEY GENERAL
DATE: DECEMBER 10, 2020
SUBJECT: APPLICATION OF LXI-CLEC, LLC AND FATBEAM, LLC FOR
APPROVAL TO ASSIGN THE CERTIFICATE OF PUBLIC
CONVENIENCE AND NECESSITY HELD BY LXI-CLEC, LLC TO
FATBEAM, LLC; CASE NOS. LXI-T-20-05; FZ4-T-20-02.
On November 17, 2020, LXI-CLEC, LLC (“LXI-CLEC”) and Fatbeam, LLC
(“Fatbeam”) (“Applicants”) jointly applied for authority for LXI-CLEC, LLC to transfer its
certificate of Public Convenience and Necessity No. 498 (“CPCN”) to Fatbeam. The Applicants
have entered into an Asset Purchase Agreement (“Agreement”) wherein Fatbeam will acquire
certain assets from LXI and associated companies Tekfinity, Tek-Hut, Inc. and Random
Investments, LLC (“Companies”). The assets include regulatory authorizations,
telecommunications equipment and facilities, certain customer and vendor contracts, and certain
rights and agreements with third parties and government agencies.
STAFF RECOMMENDATION
Staff recommends that the Commission process the Application by Modified
Procedure with a 21-day public comment period and 7-day reply period.
COMMISSION DECISION
Does the Commission wish to process the Application under Modified Procedure
with a 21-day public comment period 7-day reply period?
Dayn Hardie
Deputy Attorney General
I:\Legal\TELEPHONE\LXIT2005_FZ4T2002\LXIT2005_FZ4T2002_dec_dh.doc