BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
AT&T CORP., a New York Corporation;
AT &T COMMUNICATIONS OF THE
MOUNTAIN STATES, INC., a Colorado
Corporation,
Complainants,
vs.
QWEST CORPORATION, a Colorado
Corporation
Respondent.
CASE NO. ATT-O4-
NOTICE OF
PROCEDURAL SCHEDULE
On August 6, 2004, AT&T Corp., and AT&T Communications of the Mountain
States, Inc. (collectively AT&T) filed a complaint against Qwest Corporation. On August 31
2004, Qwest filed its response to AT&T's complaint.
On November 1 , 2004, the parties submitted a proposed procedural schedule to
complete the case.
YOU ARE HEREBY NOTIFIED that the Commission adopts the following
procedural schedule:
November 29 2004 Last day to serve discovery. Discovery responses due 14 days
from date of service.
January 3 , 2005 Last day to file Motions to Compel.
If no Motions to Compel are filed, then the schedule is as follows:
January 5, 2005 Deadline for parties to complete statement of stipulated
facts.
January 12, 2005 Parties file Motions for Summary Judgment.
January 26, 2005 Parties file responses to Motions for Summary Judgment.
Oral Argument to be scheduled.
NOTICE OF PROCEDURAL SCHEDULE
If Motions for Summary Judgment are denied:
21 days from service date of Commission Order on Motions
for Summary Judgment parties file direct testimony
Rebuttal testimony due 14 days after direct testimony filed.
Technical hearing to be scheduled.
If Motions to Compel are filed by deadline then the following schedule applies:
January 17, 2005 Responses to Motions to Compel
Week of January 31 Oral Argument on Motions to Compel
14 days from service date of Commission Order on Motions to
Compel discovery responses to be served in accordance with
Order.
14 days from service of discovery in accordance to
Commission Order - parties complete statement of stipulated
facts.
7 days from service date of statement of stipulated facts parties
file Motions for Summary Judgment.
14 days from service date of Motions for Summary Judgment
parties file responses to Motions for Summary Judgment.
Oral Argument to be scheduled.
If Motions for Summary Judgment are denied:
21 days from service date of Commission Order on Motions
for Summary Judgment parties file direct testimony
Rebuttal testimony due 14 days after direct testimony filed.
Technical hearing to be scheduled.
NOTICE OF PROCEDURAL SCHEDULE
DATED at Boise, Idaho this day of November 2004.
PAUL KJELL
MARSHA H. SMITH, COMMISSIONER
ATTEST:
Je Ii D. Jewell
Co mission Secretary
bls/O:ATTTO401 ws
NOTICE OF PROCEDURAL SCHEDTJLE